Common Information Model (CIM) Extensions and Messaging for the Integration of Renewable Distributed Energy Resources (DER)
|
|
- Amberly Watson
- 5 years ago
- Views:
Transcription
1 Common Information Model (CIM) Extensions and Messaging for the Integration of Renewable Distributed Energy Resources (DER) John Simmins, Gerald Gray, Brian Seal, Kristen Nicole, and Bob Uluski Electric Power Research Institute Eric Lambert and Jerome Fremont Électricité de France R&D CIM International User s Group New Orleans, LA October 25, 2012
2 Contents Key findings from the SG Demo survey DER Use Cases DER architecture 2
3 Now this is not the end. It is not even the beginning of the end. But it is, perhaps, the end of the beginning. Sir Winston Churchill, Speech in November 1942 British politician ( ) 3
4 Description of the Deliverable Synthesis project IntelliGrid/EDF collaboration Gerald Gray Eric Lambert SG Demo members input IEC TC 57/IntelliGrid Brian Seal Inverter modeling and messages Deliverable Use cases Actors UML Model and profile Data requirements Messages CIM IntelliGrid SG Demo IEC TC 57 Current Work WG 17 4
5 Key Findings of the Survey 5
6 Key Findings of the Survey on DER Fairly large (>300kW) plans DER Architecture: mixed Types: CVR ( ), DR, PV Communications: RF Mesh( ), RF Tower, Cellular ( ), Broadband ( ) Protocols: DNP3 ( ), IEC ( ) Concerns: Standards Data formats Effort to integrate 6
7 DER Use Cases and Messaging 7
8 DER Architecture 8
9 Low Voltage Plant Plant Plant GeneratingUnit Generating unit StaticMachine Solar panel RectifierInverter -maxp Inverter ACLineSegment Connection line Terminal -phases ConnectiviyNode Clamp LV line TopologicalNode -name Terminal Clamp ACLineSegment -name 9
10 Medium Voltage Plant Plant Plant GeneratingUnit Generating unit StaticMachine Static machine RectifierInverter Inverter SynchronousMachine Synchronous machine AsynchronousMachine Asynchronous machine ACLineSegment Connection line 10
11 11
12 Extensions to GeneratingUnit [GeneratingUnit [Equipment [PowerSystemResource [ ] ] ] ] SOURCE Class/Attribute/Association Comments CIM GeneratingUnit A single or set of synchronous machines for converting mechanical power into alternatingcurrent power. For example, individual machines within a set may be defined for scheduling purposes while a single control signal is derived for the set. In this case there would be a GeneratingUnit for each member of the set and an additional GeneratingUnit corresponding to the set. EXT GeneratingUnit.kind Generating unit kind (wind, solar, thermal, hydro, biogas, biomass, cogeneration, household waste). CIM GeneratingUnit SynchronousMachine Association with the synchronous machines of the generating unit. EXT GeneratingUnit AsynchronousMachine Association with the asynchronous machines of the generating unit. EXT GeneratingUnit StaticMachine Association with the static machines of the generating unit. 12
13 New Class: StaticMachine [StaticMachine [RegulatingCondEq [ConductingEquipment [ ] ] ] ] SOURCE Class/Attribute/Association Comments EXT StaticMachine Static machine. EXT StaticMachine.ratedS Nominal power, in kva. EXT StaticMachine.ratedU Nominal voltage, in kv. 13
14 New Class: RectifierInverter [RectifierInverter [ConductingEquipment [Equipment [PowerSystemRessource [ ] ] ] ] ] SOURCE Class/Attribute/Association Comments EXT RectifierInverter Inverter. EXT RectifierInverter.maxP Maximale power produced by the inverter, in kw. EXT RectifierInverter.ratedS Nominal power, in kva. EXT RectifierInverter StaticMachine Association with the static machine connected in the DC input of the inverter. EXT RectifierInverter AssetInfo Association with the asset information of the inverter. 14
15 Other RectifierInverter Attributes RectifierInverter.ratedS RectifierInvert.maxPabsorbed RectifierInvert.maxSabsorbed RectifierInvert.Prate RectifierInvert.referenceV RectifierInvert.referenceVoffset RectifierInvert.maxA [RectifierInverterInfo [AssetInfo [IdentifiedObject] ] ] [RectifierInverterElectronicKind] [RectifierInverterCommutationKind] 15
16 Use Cases for DER* Utility Provisions New DER Produce Distribution Power Flow Forecast Configure EPS Equipment Based on Daily DER and Load Forecast Reconfigures Systems in Response to Faulted Segment with Islanding Reconfigure Systems in Response to Faulted Segment Without Islanding Generate and Executes Substation Blackstart Sequence Distribution Management System Reconfigures Feeder with DERs Configure Substation for Island Operation Adjust System Settings in Response to Voltage Excursion *Architecture Reference Design for Distributed Energy Resource Integration: Smart Grid Demonstration Task 2.1. EPRI, Palo Alto, CA:
17 DMS Use Cases* *Seal and Uluski, Using Standards to Integrate Distributed Energy Resources with Distribution Management Systems. EPRI, Palo Alto, CA:
18 DER Use Cases* *Seal and Uluski 18
19 Results of DOE/NIST Workshop Phase 1 DER Discovery Service Report Present DER Status Real Time Real Power Dispatch Provide Forecast/Prediction of DER Opportunity Real Time Reactive Power Dispatch Nicole, Seal, and Simmins, Collaborative Initiative to Advance Enterprise Integration of DER, Workshop Results. EPRI, Palo Alto, CA:
20 Results of DOE/NIST Workshop Phase 2 Coordinate, Notify and Request DER with Circuit Reconfigurations Set DER Operating Modes & Settings DER History/Archived Status Modify Ride-Through Characteristics Notification of Settlement Activities Connect / Disconnect Provide Voltage Regulation Support DER Provide and Respond to a Price Signal Provide and Respond to a Schedule Integration of Cost Information 20
21 Comparison DER Discovery Service Report Present DER Status Provide Forecast/Prediction of DER Opportunity Real Time Real Power Dispatch Real Time Reactive Power Dispatch Provide Voltage Regulation Support Coordinate, Notify and Request DER with Circuit Reconfigurations 21 Use Cases IBM/ EPRI Seal/ Uluski DOE/ NIST DER Discovery Service X X X Report Present DER Status X X X Real Time Real Power Dispatch X X X Provide Forecast/Prediction of DER Opportunity X X X Real Time Reactive Power Dispatch X X X Coordinate, Notify and Request DER with Circuit Reconfigurations X X X Set DER Operating Modes & Settings X X DER History/Archived Status X Modify Ride-Through Characteristics X Notification of Settlement Activities X Connect / Disconnect X X Provide Voltage Regulation Support DER X X X Provide and Respond to a Price Signal X Provide and Respond to a Schedule X Integration of Cost Information X Reconfigures Systems in Response to Faulted Segment with Islanding X Reconfigure Systems in Response to Faulted Segment Without Islanding X Generate and Executes Substation Blackstart Sequence X Distribution Management System Reconfigures Feeder with DERs X Configure Substation for Island Operation X Stay off after trip X Limit DER Maximum Generation X X Peal Limiting X Phase Balancing X Retrieve DER Abnormal Condition Characteristics X
22 Let s go through the use cases. What information to set or obtain desired results Where geographic components of the desired results When temporal components of the desired results 22
23 Data Requirements - Identify DER Resources Item DER Name DER Type DER Address DER Geographic Location DER Primary Substation DER Secondary Substation DER Feeder DER Feeder Segment DER phase Description A unique identifier for each DER. Defining the type of DER device PV, storage, etc. The physical (street) address of the DER Latitude and Longitude The ID of the substation with which the DER is normally associated The ID of the substation with which the DER is alternatively associated The ID of the feeder to which the DER is connected The ID of the line segment (e.g. lateral, segment between switches) to which the DER is connected The ID of the Phase(s) to which the DER is connected) 23
24 Data Requirements - Identify DER Resources/Capabilities Item DER Watt Rating Description The as-installed watt rating of the DER (for PV plants, this may be panel-limited) DER Var Rating DER VA Rating DER Storage Watt-hours The Var capability of the DER The VA capability of the DER The usable energy storage Watt-hour capability of the DER 24
25 Data Requirements Real Time, Real Power Dispatch Item Request: Increase or Decrease in Real Power Level Description Indication passed to the DERMS of what level of real power is requested, expressed as a percentage of nameplate value. DER Being Addressed Indication passed to the DERMS of which DER are to be affected by the request. DER Connect/Disconnect Status Response to the request. A list response indicating the resulting status (connected/disconnected) of each affected DER. 25
26 Data Requirements - Provide Voltage Regulation Support Item Request: Maximum Generation Level DER Being Addressed DER Connect/Disconnect Status Description Indication passed to the DERMS of what maximum generation level is requested, expressed as a percentage of nameplate value. Indication passed to the DERMS of which DER are to be affected by the request. Options include those identified in Error! Reference source not found. Response to the request. A list response indicating the resulting status (connected/disconnected) of each affected DER. 26
27 Data Requirements - Inform DER of Alternate Circuit Configuration (Including Islanding) Item Set DER for Operation in Indicated Circuit Configuration DER Being Addressed DER Connect/Disconnect Status Description Indication passed to the DERMS that the utility circuit configuration has changed for the indicated DER devices. Circuit Configuration indicators: 1. Normal 2. Islanded 3. Alternate substation #1 4. Alternate substation #2 Indication passed to the DERMS of which DER are to be affected by the request. Options include those identified in Error! Reference source not found.error! Reference source not found. Response to the request. A list response indicating the resulting status (connected/disconnected) of each affected DER 27
28 The Where and When How Requested By Primary Substation By Circuit/Bus By Feeder By Segment By Feeder+Phase Description Request voltage reduction support from all DER connected to a specific substation Request voltage reduction support from all DER connected to a specific circuit/bus Request voltage reduction support from all DER connected to a specific feeder Request voltage reduction support from all DER connected to a specific feeder segment Request voltage reduction support from all DER connected to a specific feeder and phase By Segment+Phase Request voltage reduction support from all DER connected to a specific feeder segment and phase By Individual Device Name Request voltage reduction support from a single DER, requested by unique device ID 28
29 The Where and When 29
30 References Architecture Reference Design for Distributed Energy Resource Integration: Smart Grid Demonstration Task 2.1. EPRI, Palo Alto, CA: Common Functions for Smart Inverters. EPRI, Palo Alto, CA: Collaborative Initiative to Advance Enterprise Integration of DER, Workshop Results. EPRI, Palo Alto, CA: Using Standards to Integrate Distributed Energy Resources with Distribution Management Systems. EPRI, Palo Alto, CA: Distributed Energy Resources Integration in the Smart Grid Demonstration. EPRI, Palo Alto, CA: (in about 1 month) 30
31 Together Shaping the Future of Electricity 31
IEEE Major Revision of Interconnection Standard
IEEE 1547-2018 - Major Revision of Interconnection Standard NRECA & APA s Emerging Priorities in Energy Research Day, Anchorage, AK Charlie Vartanian PE Secretary, IEEE 1547 Working Group October 31, 2018
More informationEmbedded Generation Connection Application Form
Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed
More informationEmbedded Generation Connection Application Form
Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed
More informationCommon Functions for Smart Inverters. 4 th Edition
Common Functions for Smart Inverters 4 th Edition 3002008217 Common Functions for Smart Inverters 4 th Edition 3002008217 Technical Update, December 2016 EPRI Project Manager B. Seal ELECTRIC POWER RESEARCH
More informationRemotes Case 2&3 Form REINDEER Cases 2&3 -Connection Impact Assessment (CIA) Application
General Application Information Remotes Case 2&3 Form REINDEER Cases 2&3 -Connection Impact Assessment (CIA) Application Hydro One Remote Communities Inc. Lori.Rice@hydroone.com 1-807-474-2828 This Application
More informationImplementation of Revised IEEE Standard 1547
MAY 31, 2017 HOLYOKE, MASSACHUSETTS Implementation of Revised IEEE Standard 1547 Presentation to ISO-TO Operations Committee David Forrest Key Points As New England adds significant amounts of Distributed
More informationCIM Network Model. Model Driven Architectures and Eclipse. OGO Open Grid Systems. Alan McMorran B.Eng Ph.D
CIM Network Model Model Driven Architectures and Eclipse Technologies for the Power Industry Alan McMorran B.Eng Ph.D G Information Modelling A simple introduction to CIM UML 2 G CIM UML IEC 61970-301
More informationEmbedded Generation Connection Application Form
Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed
More informationUse Case No 28: AGC Frequency Control
DMS (T. Berry, )-03 Use Case No 28: AGC Frequency Control Summary: This use case is a description of the information exchanges between a subsystem and the load frequency control core of an Automatic Generation
More informationTechnical Requirements for Connecting Small Scale PV (sspv) Systems to Low Voltage Distribution Networks
2014 Technical Requirements for Connecting Small Scale PV (sspv) Systems to Low Voltage Distribution Networks This document specifies the technical requirement for connecting sspv to the low voltage distribution
More informationGIS Data Assessment for DMS and Smart Grid Implementation
GIS Data Assessment for DMS and Smart Grid Implementation John Dirkman, P.E. Telvent Esri EGUG 11 October 2011 11/3/2011 1 Agenda 1. Determining your Distribution Management System and Smart Grid Drivers
More informationTarget Mchunu and Themba Khoza Eskom Transmission Division, System Operator Grid Code Management
GRID CONNECTION CODE FOR RENEWABLE POWER PLANTS (RPPs) CONNECTED TO THE ELECTRICITY TRANSMISSION SYSTEM (TS) OR THE DISTRIBUTION SYSTEM (DS) IN SOUTH AFRICA Target Mchunu and Themba Khoza Eskom Transmission
More informationIEEE sion/1547revision_index.html
IEEE 1547 IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces http://grouper.ieee.org/groups/scc21/1547_revi sion/1547revision_index.html
More informationConnection Impact Assessment Application
Connection Impact Assessment Application This form is for generators applying for Connection Impact Assessment (CIA) and for generators with a project size >10 kw. Please return the completed form by email,
More informationFuel cell power system connection. Dynamics and Control of Distributed Power Systems. DC storage. DC/DC boost converter (1)
Dynamics and Control of Distributed Power Systems Fuel cell power system connection Ian A. Hiskens University of Wisconsin-Madison ACC Workshop June 12, 2006 This topology is fairly standard, though there
More informationCIM-based AMI and GIS interfaces for energy consumption analysis and grid losses estimation
IEN 2014 CIM-based AMI and GIS interfaces for energy consumption analysis and grid losses estimation Aleksander Babs Institute of Power Engineering Gdansk, Poland 26.02.2014 Grid losses general model Grid
More informationIEEE SCC Standards Update
IEEE SCC21 1547 Standards Update Michael Coddington, Tom Basso National Renewable Energy Laboratory Presented at the Solar Power International Conference IEEE Std 1547a Amendment 1, May 2014 (Amendment
More informationTesting Advanced Photovoltaic Inverters Conforming to IEEE Standard 1547 Amendment 1
> REPLACE THIS LINE WITH YOUR PAPER IDENTIFICATION NUMBER (DOUBLE-CLICK HERE TO EDIT) < Testing Advanced Photovoltaic Inverters Conforming to IEEE Standard 547 Amendment Anderson Hoke, Student Member,
More informationIntermittent Renewable Resources (Wind and PV) Distribution Connection Code (DCC) At Medium Voltage (MV)
Intermittent Renewable Resources (Wind and PV) Distribution Connection Code (DCC) At Medium Voltage (MV) IRR-DCC-MV 1. Introduction 1 IRR-DCC-MV 2. Scope 1 IRR-DCC-MV 2.1. General 1 IRR-DCC-MV 2.2. Affected
More informationQUESTIONNAIRE for Wind Farm Power Stations only
TRANSMISSION SYSTEM OPERATOR QUESTIONNAIRE for Wind Farm Power Stations only To be submitted by the Generation Licensees together with the Application for Connection Certificate according to IEC 61400-21
More informationIntelliGrid Newsletter
IntelliGrid Newsletter An EPRI Progress Report September 2012 About the Newsletter The IntelliGrid Program conducts research, development and demonstrations on the information and communications technologies
More informationWFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS
WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS WFPS1.1 INTRODUCTION 2 WFPS1.2 OBJECTIVE 2 WFPS1.3 SCOPE 3 WFPS1.4 FAULT RIDE THROUGH REQUIREMENTS 4 WFPS1.5 FREQUENCY REQUIREMENTS 5 WFPS1.6 VOLTAGE
More informationModelling Parameters. Affect on DER Impact Study Results
Modelling Parameters Affect on DER Impact Study Results Agenda Distributed Energy Resources (DER) Impact Studies DER Challenge Study Steps Lessons Learned Modeling Reverse Power Transformer Configuration
More informationPossible Future Modifications to IEEE 1547
California Rule 21 SWIG Possible Future Modifications to IEEE 1547 Michael Sheehan, P.E IREC mikes@irecusa.com PV Significant Trends Installed prices for distributed PV installations fell by at least 11
More informationRevised IEEE 1547 Standard for Interconnecting Distributed Energy Resources with Electric Power Systems- National Grid Solar Program
1 Revised IEEE 1547 Standard for Interconnecting Distributed Energy Resources with Electric Power Systems- National Grid Solar Program Babak Enayati, PhD, PE Lead Engineer, National Grid Waltham, MA Email:
More informationIEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces
IEEE PES Boston Chapter Technical Meeting IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces P1547 Chair David
More informationAmeren Illinois Company d/b/a Ameren Illinois Smart Inverter Specifications
1. SCOPE OF WORK 1.1 Purpose This document is formulated to provide guidance to SMART inverter installers in Illinois. The document provides the minimum specification for inverters that interconnect with
More informationDetermination of Smart Inverter Power Factor Control Settings for Distributed Energy Resources
21, rue d Artois, F-758 PARIS CIGRE US National Committee http : //www.cigre.org 216 Grid of the Future Symposium Determination of Smart Inverter Power Factor Control Settings for Distributed Energy Resources
More informationIDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)
IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: IDAHO POWER COMPANY Designated Contact Person: Jeremiah Creason Address: 1221 W. Idaho Street, Boise ID 83702 Telephone
More informationCustomer Standard. Standard for Embedded Generation (5MW and above)
Standard 01188 Version: 1 Released: 1/10/2014 STANDARD FOR EMBEDDED GENERATION (5MW AND ABOVE) Customer Standard Standard for Embedded Generation If this standard is a printed version, to ensure compliance,
More informationConnection Impact Assessment Application Form
Connection Impact Assessment Application Form This Application Form is for Generators applying for a Connection Impact Assessment (CIA). In certain circumstances, London Hydro may require additional information
More informationTable of Contents. Introduction... 1
Table of Contents Introduction... 1 1 Connection Impact Assessment Initial Review... 2 1.1 Facility Design Overview... 2 1.1.1 Single Line Diagram ( SLD )... 2 1.1.2 Point of Disconnection - Safety...
More informationISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements
Division 502 Technical Applicability 1(1) Section 502.1 applies to: Expedited Filing Draft August 22, 2017 the legal owner of an aggregated generating facility directly connected to the transmission system
More informationRule 21 Working Group 3.
Rule 21 Working Group 3 SIWG CALL ISSUES 27 AND 28 DECEMBER 19, 2018 https://gridworks.org/initiatives/rule-21-working-group-3/ Agenda 2:00-2:10 Schedule and introduction Issues 27 & 28 2:10-2:30 Issue
More informationImpact Assessment Generator Form
Impact Assessment Generator Form This connection impact assessment form provides information for the Connection Assessment and Connection Cost Estimate. Date: (dd/mm/yyyy) Consultant/Developer Name: Project
More informationIssued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY
WN U-60 Attachment C to Schedule 152, Page 1 SCHEDULE 152 APPLICATION FOR INTERCONNECTING A GENERATING FACILITY TIER 2 OR TIER 3 This Application is considered complete when it provides all applicable
More informationTechnical Information Short-Circuit Currents Information on short-circuit currents of SMA PV inverters
Technical Information Short-Circuit Currents Information on short-circuit currents of SMA PV inverters Content During grid failures as for example voltage dips, all PV inverters may generate currents that
More informationNEW APPROACH TO REGULATE LOW VOLTAGE DISTRIBUTION NETWORK
NEW APPROACH TO REGULATE LOW VOLTAGE DISTRIBUTION NETWORK Yves CHOLLOT Philippe DESCHAMPS Arthur JOURDAN SCHNEIDER ELECTRIC France SCHNEIDER ELECTRIC France SCHNEIDER ELECTRIC France yves.chollot@schneider-electric.com
More informationImpacts of the Renewable Energy Resources on the Power System Protection by: Brent M. Fedele, P.E., National Grid for: 11 th Annual CNY Engineering
Impacts of the Renewable Energy Resources on the Power System Protection by: Brent M. Fedele, P.E., National Grid for: 11 th Annual CNY Engineering Expo - Nov. 3, 2014 Index Normal Distribution System
More informationVOLTAGE QUALITY PROVISION IN LOW VOLTAGE NETWORKS WITH HIGH PENETRATION OF RENEWABLE PRODUCTION
VOLTAGE QUALITY PROVISION IN LOW VOLTAGE NETWORKS WITH HIGH PENETRATION OF RENEWABLE PRODUCTION ABSTRACT Anže VILMAN Elektro Gorenjska, d.d. Slovenia anze.vilman@elektro-gorenjska.si Distribution system
More informationTechnical information Grid Support Utility Interactive Inverters for Sunny Central-US and Sunny Central Storage-US
Technical information Grid Support Utility Interactive Inverters for Sunny Central-US and Sunny Central Storage-US ENGLISH SC-US-GridServices-TI-en-10 Version 1.0 Table of Contents SMA Solar Technology
More informationSolectria Renewables Modbus Level 5 For models PVI KW
Solectria Renewables Modbus Level 5 For models PVI 50 100KW Revision B 2014, Solectria Renewables, LLC DOCR 070381 B Table of Contents 1 Solectria Renewables Modbus Level 5... 3 1.1 Determine Modbus Level...
More informationEnergex Smart Network Trials
Energex Smart Network Trials 1 Agenda Power line carrier trials Low voltage network management trial Why did we do a PRIME trial Low cost technology Same cost as a electronic meter without communications
More informationTransmission Interconnection Requirements for Inverter-Based Generation
Transmission Requirements for Inverter-Based Generation June 25, 2018 Page 1 Overview: Every generator interconnecting to the transmission system must adhere to all applicable Federal and State jurisdictional
More informationCAISO Restricted - Do Not Distribute Outside of RC Project LOI and NDA Entities Page 1 of 24
RC0120A - RC IRO-010 Data Specification NOTE: Changes from Peak's Attachment A are highlighted in red in columns C through G Section Category Number Responsible Pa Data Item Data Transfer Method 1.1 Transmission
More informationForm B. Connection Impact Assessment Application Form Distribution System
Form B Connection Impact Assessment Application Form Distribution System This Application Form is for Generators applying for Connection Impact Assessment ( CIA ). It is important that the Generator provides
More informationActive Power Sharing and Frequency Control of Multiple Distributed Generators in A Microgrid
IOSR Journal of Electrical and Electronics Engineering (IOSR-JEEE) e-issn: 2278-1676,p-ISSN: 2320-3331, PP 01-07 www.iosrjournals.org Active Power Sharing and Frequency Control of Multiple Distributed
More information2016 3rd Conference on Power Engineering and Renewable Energy (ICPERE 2016)
2016 3rd Conference on Power Engineering and Renewable Energy (ICPERE 2016) Yogyakarta, Indonesia 29-30 November 2016 IEEE Catalog Number: ISBN: CFP1646T-POD 978-1-5090-5109-0 Copyright 2016 by the Institute
More informationIEEE sion/1547revision_index.html
IEEE 1547 IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces http://grouper.ieee.org/groups/scc21/1547_revi sion/1547revision_index.html
More informationBabak Enayati National Grid Thursday, April 17
2014 IEEE PES Transmission & Distribution Conference & Exposition Impacts of the Distribution System Renewable Energy Resources on the Power System Protection Babak Enayati National Grid Thursday, April
More informationRevision Control. 0 18/07/2012 Initial Document Creation. STAKEHOLDERS The following positions shall be consulted if an update or review is required:
Standard: Technical Requirements for Bumpless Transfer of Customer Load between Embedded Generators and the Distribution Network Standard Number: HPC-9OJ-13-0001-2012 * Shall be the Process Owner and is
More informationSouthern Company Interconnection Requirements for Inverter-Based Generation
Southern Company Interconnection Requirements for Inverter-Based Generation September 19, 2016 Page 1 of 16 All inverter-based generation connected to Southern Companies transmission system (Point of Interconnection
More informationGENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW
GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW ELECTRIC UTILITY CONTACT INFORMATION Consumers Energy Interconnection Coordinator 1945
More informationImplementation Guidelines CGMES v2.4.15
15 March 2016 This document provides implementation guidelines for Suppliers and TSOs on the ENTSO-E Common Grid Model Exchange Standard (CGMES) version 2.4.15. The clarifications provided in this document
More informationHARMONICS ANALYSIS USING SEQUENTIAL-TIME SIMULATION FOR ADDRESSING SMART GRID CHALLENGES
HARMONICS ANALYSIS USING SEQUENTIAL-TIME SIMULATION FOR ADDRESSING SMART GRID CHALLENGES Davis MONTENEGRO Roger DUGAN Gustavo RAMOS Universidad de los Andes Colombia EPRI U.S.A. Universidad de los Andes
More informationImpact of High PV Penetration on Grid Operation. Yahia Baghzouz Professor of Electrical engineering University of Nevada Las Vegas
Impact of High PV Penetration on Grid Operation Yahia Baghzouz Professor of Electrical engineering University of Nevada Las Vegas Overview Introduction/Background Effects of High PV Penetration on Distribution
More informationFuture. Ready. SM. Using Meters as Distribution Sensors for Capacitor Bank Monitoring. White Paper
White Paper Using Meters as Distribution Sensors for Capacitor Bank Monitoring The role capacitor banks play in maintaining power quality varies by utility. But regardless of how capacitors are deployed,
More informationRenewable Interconnection Standard & Experimental Tests. Yahia Baghzouz UNLV Las Vegas, NV, USA
Renewable Interconnection Standard & Experimental Tests Yahia Baghzouz UNLV Las Vegas, NV, USA Overview IEEE Std 1547 Voltage limitations Frequency limitations Harmonic limitations Expansion of IEEE Std
More information1200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report
1200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report Rich Bauer Associate Director Reliability Risk Management / Event Analysis Mid C Seminar July 19, 2017 Western Interconnection
More informationFeeder Protection Challenges with High Penetration of Inverter Based Distributed Generation
Feeder Protection Challenges with High Penetration of Inverter Based Distributed Generation Harag Margossian 1, Florin Capitanescu 2, Juergen Sachau 3 Interdisciplinary Centre for Security, Reliability
More informationVersion 2.6 October Comments to this document can be forwarded to:
GRID CONNECTION CODE REQUIREMENTS FOR RENEWABLE POWER PLANTS (RPPs) CONNECTED TO THE TRANSMISSION SYSTEM (TS) OR THE DISTRIBUTION SYSTEM (DS) IN SOUTH AFRICA Version 2.6 October 2012 Comments to this document
More informationMeasurement tools at heart of Smart Grid need calibration to ensure reliability
Measurement tools at heart of Smart Grid need calibration to ensure reliability Smart grid; PMU calibration position 1 The North American interconnections, or electric transmission grids, operate as a
More informationIEEE Std Bulk System Opportunities from New Distributed Energy Resource Interconnection and Interoperability Standards
IEEE Std 1547-2018 Bulk System Opportunities from New Distributed Energy Resource Interconnection and Interoperability Standards Clayton Stice, ERCOT Jens C. Boemer, EPRI (on behalf of SCC21) NERC SPIDER
More informationINVESTIGATING THE BENEFITS OF MESHING REAL UK LV NETWORKS
INVESTIGATING THE BENEFITS OF MESHING REAL UK LV NETWORKS Muhammed S. AYDIN Alejandro NAVARRO Espinosa Luis F. OCHOA The University of Manchester UK The University of Manchester UK The University of Manchester
More informationESB National Grid Transmission Planning Criteria
ESB National Grid Transmission Planning Criteria 1 General Principles 1.1 Objective The specific function of transmission planning is to ensure the co-ordinated development of a reliable, efficient, and
More informationRENEWABLE ENERGY SUB-CODE for Distribution Network connected Variable Renewable Energy Power Plants in Ghana
RENEWABLE ENERGY SUB-CODE for Distribution Network connected Variable Renewable Energy Power Plants in Ghana JANUARY 2015 i Table of Content PART A: 1 1 Introduction 1 1.1 Scope 1 1.2 Status 1 1.3 Terms
More informationDeployment of Real-time State Estimator and Load Flow in BC Hydro DMS - Challenges and Opportunities
IEEE PES General Meeting, Vancouver, Canada, July 2013 Deployment of Real-time State Estimator and Load Flow in BC Hydro DMS - Challenges and Opportunities Djordje Atanackovic, BC Hydro Valentina Dabic,
More informationISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements
Section 502.8 SCADA Technical and Operating Requirements Applicability 1 Subject to subsections 2 and 3 below, section 502.8 applies to: (a) (c) (d) the legal owner of a generating unit or an aggregated
More informationPhase-phase/phase-neutral: 24/13.8 kv star, 13.8 kv delta, 12/6.9 kv star.
Summary Of Interconnection Technical Guidelines for Renewable Energy Systems 0-100 kw under Standard Offer Contract (Extract from JPS Guide to Interconnection of Distributed Generation) This document is
More informationFNN comments on NC HVDC submitted to ENTSO E
the term HV is not defined > A further definition should be applied since the term is used all through the code A lot of terms from the Network Code RfG are used and should be checked regarding consistency
More informationJ Project Methods. V (%) Network with high generation and low load. Network with low generation and high load
J Project Methods Background The management of voltage is a growing concern with the integration of low carbon technologies, particularly distributed generation (DG), within electricity networks. The issue
More informationGENERATOR INTERCONNECTION APPLICATION Category 3 For All Projects with Aggregate Generator Output of More Than 150 kw but Less Than or Equal to 550 kw
GENERATOR INTERCONNECTION APPLICATION Category 3 For All Projects with Aggregate Generator Output of More Than 150 kw but Less Than or Equal to 550 kw ELECTRIC UTILITY CONTACT INFORMATION Consumers Energy
More informationAnalysis of an innovation: the ADMS microgrid management system
Final Degree Project Degree in Industrial Technology Analysis of an innovation: the ADMS microgrid management system MEMORY Author: Pol Cammany Ruiz Director: Jordi Olivella Nadal Date: June 2017 Escola
More informationINTEGRATED TRANSMISSION PLAN Glossary
INTEGRATED TRANSMISSION PLAN Glossary SEPTEMBER 2017 GLOSSARY Term AC ACM asset health and asset health index (AHI) automatic underfrequency load shedding (AUFLS) availability bus cable capacitor bank
More informationSynchrophasors and the Smarter Grid
Synchrophasors and the Smarter Grid Synchrophasor A synchrophasor is a phasor measurement with respect to an absolute time reference. With this measurement we can determine the absolute phase relationship
More information5 Summary test results and additional findings
LOW VOLTAGE RIDE THROUGH WITH HIGH CURRENT INJECTION 1 2 3 4 Motivation Future Requirements Test results for symmetrical failures Test results for asymmetrical failures 5 Summary test results and additional
More informationHoward Smart Transformer Specification Guide
Howard Smart Transformer Specification Guide General Requirements Overhead pole-type smart distribution transformers shall be single phase, 60 Hz, mineral-oil filled and self-cooled and shall conform as
More informationISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements
Section 502.8 SCADA Technical and Operating Applicability 1 Section 502.8 applies to: (a) the legal owner of a generating unit: (i) connected to the transmission facilities in the balancing authority area
More informationImprovement of Islanding Detector Using Interharmonics Current Injection Method and Its Applications
FEATURED TOPIC Improvement of Islanding Detector Using Interharmonics Current Injection Method and Its Applications Sadayuki ISHIKURA*, Hideyuki NAKATANI, Junya TAKAGI, Tsutomu FUKADA, Shoji NISHIMURA
More informationNORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number: Address:
NORTH CAROLINA INTERCONNECTION REQUEST Utility: Designated Contact Person: Address: Telephone Number: Fax: E-Mail Address: An is considered complete when it provides all applicable and correct information
More informationFrom: Roger Clayton Re: Notes from FERC DER Technical Conference, April Panel 4 Collection and availability of data on DER installations
Memorandum From: Roger Clayton Re: Notes from FERC DER Technical Conference, April 11 2018 Panel 4 Collection and availability of data on DER installations Q1 Type of information? Q2 Current data & sharing?
More informationPublic Consultation on the Regulatory Framework for Small Scale Grid Connected Solar PV Systems Standards Technical Standards
Consultation Paper: 1/2017 (i) Public Consultation on the Regulatory Framework for Small Scale Grid Connected Solar PV Systems Standards Technical Standards Issued on 19 January 2017 Contents 1. Introduction
More informationCompany Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System
Company Directive STANDARD TECHNIQUE: SD7F/2 Determination of Short Circuit Duty for Switchgear on the WPD Distribution System Policy Summary This document provides guidance on calculation of fault levels
More informationIslanding Detection Technique based on Simulation of IEEE16 Bus System
Islanding Detection Technique based on Simulation of IEEE16 Bus System 1 Mahesh M, 2 Kusuma Devi G.H. 1 PG Scholar, 2 Research Scholar Jain University Bengaluru. Dept. of Electrical and Electronics Engineering.
More informationNetwork Monitoring and Visibility Summary
Network Monitoring and Visibility Summary This article reviews the shortfalls in legacy monitoring and what will be needed to manage the changing nature of the distribution network. This includes a particular
More informationSetting Standards Perspectives for Future Energy Grids. Alexander Nollau Hannover,
Setting Standards Perspectives for Future Energy Grids Alexander Nollau Hannover, 23.04.2018 Future Energy Systems: Drivers Microgrids Cybersecurity Deregulation Politics Smart Energy Ancillary services
More informationSDG&E Transmission Synchrophasor Project Update
SDG&E Transmission Synchrophasor Project Update Joint Synchronized Information Subcommittee (JSIS) Meeting Tariq Rahman, May 22-25, 2017 2006 San Diego Gas & Electric Company. All copyright and trademark
More informationTasmanian Networks Pty Ltd Guideline. Technical Requirements for the Connection of Embedded Generation
Tasmanian Networks Pty Ltd Guideline Technical Requirements for the Connection of Embedded Generation Revision 08 November 2017 Disclaimer This document has been prepared for the purposes of informing
More informationDistributed Generation Application Form (Generation of Greater than 20 kw to 15 MW)
Distributed Generation Application Form (Generation of Greater than 20 kw to 15 MW) PSC-6028 R(03-04-04) Name & Address Distributed By Name & Address Supplied By Public Service Commission of Wisconsin
More informationLow Frequency Demand Disconnection Summary
Low Frequency Demand Disconnection Summary This article assesses the suitability of current low frequency protection on the network as more distributed generation is connected to WPD s network. DSOF June
More informationAnti-IslandingStrategyforaPVPowerPlant
Global Journal of Researches in Engineering: F Electrical and Electronics Engineering Volume 15 Issue 7 Version 1.0 Type: Double Blind Peer Reviewed International Research Journal Publisher: Global Journals
More informationTRANSFORMER OPERATION
Chapter 3 TRANSFORMER OPERATION 1 A transformer is a static device (no moving parts) used to transfer energy from one AC circuit to another. This transfer of energy may involve an increase or decrease
More informationPLAN... RESPOND... RESTORE! Utility Automation & Information Technology... Automation Rising
Automation Rising Q U A R T E R LY First Quarter 2013 The Digital Magazine of Automation & Information Technology for Electric, Gas and Water Utilities Utility Automation & Information Technology... PLAN...
More informationMicrogrid Operation for a Low Voltage Network with Renewable Energy Sources for Losses Minimisation and Voltage Control
Microgrid Operation for a Low Voltage Network with Renewable Energy Sources for Losses Minimisation and Voltage Control M. Z.C. Wanik, A. A. Ibrahim, Dept. of Electrical, Electronics and System Engineering
More informationDynamic Grid Edge Control
Dynamic Grid Edge Control Visibility, Action & Analytics at the Grid Edge to Maximize Grid Modernization Benefits The existence of greater volatility at the grid edge creates a set of problems that require
More informationShort Circuit Calculation in Networks with a High Share of Inverter Based Distributed Generation
Short Circuit Calculation in Networks with a High Share of Inverter Based Distributed Generation Harag Margossian, Juergen Sachau Interdisciplinary Center for Security, Reliability and Trust University
More informationWe take care of it. Special Publication. Power Quality PQ-Box 100/200. Expert opinions: Emergency power supply for hospitals and computer centres.
We take care of it. Special Publication Power Quality PQ-Box 100/200 Expert opinions: Emergency power supply for hospitals and computer centres. Power Quality PQ-Box 100/200 Emergency power supply for
More informationMV network design & devices selection EXERCISE BOOK
MV network design & devices selection EXERCISE BOOK EXERCISES 01 - MV substation architectures 02 - MV substation architectures 03 - Industrial C13-200 MV substation 04 - Max. distance between surge arrester
More informationAdvanced Metering Systems IEEE PES Cincy Section Meeting. Michael D. Simms PE Feb. 23, 2017
Advanced Metering Systems IEEE PES Cincy Section Meeting Michael D. Simms PE Feb. 23, 2017 Advanced Metering Systems This is not advanced metering! Advanced Metering Systems What is Advanced Metering?
More informationLow Voltage Grid Monitoring
Smart Grid Gotland Subproject Power Quality Low Voltage Grid Monitoring EUW Amsterdam 2017-10-04 Why monitor the low voltage grid? Power outages have so far been identified only by customers, not acceptable
More information