Renewable Interconnection Standard & Experimental Tests. Yahia Baghzouz UNLV Las Vegas, NV, USA
|
|
- Baldric Carroll
- 6 years ago
- Views:
Transcription
1 Renewable Interconnection Standard & Experimental Tests Yahia Baghzouz UNLV Las Vegas, NV, USA
2 Overview IEEE Std 1547 Voltage limitations Frequency limitations Harmonic limitations Expansion of IEEE Std through Anti-islanding Passive methods Active methods Islanding tests on local inverters
3 Publication Year: 2003
4 IEEE Std scope and purpose Scope: The standard establishes criteria and requirements for interconnection of distributed resources (DR) with electric power systems (EPS). Purpose : The document provides a uniform standard for interconnection of distributed resources with electric power systems. It provides requirements relevant to the performance, operation, testing, safety considerations, and maintenance of the interconnection.
5 Interconnection System Response to Abnormal Voltages
6 Interconnection System Response to Abnormal Frequencies
7 Maximum Harmonic Current Distortion
8 Synchronization Parameter Limits for Synchronous Interconnection
9 Maximum Voltage Distortion for Synchronous Machines
10 Expansion of IEEE Std ( Recommended Practice for Establishing Methods and Procedures that Provide Supplemental Support for Implementation Strategies for Expanded Use of IEEE Standard 1547 Pending
11 Medium Voltage Standard in Germany (10 kv-110 kv)
12 Medium Voltage Standard in Germany (10 kv-110 kv)
13 Medium Voltage Standard in Germany (10 kv-110 kv)
14 Inverter Response to Power Outage - Test Islanding occurs when the disconnected part of the power network is sustained by the connected PV systems for a significant period of time. Islanding is not desirable for several reasons: Creation of a hazard for utility line workers by touching a line that is supposed to be de-energized, lack of control over voltage and frequency in the island. Interference with restoration of normal service.
15 Expected inverter response PV inverter manufacturers market inverters that are expected to meet current interconnection standards (i.e., IEEE Std. 1547): They are expected to disconnect within 10 cycles if the voltage drops below 50% or rises above 120% of its nominal value. disconnect within 10 cycles if the supply frequency drops below 59.3 Hz or rises above 60.5 Hz. disconnect within 2 seconds cycles If the voltage drops to a value between 50%-88%, disconnect within 1 second if the voltage rises to a value between 110%-120% of the nominal value.
16 Inverter islanding detection Standard protection of grid-connected PV systems consists of four relays that will prevent islanding under most circumstances. over-voltage relay, under-voltage relay, over-frequency relay, under-frequency relay. However, if the local load closely matches the power produced by the inverter, the voltage and/or frequency deviations after a power outage may be too small to detect, i.e., fall within the non-detection zone. In this case, additional schemes are required to minimize the probability of an island to occur.
17 Voltage and frequency deviations Let the ratio of P S /P D = α, and Q S /Q D = β. Before disconnect, P (1 ) V / D 1 V ' V 1 2 R After utility disconnect, Q D 2 (1 ) V / L 1 ' 1
18 Possible Cases Case A: P S > 0 and Q S > 0: The voltage decreases. The frequency depends on the values of α and β. Case B: P S > 0 and Q S < 0: Both the voltage and frequency decrease. Case C: P S < 0 and Q S > 0: Both the voltage and frequency increase. Case D: P S < 0 and Q S < 0: The voltage increases. The frequency depends on the values of α and β. Case E: P S = 0 and Q S 0: The voltage remains constant, while the frequency changes (decreases if Q S < 0 or increases if Q S > 0). Case F: P S 0 and Q S = 0: The frequency remains constant, while the voltages changes (increases P S < 0 or decreases if P S > 0). Case G: P S = 0 and Q S = 0: Both the voltage and frequency remain constant.
19 Common Active Anti-Islanding Techniques Voltage harmonic monitoring: inverter monitors voltage total harmonic distortion and shuts down if this parameter exceeds some threshold. Phase jump detection: phase between inverter's terminal voltage and its output current is monitored for sudden jumps. Slide-mode frequency shift: the voltage-current phase angle of inverter is made a function of system frequency. Impedance measurement: perturbation periodically applied to inverter current. This will force a detectable change in voltage if the utility voltage is disconnected. Active frequency drift: inverter uses a slightly distorted output current to cause the frequency of the voltage to drift up or down when utility is disconnected.
20 PV System A: 18 kw Fixed Array (installed in 1999) Inverter Manufacturer: Trace Technologies Inc., Rating: 30 kva, 120/208V, 3-Phase. Anti-islanding technique for critical case: unknown
21 Schematic diagram of Test Circuit
22 Test Procedure and Apparatus Connect the transient recorder, load bank, and meters for reading current or power flow into the load and utility grid as shown in Figure. Adjust the load bank to the desired fraction of load relating to generated power. Open the utility disconnect while recording the voltage and current waveshapes. Repeat the two steps above for different generation-load power mismatch levels.
23 PV System A Switching Events Event No. Case P S (kw) P D (kw) Q S = -Q D (kvar) A.1 D A.2 B A.3 E Case B: P S > 0 and Q S < 0: the voltage decreases and frequency 0. Case D: P S < 0 and Q S < 0: The voltage increases, and frequency 0. Case E: P S = 0 and Q S < 0: The voltage remains constant, and frequency 0.
24 Event A.1 (α = -0.66, β = -1)
25 Event A.2 (α = +0.32, β = -1)
26 Event A.3 (α 0, β = -1)
27 PV System B: 25 kw 2-Axis Tracking (installed in 2003) Inverter Manufacturer: Advanced Energy Systems, LTD Inverter Rating: 30 kva, 120/208V, 3-Phase. Anti-islanding technique for critical case: unknown
28 PV System B Switching Events Event No. Case P S (kw) P D (kw) Q S = -Q D (kvar) B.1 D B.2 B B.3 E
29 Event B.1 (α = -0.26, β = -1 )
30 Event B.2 (α = +0.26, β = -1)
31 Event B.3 (α 0, β = -1)
32 Test Summary Both systems shut down in less than 5 cycles after the utility outage in compliance with the Interconnection standard that allows up to 10 cycles. The over-voltage and under-voltages relays isolated the inverter when there was mismatch between the PV power and local load power. The under-frequency relay isolated the inverter when there was a match between the PV power and local load power. Although small, the reactive power generated by both inverters will ultimately drive the frequency of the islanded system to zero, thus triggering the under-frequency relay under all resistive load conditions. An adjustable reactive load (in addition to the resistive load) would be needed to match both real and reactive powers and test for islanding under zero deviation in both voltage and frequency.
33 SIMPLE TEST ON 2 KW PV SYSTEM PV Array Size: 2 kw (peak) DC-side measurement AC-side measurement Response to an overvoltage ( V < 1.2 pu) Response to a large overvoltage (V > 1.2 pu)
34 DC-SIDE VOLTAGE AND CURRENT The inverter utilizes the Perturb-and-Observe method for MPPT. The voltage is perturbed by nearly 4 V, or 1.5% of the nominal value every 2 seconds.
35 AC-SIDE VOLTAGE AND CURRENT The AC current THD measures nearly 4% (the limit is 5%).
36 INVERTER RESPONSE TO 14% OVERVOLTAGE The inverter shut down after 56 cycles. The inverter is in compliance with IEEE Std which allows up to a maximum of 60 cycles for 1.1 < V < 1.2 p.u.
37 INVERTER RESPONSE TO 33% OVERVOLTAGE The inverter shut down within 8 cycles. The inverter is in compliance with IEEE Std which calls for a maximum of 10 cycles for V > 1.2 p.u.
38 Break!
Impact of High PV Penetration on Grid Operation. Yahia Baghzouz Professor of Electrical engineering University of Nevada Las Vegas
Impact of High PV Penetration on Grid Operation Yahia Baghzouz Professor of Electrical engineering University of Nevada Las Vegas Overview Introduction/Background Effects of High PV Penetration on Distribution
More informationINTERIM ARRANGEMENTS FOR GRID TIED DISTRIBUTED ENERGY RESOURCES. Technical Requirements for Grid-Tied DERs
INTERIM ARRANGEMENTS FOR GRID TIED DISTRIBUTED ENERGY RESOURCES Technical Requirements for Grid-Tied DERs Projects Division 6/29/2017 Contents 1 Definitions and Acronyms... 1 2 Technical Interconnection
More informationIEEE sion/1547revision_index.html
IEEE 1547 IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces http://grouper.ieee.org/groups/scc21/1547_revi sion/1547revision_index.html
More informationTechnical Requirements for Connecting Small Scale PV (sspv) Systems to Low Voltage Distribution Networks
2014 Technical Requirements for Connecting Small Scale PV (sspv) Systems to Low Voltage Distribution Networks This document specifies the technical requirement for connecting sspv to the low voltage distribution
More informationStudy of Centralized Anti-Islanding Method on Large-Scale Photovoltaic Power Plants
4th International Conference on Machinery, Materials and Information Technology Applications (ICMMITA 2016) Study of Centralized Anti-Islanding Method on Large-Scale Photovoltaic Power Plants Chen-Xin
More informationHybrid Islanding Detection Method for Distributed Generators
Hybrid Islanding Detection Method for Distributed Generators Priyanka Patil 1, Mrs. S.U.Kulkarni 2 PG Scholar, Dept. Of Electical Engg, Bharati Vidyapeeth University College Of Engineering, Pune, Maharashtra,
More informationProposed test procedure for the laboratory characterisation of gridconnected
Proposed test procedure for the laboratory characterisation of gridconnected micro-inverters. Mac Leod, B., Vorster, FJ., van Dyk, EE. Nelson Mandela Metropolitan University Centre for Renewable and Sustainable
More informationAnti-IslandingStrategyforaPVPowerPlant
Global Journal of Researches in Engineering: F Electrical and Electronics Engineering Volume 15 Issue 7 Version 1.0 Type: Double Blind Peer Reviewed International Research Journal Publisher: Global Journals
More informationECE 528 Understanding Power Quality
ECE 528 Understanding Power Quality http://www.ece.uidaho.edu/ee/power/ece528/ Paul Ortmann portmann@uidaho.edu 208-733-7972 (voice) Lecture 22 1 Today Homework 5 questions Homework 6 discussion More on
More informationE N G I N E E R I N G M A N U A L
1 1 1.0 PURPOSE The purpose of this document is to define policy and provide engineering guidelines for the AP operating companies (Monongahela Power Company, The Potomac Edison Company, and West Penn
More informationHybrid Anti-Islanding Algorithm for Utility Interconnection of Distributed Generation
Hybrid Anti-Islanding Algorithm for Utility Interconnection of Distributed Generation Maher G. M. Abdolrasol maher_photo@yahoo.com Dept. of Electrical Engineering University of Malaya Lembah Pantai, 50603
More informationIslanding Detection Method Based On Impedance Measurement
Islanding Detection Method Based On Impedance Measurement Chandra Shekhar Chandrakar 1, Bharti Dewani 2 Department of Electrical and Electronics Engineering Chhattisgarh Swami Vivekananda Technical University
More informationPhase-phase/phase-neutral: 24/13.8 kv star, 13.8 kv delta, 12/6.9 kv star.
Summary Of Interconnection Technical Guidelines for Renewable Energy Systems 0-100 kw under Standard Offer Contract (Extract from JPS Guide to Interconnection of Distributed Generation) This document is
More informationGrid Converters for Photovoltaic
Grid Converters for Photovoltaic and Wind Power Systems by R. Teodorescu, M. Liserre and P. Rodriguez ISBN: 978 0 470 05751 3 Copyright Wiley 2011 Chapter 3 Grid Requirements for PV Grid connection requirements
More informationDoãn Văn Đông, College of technology _ Danang University. 2. Local Techniques a. Passive Techniques
Detection of Distributed Generation Islanding Using Negative Sequence Component of Voltage Doãn Văn Đông, College of technology _ Danang University Abstract Distributed generation in simple term can be
More informationA Novel Active Anti-Islanding Protection Scheme for Grid-Interactive Roof-Top Solar PV System
A Novel Active Anti-Islanding Protection Scheme for Grid-Interactive Roof-Top Solar PV System Rohith Varier, Student member, IEEE and Naran M. Pindoriya, Member, IEEE Electrical Engineering, Indian Institute
More informationDP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation
DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation Technical Requirements for Interconnection and Parallel Operation of Distributed Generation Single Phase
More informationIEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces
IEEE PES Boston Chapter Technical Meeting IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces P1547 Chair David
More informationAn experimental Study of an Improved Active Frequency Drift Anti-Islanding Method for PV Application
International Journal of Engineering Research and Technology. ISSN 0974-3154 Volume 11, Number 5 (2018), pp. 755-762 International Research Publication House http://www.irphouse.com An experimental Study
More informationInverter-Based Resource Disturbance Analysis
Inverter-Based Resource Disturbance Analysis Key Findings and Recommendations Informational Webinar February 15, 2018 August 16, 2016 Blue Cut Fire Disturbance Key Findings and Recommendations 2 Western
More informationTable of Contents. Introduction... 1
Table of Contents Introduction... 1 1 Connection Impact Assessment Initial Review... 2 1.1 Facility Design Overview... 2 1.1.1 Single Line Diagram ( SLD )... 2 1.1.2 Point of Disconnection - Safety...
More informationGeneration Interconnection Requirements at Voltages 34.5 kv and Below
Generation Interconnection Requirements at Voltages 34.5 kv and Below 2005 March GENERATION INTERCONNECTION REQUIREMENTS AT 34.5 KV AND BELOW PAGE 1 OF 36 TABLE OF CONTENTS 1. INTRODUCTION 5 1.1. Intent
More informationEE Grid-Tied PV Systems. Y. Baghzouz Spring 2011
EE 495-695 Grid-Tied PV Systems Y. Baghzouz Spring 2011 Applicable Codes & Standards Most Important: NEC IEEE Std 1547 Summary of Content of NEC NEC (Voltage Drop Requirement) NEC requires that the voltage
More informationBED INTERCONNECTION TECHNICAL REQUIREMENTS
BED INTERCONNECTION TECHNICAL REQUIREMENTS By Enis Šehović, P.E. 2/11/2016 Revised 5/19/2016 A. TABLE OF CONTENTS B. Interconnection Processes... 2 1. Vermont Public Service Board (PSB) Rule 5.500... 2
More informationRevised IEEE 1547 Standard for Interconnecting Distributed Energy Resources with Electric Power Systems- National Grid Solar Program
1 Revised IEEE 1547 Standard for Interconnecting Distributed Energy Resources with Electric Power Systems- National Grid Solar Program Babak Enayati, PhD, PE Lead Engineer, National Grid Waltham, MA Email:
More informationIslanding and Detection of Distributed Generation Islanding using Negative Sequence Component of Current
http:// and Detection of Distributed Generation using Negative Sequence Component of Current Doan Van Dong Danang College of Technology, Danang, Vietnam Abstract - There is a renewed interest in the distributed
More informationAutomatic Phase-Shift Method for Islanding Detection of Grid-Connected Photovoltaic Inverters
IEEE TRANSACTIONS ON ENERGY CONVERSION, VOL. 18, NO. 1, MARCH 2003 169 Automatic Phase-Shift Method for Islanding Detection of Grid-Connected Photovoltaic Inverters Guo-Kiang Hung, Chih-Chang Chang, and
More informationA Novel Islanding Detection Technique for Distributed Generation (DG) Units in Power System
A Novel Islanding Detection Technique for Distributed Generation (DG) Units in Power System Amin Safari Department of Electrical Engineering, Ahar Branch, Islamic Azad University, Ahar, Iran a-safari@iau-ahar.ac.ir
More informationRemotes Case 2&3 Form REINDEER Cases 2&3 -Connection Impact Assessment (CIA) Application
General Application Information Remotes Case 2&3 Form REINDEER Cases 2&3 -Connection Impact Assessment (CIA) Application Hydro One Remote Communities Inc. Lori.Rice@hydroone.com 1-807-474-2828 This Application
More informationConnection Impact Assessment Application
Connection Impact Assessment Application This form is for generators applying for Connection Impact Assessment (CIA) and for generators with a project size >10 kw. Please return the completed form by email,
More informationRenewable Energy Systems
Renewable Energy Systems 6 Buchla, Kissell, Floyd Chapter Outline The Charge Controller and Inverter 6 Buchla, Kissell, Floyd 6-1 BATTERY CHARGERS 6-2 THE PWM CHARGE CONTROLLER 6-3 THE MPPT CHARGE CONTROLLER
More informationProtective Relaying for DER
Protective Relaying for DER Rogerio Scharlach Schweitzer Engineering Laboratories, Inc. Basking Ridge, NJ Overview IEEE 1547 general requirements to be met at point of common coupling (PCC) Distributed
More informationPOWER QUALITY AND SAFETY
POWER QUALITY AND SAFETY Date : November 27, 2015 Venue : 40 th IIEE Annual National Convention and 3E XPO 2015 PRESENTATION OUTLINE Power Quality I. INTRODUCTION II. GRID CODE REQUIREMENTS III. ERC RESOLUTION
More informationOPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS
OPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS AND MEDIUM-SIZE FACILITIES (5,000-25,000KW) CONNECTED
More informationOPERATING, METERING, AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 2,000 KILOWATTS
OPERATING, METERING, AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 2,000 KILOWATTS CONNECTED TO THE DISTRIBUTION SYSTEM ORANGE AND ROCKLAND
More informationIEEE Major Revision of Interconnection Standard
IEEE 1547-2018 - Major Revision of Interconnection Standard NRECA & APA s Emerging Priorities in Energy Research Day, Anchorage, AK Charlie Vartanian PE Secretary, IEEE 1547 Working Group October 31, 2018
More informationImprovement of Islanding Detector Using Interharmonics Current Injection Method and Its Applications
FEATURED TOPIC Improvement of Islanding Detector Using Interharmonics Current Injection Method and Its Applications Sadayuki ISHIKURA*, Hideyuki NAKATANI, Junya TAKAGI, Tsutomu FUKADA, Shoji NISHIMURA
More informationSouthern Company Interconnection Requirements for Inverter-Based Generation
Southern Company Interconnection Requirements for Inverter-Based Generation September 19, 2016 Page 1 of 16 All inverter-based generation connected to Southern Companies transmission system (Point of Interconnection
More informationIntermittent Renewable Resources (Wind and PV) Distribution Connection Code (DCC) At Medium Voltage (MV)
Intermittent Renewable Resources (Wind and PV) Distribution Connection Code (DCC) At Medium Voltage (MV) IRR-DCC-MV 1. Introduction 1 IRR-DCC-MV 2. Scope 1 IRR-DCC-MV 2.1. General 1 IRR-DCC-MV 2.2. Affected
More informationGrid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017
Grid codes and wind farm interconnections CNY Engineering Expo Syracuse, NY November 13, 2017 Purposes of grid codes Grid codes are designed to ensure stable operating conditions and to coordinate the
More informationNORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number: Address:
NORTH CAROLINA INTERCONNECTION REQUEST Utility: Designated Contact Person: Address: Telephone Number: Fax: E-Mail Address: An is considered complete when it provides all applicable and correct information
More informationIslanding Detection Techniques for Distributed Energy Resources-Review
Islanding Detection Techniques for Distributed Energy Resources-Review Janki N. Patel 1 P.G. Student, Department of Electrical Engineering, SCET, Surat, Gujarat, India 1 ABSTRACT: Distributed generators
More informationTechnical Interconnection Requirements For Transmission Voltage Customers for Service at 60,000 to 287,000 Volts R XX
Technical Interconnection Requirements For Transmission Voltage Customers for Service at 60,000 to 287,000 Volts R XX May 2018 Disclaimer This document provides general technical interconnection requirements
More informationHarmonics Issues that Limit Solar Photovoltaic Generation on Distribution Circuits
WREF 01 Paper # 048 Harmonics Issues that Limit Solar Photovoltaic Generation on Distribution Circuits Ketut Dartawan Ricardo Austria, Le Hui and Mark Suehiro* Pterra Consulting Maui Electric Company*
More informationTECHNICAL GUIDELINE FOR THE INTERCONNECTION OF DISTRIBUTED ENERGY RESOURCES TO EPCOR DISTRIBUTION AND TRANSMISSION INC. S DISTRIBUTION SYSTEM
TECHNICAL GUIDELINE FOR THE INTERCONNECTION OF DISTRIBUTED ENERGY RESOURCES TO EPCOR DISTRIBUTION AND TRANSMISSION INC. S DISTRIBUTION SYSTEM January 5, 2017 Francesco Mannarino SVP, Electricity Operations
More informationTesting Advanced Photovoltaic Inverters Conforming to IEEE Standard 1547 Amendment 1
> REPLACE THIS LINE WITH YOUR PAPER IDENTIFICATION NUMBER (DOUBLE-CLICK HERE TO EDIT) < Testing Advanced Photovoltaic Inverters Conforming to IEEE Standard 547 Amendment Anderson Hoke, Student Member,
More informationNon-detection zone of LOM protection for converter connected wind turbines
- 1 - Non-detection zone of LOM protection for converter connected wind turbines Ontrei Raipala, Tampere University of Technology, Finland Table of contents Table of contents... 1 Introduction... 2 Loss
More informationThe Connecticut Light and Power Company
The Connecticut Light and Power Company and The United Illuminating Company Exhibit B - Generator Interconnection Technical Requirements May 12, 2010 Page 1 of 26 Table of Contents 1. SCOPE... 3 2. GENERAL
More informationREACTIVE POWER BASED ANTI-ISLANDING SCHEME FOR SYNCHRONOUS DISTRIBUTED GENERATORS
International Journal on Technical and Physical Problems of Engineering (IJTPE) Published by International Organization of IOTPE ISSN 2077-3528 IJTPE Journal www.iotpe.com ijtpe@iotpe.com December 2012
More informationGENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW
GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW ELECTRIC UTILITY CONTACT INFORMATION Consumers Energy Interconnection Coordinator 1945
More informationImplementation of Revised IEEE Standard 1547
MAY 31, 2017 HOLYOKE, MASSACHUSETTS Implementation of Revised IEEE Standard 1547 Presentation to ISO-TO Operations Committee David Forrest Key Points As New England adds significant amounts of Distributed
More informationA Hybrid Anti-Islanding Method for Inverter-Based Distributed Generation
A Hybrid Anti-Islanding Method for Inverter-Based Distributed Generation Ebrahim Rokrok 1, Miadreza Shafie-khah 1, Hamid Reza Karshenas 2, Esmail Rokrok 3, João P.S. Catalão 1,4,5 1 C-MAST, University
More informationImpact Assessment Generator Form
Impact Assessment Generator Form This connection impact assessment form provides information for the Connection Assessment and Connection Cost Estimate. Date: (dd/mm/yyyy) Consultant/Developer Name: Project
More information1200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report
1200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report Rich Bauer Associate Director Reliability Risk Management / Event Analysis Mid C Seminar July 19, 2017 Western Interconnection
More informationTEST REPORT AS :2005 and AS :2005 Grid connection of energy systems via inverters Grid protection requirements
TEST REPORT AS 4777.2:2005 and AS 4777.3:2005 Grid connection of energy systems via inverters Grid protection requirements Report reference No...: 09TH0459-AS4777_2 Tested by (printed name and signature)...:
More informationIEEE sion/1547revision_index.html
IEEE 1547 IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces http://grouper.ieee.org/groups/scc21/1547_revi sion/1547revision_index.html
More informationSmall-scale PV Inverters EEA Conference, Wellington. Bill Heffernan, Patrick Chen and Ankur Mishra June 2016
Small-scale PV Inverters EEA Conference, Wellington Bill Heffernan, Patrick Chen and Ankur Mishra June 2016 Introduction Concern exists regarding the effects of many inverters connecting to the LV system
More informationPublic Consultation on the Regulatory Framework for Small Scale Grid Connected Solar PV Systems Standards Technical Standards
Consultation Paper: 1/2017 (i) Public Consultation on the Regulatory Framework for Small Scale Grid Connected Solar PV Systems Standards Technical Standards Issued on 19 January 2017 Contents 1. Introduction
More informationGENERATOR INTERCONNECTION APPLICATION Category 3 For All Projects with Aggregate Generator Output of More Than 150 kw but Less Than or Equal to 550 kw
GENERATOR INTERCONNECTION APPLICATION Category 3 For All Projects with Aggregate Generator Output of More Than 150 kw but Less Than or Equal to 550 kw ELECTRIC UTILITY CONTACT INFORMATION Consumers Energy
More informationIEEE Std Bulk System Opportunities from New Distributed Energy Resource Interconnection and Interoperability Standards
IEEE Std 1547-2018 Bulk System Opportunities from New Distributed Energy Resource Interconnection and Interoperability Standards Clayton Stice, ERCOT Jens C. Boemer, EPRI (on behalf of SCC21) NERC SPIDER
More informationGrid Code 2015 for Small Scale Distributed Generation (SSDG) Net Metering Scheme Version June 2017 Central Electricity Board
Grid Code 2015 for Small Scale Distributed Generation (SSDG) Net Metering Scheme Version 2.2 - June 2017 Central Electricity Board Foreword The purpose of this document is to assist the public to better
More informationDER Ride-Through Performance Categories and Trip Settings Presentation at PJM Ride-Through Workshop, Philadelphia, PA, October 1-2, 2018
DER Ride-Through Performance Categories and Trip Settings Presentation at PJM Ride-Through Workshop, Philadelphia, PA, October 1-2, 2018 Dr. Jens C. Boemer, Principal Technical Leader, EPRI Reigh Walling,
More informationEVALUATION OF ANTI-ISLANDING PROTECTION SCHEMES
EVALUATION OF ANTI-ISLANDING PROTECTION SCHEMES INDIAN CONTEXT Renewable Energy World India Kona Eswararao Gamesa R&D Chennai New Delhi / 21 April 2012 EVALUATION OF ANTI - ISLANDING SCHEMES Distributed
More informationCHAPTER 4 PV-UPQC BASED HARMONICS REDUCTION IN POWER DISTRIBUTION SYSTEMS
66 CHAPTER 4 PV-UPQC BASED HARMONICS REDUCTION IN POWER DISTRIBUTION SYSTEMS INTRODUCTION The use of electronic controllers in the electric power supply system has become very common. These electronic
More informationSynchronization and Smooth Connection of Solar Photovoltaic Generation to Utility Grid
International Journal of Electrical Engineering. ISSN 0974-2158 Volume 9, Number 1 (2016), pp. 51-56 International Research Publication House http://www.irphouse.com Synchronization and Smooth Connection
More informationDYNAMIC VOLTAGE RESTORER FOR VOLTAGE SAG MITIGATION IN OIL & GAS INDUSTRY
Department of Electrical Engineering Senior Design Project ELEC 499 DYNAMIC VOLTAGE RESTORER FOR VOLTAGE SAG MITIGATION IN OIL & GAS INDUSTRY Student Names: Chresteen Baraket Marina Messiha Supervised
More informationProject acronym: Multi-island
Technical report for The Experimental investigation on the performance characteristics of anti-islanding techniques in the prospect of high PV penetration level Project acronym: Multi-island USER PROJECT
More informationSection G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES
Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES Purpose This section specifies the requirements for protective relays and control devices for Generation Entities interconnecting
More informationInverter Source Requirement Document of ISO New England (ISO-NE)
Inverter Source Requirement Document of ISO New England (ISO-NE) This Source Requirement Document applies to inverters associated with specific types of generation for projects that have applied for interconnection
More informationHARMONICS ANALYSIS USING SEQUENTIAL-TIME SIMULATION FOR ADDRESSING SMART GRID CHALLENGES
HARMONICS ANALYSIS USING SEQUENTIAL-TIME SIMULATION FOR ADDRESSING SMART GRID CHALLENGES Davis MONTENEGRO Roger DUGAN Gustavo RAMOS Universidad de los Andes Colombia EPRI U.S.A. Universidad de los Andes
More informationA Novel Grid Connected PV Micro Inverter
IOSR Journal of Electrical and Electronics Engineering (IOSR-JEEE) e-issn: 2278-1676,p-ISSN: 2320-3331 PP 66-71 www.iosrjournals.org A Novel Grid Connected PV Micro Inverter Jijo Balakrishnan 1, Kannan
More informationIssued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY
WN U-60 Attachment C to Schedule 152, Page 1 SCHEDULE 152 APPLICATION FOR INTERCONNECTING A GENERATING FACILITY TIER 2 OR TIER 3 This Application is considered complete when it provides all applicable
More informationPOWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS.
POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS. This document may be subject to changes. Contact ARTECHE to confirm the characteristics and availability of the products
More informationFNN comments on NC HVDC submitted to ENTSO E
the term HV is not defined > A further definition should be applied since the term is used all through the code A lot of terms from the Network Code RfG are used and should be checked regarding consistency
More informationPRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75
PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion
More informationAnti-Islanding Protection of Distributed Generation Resources Using Negative Sequence Component of Voltage
POWERENG 2007, April 12-14, 2007, Setúbal, Portugal Anti-Islanding Protection of Distributed Generation Resources Using Negative Sequence Component of Voltage Amin Helmzadeh, Javad Sadeh and Omid Alizadeh
More informationIJSRD - International Journal for Scientific Research & Development Vol. 4, Issue 04, 2016 ISSN (online):
IJSRD - International Journal for Scientific Research & Development Vol. 4, Issue 04, 2016 ISSN (online): 2321-0613 Boost Converter fed PV Interfaced AC Distribution System Incorporating Islanding Detection
More informationTechnical Requirements For Generation Connected to The ODEC System
Old Dominion Electric Cooperative Technical Requirements For Generation Connected to The ODEC System March 30, 2010 1 2 Table of Contents Topics Page Number Disclaimer.. 3 Perquisites.. 3 Applicability..
More informationA New Islanding Detection Method Based On Wavelet-transform and ANN for Inverter Assisted Distributed Generator
University of Kentucky UKnowledge Theses and Dissertations--Electrical and Computer Engineering Electrical and Computer Engineering 215 A New Islanding Detection Method Based On Wavelet-transform and ANN
More informationFundamentals of Grid Connected Photo-Voltaic Power Electronic Converter Design
Fundamentals of Grid Connected Photo-Voltaic Power Electronic Converter Design Svein Erik Evju Master of Science in Energy and Environment Submission date: June 007 Supervisor: Lars Einar Norum, ELKRAFT
More informationDelhi Technological University (formerly DCE) Delhi-42, India
American International Journal of Research in Science, Technology, Engineering & Mathematics Available online at http://www.iasir.net ISSN (Print): 2328-3491, ISSN (Online): 2328-358, ISSN (CD-ROM): 2328-3629
More informationHOOSIER ENERGY REC, INC. Requirements for Connection of Generation Facilities. to the HE Transmission System
HOOSIER ENERGY REC, INC Requirements for Connection of Generation Facilities to the HE Transmission System January 2009 Table of Contents 1.0 INTRODUCTION...1 2.0 TYPES OF CONNECTED CIRCUIT CONFIGURATIONS...6
More informationUtility Interconnection and System Protection
Utility Interconnection and System Protection Alex Steselboim President, Advanced Power Technologies, Inc. Utility paralleling vs. isolated operation. Isochronous kw load sharing Reactive power (VAR) sharing
More informationGUIDE FOR GENERATOR INTERCONNECTION THE WIRES OWNER DISTRIBUTION SYSTEM
DATE: 200/06/2 PAGE 1 of GUIDE FOR GENERATOR INTERCONNECTION TO THE WIRES OWNER DISTRIBUTION SYSTEM The intent of this Guide is to establish the interconnection requirements of Distributed Resources with
More informationInstallation and Operating Instructions. Power IT Power Factor Controller RVC
Installation and Operating Instructions Power IT Power Factor Controller RVC Table of contents Page 1. Read this first... 3 About this Instruction Manual... 3 Safety... 3 Electromagnetic compatibility...
More informationHarmonic Study in Low Voltage Distribution Network in a Real Time Foundry Industry
I J C T A, 9(37) 2016, pp. 769-781 International Science Press Harmonic Study in Low Voltage Distribution Network in a Real Time Foundry Industry D. Ravichandran * and Er. R. Panneerselvam ** Abstract:
More informationWind Power Facility Technical Requirements CHANGE HISTORY
CHANGE HISTORY DATE VERSION DETAIL CHANGED BY November 15, 2004 Page 2 of 24 TABLE OF CONTENTS LIST OF TABLES...5 LIST OF FIGURES...5 1.0 INTRODUCTION...6 1.1 Purpose of the Wind Power Facility Technical
More informationeach time the Frequency is above 51Hz. Continuous operation is required
GC0101 EXTRACT OF EUROPEAN CONNECTION CONDITIONS LEGAL TEXT DATED 08/01/2018. ECC.6 ECC.6.1 ECC.6.1.1 ECC.6.1.2 ECC.6.1.2.1 ECC.6.1.2.1.1 ECC.6.1.2.1.2 ECC.6.1.2.1.3 TECHNICAL, DESIGN AND OPERATIONAL CRITERIA
More informationPRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76
PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion
More informationRENEWABLE ENERGY SUB-CODE for Distribution Network connected Variable Renewable Energy Power Plants in Ghana
RENEWABLE ENERGY SUB-CODE for Distribution Network connected Variable Renewable Energy Power Plants in Ghana JANUARY 2015 i Table of Content PART A: 1 1 Introduction 1 1.1 Scope 1 1.2 Status 1 1.3 Terms
More informationAPS M1P Single-phase Micro-inverter Installation and User Manual
APS M1P Single-phase Micro-inverter Installation and User Manual Version: 2.0 ALTENERGY POWER SYSTEM, INC. All rights reserved 1 Contact Information ALTENERGY POWER SYSTEM Inc. 1 Yatai Road, Jiaxing, PR
More information2012 Grid of the Future Symposium. Impacts of the Decentralized Photovoltaic Energy Resources on the Grid
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2012 Grid of the Future Symposium Impacts of the Decentralized Photovoltaic Energy Resources on the Grid B. ENAYATI, C.
More informationADVANCED VECTOR SHIFT ALGORITHM FOR ISLANDING DETECTION
23 rd International Conference on Electricity Distribution Lyon, 5-8 June 25 Paper 48 ADVANCED VECT SHIFT ALGITHM F ISLANDING DETECTION Murali KANDAKATLA Hannu LAAKSONEN Sudheer BONELA ABB GISL India ABB
More informationPOWER QUALITY IMPACTS AND MITIGATION OF DISTRIBUTED SOLAR POWER
POWER QUALITY IMPACTS AND MITIGATION OF DISTRIBUTED SOLAR POWER Presented by Ric Austria, Principal at Pterra Consulting to the IEEE San Francisco Chapter Feb 17, 2016 California Public Utilities Commission,
More informationHarmonic Mitigation for Variable Frequency Drives. HWEA Conference February 15, Kelvin J. Hurdle Rockwell Bus. Dev. Mgr.
Harmonic Mitigation for Variable Frequency Drives HWEA Conference February 15, 2011 Kelvin J. Hurdle Rockwell Bus. Dev. Mgr. 1 OVERVIEW Linear vs. Non- Linear Load Definitions AC Drive Input Current Harmonics
More informationForm B. Connection Impact Assessment Application Form Distribution System
Form B Connection Impact Assessment Application Form Distribution System This Application Form is for Generators applying for Connection Impact Assessment ( CIA ). It is important that the Generator provides
More informationISLANDING DETECTION IN DISTRIBUTION SYSTEM EMBEDDED WITH RENEWABLE-BASED DISTRIBUTED GENERATION. Saurabh Talwar
ISLANDING DETECTION IN DISTRIBUTION SYSTEM EMBEDDED WITH RENEWABLE-BASED DISTRIBUTED GENERATION by Saurabh Talwar B. Eng, University of Ontario Institute of Technology, Canada, 2011 A Thesis Submitted
More informationRapid Backup Power Solution Guide with Stabiliti PCS
Application Note 504 Rapid Backup Power Solution Guide with Stabiliti PCS 1.0 PURPOSE AND SCOPE The Stabiliti series are 30 kw bi-directional Power Conversion Systems (PCS) for commercial 3-phase electricity
More informationGrid Code Violation during Fault Triggered Islanding of Hybrid Micro-grid
Grid Code Violation during Fault Triggered Islanding of Hybrid Micro-grid Mazheruddin H. Syed, Student Member, IEEE, H.H. Zeineldin and M.S. El Moursi, Member, IEEE Department of Electrical Power Engineering
More informationProgrammable Grid Simulator THE POWER TEST EXPERTS
PAS-F Series 45kVA to 1.6MVA Programmable Grid Simulator THE POWER TEST EXPERTS PAS-F Series 45kVA to 1.6MVA Product Overview The PAS-F Series is a broad line of programmable three phase output regenerative
More information