Massive Transient Stability Based Cascading Analysis and On-line Identification of Critical Cascades

Size: px
Start display at page:

Download "Massive Transient Stability Based Cascading Analysis and On-line Identification of Critical Cascades"

Transcription

1 1 Massive Transient Stability Based Cascading Analysis and On-line Identification of Critical Cascades Paper Number: 16PESGM2419 Marianna Vaiman, V&R Energy 2016 IEEE PES General Meeting, Boston, MA CFWG Panel Session Cascading Outages - Dynamics, Protection, Validation and Data July 20, 2016

2 2 Contents: 1. Massive Transient Stability Based Cascading Analysis 2. On-Line Identification of Critical Cascades

3 3 1. Massive Transient Stability Based Cascading Analysis

4 CWFG Survey What would make you more satisfied/are there any computations associated with cascading outages you feel present tools fail to address? Dynamic simulation of cascading outages which should include protection system modeling Better solution algorithms/robust tools Automated/optimized mitigation measures Identifying and classifying widespread system area limitation versus local area limitation Identifying and quantifying the risk of complicated cascades and large blackouts in a way that allows these risks to be monitored and mitigated Having a screening tool Wide area visualization and analysis tools that can identify stress indicators early and help operators take appropriate actions

5 NERC Standards Related to Cascading PRC Disturbance Monitoring and Reporting Requirements TPL Transmission System Planning Performance Requirements CIP Physical Security CIP Cyber Security BES Cyber System Categorization PRC Transmission Relay Loadability PRC Generator Frequency and Voltage Protective Relay Settings EOP Capacity and Energy Emergencies EOP Load Shedding Plans TOP Transmission Operations TOP Transmission Operations FAC Transmission Vegetation Management FAC System Operating Limits Methodology for the Operations Horizon IRO Reliability Coordinator Operational Analyses and Real-time Assessments IRO-010-1a Reliability Coordinator Data Specification and Collection

6 6 An Approach to Transient Stability Based Cascading Analysis Implemented in Potential Cascading Modes Transient Stability (PCM-TS) application: Analyzes cascading outages from transient stability perspective while considering protection system Used to address NERC TPL standard Addresses the following aspects of assessment of cascading outages: Initiating events three-phase & unbalanced faults, and user-defined switching sequences Considers generator out-of-step conditions, overloads, transient voltage deviation Incorporates protection system modeling

7 7 A Cascading Event from Transient Stability Perspective An event is classified as a cascading outage if at least one of the conditions is met: Sharp drop in transient voltages in a large part of the network Sharp drop in frequency followed by system separation Islands are formed as a result of protection operation, with significant amount of load/ generation within the island Disconnection of large amount of generation Disconnection of large amount of load

8 8 Time-Domain Simulation during Cascading Analysis Each cascading event is simulated using time domain simulation: Associated time constants are specified as the user input During a cascading event, elements are being tripped. Tripped elements may be lines, transformers, loads, and generators

9 9 Critical Cascade Criteria Time-domain simulation runs until at least one of the Critical Cascade criteria is met: Islanding Total MW of load in all created islands, except the largest island exceeds a pre-defined threshold Interface limit violation Interface MW flow during cascade exceeds interface limit MW load loss Total MW loss of load tripped during cascade exceeds a pre-defined threshold MW generation loss Total MW loss of generation exceeds a pre-defined threshold Cascade propagation Cascade propagates beyond the user-defined control area(s)

10 10 Generator Angle Deviation Checks the maximum change in the rotor angle deviation Computes the difference between maximum and minimum generator rotor angles, and determines the maximum difference: Computed during user-defined time interval Units with smaller real power output may be excluded from monitoring Done for informational purposes only; this is not included in Critical Cascade criteria

11 11 Checking Steady-State Stability After time-domain computation is completed, all elements tripped as a result of a cascading chain, are tripped using steady-state (e.g., load flow) computation Power flow solution is obtained

12 12 Critical Tripping Criteria and Delays Tripping occurs during a cascading event if at least one of the tripping criteria is met: Line tripping threshold Transformer tripping threshold Load tripping threshold Generator tripping thresholds Element Tripping and Delays: Tripping occurs only if a criterion continues to be met during Relay Delay time interval In this case, the element will be tripped after Relay Delay time interval elapsed

13 13 Modeling Relay Operation Four types of relays considered during the analysis: Distance relays Overcurrent relays Undervoltage relays Underfequencyrelay It is assumed that the above relays are installed on all lines, transformers, loads, and generators Relay operation is modeled using the user-defined delays

14 14 Types of Cascading Outcomes Based on determination and comparison of damping parameters Outcome Outcome Type 1 Decreasing amplitude oscillations 2 Increasing amplitude oscillations 3 Oscillations with decreasing frequency 4 Oscillations with increasing frequency 5 Monotonously increasing frequency 6 Monotonously decreasing frequency

15 15 Results of Massive Cascading Analysis Detailed and summarized results of cascading analysis are produced

16 16 2. On-Line Identification of Critical Cascades

17 17 On-Line Cascading Analysis Steady-state analysis of fast developing cascading events when Operator has no time to react Uses node-breaker model of the system: SCADA-based State-Estimator cases or PMU-based Linear State Estimator Cases Initiating Events are complex contingencies (N-2, stuck breaker) beyond N-1 which are addressed in regular dispatch Classifies every Initiating Event as Critical, Near critical or Acceptable: Based on operational reliability criteria applied to consequences of potential cascade Implemented in ROSE/PCM tool

18 18 Identification of a Critical Cascade Purpose: classification of Cascade as Critical is the identification of IROL violation based on measurable consequences Existence of a Critical Cascade longer than 30 minutes means IROL violation reportable event Concept of Critical Cascade is a consistent, quantifiable and auditable process of IROL violation analysis Concept of Critical Cascade is a practical instrument to satisfy generic NERC requirements of IROL compliance Source: ISONE and V&R Energy

19 19 Attributes of a Critical Cascade Critical Cascade satisfies at least one of the following criteria: System wide voltage collapse occurs upon applying initiating contingency or as the result of cascading tripping Islanding of the system and total MW of load in separated islands is greater than pre-defined threshold Actual interface MW flow during cascade exceeds stability interface limit by pre-defined % level Total MW loss of load exceeds pre-defined threshold Total MW loss of generation exceeds pre-defined threshold Cascade propagates beyond Balancing Area footprint Each criterion for a Critical Cascade is configurable : Enable/Disable Threshold value

20 20 Data Flow for On-Line Analysis Source: Slava Maslennikov, Eugene Litvinov, ISONE

21 21 Process of On-Line Cascading Analysis Source: Slava Maslennikov, Eugene Litvinov, ISONE

22 22 On-line ROSE-PCM GUI Source: Slava Maslennikov, Eugene Litvinov, ISONE

23 23 Metrics of Locality of Voltage Collapse Non-convergence of power flow is reported as voltage instability. Majority ( >90%) of voltage instability has local impact and affects quite limited MW of loads Typical power flow solution cannot distinguish local from wide spread voltage instability Locality of voltage collapse is measured by the minimal MW of load shedding necessary to prevent voltage collapse Source: Slava Maslennikov, Eugene Litvinov, ISONE

24 Thank you! 24

ROSE - Real Time Analysis Tool for Enhanced Situational Awareness

ROSE - Real Time Analysis Tool for Enhanced Situational Awareness ROSE - Real Time Analysis Tool for Enhanced Situational Awareness Marianna Vaiman V&R Energy Copyright 1997-2013 V&R Energy Systems Research, Inc. All rights reserved. WECC JSIS Salt Lake City, UT October

More information

System Operating Limit Definition and Exceedance Clarification

System Operating Limit Definition and Exceedance Clarification System Operating Limit Definition and Exceedance Clarification The NERC-defined term System Operating Limit (SOL) is used extensively in the NERC Reliability Standards; however, there is much confusion

More information

Linear State Estimation

Linear State Estimation Linear State Estimation Marianna Vaiman, V&R Energy marvaiman@vrenergy.com WECC JSIS Meeting Salt Lake City, UT October 15 17, 2013 Copyright 1997-2013 V&R Energy Systems Research, Inc. All rights reserved.

More information

September 19, Errata to Implementation Plan for the Revised Definition of Remedial Action Scheme

September 19, Errata to Implementation Plan for the Revised Definition of Remedial Action Scheme !! September 19, 2017 VIA ELECTRONIC FILING Veronique Dubois Régie de l'énergie Tour de la Bourse 800, Place Victoria Bureau 255 Montréal, Québec H4Z 1A2 RE: Errata to for the Revised Definition of Remedial

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the Board of Trustees. Description

More information

Understanding Cascading Phenomenon: Methodologies and Industry Practice for Analysis of Cascading Failures. Table of Contents

Understanding Cascading Phenomenon: Methodologies and Industry Practice for Analysis of Cascading Failures. Table of Contents Understanding Cascading Phenomenon: Methodologies and Industry Practice for Analysis of Cascading Failures 2015 IEEE PES General Meeting Denver, CO Sponsored by Cascading Failure Working Group under IEEE

More information

Assessing Vulnerability to Cascading Outages

Assessing Vulnerability to Cascading Outages 1 Assessing Vulnerability to Cascading Outages N. Bhatt, Senior Member, IEEE, S. Sarawgi, Member, IEEE, R. O'Keefe, Member, IEEE, P. Duggan, Senior Member, IEEE, M. Koenig, Member, IEEE, M. Leschuk, Member,

More information

(Circuits Subject to Requirements R1 R5) Generator Owner with load-responsive phase protection systems as described in

(Circuits Subject to Requirements R1 R5) Generator Owner with load-responsive phase protection systems as described in A. Introduction 1. Title: Transmission Relay Loadability 2. Number: PRC-023-3 3. Purpose: Protective relay settings shall not limit transmission loadability; not interfere with system operators ability

More information

May 30, Errata to Implementation Plan for the Revised Definition of Remedial Action Scheme Docket No. RM15-13-_

May 30, Errata to Implementation Plan for the Revised Definition of Remedial Action Scheme Docket No. RM15-13-_ May 30, 2018 VIA ELECTRONIC FILING Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C. 20426 RE: Errata to for the Revised Definition of Remedial Action

More information

GridLiance Reliability Criteria

GridLiance Reliability Criteria GridLiance Reliability Criteria Planning Department March 1, 2018 FOREWORD The GridLiance system is planned, designed, constructed, and operated to assure continuity of service during system disturbances

More information

MidAmerican Energy Company Reliability Planning Criteria for 100 kv and Above

MidAmerican Energy Company Reliability Planning Criteria for 100 kv and Above MidAmerican Energy Company Reliability Planning Criteria for 100 kv and Above March 13, 2018 Issued by: Dehn Stevens, Director System Planning and Services 1.0 SCOPE This document defines the criteria

More information

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/ ITC Holdings Planning Criteria Below 100 kv * Category: Planning Type: Policy Eff. Date/Rev. # 12/09/2015 000 Contents 1. Goal... 2 2. Steady State Voltage & Thermal Loading Criteria... 2 2.1. System Loading...

More information

ESB National Grid Transmission Planning Criteria

ESB National Grid Transmission Planning Criteria ESB National Grid Transmission Planning Criteria 1 General Principles 1.1 Objective The specific function of transmission planning is to ensure the co-ordinated development of a reliable, efficient, and

More information

Phase Angle Monitoring:

Phase Angle Monitoring: Phase Angle Monitoring: Industry Experience Following the 2011 Pacific Southwest Outage Recommendation 27 Ryan D. Quint, PhD, PE NERC SMS Coordinator NASPI Work Group Meeting October 2016 Background Purpose:

More information

NORMES DE FIABILITÉ DE LA NERC (VERSION ANGLAISE)

NORMES DE FIABILITÉ DE LA NERC (VERSION ANGLAISE) COORDONNATEUR DE LA FIABILITÉ Direction Contrôle des mouvements d énergie Demande R-3944-2015 NORMES DE FIABILITÉ DE LA NERC (VERSION ANGLAISE) Original : 2016-10-14 HQCMÉ-10, Document 2 (En liasse) Standard

More information

Real Time Stability Analysis at Peak Reliability. Slaven Kincic, Hongming Zhang JSIS May 2017, SLC

Real Time Stability Analysis at Peak Reliability. Slaven Kincic, Hongming Zhang JSIS May 2017, SLC Real Time Stability Analysis at Peak Reliability Slaven Kincic, Hongming Zhang JSIS May 2017, SLC Overview: Overview of Peak s DSA Application; o Set up o User Cases Transient Stability Criteria; TSAT

More information

4.2.1 Generators Transformers Transmission lines. 5. Background:

4.2.1 Generators Transformers Transmission lines. 5. Background: PRC-026-1 Relay Performance During Stable Power Swings A. Introduction 1. Title: Relay Performance During Stable Power Swings 2. Number: PRC-026-1 3. Purpose: To ensure that load-responsive protective

More information

Standard Development Timeline

Standard Development Timeline PRC-026-1 Relay Performance During Stable Power Swings Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the

More information

Standard Development Timeline

Standard Development Timeline PRC-026-1 Relay Performance During Stable Power Swings Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the

More information

TTC Study for: the PEGS-Ambrosia Lake 230 kv Line and the PEGS-Bluewater 115 kv Line

TTC Study for: the PEGS-Ambrosia Lake 230 kv Line and the PEGS-Bluewater 115 kv Line TTC Study for: the PEGS-Ambrosia Lake 230 kv Line and the PEGS-Bluewater 115 kv Line Vince Leung March 27, 2017 Reviewed by Johnny Nguyen Table of Contents Background 2 Objective 3 Base Case Assumptions

More information

Online Oscillation Management at ISO New England

Online Oscillation Management at ISO New England NASPI. SEPTEMBER 27,2017 Online Oscillation Management at ISO New England SLAVA MASLENNIKOV XIAOCHUAN LUO FRANKIE ZHANG IZUDIN LELIC EUGENE LITVINOV PMU Infrastructure at ISO New England Installed in 2012

More information

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell Power Plant and Transmission System Protection Coordination Phase Distance (21) and Voltage-Controlled or Voltage-Restrained Overcurrent Protection (51V) NERC Protection Coordination Webinar Series June

More information

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1 PRC-025-1 Generator Relay Loadability A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1 Purpose: To set load-responsive protective relays associated with generation Facilities

More information

NERC / TVA STABILITY WORKSHOP

NERC / TVA STABILITY WORKSHOP NERC / TVA STABILITY WORKSHOP CHATTANOOGA, TN MAY 23-24, 24, 2007 Robert Dintelman Utility System Efficiencies, Inc. WECC Transmission System 1996 Western Outages July 2, 1996 July 3, 1996 August 10, 1996

More information

NPCC Regional Reliability Reference Directory # 12. Underfrequency Load Shedding Program Requirements

NPCC Regional Reliability Reference Directory # 12. Underfrequency Load Shedding Program Requirements NPCC Regional Reliability Reference Directory # 12 Under frequency Load Shedding Program Requirements Task Force on System Studies Revision Review Record: June 26 th, 2009 March 3 rd, 2010 Adopted by the

More information

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1 A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1 Purpose: To set load-responsive protective relays associated with generation Facilities at a level to prevent unnecessary tripping

More information

DUKE ENERGY CAROLINAS TRANSMISSION SYSTEM PLANNING GUIDELINES. Transmission Planning

DUKE ENERGY CAROLINAS TRANSMISSION SYSTEM PLANNING GUIDELINES. Transmission Planning DUKE ENERGY CAROLINAS TRANSMISSION SYSTEM PLANNING GUIDELINES Transmission Planning TABLE OF CONTENTS I. SCOPE 1 II. TRANSMISSION PLANNING OBJECTIVES 2 III. PLANNING ASSUMPTIONS 3 A. Load Levels 3 B. Generation

More information

Smart Grid Where We Are Today?

Smart Grid Where We Are Today? 1 Smart Grid Where We Are Today? Meliha B. Selak, P. Eng. IEEE PES DLP Lecturer melihas@ieee.org 2014 IEEE ISGT Asia, Kuala Lumpur 22 nd May 2014 2 Generation Transmission Distribution Load Power System

More information

PRC Disturbance Monitoring and Reporting Requirements

PRC Disturbance Monitoring and Reporting Requirements Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Transmission System Phase Backup Protection

Transmission System Phase Backup Protection Reliability Guideline Transmission System Phase Backup Protection NERC System Protection and Control Subcommittee Draft for Planning Committee Approval June 2011 Table of Contents 1. Introduction and Need

More information

Industry Webinar. Reactive Power Planning. NERC System Analysis and Modeling Subcommittee (SAMS) March 2017

Industry Webinar. Reactive Power Planning. NERC System Analysis and Modeling Subcommittee (SAMS) March 2017 Industry Webinar Reactive Power Planning NERC System Analysis and Modeling Subcommittee (SAMS) March 2017 Webinar Topics Reliability Guideline on Reactive Power Planning Webinar Topics Fundamentals of

More information

Power System Stability. Course Notes PART-1

Power System Stability. Course Notes PART-1 PHILADELPHIA UNIVERSITY ELECTRICAL ENGINEERING DEPARTMENT Power System Stability Course Notes PART-1 Dr. A.Professor Mohammed Tawfeeq Al-Zuhairi September 2012 1 Power System Stability Introduction Dr.Mohammed

More information

ReliabilityFirst Regional Criteria 1. Disturbance Monitoring and Reporting Criteria

ReliabilityFirst Regional Criteria 1. Disturbance Monitoring and Reporting Criteria ReliabilityFirst Regional Criteria 1 Disturbance Monitoring and Reporting Criteria 1 A ReliabilityFirst Board of Directors approved good utility practice document which are not reliability standards. ReliabilityFirst

More information

Project System Operating Limits Drafting Team Meeting Notes

Project System Operating Limits Drafting Team Meeting Notes Notes Tuesday, February 23, 2016 8:30 AM 5:00 PM Wednesday, February 24, 2016 8:30 AM 5:00 PM Thursday, February 25, 2016 8:30 AM 12:00 PM WECC office 155 North 400 West Salt Lake City, Utah 84103 ReadyTalk

More information

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1 NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1 Charles J. Mozina, Consultant Beckwith Electric Co., Inc. www.beckwithelectric.com I. Introduction During the 2003 blackout,

More information

Setting and Verification of Generation Protection to Meet NERC Reliability Standards

Setting and Verification of Generation Protection to Meet NERC Reliability Standards 1 Setting and Verification of Generation Protection to Meet NERC Reliability Standards Xiangmin Gao, Tom Ernst Douglas Rust, GE Energy Connections Dandsco LLC. Abstract NERC has recently published several

More information

Central Hudson Gas & Electric Corporation. Transmission Planning Guidelines

Central Hudson Gas & Electric Corporation. Transmission Planning Guidelines Central Hudson Gas & Electric Corporation Transmission Planning Guidelines Version 4.0 March 16, 2016 Version 3.0 March 16, 2009 Version 2.0 August 01, 1988 Version 1.0 June 26, 1967 Table of Contents

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

Unit Auxiliary Transformer (UAT) Relay Loadability Report

Unit Auxiliary Transformer (UAT) Relay Loadability Report Background and Objective Reliability Standard, PRC 025 1 Generator Relay Loadability (standard), developed under NERC Project 2010 13.2 Phase 2 of Relay Loadability: Generation, was adopted by the NERC

More information

Study on the Improvement of the Special Protection Scheme (SPS) in the Korean power system

Study on the Improvement of the Special Protection Scheme (SPS) in the Korean power system Study on the Improvement of the Special Protection Scheme (SPS) in the Korean power system Jeonghoon Shin, Suchul Nam, Seungtae Cha, Jaegul Lee, Taekyun Kim, Junyoen Kim, Taeok Kim, Hwachang Song Abstract--This

More information

Recently, the SS38 Working Group on Inter-Area Dynamic Analysis completed two study reports on behalf of the UFLS Regional Standard Drafting Team.

Recently, the SS38 Working Group on Inter-Area Dynamic Analysis completed two study reports on behalf of the UFLS Regional Standard Drafting Team. December 7 th, 2010 NPCC Full Member Committee; Please find attached a draft revised NPCC Regional Reliability Directory #12 Underfrequency Load Shedding Program Requirements and a draft revised NPCC UFLS

More information

Power Plant and Transmission System Protection Coordination

Power Plant and Transmission System Protection Coordination Technical Reference Document Power Plant and Transmission System Protection Coordination NERC System Protection and Control Subcommittee Revision 1 July 2010 Table of Contents 1. Introduction... 1 1.1.

More information

Testing and Implementation of a Source Locating method at ISO New England

Testing and Implementation of a Source Locating method at ISO New England 1 Testing and Implementation of a Source Locating method at ISO New England Slava Maslennikov Principal Analyst Business Architecture and Technology Department ISO New England smaslennikov@iso-ne.com 2

More information

Measurement tools at heart of Smart Grid need calibration to ensure reliability

Measurement tools at heart of Smart Grid need calibration to ensure reliability Measurement tools at heart of Smart Grid need calibration to ensure reliability Smart grid; PMU calibration position 1 The North American interconnections, or electric transmission grids, operate as a

More information

Remedial Action Scheme Definition Development

Remedial Action Scheme Definition Development Remedial Action Scheme Definition Development Background and Frequently Asked Questions Project 2010-05.2 Special Protection Systems June 2014 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA

More information

System Protection Schemes in Power Network based on New Principles

System Protection Schemes in Power Network based on New Principles System Protection Schemes in Power Network based on New Principles Daniel Karlsson, ABB Automation Products AB S-721 59 Västerås, SWDN daniel.h.karlsson@se.abb.com Abstract This report describes how a

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

Test Cases Library and Real-life Oscillation Examples

Test Cases Library and Real-life Oscillation Examples Test Cases Library and Real-life Oscillation Examples Kai Sun 1, Bin Wang 2, Slava Maslennikov 3 1- University of Tennessee, 2- Texas A&M University, 3- ISO New England Paper No. 18PESGM0563 2018 IEEE

More information

Wind Power Facility Technical Requirements CHANGE HISTORY

Wind Power Facility Technical Requirements CHANGE HISTORY CHANGE HISTORY DATE VERSION DETAIL CHANGED BY November 15, 2004 Page 2 of 24 TABLE OF CONTENTS LIST OF TABLES...5 LIST OF FIGURES...5 1.0 INTRODUCTION...6 1.1 Purpose of the Wind Power Facility Technical

More information

1

1 Guidelines and Technical Basis Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive

More information

Implementation of Revised IEEE Standard 1547

Implementation of Revised IEEE Standard 1547 MAY 31, 2017 HOLYOKE, MASSACHUSETTS Implementation of Revised IEEE Standard 1547 Presentation to ISO-TO Operations Committee David Forrest Key Points As New England adds significant amounts of Distributed

More information

Remedial Action Scheme Definition Development Background and Frequently Asked Questions

Remedial Action Scheme Definition Development Background and Frequently Asked Questions Remedial Action Scheme Definition Development Background and Frequently Asked Questions Project 2010-05.2 Special Protection Systems October 2014 1 3353 Peachtree Road NE Suite 600, North Tower Atlanta,

More information

Reliability Guideline Methods for Establishing IROLs

Reliability Guideline Methods for Establishing IROLs Reliability Guideline Methods for Establishing IROLs September 2018 NERC Report Title Report Date I Table of Contents Preface... iv Preamble... v Executive Summary... vi Introduction... vii Use of Terminology

More information

SYNCHROPHASOR TECHNOLOGY GLOSSARY Revision Date: April 24, 2011

SYNCHROPHASOR TECHNOLOGY GLOSSARY Revision Date: April 24, 2011 SYNCHROPHASOR TECHNOLOGY GLOSSARY Revision Date: April 24, 2011 Baselining using large quantities of historical phasor data to identify and understand patterns in interconnection-wide grid behavior, to

More information

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event Texas Reliability Entity Event Analysis Event: May 8, 2011 Loss of Multiple Elements Category 1a Event Texas Reliability Entity July 2011 Page 1 of 10 Table of Contents Executive Summary... 3 I. Event

More information

Generation and Load Interconnection Standard

Generation and Load Interconnection Standard Generation and Load Interconnection Standard Rev. 0 DRAFT Name Signature Date Prepared: Approved: VP Acceptance APEGGA Permit to Practice P-08200 TABLE OF CONTENTS 1.0 INTRODUCTION...5 1.1 Purpose...5

More information

BED INTERCONNECTION TECHNICAL REQUIREMENTS

BED INTERCONNECTION TECHNICAL REQUIREMENTS BED INTERCONNECTION TECHNICAL REQUIREMENTS By Enis Šehović, P.E. 2/11/2016 Revised 5/19/2016 A. TABLE OF CONTENTS B. Interconnection Processes... 2 1. Vermont Public Service Board (PSB) Rule 5.500... 2

More information

Overview. The Principles of Power System Operation module presents the following topics:

Overview. The Principles of Power System Operation module presents the following topics: Course Outline 1. Introduction to WECC 2. Fundamentals of Electricity 3. Power System Overview 4. Principles of Generation 5. Substation Overview 6. Transformers 7. Power Transmission 8. System Protection

More information

VOLTAGE STABILITY OF THE NORDIC TEST SYSTEM

VOLTAGE STABILITY OF THE NORDIC TEST SYSTEM 1 VOLTAGE STABILITY OF THE NORDIC TEST SYSTEM Thierry Van Cutsem Department of Electrical and Computer Engineering University of Liège, Belgium Modified version of a presentation at the IEEE PES General

More information

Advantages and Disadvantages of EHV Automatic Reclosing

Advantages and Disadvantages of EHV Automatic Reclosing Technical Reference Document Advantages and Disadvantages of EHV Automatic Reclosing NERC System Protection and Control Subcommittee December 2009 Table of Contents 1. Introduction...1 2. Significant Autoreclosing

More information

Voltage and Reactive Procedures CMP-VAR-01

Voltage and Reactive Procedures CMP-VAR-01 Voltage and Reactive Procedures CMP-VAR-01 NERC Standards: VAR-001-2 VAR-002-1.1b Effective Date: 07/31/2012 Document Information Current Revision 2.0 Review Cycle Annual Subject to External Audit? Yes

More information

Synchrophasor Technology PMU Use Case Examples

Synchrophasor Technology PMU Use Case Examples 1 IEEE Tutorial on Use of Synchrophasors in Grid Operations - Oscillation Source Detection and Operational Use of Synchrophasors Synchrophasor Technology PMU Use Case Examples Sarma (NDR) Nuthalapati,

More information

Power System Protection Where Are We Today?

Power System Protection Where Are We Today? 1 Power System Protection Where Are We Today? Meliha B. Selak Power System Protection & Control IEEE PES Distinguished Lecturer Program Preceding IEEE PES Vice President for Chapters melihas@ieee.org PES

More information

Decision Tree Based Online Voltage Security Assessment Using PMU Measurements

Decision Tree Based Online Voltage Security Assessment Using PMU Measurements Decision Tree Based Online Voltage Security Assessment Using PMU Measurements Vijay Vittal Ira A. Fulton Chair Professor Arizona State University Seminar, January 27, 29 Project Team Ph.D. Student Ruisheng

More information

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction A. Introduction 1. Title: Generator Frequency and Voltage Protective Relay Settings 2. Number: PRC-024-1 3. Purpose: Ensure Generator Owners set their generator protective relays such that generating units

More information

Update on the Creation of a Public Library of PMU Cases for Oscillatory Events

Update on the Creation of a Public Library of PMU Cases for Oscillatory Events 1 JSIS Meeting, May 17, 2018 Update on the Creation of a Public Library of PMU Cases for Oscillatory Events IEEE PES/PSDP/PSSC Task Force on Oscillation Source Location Slava Maslennikov ISO New England

More information

INCIDENTS CLASSIFICATION SCALE METHODOLOGY

INCIDENTS CLASSIFICATION SCALE METHODOLOGY 8 May 2014 WORKING GROUP INCIDENT CLASSIFICATION UNDER SYSTEM OPERATIONS COMMITTEE Contents Revisions... 5 References and Related documents... 5 Change request... 5 1. Overview... 6 1.1 Objectives and

More information

A Review of Adaptive Under Frequency Load Shedding Scheme on Islanded Distribution System Using MATLAB/SIMULINK

A Review of Adaptive Under Frequency Load Shedding Scheme on Islanded Distribution System Using MATLAB/SIMULINK A Review of Adaptive Under Frequency Load Shedding Scheme on Islanded Distribution System Using MATLAB/SIMULINK Dhananjay 1, Vijay Garg 2 1 M.Tech Scholar, Electrical Engineering, U.I.E.T, Kurukshetra,

More information

Geomagnetic Disturbances. IEEE PES Chicago Chapter Technical Presentation March 12, Alan Engelmann Transmission Planning ComEd.

Geomagnetic Disturbances. IEEE PES Chicago Chapter Technical Presentation March 12, Alan Engelmann Transmission Planning ComEd. Geomagnetic Disturbances IEEE PES Chicago Chapter Technical Presentation March 12, 2014 Alan Engelmann Transmission Planning ComEd GMD Background Solar Disturbances Impacts Monitoring Events 2 Solar Disturbances

More information

Power Plant and Transmission System Protection Coordination

Power Plant and Transmission System Protection Coordination Agenda Item 5.h Attachment 1 A Technical Reference Document Power Plant and Transmission System Protection Coordination Draft 6.9 November 19, 2009 NERC System Protection and Control Subcommittee November

More information

International Journal of Advance Engineering and Research Development

International Journal of Advance Engineering and Research Development Scientific Journal of Impact Factor (SJIF): 3.134 International Journal of Advance Engineering and Research Development Volume 2,Issue 12,December -2015 E-ISSN (O): 2348-4470 P-ISSN (P): 2348-6406 Detection

More information

CAISO Restricted - Do Not Distribute Outside of RC Project LOI and NDA Entities Page 1 of 24

CAISO Restricted - Do Not Distribute Outside of RC Project LOI and NDA Entities Page 1 of 24 RC0120A - RC IRO-010 Data Specification NOTE: Changes from Peak's Attachment A are highlighted in red in columns C through G Section Category Number Responsible Pa Data Item Data Transfer Method 1.1 Transmission

More information

SynchroPhasor Roadmap

SynchroPhasor Roadmap SynchroPhasor Roadmap (Voltage Stability) JSIS Meeting January 16 th, 2013 Manu Parashar Our Vision Traditional MODEL-BASED Analysis (EMS) PMU MEASUREMENT-BASED Analysis (PhasorPoint) SCADA & Alarms WAMS

More information

Using Synchrophasors for Frequency Response Analysis in the Western Interconnection. Bonneville Power Administration -- WECC JSIS Chair

Using Synchrophasors for Frequency Response Analysis in the Western Interconnection. Bonneville Power Administration -- WECC JSIS Chair 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2014 Grid of the Future Symposium Using Synchrophasors for Frequency Response Analysis in the Western Interconnection

More information

Keeping it up to Speed Off-Nominal Frequency Operations. CETAC 2018 San Ramon

Keeping it up to Speed Off-Nominal Frequency Operations. CETAC 2018 San Ramon Keeping it up to Speed Off-Nominal Frequency Operations CETAC 2018 San Ramon 1 Welcome CETAC 2018 San Ramon Valley Conference Center General Class Information: Safety/Fire evacuation In event of emergency,

More information

Inverter-Based Resource Disturbance Analysis

Inverter-Based Resource Disturbance Analysis Inverter-Based Resource Disturbance Analysis Key Findings and Recommendations Informational Webinar February 15, 2018 August 16, 2016 Blue Cut Fire Disturbance Key Findings and Recommendations 2 Western

More information

Wide Area Monitoring with Phasor Measurement Data

Wide Area Monitoring with Phasor Measurement Data Wide Area Monitoring with Phasor Measurement Data Dr. Markus Wache Siemens E D EA, Nuremberg, Germany Content Content Basics of Phasor Measurement Realization of PMUs Power System Stability Standard IEEE

More information

Stability Issues of Smart Grid Transmission Line Switching

Stability Issues of Smart Grid Transmission Line Switching Preprints of the 19th World Congress The International Federation of Automatic Control Stability Issues of Smart Grid Transmission Line Switching Garng. M. Huang * W. Wang* Jun An** *Texas A&M University,

More information

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF GENERATION FACILITIES NOT SUBJECT TO FERC JURISDICTION

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF GENERATION FACILITIES NOT SUBJECT TO FERC JURISDICTION TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF GENERATION FACILITIES NOT SUBJECT TO FERC JURISDICTION Document 9022 Puget Sound Energy, Inc. PSE-TC-160.70 December

More information

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC A. Introduction 1. Title: Generator Frequency and Voltage Protective Relay Settings 2. Number: PRC-024-2 3. Purpose: Ensure Generator Owners set their generator protective relays such that generating units

More information

VAR Voltage and Reactive Control

VAR Voltage and Reactive Control VAR-001-4 Voltage and Reactive Control A. Introduction 1. Title: Voltage and Reactive Control 2. Number: VAR-001-4 3. Purpose: To ensure that voltage levels, reactive flows, and reactive resources are

More information

A. Introduction. VAR Voltage and Reactive Control

A. Introduction. VAR Voltage and Reactive Control A. Introduction 1. Title: Voltage and Reactive Control 2. Number: VAR-001-4.2 3. Purpose: To ensure that voltage levels, reactive flows, and reactive resources are monitored, controlled, and maintained

More information

EASING NERC TESTING WITH NEW DIGITAL EXCITATION SYSTEMS

EASING NERC TESTING WITH NEW DIGITAL EXCITATION SYSTEMS EASING NERC TESTING WITH NEW DIGITAL EXCITATION SYSTEMS David S. Kral, Xcel Energy, and Richard C. Schaefer, Basler Electric Abstract - This paper discusses a portion of the NERC Policy involving Generator

More information

Implementation of Automatic Under Voltage Load Shedding Program in Entergy System

Implementation of Automatic Under Voltage Load Shedding Program in Entergy System Implementation of Automatic Under Voltage Load Shedding Program in Entergy System Sharma Kolluri, IEEE Fellow Manager, Transmission Planning Entergy Services, Inc. Presentation at i-pcgrid Workshop San

More information

Implementation Plan Project Balancing Authority Reliability-based Controls - Reserves

Implementation Plan Project Balancing Authority Reliability-based Controls - Reserves Implementation Plan Project 2010-14.1 Balancing Authority Reliability-based Controls - Reserves Implementation Plan for Approvals Required Prerequisite Approvals None Revisions to Glossary Terms The following

More information

NERC Protection Coordination Webinar Series June 30, Dr. Murty V.V.S. Yalla

NERC Protection Coordination Webinar Series June 30, Dr. Murty V.V.S. Yalla Power Plant and Transmission System Protection ti Coordination Loss-of-Field (40) and Out-of of-step Protection (78) NERC Protection Coordination Webinar Series June 30, 2010 Dr. Murty V.V.S. Yalla Disclaimer

More information

Power Plant and Transmission System Protection Coordination Fundamentals

Power Plant and Transmission System Protection Coordination Fundamentals Power Plant and Transmission System Protection Coordination Fundamentals NERC Protection Coordination Webinar Series June 2, 2010 Jon Gardell Agenda 2 Objective Introduction to Protection Generator and

More information

AMEREN s (On Behalf of Its Transmission Owning Affiliates, Including Ameren Missouri, Ameren Illinois, and Ameren Transmission Company of Illinois)

AMEREN s (On Behalf of Its Transmission Owning Affiliates, Including Ameren Missouri, Ameren Illinois, and Ameren Transmission Company of Illinois) AMEREN s (On Behalf of Its Transmission Owning Affiliates, Including Missouri, Illinois, and Transmission Company of Illinois) TRANSMISSION PLANNING CRITERIA AND GUIDELINES March 28, 2003 Revised April

More information

Procedure for ERO Support of Frequency Response and Frequency Bias Setting Standard. Event Selection Process

Procedure for ERO Support of Frequency Response and Frequency Bias Setting Standard. Event Selection Process This procedure outlines the Electric Reliability Organization (ERO) process for supporting the Frequency Response Standard (FRS). A Procedure revision request may be submitted to the ERO for consideration.

More information

Accurate Synchrophasor Estimation to Support the Islanding Maneuver of Active Distribution Networks

Accurate Synchrophasor Estimation to Support the Islanding Maneuver of Active Distribution Networks Working Group Meeting June 5-6, 2012 Accurate Synchrophasor Estimation to Support the Islanding Maneuver of Active Distribution Networks Prof. Mario Paolone EPFL, Switzerland - Distributed Electrical Systems

More information

System Protection and Control Subcommittee

System Protection and Control Subcommittee Power Plant and Transmission System Protection Coordination Volts Per Hertz (24), Undervoltage (27), Overvoltage (59), and Under/Overfrequency (81) Protection System Protection and Control Subcommittee

More information

EE 742 Chapter 9: Frequency Stability and Control. Fall 2011

EE 742 Chapter 9: Frequency Stability and Control. Fall 2011 EE 742 Chapter 9: Frequency Stability and Control Fall 2011 Meeting demand with generation Large and slow changes (24 hr) in power demand are met by unit commitment Medium and relatively fast changes (30

More information

Experiences of Using Synchrophasors at Duke Energy

Experiences of Using Synchrophasors at Duke Energy 1 Experiences of Using Synchrophasors at Duke Energy Tim Bradberry, Megan Vutsinas, Kat Sico Duke Energy IEEE PES Tutorial July 19 th, 2016 Duke Energy s Phasor Plans Carolinas West Currently have 125

More information

PRC Compliance Using Bitronics 70 Series Recorders

PRC Compliance Using Bitronics 70 Series Recorders PRC-002-2 Compliance Using Bitronics 70 Series Recorders Introduction The North American Electric Reliability Council (NERC) has defined standards for disturbance monitoring and reporting requirements

More information

NVESTIGATIONS OF RECENT BLACK-

NVESTIGATIONS OF RECENT BLACK- DIGITAL VISION outs indicate that the root cause of almost all major power system disturbances is voltage collapse rather than the underfrequency conditions prevalent in the blackouts of the 1960s and

More information

Introduce system protection relays like underfrequency relays, rate of change of frequency relays, reverse - power flow

Introduce system protection relays like underfrequency relays, rate of change of frequency relays, reverse - power flow Module 1 : Fundamentals of Power System Protection Lecture 3 : Protection Paradigms - System Protection Objectives In this lecture we will: Overview dynamics in power systems. Introduce system protection

More information

Generation and Load Interconnection Standard

Generation and Load Interconnection Standard Generation and Load Interconnection Standard Rev. 0A DRAFT Name Signature Date Prepared: Approved: VP Acceptance APEGGA Permit to Practice P-08200 TABLE OF CONTENTS 1.0 INTRODUCTION...5 1.1 Purpose...5

More information

Dynamic security assessment processing system

Dynamic security assessment processing system Graduate Theses and Dissertations Graduate College 2014 Dynamic security assessment processing system Lei Tang Iowa State University Follow this and additional works at: http://lib.dr.iastate.edu/etd Part

More information

GRID RELIABILITY MONITORING

GRID RELIABILITY MONITORING GRID RELIABILITY MONITORING Using Smart Grids WASS TM - A SynchroPhasor Technology based Real Time Wide Area Situational Awareness Software for Monitoring, Detection and Diagnosis of Power System Issues

More information

1200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report

1200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report 1200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report Rich Bauer Associate Director Reliability Risk Management / Event Analysis Mid C Seminar July 19, 2017 Western Interconnection

More information