LHC Electronics irradiation tests in the CNGS side gallery September 2009

Size: px
Start display at page:

Download "LHC Electronics irradiation tests in the CNGS side gallery September 2009"

Transcription

1 LHC Electronics irradiation tests in the CNGS side gallery September 2009 D.Kramer for the RADWG Thanks to B.Todd, E.Gousiou, E.Calvo, E.Effinger, R.Denz, K.Roeed, J.Lendaro, M.Brugger, EN/MEF, DG/SCR, Fluka team and the RadMon team (T.Wijnands, A.Nyul, C.Pignard) 30/9/09 report to LMC 1

2 Outline Test facility overview Planning of slots Calibration of test positions Comparison with Fluka User results CRYO BIC/PIC BLM BPM QPS HTS CL heaters not enough data WorldFip not enough data TE/EPC no data yet SURVEY no data yet 30/9/09 report to LMC 2

3 Testing area in the TSG4 side gallery of CNGS Radiation fields similar to the ones expected in LHC Area available after the displacement of the CNGS electronics to the ventilation chamber 30/9/09 report to LMC 3

4 HTS CL heaters QPS 2 Test areas High & Low flux and dose rate with multiple calibrated locations Target chamber Hottest test area in TSG46: ~ 1.5 Gy(SiO 2 )/week ~ (1MeV n eq.)cm -2 /week RadMon Survey New FLUKA simulations are now available thanks to K.Roeed BIC/PIC Target chamber WorldFip Hottest test area in TSG45 : ~ 12Gy(SiO 2 )/week ~ (1MeV n eq.)cm -2 /week This is expected in the LHC arcs* or UJ56/14/16 in 1 nominal year (10Gy/y, 3e11cm -2 ) BLM CRYO TE/EPC 30/9/09 *Alongside a dipole report to LMC 4

5 Calibrated radiation field data for all test locations accessible via dedicated Java GUI Hottest test area TSG46: ~ 1.5 Gy(SiO 2 )/week ~ (1MeV n eq.)cm -2 /week Hottest test area TSG45 : ~ 12Gy(SiO 2 )/week ~ (1MeV n eq.)cm -2 /week 30/9/09 report to LMC 5

6 Like it is the case for FLUKA, Safety Factor of 2 should be used for all the CNGS measurements (high gradients, small detector size) Calibrated radiation field data for all test locations accessible via dedicated Java GUI Hottest test area TSG46: ~ 1.5 Gy(SiO 2 )/week ~ (1MeV n eq.)cm -2 /week By assuming all the devices to be installed in the worst locations, the estimations are more conservative than 2 times (for SEE related failures) Example for the BLM location 1month time Hottest test area TSG45 : ~ 12Gy(SiO 2 )/week ~ (1MeV n eq.)cm -2 /week 30/9/09 report to LMC 6

7 Planning for the user tests Additional measurements: Activation of water samples TLD (Li6 & Li7) Au & Bi activation foils BLMI sensitivity to thermal neutrons Temporary procedure for handling irradiated electronics was put in place for CNGS. Valid until 30/11/09. Radioactive electronics WORKSHOP has to be used afterwards. All users requesting beam time in 2009 received a slot Only the vacuum group didn t receive the turbo pumps -> no tests possible Slot # End in week TSG45-1 TSG45-2 TSG46-3 TSG WorldFip BLM/BPM CRYO QPS 2 29 WorldFip BLM/BPM CRYO QPS 3 33 WorldFip BLM/BPM CRYO QPS 4 38 WorldFip + BLM/BPM BIC/PIC + QPS TE/EPC CRYO 5 41 TE/EPC Survey + BIC/PIC QPS BLM 6 47 TE/EPC Survey BIC/PIC QPS 30/9/09 report to LMC 7

8 USER test results CRYO BIC/PIC BLM BPM QPS HTS CL not enough data WorldFip not enough data TE/EPC no data yet SURVEY no data yet The presented radiation levels are for nominal LHC beam Estimations for the 2009/10 operation are added when necessary 30/9/09 report to LMC 8

9 Tunnel equipment in CNGS: Tunnel Electronics CRYO Tunnel electronics (~9500 channels in LHC tunnel) have received till now a cumulated dose of: TID (Gy) ~125 NIEL (n/cm 2 ) ~4e12..and the tests are still ongoing. No Single Event Errors LHC years in 90% of the cases (apart from DS) >10 o Output accuracy still within specs ( <0.3% ) Resistance measurements of 5 conditioners: 51 Resistance (Ω) 48 0 TID (Gy) 120 -Temperature reading (18 Channels) - Helium level reading (12 Channels) - Digital inputs (24 Channels) - Cold mass electrical heater DC supply (4 Channels) - FIP communication (8 agents) - Power supply (2 cards) 30/9/09 report to LMC 9

10 Protected Areas Electronics Cumulative Effects Failures CRYO Safety factor 2x to be applied o QRL electrical Heater AC supply o Insulated Temperature reading (~45 channels in protected areas): (~2400 channels in protected areas): TID (Gy) 5 NIEL (n/ cm 2 ) LHC years in the worst case (UJ14, UJ16, UJ56) 7e LHC years assuming 09/10 conditions in the worst case (UJ14, UJ16, UJ56) 500 TID (Gy) 70 NIEL (n/ cm 2 ) LHC years in the worst case (UJ14, UJ16, UJ56) 2e12 7 LHC years assuming 09/10 conditions in the worst case (UJ14, UJ16, UJ56) 7000 Failing component: solid state relay. Planning of moving electronics or shielding of protected areas. Failing component: DC-DC converter. Planning of scheduled replacements. o Same results for several channels and reproduced in two different CNGS locations. 30/9/09 report to LMC 10

11 Protected Areas Electronics Single Event Upsets CRYO o Insulated Temperature Conditioners (~2400 channels in protected areas): Cross Section (cm 2 ) 2e-9 LHC SEU/ hr for the total channels if all in UJ56 Failing component: ISO 150 Digital Isolator. 6 Foreseen SEU rate in 2009/10 For the total channels if ALL in UJ56 2/month Mitigation technique for LHC (in progress): soft reset automatically forced by the control system; No influence on proper operation of the machine. o Same results for 12 channels and reproduced in two different CNGS locations. 30/9/09 report to LMC 11

12 USER test results CRYO BIC/PIC BLM BPM QPS HTS CL 30/9/09 report to LMC

13 CPLDs Used in the Interlock Systems (5V) 500nm (3.3V) 350nm Beam Interlock System XC95288 x 300 XC95288XL x 34 UA, UJ, RR UA, SR, TZ (5V) 500nm Power Interlock Controllers XC95144 x 36 UA, UJ, RR 95288/144 (5V) failure = maintenance required = not machine critical 95288XL (3.3V) failure = can compromise safety* N.B. Whole BIS is redundant = *needs two identical failures during a mission 95288XL is used in the control VME chassis TE/MPE/MI has installed a Radiation Test Bench in CNGS XC95144 x 32 Almost = # in LHC XC95288XL x 32 30/9/09 report to LMC 13

14 XILINX CPLD test setup in CNGS for BIS and PIC Dedicated test setup produced only for the radiation tests One test card (5V) failed after 77Gy Setup remains in CNGS to verify total dose resistance of the CPLDs No destructive Latchup observed so far (to be confirmed) 30/9/09 report to LMC 14

15 XC9500XL (3.3V) [ UAs, SR, TZ76 etc ] Failure (SEE induced) cross-section per device = 2.8e-10 cm 2 In UA87 one expects high energy hadron fluence less than (conservative!) 1e8 cm -2 /y The resulting failure rate for 1 device = SEEs/y If all the 36 CPLDs were in UA87 (not considering the shielding installed last week), we would get 0.9 failures/y, out of which 20% produce loss of redundancy (5.5y MTBF) 80% lead to a false dump (1.4y MTBF) We have to keep in mind that this is a low voltage device and might be sensitive to thermal neutrons. In areas like UAs their fluence could be up to 10xhigher than hadrons>20mev (Fluka analysis to be performed). If this is true, the 0.9 failures/y is a conservative but not exaggerated estimation. Tests in thermal neutron beam are being considered 30/9/09 report to LMC 15

16 XC9500 (5V) The device has a very low error cross-section! Failure (SEE) cross-section = 3.8e-13 cm2 We can assume conservatively 1e9cm -2 /y for the high energy hadron fluence in the RRs. We get then 3.8e-4 SEEs/y/device which makes 0.14 SEEs/y for the 366 devices, i.e. 7.2y MTBF In 10% of cases the SEE produces a False dump In 90% of cases the SEE produces a Monitoring problem These figures are of the same order of magnitude as the Electrical Reliability of the devices (according to Xilinx) In both cases above we don t care about the total dose, one should not reach 1Gy/y for the concerned locations (except the locations below) Relocation from UJ56/UJ14/16 is in preparation (cables placed, new location identified) 30/9/09 report to LMC 16

17 USER test results CRYO BIC/PIC BLM BPM QPS HTS CL 30/9/09 report to LMC

18 Quick report on the early QPS measurements WorldFip problems Field-bus coupler type DQAMGS (new QPS layer) Errors produced by SEUs in the WorldFip part Using latest MicroFip TM and FIELDRIVE TM (line driver) version Data are still readable but no longer updated -> *Access required prior to next fill Cross section ~ 2.8x10-10 cm 2 Assuming 4x10 10 cm -2 /y (10Gy/y) in the arcs and 450 devices one gets: 14 errors*/day Hardware solution was found and being successfully (so far) tested in CNGS Accelerated SW compatible MicroFip TM and FIELDRIVE TM development would be much appreciated not only by the QPS team for any future developments This year s tests in CGNS confirmed the radiation tolerance of the detection systems of the new QPS layer including the power supplies. Detailed evaluation still to be done. 30/9/09 report to LMC 18

19 USER test results CRYO BIC/PIC BLM BPM QPS HTS CL 30/9/09 report to LMC 19

20 BLM- System: Installation overview Arc Installation In all the arcs from 12L 33L, 12R 34R Expected Radiation levels: worst case Dose = 1-10 Gy/y (1MeV eq. neutrons = 3* *10 11 cm -2 /y) 360 * BLECF Card (Analogue data acquisition cards) 360 * Hand made power supplies Straight Section Installation RR13, RR17, UA23, UA27, UJ33, UA43, UA47, RR53, RR57, UJ63, UJ67, RR73, RR77, UA83, UA87 Expected Radiation levels: worst case Dose = <0.7Gy/y (1MeV eq. neutrons = 1*10 9-1*10 10 cm -2 /y) 309 * BLECF Card (Analogue data acquisition cards) 74 * 5V Power supplies (Haltec-USR515-5A, of-the-shelf) 37 * 2.5V Power supplies (Haltec-USR515S-2A, of-the-shelf) 30/9/09 report to LMC 20

21 BLM- System: test conclusions Power supplies 5V: 19 years of nominal LHC operation possible Power supplies 2.5V: 20 years of nominal LHC operation possible BLECF (Tunnel acquisition card): more than 20 years LHC operation possible 1 SEE induced failure (false dump) observed Cross section = 2.2x10-13 cm 2, this means for 600 cards assuming all in the arcs 70 days MTBF (fail safe)

22 USER test results CRYO BIC/PIC BLM BPM QPS HTS CL 30/9/09 report to LMC 22

23 BPM electronics Tested up to 123 Gy (>10 nominal years) 1 Chassis similar to the installed on LHC. 1 Power supply 545x in LHC 2 WBTNs 1 Intensity card 1 ufip controller card Eva Calvo (BI/QP) 2160x in LHC

24 BPM electronics Tested up to 123 Gy (>10 nominal years) Chassis similar to the one installed in LHC. 1 Power supply OK 545x in LHC 2 WBTNs 1 Intensity card 1 ufip controller card OK failed SEEs Eva Calvo (BI/QP) 2160x in LHC 330x in LHC

25 BPM electronics Tested up to 123 Gy (>10 nominal years) Intensity card failed very soon Aim of the intensity cards is to detect obstacles in the machine during its initial operation (low intensity beam) 3x10 10 cm -2 (1MeV n. eq.) means ~ 0.5 nominal LHC years Most probably not an issue for 2009/10 Measurement corrupted after the event (SEL?, card to be inspected) ufip controller card sensitive to SEEs sending the sensitivity settings of the WBTNs, launch calibrations, or monitoring the power supplies Return to the default state after SEE (calib. off, high sens.) SEE Cross section = 4x10-12 cm 2 thus 2.2days MTBF Worst case: 250um offset for 60s for 1 channel can be compensated by orbit feedback -> not an issue for operation 30/9/09 report to LMC 25

26 Summary (detailed report to be written after the end of tests) CRYO tunnel cards perform very well no concerns Some CRYO non-tunnel cards sensitive to total dose, replacements after 0.5y of nominal beam UJ14/16/56 not critical for operation Some CRYO non-tunnel cards sensitive to SEUs, software mitigation in progress (6 SEUs/h for nominal beam) BIC VME chassis uses sensitive CPLDs but only a small number and not in the most critical areas (5.5y MTBF) very little concern BIC/PIC installations use low cross-section CPLDs which always fail in a safe way (7.2y MTBF) no concerns No cumulative effect problems expected for the BLM system Marginal sensitivity of tunnel card to SEE means 70 days MTBF (fail safe) Very sensitive latest WorldFip chip could compromise the new QPS layer hardware solution looks very promising (450 cards in LHC) If uncorrected, 14 errors/day in nominal conditions (no issue for safety) BPM cards showed no radiation related problems, intensity cards don t stand high intensity (needed for low intensity), ufip card sensitive to SEEs (2.2days MTBF) but handled by the orbit feedback CNGS side gallery proved to be a very useful facility!! 26

27 Reserve slides CNGS Fluka simulations 30/9/09 report to LMC 27

28 Simulated radiation fields of the selected most critical non-tunnel locations LHC Area Beam conditions Hadrons>20MeV [cm -2 /y] 1MeV n. eq. fluence [cm -2 /y] UJ56 09/10 4x x10 7 4x UJ56 nominal 4x x x x UJ14/16 09/10 4x x10 7 4x UJ14/16 nominal 4x x x x Dose [Gy(air)/y] RR13/17 nominal 3x x x x RR77/73 09/ x RR77/73 nominal 1x x10 8 5x x UJ76 09/ x UJ76 nominal x UA87 2x10 15 protons on TED/y* x /9/09 *Assuming 2 shots per week on TED report to LMC 28

29 BLM- System: Status CNGS Result power supplies PS1, PS2, PS3 and BLECF Device Date Hadrons>20MeV [1e11*cm-2] 1MeV eq. neutrons [1e11*cm-2] Dose [Gy] Observation PS 1 (5V) (Haltec- USR515-5A) PS2 (5V) (Haltec- USR515-5A) PS3 (2.5V) (Haltec- USR515S-2A) BLECF_ : Voltage starts to increase : Voltage increased by 20% (1V) : Voltage dropped to 0V : Voltage starts to increase : Voltage increased by 11% (0.55V) : Voltage dropped to 0V : Voltage starts to increase : Voltage increase of 10% (0.25V) : Voltage dropped to 0V : Card stopped : Card reset -> card works again : Card still working RadMon data for the BLM crate positioned in TSG45. Beam intensity data was scaled with the calibration data from 2009.

Summary of the 2009 irradiation tests and perspectives for future tests and facilities

Summary of the 2009 irradiation tests and perspectives for future tests and facilities Summary of the 2009 irradiation tests and perspectives for future tests and facilities D.Kramer, E.Calvo, R.Denz, S.Dubettier, E.Effinger, E.Gousiou, A.Marin, S.Le Naour, J.Palluel, Y.Thurel, B.Todd, M.Zerlauth,

More information

On line radiation monitoring for the LHC machine and experimental caverns

On line radiation monitoring for the LHC machine and experimental caverns On line radiation monitoring for the LHC machine and experimental caverns T.Wijnands, C. Pignard, R. Tesarek CERN, Geneva, Switzerland FNAL, O.O. Box 5, Batavia, Illinois 65, USA Abstract With an unprecedented

More information

Radiation Test Report Paul Scherer Institute Proton Irradiation Facility

Radiation Test Report Paul Scherer Institute Proton Irradiation Facility the Large Hadron Collider project CERN CH-2 Geneva 23 Switzerland CERN Div./Group RadWG EDMS Document No. xxxxx Radiation Test Report Paul Scherer Institute Proton Irradiation Facility Responsibility Tested

More information

RADIATION CONSTRAINTS IN THE DESIGN AND CONCEPTION OF LHC CONTROL SYSTEMS

RADIATION CONSTRAINTS IN THE DESIGN AND CONCEPTION OF LHC CONTROL SYSTEMS RADIATION CONSTRAINTS IN THE DESIGN AND CONCEPTION OF LHC CONTROL SYSTEMS RADiation Working Group (RADWG) T. Wijnands, C. Pignard, A. Presland, R.Rausch, A.Tsoulou. CERN, 1211 Geneva 23, Switzerland Abstract

More information

Test results on 60 MeV proton beam at CYCLONE - UCL Performed on CAEN HV prototype module A June 2001 Introduction

Test results on 60 MeV proton beam at CYCLONE - UCL Performed on CAEN HV prototype module A June 2001 Introduction Test results on 60 MeV proton beam at CYCLONE - UCL Performed on CAEN HV prototype module A877 27-28 June 2001 (M. De Giorgi, M. Verlato INFN Padova, G. Passuello CAEN spa) Introduction The test performed

More information

Betatron cleaning in IR3: results of FLUKA calculations. Fluka team

Betatron cleaning in IR3: results of FLUKA calculations. Fluka team Betatron cleaning in IR3: results of FLUKA calculations Fluka team R2E Meeting, July 17 th 2008 Goal of the study Verify the impact of the optional temporary functional move of the betatron cleaning to

More information

Hardware Commissioning

Hardware Commissioning Hardware Commissioning an update the status of the documentation the report on the resources the programme of the coming year Roberto Saban on behalf of the Hardware Commissioning Working Group status

More information

The LHC beam loss monitoring system s data acquisition card

The LHC beam loss monitoring system s data acquisition card The LHC beam loss monitoring system s data acquisition card B. Dehning a, E.Effinger a, J. Emery a, G. Ferioli a, G. Gauglio b, C. Zamantzas a a CERN, 1211 Geneva 23, Switzerland b MEMC, 28100 Novara,

More information

The CMS Silicon Strip Tracker and its Electronic Readout

The CMS Silicon Strip Tracker and its Electronic Readout The CMS Silicon Strip Tracker and its Electronic Readout Markus Friedl Dissertation May 2001 M. Friedl The CMS Silicon Strip Tracker and its Electronic Readout 2 Introduction LHC Large Hadron Collider:

More information

The SIRAD irradiation facility at the INFN - Legnaro National Laboratory

The SIRAD irradiation facility at the INFN - Legnaro National Laboratory The SIRAD irradiation facility at the INFN - Legnaro National Laboratory I. Introduction 2 The INFN - Legnaro National Laboratory (LNL) SIRAD beamline http://www.lnl.infn.it 3 What is SIRAD? SIRAD is the

More information

STUDY OF THE RADIATION HARDNESS OF VCSEL AND PIN ARRAYS

STUDY OF THE RADIATION HARDNESS OF VCSEL AND PIN ARRAYS STUDY OF THE RADIATION HARDNESS OF VCSEL AND PIN ARRAYS K.K. GAN, W. FERNANDO, H.P. KAGAN, R.D. KASS, A. LAW, A. RAU, D.S. SMITH Department of Physics, The Ohio State University, Columbus, OH 43210, USA

More information

PoS(TIPP2014)382. Test for the mitigation of the Single Event Upset for ASIC in 130 nm technology

PoS(TIPP2014)382. Test for the mitigation of the Single Event Upset for ASIC in 130 nm technology Test for the mitigation of the Single Event Upset for ASIC in 130 nm technology Ilaria BALOSSINO E-mail: balossin@to.infn.it Daniela CALVO E-mail: calvo@to.infn.it E-mail: deremigi@to.infn.it Serena MATTIAZZO

More information

QUALIFICATION of ELECTRONICS for the LHC RADIATION ENVIRONMENT

QUALIFICATION of ELECTRONICS for the LHC RADIATION ENVIRONMENT QUALIFICATION of ELECTRONICS for the LHC RADIATION ENVIRONMENT! - Introduction! - Radiation Test Facility for LHC Tunnel Electronics! - Some Results from 6 Experiments (out of 20)! - Conclusions 1 Why

More information

THE CRYOGENIC SYSTEM OF TESLA

THE CRYOGENIC SYSTEM OF TESLA THE CRYOGENIC SYSTEM OF TESLA S. Wolff, DESY, Notkestr. 85, 22607 Hamburg, Germany for the TESLA collaboration Abstract TESLA, a 33 km long 500 GeV centre-of-mass energy superconducting linear collider

More information

Packaging of Cryogenic Components

Packaging of Cryogenic Components Packaging of Cryogenic Components William J. Schneider Senior Mechanical Engineer Emeritus November 19-23 2007 1 Packaging of Cryogenic Components Day one Introduction and Overview 2 What is important?

More information

Magnet Powering with zero downtime a dream?

Magnet Powering with zero downtime a dream? Magnet Powering with zero downtime a dream? M. Zerlauth LHC Performance Workshop February 2012 Thanks to : HWC team, H.Thiesen, V.Montabonnet, J.P.Burnet, S.Claudet, E.Blanco, R.Denz, R.Schmidt, E.Blanco,

More information

CERN (The European Laboratory for Particle Physics)

CERN (The European Laboratory for Particle Physics) 462 IEEE TRANSACTIONS ON INSTRUMENTATION AND MEASUREMENT, VOL. 48, NO. 2, APRIL 1999 The Measurement Challenge of the LHC Project Gunnar Fernqvist Abstract In 2005, CERN is planning to commission its next

More information

Beam Loss Monitoring (BLM) System for ESS

Beam Loss Monitoring (BLM) System for ESS Beam Loss Monitoring (BLM) System for ESS Lali Tchelidze European Spallation Source ESS AB lali.tchelidze@esss.se March 2, 2011 Outline 1. BLM Types; 2. BLM Positioning and Calibration; 3. BLMs as part

More information

Philippe Lebrun & Laurent Tavian, CERN

Philippe Lebrun & Laurent Tavian, CERN 7-11 July 2014 ICEC25 /ICMC 2014 Conference University of Twente, The Netherlands Philippe Lebrun & Laurent Tavian, CERN Ph. Lebrun & L. Tavian, ICEC25 Page 1 Contents Introduction: the European Strategy

More information

LHC COMMISSIONING AT HIGHER ENERGY

LHC COMMISSIONING AT HIGHER ENERGY LHC COMMISSIONING AT HIGHER ENERGY P. Collier, F. Bordry, J. Wenninger, CERN, Geneva, Switzerland Abstract The LHC has just come to the end of its first Long Shutdown (LS1) and preparations are underway

More information

R. Assmann, CERN/AB. for the Collimation Project 7/12/2007 LHC MAC RWA, LHC MAC 12/07

R. Assmann, CERN/AB. for the Collimation Project 7/12/2007 LHC MAC RWA, LHC MAC 12/07 Plan for Collimator Commissioning R. Assmann, CERN/AB 7/12/2007 for the Collimation Project LHC MAC RWA, LHC MAC 12/07 1) Installation Planning and Performance Reach Collimation is an performance-driven

More information

High SEE Tolerance in a Radiation Hardened CMOS Image Sensor Designed for the Meteosat Third Generation FCI-VisDA Instrument

High SEE Tolerance in a Radiation Hardened CMOS Image Sensor Designed for the Meteosat Third Generation FCI-VisDA Instrument CMOS Image Sensors for High Performance Applications 18 th and 19 th Nov 2015 High SEE Tolerance in a Radiation Hardened CMOS Image Sensor Designed for the Meteosat Third Generation FCI-VisDA Instrument

More information

Interfaces with MPS/PSS

Interfaces with MPS/PSS Interfaces with / European Spallation Source Accelerator Division TB, 16 November 2016, Lund, Sweden / interfaces 1/21 Outline 1 Introduction 2 3 4 Conclusions / interfaces 2/21 Outline 1 Introduction

More information

ELECTRONIC SYSTEMS FOR THE PROTECTION OF SUPERCONDUCTING ELEMENTS IN THE LHC

ELECTRONIC SYSTEMS FOR THE PROTECTION OF SUPERCONDUCTING ELEMENTS IN THE LHC EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics Large Hadron Collider Project LHC Project Report 697 ELECTRONIC SYSTEMS FOR THE PROTECTION OF SUPERCONDUCTING ELEMENTS

More information

Radiation and Reliability Considerations in Digital Systems for Next Generation CubeSats

Radiation and Reliability Considerations in Digital Systems for Next Generation CubeSats Radiation and Reliability Considerations in Digital Systems for Next Generation CubeSats Enabling Technology: P200k-Lite Radiation Tolerant Single Board Computer for CubeSats Clint Hadwin, David Twining,

More information

Study the Compact Photon Source Radiation Using FLUKA

Study the Compact Photon Source Radiation Using FLUKA Study the Compact Photon Source Radiation Using FLUKA Jixie Zhang, Donal Day, Rolf Ent Nov 30, 2017 This is a summary of radiation studies done for both the UVa target alone (for electron and photon beams)

More information

Radiation Test Plan for GLAST LAT TKR ASICs

Radiation Test Plan for GLAST LAT TKR ASICs Page 1 of 20 GLAST LAT PROCUREMENT DOCUMENT Document # Date Effective LAT-PS-01325 1/31/03 Author(s) Supersedes Riccardo Rando Hartmut Sadrozinski Subsystem/Office TKR Document Title Radiation Test Plan

More information

Irradiation Measurements of the Hitachi H8S/2357 MCU.

Irradiation Measurements of the Hitachi H8S/2357 MCU. Irradiation Measurements of the Hitachi H8S/2357 MCU. A. Ferrando 1, C.F. Figueroa 2, J.M. Luque 1, A. Molinero 1, J.J. Navarrete 1, J.C. Oller 1 1 CIEMAT, Avda Complutense 22, 28040 Madrid, Spain 2 IFCA,

More information

High-Speed/Radiation-Hard Optical Links

High-Speed/Radiation-Hard Optical Links High-Speed/Radiation-Hard Optical Links K.K. Gan, H. Kagan, R. Kass, J. Moore, D.S. Smith The Ohio State University P. Buchholz, S. Heidbrink, M. Vogt, M. Ziolkowski Universität Siegen September 8, 2016

More information

AIDA-2020 Advanced European Infrastructures for Detectors at Accelerators. Milestone Report

AIDA-2020 Advanced European Infrastructures for Detectors at Accelerators. Milestone Report AIDA-2020-MS15 AIDA-2020 Advanced European Infrastructures for Detectors at Accelerators Milestone Report Design specifications of test stations for irradiated silicon sensors and LHC oriented front-end

More information

Proposal of test setup

Proposal of test setup Proposal of test setup Status of the study The Compact Linear collider (CLIC) study is a site independent feasibility study aiming at the development of a realistic technology at an affordable cost for

More information

Radiation-hard/high-speed data transmission using optical links

Radiation-hard/high-speed data transmission using optical links Radiation-hard/high-speed data transmission using optical links K.K. Gan a, B. Abi c, W. Fernando a, H.P. Kagan a, R.D. Kass a, M.R.M. Lebbai b, J.R. Moore a, F. Rizatdinova c, P.L. Skubic b, D.S. Smith

More information

Roman Pots. Marco Oriunno SLAC, PPA. M.Oriunno, SLAC

Roman Pots. Marco Oriunno SLAC, PPA. M.Oriunno, SLAC Roman Pots Marco Oriunno SLAC, PPA The Roman Pot technique 1. The Roman Pot, an historically successful technique for near beam physics: ISR, SPS, TEVATRON, RICH, DESY 2. A CERN in-house technology: ISR,

More information

RF System LSD Work. William Merz

RF System LSD Work. William Merz RF System LSD Work William Merz LSD Re-Baseline Review Jefferson Lab Thomas Jefferson National Accelerator Facility Page 1 Outline What I will talk about 12 GEV RF power system installation and commissioning

More information

200 MHz 350 MHz 750 MHz Linac2 RFQ2 202 MHz 0.5 MeV /m Weight : 1000 kg/m Ext. diameter : 45 cm

200 MHz 350 MHz 750 MHz Linac2 RFQ2 202 MHz 0.5 MeV /m Weight : 1000 kg/m Ext. diameter : 45 cm M. Vretenar, CERN for the HF-RFQ Working Group (V.A. Dimov, M. Garlasché, A. Grudiev, B. Koubek, A.M. Lombardi, S. Mathot, D. Mazur, E. Montesinos, M. Timmins, M. Vretenar) 1 1988-92 Linac2 RFQ2 202 MHz

More information

Southern Methodist University Dallas, TX, Southern Methodist University Dallas, TX, 75275

Southern Methodist University Dallas, TX, Southern Methodist University Dallas, TX, 75275 Single Event Effects in a 0.25 µm Silicon-On-Sapphire CMOS Technology Wickham Chen 1, Tiankuan Liu 2, Ping Gui 1, Annie C. Xiang 2, Cheng-AnYang 2, Junheng Zhang 1, Peiqing Zhu 1, Jingbo Ye 2, and Ryszard

More information

STPA FOR LINAC4 AVAILABILITY REQUIREMENTS. A. Apollonio, R. Schmidt 4 th European STAMP Workshop, Zurich, 2016

STPA FOR LINAC4 AVAILABILITY REQUIREMENTS. A. Apollonio, R. Schmidt 4 th European STAMP Workshop, Zurich, 2016 STPA FOR LINAC4 AVAILABILITY REQUIREMENTS A. Apollonio, R. Schmidt 4 th European STAMP Workshop, Zurich, 2016 LHC colliding particle beams at very high energy 26.8 km Circumference LHC Accelerator (100

More information

Diamond sensors as beam conditions monitors in CMS and LHC

Diamond sensors as beam conditions monitors in CMS and LHC Diamond sensors as beam conditions monitors in CMS and LHC Maria Hempel DESY Zeuthen & BTU Cottbus on behalf of the BRM-CMS and CMS-DESY groups GSI Darmstadt, 11th - 13th December 2011 Outline 1. Description

More information

SEU effects in registers and in a Dual-Ported Static RAM designed in a 0.25 µm CMOS technology for applications in the LHC

SEU effects in registers and in a Dual-Ported Static RAM designed in a 0.25 µm CMOS technology for applications in the LHC SEU effects in registers and in a Dual-Ported Static RAM designed in a 0.25 µm CMOS technology for applications in the LHC F.Faccio 1, K.Kloukinas 1, G.Magazzù 2, A.Marchioro 1 1 CERN, 1211 Geneva 23,

More information

The SMUX chip Production Readiness Review

The SMUX chip Production Readiness Review CERN, January 29 th, 2003 The SMUX chip Production Readiness Review D. Dzahini a, L. Gallin-Martel a, M-L Gallin-Martel a, O. Rossetto a, Ch. Vescovi a a Institut des Sciences Nucléaires, 53 Avenue des

More information

Rad hard test of Caen HV prototype A877 for MDT and TGC performed on the CYCLONE proton beam

Rad hard test of Caen HV prototype A877 for MDT and TGC performed on the CYCLONE proton beam Muon Note June 9, 2003 Rad hard test of Caen HV prototype A877 for MDT and TGC performed on the CYCLONE proton beam G. Iuvino, A. Lanza, P. Novelli*, W. Vandelli & Istituto Nazionale di Fisica Nucleare,

More information

BCS UPDATE. j. welch 2/9/17

BCS UPDATE. j. welch 2/9/17 BCS UPDATE j. welch 2/9/17 TOPICS RP requirements Shutoff path Beam loss detection scheme Beam loss detectors and FPGAs Current monitors Dumps RP REQUIREMENTS Revised BCS PRD was circulated Tuesday for

More information

A Low Power Optical Communication Instrument for Deep-Space CubeSats. Paul Serra, CubeSat Developers Workshop, 2015 v1.5

A Low Power Optical Communication Instrument for Deep-Space CubeSats. Paul Serra, CubeSat Developers Workshop, 2015 v1.5 A Low Power Optical Communication Instrument for Deep-Space CubeSats Paul Serra, Nathan Barnwell, John W. Conklin Paul Serra, CubeSat Developers Workshop, 2015 v1.5 Motivation and Objectives Objectives:

More information

Quality assurance for CMS Tracker LV and HV Power Supplies

Quality assurance for CMS Tracker LV and HV Power Supplies Quality assurance for CMS Tracker LV and HV Power Supplies M. Costa a,b, A. Peruzzo a, M. Sertoli a, P. Trapani a,b L.Periale b, L.Isabella c, C. Landi c, A.Lucchesi c a Dipartimento di Fisica sperimentale,

More information

Proton Induced Thermal Stress Wave Measurements in. Solid Targets

Proton Induced Thermal Stress Wave Measurements in. Solid Targets Proton Induced Thermal Stress Wave Measurements in Solid Targets R. Wilfinger, J. Lettry, A. Fabich, M. Eller, R. Catherall, E. Barbero, D. Carminati, B. Crepieux Laser Doppler Vibrometer Single-Point

More information

SINGLE EVENT LATCH-UP TEST REPORT ADCLK925S

SINGLE EVENT LATCH-UP TEST REPORT ADCLK925S SINGLE EVENT LATCH-UP TEST REPORT ADCLK925S April 2016 Generic Radiation Test Report Product: ADCLK925S Effective LET: 85 MeV-cm 2 /mg Fluence: 1E7 Ions/cm 2 Die Type: AD8210 Facilities: TAMU Tested: June

More information

How did the LHC access system perform in 2009

How did the LHC access system perform in 2009 How did the LHC access system perform in 2009 L. Ponce On behalf of the OP team And a special thanks to all the volunteers who helped giving access Outline Some preliminary remarks Status and major issues

More information

C100 Cryomodule. Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint

C100 Cryomodule. Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint 1 new module C100 Cryomodule Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint Fundamental frequency f 0 Accelerating gradient E acc 1497 MHz >

More information

Reliability studies for a superconducting driver for an ADS linac

Reliability studies for a superconducting driver for an ADS linac Mol, Belgium, 6-9 May 2007 Reliability studies for a superconducting driver for an ADS linac Paolo Pierini, Luciano Burgazzi Work supported by the EURATOM 6 framework program of the EC, under contract

More information

AMICSA Bridging Science & Applications F r o m E a r t h t o S p a c e a n d b a c k. Kayser-Threde GmbH. Space

AMICSA Bridging Science & Applications F r o m E a r t h t o S p a c e a n d b a c k. Kayser-Threde GmbH. Space Bridging Science & Applications F r o m E a r t h t o S p a c e a n d b a c k E a r t h S p a c e & F u t u r e Kayser-Threde GmbH Space Industrial Applications AMICSA 2008 First radiation test results

More information

Herwig Schopper CERN 1211 Geneva 23, Switzerland. Introduction

Herwig Schopper CERN 1211 Geneva 23, Switzerland. Introduction THE LEP PROJECT - STATUS REPORT Herwig Schopper CERN 1211 Geneva 23, Switzerland Introduction LEP is an e + e - collider ring designed and optimized for 2 100 GeV. In an initial phase an energy of 2 55

More information

Machine-Detector Interface. Emmanuel Tsesmelis / TS-LEA LHCMAC17 9 June 2005

Machine-Detector Interface. Emmanuel Tsesmelis / TS-LEA LHCMAC17 9 June 2005 Machine-Detector Interface Emmanuel Tsesmelis / TS-LEA LHCMAC17 9 June 2005 Table of Contents General Organization Experiment-Machine Communications Beam Monitoring Radiation Monitoring Machine-induced

More information

Development of Radiation-Hard ASICs for the ATLAS Phase-1 Liquid Argon Calorimeter Readout Electronics Upgrade

Development of Radiation-Hard ASICs for the ATLAS Phase-1 Liquid Argon Calorimeter Readout Electronics Upgrade Development of Radiation-Hard ASICs for the ATLAS Phase-1 Liquid Argon Calorimeter Readout Electronics Upgrade Tim Andeen*, Jaroslav BAN, Nancy BISHOP, Gustaaf BROOIJMANS, Alex EMERMAN,Ines OCHOA, John

More information

Low Power Radiation Tolerant CMOS Design using Commercial Fabrication Processes

Low Power Radiation Tolerant CMOS Design using Commercial Fabrication Processes Low Power Radiation Tolerant CMOS Design using Commercial Fabrication Processes Amir Hasanbegovic (amirh@ifi.uio.no) Nanoelectronics Group, Dept. of Informatics, University of Oslo November 5, 2010 Overview

More information

QPLL a Quartz Crystal Based PLL for Jitter Filtering Applications in LHC

QPLL a Quartz Crystal Based PLL for Jitter Filtering Applications in LHC QPLL a Quartz Crystal Based PLL for Jitter Filtering Applications in LHC Paulo Moreira and Alessandro Marchioro CERN-EP/MIC, Geneva Switzerland 9th Workshop on Electronics for LHC Experiments 29 September

More information

Initial Results from a Cryogenic Proton Irradiation of a p-channel CCD

Initial Results from a Cryogenic Proton Irradiation of a p-channel CCD Centre for Electronic Imaging Initial Results from a Cryogenic Proton Irradiation of a p-channel CCD Jason Gow Daniel Wood, David Hall, Ben Dryer, Simeon Barber, Andrew Holland and Neil Murray Jason P.

More information

The Versatile Transceiver Proof of Concept

The Versatile Transceiver Proof of Concept The Versatile Transceiver Proof of Concept J. Troska, S.Detraz, S.Papadopoulos, I. Papakonstantinou, S. Rui Silva, S. Seif el Nasr, C. Sigaud, P. Stejskal, C. Soos, F.Vasey CERN, 1211 Geneva 23, Switzerland

More information

Cosmic Rays induced Single Event Effects in Power Semiconductor Devices

Cosmic Rays induced Single Event Effects in Power Semiconductor Devices Cosmic Rays induced Single Event Effects in Power Semiconductor Devices Giovanni Busatto University of Cassino ITALY Outline Introduction Cosmic rays in Space Cosmic rays at Sea Level Radiation Effects

More information

INSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM

INSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM INSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM FOR THE EUROPEAN XFEL Julien Branlard, for the LLRF team TALK OVERVIEW 2 Introduction Brief reminder about the XFEL LLRF system Commissioning goals

More information

R.Bachimanchi, IPAC, May 2015, Richmond, VA

R.Bachimanchi, IPAC, May 2015, Richmond, VA 1 new module C100 Cryomodule Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint Fundamental frequency f 0 Accelerating gradient E acc 1497 MHz >

More information

LUCX - THZ PROGRAM: OVERVIEW AND PROSPECTS

LUCX - THZ PROGRAM: OVERVIEW AND PROSPECTS LUCX - THZ PROGRAM: OVERVIEW AND PROSPECTS A. Aryshev On behalf of QB group and THz collaboration 14 Outline THz project overview LUCX activity LUCX Projects Overview THz program LUCX Laser system LUCX

More information

LV Power Box for the HEC Front-end Electronics (Document for the PRR of the Power Board)

LV Power Box for the HEC Front-end Electronics (Document for the PRR of the Power Board) LV Power Box for the HEC Front-end Electronics (Document for the PRR of the Power Board) A.Barajas, W.D.Cwienk, J.Habring, E.Rauter Max-Planck-Institut für Physik, Munich, Germany 11th January 2005 2 Contents

More information

Spectrometer cavern background

Spectrometer cavern background ATLAS ATLAS Muon Muon Spectrometer Spectrometer cavern cavern background background LPCC Simulation Workshop 19 March 2014 Jochen Meyer (CERN) for the ATLAS Collaboration Outline ATLAS Muon Spectrometer

More information

Chapter 6. Cold Powering. 6 Cold powering. A. Ballarino 1, J.P. Burnet 1, D. Ramos 1, U. Wagner 1, S. Weisz 1 and Y. Yang 2

Chapter 6. Cold Powering. 6 Cold powering. A. Ballarino 1, J.P. Burnet 1, D. Ramos 1, U. Wagner 1, S. Weisz 1 and Y. Yang 2 Chapter 6 Cold Powering A. Ballarino 1, J.P. Burnet 1, D. Ramos 1, U. Wagner 1, S. Weisz 1 and Y. Yang 2 1 CERN, Accelerator & Technology Sector, Geneva, Switzerland 2 University of Southampton, Southampton,

More information

SIMULATION OF A SIGNAL IN THE BEAM LOSS

SIMULATION OF A SIGNAL IN THE BEAM LOSS RADIATION ASPECTS OF LHC SIMULATION OF A SIGNAL IN THE BEAM LOSS MONITORS OF THE MOMENTUM CLEANING INSERTION FOR THE NEW COLLIMATOR JAWS DESIGN IHEP, Protvino, Russia Summary of the presentation Page 1

More information

AIDA Advanced European Infrastructures for Detectors at Accelerators. Conference Contribution

AIDA Advanced European Infrastructures for Detectors at Accelerators. Conference Contribution AIDA-CONF-2015-018 AIDA Advanced European Infrastructures for Detectors at Accelerators Conference Contribution Evaluating Multi-Gigabit Transceivers (MGT) for Use in High Energy Physics Through Proton

More information

A new strips tracker for the upgraded ATLAS ITk detector

A new strips tracker for the upgraded ATLAS ITk detector A new strips tracker for the upgraded ATLAS ITk detector, on behalf of the ATLAS Collaboration : 11th International Conference on Position Sensitive Detectors 3-7 The Open University, Milton Keynes, UK.

More information

1.0 Introduction. 2.0 Scope

1.0 Introduction. 2.0 Scope 1.0 Introduction The LCLS project requires one horizontal kicker magnet (BXKIK) to be installed at sector 25-3d. Nominal LCLS beam energy at that location is 4.8 GeV. The BXKIK magnet is planned to be

More information

Activities on Beam Orbit Stabilization at BESSY II

Activities on Beam Orbit Stabilization at BESSY II Activities on Beam Orbit Stabilization at BESSY II J. Feikes, K. Holldack, P. Kuske, R. Müller BESSY Berlin, Germany IWBS`02 December 2002 Spring 8 BESSY: Synchrotron Radiation User Facility BESSY II:

More information

COTS FPGA/SRAM Irradiations Using a Dedicated Testing Infrastructure for Characterization of Large Component Batches

COTS FPGA/SRAM Irradiations Using a Dedicated Testing Infrastructure for Characterization of Large Component Batches CERN-ACC-2015-0001 Slawosz.Uznanski@cern.ch COTS /SRAM Irradiations Using a Dedicated Testing Infrastructure for Characterization of Large Component Batches Slawosz Uznanski, Benjamin Todd, Johannes Walter,

More information

Summary. *LXOLR*UDQGH 3URJHWWD]LRQHHOHWWURQLFDQHJOLDPELHQWLDULVFKLRµ

Summary. *LXOLR*UDQGH 3URJHWWD]LRQHHOHWWURQLFDQHJOLDPELHQWLDULVFKLRµ Summary RadHard device versus COTS Radiation environment Radiation effects High reliability solutions Tests overview ASIC for Supply Current Control (SCC) Future work RadHard components J Immune or resistant

More information

Radiation hardness and precision timing study of Silicon Detectors for the CMS High Granularity Calorimeter (HGC)

Radiation hardness and precision timing study of Silicon Detectors for the CMS High Granularity Calorimeter (HGC) Radiation hardness and precision timing study of Silicon Detectors for the CMS High Granularity Calorimeter (HGC) Esteban Currás1,2, Marcos Fernández2, Christian Gallrapp1, Marcello Mannelli1, Michael

More information

INSTRUMENTATION AND CONTROL SYSTEM FOR THE INTERNATIONAL ERL CRYOMODULE

INSTRUMENTATION AND CONTROL SYSTEM FOR THE INTERNATIONAL ERL CRYOMODULE INSTRUMENTATION AND CONTROL SYSTEM FOR THE INTERNATIONAL ERL CRYOMODULE S. M. Pattalwar, R. Bate, G. Cox, P.A. McIntosh and A. Oates, STFC, Daresbury Laboratory, Warrington, UK Abstract ALICE is a prototype

More information

Acceleration of High-Intensity Protons in the J-PARC Synchrotrons. KEK/J-PARC M. Yoshii

Acceleration of High-Intensity Protons in the J-PARC Synchrotrons. KEK/J-PARC M. Yoshii Acceleration of High-Intensity Protons in the J-PARC Synchrotrons KEK/J-PARC M. Yoshii Introduction 1. J-PARC consists of 400 MeV Linac, 3 GeV Rapid Cycling Synchrotron (RCS) and 50 GeV Main synchrotron

More information

OPTICAL LINK OF THE ATLAS PIXEL DETECTOR

OPTICAL LINK OF THE ATLAS PIXEL DETECTOR OPTICAL LINK OF THE ATLAS PIXEL DETECTOR K.K. Gan, W. Fernando, P.D. Jackson, M. Johnson, H. Kagan, A. Rahimi, R. Kass, S. Smith Department of Physics, The Ohio State University, Columbus, OH 43210, USA

More information

Enhanced Low Dose Rate Sensitivity (ELDRS) Radiation Testing of the RH1814MW Quad Op Amp for Linear Technology

Enhanced Low Dose Rate Sensitivity (ELDRS) Radiation Testing of the RH1814MW Quad Op Amp for Linear Technology Enhanced Low Dose Rate Sensitivity (ELDRS) Radiation Testing of the RH1814MW Quad Op Amp for Linear Technology Customer: Linear Technology (PO 57472L) RAD Job Number: 10-417 Part Type Tested: Linear Technology

More information

1. PUBLISHABLE SUMMARY

1. PUBLISHABLE SUMMARY Ref. Ares(2018)3499528-02/07/2018 1. PUBLISHABLE SUMMARY Summary of the context and overall objectives of the project (For the final period, include the conclusions of the action) The AIDA-2020 project

More information

Optical Readout and Control Systems for the CMS Tracker

Optical Readout and Control Systems for the CMS Tracker This material is presented to ensure timely dissemination of scholarly and technical work. Copyright and all rights therein are retained by authors or by other copyright holders. All persons copying this

More information

The CMS Muon Trigger

The CMS Muon Trigger The CMS Muon Trigger Outline: o CMS trigger system o Muon Lv-1 trigger o Drift-Tubes local trigger o peformance tests CMS Collaboration 1 CERN Large Hadron Collider start-up 2007 target luminosity 10^34

More information

Beam Loss monitoring R&D. Arden Warner Fermilab MPS2014 Workshop March 5-6, 2014

Beam Loss monitoring R&D. Arden Warner Fermilab MPS2014 Workshop March 5-6, 2014 Beam Loss monitoring R&D Arden Warner Fermilab MPS2014 Workshop March 5-6, 2014 Outline PXIE Technical Concerns PXIE Study plans Preliminary scvd R&D Cold Ionization chambers 2 MPS2014; Arden Warner Loss

More information

Attilio Andreazza INFN and Università di Milano for the ATLAS Collaboration The ATLAS Pixel Detector Efficiency Resolution Detector properties

Attilio Andreazza INFN and Università di Milano for the ATLAS Collaboration The ATLAS Pixel Detector Efficiency Resolution Detector properties 10 th International Conference on Large Scale Applications and Radiation Hardness of Semiconductor Detectors Offline calibration and performance of the ATLAS Pixel Detector Attilio Andreazza INFN and Università

More information

Results of FE65-P2 Pixel Readout Test Chip for High Luminosity LHC Upgrades

Results of FE65-P2 Pixel Readout Test Chip for High Luminosity LHC Upgrades for High Luminosity LHC Upgrades R. Carney, K. Dunne, *, D. Gnani, T. Heim, V. Wallangen Lawrence Berkeley National Lab., Berkeley, USA e-mail: mgarcia-sciveres@lbl.gov A. Mekkaoui Fermilab, Batavia, USA

More information

Study of the radiation-hardness of VCSEL and PIN

Study of the radiation-hardness of VCSEL and PIN Study of the radiation-hardness of VCSEL and PIN 1, W. Fernando, H.P. Kagan, R.D. Kass, H. Merritt, J.R. Moore, A. Nagarkara, D.S. Smith, M. Strang Department of Physics, The Ohio State University 191

More information

Use COTS or Not Use COTS in Space Applications?

Use COTS or Not Use COTS in Space Applications? Use COTS or Not Use COTS in Space Applications? Addressing concerns over this growing question. October 2017 With the recent shift in space electronics using ruggedized commercial components as a cost-efficient

More information

2 nd Generation CMOS Charge Transfer TDI: Results on Proton Irradiation

2 nd Generation CMOS Charge Transfer TDI: Results on Proton Irradiation 2 nd Generation CMOS Charge Transfer TDI: Results on Proton Irradiation F. Mayer, J. Endicott, F. Devriere e2v, Avenue de Rochepleine, BP123, 38521 Saint Egrève Cedex, France J. Rushton, K. Stefanov, A.

More information

Assessment of BLM Thresholds in Collimation Regions for the LHC startup

Assessment of BLM Thresholds in Collimation Regions for the LHC startup Assessment of BLM Thresholds in Collimation Regions for the LHC startup By Till Böhlen & BLM Team 1/11 Content Introduction to Protection of Collimators Approach & Work so far Experiment @ SPS & Simulations

More information

Monolithic Pixel Sensors in SOI technology R&D activities at LBNL

Monolithic Pixel Sensors in SOI technology R&D activities at LBNL Monolithic Pixel Sensors in SOI technology R&D activities at LBNL Lawrence Berkeley National Laboratory M. Battaglia, L. Glesener (UC Berkeley & LBNL), D. Bisello, P. Giubilato (LBNL & INFN Padova), P.

More information

Enhanced Low Dose Rate Sensitivity (ELDRS) of the RH1078MJ8 Dual Precision Op Amp for Linear Technology

Enhanced Low Dose Rate Sensitivity (ELDRS) of the RH1078MJ8 Dual Precision Op Amp for Linear Technology Enhanced Low Dose Rate Sensitivity (ELDRS) of the RH1078MJ8 Dual Precision Op Amp for Linear Technology Customer: Linear Technology, PO# 54873L RAD Job Number: 09-578 Part Type Tested: Linear Technology

More information

The NaoSat nanosatellite platform for in-flight radiation testing. Jose A Carrasco CEO EMXYS Spain

The NaoSat nanosatellite platform for in-flight radiation testing. Jose A Carrasco CEO EMXYS Spain Jose A Carrasco CEO EMXYS Spain Presentation outline: - Purpose and objectives of EMXYS NaoSat plattform - The Platform: service module - The platform: payload module and ICD - NaoSat intended missions

More information

Quality Assurance for the ATLAS Pixel Sensor

Quality Assurance for the ATLAS Pixel Sensor Quality Assurance for the ATLAS Pixel Sensor 1st Workshop on Quality Assurance Issues in Silicon Detectors J. M. Klaiber-Lodewigs (Univ. Dortmund) for the ATLAS pixel collaboration Contents: - role of

More information

Test bench for evaluation of radiation hardness in Application Specific Integrated Circuits

Test bench for evaluation of radiation hardness in Application Specific Integrated Circuits SHEP 2016 Workshop on Sensors and High Energy Physics Test bench for evaluation of radiation hardness in Application Specific Integrated Circuits Vlad Mihai PLĂCINTĂ 1,3 Lucian Nicolae COJOCARIU 1,2 1.

More information

ALICE SRF SYSTEM COMMISSIONING EXPERIENCE A. Wheelhouse ASTeC, STFC Daresbury Laboratory

ALICE SRF SYSTEM COMMISSIONING EXPERIENCE A. Wheelhouse ASTeC, STFC Daresbury Laboratory ALICE SRF SYSTEM COMMISSIONING EXPERIENCE A. Wheelhouse ASTeC, STFC Daresbury Laboratory ERL 09 8 th 12 th June 2009 ALICE Accelerators and Lasers In Combined Experiments Brief Description ALICE Superconducting

More information

Market Survey. Technical Description. Supply of Medium Voltage Pulse Forming System for Klystron Modulators

Market Survey. Technical Description. Supply of Medium Voltage Pulse Forming System for Klystron Modulators EDMS No. 1972158 CLIC Drive Beam Klystron Modulator Group Code: TE-EPC Medium Voltage Pulse Forming System for CLIC R&D Market Survey Technical Description Supply of Medium Voltage Pulse Forming System

More information

Versatile transceiver production and quality assurance

Versatile transceiver production and quality assurance Journal of Instrumentation OPEN ACCESS Versatile transceiver production and quality assurance To cite this article: L. Olantera et al Related content - Temperature characterization of versatile transceivers

More information

The LHCb VELO Upgrade. Stefano de Capua on behalf of the LHCb VELO group

The LHCb VELO Upgrade. Stefano de Capua on behalf of the LHCb VELO group The LHCb VELO Upgrade Stefano de Capua on behalf of the LHCb VELO group Overview [J. Instrum. 3 (2008) S08005] LHCb / Current VELO / VELO Upgrade Posters M. Artuso: The Silicon Micro-strip Upstream Tracker

More information

SARAF commissioning & safety issues. L. Weissman on behalf of the SARAF team SPIRAL week 2010

SARAF commissioning & safety issues. L. Weissman on behalf of the SARAF team SPIRAL week 2010 SARAF commissioning & safety issues L. Weissman on behalf of the SARAF team SPIRAL week 2010 1 Outline commissioning of SARAF project : RFQ status Cryomodule status Accumulated beam operation experience

More information

Nano Beam Position Monitor

Nano Beam Position Monitor Introduction Transparent X-ray beam monitoring and imaging is a new enabling technology that will become the gold standard tool for beam characterisation at synchrotron radiation facilities. It allows

More information

Radiological Safety Analysis Document for the CLAS12 Engineering and the first physics run of Run Group A

Radiological Safety Analysis Document for the CLAS12 Engineering and the first physics run of Run Group A Radiological Safety Analysis Document for the CLAS12 Engineering and the first physics run of Run Group A This Radiological Safety Analysis Document (RSAD) will identify the general conditions associated

More information

Preparing for the Future: Upgrades of the CMS Pixel Detector

Preparing for the Future: Upgrades of the CMS Pixel Detector : KSETA Plenary Workshop, Durbach, KIT Die Forschungsuniversität in der Helmholtz-Gemeinschaft www.kit.edu Large Hadron Collider at CERN Since 2015: proton proton collisions @ 13 TeV Four experiments:

More information

Heavy Ion Test Report for the MSK5063RH Switching Regulator with the RH3845 and RH411 Die

Heavy Ion Test Report for the MSK5063RH Switching Regulator with the RH3845 and RH411 Die Heavy Ion Test Report for the MSK5063RH Switching Regulator with the RH3845 and RH411 Die Shirley Hart 1, Paul Musil 2, David Beebe 3, and Bryan Horton 2 Report prepared by: Dakai Chen 3 1. Previously

More information