1 CVE Surveying Lab #4 LOCATION SURVEY EQUIPMENT Right angle mirror (pentaprism) Surveyor s tape Plumb bobs Range poles INTRODUCTION Many times the surveyor is called upon to catalog details of a project prior to construction and after completion of the improvements. Prior to construction information concerning the location of details in the vicinity of a construction project is included on plans created by the engineer for the project. In a similar fashion, details of the project area after construction are placed on plans that are appropriately called as-built. Important information can include (but is not limited to) the following: a) trees, shrubs and hedges - type and size b) buildings - type and plan outline c) edge of pavements - asphalt, concrete, gravel, sidewalks, etc. d) catch basins e) concrete culverts d) corrugated steel pipe e) hydrants f) manholes g) fences h) utility poles - light, electricity, telephone, etc. The above list is by no means complete. Before a location survey takes place, a clear understanding is needed in regards to the precision necessary to locating details. If the survey is required to locate details that will later appear on small scale maps, then low order precision is called for. However, for most urban and suburban location surveys, cataloging and locating existing details can aid the engineer during the design phase of a project. In addition, the surveyor can minimize litigation after a project is completed if the contractor must restore facilities to their prior condition. Here the order of precision is determined by the economics of designing around existing features and/or replacing existing features. Prof. S.F. Duffy PhD, PE, F. ASCE Revised: 9/26/2006 Page 1
2 There are several ways to locate existing details mentioned above. These methods include: a) station and right angle offset (rectangular coordinates). b) station, angle, and distance (polar coordinates). c) angles from two known points (usually project stations or project bench marks). d) distances from two known points (usually project stations or project bench marks) For higher order precision the objective is to locate existing details with at least one measurement more (i.e., a check measurement) than is actually needed to plot a detail in plan view. The competing economic objective is minimizing the time necessary to achieve the first objective. Many types of surveys use the right-angle offset technique to locate details. With this method existing details are located by measuring the perpendicular distance from a base line (or traverse leg) to the detail. In addition, the distance along the base line (traverse leg) to the point of perpendicularity (see the figure below) must be recorded. The base line (traverse leg) is established in the field with stakes, PK nails in asphalt, or drill holes in concrete pavement. Appropriate intervals, usually ft are established along the base line. If the terrain is smooth a tape can be placed on the ground between stations. This will permit the student surveyor to move along the tape (preferably in the direction of the forward station), making field sketches and recording information relative to the stations, and offset dimensions, of details on either sides of the base line. A sketch is entered in the field book before the measurements for each detail commences. The right angle for each location tie can be established using a pentaprism (a right angle mirror) or the arm method (an approximate method to establish a right angle in the field). With the arm method the student surveyor stands on the base line facing a point on the detail being located. One arm is pointed down the base line in the direction of one bench mark, and the other arm is pointed down the baseline towards another bench mark in the opposite direction. After checking both arms for proper alignment by alternatively sighting down either index finger, the student surveyor closes his or her eyes while swinging the arms together in front. Presumably, the student surveyor should be pointing at the requisite point on the detail. If the student surveyor is not pointing at the appropriate spot on the detail, the student surveyor moves slightly along the baseline and repeats the procedure until the detail has been correctly sighted. The station is then read off the tape and recorded in the field book. This approximate method is used a great deal in route surveys and municipal surveys. This technique provides good results over short offset distances (50 ft or 15 m). For longer offset distances or for important details, a pentaprism is used to determine the station along the base line. Once all pertinent details have been located along the base line and recorded, the student surveyor must then measure the offsets left and right of the baseline.. Prof. S.F. Duffy PhD, PE, F. ASCE Revised: 9/26/2006 Page 2
3 The figure below illustrates topographic field notes that have been recorded using a single base line. In this figure the offsets are shown on the dimension lines and the stations are shown opposite the dimension line, or as close as possible to the actual tie point on the base line. As previously indicated, at least one check tie or check dimension should be taken on each object. These checks are omitted in the figure above so that the various methods may be shown clearly Catch Basin 79.2 ft Station BM A 31.7 ft Station 2+55 Residence 223 Elm Drive 10 ft Station ft Station ft Station 2+00 Ash Tree 18 in diam. BM B Edge of Pavement Elm Drive - 75 ROW NTS When field drawings become too cluttered the reference base line in a drawing can be split. Here two lines are drawn representing the base line. leaving a space (representing zero dimension) between the base lines for the inclusion of stations. The split base line technique is particularly valuable in densely detailed areas where single baseline notes would tend to become crowded and difficult to decipher (note the area in the general vicinity of BM B in the previous figure). The earliest topographic surveyors in North America used the split base line method of note keeping. Methods (b), (c) and (d) listed above can be implemented using an EDMI. Although the EDMI will not be utilized until a later lab, the student surveyor should recognize that the polar coordinate approach illustrated in the figure below is more efficient than the right angle approach if existing field details are readily visible. Efficiency requires that the student surveyor use as Prof. S.F. Duffy PhD, PE, F. ASCE Revised: 9/26/2006 Page 3
4 few instrument setups as possible when mapping an area. If the EDMI is used in a location survey then the instrument setup point should be a bench mark within the traverse. The most efficient instrument setup point would be located at a place where as many existing details as possible within the project area are visible. In taking the field measurement, the student surveyor must constantly keep in mind the way in which these measurements will be used in plotting the data. SFD Wharehouse ft Traverse Line BM B BM A When using an instrument, the setup point is located nearby a horizontal control point that is visible from the instrument. With the instrument in position over the setup point, the telescope is sighted on the control point. The back azimuth of the instrument setup point to the nearby control point is set into the instrument s horizontal circle and the lower motion is clamped. This requires prior knowledge of the back azimuth of the instrument setup point and the control point Thus when the EDMI is sighted on an existing detail in the field, the horizontal circle will read the azimuth to the point. This procedure is called the azimuth transfer method. Prof. S.F. Duffy PhD, PE, F. ASCE Revised: 9/26/2006 Page 4
5 PROCEDURE Each student survey crew will locate details along one course of the traverse utilized in Lab #1. The instructor will assign the student survey crews to a specific course. The two courses utilized in this lab will be the north-south course between Stilwell Hall and Woodling Gym as well as the east-west course that parallels Chester Avenue. The student survey crew will locate as many details as directed by the lab assistant. In order to locate details the student survey crew will: 1. Begin at one bench mark within the traverse and lay the surveyor s tape on the ground on line (use range poles) with the next bench mark in the traverse. 2. Mark 50 foot stations. 3. Utilizing the right angle prism locate the position of details relative to the tape. Mark the position at the tape with keel. 4. After the position of specified points on a detail has been determined along the surveyor s tape, measure the perpendicular distance from the tape to the each point on the detail with a cloth tape. 5. Repeat steps 3 and 4 and locate all details mentioned earlier along the assigned traverse course. Note that this effort will be repeated with the EDMI in a later lab. The student will notice the increase in productivity (i.e., more details will be located) when azimuths and distances are determined with the EDMI. Prof. S.F. Duffy PhD, PE, F. ASCE Revised: 9/26/2006 Page 5
6 FIELD NOTES Take careful notes. Record sizes and descriptions. A data collector will not have the descriptive capacity that a field book has, so record detailed information in this lab. Use the following format in your field book: Station Dist. from Description Size ID # 9/6/00 J.Salem Baseline 66 F J. Palko E. Baker BM A ' north Catch Basin 4 sq ft ' north Parking Meter 1" diam 1101 Sketch Here - See Previous Figures ' south Oak Tree 4" diam ' south NW Corn. Bldg Prof. S.F. Duffy PhD, PE, F. ASCE Revised: 9/26/2006 Page 6
COURSE SYLLABUS SURVEYING I
Solution Manual for Surveying Fundamentals and Practices 6th Edition by Nathanson Lanzafama Emeritus Link full download: http://testbankcollection.com/download/solution-manual-forsurveying-fundamentals-and-practices-6th-edition-by-nathanson-lanzafamaemeritus/
More informationSection E NSPS MODEL STANDARDS FOR TOPOGRAPHIC SURVEYS Approved 3/12/02
Section E NSPS MODEL STANDARDS FOR TOPOGRAPHIC SURVEYS Approved 3/12/02 1. INTRODUCTION This standard is written to provide the professional surveyor (Surveyor) and the client with a guideline for producing
More informationPART XII: TOPOGRAPHIC SURVEYS
PART XII: TOPOGRAPHIC SURVEYS 12.1 Purpose and Scope The purpose of performing topographic surveys is to map a site for the depiction of man-made and natural features that are on, above, or below the surface
More informationSuveying Lectures for CE 498
Suveying Lectures for CE 498 SURVEYING CLASSIFICATIONS Surveying work can be classified as follows: 1- Preliminary Surveying In this surveying the detailed data are collected by determining its locations
More informationSurveying & Measurement. Detail Survey Topographic Surveying
Surveying & Measurement Detail Survey Topographic Surveying Introduction Mapping surveys are made to determine the relief of the earth s surface and locate critical points on it. to determine the locations
More informationInstructors Manual for Construction Surveying and Layout Third Edition Part Three - Applications Chapters Prepared by Wesley G.
Instructors Manual for Construction Surveying and Layout Third Edition Part Three - Applications Chapters 19-22 Prepared by Wesley G. Crawford TABLE OF CONTENTS Chapter 19 - Layout Techniques... 3 Chapter
More informationSTATE UNIVERSITY CONSTRUCTION FUND
DIRECTIVE 1C-12 Issue date: August 2012 1. General SURVEY, MAPPING AND UTILITY LOCATING This Directive has been developed as a general guide for the survey and mapping effort required for Fund projects.
More informationQUANTITY SURVEYS. Introduction
QUANTITY SURVEYS Introduction In engineering surveying, we often consider a route (road, sewer pipeline, channel, etc.) from three distinct perspectives. The plan view of route location is the same as
More information1.1 GENERAL RECORD DRAWING REQUIREMENTS
Page 1 of 5 VILLAGE OF ROMEOVILLE RECORD DRAWINGS CHECKLIST PART I GENERAL Record drawings are required to provide a means of schematic verification that the intent of the approved engineering design has
More informationSurvey Requirements. Design Guidelines and Standards. June Office of the University Architect
Design Guidelines and Standards Survey Requirements June 2004 Office of the University Architect Construction Management P.O. Box 210181 Cincinnati, Ohio 45221-0181 Table of Contents Survey Requirements
More informationCITY OF LOMPOC DEVELOPMENT ASSISTANCE BROCHURE ENCROACHMENT PERMITS AND PUBLIC IMPROVEMENT PLANS
CITY OF LOMPOC DEVELOPMENT ASSISTANCE BROCHURE E-10 ENCROACHMENT PERMITS AND PUBLIC IMPROVEMENT PLANS The City of Lompoc has determined that the Engineering Division should administer and issue Encroachment
More informationCity of Massillon Site Plan Checklist
City of Massillon Site Plan Checklist The following information MUST be included with all Site Plans submitted for review and processing in order to constitute a complete Site Plan Package. Incomplete
More informationDate Requested, 200_ Work Order No. Funding source Name of project Project limits: Purpose of the project
Bureau of Engineering SURVEY DIVISION REQUEST FOR TOPOGRAPHIC SURVEY Date Requested, 200_ Work Order No. Funding source Name of project Project limits: Purpose of the project Caltrans involvement (must
More informationSECTION SITE SURVEYS
SECTION 02 21 13 SITE SURVEYS SPEC WRITER NOTE: 1. Delete text between // // not applicable to project. Edit remaining text to suit project. 2. Use this section to specify survey required before design
More informationCHAPTER 11. Plan Standards
CHAPTER 11 Plan Standards A. Introduction The city requires uniform public improvement plans for ease of record keeping and understanding. The following standards govern most plan submittals to the city.
More informationBRASELTON WATER AND WASTEWATER DEPARTMENT CONSTRUCTION PLAN REVIEW CHECKLIST May 2006
Project Name: BRASELTON WATER AND WASTEWATER DEPARTMENT CONSTRUCTION PLAN REVIEW CHECKLIST May 2006 Phase: Unit: # Lots: Development Type (residential, commercial, industrial, etc.) Braselton Project No.
More informationConstruction Plan Reading Basics & Applications
Construction Plan Reading Basics & Applications July 12 th, 2016 / 4 p.m. Richland County Transportation Penny Office Instructor Ben W. Lewis, PE Welcome & Introductions Instructor Ben W. Lewis, PE Project
More informationDepartment of Civil and Environmental Engineering
Department of Civil and Environmental Engineering CEE213L Surveying & Introduction to GIS Lab SURVEYING LABORATORY NORTH SOUTH UNIVERSITY Center of Excellence in Higher Education The First Private University
More information.1 Applicability: These criteria shall be applied as follows:
DESIGN CRITERIA DIVISION 4800 STREET LIGHTING 4801 GENERAL: These criteria shall be adhered to for the design of all publiclyfinanced or privately-financed traffic signal systems to be installed in the
More informationSEATS (middle and front row): 1. Sort six (6) 2x6x10 pieces. 2. Measure and cut one (1) 72 length and one (1) 48 length from each piece.
# Materials: Quantity Each: Total Quantity: 2x6x8 6 2x6x10 6 2x4x8 4 4x4x8 7 TIPS FOR SUCCESSFUL PREP WORK: Before starting, carefully read through the entire instruction sheet. Refer to the material list
More informationCHAPTER F IVE ROBOTIC TOTAL STATION
CHAPTER F IVE ROBOTIC TOTAL STATION 5 ROBOTIC TOTAL STATION 5 OVERVIEW If necessity is the mother of invention, then the invention of the Total Station robotic instrument truly fits the requirements of
More informationList of Figures. List of Forms
City of Columbia Engineering Regulations PART 1: SUBMISSION OF PLANS Table of Contents Paragraph Description Page No. 1.1 General 1-1 1.2 Engineer s Report 1-1 1.3 Plans 1-3 1.4 Revisions to Approved Plan
More informationPART XIII: HYDRAULIC/ HYDROLOGY SURVEYS
PART XIII: HYDRAULIC/ HYDROLOGY SURVEYS 13.1 Purpose and Scope Hydraulic surveys are required for flow analysis to determine bridge and culvert design characteristics. A hydraulic survey is usually but
More informationINSTRUCTIONS: 1. Record the transmittal letter number, date, and subject on the transmittal record sheet located in the front of the manual.
MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards ISSUED BY: Office of Technical Support Design Services Section TRANSMITTAL LETTER NO. (0-03) MANUAL: Standard Plates DATED: September
More informationEngineering Surveying -1 CE212 Chain Survey
Engineering Surveying -1 CE212 Chain Survey Lecture 2016, September 26-27 Muhammad Noman Chain Survey Chain survey is the simplest method of surveying. In this survey only measurements are taken in the
More informationCouncil Policy Engineering Drawing Submission Requirements
POLICY 265 City of Kelowna 1435 Water Street Kelowna, BC V1Y 1J4 250 469-8500 kelowna.ca Council Policy Engineering Drawing Submission Requirements APPROVED June 4, 2001 RESOLUTION: R375/10/04/26 REPLACING:
More informationIAN HUMBY TEACHING. List of Hand-Outs. Levelling
IAN HUMBY TEACHING List of Hand-Outs Levelling 6-1 Equipment List (Levelling) 11-1 to 11-3 Introduction to Levelling 11-4 Levelling Terminology 12-1 to 12-2 Measuring Height Change by Basic Methods 13-1
More informationCITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division STREET/ALLEY IMPROVEMENT PLAN REVIEW CHECKLIST
CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil ing Division STREET/ALLEY IMPROVEMENT PLAN REVIEW CHECKLIST The following checklist consists of the minimum requirements for preparation
More informationFACULTY OF CIVIL ENGINEERING & EARTH RESOURCES ENGINEERING SURVEY FIELDWORK. LEVELING (Standard Of Procedure)
FACULTY OF CIVIL ENGINEERING & EARTH RESOURCES ENGINEERING SURVEY FIELDWORK LEVELING (Standard Of Procedure) Subject Code Date Group Number Student Name & ID Number Group Member Name & ID Number 1 2 Lecturer
More informationQuestion bank. Unit 1: Introduction
Question bank Unit 1: Introduction 1. Define surveying. 2. State the objects of surveying 3. State and explain the principle of surveying 4. State and explain the classification of surveying 5. Differentiate
More informationMILL HILL ARTS VILLAGE
OWNER CIVIL ENGINEER MACON-BIBB URBAN DEVELOPMENT AUTHORITY ALEX MORRISON, EXECUTIVE DIRECTOR 200 CHERRY STREET, SUITE 300 MACON, GA 31201 OFFICE PHONE : (478) 803-2402 TRIPLE POINT ENGINEERING DAN WALLACE,
More informationTOWN of LAKESHORE SITE PLAN CHECKLIST
TOWN of LAKESHORE SITE PLAN CHECKLIST Last Revised December 17, 2009 Project Name: Project Location: Date Submitted: Name Phone Number E-mail Address Owner: Contractor/ Engineer: ( ) ( ) Applicant: ( )
More information7000 Fifteen Mile Road Sterling Heights, Michigan
7000 Fifteen Mile Road Sterling Heights, Michigan Industrial Building With Excess Land and Rail Access As exclusive agents, we are pleased to offer the following property for lease: 128,648 Sq. Ft. Completely
More information1 Exam Prep Prov Module: Distance Measurement and Leveling Questions and Answers
1 Exam Prep Prov Module: 28306-05 Distance Measurement and Leveling Questions and Answers 1. Site layout involves extensive use of plans. A. Foundation B. Elevation C. Floor D. Plot 2. Contour lines are
More informationMapping The Study Area
While on the beach you will need to take some measurements to show where the study area is relative to the rest of the world and to show what is inside the study area. Once the measurements have been taken,
More information3. DESIGN SPECIFICATIONS
Schedule H to Bylaw 7452, Subdivision Bylaw Page 10 3. DESIGN SPECIFICATIONS 3.1 General 3.1.1 The Design Specifications apply to the design of sanitary sewers, storm drains, waterworks, roadways, and
More informationMemorandum. Mayor and Board of Aldermen. Benjamin Requet, Senior Planner. Date: February 21, Request for Water and Sewer Service for Clay Canvas
Memorandum To: From: Mayor and Board of Aldermen Benjamin Requet, Senior Planner February 21, 2017 Re: Request for Water and Sewer Service for Clay Canvas Please consider this request for granting water
More informationSTANDARD BID ITEM NUMBERS
10701 TRAFFIC CONTROL LUMP SUM 10702 Traffic Control for Storm Sewer Installation LUMP SUM 10703 Traffic Control for Water Main Installation LUMP SUM 10704 Traffic Control for Sanitary Sewer Installation
More informationSUBJECT: Standard Plate Turf Establishment Areas (at Pipe Culvert Ends)
MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards ISSUED BY: Office of Program Management and Technical Support, Design Support Section TRANSMITTAL LETTER NO. (14-01) MANUAL: Standard
More informationCOSC 301 Construction Surveying & Layout Activity VI Transit; Existing Building (As built) and Vertical Angles
COSC 301 Construction Surveying & Layout Activity VI Transit; Existing Building (As built) and Vertical Angles Introduction 1. Review chapter 4 The Digital Transit and watch and understand chapter 5 Control
More information2. Remove from the Standard Plate manual: Standard Plate Index, Sheets 1-4 of 4, Numerical Index of Standard Plates (August 31, 2012)
MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards ISSUED BY: Office of Program Management & Technical Support, Design Support Section TRANSMITTAL LETTER NO. (12-04) MANUAL: Standard
More informationLocation of Structure on Site
Chapter 1 Location of Structure on Site A number of factors affect the location of a structure on a site, as well as the type of building that may be erected. Once the site is chosen, different methods
More informationGeneral Physics Experiment 5 Optical Instruments: Simple Magnifier, Microscope, and Newtonian Telescope
General Physics Experiment 5 Optical Instruments: Simple Magnifier, Microscope, and Newtonian Telescope Objective: < To observe the magnifying properties of the simple magnifier, the microscope and the
More informationInstallation Fence Guide Kodiak Iron. Exceptional Fencing Extraodinary Customer Service
Installation Fence Guide Kodiak Iron Exceptional Fencing Extraodinary Customer Service Kodiak Fence System Installation Guide Thank you for the purchasing the Kodiak Fence System. Fence installation is
More informationLesson 8: Surveying the Forest
Lesson 8: Surveying the Forest TEACHER: SCHOOL: GRADE LEVEL: 9-12 TASKS/COMPETENCIES ANR8046.172 Set up and operate a transit level and rod. ANR8046.173 Read a rod and a level to calculate slope. ANR8046.174
More informationB.2 MAJOR SUBDIVISION PRELIMINARY PLAN CHECKLIST
B.2 MAJOR SUBDIVISION PRELIMINARY PLAN CHECKLIST YES* GENERAL SUBMISSION ITEMS Does the submission include: 1. Thirteen (13) copies of completed Application Form? 2. Thirteen (13) copies of the Preliminary
More informationFigure 8-1 Layout equipment and tools. Tape measure. String line level. Eyepiece level. Laser plane level Delmar/Cengage Learning.
3 2 1 0 Tape measure String line level Clinometer Eyepiece level Transit Dumpy level Carpenter s or builder s level Electronic measurement Tool Laser plane level Figure 8-1 Layout equipment and tools.
More informationENGINEERING SURVEYING (221 BE) Setting Out And Site Control. Sr Tan Liat Choon Mobile:
ENGINEERING SURVEYING (221 BE) Setting Out And Site Control Sr Tan Liat Choon Email: tanliatchoon@gmail.com Mobile: 016-4975551 WHAT IS SETTING OUT Setting out is all about transferring measurements from
More informationConstruction Surveying and Layout
Construction Surveying and Layout A Field Engineering Methods Manual Third Edition WESLEY G. CRAWFORD.CREATIVE CONSTRUCTION Creative Construction Publishing, Inc. 2720 South River Road West Lafayette,
More informationSUPPLEMENTARY STANDARD DETAIL DRAWINGS
CITY OF MAPLE RIDGE DESIGN AND CONSTRUCTION DOCUMENTS Part 4 SUPPLEMENTARY STANDARD DETAIL DRAWINGS September 2015 Updated: October 2015 THIS PAGE INTENTIONALLY LEFT BLANK City of Maple Ridge Supplementary
More informationMINIMUM C/L RADII OF CURVATURE OF LOCAL ROADS IN SUBDIVISIONS
75m 70m 65m 60m DEFLECTION ANGLE C/L RADII OF CURVATURE 55m 50m 45m 40m 35m 30m 25m 20m 15m 90 80 70 60 50 40 30 20 10 0 DEFLECTION ANGLE - MINIMUM C/L RADII OF CURVATURE OF LOCAL ROADS IN SUBDIVISIONS
More informationManhole or Catch Basin Type A & B Cone Sections Precast - Design F Manhole or Catch Basin Cover (Reducer Cone Section Precast) Design D
MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards ISSUED BY: Office of Program Management and Technical Support, Design Support Section TRANSMITTAL LETTER NO. (14-02) MANUAL: Standard
More informationPorter County Plan Commission
Plan Type: Development Plan Administrative DRC PC Primary Plan Administrative DRC PC Secondary Plat/Replat Administrative DRC PC PUD Conceptual Detailed Final Project Information Project Name: Developer
More informationUTILITY AND STREET CONSTRUCTION PLAN REQUIREMENTS SECTION 1
UTILITY AND STREET CONSTRUCTION PLAN REQUIREMENTS SECTION 1 ENGINEERING STANDARDS FOR UTILITY AND STREET CONSTRUCTION PLANS MARCH 2014 CONSTRUCTION PLAN SHEET FORMAT REQUIREMENTS REPRODUCIBLE MYLAR 1.
More informationTSA Surveying Course
TSA Surveying Course with ProQual Level 3 in Engineering Surveying A block by block outline Preamble The TSA Surveying Course comprises six study periods of two weeks each spread over a period of two years
More informationCITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA (360)
CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA 98501 (360) 754-4180 Email: cdd@ci.tumwater.wa.us WATER-SEWER-STREET-STORM (IN CITY) Submittal Checklist TUM - RCVD BY DATE STAMP APPLICANT INFORMATION
More informationCity of Kitchener Infrastructure Services Department Engineering Services Division. CAD Standards for Engineering
City of Kitchener Infrastructure Services Department Engineering Services Division CAD Standards for Engineering Printed: October 29, 2012 Revision History Revision Description Date Layer revisions. June
More informationCity of Vaughan Engineering Department DESIGN STANDARD DRAWINGS
City of Vaughan Engineering Department DESIGN STANDARD DRAWINGS March 2004 STANDARD DRAWINGS Partners With The Environment March 2004 FORWARD The March 2004 version of the City of Vaughan Design Standard
More informationSECTION 4 DESIGN SURVEYS
SECTION 4 DESIGN SURVEYS Table of Contents Page No 4.1 AERIAL PHOTOGRAPHY CRITERIA...1 4.1.1 SCALE OF NEGATIVES... 1 4.1.2 PHOTOGRAMMETRIC GROUND CONTROL... 1 4.1.3 LOW ALTITUDE MAPPING & PHOTOGRAMMETRY
More informationSpecifications for Land Surveys January 2014 Version
Specifications for Land Surveys January 2014 Version 01.2014 BROWARD COLLEGE Page 1 of 15 SPECIFICATIONS FOR LAND SURVEYS January 2014 Broward College (BC) requires surveys to be performed from time to
More informationPART 4 STANDARD DRAWINGS FOR CONSTRUCTION
4.0. INTRODUCTION PART 4 STANDARD DRAWINGS FOR CONSTRUCTION In this document, Ivins City adopts the most recent edition (currently 2007), including all amendments, of the APWA Utah Chapter s Manual of
More informationEXTERIOR BUILDING, ROOFING, AND SITE IMPROVEMENTS
CONTRACT NUMBER: IFB-8-B006 ARCHITECT / ENGINEER : HURST-ROSCHE, INC. NO. LINOIS 62203 (68) 398-0890 -7 E. RANDLE ST./ N. FRITZ ST. 402 CHERRY ST., 404-406 ST. LOUIS ST. 502-506 DEE ST. 50-505 PLUM ST.
More informationSeptember 21, Mannik Smith Group 1771 North Dixie Highway Monroe, Michigan RE: LA Fitness City File No.: CVLP
CITY OF ANN ARBOR, MICHIGAN Public Services Area / Engineering 301 E. Huron Street, P.O. Box 8647 Ann Arbor, Michigan 48107 Phone (734) 794-6410 Fax (734) 994-1744 Web: www.a2gov.org Printed on recycled
More informationCHAPTER 11 SURVEY CADD
CHAPTER 11 SURVEY CADD Chapter Contents Sec. 11.01 Sec. 11.02 Sec. 11.03 Sec. 11.04 Sec. 11.05 Sec. 11.06 Sec. 11.07 Sec. 11.08 Sec. 11.09 Sec. 11.10 General Description of Survey File Contents of Survey
More informationBasic Surveying. Kabul, Afghanistan February 2011
Basic Surveying Kabul, Afghanistan February 2011 1 This watershed rehabilitation and restoration training was prepared by the U.S. Department of Agriculture (USDA) team of Jon Fripp (Civil Engineer USDA/NRCS),
More informationWATER STRUCTURE LEGAL & SURVEY TOPOGRAPHY/GRADING LANDSCAPE/VEGETATION
REVISION IDENTIFIER DETAIL LABEL CALLOUT LABEL 1 SHEET ABANDONED ASBESTOS CEMENT BALK OF WALK BEGINNING OF CURVE BENCH MARK BUILDING CAPACITY CAST IRON CATCH BASIN CATCH BASIN MANHOLE CENTER LINE CERTIFICATE
More informationACWWA DRAWING SUBMITTAL INFORMATION - UTILITY DRAWING REQUIREMENTS
ACWWA DRAWING SUBMITTAL INFORMATION - UTILITY DRAWING REQUIREMENTS Detailed construction drawings for system extensions shall be prepared for approval with a submittal to the Authority. All construction
More informationCONTRACT PLANS READING
CONTRACT PLANS READING A training course developed by the FLORIDA DEPARTMENT OF TRANSPORTATION This 2009 revision was carried out under the direction of Ralph Ellis, P. E., Associate Professor of Civil
More informationBabcock Ranch Water Utilities as operated by Town & Country Utilities and Babcock Ranch Irrigation
Babcock Ranch Water Utilities as operated by Town & Country Utilities and Babcock Ranch Irrigation Utility Acceptance Package THE FOLLOWING ITEMS MUST BE ON FILE WITH THE DISTRICT, PRIOR TO INSTALLATION
More informationStandard Plate 7036 is discontinued. It is replaced by Standard Plan Pedestrian Curb Ramp Details.
DEVELOPED BY: Design Standards ISSUED BY: Office of Program Management & Technical Support, Design Support Section TRANSMITTAL LETTER NO. (12-02) MANUAL: Standard Plates DATED: May 11, 2012 SUBJECT: Standard
More informationTwo Dimensional Motion Activity (Projectile Motion)
Two Dimensional Motion Activity (Projectile Motion) Purpose A projectile launched into the air either horizontally or at an angle represents Two Dimensional Motion. Using a launcher and two photogates,
More informationMinimum Drawing & Electronic Submittal Requirements For Record Drawings /As-Builts
Minimum Drawing & Electronic Submittal Requirements For Record Drawings /As-Builts PUBLIC WORKS ENGINEERING DEPARTMENT Revised: February 1, 2017 MINIMUM DRAWING REQUIREMENTS A. GENERAL PLAN REQUIREMENTS:
More informationFigure Sample field notes from cross-section leveling at first three stations shown in figure NAVEDTRA 14069A 15-26
method so that a point 100 feet away is within 1 foot of the true perpendicular. Measure elevations consisting of abrupt changes or breaks in the ground with a rod and level. Use a metallic tape to measure
More informationA. Suggested Tool List
These instructions are intended to be a basic guide to the installation and assembly of plate structures. Job site specific conditions may require other procedures. A Statement on Safety The assembly procedure
More informationAnne Arundel County Dept. of Inspections and Permits Storm Drain Checklist
Project Name Project Number Engineer Plans are to be designed based on the standards set forth in the Anne Arundel County Design Manual Standards and Specifications, and all other manuals as stipulated
More informationSURVEY GUIDANCE AND FORMS
Appendix H Clean Water Nashville Overflow Abatement Program GUIDANCE FOR DESIGN SURVEY GUIDANCE AND FORMS Version 2.0 April 2014 1 Table of Contents Section 1 Survey and Mapping... 1 1.1 Introduction...
More informationExisting and proposed contours at 1-foot intervals. The fill and/or excavation quantities in cubic yards.
PLAN REQUIREMENTS The plans for street design shall conform to the requirements of Sections 3 and 4. The following requirements shall also be shown on the plans where applicable. Road and Storm Plans:
More informationPre-Lab Questions. Physics 1BL MAGNETISM Spring 2009
In this lab, you will focus on the concepts of magnetism and magnetic fields and the interaction between flowing charges (electric current) and magnetic fields. You will find this material in Chapter 19
More informationMARQUETTE GREENWAY TRAIL
------ ------ TRAFFIC DATA A.A.D.T. (2010) A.A.D.T. (ED 2022) D.H.V. (2022) DIRECTIONAL DISTRIBUTION TRUCKS N/A N/A N/A N/A N/A DESIGN DATA DESIGN SPEED DESIGN CRITERIA FUNCTIONAL CLASSIFICATION RURAL/URBAN
More informationDFTG-1305 Technical Drafting Prof. Francis Ha
DFTG-1305 Technical Drafting Prof. Francis Ha Session 4 Orthographic Projection (or Multiview Projection) Reading: Geisecke s textbook: 14 th Ed. Chapter 5 p.162 15 th Ed. Chapter 6 p.232 Update: 18-0205
More informationModule 10. Assemblies and Corridors. Objectives
NOTES Module 10 Assemblies and Corridors In this module, you learn to work with assemblies and corridors in AutoCAD Civil 3D. Corridor models are used to represent road designs in Civil 3D. An assembly
More informationTown of Westlake Construction Plans Review Checklist
CONSTRUCTION PLANS CONTENTS All Drawings 24 x 36 Cover Sheet Final Plat Site Plan Demolition Plan Utility Plan Drainage Area Map and Calculations Paving Plan & Profile Sheets Storm Drain Plan & Profile
More informationSurvey Aspects of Automated Machine Control. The Changing Role of the Construction Surveyor / Inspector/Grader
Survey Aspects of Automated Machine Control The Changing Role of the Construction Surveyor / Inspector/Grader Charlie Brown, PE, PLS NCDOT State Location & Surveys Engineer AASHTO TIG AMG Work Group The
More informationSPECIFICATION WORDING RECOMMENDATIONS
SPECIFICATION WORDING RECOMMENDATIONS VOLUME 1; revision B PHOTO DOCUMENTATION OF SURFACE CONDITIONS FOR STREET AND PIPELINE PR0JECTS P-Tn RoutePHOTOS P-Tn RouteSCANS The following terms (as written) are
More informationINSTRUCTION MANUAL. In vivo Test Apparatus for 305B Muscle Lever Systems
INSTRUCTION MANUAL Model 806A In vivo Test Apparatus for 305B Muscle Lever Systems May 18, 2005, Revision 3 Copyright 2005 Aurora Scientific Inc. Aurora Scientific Inc. 360 Industrial Parkway S., Unit
More informationE:\Wilmot\DGN\14018pp.dgn 3/11/2015 6:49:16 AM
600-06 SHOULDER WIDENING FOR TYPE (SPECIAL) GUARDRAIL TERMINALS E:\Wilmot\DGN\08pp.dgn //05 6:9:6 AM E:\DGN\08SUP.dgn //05 ::55 PM E:\DGN\08SUP.dgn //05 :8:0 PM E:\DGN\08-WRG.dgn //05 :8:5 PM E:\DGN\08SM.dgn
More informationSuggested Traffic Signal Design Procedures Indefinite Delivery (ID) Contract Locations and Conventional Signal Contract Locations
Suggested Traffic Signal Design Procedures Indefinite Delivery (ID) Contract Locations and Conventional Signal Contract Locations MDOT SUGGESTED TRAFFIC SIGNAL DESIGN PROCEDURE INDEFINITE DELIVERY INSTALLATION
More informationProject: # Solano Community College District
ADDENDUM #02 Project: #16 007 Solano Community College District Horticulture Site Improvements Date: April 26, 2016 The following clarifications are provided based on questions received or changes in District
More informationACSA PLAN REVIEW CHECKLIST (Guideline Only) (4) Standard water and sewer general plan notes (attached).
ACSA PLAN REVIEW CHECKLIST (Guideline Only) Revised: December 3, 2015 General (1) Proper Title (2) Vicinity map on first sheet. (3) Date and latest plan revision. (4) Standard water and sewer general plan
More informationIF YOU WERE GIVEN the task of installing a drainage
Applying Profile Leveling Techniques IF YOU WERE GIVEN the task of installing a drainage system, how would you determine the slope needed to keep the water flowing? Profile leveling is an option. As part
More informationCrime Scene Mapping and Diagramming. Forensic Science
Crime Scene Mapping and Diagramming Forensic Science (insert pictures of Crime Scene sketches) Reasons why Crime Scene sketches are made: Permanent record of conditions of scene Can be used to reconstruct
More informationNSPS SURVEY TECHNICIAN CERTIFICATION PROGRAM LEVEL III SAMPLE EXAMINATION QUESTIONS
NSPS SURVEY TECHNICIAN CERTIFICATION PROGRAM LEVEL III SAMPLE EXAMINATION QUESTIONS NATIONAL SOCIETY OF PROFESSIONAL SURVEYORS July 2018 This booklet has been prepared to provide an example of what an
More informationChapter 23. Garage Construction
Chapter 23. Garage Construction 23.1 ESTABLISHING CHALK LINES 23.2 MEASURING AND CUTTING WALL PLATES 23.3 MARKING WINDOW & DOOR LOCATIONS ON EXTERIOR WALL PLATES 23.4 MARKING STUDS ON EXTERIOR WALL PLATES
More informationSECTION 100 PRELIMINARY CONSIDERATIONS & INSTRUCTIONS
SECTION 100 PRELIMINARY CONSIDERATIONS & INSTRUCTIONS 101 General 102 Submittal Requirements A. Initial Submittal B. Second Submittal 103 Plan Requirements A. Subdivisions B. Site Plans 104 Approval of
More informationDRAFTING STANDARDS 9.00 DRAFTING STANDARDS
DRAFTING STANDARDS 9.00 DRAFTING STANDARDS Final plans shall conform in appearance, format, accuracy, and quality to the standards used in the Springfield Engineering Division. Additional standards shall
More informationDOUBLE PROPORTION MADE COMPLEX
DOUBLE PROPORTION MADE COMPLEX Jerry L. Wahl Branch of Cadastral Surveys Bureau of Land Management California State Office 2800 Cottage Way, E-2841 Sacramento, California 95825 ABSTRACT Our ever increasing
More informationIntroduction to Total Station and GPS
Introduction to Total Station and GPS Dr. P. NANJUNDASWAMY Professor of Civil Engineering J S S Science and Technology University S J College of Engineering Mysuru 570 006 Introduction History GPS Overview
More informationCHECKLIST PRELIMINARY SUBDIVISION AND PRELIMINARY SITE PLAN
N/A Waiver (1) Four (4) copies of application form. (2) Fifteen (15) copies of plan (3) Subdivision/site plan application fee & professional review escrow deposit (4) Variance application fee & professional
More informationSANITARY SEWER SYSTEM ADMINISTRATIVE STANDARDS A.1 SANITARY SEWER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS
SANITARY SEWER SYSTEM ADMINISTRATIVE STANDARDS A.1 SANITARY SEWER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS All plans for sanitary sewer main extensions, improvements and modifications
More informationSECTION CONSTRUCTION PHOTOGRAPHS AND VIDEO RECORDING
SECTION 01321 CONSTRUCTION PHOTOGRAPHS AND VIDEO RECORDING PART 1 GENERAL 1.01 SUMMARY A. Employ a competent photographer to take construction record photographs for preconstruction conditions, periodically
More information