1 CITY OF ANN ARBOR, MICHIGAN Public Services Area / Engineering 301 E. Huron Street, P.O. Box 8647 Ann Arbor, Michigan Phone (734) Fax (734) Web: Printed on recycled paper September 21, 2017 Mannik Smith Group 1771 North Dixie Highway Monroe, Michigan Attention: Jeff Myers RE: LA Fitness City File No.: CVLP Ladies and Gentlemen: We have reviewed the construction plans dated August 22, 2017 for the public sanitary sewer, water main and sidewalk for the above referenced project, and have the following comments: 1. General Comments: a. As the project proposes a new domestic and fire service connection, the applicant must submit a backflow prevention and metering arrangement drawing for review prior to the start of construction. Approval of site or construction plans does not relieve the applicant of complying with City standards on backflow prevention and metering. It is the responsibility of the applicant to submit appropriate plans to Engineering for review when available, and no later than the start of building construction. The domestic meter arrangement drawing is included within this plan set. The fire service metering arrangement may also appear in this plan set, or may be submitted under separate cover.
2 b. The following notes shall be included on the plans: 2. Sheet 2 General Notes: i. The construction covered by these plans shall conform to the City of Ann Arbor Public Services Standard Specifications. ii. The omission of any standard details does not relieve the contractors of their obligation to construct items in complete accordance with the Public Services Standard Specifications. iii. Use of line stops is required where existing water mains cannot be sufficiently isolated to complete the work. The cost of any line stop installation is the responsibility of the developer and/or contractor. iv. Pavement markings disturbed due to pavement cuts or construction related activities shall be replaced as directed by Engineering. Replacement during construction of the project may be considered temporary, with final pavement marking restoration to occur at the end of the project. v. The contractor shall take all necessary precautions to protect the existing public road pavement. Damage to the public road pavement during the course of construction may necessitate milling and resurfacing of the damaged areas prior to issuance of the Certificate of Occupancy. a. General Construction Notes item 7 refers to the need for a preconstruction meeting. Note that the City requires a minimum of seven (7) days notification prior to holding a preconstruction meeting for public utility construction. b. General Construction Notes item 21 requires that changes to approved drawings be submitted to the owner. Please note that any changes to public utilities work after the construction plans have been approved by the City shall be submitted to the City for further review and shall be reapproved prior to commencement of construction of any affected utility. c. Sewer Notes item 6 refers to wyes for connections to the main. Please note that the City requires the connection to be made with a tee if the lead contains a riser. d. Sewer Notes item 7 references encasing utility crossings in concrete. The City does not accept concrete encasement as an acceptable means of accomplishing a utility crossing. In addition, sewers may cross one another and any franchise utility with 12 of vertical clearance. A vertical clearance of 18 is required only for water main crossings.
3 3. Sheet 6 Existing Conditions/Demolition Plan: a. A minimum of two benchmarks shall appear throughout this construction plan set. It appears that benchmarks 252 and 253 as shown on Sheet AL-1 are close enough to the subject site to appear on this sheet, Sheet 10 and Sheet 11. b. Removals callout 18 refers to abandoning the existing fire hydrant. Please note that the tee for the fire hydrant lead shall be removed from the main. c. Removals callout 19 refers to abandoning the existing 6 service lead. Please note that the tee for the service lead shall be removed from the main and the pipe repaired with a solid sleeve. d. Removals callout 22 refers to sanitary sewer removal. Note that sanitary sewer main may be abandoned in place per the requirements of the Public Services Standard Specifications, rather than removed. e. Removals callout 23 refers to removal of sanitary sewer manholes. Note that sanitary sewer manholes may be partially abandoned in place per the Public Services Standard Specifications. 4. Sheet 7 Construction Staging/Temporary Utilities Plan: A note on this sheet calls for connecting a temporary water service lead to the existing service lead for PNC Bank. This arrangement is not permissible. A temporary lead for the Sales Trailer shall be connected to the existing 10 water main adjacent to the project site. 5. Sheet 8 Site Plan: a. Existing infrastructure to remain appears too light on this sheet. Particularly, existing easements shall be made more visible on this sheet. b. A short sidewalk piece appears approximately half way across the building frontage that connects to the public sidewalk along North Maple Road. Provide spot elevations at the right-of-way line and the intersection with the existing public walk on both sides of the sidewalk so we may confirm that this connector walk meets ADA standards. The existing sidewalk at the interface with the proposed sidewalk shall be removed and replaced with a level landing (max. slope of 1% in each direction). Fifteen feet of existing sidewalk on either side of the level landing shall be removed and replaced with ADA compliant transitions to the level landing. c. The blow-up of the northern site sidewalk connection to the public sidewalk along North Maple Road shall be shown at a measureable scale, and spot elevations shall be provided at the proposed sidewalk intersection with the public right-of-
4 way, at its intersection with existing public sidewalk, and at changes of direction of the proposed sidewalk. The existing sidewalk at the interface with the proposed sidewalk shall be removed and replaced with a level landing (max. slope of 1% in each direction). Fifteen feet of existing sidewalk on either side of the level landing shall be removed and replaced with ADA compliant transitions to the level landing. 6. Sheet 10 Grading Plan: Revise Section A-A and B-B to indicate that the decorative fence detail appears on Sheet 25 rather than on Sheet Sheet 11 Utility Plan: a. Maple Road along the frontage of this project shall be labeled as North Maple Road on this and any other sheets where the public road name appears. b. Pool backwash water is shown discharging to an existing catch basin located near the northeast corner of the proposed building. Add a note to this sheet indicating how the backwash pump discharge has been de-chlorinated and confirm that it has been detained per the requirements of the Washtenaw County Water Resources Commissioner. c. A blow-up detail of the water service leads includes a label indicating that the service valve will be located 5 typ. off the public water main. The service valves shall be located 5 off the public water main. Remove the text typ. from this label. d. Sheet Notes item 3 states that a booster pump may be provided if necessary. The need for booster pumps on the domestic and fire service leads shall be determined definitively at this time. Revise this note as required. e. In Fire Protection Notes item 2, add City of Ann Arbor prior to Engineering, and replace are near the end of this note with may be. f. Note that the existing fire hydrant may be used for relocation if it meets current city standards and is in good condition. 8. Sheet 12 Easements: a. Legal descriptions for the utility easements shall be submitted in Word format, and the easement drawing shall be submitted as an 8.5 x11 PDF. Sketches and descriptions are not required to be submitted within construction plan sets.
5 b. Show the existing sanitary sewer easement on the proposed sanitary sewer easement drawing and descriptions. The bearings and distances do not need to be shown, but the easement lines shall be shown. c. If any portion of the existing sanitary sewer easement will be vacated, a drawing in PDF format and legal description(s) in Word format describing the portion(s) of existing easements to be vacated shall be submitted to the City for review. 9. Sheet 13 ROW Dedication/Sidewalk Easement: Show the existing sidewalk within the sidewalk easement drawing so we may verify that the proposed easement properly encompasses the existing sidewalk. 10. Sheet 14 Drainage Map and Calculations: Confirm that the pool backwash water discharge has been properly accounted for in the calculations shown on this sheet. 11. Sheet 15 Sanitary Plan & Profile: a. Station the centerline of the proposed pipe with Sta appearing at the connection to the public sanitary sewer in North Maple Road. Full stations shall be labeled (i.e. 1+00, 10+00, etc.). It is preferred for the station labels to be perpendicular to the main. b. Full stations shall appear above or below the profile grid. c. A structure/casting schedule is required for sanitary sewer main plan/profile sheets. The schedule shall contain the structure number and station, rim elevation, invert elevations, structure depth, and casting and cover type. d. Remove the sheet Note from this sheet. Concrete cradles are not permissible. e. The proposed 6 sanitary sewer lead shall be labeled with the lead length, pipe slope and the lead material in addition to the invert at the end of the lead. f. Sanitary sewer structures shall be labeled in the plan view with the station, rim elevation, and invert elevations in addition to the structure number. g. The horizontal and vertical scale of the profile shall match the scale of the plan view. As the sheet is currently shown at 20-scale, the vertical scale for the profile shall be 1 = 2. h. To improve visibility of the profile, remove the sand hatching and provide dimensions or beginning and end stations for standard trench detail applications.
6 i. Label utility crossings with the type of utility crossed, station of the crossing, invert or top of pipe elevation of the crossed utility, and the vertical clearance between the utilities. j. A storm sewer crossing appears to be missing between SMH1 and SMH2. k. Invert elevations changes 24 or greater require an external drop at the manhole. Drop connections shall be labeled in the plan and profile view. l. The minimum slope for 8 sanitary sewer pipe is 0.50%, with 0.60% required for terminal sanitary sewer runs. The slope between SMH1 and SMH2 shall be a minimum of 0.60%, and the minimum slope for all runs between SMH2 and SMH6 shall be 0.05%. m. Sanitary sewer structure labels in the profile shall include the station. n. A 0.20 drop is required between the upstream and downstream inverts in structure SMH2. o. Label existing lead inverts as ex. or existing rather than changing the size or shade of the text. p. The distance between SMH1 and SMH2 scales as 105 LF in the profile, however the length is labeled 104 LF in the plan and the profile. Please correct. q. The distance between SMH2 and SMH3 scales as 159 LF in the plan view, however the length is labeled 160 LF in the plan and the profile. Please correct. 12. Sheet 17 Water Plan & Profiles: a. The Domestic Water Service Detail shall be labeled with the maximum spacing between the building wall to the first isolation valve (24, max.), the required distance between the upstream isolation valve and the meter (5 pipe diameters) and the required distance between the meter and the downstream isolation valve (3 pipe diameters). b. Centerline stationing shall begin with Station 0+00 at the lead connection point to the public water main. Label Station 0+00 on the plan view of each lead. c. The horizontal and vertical scale of the profile shall match the scale of the plan view. In addition, this sheet shall be submitted at 20-scale, or 40-scale, with the vertical scale in the profile as either 1 =2 or 1 =4 respectively.
7 d. Please note that 5.5 is the typical depth of bury, not the minimum. Revise each depth of bury label in each profile accordingly. e. Dimension restrained joint lengths in the profiles. Submit DIPRA restrained joint calculations as a PDF separate from the plans. It is permissible to restrain all joints; however, the notes located near the lower right-hand corners of each profile shall be revised to clarify that restraint is for the whole lead, rather than for this length of pipe. f. Label the size of the sanitary sewer in each plan view. In addition, label the grey line located a few feet south of the sanitary sewer. g. Label the gate valves for the service leads in the plan view with rim elevation, station and size of valve. In addition, show and label the gate valves in the profile. The profile labels shall include the rim elevation, top of pipe elevation, valve size and station. In both views, indicate within the labels if the valves will be constructed in wells or boxes. h. Indicate within the label for the proposed 10 main line valve if the valve will be constructed with a well or a box. In addition, the rim and top of pipe elevations shall be included within the label for this structure. i. Revise the service lead tee labels in the plan and in the profile to show the correct size of the existing water main, which is 10. j. Profile each water service lead separately. Currently, the profile only contains labels for the 6 fire service lead appurtenances. The appurtenances for the 4 domestic service lead shall also be labeled in the profile. k. It is noted that a minimum of 12 of vertical clearance is required between water main and franchise utilities such as communications cables, rather than the 18 required for crossing sewers. l. The water service leads exceed 5.5 of bury for the majority of the leads. The depth of bury shall be kept as near 5.5 of bury as is practical. m. Label the proposed pipe material within the fire hydrant lead profile. n. Revise the fire hydrant lead tee labels in the plan and profile to show the correct size of the existing water main, which is 10. o. The depth of the fire hydrant operating valve shall be 5.5 below grade.
8 Please submit three (3) sets of revised paper plans along with correspondence indicating how each comment was addressed, as well as any other plan changes. In addition, upload the revised plans and response letter in PDF format to etrakit project file CVLP The MDEQ Water System Construction Permit may be submitted in Word format. Very truly yours, Engineering Nichole Woodward, P.E., Project Manager AH:nw (S:\Engineering\Private Development\Comments\LA Fitness\Construction Review 1.docx) C: Cresson Slotten, P.E., Systems Planning Manager (via ) Private Development Team (via ) David Clemons, CES Supervisor (via ) Mark Salma, Brixmor Property Group (via )
Anne Arundel County Dept. of Inspections and Permits Water Sewer Plan Checklist
Project Name Project Number Engineer Plans are to be designed based on the standards set forth in the Anne Arundel County Design Manual Standards and Specifications, and all other manuals as stipulated
More informationUTILITY AND STREET CONSTRUCTION PLAN REQUIREMENTS SECTION 1
UTILITY AND STREET CONSTRUCTION PLAN REQUIREMENTS SECTION 1 ENGINEERING STANDARDS FOR UTILITY AND STREET CONSTRUCTION PLANS MARCH 2014 CONSTRUCTION PLAN SHEET FORMAT REQUIREMENTS REPRODUCIBLE MYLAR 1.
More informationPlan Submittal and Review Checklist
Improving quality of life today creating a better tomorrow Plan Submittal and Review Checklist Version 1.2 September 4, 2017 Contents Overview... 2 Plan Submittal Checklist... 2 Plan Review Checklist -
More informationBRASELTON WATER AND WASTEWATER DEPARTMENT CONSTRUCTION PLAN REVIEW CHECKLIST May 2006
Project Name: BRASELTON WATER AND WASTEWATER DEPARTMENT CONSTRUCTION PLAN REVIEW CHECKLIST May 2006 Phase: Unit: # Lots: Development Type (residential, commercial, industrial, etc.) Braselton Project No.
More informationCITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division STORM DRAIN IMPROVEMENT PLAN REVIEW CHECKLIST
CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil ing Division STORM DRAIN IMPROVEMENT PLAN REVIEW CHECKLIST The following checklist consists of the minimum requirements for preparation
More informationCITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division SANITARY SEWER IMPROVEMENT PLAN REVIEW CHECKLIST
CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil ing Division SANITARY SEWER IMPROVEMENT PLAN REVIEW CHECKLIST The following checklist consists of the minimum requirements for
More informationExisting and proposed contours at 1-foot intervals. The fill and/or excavation quantities in cubic yards.
PLAN REQUIREMENTS The plans for street design shall conform to the requirements of Sections 3 and 4. The following requirements shall also be shown on the plans where applicable. Road and Storm Plans:
More informationNEWTON COUNTY WATER AND SEWERAGE AUTHORITY RESIDENTIAL, COMMERCIAL, INSTITUTIONAL AND INDUSTRIAL SUBDIVISIONS CONSTRUCTION PLANS CHECK LIST
NEWTON COUNTY WATER AND SEWERAGE AUTHORITY RESIDENTIAL, COMMERCIAL, INSTITUTIONAL AND INDUSTRIAL SUBDIVISIONS CONSTRUCTION PLANS CHECK LIST Project Name Checked By Date Designer Check List marks to be
More informationB17. Sewer Site Plans BULLETIN
BULLETIN B17 Revised 5/2/2016 Sewer Site Plans Public Works This bulletin is designed to assist you in submitting the required documentation for sewer site plans to the Pierce County Sewer Division in
More informationAnne Arundel County Dept. of Inspections and Permits Storm Drain Checklist
Project Name Project Number Engineer Plans are to be designed based on the standards set forth in the Anne Arundel County Design Manual Standards and Specifications, and all other manuals as stipulated
More informationLincoln County Public Works Water and Sewer Submittal Application
Lincoln County Public Works Water and Sewer Submittal Application 1. Date Submitted: Submittal Number: 2. Project Name of Project: 3. Project Address/Location: 4. Owners Name: Address: Contact Number:
More informationSECTION 100 PRELIMINARY CONSIDERATIONS & INSTRUCTIONS
SECTION 100 PRELIMINARY CONSIDERATIONS & INSTRUCTIONS 101 General 102 Submittal Requirements A. Initial Submittal B. Second Submittal 103 Plan Requirements A. Subdivisions B. Site Plans 104 Approval of
More informationClarifications in italics added July 2018
SECTION 10000 RECORD DRAWING CHECKLIST Clarifications in italics added July 2018 All entities who construct public infrastructure, private streets, private storm drain collection systems and travel lanes,
More informationSECTION III SUBMITTALS AND APPROVALS
SECTION III SUBMITTALS AND APPROVALS In order to expedite the approval process of new water distribution system and sanitary sewer collection system extensions, the Hilton Head No. 1 Public Service District
More informationSewer Line Extension Permit Design Checklist
CHECKLIST C1 Revised 4/7/2017 Sewer Line Extension Permit Design Checklist DISCLAIMER - This checklist is provided to Consulting Engineers for the express purpose of assisting them in compiling sewer line
More informationCity of Massillon Site Plan Checklist
City of Massillon Site Plan Checklist The following information MUST be included with all Site Plans submitted for review and processing in order to constitute a complete Site Plan Package. Incomplete
More informationCITY OF MUSKEGO DRAFTING STANDARDS
CITY OF MUSKEGO DRAFTING STANDARDS GENERAL - These standards apply to all plans. 1. Plans must be prepared on sheets measuring 36 inch across and 22 inch to 24 inch high unless otherwise specified under
More informationCITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA (360)
CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA 98501 (360) 754-4180 Email: cdd@ci.tumwater.wa.us WATER-SEWER-STREET-STORM (IN CITY) Submittal Checklist TUM - RCVD BY DATE STAMP APPLICANT INFORMATION
More information10010 RECORD DRAWING INFORMATION
SECTION 10000 RECORD DRAWING CHECK LIST All entities who construct public infrastructure, private streets, private storm drain collection systems and travel lanes, shall submit to the Town of Cary Engineering
More informationMINIMUM DRAWING REQUIREMENTS FOR WATER AND SEWER LINE PROJECTS
Public Works Department Water & Wastewater Services WATER & WASTEWATER ENGINEERING DIVISION 2555 West Copans Road Pompano Beach, Florida 33369 954-831-0745 FAX 954-831-0798/0925 MINIMUM DRAWING REQUIREMENTS
More information1.1 GENERAL RECORD DRAWING REQUIREMENTS
Page 1 of 5 VILLAGE OF ROMEOVILLE RECORD DRAWINGS CHECKLIST PART I GENERAL Record drawings are required to provide a means of schematic verification that the intent of the approved engineering design has
More informationCITY OF LOMPOC DEVELOPMENT ASSISTANCE BROCHURE ENCROACHMENT PERMITS AND PUBLIC IMPROVEMENT PLANS
CITY OF LOMPOC DEVELOPMENT ASSISTANCE BROCHURE E-10 ENCROACHMENT PERMITS AND PUBLIC IMPROVEMENT PLANS The City of Lompoc has determined that the Engineering Division should administer and issue Encroachment
More informationACSA PLAN REVIEW CHECKLIST (Guideline Only) (4) Standard water and sewer general plan notes (attached).
ACSA PLAN REVIEW CHECKLIST (Guideline Only) Revised: December 3, 2015 General (1) Proper Title (2) Vicinity map on first sheet. (3) Date and latest plan revision. (4) Standard water and sewer general plan
More informationLOWNDES COUNTY ENGINEERING PLAN REVIEW CHECKLIST. Design Professional: Phone: Developer: Phone: 2 nd Submittal (No Fee)
MEMORANDUM MICHAEL B. FLETCHER, P.E. COUNTY ENGINEER 327 N. Ashley Street Valdosta, GA 31601 Telephone: (229) 671-2424 Fax: (229) 245-5299 mfletcher@lowndescounty.com LOWNDES COUNTY ENGINEERING PLAN REVIEW
More informationCITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division STREET/ALLEY IMPROVEMENT PLAN REVIEW CHECKLIST
CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil ing Division STREET/ALLEY IMPROVEMENT PLAN REVIEW CHECKLIST The following checklist consists of the minimum requirements for preparation
More information3. The PAC (Permit Application Center) will notify the design professional of plan review results.
Planning and Development Dept. Infrastructure Division P.O. Box 11706, or 155 Johnston Street Rock Hill, South Carolina 29731-1706 Phone: 803-329-5515 FAX: 803-329-7228 www.cityofrockhill.com AS-BUILT
More informationACWWA DRAWING SUBMITTAL INFORMATION - UTILITY DRAWING REQUIREMENTS
ACWWA DRAWING SUBMITTAL INFORMATION - UTILITY DRAWING REQUIREMENTS Detailed construction drawings for system extensions shall be prepared for approval with a submittal to the Authority. All construction
More informationKC Water Rules and Regulations For Water Main Extensions and Relocations
KC Water Rules and Regulations For Water Main Extensions and Relocations MAY 2017 NOTE: Changes from 2016 are highlighted in yellow and appear on Pages 5, 8, 10-11, 13, and 15. Additional changes made
More informationCHECKLIST PRELIMINARY SUBDIVISION AND PRELIMINARY SITE PLAN
N/A Waiver (1) Four (4) copies of application form. (2) Fifteen (15) copies of plan (3) Subdivision/site plan application fee & professional review escrow deposit (4) Variance application fee & professional
More informationAPPENDIX 1: CONSTRUCTION PLAN CHECKLIST
APPENDIX 1: CONSTRUCTION PLAN CHECKLIST October 2017 APPENDIX A APPENDIX 1: CONSTRUCTION PLAN CHECKLIST ALL PLANS Plans on 24-inch by 36-inch paper (Originals shall be transmitted on a CD as an electronic
More information1. Land survey Work. 2. Civil and Structural engineering services.
SECTION 01050 FIELD ENGINEERING PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division-1 Specification
More informationCHAPTER 11. Plan Standards
CHAPTER 11 Plan Standards A. Introduction The city requires uniform public improvement plans for ease of record keeping and understanding. The following standards govern most plan submittals to the city.
More informationMinimum Drawing & Electronic Submittal Requirements For Record Drawings /As-Builts
Minimum Drawing & Electronic Submittal Requirements For Record Drawings /As-Builts PUBLIC WORKS ENGINEERING DEPARTMENT Revised: February 1, 2017 MINIMUM DRAWING REQUIREMENTS A. GENERAL PLAN REQUIREMENTS:
More informationB-PERMIT PLAN CHECK MANUAL
B-PERMIT PLAN CHECK MANUAL 5. SEWER PLANS Sewer Plans are usually submitted in conjunction with Street Plans to meet the requirements of conditions imposed on a Planning or Zoning action. In some cases
More informationGrease Interceptor Design Checklist
CHECKLIST C2 Revised 5/2/2016 Grease Interceptor Design Checklist Public Works DISCLAIMER - This checklist is provided to Consulting Engineers for the express purpose of assisting them in compiling private
More informationCharlotte County Utilities DESCRIPTION
As-built Drawings / Surveyor 1. Electronic copy of survey data in tabular form of the utility assets 2. A signed and sealed letter with the following statement: "I hereby certify that the as-built location
More informationPLANNING AND DEVELOPMENT
OVERVIEW Effective January 1, 1992 all applications for multi-family residential and all non-residential building permits require site plan approval before permit issuance. All new developments and existing
More informationSECTION 2.0 PREPARATION OF MASTER PLANS, CONSTRUCTION PLANS, AND RECORD DRAWINGS
SECTION 2.0 PREPARATION OF MASTER PLANS, CONSTRUCTION PLANS, AND RECORD DRAWINGS 2.1 MASTER PLAN 2.1.1 A Master Plan for water, wastewater, and/or reclaimed water is required for all residential or commercial
More informationTown of Westlake Construction Plans Review Checklist
CONSTRUCTION PLANS CONTENTS All Drawings 24 x 36 Cover Sheet Final Plat Site Plan Demolition Plan Utility Plan Drainage Area Map and Calculations Paving Plan & Profile Sheets Storm Drain Plan & Profile
More informationWATER & SEWER CONSTRUCTION SITE PLAN DESIGN SUMMARY COMMERCIAL & RESIDENTIAL
WATER & SEWER CONSTRUCTION SITE PLAN DESIGN SUMMARY COMMERCIAL & RESIDENTIAL This summary is not all inclusive of the requirements set forth by the York County Planning & Development Services, York County
More informationAppendix C Construction Details
7172 Kennedy Road Warrenton, Virginia 20187 Appendix C Construction Details November 2017 TABLE OF CONTENTS THRUST BLOCKS Anchorage for 11 1/4 o, 22 1/2 o & 45 o Upper Vertical Bends... AV 01 Buttresses
More informationSECTION 9.00 AS-BUILT DRAWING REQUIREMENTS SUB-INDEX
SECTION 9.00 AS-BUILT DRAWING REQUIREMENTS SUB-INDEX 9.00 AS-BUILT DRAWING REQUIREMENTS 9.01 As-Built Check List 1 Supp 1 2016 Supp # 2 Aug. 2017 AS-BUILT DRAWING REQUIREMENTS As-Built Review Fee is $200.00
More informationSurvey Requirements. Design Guidelines and Standards. June Office of the University Architect
Design Guidelines and Standards Survey Requirements June 2004 Office of the University Architect Construction Management P.O. Box 210181 Cincinnati, Ohio 45221-0181 Table of Contents Survey Requirements
More informationB.2 MAJOR SUBDIVISION PRELIMINARY PLAN CHECKLIST
B.2 MAJOR SUBDIVISION PRELIMINARY PLAN CHECKLIST YES* GENERAL SUBMISSION ITEMS Does the submission include: 1. Thirteen (13) copies of completed Application Form? 2. Thirteen (13) copies of the Preliminary
More informationOil-Water Separator Design Checklist
CHECKLIST C3 Revised 5/2/2016 Oil-Water Separator Design Checklist DISCLAIMER - This checklist is provided to Consulting Engineers for the express purpose of assisting them in compiling private oil-water
More information3. DESIGN SPECIFICATIONS
Schedule H to Bylaw 7452, Subdivision Bylaw Page 10 3. DESIGN SPECIFICATIONS 3.1 General 3.1.1 The Design Specifications apply to the design of sanitary sewers, storm drains, waterworks, roadways, and
More informationPublic Works City of Lebanon, Tennessee; Department of Public Works
SECTION 1 GENERAL 1. DEFINITIONS Public Works City of Lebanon, Tennessee; Department of Public Works City City of Lebanon, Wilson County, Tennessee City Engineer Employed by the City of Lebanon, Registered
More informationCITY OF REEDLEY NEW DEVELOPMENT PLAN REVIEW CHECK LIST
CITY OF REEDLEY NEW DEVELOPMENT PLAN REVIEW CHECK LIST Tract Number and Subdivision Name: Engineering Firm: Contact Person: Address: City: State: Zip: Phone No. Fax No. Assessor s Parcel Number(s) Tentative
More informationPorter County Plan Commission
Plan Type: Development Plan Administrative DRC PC Primary Plan Administrative DRC PC Secondary Plat/Replat Administrative DRC PC PUD Conceptual Detailed Final Project Information Project Name: Developer
More informationTOWN of LAKESHORE SITE PLAN CHECKLIST
TOWN of LAKESHORE SITE PLAN CHECKLIST Last Revised December 17, 2009 Project Name: Project Location: Date Submitted: Name Phone Number E-mail Address Owner: Contractor/ Engineer: ( ) ( ) Applicant: ( )
More informationList of Figures. List of Forms
City of Columbia Engineering Regulations PART 1: SUBMISSION OF PLANS Table of Contents Paragraph Description Page No. 1.1 General 1-1 1.2 Engineer s Report 1-1 1.3 Plans 1-3 1.4 Revisions to Approved Plan
More informationSUBDIVISION APPLICATION FOR DRT SUBMITTAL PUBLIC WORKS DEPARTMENT
Case #: SUBDIVISION APPLICATION FOR DRT SUBMITTAL PUBLIC WORKS DEPARTMENT 171 North Ross Street, Suite 200 Auburn, AL 36830 (334) 501-3000 ~ Fax: (334) 501-7294 Applicant Name: Mailing Address: Email Address:
More informationAuthorized Agent: City of Manassas Check List Attached: Contact: Address: Phone Number: Fax Number: Developer s Name: Phone Number:
CITY OF MANASSAS DEPARTMENT OF COMMUNITY DEVELOPMENT DEVELOPMENT SERVICES DIVISION 9027 Center Street Room 201 Manassas, Virginia, 20110 Phone: 703-257-8278 Fax: 703-257-5831 Application Date: APPLICANT
More informationWashington County Road Engineering Plan Submittal/Review Checklist
Washington County Road Engineering Plan Submittal/Review Checklist Washington County Land Use Case File Number: Parcel(s): Developer/Owner Name(s): Developer/Owner E-mail(s): The following elements should
More informationGuidelines and Checklist For SAWS Sanitary Sewer. Developmental Engineering Division
Guidelines and Checklist For SAWS Sanitary Sewer Developmental Engineering Division INITIAL CONSIDERATIONS UTILITY SERVICE AGREEMENT Utility Service Agreement A Utility Service Agreement (USA) will be
More informationSANITARY SEWER SYSTEM ADMINISTRATIVE STANDARDS A.1 SANITARY SEWER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS
SANITARY SEWER SYSTEM ADMINISTRATIVE STANDARDS A.1 SANITARY SEWER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS All plans for sanitary sewer main extensions, improvements and modifications
More informationBabcock Ranch Water Utilities as operated by Town & Country Utilities and Babcock Ranch Irrigation
Babcock Ranch Water Utilities as operated by Town & Country Utilities and Babcock Ranch Irrigation Utility Acceptance Package THE FOLLOWING ITEMS MUST BE ON FILE WITH THE DISTRICT, PRIOR TO INSTALLATION
More informationCITY OF APACHE JUNCTION DEVELOPMENT SERVICES CIVIL ENGINEERING PLAN REVIEW CHECKLIST PROJECT: LOCATION:
CITY OF APACHE JUNCTION DEVELOPMENT SERVICES CIVIL ENGINEERING PLAN REVIEW CHECKLIST PROJECT: LOCATION: LOG NO.: LEGEND REVIEW REVIEWED BY DATE / - Requirement satisfied 1 O Requirement not satisfied 2?
More informationAPPLICATION FOR SITE PREPARATION PERMIT
Engineering Division 550 Landa Street New Braunfels, Texas 78130 (830) 221-4020 1. Subdivision/Plat Name: Location Description/ Nearest Intersection: Acreage: APPLICATION FOR SITE PREPARATION PERMIT No.
More informationSTATE UNIVERSITY CONSTRUCTION FUND
DIRECTIVE 1C-12 Issue date: August 2012 1. General SURVEY, MAPPING AND UTILITY LOCATING This Directive has been developed as a general guide for the survey and mapping effort required for Fund projects.
More informationCity of Vaughan Engineering Department DESIGN STANDARD DRAWINGS
City of Vaughan Engineering Department DESIGN STANDARD DRAWINGS March 2004 STANDARD DRAWINGS Partners With The Environment March 2004 FORWARD The March 2004 version of the City of Vaughan Design Standard
More informationREQUIREMENTS. for ENGINEERING SERVICES PUBLIC CONSTRUCTION PROJECTS
REQUIREMENTS for ENGINEERING SERVICES on PUBLIC CONSTRUCTION PROJECTS April, 2007 David W. Johnson Senior Engineer Design & Construction Requirements for Engineering Services on Public Construction Projects
More informationPlan Preparation Checklist
Appendix D Plan Preparation Checklist It is the responsibility of the Designer to complete and submit this checklist along with all required drawings for OUC (EFP) Review. All drawings submitted for OUC
More informationHUSSEY GAY BELL SAVANNAH, GEORGIA
HUSSEY GAY BELL SAVANNAH, GEORGIA ------------------------------------------------------------------------------------------------------------ ADDENDUM NO. 3 TO THE CONTRACT DOCUMENTS AND TECHNICAL SPECIFICATIONS
More informationZoning District: R-1, R-2, and R-4 Applicant: Exeter Rose Farm, LLC, 953 Islington Street #23D Portsmouth, NH 03801
2220.00, Town Planner Town Planning Office, Town of Exeter 10 Front Street Exeter, NH 03833 Re: Exeter Rose Farm Subdivision Design Review Engineering Services Exeter, New Hampshire Site Information: Tax
More informationDEVELOPMENT PLAN CHECKLIST
Project Identification Information: DEVELOPMENT PLAN CHECKLIST 1.0 GENERAL 1.1 Additional information as required by specific Land Use 1.2 All sheets to include sheet number ( of ) 1.3 Seal and signature
More informationGENERAL RESPONSIBILITIES, REQUIREMENTS AND PROCESSES 1.1 ENGINEER OF RECORD REQUIREMENTS & RESPONSIBILITIES. A. Requirements
SECTION 1 GENERAL RESPONSIBILITIES, REQUIREMENTS AND PROCESSES 1.1 ENGINEER OF RECORD REQUIREMENTS & RESPONSIBILITIES A. Requirements The Engineer of Record for all projects shall be a Professional Engineer
More information5.0 PLAN FORMAT AND REQUIREMENTS WATER, RECYCLED WATER AND SEWER
5.0 PLAN FORMAT AND REQUIREMENTS WATER, RECYCLED WATER AND SEWER The Developer s engineer shall prepare system improvement plans that are clear, concise, and meet Western s standards. A set of plans that
More informationCommunity & Economic Development Department Planning Division Frederick Street PO Box 8805 Moreno Valley, CA SUBMITAL REQUIREMENTS
Community & Economic Development Department Planning Division 14177 Frederick Street PO Box 8805 Moreno Valley, CA 92552-0805 (951) 413-3206 Fax (951) 413-3210 SECOND UNITS Completed and Signed Project
More informationSECTION 3 IMPROVEMENT PLAN REQUIREMENTS
SECTION 3 IMPROVEMENT PLAN REQUIREMENTS CONTENTS Page 3-1 Digital Submittals 3-2 3-2 Paper Size and Scale 3-2 3-3 Drafting Standard 3-2 3-4 Title Sheet 3-2 3-5 Title Block 3-3 3-6 Drainage, Sewer, Water,
More informationSite Plan Review Application. Interest in the Property (e.g. fee simple, land option, etc.)
1. Identification CITY OF FENTON 301 South Leroy Street Fenton, Michigan 48430-2196 (810) 629-2261 FAX (810) 629-2004 Site Plan Review Application Project Name Applicant Name Address City/State/Zip Phone
More informationRecord Drawing Standards for Projects Version 2.1
for Projects Version 2.1 Updated September 21, 2016 Department: Spatial Data Group Engineering & Maintenance 1. INTRODUCTION... 1 2. GENERAL STANDARDS... 1 2.1 Drawing Standards... 1 2.2 Digital Submission
More informationEngineering and Construction Services Division Construction Drawings for Sewers and Watermains. T No. Revision T No. Revision Remarks All T drawings
Engineering and Construction Services Division Construction Drawings for Sewers and Watermains Revision No. 8 April All T drawings New title block for each drawing is now standardized. Revision numbers
More informationSTREETSCAPE FEASIBILITY TERMS OF REFERENCE
Introduction STREETSCAPE FEASIBILITY TERMS OF REFERENCE As outlined in the Official Plan, Section 9, Build A Desirable Urban Form, Mississauga will transform the public realm to create a strong sense of
More informationSTANDARD BID ITEM NUMBERS
10701 TRAFFIC CONTROL LUMP SUM 10702 Traffic Control for Storm Sewer Installation LUMP SUM 10703 Traffic Control for Water Main Installation LUMP SUM 10704 Traffic Control for Sanitary Sewer Installation
More informationOnslow Water & Sewer Authority
Onslow Water & Sewer Authority REQUIREMENTS FOR SITE PLAN SUBMITTALS THAT DO NOT INCLUDE EXTENSIONS OF WATER/SEWER MAINS BY OWNERS/DEVELOPERS/CONTRACTORS February 28, 2017 (Revised) Required Items for
More informationMAJOR GRADING PLAN CHECKLIST
MAJOR GRADING PLAN CHECKLIST PUBLIC WORKS DEPARTMENT / ENGINEERING DIVISION 8130 Allison Avenue, La Mesa, CA 91942 Phone: (619) 667-1166 Fax: (619) 667-1380 Grading plans shall address both rough grading
More informationPlan Review and Standards
Plan Review and Standards Minnesota Rules, part 4720.0010, states that prior to the installation, alteration, or extension of any water supply infrastructure, plans and specifications must be submitted
More informationSubdivision Application Checklist
City of Portsmouth, New Hampshire Subdivision Application Checklist This subdivision application checklist is a tool designed to assist the applicant in the planning process and for preparing the application
More informationHAMILTON SOUTHEASTERN UTILITIES, INC. SANITARY SEWER COMPLETION SPECIFICATIONS
HAMILTON SOUTHEASTERN UTILITIES, INC. SANITARY SEWER COMPLETION SPECIFICATIONS The ideas, designs, drawings and concepts contained herein are the exclusive intellectual property of Sanitary Management
More informationSCHEDULE 10 ENGINEERING DRAWING SUBMISSION
SCHEDULE 10 ENGINEERING DRAWING SUBMISSION Subdivision, Development and Servicing Bylaw No. 1535 10. ENGINEERING DRAWING SUBMISSIONS TABLE OF CONTENTS 1.0 General 3 1.1. Introduction 3 1.2. General Requirements
More informationProject Name: County File No.: Checked by: For: Date:
Project Name: County File No.: Checked by: For: Date: Print name Firm or agency Items noted in the checklist shall be considered the minimum amount of information necessary for submission of construction
More information50.24 Type, Size and Location Plans for Culverts, Bridges and Culvert Bridges
50.24 Culverts, Bridges and Culvert Bridges Type, Size and Location (T, S & L) Plans shall be required for all Bridges, Culvert Bridges and Culverts of eight-foot (8') clear span or greater as follows:
More informationChapter 13 Plan Submittals
Chapter 13 Plan Submittals U30013.DOC 02/01/07 Chapter 13 Plan Submittals Section Topic Page 13.1 General 13.1 13.2 Subdivision Plans 13.1 13.3 Capital Improvement Project Plans 13.12 U30013.DOC 02/01/07
More informationPART 4 STANDARD DRAWINGS FOR CONSTRUCTION
4.0. INTRODUCTION PART 4 STANDARD DRAWINGS FOR CONSTRUCTION In this document, Ivins City adopts the most recent edition (currently 2007), including all amendments, of the APWA Utah Chapter s Manual of
More informationDIVISION A GENERAL AND DRAFTING ENGINEERING STANDARDS
CITY OF ALBANY DEPARTMENT OF PUBLIC WORKS DIVISION A GENERAL AND DRAFTING ENGINEERING STANDARDS Prepared By PUBLIC WORKS DEPARTMENT ALBANY, OREGON 97321 Telephone: (541) 917-7676 TABLE OF CONTENTS A 1.00
More informationCITY OF LA MARQUE CHAPTER GRAPHIC REQUIREMENTS CONSTRUCTION PLAN AND MISCELLANEOUS REQUIREMENTS
CITY OF LA MARQUE CHAPTER 2 -------------------------------------------- GRAPHIC REQUIREMENTS CONSTRUCTION PLAN AND MISCELLANEOUS REQUIREMENTS CHAPTER 2 ------------------------------------------------
More informationAPPENDIX 4. Checklists. Township of King Design Criteria and Standard Detail Drawings
APPENDIX 4 Checklists Township of King Design Criteria and Standard Detail Drawings Township of King Design Criteria and Standard Detail Drawings APPENDIX 4 CHECKLISTS Engineering Submissions : The following
More informationSection 101. Street Design
Section 101 Street Design This section establishes the uniform policies and procedures for the preparation of street design plans and construction requirements in the City of Irvine. It is not intended
More informationUPDATE LOG FOR STANDARD DRAWINGS Item(s) Changed 6/1/18 STANDARD DRAWINGS
Date 6/1/18 STANDARD DRAWINGS UPDATE LOG FOR STANDARD DRAWINGS Item(s) Changed WATER STANDARD DRAWINGS Title Drawing Number Current Date Fire Hydrant and Appurtenance Locations, Improved Streets with Curb
More informationPRECISE GRADING PLAN CHECKLIST
PRECISE GRADING PLAN CHECKLIST PUBLIC WORKS DEPARTMENT / ENGINEERING DIVISION 8130 Allison Avenue, La Mesa, CA 91942 Phone: 619. 667.1166 Fax: 619. 667.1380 Grading plans shall address both rough grading
More informationEssential Skills: Reading and Interpreting Maps and Plans
Essential Skills: Reading and Interpreting Maps and Plans Prepared for: NEW YORK STATE PLANNING FEDERATION April 14, 2015 Prepared by: BME ASSOCIATES Peter G. Vars, P.E. Stages of Plan Review Concept /
More informationCONCEPT REVIEW GUIDELINES
Department of Planning & Community Development @ Jefferson Station 1526 E. Forrest Avenue Suite 100 East Point, GA 30344 404.270.7212 (Phone) 404.765.2784 (Fax) www.eastpointcity.org CONCEPT REVIEW GUIDELINES
More informationSECTION 095 SPECIFICATIONS DETAIL DRAWINGS. Index of Detail Drawings
SECTION 095 SPECIFICATIONS DETAIL DRAWINGS Index of Detail Drawings Flat Top Manhole... 095-1 Splash Drop Manhole and Regular Drop Manhole... 095-2 Special Detail Splash Drop Manhole and Special Detail
More informationBestall Collaborative Limited Planning Environment Construction Management Development
November 18, 2017 Bestall Collaborative Limited Lori Hight, AICP, Senior Planner City Development Department City of Thornton City Hall 9500 Civic Center Drive Thornton, Colorado 80229-4326 RE: River Valley
More informationDRAFTING STANDARDS 9.00 DRAFTING STANDARDS
DRAFTING STANDARDS 9.00 DRAFTING STANDARDS Final plans shall conform in appearance, format, accuracy, and quality to the standards used in the Springfield Engineering Division. Additional standards shall
More informationAppendix E-4. City of Fort Collins. Requirements for Utility Plans
Appendix E-4 City of Fort Collins Requirements for Utility Plans Project Name: Project Planner: Design Engineering Firm: Developer: All applications for final development plans must include final development
More information.1 Applicability: These criteria shall be applied as follows:
DESIGN CRITERIA DIVISION 4800 STREET LIGHTING 4801 GENERAL: These criteria shall be adhered to for the design of all publiclyfinanced or privately-financed traffic signal systems to be installed in the
More informationCONSULTANT: Wantman Group, Inc SERVICE AUTHORIZATION NO. _12-03 FOR CONSULTING SERVICES CITY PROJECT NO CONSULTANT PROJECT NO.
EXHIBIT A CONSULTING SERVICE AUTHORIZATION DATE: CONSULTANT: Wantman Group, Inc SERVICE AUTHORIZATION NO. _12-03 FOR CONSULTING SERVICES CITY P.O. NO. CITY EXPENSE CODE CITY PROJECT NO. 14-073 CONSULTANT
More informationSECTION II PLAN FORMAT AND REQUIREMENTS WATER AND SEWER
SECTION II PLAN FORMAT AND REQUIREMENTS WATER AND SEWER SECTION II PLAN FORMAT AND REQUIREMENTS WATER AND SEWER The Developer's engineer shall prepare system improvement plans that are clear, concise,