CASE STUDY- FAULT IN POWER TRANSFORMER AT LOKTAK POWER STATION. - S K Mishra & S K Das NHPC Ltd O&M Division

Size: px
Start display at page:

Download "CASE STUDY- FAULT IN POWER TRANSFORMER AT LOKTAK POWER STATION. - S K Mishra & S K Das NHPC Ltd O&M Division"

Transcription

1 CASE STUDY- FAULT IN POWER TRANSFORMER AT LOKTAK POWER STATION - S K Mishra & S K Das NHPC Ltd O&M Division 1

2 PRESENTATION COVERS Introduction DESCRIPTION OF EVENTS INITIAL RESPONSE DETAILED INSPECTION FINDINGS RESTORATION R OF TRANSFORMER ANALYSIS OF EVENT AND ROOT CAUSE FINDINGS CONCLUSION RECOMMENDATION 2

3 INTRODUCTION The faulted transformer (Identification no. B5255) under study is MVA, single phase, 11 KV/132 KV/ 3, ONAF and was manufactured by GEC in 1977 and under operation since The winding of the said transformer was replaced in 2011 at factory works of OEM. The repaired transformer was transported to Power House by road & put into service in The Power evacuation system at Loktak Power Station consists of four 132 KV transmission line. Due to hilly terrain and the lines are laid through dense forest, frequent fault occurs on transmission lines. The transformers installed at Loktak Power Station are subject to frequent short circuit current vis-à-vis electro-mechanical stress. 3

4 DESCRIPTION OF EVENTS On 07/08/2016 all the three units ( 3 x 35 MW) of Loktak Power Station were running at full load prior to the event. At 9:00 hrs on 07/08/2016, Buchholz relay alarm of Y-phase transformer of Unit#3 appeared. During inspection, gas accumulation in the Buchholz relay was observed and the unit was stopped at 11:10 hrs for further investigation. Here it is pertinent to mention that, no other protection relay started or operated even after operation of transformer under fault condition for more than two hours which indicates low energy fault. 4

5 INITIAL RESPONSE Tan Delta and capacitance test: The test was conducted at 2 KV, 5KV & 10 KV at HV side and 1 KV, 3KV & 5KV at LV side at winding/oil temperature at 52 0 C. The test result at 10KV (HV side) and 5KV (LV side) is presented below: Sl. No. Insulation Tested Capacitance (pf) Tan Delta (%) The above test results showed no abnormality in transformer winding insulation. ma Watts 1 HV to LV +GND HV-GND HV-LV LV to HV +GND LV to GND LV to HV

6 INITIAL RESPONSE Breakdown Voltage (BDV) test: The BDV of transformer oil was tested as 47 KV at 2.5 mm gap, which was also within permissible limit. Therefore, transformer oil insulation property also found to be acceptable. Insulation Resistance (IR) Test: IR test of transformer winding was conducted at 46 0 C by using 5KV applied voltage. Winding IR at 5KV/60Sec (GΩ) PI (IR at 10 min/ir at 1 min) HV-LV HV-LV+E LV-HV+E The above test result showed readings within permissible limit. In addition to above turn ratio and magnetizing current tests were also conducted and the results were within normal limit. 6

7 INITIAL RESPONSE Result of DGA test: The DGA test of transformer oil (after fault) was conducted. The recent DGA test result of transformer oil sample along with that of previous result is as under: Characteristics PPM (measured on 08/08/2016) PPM (measured on 25/05/2016) Methane 70 4 Ethane 18 1 Ethylene Acetylene 3 ND Hydrogen 29 2 Oxygen Nitrogen Carbon monoxide Carbon dioxide

8 INITIAL RESPONSE The DGA test conducted on 08/08/2016 showed increased content of hydro-carbon gases i.e. Methane, Ethane, Ethylene and Acetylene as compared to that of previous result. This clearly indicated that there can be an arc inside the transformer causing overheating of oil and successive generation of hydro-carbon gases. The transformer was removed from service for further investigation. Unit#3 was restored using spare transformer. 8

9 DETAILED INSPECTION FINDINGS The faulty transformer was thoroughly inspected on 25/08/2016 at site. After dismantling of all the accessories and top cover from the transformer, it was found that the core along with winding had shifted from its original position. Metal dust was also found on the transformer tank guiding rail area. The core along with winding was removed from the transformer tank to check the extent of damage caused and it was found that the insulation sheet at the bottom of the tank got shifted from its original position. However, no deformation of core/winding or any hot spot was observed over the core/winding. The Inspection at tap changer section reveals partial melting of contact finger from its edge 9

10 DETAILED INSPECTION FINDINGS Fig.1 Metal Dust at core foundation rail Fig.2 Displacement of core insulation 10

11 DETAILED INSPECTION FINDINGS DETAILED INSPECTION FINDINGS Fig. 3 Healthy winding Fig. 4 Hot spot at Tap Changer contact 11

12 RESTORATION OF TRANSFORMER Thorough cleaning of transformer core and winding was done. It was decided to bypass the tap changer section based on following consideration: The tap changer is not used to control reactive power supply vis-à- vis bus voltage at our Generator Bus (PV bus). The reactive Power supplied by the generator is sufficient to control the bus voltage within permissible limit. Fig. 5 Tap Changer Bypassed 12

13 RESTORATION OF TRANSFORMER The transformer core-winding was put into transformer tank properly. The IR test was conducted to ensure proper insulation between Channel to core, Tank to Core and Channel to Tank. The transformer was properly boxed up by using new gaskets. All the accessories except conservator were fitted and the transformer was filled with Nitrogen with a pressure of 0.2 Kg/sqcm to ensure leakage free boxing up of transformer. The main tank of the transformer was kept under partial vacuum (at 400 mmhg) for 12 hrs to facilitate release of moisture from paper insulator. Oil filling was started thereafter by oil filtration plant after installation of Conservator and radiator. All electrical tests were conducted and the test results showed the value within permissible limit. The work was completed in 6 days & the transformer is kept as spare. 13

14 ANALYSIS OF EVENT & ROOT CAUSE FINDINGS Two possibilities for the failure is envisaged. a) Displacement of core-winding section may have occurred during transport of transformer after repair. b) Due to frequent line fault the transformer was subjected to electromechanical stress vis-à-vis vibration. This may have further contributed towards misalignment of tap changer contact finger and successive low energy PD/fault Premature O&M failures are occurring due to accelerated ageing and/or weakening of short circuit withstand capability of transformer due to repeated short circuits in the network. The number of through faults seen by the transformers being high has a cumulative effect on the mechanical weakening of the winding supports and insulation & increases the probability of premature failure of the transformer. 14

15 ANALYSIS OF EVENT & ROOT CAUSE FINDINGS A recent, extensive survey of about 1000 major transformer failures by CIGRE WG A2.37 [8] showed that: Windings are the most common failure location mechanical failures account for over 20% of all failures of substation transformers, External short-circuit is the second largest known failure cause (after ageing). 15

16 CONCLUSION The weakening of winding foundation, if any during transportation is required to be confirmed before putting the transformer into service. The Sweep Frequency Response Analysis Test (SFRA) should necessarily be conducted both before despatch and after receiving/installing of transformer at site. Any deviation in frequency response signatures before and after transport should be observed carefully as it indicates mechanical displacement and deformation of winding occurred during transport. The frequent faults in transmission line also aggravate the situation and further accelerate the deformation/displacement of transformer winding. 16

17 CONCLUSION The Following facts are presented here as envisaged from above analysis: a) Transformers subjected to frequent short circuit (through fault) condition, may develop faults due to mechanical stress. However, no routine electrical test could specifically pin point such fault as the fault do not involve earth and the same is evident from the above test results. c) The Power Station should do periodic DGA tests of the GSU transformer oil as per present practice. A database consisting of all test records of individual transformer along with fault/failure history should be maintained. c) Immediate shutdown of unit should be ensured if Buchholz alarm appears. Restart of unit can only be considered after completion of thorough investigation. d) Buchholz-relays may operate unnecessarily due to the vibrations that occur during short-circuit conditions. Therefore, the behaviour of such relays for any transformer should carefully be monitored and recorded. 17

18 RECOMMENDATIONS The Power Station should consider carrying out (preferably include in the specification) Sweep Frequency Response Analysis Test (SFRA) on transformer both before transportation from workshop and after receiving at site. By comparing the above two signatures, physical displacement of transformer winding, if any, caused during transportation can be assessed. Further, the transformer should be fitted with impact recorder before transportation to record the mechanical impact on the transformer during transportation. 18

19 THANK YOU 19

RESIDUAL LIFE ASSESSMENT OF GENERATOR TRANSFORMERS IN OLD HYDRO POWER PLANTS

RESIDUAL LIFE ASSESSMENT OF GENERATOR TRANSFORMERS IN OLD HYDRO POWER PLANTS RESIDUAL LIFE ASSESSMENT OF GENERATOR TRANSFORMERS IN OLD HYDRO POWER PLANTS Authored by: Sanjay Srivastava, Chief Engineer (HE&RM), Rakesh Kumar, Director (HE&RM), R.K. Jayaswal, Dy. Director (HE&RM)

More information

REPORT ON INVESTIGATION OF FAILURE OF 100 MVA, 220/66-33/11 KV POWER TRANSFORMER AT 220KV GEETA COLONY SUBSTATION OF DELHI TRANSCO LTD.

REPORT ON INVESTIGATION OF FAILURE OF 100 MVA, 220/66-33/11 KV POWER TRANSFORMER AT 220KV GEETA COLONY SUBSTATION OF DELHI TRANSCO LTD. REPORT ON INVESTIGATION OF FAILURE OF 100 MVA, 220/66-33/11 KV POWER TRANSFORMER AT 220KV GEETA COLONY SUBSTATION OF DELHI TRANSCO LTD. (DTL) 1.0 Introduction: 1.1 DTL vide letter No. F.DTL/206/2015-16/Mgr(T)O&M-E-2/22

More information

Benefits of SFRA - Case Studies

Benefits of SFRA - Case Studies 6 th International Conference on Large Power Transformers- Modern Trends Benefits of SFRA - Case Studies B B Ahir Gujarat Energy Transmission Corporation Limited 1 Outline Condition Monitoring in GETCO

More information

Chapter 7 Conclusion 7.1 General

Chapter 7 Conclusion 7.1 General Chapter 7 7.1 General The mechanical integrity of a transformer winding is challenged by several mechanisms. Many dielectric failures in transformers are direct results of reduced mechanical strength due

More information

Report on investigation of failure of 315 MVA Auto transformer at 400 kv Bawana Substation of Delhi Transco Ltd.(DTL)

Report on investigation of failure of 315 MVA Auto transformer at 400 kv Bawana Substation of Delhi Transco Ltd.(DTL) Report on investigation of failure of 315 MVA Auto transformer at 400 kv Bawana Substation of Delhi Transco Ltd.(DTL) 1.0 Introduction: 1.1 DTL vide letter No. F.DTL/206/F.06/2015-16/Mgr(Bawana)/353 dated

More information

Operational Management of Grid Transformers An Experience of POWERGRID

Operational Management of Grid Transformers An Experience of POWERGRID Operational Management of Grid Transformers An Experience of POWERGRID 1.0 Introduction P.N. Dixit, GM; S. Victor, AGM; V.K. Bhaskar, CM; Gunjan Agrawal, Manager Operation Services Department Power Grid

More information

Innovative Test Techniques and Diagnostic Measurements to Improve the Performance and Reliability of Power System Transformers

Innovative Test Techniques and Diagnostic Measurements to Improve the Performance and Reliability of Power System Transformers Innovative Test Techniques and Diagnostic Measurements to Improve the Performance and Reliability of Power System Transformers Dr. Michael Krüger, Alexander Kraetge, OMICRON electronics GmbH, Austria Alexander

More information

Acoustic Emission in power transformers. Ajusco 15, Colonia Portales, Delegación Benito Juárez, C.P , México, D.F.

Acoustic Emission in power transformers. Ajusco 15, Colonia Portales, Delegación Benito Juárez, C.P , México, D.F. Acoustic Emission in power transformers 1 More expensive equipment in the substation Many years of operation First indication of a problem: Dissolved Gases Begin investigation to determine the origin of

More information

ABB Power Products Service

ABB Power Products Service Raben Naidoo, Technology days, May 21-22th, 2014, Cape Town, South Africa, Enhanced availability of transformers via transformer remote monitoring - TEC ABB Power Products Service Why a session on availability?

More information

Variation in SFRA plot due to design and external parameter

Variation in SFRA plot due to design and external parameter Chapter 6 Variation in SFRA plot due to design and external parameter 6.1 Introduction As the experience grows with Sweep Frequency Response Analysis in world, it is useful to discuss the measurements

More information

N S Sodha, Former Executive Director, POWERGRID Corpn, Gurgaon

N S Sodha, Former Executive Director, POWERGRID Corpn, Gurgaon N S Sodha, Former Executive Director, POWERGRID Corpn, Gurgaon POWER TRANSFORMERS Factory condition POWER TRANSFORMERS Site condition POWER TRANSFORMER FAULTS Faults in a Transformer 1. Internal Faults

More information

Power transformer failure management on the Eskom distribution network in Limpopo

Power transformer failure management on the Eskom distribution network in Limpopo Power transformer failure management on the Eskom distribution network in Limpopo MM Sako*, A Wessels** and JHC Pretorius*** *Eskom Holdings SOC Ltd, Distribution, Gobie Street, Menlopark, South Africa

More information

Basic Principles and Operation of Transformer

Basic Principles and Operation of Transformer Basic Principles and Operation of Transformer CONSTRUCTIONAL ASPECTS Cores In order to enhance core s magnetic properties, it is constructed from an iron and silicon mixture (alloy). The magnetic core

More information

Cholla T809 Condition Assessment Report Provided by students of Northern Arizona University with the support of Arizona Public Service

Cholla T809 Condition Assessment Report Provided by students of Northern Arizona University with the support of Arizona Public Service Cholla T809 Condition Assessment Report Provided by students of Northern Arizona University with the support of Arizona Public Service Andrew Morin, Richard Barnes, Kyle Wiedeman, Scott Lederhos, Kenneth

More information

HOW TO SAFE GUARD THE TRANSFORMER..???

HOW TO SAFE GUARD THE TRANSFORMER..??? CPRI HOW TO SAFE GUARD THE TRANSFORMER..??? CPRI Efficient and Effective network planning, Design and Forecasting Highly Reliable and Stable Protection system and co-ordination Measures to mitigate various

More information

Transformer Factory Testing

Transformer Factory Testing Transformer Factory Testing John J. Foschia Test Engineer John.Foschia@spx.com September 2018 Reasons for Testing Compliance with user specifications Assessment of quality and reliability Verification

More information

Hands-On Transformer Testing and Maintenance

Hands-On Transformer Testing and Maintenance Hands-On Course Description This Hands-On course will teach you how to prioritize your transformer maintenance strategy, stretch your maintenance budget and at the same time maximize the life and condition

More information

Advanced Diagnostic Testing Services. Provides detailed and reliable results

Advanced Diagnostic Testing Services. Provides detailed and reliable results Advanced Diagnostic Testing Services Provides detailed and reliable results Advanced Diagnostic Testing Services from the world s leading manufacturer of power transformers ABB leadership begins with our

More information

DEFERRING REPLACEMENT OF A 600 MVA, 345GRD Y/138GRD Y/ 13.8 kv SHELL TYPE WESTINGHOUSE AUTOTRANSFORMER

DEFERRING REPLACEMENT OF A 600 MVA, 345GRD Y/138GRD Y/ 13.8 kv SHELL TYPE WESTINGHOUSE AUTOTRANSFORMER DEFERRING REPLACEMENT OF A 600 MVA, 345GRD Y/138GRD Y/ 13.8 kv SHELL TYPE WESTINGHOUSE AUTOTRANSFORMER JESSE M LOPEZ CPS ENERGY USA EMILIO MORALES CRUZ QUALITROL USA SUMMARY Power transformers are essential

More information

Substation Preventive Maintenance

Substation Preventive Maintenance Substation Preventive Maintenance PROVINCIAL ELECTRICITY AUTHORITY 1 Presentation Contents 1) A kind of substation 2) Electrical equipment details of AIS substation 3) Electrical equipment details of GIS

More information

Understanding the Value of Electrical Testing for Power Transformers. Charles Sweetser, OMICRON electronics Corp. USA

Understanding the Value of Electrical Testing for Power Transformers. Charles Sweetser, OMICRON electronics Corp. USA Understanding the Value of Electrical Testing for Power Transformers Charles Sweetser, OMICRON electronics Corp. USA Understanding the Value of Electrical Testing for Power Transformers Charles Sweetser,

More information

Monitoring Solutions For Power Transformers, Reactors, Bushings and Instrument Transformers

Monitoring Solutions For Power Transformers, Reactors, Bushings and Instrument Transformers in cooperation with Monitoring Solutions For Power Transformers, Reactors, Bushings and Instrument Transformers BZ-MS/1 pazifik power Complete Transformer Monitoring System (TMS) ZVCM-1001 Bushing Monitoring

More information

POWER TRANSFORMER SPECIFICATION, DESIGN, QUALITY CONTROL AND TESTING 18 MARCH 2009

POWER TRANSFORMER SPECIFICATION, DESIGN, QUALITY CONTROL AND TESTING 18 MARCH 2009 POWER TRANSFORMER SPECIFICATION, DESIGN, QUALITY CONTROL AND TESTING 18 MARCH 2009 Nkosinathi Buthelezi Senior Consultant: Power Transformers and Reactors Presentation Content Standardization of Power

More information

Power Transformer Condition Assessment Based on Standard Diagnosis

Power Transformer Condition Assessment Based on Standard Diagnosis Power Transformer Condition Assessment Based on Standard Cattareeya Suwanasri Abstract The diagnostic techniques of electrical and insulating oil testing are proposed to assess the internal condition of

More information

GUJARAT TECHNOLOGICAL UNIVERSITY, AHMEDABAD, GUJARAT

GUJARAT TECHNOLOGICAL UNIVERSITY, AHMEDABAD, GUJARAT GUJARAT TECHNOLOGICAL UNIVERSITY, AHMEDABAD, GUJARAT COURSE CURRICULUM COURSE TITLE: MAINTENANCE OF TRANSFORMER AND CIRCUIT BREAKER (COURSE CODE:3360907) Diploma Programme in which this course is offered

More information

Schedule of Accreditation issued by United Kingdom Accreditation Service 2 Pine Trees, Chertsey Lane, Staines-upon-Thames, TW18 3HR, UK

Schedule of Accreditation issued by United Kingdom Accreditation Service 2 Pine Trees, Chertsey Lane, Staines-upon-Thames, TW18 3HR, UK 2 Pine Trees, Chertsey Lane, Staines-upon-Thames, TW18 3HR, UK PO Box 25876 Safat 13119 Kuwait Contact: Mr Atul Madhukar Vaidya Tel: +965 1822600 Fax: +965 24761963 E-Mail: factory@ahleiasg.com Website:

More information

Understanding the Value of Electrical Testing for Power Transformers. Charles Sweetser - OMICRON

Understanding the Value of Electrical Testing for Power Transformers. Charles Sweetser - OMICRON Understanding the Value of Electrical Testing for Power Transformers Charles Sweetser - OMICRON Transformers Diagnostic Testing - OVERALL DGA Oil Screen Power Factor / Capacitance Exciting Current Transformer

More information

A Comparative Diagnosis Approach on Transformer s Insulating Oil Ming-Jong Lin

A Comparative Diagnosis Approach on Transformer s Insulating Oil Ming-Jong Lin Information Technology and Mechatronics Engineering Conference (ITOEC 2015) A Comparative Approach on Transformer s Insulating Oil Ming-Jong Lin No. 11 North Road Nanke, Shanhua District, Tainan City,

More information

Power Transformers Basics

Power Transformers Basics Power Transformers Basics Transformer Basic Objective Introduce Basic Transformer Theory as it Relates to Diagnostics Provide a Better Understanding of the Diagnostic Test Environment Identify Important

More information

EPS AUSTRALIA SERVICES HV TESTING & COMMISSIONING CAPABILITY

EPS AUSTRALIA SERVICES HV TESTING & COMMISSIONING CAPABILITY EPS AUSTRALIA SERVICES HV TESTING & COMMISSIONING CAPABILITY EPS AUSTRALIA SERVICES COMPANY OVERVIEW EPS is a recognised company specialising in Electrical, Instrumentation, Structural, Mechanical and

More information

TesTIng of Power. Transformers are the largest, most. feature. By brandon dupuis

TesTIng of Power. Transformers are the largest, most. feature. By brandon dupuis feature By brandon dupuis An Introduction to Electrical diagnostic TesTIng of Power Transformers 38 Transformers are the largest, most expensive, and highly critical components of most utility substations.

More information

Power Transformer Testing

Power Transformer Testing Power Transformer Testing Course No: E03-041 Credit: 3 PDH Velimir Lackovic, Char. Eng. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800 F: (877)

More information

CHAPTER 3 REVIEW OF POWER TRANSFORMER PROTECTION SCHEMES

CHAPTER 3 REVIEW OF POWER TRANSFORMER PROTECTION SCHEMES CHAPTER 3 REVIEW OF POWER TRANSFORMER PROTECTION SCHEMES 3.1. Introduction Power Transformer is the nerve centre of any power distribution system. The capacity of power transformers is generally decided

More information

FIELD ELECTRICAL TESTING SPX TRANSFORMER SOLUTIONS, INC.

FIELD ELECTRICAL TESTING SPX TRANSFORMER SOLUTIONS, INC. Regional Technical Seminar FIELD ELECTRICAL TESTING SPX TRANSFORMER SOLUTIONS, INC. Field Electrical Testing Applications Key Purposes of Field Electrical Testing: Receiving inspection Acceptance testing/commissioning

More information

Transformer Protection

Transformer Protection Transformer Protection Nature of transformer faults TXs, being static, totally enclosed and oil immersed develop faults only rarely but consequences large. Three main classes of faults. 1) Faults in Auxiliary

More information

IN ELECTRICAL ENGINEERING - I C M E T CRAIOVA

IN ELECTRICAL ENGINEERING - I C M E T CRAIOVA Taking into account that power transformer is the major item of equipment in power systems, its correct operation is vital to system operation. It is well known that transformer failures are sometimes

More information

Application of Polarisation Depolarisation Current (PDC) technique on fault and trouble analysis of stator insulation

Application of Polarisation Depolarisation Current (PDC) technique on fault and trouble analysis of stator insulation CIGRE SC A1 & D1 JOINT COLLOQUIUM October 24, 2007 Application of Polarisation Depolarisation Current (PDC) technique on fault and trouble analysis of stator insulation S. A. BHUMIWAT Independent Consultant

More information

Discipline Electrical Testing Issue Date Certificate Number T-2837 Valid Until Last Amended on - Page 1 of 6 LOCATION 1

Discipline Electrical Testing Issue Date Certificate Number T-2837 Valid Until Last Amended on - Page 1 of 6 LOCATION 1 Post: Last Amended on - Page 1 of 6 LOCATION 1 I. TRANSFORMERS AND REACTORS 1. 500 MVA, 765 kv 500 MVA, 400 kv Ratio & Polarity Check Magnetic Balance & Magnetizing Current Measurement at Low Voltage Vector

More information

Effective maintenance test techniques for power transformers

Effective maintenance test techniques for power transformers Effective maintenance test techniques for power transformers by Alexander Dierks, Herman Viljoen, Alectrix, South Africa, and Dr. Michael Krüger, Omicron Electronics, Austria Due to ever-increasing pressure

More information

Use of On and Offline Oil Analysis on the ESB, Distribution and Generation Networks

Use of On and Offline Oil Analysis on the ESB, Distribution and Generation Networks Reliability Ireland Conference 2016, Grand Hotel Malahide, 12-13 April 2016, Dublin, Ireland. Use of On and Offline Oil Analysis on the ESB, Distribution and Generation Networks J. Carpenter*, ESB International,

More information

Matz Ohlen Director Transformer Test Systems. Megger Sweden

Matz Ohlen Director Transformer Test Systems. Megger Sweden Matz Ohlen Director Transformer Test Systems Megger Sweden Frequency response analysis of power transformers Measuring and analyzing data as function of frequency, variable frequency diagnostics Impedance

More information

7. INSPECTION AND TEST PROCEDURES

7. INSPECTION AND TEST PROCEDURES 7.1 Switchgear and Switchboard Assemblies A. Visual and Mechanical Inspection 1. Compare equipment nameplate data with drawings and specifications. 2. Inspect physical and mechanical condition. 3. Inspect

More information

Identification of Overheating in Transformer Solid Insulation by Polarization Depolarization Current Analysis

Identification of Overheating in Transformer Solid Insulation by Polarization Depolarization Current Analysis 2013 Electrical Insulation Conference, Ottawa, Ontario, Canada, 2 to 5 June 2013 Identification of Overheating in Transformer Solid Insulation by Polarization Depolarization Current Analysis S.A. Bhumiwat

More information

Transformers handling and transport

Transformers handling and transport Special tests (Credit: http://www.breakbulk.com/wp-content/uploads/2015/02/20141117160247x.jpg) Transformers handling and transport Damages that may arise and how to find them Table of contents summary

More information

Martin Stoessl R&D Manager Siemens Transformers Austria - Weiz

Martin Stoessl R&D Manager Siemens Transformers Austria - Weiz Martin Stoessl R&D Manager Siemens Transformers Austria - Weiz 2007 1979 1892 Transformer reliability Ability to perform its required functions under stated conditions for a specified period of time Failure

More information

PRE COMMISSIONING TESTS ON EQUIPMENT AT 33/11 KV SUB STATIONS. IR Values are to be read on the megger by meggering the Power transformer

PRE COMMISSIONING TESTS ON EQUIPMENT AT 33/11 KV SUB STATIONS. IR Values are to be read on the megger by meggering the Power transformer PRE COMMISSIONING TESTS ON EQUIPMENT AT 33/11 KV SUB STATIONS TESTS ON TRANSFORMERS 1. IR Values This is measured to measure the Insulation Resistance of the whole transformer. a) For 33/11 KV Power Transformer

More information

Understanding and Extracting Valuable Information from Basic and Advanced Power Transformer Testing Techniques

Understanding and Extracting Valuable Information from Basic and Advanced Power Transformer Testing Techniques Understanding and Extracting Valuable Information from Basic and Advanced Power Transformer Testing Techniques Charles Sweetser, Services Manager, PRIM Engineering, Waltham, Mass. Topics of Discussion

More information

Effective Maintenance Test Techniques and Diagnostic Measurements to Improve the Performance and Reliability of Power System Transformers

Effective Maintenance Test Techniques and Diagnostic Measurements to Improve the Performance and Reliability of Power System Transformers Effective Maintenance Test Techniques and Diagnostic Measurements to Improve the Performance and Reliability of Power System Transformers Alexander Dierks, Herman Viljoen, Alectrix (Pty) Ltd, South Africa

More information

SERVICE OFFERINGS FOR POWER SYSTEM STUDY & CONDITION MONITORING FOR STATIC EQUIPMENT

SERVICE OFFERINGS FOR POWER SYSTEM STUDY & CONDITION MONITORING FOR STATIC EQUIPMENT SERVICE OFFERINGS FOR POWER SYSTEM STUDY & CONDITION MONITORING FOR STATIC EQUIPMENT Page TABLE OF CONTENTS POWER SYSTEM STUDY: 5 DATA COLLECTION AND NETWORK MODELLING 5 LOAD FLOW STUDY 5 SHORT CIRCUIT

More information

Specialists in HV and MV test and diagnostics. Testing in Substations

Specialists in HV and MV test and diagnostics. Testing in Substations Specialists in HV and MV test and diagnostics Testing in Substations Testing in Substations Testing in Substations At 4fores we specialize in the diagnosis and measurement of all types of existing technologies

More information

Modern transformer relays include a comprehensive set of protective elements to protect transformers from faults and abnormal operating conditions

Modern transformer relays include a comprehensive set of protective elements to protect transformers from faults and abnormal operating conditions 1 Transmission transformers are important links in the bulk power system. They allow transfer of power from generation centers, up to the high-voltage grid, and to bulk electric substations for distribution

More information

DATA SHEET FOR LIGHTING TRANSFORMER APPD. BY VDV PROJECT NO

DATA SHEET FOR LIGHTING TRANSFORMER APPD. BY VDV PROJECT NO PART - A : SPECIFIC REQUIREMENTS THIS DATA SHEET IS APPLICABLE FOR IN BOILER A CLIMATIC CONDITIONS PACKAGE 1 DESIGN AMBIENT TEMPERATURE 45 C 2 ALTITUDE ( ABOVE MSL ) 6.71 MTRS. 3 RELATIVE HUMIDITY 74 %

More information

Distribution Equipments - Technology and Applications. Training Module for DISTRIBUTION TRANSFORMER

Distribution Equipments - Technology and Applications. Training Module for DISTRIBUTION TRANSFORMER Distribution Equipments - Technology and Applications Training Module for DISTRIBUTION TRANSFORMER Transformer specification Transformer design Manufacturing / quality control Testing in the Works Transportation

More information

About us. Vision. To lead our field in innovation, quality and customer service.

About us. Vision. To lead our field in innovation, quality and customer service. a Index 1 2 4 6 7 8 13 About us Low voltage switchgear & bus duct Medium voltage switchgear & bus duct UKAS ACCREDITATION ASTA RECOGNITION Distribution and Power transformers OUR TEAM About us Vision To

More information

PARTIAL DISCHARGE MEASUREMENT

PARTIAL DISCHARGE MEASUREMENT PARTIAL DISCHARGE MEASUREMENT Partial Discharges are small electrical sparks which occur predominantly at insulation imperfection. It is the phenomenon which occurs in the insulation on application of

More information

EI HIGH VOLTAGE INSULATION TESTING POLICY

EI HIGH VOLTAGE INSULATION TESTING POLICY Network(s): Summary: ENGINEERING INSTRUCTION EI 09-0001 HIGH VOLTAGE INSULATION TESTING POLICY EPN, LPN, SPN This engineering instruction details the policy for the on-site insulation testing of new and

More information

EFFECETIVE TRANSFORMER CONDITION ASSESSMENT

EFFECETIVE TRANSFORMER CONDITION ASSESSMENT EFFECETIVE TRANSFORMER CONDITION ASSESSMENT Luwendran Moodley, Doble Engineering Africa Abstract. This paper details a novel approach to transformer condition assessment. This method has proven itself

More information

HOLISTIC APPROACH TO ON-LINE TRANSFORMER MONITORING: KNOWLEDGE MANAGEMENT FIRST!

HOLISTIC APPROACH TO ON-LINE TRANSFORMER MONITORING: KNOWLEDGE MANAGEMENT FIRST! HOLISTIC APPROACH TO ON-LINE TRANSFORMER MONITORING: KNOWLEDGE MANAGEMENT FIRST! M. Tozzi, E. Savorelli, A. Mudryk, M. Skelton Camlin Power Ltd N. Ireland SUMMARY This paper describes a method to convert

More information

Welcome to the Session on. HT Distribution Network

Welcome to the Session on. HT Distribution Network Welcome to the Session on HT Distribution Network Learning Objective By the end of this session you will be able to: Explain the HT distribution network breakdown maintenance - possible faults, identification

More information

A Novel Technique to Precise the Diagnosis of Power Transformer Internal Faults

A Novel Technique to Precise the Diagnosis of Power Transformer Internal Faults A Novel Technique to Precise the Diagnosis of Power Transformer Internal Faults U. Mohan Rao 1 & D.Vijay Kumar 2 1 Department of Electrical Engineering, National Institute of Technology, Hamirpur, H.P,

More information

B3-102 THE ROMANIAN EXPERIENCE REGARDING THE RISK OF MANAGEMENT IN THE OPERATION AND MAINTENANCE OF LARGE POWER TRANSFORMERS IN HV SUBSTATIONS

B3-102 THE ROMANIAN EXPERIENCE REGARDING THE RISK OF MANAGEMENT IN THE OPERATION AND MAINTENANCE OF LARGE POWER TRANSFORMERS IN HV SUBSTATIONS 21, rue d'artois, F-75008 Paris http://www.cigre.org B3-102 Session 2004 CIGRÉ THE ROMANIAN EXPERIENCE REGARDING THE RISK OF MANAGEMENT IN THE OPERATION AND MAINTENANCE OF LARGE POWER TRANSFORMERS IN HV

More information

TIGHTENING TORQUE ON WOODEN CORE CLAMP (Nm) (STEEL FASTENER) 1 M M M M M

TIGHTENING TORQUE ON WOODEN CORE CLAMP (Nm) (STEEL FASTENER) 1 M M M M M SL. NO NOMINAL DIAMETER "D" mm GASKETED JOINT (Nm) WOODEN CORE CLAMP (Nm) STEEL FIXING STUD FOR BUSHING (Nm) BUSHING STEM (Nm) (BRASS /COPPER) COPPER BUSBAR (Nm) 1 M6 5 - - - - 2 M8 12 - - 10-3 M10 22

More information

Form-IV. Form of Inspection/Test Report. (Under Regulation 43)

Form-IV. Form of Inspection/Test Report. (Under Regulation 43) Form-IV Form of Inspection/Test Report (Under Regulation 43) 1. Name and address of the Chartered Electrical Safety Engineer 2. Name and address of the consumer (or) Owner(or) supplier: Contact No: E-Mail:

More information

Commissioning Manual Distribution Transformers - Three-phase Oil Filled

Commissioning Manual Distribution Transformers - Three-phase Oil Filled 1LPL000006A2110 rev. 1 Commissioning Manual Distribution Transformers - Three-phase Oil Filled 1LPL000006A2110 rev. 1 2 / 7 Table of contents 1 Commissioning and start-up... 3 1.1 Transformer survey...

More information

IMPORTANCE & PROCESS OF RLA STUDIES IN ASSESSMENT OF NEED FOR R&M - A CASE STUDY. CPRI, Bengaluru

IMPORTANCE & PROCESS OF RLA STUDIES IN ASSESSMENT OF NEED FOR R&M - A CASE STUDY. CPRI, Bengaluru IMPORTANCE & PROCESS OF RLA STUDIES IN ASSESSMENT OF NEED FOR R&M - A CASE STUDY CPRI, Bengaluru What is RLA? RLA is a technique to examine systematically and monitor the plant, during and after service

More information

Testing and Diagnostic of Power Transformers & Distribution Transformers

Testing and Diagnostic of Power Transformers & Distribution Transformers Testing and Diagnostic of Power Transformers & Distribution Transformers APT Power Technology Co., Ltd. Xi an FOREWORD Transformers play an very important role in power transmission and distribution system.

More information

KNOW MORE ABOUT THE TRANSFORMERS. Glossary Transformers

KNOW MORE ABOUT THE TRANSFORMERS. Glossary Transformers KNOW MORE ABOUT THE TRANSFORMERS Glossary Transformers Ambient temperature The existing temperature of the atmosphere surrounding a transformer installation. Ampere The practical unit of electric current.

More information

Fault Detection in Transformer Using Frequency (Sweep) Response Analysis

Fault Detection in Transformer Using Frequency (Sweep) Response Analysis Fault Detection in Transformer Using Frequency (Sweep) Response Analysis Miss. Kajal R. Pachbhai PG Student at Ballarpur Institute of Technology, Ballarpur-442701 India kajalpachbhai86@gmail.com Mr. Sagar

More information

PDS100 Application Note: The use of High Frequency Current Transformer as sensor for Transformer diagnostics

PDS100 Application Note: The use of High Frequency Current Transformer as sensor for Transformer diagnostics PDS100 Application Note: The use of High Frequency Current Transformer as sensor for Transformer diagnostics CASE STUDY 1 (Doble Client Conference 2011, ACCA committee meeting) Dissolved Gas Analysis (DGA)

More information

TECHIMP Power Transformer Monitoring

TECHIMP Power Transformer Monitoring TECHIMP Power Transformer Monitoring Kontakt: Martin Hesse Techimp Germany GmbH i.g. E-Mail: mhesse@techimp.com Tel.: +49 5724 391 007 Mobil: +49 170 2364 735 PD Monitoring of Power Transformers Power

More information

ELE-CMOS-E-2001 Electrical Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS

ELE-CMOS-E-2001 Electrical Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS 101135-ELE-CMOS-E-2001 Electrical Engineer Holds a B. Sc. in Electrical Power & Machines Engineering and has over 14 years hands-on experience, including 13 years working in operation, maintenance, construction

More information

Transformer condition assessment with an integrated test van

Transformer condition assessment with an integrated test van Transformer condition assessment with an integrated test van 1 2012 SebaKMT Measuring and locating techniques MADE in GERMANY 2 Testing and Standards for Power Transformers CIGRE CIGRE Brochure 342 (SFRA-FRAX)

More information

Training Fees 3,300$ per participant including Materials/Handouts, Tea/Coffee Refreshments & International Buffet Lunch.

Training Fees 3,300$ per participant including Materials/Handouts, Tea/Coffee Refreshments & International Buffet Lunch. Training Title POWER TRANSFORMERS Training Duration 5 days Training Venue and Dates Power transformers 5 20-24 May $3,300 Abu Dhabi In any of the 5 star hotel. The exact venue will be informed soon. Training

More information

Health indexes for power transformers: A case study

Health indexes for power transformers: A case study Health indexes for power transformers: A case study Félix Ortiz, Inmaculada Fernández, Alfredo Ortiz, Carlos J. Renedo, Fernando Delgado, Cristina Fernández Electrical and Energy Engineering Department,

More information

Case Studies of Electric Power Equipment Diagnostics Using Acoustic Emission

Case Studies of Electric Power Equipment Diagnostics Using Acoustic Emission 17th World Conference on Nondestructive Testing, 25-28 Oct 2008, Shanghai, China Case Studies of Electric Power Equipment Diagnostics Using Acoustic Emission Oswaldo G. SANTOS FILHO 1, Sergio L. ZAGHETTO

More information

Condition Assessment of High Voltage Insulation in Power System Equipment. R.E. James and Q. Su. The Institution of Engineering and Technology

Condition Assessment of High Voltage Insulation in Power System Equipment. R.E. James and Q. Su. The Institution of Engineering and Technology Condition Assessment of High Voltage Insulation in Power System Equipment R.E. James and Q. Su The Institution of Engineering and Technology Contents Preface xi 1 Introduction 1 1.1 Interconnection of

More information

ECP HV INSULATION TESTING

ECP HV INSULATION TESTING Document Number: ECP 11-0006 Network(s): Summary: ENGINEERING COMMISSIONING PROCEDURE EPN, LPN, SPN ECP 11-0006 HV INSULATION TESTING This standard details the policy for the on-site insulation testing

More information

TECHIMP Technologies & Services for Diagnostics and Monitoring of High Voltage Assets

TECHIMP Technologies & Services for Diagnostics and Monitoring of High Voltage Assets TECHIMP Technologies & Services for Diagnostics and Monitoring of High Voltage Assets Who we are TECHIMP is one of the leading providers of Condition Assessment Services Data Acquisition and Test Equipment

More information

SAMPLE. Determining the health of your power transformer begins with Transformer Clinic s SAMPLE testing programs.

SAMPLE. Determining the health of your power transformer begins with Transformer Clinic s SAMPLE testing programs. Keep Powering On SAMPLE Determining the health of your power transformer begins with Transformer Clinic s SAMPLE testing programs. Overheating, arcing, partial discharge, and other active or slow-evolving

More information

Federal Power Transformers LLC based in Abu Dhabi, UAE

Federal Power Transformers LLC based in Abu Dhabi, UAE www.fpt.ae Federal Power Transformers LLC based in Abu Dhabi, UAE CONTENTS The Company...03 Design Process...05 Manufacturing...07 Testing...11 Quality...13 After Sales Support & Other Services...15 Satisfied

More information

Power Station Electrical Protection A 2 B 2 C 2 Neutral C.T E M L } a 2 b 2 c 2 M M M CT Restricted E/F Relay L L L TO TRIP CIRCUIT Contents 1 The Need for Protection 2 1.1 Types of Faults............................

More information

Shunt Reactors. Global Top Energy, Machinery & Plant Solution Provider

Shunt Reactors. Global Top Energy, Machinery & Plant Solution Provider Shunt Reactors Global Top Energy, Machinery & Plant Solution Provider Our Business Brief introduction of Hyosung Power & Industrial Systems PG While Hyosung is an established name for world-class electrical

More information

Transformer Shunt Fault Detection using Two Techniques

Transformer Shunt Fault Detection using Two Techniques Transformer Shunt Fault Detection using Two Techniques Swathy Sasikumar 1, Dr. V. A. Kulkarni 2 P.G. Student, Department of Electrical Engineering, Government College of Engineering, Aurangabad, Maharashtra,

More information

Efacec work every day to anticipate solutions for a sustainable world in the new energy era.

Efacec work every day to anticipate solutions for a sustainable world in the new energy era. Transformers Efacec is the largest industrial portuguese company of the electric and electromechanical sector developing high technology products, solutions and systems used every day by millions of people

More information

save energy, it is precious SYNERGY transformers Mfg. of all types of Distribution / Power & Furnace Transformers

save energy, it is precious SYNERGY transformers Mfg. of all types of Distribution / Power & Furnace Transformers save energy, it is precious Mfg. of all types of Distribution / Power & Furnace Transformers SYNERGY transformers SAFETY AND EFFICIENCY, COMBINED WITH LONG-TERM RELIABILITY, ARE THE HALLMARKS OF WORLD-RENOWNED

More information

شركة كهرباء محافظة القدس المساهمة المحدودة JERUSALEM DISTRICT ELECTRICITY CO. LTD.

شركة كهرباء محافظة القدس المساهمة المحدودة JERUSALEM DISTRICT ELECTRICITY CO. LTD. Our Ref : 2/2018- Date : Messrs: Dear Sir, Tender 2/2018 Main Transformers You are kindly requested to quote for the supply and delivery DDP to our stores the transformers detailed in the attached schedules

More information

DMRC ELECTRICAL STANDARDS & DESIGN WING (DESDW)

DMRC ELECTRICAL STANDARDS & DESIGN WING (DESDW) DELHI METRO RAIL CORPORATION LIMITED DMRC ELECTRICAL STANDARDS & DESIGN WING (DESDW) SPECIFICATION NO. DMES- 0005/ DMRC-E-TR-TRANSF-05 SPECIFICATIONS FOR THREE PHASE 33 kv/415 V AUXILIARY Issued on: Date

More information

Mots clés Power Transformer, Condition Assessment, On-line Monitoring Internet. Par S. Tenbohlen *, T. Stirl, M. Rösner * * ALSTOM T&D, Germany

Mots clés Power Transformer, Condition Assessment, On-line Monitoring Internet. Par S. Tenbohlen *, T. Stirl, M. Rösner * * ALSTOM T&D, Germany Benefit of sensors for on-line monitoring systems for power transformers Mots clés Power Transformer, Condition Assessment, On-line Monitoring Internet Par S. Tenbohlen *, T. Stirl, M. Rösner * * ALSTOM

More information

ECP HV INSULATION TESTING

ECP HV INSULATION TESTING Document Number: ECP 11-0006 Network(s): Summary: All ENGINEERING COMMISSIONING PROCEDURE ECP 11-0006 HV INSULATION TESTING This standard details the policy for the on-site insulation testing of new and

More information

TECHNICAL DATA TYPE CMD OIL-IMMERSED ON-LOAD TAP CHANGER

TECHNICAL DATA TYPE CMD OIL-IMMERSED ON-LOAD TAP CHANGER TECHNICAL DATA TYPE CMD OIL-IMMERSED ON-LOAD TAP CHANGER HM0.154.1901 SHANGHAI HUAMING POWER EQUIPMENT CO., LTD. General 1. General 3 2. Technical specifications 4 3. Type explanation 5 4. Terms and definitions

More information

Transformer Winding Design. The Design and Performance of Circular Disc, Helical and Layer Windings for Power Transformer Applications

Transformer Winding Design. The Design and Performance of Circular Disc, Helical and Layer Windings for Power Transformer Applications The Design and Performance of Circular Disc, Helical and Layer Windings for Power Transformer Applications Minnesota Power Systems Conference November 3 5, 2009 Earl Brown Heritage Center University of

More information

TRANSFORMER OPERATIONAL PRINCIPLES, SELECTION & TROUBLESHOOTING

TRANSFORMER OPERATIONAL PRINCIPLES, SELECTION & TROUBLESHOOTING Training Title TRANSFORMER OPERATIONAL PRINCIPLES, SELECTION & TROUBLESHOOTING Training Duration 5 days Training Date Transformer Operational Principles, Selection & Troubleshooting 5 15 19 Nov $4,250

More information

Power Measurements and Basic Electrical Diagnostic Tests

Power Measurements and Basic Electrical Diagnostic Tests Power Measurements and Basic Electrical Diagnostic Tests Instrument Basics Burden VA Sources V and I Meters V and I KVL and KCL Kelvin Connection KVL and KCL Kelvin Connection 4-Wire Technique Exclude

More information

Problems connected with Commissioning of Power Transformers

Problems connected with Commissioning of Power Transformers Problems connected with Commissioning of Power Transformers ABSTRACT P Ramachandran ABB India Ltd, Vadodara, India While commissioning large Power Transformers, certain abnormal phenomena were noticed.

More information

EE188: Transformer Design, Construction, Testing & Maintenance

EE188: Transformer Design, Construction, Testing & Maintenance EE188: Transformer Design, Construction, Testing & Maintenance EE188 Rev.001 CMCT COURSE OUTLINE Page 1 of 5 Training Description: This intensive training covers the design, theory, operation, maintenance

More information

TAP CHANGER SELECTING MANUAL TECHNICAL DATA

TAP CHANGER SELECTING MANUAL TECHNICAL DATA TECHNICAL DATA HM0.154.000 SHANGHAI HUAMING POWER EQUIPMENT CO., LTD. General 1. General requirement for tap changer selecting 2 2. Attention for tap changer mounting 10 3. Tap changer accessories 10 4.

More information

INTERPRETATION METHODOLOGY TO IDENTIFY FAULT LOCATION IN A POWER TRANSFORMER

INTERPRETATION METHODOLOGY TO IDENTIFY FAULT LOCATION IN A POWER TRANSFORMER Volume: 03 Issue: 07 July16 www.irjet.net p-issn: 2395-0072 INTERPRETATION METHODOLOGY TO IDENTIFY FAULT LOCATION IN A POWER TRANSFORMER Sameer S. Patel 1, 1 Student, Electrical Dept, Rajasthan Institute

More information

Transformer Design: Economics & Reliability

Transformer Design: Economics & Reliability Transformer Design: Economics & Reliability Weidmann-ACTI Inc. Technical Conference New Diagnostic Concepts for Better Asset Management November 8 10, 2004 Holiday Inn Capitol Plaza, Sacramento, CA H.

More information

EE223D: Distribution Power Transformer

EE223D: Distribution Power Transformer EE223D: Distribution Power Transformer Aug 07-09, 2018 / Dubai EE223 Rev.001 CMCT COURSE OUTLINE Page 1 of 5 Training Description: This intensive course is designed to provide participants with the skills

More information