OPERATING PROCEDURE. Table of Contents

Size: px
Start display at page:

Download "OPERATING PROCEDURE. Table of Contents"

Transcription

1 Table of Contents PURPOSE CAISO DISPATCHER RESPONSIBILITIES... 2 Monitor Loads and Generators... 2 Monitor Balancing Areas... 2 Operate CAISO Controlled Grid Voltage Equipment... 3 Voltage Schedules... 4 CAISO Planning PARTICIPATING ENTITY RESPONSIBILITIES... 5 Participating Generator... 5 Participating Load/UDCs... 6 Participating Transmission Owners (PTOs) GENERAL VOLTAGE/VAR CONTROL GUIDANCE... 8 Adjusting Voltage, VARs, or Power Factors... 8 Other measures... 9 Voltage Guidelines... 9 Voltage Schedules... 9 SUPPORTING INFORMATION Operationally Affected Parties Responsibilities References Policy Definitions Version History TECHNICAL REVIEW APPROVAL Purpose Outlines the methods for maintaining acceptable voltage levels and VAR flow on the CAISO Controlled Grid. Page 1 of 13

2 1.0 CAISO Dispatcher Responsibilities Monitor Loads and Generators The CAISO dispatcher conducts the following actions as necessary: Step Action 1 Monitor Loads and Generators to verify that the Grid is operated at the appropriate voltage level. 2 Verify that each Participating Entity is complying with Voltage Support requirements. 3 Coordinate adjustments to prevent offsetting or competing Voltage Support measures. 4 When Then Notified of the loss of an Notify the applicable PTO of the status of automatic voltage the device (the TO will direct the regulator control (AVR), Generator Operator to maintain or change And the SC has not either its voltage schedule or its Reactive notified the PTO, Power schedule as appropriate). Monitor Balancing Areas The CAISO dispatcher conducts the following actions as necessary: Step Action 1 Monitor the interface points between the CAISO Controlled Grid and interconnections with Balancing Areas to confirm that the interconnected power system is operated at the appropriate voltage level with acceptable VAR exchange. 2 Coordinate adjustments with interconnected Balancing Areas. 3 Monitor State Estimator results for accuracy and to ensure that the CAISO Controlled Grid remains within the appropriate voltage parameters Page 2 of 13

3 Operate CAISO Controlled Grid Voltage Equipment The CAISO dispatcher conducts the following actions as necessary: Step Action 1 Maintain operational control of the Voltage Support equipment, And request additional Voltage Support as required. 2 Prior to requesting that Participating Generation Units provide Voltage Support,Dispatch Must-Run units first. 3 Coordinate the use of Voltage Support equipment among PTO s, UDC s, Generators, and other Balancing Areas in order to: Ensure that Participating Entities maintain appropriate Voltage Schedule[s], Ensure that Participating UDCs maintain reactive power flow at Grid interface points within the power factor band of 0.97 lag and 0.99 lead, Coordinate switching of Voltage Support equipment, Ensure that Participating Generators operate Generation within the power factor band of 0.90 lag and 0.95 lead, unless otherwise required by the CAISO, Coordinate events and changes that impact the Voltage Support equipment availability, reliability, or ability to operate within the power factor band, Ensure that the Grid provides the appropriate reactive supply and reserves to the interconnected power system, Coordinate/optimize Voltage Schedules and VAR flows between Balancing Areas for system stability. Page 3 of 13

4 Voltage Schedules Refer to the Participating Entities Voltage/Var Schedules under their applicable Transmission Owner Procedures: UDC Procedure PG&E O-59 SCE SOB 017 SDG&E TMC 1005 LADWP Operating Bulletin 31 SMUD PSE 104 CAISO Planning Conduct power flow studies and determine future Voltage/VAR requirements of the Grid. Page 4 of 13

5 2.0 Participating Entity Responsibilities Participating Generator The Participating Generator operates by the following: Step Action 1 Operate Generation within established protocols and procedures, specifically normal MW/VAR capacity profiles, at the applicable Voltage Schedule. 2 Comply with the Voltage Schedule in automatic voltage control mode (AVR in service and controlling voltage) 3 Produce or consume reactive power when requested by the CAISO. 4 Notify the CAISO of system conditions including, coordination of switching of Voltage Support equipment. 5 Notify the CAISO of events and changes that impact the MW/VAR capacity, reliability, or ability to operate within the power factor band. 6 Notify the applicable PTO and the CAISO as soon as practical, but within 30 minutes of changes to the status of automatic voltage regulators (AVRs) or power system stabilizers (PSSs). 7 Respond to Emergency Requests. NOTE: Compensation for Voltage Support will be in agreement with the CAISO Tariff (e.g., see section ). Page 5 of 13

6 Participating Load/UDCs The Participating Load/UDCs operates by the following Step Action 1 Operate in accordance with Good Utility Practice within established protocols and Operating Procedures, and adhere to specified Voltage Schedules. 2 Maintain reactive power flow at Grid interface points within the power factor band of 0.97 lag and 0.99 lead. 3 Notify the CAISO of system conditions including coordinated switching of Voltage Support equipment. 4 Notify the CAISO of events and changes that impact the Voltage Support equipment availability, reliability, or ability to operate within the power factor band. 5 Respond to CAISO requests for Voltage Support while operating within the power factor band. NOTE: The CAISO has the authority to request connected Loads/UDCs to provide uncompensated Voltage Support while operating in the power factor band. 6 Respond to Emergency Requests. Page 6 of 13

7 Participating Transmission Owners (PTOs) The Participating Transmission Owners operate by the following: Step Action 1 Operate the system in accordance with Good Utility Practice and in a manner that ensures safe and reliable operation. 2 Maintain appropriate Voltage Schedule(s). 3 When Then A Generators Operator or the Direct the Generator Operator Cal ISO notifies the PTO of to maintain or change either its changes to the status of voltage schedule or its automatic voltage regulators Reactive Power schedule as (AVRs) or power system appropriate. stabilizers (PSSs) 4 Notify the CAISO of system conditions and coordinate switching of Voltage Support equipment. 5 Notify the CAISO of events and changes that impact the Voltage Support equipment availability, or reliability. NOTE: The CAISO has the authority to coordinate the use of all Voltage Support equipment as required. 6 Respond to requests for Voltage Support. 7 Respond to Emergency Requests. Page 7 of 13

8 3.0 General Voltage/Var Control Guidance Adjusting Voltage, VARs, or Power Factors Use the table below for guidance on how to adjust voltage, VARs, or Power Factors (includes preventing voltage collapse): To increase voltage, produce VARs, and/or shift power factor towards lag Increase Generator Terminal Voltage [over-excite, move power factor toward lag] De-energize Shunt reactors Energize Shunt Capacitors Energize HVDC harmonic filters Boost synchronous condensers [over-excite, move power factor toward lead] Synchronize additional equipment [generators, condensers] capable of producing VARs Energize additional circuits [high voltage transmission lines and cables] Reduce load To decrease voltage, consume VARs, and/or shift power factor towards lead Decrease Generator Terminal Voltage [under-excite, move power factor toward lead] Energize shunt reactors De-energize Shunt Capacitors De-energize HVDC harmonic filters Buck synchronous condensers [under-excite, move power factor toward lag] Synchronize additional equipment capable of consuming VARs De-energize circuits [high voltage transmission lines and cables capable of being unloaded] Increase load (e.g. pump load) Page 8 of 13

9 Other measures The following are other miscellaneous measures that can be taken to adjust Voltage/VARS: Part Description 1 Transformer Bank Taps can be changed to push VARs. 2 Generally, increasing the high side voltage and decreasing the lowside voltage will cause VARs to flow towards the high side and away from the low side. 3 Series Capacitor switching will change the MW and VAR loading on associated line(s) and parallel lines. This will generally impact transfer capability. Voltage Guidelines The CAISO will use Protocols and power flow studies to establish and issue specific Voltages Schedules for specific circuits on the Grid. The general voltage guidelines are as follows: Nominal Voltage [kv] Operating Limits Ideal Voltage Range Voltage Schedules Refer to the Participating Entities Voltage/Var Schedules under their applicable Transmission Owner Procedures: UDC Procedure PG&E O-59 SCE SOB 017 SDG&E TMC 1005 LADWP Operating Bulletin 31 SMUD PSE 104 Page 9 of 13

10 Supporting Information Operationally Affected Parties N/A Posted on the Internet Responsibilities CAISO Participating Generators Participating Loads Transmission Owners Maintains acceptable voltage levels and VAR flow on the CAISO Controlled Grid using all voltage control support equipment required to meet the operating criteria specified in the NERC and WECC Minimum Operating Reliability Criteria. Participating Generators are required to operate within a specified power factor band. Generators operating within this range shall receive no compensation for Voltage Support. Notify the PTO & the CAISO of changes as soon as practical, but within 30 minutes to the status of AVRs and PSSs. Participating Loads are required to maintain VAR flow at Grid interface points within a specified power factor band. Loads operating within this range shall receive no compensation for Voltage Support. Transmission Owners operate Voltage Support equipment to maintain normal voltage and VAR flow according to the CAISO Protocols. Dispatch of voltage support equipment will not be compensated, provided that the specified power factor range is maintained. Page 10 of 13

11 References ISO Tariff Sections and CAISO Transmission Control Agreement PG&E Transmission System Voltage Control Procedure O-59 SCE System Operating Bulletin No. 17 SDG&E TMC 1005 LADWP Operating Bulletin 31 NERC Standard VAR bookmark: R4 VAR-001-1a bookmark: R1, R8, R9 Policy The CAISO operates the CAISO Controlled Grid as deemed appropriate to ensure System Reliability. This may include the use of any available voltage support equipment so that the operation of the CAISO Controlled Grid will meet or exceed the operating criteria as specified by the North American Electric Reliability Council (NERC) and the Western Electricity Coordinating Council (WECC). The CAISO will operate and monitor the system in accordance with the Good Utility Practice to ensure safe and reliable operations. Definitions Unless the context otherwise indicates, any word or expression defined in the Master Definitions Supplement to the CAISO Tariff shall have that meaning when capitalized in this Operating Procedure. The following additional terms are capitalized in this Operating Procedure when used as defined below: Participating Entity A Participating Generator, Participating Load/UDC, or PTO. Page 11 of 13

12 Version History Version Change By Date 1.0 Drafted 12/4/97 Reviewed 12/30/97 Revised 9/29/ Summer Update 6/5/ Semi-Annual review, no change 12/10/ Summer Update, no change 5/7/ Annual Review, no change 12/15/ New Format 8/16/ Step to monitor State Estimator results 11/30/ AVR & PSS 11/20/ Annual review and changed PG&E Procedure to O-59 and added O-59 as references 4/15/ Annual review and added SMUD Voltage Procedure PSE /21/ Annual Review, verified all information is correct and up to date. 12/8/09 Page 12 of 13

13 Technical Review Reviewed By Content Expert Operations Support Regional Transmission System Operations Market Ops Outage Management Scheduling Signature Date Approval Approved By Signature Date Director of Grid Operations Page 13 of 13

Voltage and Reactive Procedures CMP-VAR-01

Voltage and Reactive Procedures CMP-VAR-01 Voltage and Reactive Procedures CMP-VAR-01 NERC Standards: VAR-001-2 VAR-002-1.1b Effective Date: 07/31/2012 Document Information Current Revision 2.0 Review Cycle Annual Subject to External Audit? Yes

More information

Wind Power Facility Technical Requirements CHANGE HISTORY

Wind Power Facility Technical Requirements CHANGE HISTORY CHANGE HISTORY DATE VERSION DETAIL CHANGED BY November 15, 2004 Page 2 of 24 TABLE OF CONTENTS LIST OF TABLES...5 LIST OF FIGURES...5 1.0 INTRODUCTION...6 1.1 Purpose of the Wind Power Facility Technical

More information

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting Document C-29 Procedures for System Modeling: January 5 th, 2016 TFSS Revisions Clean Open Process Posting Prepared by the SS-37 Working Group on Base Case Development for the Task Force on System Studies.

More information

Generation and Load Interconnection Standard

Generation and Load Interconnection Standard Generation and Load Interconnection Standard Rev. 0A DRAFT Name Signature Date Prepared: Approved: VP Acceptance APEGGA Permit to Practice P-08200 TABLE OF CONTENTS 1.0 INTRODUCTION...5 1.1 Purpose...5

More information

Generation and Load Interconnection Standard

Generation and Load Interconnection Standard Generation and Load Interconnection Standard Rev. 0 DRAFT Name Signature Date Prepared: Approved: VP Acceptance APEGGA Permit to Practice P-08200 TABLE OF CONTENTS 1.0 INTRODUCTION...5 1.1 Purpose...5

More information

Standard VAR Voltage and Reactive Control

Standard VAR Voltage and Reactive Control A. Introduction 1. Title: Voltage and Reactive Control 2. Number: VAR-001-3 3. Purpose: To ensure that voltage levels, reactive flows, and reactive resources are monitored, controlled, and maintained within

More information

Standard VAR b Generator Operation for Maintaining Network Voltage Schedules

Standard VAR b Generator Operation for Maintaining Network Voltage Schedules A. Introduction 1. Title: Generator Operation for Maintaining Network Voltage Schedules 2. Number: VAR-002-1.1b 3. Purpose: To ensure generators provide reactive and voltage control necessary to ensure

More information

VAR Voltage and Reactive Control

VAR Voltage and Reactive Control VAR-001-4 Voltage and Reactive Control A. Introduction 1. Title: Voltage and Reactive Control 2. Number: VAR-001-4 3. Purpose: To ensure that voltage levels, reactive flows, and reactive resources are

More information

A. Introduction. VAR Voltage and Reactive Control

A. Introduction. VAR Voltage and Reactive Control A. Introduction 1. Title: Voltage and Reactive Control 2. Number: VAR-001-4.2 3. Purpose: To ensure that voltage levels, reactive flows, and reactive resources are monitored, controlled, and maintained

More information

VAR Voltage and Reactive Control. A. Introduction

VAR Voltage and Reactive Control. A. Introduction VAR-001-5 Voltage and Reactive Control A. Introduction 1. Title: Voltage and Reactive Control 2. Number: VAR-001-5 3. Purpose: To ensure that voltage levels, reactive flows, and reactive resources are

More information

VAR Generator Operation for Maintaining Network Voltage Schedules

VAR Generator Operation for Maintaining Network Voltage Schedules A. Introduction 1. Title: Generator Operation for Maintaining Network Voltage Schedules 2. Number: VAR-002-4 3. Purpose: To ensure generators provide reactive support and voltage control, within generating

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements Division 502 Technical Applicability 1(1) Section 502.1 applies to: Expedited Filing Draft August 22, 2017 the legal owner of an aggregated generating facility directly connected to the transmission system

More information

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules. 45-day Formal Comment Period with Initial Ballot June July 2014

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules. 45-day Formal Comment Period with Initial Ballot June July 2014 Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

VAR Generator Operation for Maintaining Network Voltage Schedules

VAR Generator Operation for Maintaining Network Voltage Schedules A. Introduction 1. Title: Generator Operation for Maintaining Network Voltage Schedules 2. Number: VAR-002-3 3. Purpose: To ensure generators provide reactive support and voltage control, within generating

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements Section 502.8 SCADA Technical and Operating Applicability 1 Section 502.8 applies to: (a) the legal owner of a generating unit: (i) connected to the transmission facilities in the balancing authority area

More information

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

VAR Generator Operation for Maintaining Network Voltage Schedules

VAR Generator Operation for Maintaining Network Voltage Schedules Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF LARGE GENERATION FACILITIES. Document 9020

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF LARGE GENERATION FACILITIES. Document 9020 TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF LARGE GENERATION FACILITIES Document 9020 Puget Sound Energy, Inc. PSE-TC-160.50 December 19, 2016 TABLE OF CONTENTS

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements Section 502.8 SCADA Technical and Operating Requirements Applicability 1 Subject to subsections 2 and 3 below, section 502.8 applies to: (a) (c) (d) the legal owner of a generating unit or an aggregated

More information

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF GENERATION FACILITIES NOT SUBJECT TO FERC JURISDICTION

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF GENERATION FACILITIES NOT SUBJECT TO FERC JURISDICTION TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF GENERATION FACILITIES NOT SUBJECT TO FERC JURISDICTION Document 9022 Puget Sound Energy, Inc. PSE-TC-160.70 December

More information

VAR Generator Operation for Maintaining Network Voltage Schedules

VAR Generator Operation for Maintaining Network Voltage Schedules A. Introduction 1. Title: Generator Operation for Maintaining Network Voltage Schedules 2. Number: VAR-002-3 3. Purpose: To ensure generators provide reactive support and voltage control, within generating

More information

Unit Auxiliary Transformer (UAT) Relay Loadability Report

Unit Auxiliary Transformer (UAT) Relay Loadability Report Background and Objective Reliability Standard, PRC 025 1 Generator Relay Loadability (standard), developed under NERC Project 2010 13.2 Phase 2 of Relay Loadability: Generation, was adopted by the NERC

More information

COS MANUAL. March 24, Version 1.2. Outage Coordination Process. Peak Reliability. Version 1.0. NERC Reliability Standard IRO-017-1

COS MANUAL. March 24, Version 1.2. Outage Coordination Process. Peak Reliability. Version 1.0. NERC Reliability Standard IRO-017-1 Outage Coordination Process Version 1.0 NERC Reliability Standard IRO-017-1 COS MANUAL March 24, 2017 www.peakrc.com. Contents 1. Conventions... 2 2. Introduction... 2 3. Purpose... 2 4. Applicability...

More information

Industry Webinar. Reactive Power Planning. NERC System Analysis and Modeling Subcommittee (SAMS) March 2017

Industry Webinar. Reactive Power Planning. NERC System Analysis and Modeling Subcommittee (SAMS) March 2017 Industry Webinar Reactive Power Planning NERC System Analysis and Modeling Subcommittee (SAMS) March 2017 Webinar Topics Reliability Guideline on Reactive Power Planning Webinar Topics Fundamentals of

More information

1

1 Guidelines and Technical Basis Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive

More information

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR SMALL GENERATION INTERCONNECTIONS

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR SMALL GENERATION INTERCONNECTIONS TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR SMALL GENERATION INTERCONNECTIONS Puget Sound Energy, Inc. PSE-ET-160.60 October 30, 2007 TABLE OF CONTENTS 1. INTRODUCTION...1 1.1 GENERAL

More information

VAR Generator Operation for Maintaining Network Voltage Schedules

VAR Generator Operation for Maintaining Network Voltage Schedules Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Wide Area Voltage Dispatch. - Case studies of ISO New England using NETSS AC XOPF program

Wide Area Voltage Dispatch. - Case studies of ISO New England using NETSS AC XOPF program Wide Area Voltage Dispatch - Case studies of ISO New England using NETSS AC XOPF program Xiaochuan Luo ISO New England Inc Marija Ilic, Jeff Lang NETSS Inc. EPRI AVC Workshop PJM, Norristown, PA May 19,

More information

Fundamental Concepts of Dynamic Reactive Compensation. Outline

Fundamental Concepts of Dynamic Reactive Compensation. Outline 1 Fundamental Concepts of Dynamic Reactive Compensation and HVDC Transmission Brian K. Johnson University of Idaho b.k.johnson@ieee.org 2 Outline Objectives for this panel session Introduce Basic Concepts

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements Applicability 1(1) Section 502.1 applies to the ISO, and subject to the provisions of subsections 1(2), (3) and (4) to any: (a) a new wind aggregated generating facility to be connected to the transmission

More information

15.2 Rate Schedule 2 - Payments for Supplying Voltage Support Service

15.2 Rate Schedule 2 - Payments for Supplying Voltage Support Service 15.2 Rate pport Service This Rate Schedule applies to payments to Suppliers who provide Voltage Support Service to the ISO. Transmission Customers and Customers will purchase Voltage Support Service from

More information

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/ ITC Holdings Planning Criteria Below 100 kv * Category: Planning Type: Policy Eff. Date/Rev. # 12/09/2015 000 Contents 1. Goal... 2 2. Steady State Voltage & Thermal Loading Criteria... 2 2.1. System Loading...

More information

August 25, Please contact the undersigned if you have any questions concerning this filing.

August 25, Please contact the undersigned if you have any questions concerning this filing. !! August 25, 2017 VIA ELECTRONIC FILING Ms. Erica Hamilton, Commission Secretary British Columbia Utilities Commission Box 250, 900 Howe Street Sixth Floor Vancouver, B.C. V6Z 2N3 Re: North American Electric

More information

August 25, 2017 VIA ELECTRONIC FILING

August 25, 2017 VIA ELECTRONIC FILING !! August 25, 2017 VIA ELECTRONIC FILING Kirsten Walli, Board Secretary Ontario Energy Board P.O Box 2319 2300 Yonge Street Toronto, Ontario, Canada M4P 1E4 Re: North American Electric Reliability Corporation

More information

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: IDAHO POWER COMPANY Designated Contact Person: Jeremiah Creason Address: 1221 W. Idaho Street, Boise ID 83702 Telephone

More information

Transmission Interconnection Requirements for Inverter-Based Generation

Transmission Interconnection Requirements for Inverter-Based Generation Transmission Requirements for Inverter-Based Generation June 25, 2018 Page 1 Overview: Every generator interconnecting to the transmission system must adhere to all applicable Federal and State jurisdictional

More information

Facility Interconnection Requirements for Colorado Springs Utilities Version 03 TABLE OF CONTENTS

Facility Interconnection Requirements for Colorado Springs Utilities Version 03 TABLE OF CONTENTS TABLE OF CONTENTS 1.0 INTRODUCTION (NERC FAC-001 Requirement R1, R2)... 4 2.0 INTERCONNECTION REQUIREMENTS FOR GENERATION, TRANSMISSION, AND END-USER FACILITIES (NERC FAC-001 Requirements R3 & R4)... 4

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION North American Electric Reliability Corporation ) ) Docket No. PETITION OF THE NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION FOR

More information

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction A. Introduction 1. Title: Generator Frequency and Voltage Protective Relay Settings 2. Number: PRC-024-1 3. Purpose: Ensure Generator Owners set their generator protective relays such that generating units

More information

Transmission Interconnection Handbooks For NERC Reliability Compliance Program. Pacific Gas and Electric Company. Combined Version

Transmission Interconnection Handbooks For NERC Reliability Compliance Program. Pacific Gas and Electric Company. Combined Version Transmission Interconnection Handbooks For NERC Reliability Compliance Program Pacific Gas and Electric Company Combined Version Effective Date: January 25, 2012 Table of Contents TABLE OF CONTENTS...

More information

Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES

Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES Purpose This section specifies the requirements for protective relays and control devices for Generation Entities interconnecting

More information

Final ballot January BOT adoption February 2015

Final ballot January BOT adoption February 2015 Standard PRC-024-21(X) Generator Frequency and Voltage Protective Relay Settings Standard Development Timeline This section is maintained by the drafting team during the development of the standard and

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

VAR Outreach Presentation

VAR Outreach Presentation VAR Outreach Presentation Soo Jin Kim, NERC Standards Developer November 4, 2013 Administrative Items NERC Antitrust Guidelines It is NERC s policy and practice to obey the antitrust laws and to avoid

More information

Southern Company Interconnection Requirements for Inverter-Based Generation

Southern Company Interconnection Requirements for Inverter-Based Generation Southern Company Interconnection Requirements for Inverter-Based Generation September 19, 2016 Page 1 of 16 All inverter-based generation connected to Southern Companies transmission system (Point of Interconnection

More information

WECC Standard VAR-002-WECC-2 Automatic Voltage Regulators

WECC Standard VAR-002-WECC-2 Automatic Voltage Regulators Document Title File Name Category Document date Adopted/approved by Date adopted/approved Custodian (entity responsible for maintenance and upkeep) Stored/filed Previous name/number Status Automatic Voltage

More information

Indication of Dynamic Model Validation Process

Indication of Dynamic Model Validation Process Indication of Dynamic Model Validation Process Document Identifier Written by David Cashman Document Version Draft Checked by Date of Current Issue November 2013 Approved by Jon O Sullivan Disclaimer EirGrid,

More information

DUKE ENERGY CAROLINAS TRANSMISSION SYSTEM PLANNING GUIDELINES. Transmission Planning

DUKE ENERGY CAROLINAS TRANSMISSION SYSTEM PLANNING GUIDELINES. Transmission Planning DUKE ENERGY CAROLINAS TRANSMISSION SYSTEM PLANNING GUIDELINES Transmission Planning TABLE OF CONTENTS I. SCOPE 1 II. TRANSMISSION PLANNING OBJECTIVES 2 III. PLANNING ASSUMPTIONS 3 A. Load Levels 3 B. Generation

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

SRI VIDYA COLLEGE OF ENGG AND TECH

SRI VIDYA COLLEGE OF ENGG AND TECH EEE6603 PSOC Page 1 UNIT-III REACTIVE POWER VOLTAGE CONTROL 1. List the various components of AVR loop? The components of automatic voltage regulator loop are exciter, comparator, amplifier, rectifier

More information

GENERAL REQUIREMENTS FOR TRANSMISSION INTERCONNECTION

GENERAL REQUIREMENTS FOR TRANSMISSION INTERCONNECTION GENERAL REQUIREMENTS FOR TRANSMISSION INTERCONNECTION May 31 st, 2017 Rev. 04 Public Utility District No. 2 of Grant County P.O. Box 878, Ephrata, WA 98823 (509) 754-0500 GENERAL REQUIREMENTS FOR INTERCONNECTION

More information

September 19, Errata to Implementation Plan for the Revised Definition of Remedial Action Scheme

September 19, Errata to Implementation Plan for the Revised Definition of Remedial Action Scheme !! September 19, 2017 VIA ELECTRONIC FILING Veronique Dubois Régie de l'énergie Tour de la Bourse 800, Place Victoria Bureau 255 Montréal, Québec H4Z 1A2 RE: Errata to for the Revised Definition of Remedial

More information

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC A. Introduction 1. Title: Generator Frequency and Voltage Protective Relay Settings 2. Number: PRC-024-2 3. Purpose: Ensure Generator Owners set their generator protective relays such that generating units

More information

Real Time Stability Analysis at Peak Reliability. Slaven Kincic, Hongming Zhang JSIS May 2017, SLC

Real Time Stability Analysis at Peak Reliability. Slaven Kincic, Hongming Zhang JSIS May 2017, SLC Real Time Stability Analysis at Peak Reliability Slaven Kincic, Hongming Zhang JSIS May 2017, SLC Overview: Overview of Peak s DSA Application; o Set up o User Cases Transient Stability Criteria; TSAT

More information

BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 7T-30A. NORTH COAST INTERCONNECTION: SKEENA BOB QUINN SUBSYSTEM Supersedes OO 7T-30A dated 07 July 2014

BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 7T-30A. NORTH COAST INTERCONNECTION: SKEENA BOB QUINN SUBSYSTEM Supersedes OO 7T-30A dated 07 July 2014 BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 7T-30A NORTH COAST INTERCONNECTION: SKEENA BOB QUINN SUBSYSTEM Supersedes OO 7T-30A dated 07 July 2014 Expiry Year: 2018 APPROVED BY: Original signed by: Paul

More information

Central Hudson Gas & Electric Corporation. Transmission Planning Guidelines

Central Hudson Gas & Electric Corporation. Transmission Planning Guidelines Central Hudson Gas & Electric Corporation Transmission Planning Guidelines Version 4.0 March 16, 2016 Version 3.0 March 16, 2009 Version 2.0 August 01, 1988 Version 1.0 June 26, 1967 Table of Contents

More information

Testing model data usability Excitation Systems PSS Limiters

Testing model data usability Excitation Systems PSS Limiters 1 2016 IEEE/PES General Meeting July 17 th -21 st, 2016 Boston, MA Panel Session Use of the New Revisions of IEEE Std. 421.2 and 421.5 to Satisfy International Grid Code Requirements Testing model data

More information

Keeping it up to Speed Off-Nominal Frequency Operations. CETAC 2018 San Ramon

Keeping it up to Speed Off-Nominal Frequency Operations. CETAC 2018 San Ramon Keeping it up to Speed Off-Nominal Frequency Operations CETAC 2018 San Ramon 1 Welcome CETAC 2018 San Ramon Valley Conference Center General Class Information: Safety/Fire evacuation In event of emergency,

More information

THIS DOCUMENT IS RETIRED BY FERC EFFECTIVE SEPTEMBR 5, 2018.

THIS DOCUMENT IS RETIRED BY FERC EFFECTIVE SEPTEMBR 5, 2018. THIS DOCUMENT IS RETIRED BY FERC EFFECTIVE SEPTEMBR 5, 2018. A. Introduction 1. Title: Automatic Voltage Regulators (AVR) 2. Number: VAR-002-WECC-2 3. Purpose: To ensure that Automatic Voltage Regulators

More information

May 30, Errata to Implementation Plan for the Revised Definition of Remedial Action Scheme Docket No. RM15-13-_

May 30, Errata to Implementation Plan for the Revised Definition of Remedial Action Scheme Docket No. RM15-13-_ May 30, 2018 VIA ELECTRONIC FILING Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C. 20426 RE: Errata to for the Revised Definition of Remedial Action

More information

Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES

Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES Purpose This section specifies the requirements for protective relays and control devices for Generation Entities interconnecting

More information

San Diego Gas & Electric Company Generation Interconnection Handbook

San Diego Gas & Electric Company Generation Interconnection Handbook San Diego Gas & Electric Company Generation Interconnection Handbook For Generators Interconnecting to SDG&E-Owned Transmission Facilities 1 1 For generators interconnecting

More information

Central East Voltage and Stability Analysis for Marcy FACTS Project Phase I

Central East Voltage and Stability Analysis for Marcy FACTS Project Phase I Prepared by NYISO Operations Engineering 1. INTRODUCTION Central East Voltage and Stability Analysis for The Marcy Flexible AC Transmission System (FACTS) project is a joint technology partnership between

More information

HOOSIER ENERGY REC, INC. Requirements for Connection of Generation Facilities. to the HE Transmission System

HOOSIER ENERGY REC, INC. Requirements for Connection of Generation Facilities. to the HE Transmission System HOOSIER ENERGY REC, INC Requirements for Connection of Generation Facilities to the HE Transmission System January 2009 Table of Contents 1.0 INTRODUCTION...1 2.0 TYPES OF CONNECTED CIRCUIT CONFIGURATIONS...6

More information

New HVDC Interaction between AC networks and HVDC Shunt Reactors on Jeju Converter Stations

New HVDC Interaction between AC networks and HVDC Shunt Reactors on Jeju Converter Stations New HVDC Interaction between AC networks 233 JPE 7-3-6 New HVDC Interaction between AC networks and HVDC Shunt Reactors on Jeju Converter Stations Chan-Ki Kim, Young-Hun Kwon * and Gil-Soo Jang ** KEPRI,

More information

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. April 2009 Version 2

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. April 2009 Version 2 MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS April 2009 Version 2 LEGISLATIVE AUTHORITY Section 15(5) of The Manitoba Hydro Act authorizes Manitoba Hydro to set, coordinate and enforce

More information

FACILITY CONNECTION REQUIREMENTS

FACILITY CONNECTION REQUIREMENTS Portland General Electric Facility Connection Requirements - Generation Resources FACILITY CONNECTION REQUIREMENTS FOR GENERATION RESOURCES PORTLAND GENERAL ELECTRIC PORTLAND, OREGON JULY 12, 2013 REVISION

More information

BEFORE THE ALBERTA ELECTRIC SYSTEM OPERATOR

BEFORE THE ALBERTA ELECTRIC SYSTEM OPERATOR BEFORE THE ALBERTA ELECTRIC SYSTEM OPERATOR NORTH AMERICAN ELECTRIC ) RELIABILITY CORPORATION ) NOTICE OF FILING OF THE NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION OF PROPOSED RELIABILITY STANDARD

More information

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES Highgate Converter Overview Prepared by Joshua Burroughs & Jeff Carrara IEEE PES Highgate Converter Abstract Introduction to HVDC Background on Highgate Operation and Control schemes of Highgate 22 Why

More information

Table of Contents. Introduction... 1

Table of Contents. Introduction... 1 Table of Contents Introduction... 1 1 Connection Impact Assessment Initial Review... 2 1.1 Facility Design Overview... 2 1.1.1 Single Line Diagram ( SLD )... 2 1.1.2 Point of Disconnection - Safety...

More information

Integration of Wind Generation into Weak Grids

Integration of Wind Generation into Weak Grids Integration of Wind Generation into Weak Grids Jason MacDowell GE Energy Consulting NERC ERSTF Atlanta, GA December 10-11, 2014 Outline Conventional and Power Electronic (PE) Sources Stability limitations

More information

CAISO Restricted - Do Not Distribute Outside of RC Project LOI and NDA Entities Page 1 of 24

CAISO Restricted - Do Not Distribute Outside of RC Project LOI and NDA Entities Page 1 of 24 RC0120A - RC IRO-010 Data Specification NOTE: Changes from Peak's Attachment A are highlighted in red in columns C through G Section Category Number Responsible Pa Data Item Data Transfer Method 1.1 Transmission

More information

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. July 2016 Version 4

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. July 2016 Version 4 MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS July 2016 Version 4 This page intentionally blank LEGISLATIVE AUTHORITY Section 15.0.3(1) of The Manitoba Hydro Act (C.C.S.M. c. H190) authorizes

More information

Implementation Plan Project Alignment of Terms

Implementation Plan Project Alignment of Terms Revisions to Defined Terms in the NERC Glossary of Terms Used in Reliability Standards The drafting team proposes modifying the following Glossary of Terms definitions: Blackstart Resource

More information

Recently, the SS38 Working Group on Inter-Area Dynamic Analysis completed two study reports on behalf of the UFLS Regional Standard Drafting Team.

Recently, the SS38 Working Group on Inter-Area Dynamic Analysis completed two study reports on behalf of the UFLS Regional Standard Drafting Team. December 7 th, 2010 NPCC Full Member Committee; Please find attached a draft revised NPCC Regional Reliability Directory #12 Underfrequency Load Shedding Program Requirements and a draft revised NPCC UFLS

More information

Cover Sheet. Technical Justification Retirement of WECC Regional Reliability Standard VAR-002-WECC-2 Automatic Voltage Regulators (AVR)

Cover Sheet. Technical Justification Retirement of WECC Regional Reliability Standard VAR-002-WECC-2 Automatic Voltage Regulators (AVR) Cover Sheet Attachment G (AVR) Retirement of WECC Regional Reliability Standard VAR-002-WECC-2 (AVR) Page 1 of 23 Request to Retire White Paper Retirement of WECC Regional Reliability Standard VAR-002-WECC-2

More information

Grid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017

Grid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017 Grid codes and wind farm interconnections CNY Engineering Expo Syracuse, NY November 13, 2017 Purposes of grid codes Grid codes are designed to ensure stable operating conditions and to coordinate the

More information

Standard PRC Coordination of Generating Unit or Plant Voltage Regulating Controls with Generating Unit or Plant Capabilities and Protection

Standard PRC Coordination of Generating Unit or Plant Voltage Regulating Controls with Generating Unit or Plant Capabilities and Protection Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed:

More information

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY WN U-60 Attachment C to Schedule 152, Page 1 SCHEDULE 152 APPLICATION FOR INTERCONNECTING A GENERATING FACILITY TIER 2 OR TIER 3 This Application is considered complete when it provides all applicable

More information

VOLTAGE STABILITY OF THE NORDIC TEST SYSTEM

VOLTAGE STABILITY OF THE NORDIC TEST SYSTEM 1 VOLTAGE STABILITY OF THE NORDIC TEST SYSTEM Thierry Van Cutsem Department of Electrical and Computer Engineering University of Liège, Belgium Modified version of a presentation at the IEEE PES General

More information

NPCC Regional Reliability Reference Directory # 12. Underfrequency Load Shedding Program Requirements

NPCC Regional Reliability Reference Directory # 12. Underfrequency Load Shedding Program Requirements NPCC Regional Reliability Reference Directory # 12 Under frequency Load Shedding Program Requirements Task Force on System Studies Revision Review Record: June 26 th, 2009 March 3 rd, 2010 Adopted by the

More information

Voltage Control with Distributed Generators to Enhance Voltage Stability

Voltage Control with Distributed Generators to Enhance Voltage Stability Advanced Electricity Infrastructure Workshop Global Climate & Energy Project STANFORD UNIVERSITY, Nov. 1~2, 2007 Voltage Control with Distributed Generators to Enhance Voltage Stability Presenter: Fangxing

More information

EH2741 Communication and Control in Electric Power Systems Lecture 2

EH2741 Communication and Control in Electric Power Systems Lecture 2 KTH ROYAL INSTITUTE OF TECHNOLOGY EH2741 Communication and Control in Electric Power Systems Lecture 2 Lars Nordström larsno@kth.se Course map Outline Transmission Grids vs Distribution grids Primary Equipment

More information

GUIDE FOR GENERATOR INTERCONNECTION THE WIRES OWNER DISTRIBUTION SYSTEM

GUIDE FOR GENERATOR INTERCONNECTION THE WIRES OWNER DISTRIBUTION SYSTEM DATE: 200/06/2 PAGE 1 of GUIDE FOR GENERATOR INTERCONNECTION TO THE WIRES OWNER DISTRIBUTION SYSTEM The intent of this Guide is to establish the interconnection requirements of Distributed Resources with

More information

GUIDELINES FOR UTILIZATION OF FREQUENCY AND TIME ERROR DEVICES AND CALIBRATING TIE LINE SIGNAL

GUIDELINES FOR UTILIZATION OF FREQUENCY AND TIME ERROR DEVICES AND CALIBRATING TIE LINE SIGNAL Document name Category Document date March 11, 2003 Adopted/approved by GUIDELINES FOR UTILIZATION OF FREQUENCY AND TIME ERROR DEVICES AND CALIBRATING TIE LINE SIGNAL ( ) Regional Reliability Standard

More information

METERING REQUIREMENTS FOR INTERCONNECTION POINTS OF SERVICE

METERING REQUIREMENTS FOR INTERCONNECTION POINTS OF SERVICE METERING REQUIREMENTS FOR INTERCONNECTION POINTS OF SERVICE Author: AXLIU Origination Date: 05/07/2010 Version: 8.3 Revised By: Approver s Name: OXPAIS REROMAK REROMAK 1 PURPOSE Revision Date: 9/12/2016

More information

NERC / TVA STABILITY WORKSHOP

NERC / TVA STABILITY WORKSHOP NERC / TVA STABILITY WORKSHOP CHATTANOOGA, TN MAY 23-24, 24, 2007 Robert Dintelman Utility System Efficiencies, Inc. WECC Transmission System 1996 Western Outages July 2, 1996 July 3, 1996 August 10, 1996

More information

5. Effective Date: On the first day of the first quarter, after applicable regulatory approval.

5. Effective Date: On the first day of the first quarter, after applicable regulatory approval. A. Introduction 1. Title: Automatic Voltage Regulators (AVR) 2. Number: VAR-002-WECC-2 3. Purpose: To ensure that Automatic Voltage Regulators on synchronous generators and condensers shall be kept in

More information

Functional Specification Revision History

Functional Specification Revision History Functional Specification Revision History Revision Description of Revision By Date V1D1 For Comments Yaoyu Huang October 27, 2016 V1 For Issuance Yaoyu Huang November 21, 2016 Section 5.3 updated Transformer

More information

Power Plant and Transmission System Protection Coordination of-field (40) and Out-of. of-step Protection (78)

Power Plant and Transmission System Protection Coordination of-field (40) and Out-of. of-step Protection (78) Power Plant and Transmission System Protection Coordination Loss-of of-field (40) and Out-of of-step Protection (78) System Protection and Control Subcommittee Protection Coordination Workshop Phoenix,

More information

Rule 21 Working Group 3.

Rule 21 Working Group 3. Rule 21 Working Group 3 SIWG CALL ISSUES 27 AND 28 DECEMBER 19, 2018 https://gridworks.org/initiatives/rule-21-working-group-3/ Agenda 2:00-2:10 Schedule and introduction Issues 27 & 28 2:10-2:30 Issue

More information

NERC Protection Coordination Webinar Series June 30, Dr. Murty V.V.S. Yalla

NERC Protection Coordination Webinar Series June 30, Dr. Murty V.V.S. Yalla Power Plant and Transmission System Protection ti Coordination Loss-of-Field (40) and Out-of of-step Protection (78) NERC Protection Coordination Webinar Series June 30, 2010 Dr. Murty V.V.S. Yalla Disclaimer

More information

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number: Address:

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number:  Address: NORTH CAROLINA INTERCONNECTION REQUEST Utility: Designated Contact Person: Address: Telephone Number: Fax: E-Mail Address: An is considered complete when it provides all applicable and correct information

More information

IEEE Major Revision of Interconnection Standard

IEEE Major Revision of Interconnection Standard IEEE 1547-2018 - Major Revision of Interconnection Standard NRECA & APA s Emerging Priorities in Energy Research Day, Anchorage, AK Charlie Vartanian PE Secretary, IEEE 1547 Working Group October 31, 2018

More information

Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing Methods

Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing Methods Proceedings of the th WSEAS International Conference on Power Systems, Beijing, China, September -, 200 Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing

More information

Canadian Technology Accreditation Criteria (CTAC) POWER SYSTEMS ENGINEERING TECHNOLOGY - TECHNICIAN Technology Accreditation Canada (TAC)

Canadian Technology Accreditation Criteria (CTAC) POWER SYSTEMS ENGINEERING TECHNOLOGY - TECHNICIAN Technology Accreditation Canada (TAC) Canadian Technology Accreditation Criteria (CTAC) POWER SYSTEMS ENGINEERING TECHNOLOGY - TECHNICIAN Technology Accreditation Canada (TAC) Preamble These CTAC are applicable to programs having titles involving

More information

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications 1 1 1 1 1 1 1 1 0 1 0 1 0 1 Reliability Guideline: Generating Unit Operations During Complete Loss of Communications Preamble: It is in the public interest for the North American Electric Reliability Corporation

More information

ESB National Grid Transmission Planning Criteria

ESB National Grid Transmission Planning Criteria ESB National Grid Transmission Planning Criteria 1 General Principles 1.1 Objective The specific function of transmission planning is to ensure the co-ordinated development of a reliable, efficient, and

More information

2.4 Modeling on reactive power or voltage control. Saadat s Chapters Kundur s Chapters 5.4, 8 and 11.2 EPRI Tutorial s Chapter 5

2.4 Modeling on reactive power or voltage control. Saadat s Chapters Kundur s Chapters 5.4, 8 and 11.2 EPRI Tutorial s Chapter 5 2.4 Modeling on reactive power or voltage control Saadat s Chapters 12.6 12.7 Kundur s Chapters 5.4, 8 and 11.2 EPRI Tutorial s Chapter 5 1 Objectives of Reactive Power and Voltage Control Equipment security:

More information