GUIDELINES FOR UTILIZATION OF FREQUENCY AND TIME ERROR DEVICES AND CALIBRATING TIE LINE SIGNAL

Size: px
Start display at page:

Download "GUIDELINES FOR UTILIZATION OF FREQUENCY AND TIME ERROR DEVICES AND CALIBRATING TIE LINE SIGNAL"

Transcription

1 Document name Category Document date March 11, 2003 Adopted/approved by GUIDELINES FOR UTILIZATION OF FREQUENCY AND TIME ERROR DEVICES AND CALIBRATING TIE LINE SIGNAL ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy (x) Guideline ( ) Report or other ( ) Charter Board of Directors Date adopted/approved December 5, 2003 Custodian (entity responsible for maintenance and upkeep) Stored/filed Previous name/number (if any) Status Control Work Group Physical location: Web URL: (x) in effect ( ) usable, minor formatting/editing required ( ) modification needed ( ) superseded by ( ) other ( ) obsolete/archived)

2 WECC Guideline: UTILIZATION OF FREQUENCY AND TIME ERROR DEVICES AND CALIBRATING TIE LINE SIGNALS Date: March 11, 2003 These guidelines should be considered by Member Systems to provide acceptable interconnected system operation. The guidelines provide information for frequency, time error, and tie line control devices. The recommendations are intended to promote uniformity of control within the Western Electricity Coordinating Council (WECC) interconnected system without placing an undue burden on the Member Systems. If a Member System's present equipment does not meet these criteria, then an orderly replacement effort is expected. Specific values rather than general terms are provided below regarding accuracy, maintenance intervals, and availability. The intent is to provide better information for system managers in justifying and specifying the devices required for acceptable interconnected system operation. The values for accuracy were selected on the basis of recommendations made by the WECC Control Work Group. Within the recommended accuracy, the control errors for a WECC system with a bias of 300 or less will be approximately 1 percent of the bias for both time and frequency error. For systems with a bias greater than 300, the control errors should be 0.5 percent or better of the bias for both time and frequency error. Tie line telemetering error shall be 0.5% or better of the full scale of the tie line telemetry. Improved measurements for control and monitoring have material benefits. However, the direct value of control measurement improvement is difficult to quantify. A direct benefit of more accurate control is less inadvertent interchange. Improved monitoring accuracy greatly simplifies post-disturbance analysis. In general, the Control Work Group regards adequate control and monitoring facilities to be essential to meet the overall benefits of interconnected system operation. I. Time and Frequency Error Devices Low-cost, accurate time error and frequency devices are available and WECC Member Systems are encouraged to use such devices as described below: A. Time Error Devices -2-

3 1. Time error devices should have an internal oscillator drift of no more than 50 milliseconds per day. While operating on an internal oscillator the system's reference time will then not drift more than this amount between daily time error checks sent out by the WECC time error monitor. 2. The availability of time error control should be better than 99 percent when tie-line bias and automatic time error correction mode is being used in AGC. 3. The maximum error in conversion from the standard time to the time error in the control algorithm should not be greater than 50 milliseconds. 4. The time error device should be equipped with an easy means of resetting the time error by the dispatcher. 5. Periodic tests should be made to ensure drift and conversion accuracy of the time error used for control. These tests should be performed at least once a year or more frequently if required to ensure accuracy. 6. Suggested minimum sample rate is to use at least the same scan cycle as the generation control algorithm for interchange data acquisition. B. Frequency Devices 1. Use of dual scale frequency equipment is desirable. A narrow-band scale with high accuracy and resolution is recommended for control; a wide-band scale should be used for system disturbance monitoring. The narrow-band range is approximately Hz to Hz. The wide-band range is selected based on the control area's expected frequency deviation should it become separated from the remainder of the system. For example, 55.0 Hz to 65.0 Hz. 2. At least one alternate system frequency source for use during loss of the normal control center source is desirable. The alternate source should be from the main portion of the power system and be readily available for control input. A means should be provided to monitor the availability of the alternate source. 3. The frequency equipment accuracy times the frequency bias should be less than 2 MW. Telemetering accuracy criteria should apply for an alternate frequency source. For control purposes, if a control area's frequency bias setting is less than 150 MW/0.1Hz, the minimum accuracy for frequency deviation output equipment should be at least 0.01 Hz, including any final conversions for computing. Control areas with large bias settings should have an accuracy value of at least Hz. 4. Frequency devices for control should have the same availability as the system's generation control equipment. -3-

4 5. Frequency devices should be tested for accuracy with laboratory-quality measurement devices at least once a year or more frequently if required to ensure accuracy. 6. Frequency devices should respond to rapid changes at a rate of at least 1 Hz/sec. 7. Sample rates of frequency devices should be at least as fast as the generation control data acquisition rate. For disturbance monitoring, sampling up to 20 scans/sec is helpful. An alternative is to sample at least twice the frequency as the frequency of the information you are trying to capture (this is called the Shannon frequency). 8. Digital monitoring and retention of system frequency during a disturbance is recommended for systems with generation capacity greater than 500 MW to augment chart recorder record keeping. The range, accuracy, and sampling rate should be consistent with recommendations 1-7. A hardcopy as well as an electronic copy of the report should be provided upon request to enable postdisturbance frequency analysis. 9. Reasonably priced frequency transducers are available from several manufacturers, which provide at least 0.02% of center frequency accuracy (± Hz for 60 Hz). Most of these transducers utilize a nominal 120 VAC input with a millivolt or milliampere analog output which can be used to drive a strip chart recorder or an A/D converter. More sophisticated transducers with accuracy s up to Hz are available for larger control areas to meet the requirement of section I.B.3 and to provide greater control accuracy. II. Calibrating Tie Line Signals Tie line data from each point of interconnection should consist of a common accurate MWh energy reading and MW power flow signal to each control center. Continuous use of this data for control and accounting and for monitoring data accuracy by both parties to the interconnection is recommended. A. MW Telemetering 1. Digital control center computers easily integrate the telemetered MW power flow signal over an MWh energy measurement period. Automatic comparison of the integrated MW signal with the hourly accounting MWh reading is a proven method of monitoring the accuracy of the control data. This method should be used as much as possible by Member Systems. Telemetering found to be out of calibration should be corrected as soon as possible. 2. Systems that do not use digital computers for tie line data acquisition are encouraged to locate persistent errors by other methods, such as analog chart recorder analysis to compare tie line MW telemetering with MWh readings. -4-

5 3. Systems that are party to a tie line should use common metering and telemetering equipment associated with the tie line. With this arrangement, errors will cause bilateral inadvertent interchange between the parties and not affect other systems. Where deviations from the above occur, procedures for error checking must be established. 4. The accuracy of analog tie line MW telemetering is expected to be within 0.5 percent full scale, when the hourly integrated value is compared to MWh energy accounting. Overall accuracy of tie line telemetering signals from measurement and transmission and conversion to the control algorithm should be adjusted to 0.5 percent full scale when errors exceeding 1 percent full scale accuracy are detected. 5. If integrated MW values are not used to monitor tie line telemetering accuracy, the tie line telemetering devices should be tested and calibrated at least annually or as required to maintain accuracy for control. More frequent calibration is required if state-of-the-art, solid-state devices are not used. 6. Digital tie line MW telemetering equipment, which has greater accuracy than analog equipment is available and should meet or exceed the requirements specified in II.A.4. Use of digital equipment should be considered for new or replacement telemetering, particularly for high capacity tie lines. Accurate metering inputs remain a requirement. 7. It is recommended that high capacity tie lines have redundant MW telemetering communications to assure continuous availability. Redundant metering, in addition to telemetering, is desirable for the more critical high capacity tie lines. 8. Sampling rates should equal the generation control data acquisition rate. For disturbance monitoring, sampling rates as high as 20 scans/sec are useful. An alternative is to sample at a minimum Shannon frequency of the telemetered data. B. MWh Readings For Hourly Accounting 1. To ensure accurate MWh energy accounting readings, all control area tie line meters shall receive a single end-of-hour freeze signal. In addition, the single end-of-hour freeze signal shall be backed up by an automatic separate signal within five seconds of the primary freeze. Most kilowatt-hour remotes can be modified to block a secondary freeze signal within a specified time window. End-of-hour freeze signals should be triggered by a timing system or computer clock synchronized to the standard time receiver. 2. If two sets of meters are used, one reading must be considered primary and this reading used by both parties. The reading from the second set can be used for backup and comparison. -5-

6 3. Accounting MWh number corrections because of missing data or transmission errors should be corrected promptly and mutually by both parties in accordance with NERC Operating Manual. Approving Committee, Entity or Person Date Board of Directors December 5, 2003 Operating Committee October 30, 2003 Technical Operations Subcommittee September 15, 2003 Control Work Group - Drafted March 11,

Standard BAL-005-0b Automatic Generation Control

Standard BAL-005-0b Automatic Generation Control A. Introduction 1. Title: Automatic Generation Control 2. Number: BAL-005-0b 3. Purpose: This standard establishes requirements for Balancing Authority Automatic Generation Control (AGC) necessary to calculate

More information

Standard BAL b Automatic Generation Control

Standard BAL b Automatic Generation Control A. Introduction 1. Title: Automatic Generation Control 2. Number: BAL-005-0.2b 3. Purpose: This standard establishes requirements for Balancing Authority Automatic Generation Control (AGC) necessary to

More information

WECC Standard VAR-002-WECC-2 Automatic Voltage Regulators

WECC Standard VAR-002-WECC-2 Automatic Voltage Regulators Document Title File Name Category Document date Adopted/approved by Date adopted/approved Custodian (entity responsible for maintenance and upkeep) Stored/filed Previous name/number Status Automatic Voltage

More information

Standard BAL b Automatic Generation Control

Standard BAL b Automatic Generation Control A. Introduction 1. Title: Automatic Generation Control 2. Number: BAL-005-0.2b 3. Purpose: This standard establishes requirements for Balancing Authority Automatic Generation Control (AGC) necessary to

More information

Standard BAL b3 Automatic GenerationBalancing Authority Control DRAFT

Standard BAL b3 Automatic GenerationBalancing Authority Control DRAFT A. Introduction 1. Title: Balancing Authority ControlAutomatic Generation Control 2. Number: BAL-005-30.2b 3. Purpose: This standard establishes requirements for acquiring necessary data for the Balancing

More information

Calculating and Using Reporting ACE in a Tie Line Bias Control Program

Calculating and Using Reporting ACE in a Tie Line Bias Control Program Calculating and Using Reporting ACE in a Tie Line Bias Control Program Introduction: Tie Line Bias 1 (TLB) control has been used as the preferred control method in North America for 75 years. In the early

More information

MODEL POWER SYSTEM TESTING GUIDE October 25, 2006

MODEL POWER SYSTEM TESTING GUIDE October 25, 2006 October 25, 2006 Document name Category MODEL POWER SYSTEM TESTING GUIDE ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy ( ) Guideline ( x ) Report or other ( ) Charter Document date

More information

Reliability Guideline Integrating Reporting ACE with the NERC Reliability Standards

Reliability Guideline Integrating Reporting ACE with the NERC Reliability Standards Reliability Guideline Integrating Reporting ACE with the NERC Reliability Standards Applicability: Balancing Authorities (BAs) Introduction and Purpose: It is in the public interest for NERC to develop

More information

Lecture 15 EMS Application II Automatic Generation Contol. Davood Babazadeh

Lecture 15 EMS Application II Automatic Generation Contol. Davood Babazadeh Lecture 15 EMS Application II Automatic Generation Contol Davood Babazadeh 2015-12-03 Outline Generation Control - Why - How AGC design - Area Control Error - Parameter Calculation 2 Course road map 3

More information

Frequency Response Characteristic Survey Training Document

Frequency Response Characteristic Survey Training Document Frequency Response Characteristic Survey Training Document Training Document Subsections Frequency Response Characteristic Response to Internal and External Generation/Load Imbalances Frequency Bias versus

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Description of Current Draft

More information

Implementation Plan Project Balancing Authority Reliability-based Controls - Reserves

Implementation Plan Project Balancing Authority Reliability-based Controls - Reserves Implementation Plan Project 2010-14.1 Balancing Authority Reliability-based Controls - Reserves Implementation Plan for Approvals Required Prerequisite Approvals None Revisions to Glossary Terms The following

More information

Project Balancing Authority Reliability-based Controls Reliability Standard BAL-005-1

Project Balancing Authority Reliability-based Controls Reliability Standard BAL-005-1 Implementation Plan Project 2010-14.2.1 Balancing Authority Reliability-based Controls Reliability Standard BAL-005-1 Requested Approval s Requested Retirement BAL-005-0.2b Automatic Generation Control

More information

Monitoring and Situational Awareness Conference. Improving EMS Reliability Denver, CO September 18, 2013

Monitoring and Situational Awareness Conference. Improving EMS Reliability Denver, CO September 18, 2013 Monitoring and Situational Awareness Conference Hani Alarian Improving EMS Reliability Denver, CO September 18, 2013 Director, Power Systems Technology Operations, CAISO California ISO by the numbers 57,963

More information

HOOSIER ENERGY REC, INC. Requirements for Connection of Generation Facilities. to the HE Transmission System

HOOSIER ENERGY REC, INC. Requirements for Connection of Generation Facilities. to the HE Transmission System HOOSIER ENERGY REC, INC Requirements for Connection of Generation Facilities to the HE Transmission System January 2009 Table of Contents 1.0 INTRODUCTION...1 2.0 TYPES OF CONNECTED CIRCUIT CONFIGURATIONS...6

More information

Area Control Error (ACE) Equation Special Cases

Area Control Error (ACE) Equation Special Cases Area Control Error (ACE) Equation Special Cases Purpose: It is the obligation of each Balancing Authority to manage its Area Control Error in accordance with NERC reliability standards. This Standard provides

More information

Wind Power Facility Technical Requirements CHANGE HISTORY

Wind Power Facility Technical Requirements CHANGE HISTORY CHANGE HISTORY DATE VERSION DETAIL CHANGED BY November 15, 2004 Page 2 of 24 TABLE OF CONTENTS LIST OF TABLES...5 LIST OF FIGURES...5 1.0 INTRODUCTION...6 1.1 Purpose of the Wind Power Facility Technical

More information

METERING REQUIREMENTS FOR INTERCONNECTION POINTS OF SERVICE

METERING REQUIREMENTS FOR INTERCONNECTION POINTS OF SERVICE METERING REQUIREMENTS FOR INTERCONNECTION POINTS OF SERVICE Author: AXLIU Origination Date: 05/07/2010 Version: 8.3 Revised By: Approver s Name: OXPAIS REROMAK REROMAK 1 PURPOSE Revision Date: 9/12/2016

More information

Protection Test Guidelines.pdf

Protection Test Guidelines.pdf Document Title File Name Category Guidelines for OEL and OEP Testing GuidelinesforOELandOEPTesting.pdf ( ) Regional reliability standard ( ) Regional criteria ( ) Policy (X) Guideline ( ) Report or other

More information

Alberta Reliability Standard Frequency Response and Frequency Bias Setting BAL-003-AB-1.1

Alberta Reliability Standard Frequency Response and Frequency Bias Setting BAL-003-AB-1.1 1. Purpose The purpose of this reliability standard is to: (a) require sufficient frequency response from the ISO to maintain Interconnection frequency within predefined bounds by arresting frequency deviations

More information

Keeping it up to Speed Off-Nominal Frequency Operations. CETAC 2018 San Ramon

Keeping it up to Speed Off-Nominal Frequency Operations. CETAC 2018 San Ramon Keeping it up to Speed Off-Nominal Frequency Operations CETAC 2018 San Ramon 1 Welcome CETAC 2018 San Ramon Valley Conference Center General Class Information: Safety/Fire evacuation In event of emergency,

More information

Table 1 - Assignment of BA Obligations... 8

Table 1 - Assignment of BA Obligations... 8 Dynamic Transfer Reference Guidelines Version 2 June 2010 Table of Contents Table of Contents Chapter 1 Overview... 3 Purpose... 3 Terms... 3 Chapter 2 Dynamic Schedule Versus Pseudo-tie Fundamentals...

More information

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications 1 1 1 1 1 1 1 1 0 1 0 1 0 1 Reliability Guideline: Generating Unit Operations During Complete Loss of Communications Preamble: It is in the public interest for the North American Electric Reliability Corporation

More information

Final ballot January BOT adoption February 2015

Final ballot January BOT adoption February 2015 Standard PRC-024-21(X) Generator Frequency and Voltage Protective Relay Settings Standard Development Timeline This section is maintained by the drafting team during the development of the standard and

More information

1

1 Guidelines and Technical Basis Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive

More information

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction A. Introduction 1. Title: Generator Frequency and Voltage Protective Relay Settings 2. Number: PRC-024-1 3. Purpose: Ensure Generator Owners set their generator protective relays such that generating units

More information

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications 1 1 1 1 1 1 1 1 0 1 0 1 0 1 Reliability Guideline: Generating Unit Operations During Complete Loss of Communications Preamble It is in the public interest for the North American Electric Reliability Corporation

More information

\NYISO REVENUE METERING REQUIREMENTS MANUAL

\NYISO REVENUE METERING REQUIREMENTS MANUAL \NYISO REVENUE METERING REQUIREMENTS MANUAL 1.0 Operating Procedures The operating practices presented herein include: Meter Certification for Participants of the NYISO NYISO Guidelines for The Installation,

More information

NPCC Regional Reliability Reference Directory # 12. Underfrequency Load Shedding Program Requirements

NPCC Regional Reliability Reference Directory # 12. Underfrequency Load Shedding Program Requirements NPCC Regional Reliability Reference Directory # 12 Under frequency Load Shedding Program Requirements Task Force on System Studies Revision Review Record: June 26 th, 2009 March 3 rd, 2010 Adopted by the

More information

BAL Standard Project Frequency Response and Frequency Bias Setting Industry Webinar

BAL Standard Project Frequency Response and Frequency Bias Setting Industry Webinar BAL-003-1 Standard Project 2007-12 Frequency Response and Frequency Bias Setting Industry Webinar Terry L. Bilke Midwest ISO, Inc. David F. Lemmons Xcel Energy, Inc. Sydney L. Niemeyer NRG Texas LP November

More information

PRC Disturbance Monitoring and Reporting Requirements

PRC Disturbance Monitoring and Reporting Requirements Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

OPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS

OPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS OPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS AND MEDIUM-SIZE FACILITIES (5,000-25,000KW) CONNECTED

More information

Proposed Language in BAL-003-1/Comments New Standard or Other Action R1. Each Balancing Authority shall This. Attachment A.

Proposed Language in BAL-003-1/Comments New Standard or Other Action R1. Each Balancing Authority shall This. Attachment A. in Approved Standard Translation to R1. Each Balancing Authority shall review its Frequency Bias Each Balancing Authority shall report its previous year s Settings by January 1 of each Frequency Response

More information

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC A. Introduction 1. Title: Generator Frequency and Voltage Protective Relay Settings 2. Number: PRC-024-2 3. Purpose: Ensure Generator Owners set their generator protective relays such that generating units

More information

Recently, the SS38 Working Group on Inter-Area Dynamic Analysis completed two study reports on behalf of the UFLS Regional Standard Drafting Team.

Recently, the SS38 Working Group on Inter-Area Dynamic Analysis completed two study reports on behalf of the UFLS Regional Standard Drafting Team. December 7 th, 2010 NPCC Full Member Committee; Please find attached a draft revised NPCC Regional Reliability Directory #12 Underfrequency Load Shedding Program Requirements and a draft revised NPCC UFLS

More information

Standard BAL Frequency Response and Frequency Bias Setting

Standard BAL Frequency Response and Frequency Bias Setting A. Introduction Title: and Frequency Bias Setting Number: BAL-003-1 Purpose: To require sufficient from the Balancing (BA) to maintain Interconnection Frequency within predefined bounds by arresting frequency

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

OPERATING, METERING, AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 2,000 KILOWATTS

OPERATING, METERING, AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 2,000 KILOWATTS OPERATING, METERING, AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 2,000 KILOWATTS CONNECTED TO THE DISTRIBUTION SYSTEM ORANGE AND ROCKLAND

More information

BED INTERCONNECTION TECHNICAL REQUIREMENTS

BED INTERCONNECTION TECHNICAL REQUIREMENTS BED INTERCONNECTION TECHNICAL REQUIREMENTS By Enis Šehović, P.E. 2/11/2016 Revised 5/19/2016 A. TABLE OF CONTENTS B. Interconnection Processes... 2 1. Vermont Public Service Board (PSB) Rule 5.500... 2

More information

Table of Contents Error! Bookmark not defined.

Table of Contents Error! Bookmark not defined. Table of Contents Table of Contents... 1 Introduction... 2 Background... 2 Rationale by Requirement... 204 Requirement 1... 204 Background and Rationale... 204 Requirement 2... 268 Background and Rationale...

More information

Overview. The Principles of Power System Operation module presents the following topics:

Overview. The Principles of Power System Operation module presents the following topics: Course Outline 1. Introduction to WECC 2. Fundamentals of Electricity 3. Power System Overview 4. Principles of Generation 5. Substation Overview 6. Transformers 7. Power Transmission 8. System Protection

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

( ) usable, minor formatting/editing required ( ) modification needed ( ) superseded by ( ) other ( ) obsolete/archived)

( ) usable, minor formatting/editing required ( ) modification needed ( ) superseded by ( ) other ( ) obsolete/archived) Document name Category Model Validation Report for May 16, 2014 RAS Event ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy ( ) Guideline (X) Report or other ( ) Charter Document date

More information

Frequency Response Standard Background Document November, 2012

Frequency Response Standard Background Document November, 2012 Frequency Response Standard Background Document November, 2012 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com Table of Contents Table of Contents... 1 Introduction...

More information

VAR Voltage and Reactive Control

VAR Voltage and Reactive Control VAR-001-4 Voltage and Reactive Control A. Introduction 1. Title: Voltage and Reactive Control 2. Number: VAR-001-4 3. Purpose: To ensure that voltage levels, reactive flows, and reactive resources are

More information

A. Introduction. VAR Voltage and Reactive Control

A. Introduction. VAR Voltage and Reactive Control A. Introduction 1. Title: Voltage and Reactive Control 2. Number: VAR-001-4.2 3. Purpose: To ensure that voltage levels, reactive flows, and reactive resources are monitored, controlled, and maintained

More information

VAR Voltage and Reactive Control. A. Introduction

VAR Voltage and Reactive Control. A. Introduction VAR-001-5 Voltage and Reactive Control A. Introduction 1. Title: Voltage and Reactive Control 2. Number: VAR-001-5 3. Purpose: To ensure that voltage levels, reactive flows, and reactive resources are

More information

Informational Filing, Interim Report on Balancing Authority ACE Limit Field Trial Docket No. RM

Informational Filing, Interim Report on Balancing Authority ACE Limit Field Trial Docket No. RM VIA ELECTRONIC FILING July 31, 2014 Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C. 20426 Re: Informational Filing, Interim Report on Balancing

More information

OPERATING PROCEDURE. Table of Contents

OPERATING PROCEDURE. Table of Contents Table of Contents PURPOSE... 1 1.0 CAISO DISPATCHER RESPONSIBILITIES... 2 Monitor Loads and Generators... 2 Monitor Balancing Areas... 2 Operate CAISO Controlled Grid Voltage Equipment... 3 Voltage Schedules...

More information

DRAFT. City of Lethbridge Electric ENGINEERING STANDARDS GUIDELINE FOR GENERATOR INTERCONNECTION THE CITY OF LETHBRIDGE ELECTRIC DISTRIBUTION SYSTEM

DRAFT. City of Lethbridge Electric ENGINEERING STANDARDS GUIDELINE FOR GENERATOR INTERCONNECTION THE CITY OF LETHBRIDGE ELECTRIC DISTRIBUTION SYSTEM City of Lethbridge Electric ENGINEERING STANDARDS DRAFT GUIDELINE FOR GENERATOR INTERCONNECTION TO THE CITY OF LETHBRIDGE ELECTRIC DISTRIBUTION SYSTEM Rev. 1 Rev. Date: 2003/01/24 Prepared by: Brent Smith

More information

UNIT-4 POWER QUALITY MONITORING

UNIT-4 POWER QUALITY MONITORING UNIT-4 POWER QUALITY MONITORING Terms and Definitions Spectrum analyzer Swept heterodyne technique FFT (or) digital technique tracking generator harmonic analyzer An instrument used for the analysis and

More information

Table of Contents. NERC 2016 Frequency Response Annual Analysis September 2016 ii

Table of Contents. NERC 2016 Frequency Response Annual Analysis September 2016 ii 2016 Frequency Response Annual Analysis September 2016 I Table of Contents Preface... iii This Report... iv Executive Summary... v Recommendations... v Findings... vii Interconnection Frequency Characteristic

More information

Reference Document Balancing Authority Area Footprint Change Tasks

Reference Document Balancing Authority Area Footprint Change Tasks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 Reference Document Balancing Authority Area Footprint Change Tasks Purpose The purpose of this reference

More information

Unit Auxiliary Transformer Overcurrent Relay Loadability During a Transmission Depressed Voltage Condition

Unit Auxiliary Transformer Overcurrent Relay Loadability During a Transmission Depressed Voltage Condition Unit Auxiliary Transformer Overcurrent Relay Loadability During a Transmission Depressed Voltage Condition NERC System Protection and Control Subcommittee March 2016 NERC Report Title Report Date I Table

More information

Superseded by a more recent version INTERNATIONAL TELECOMMUNICATION UNION

Superseded by a more recent version INTERNATIONAL TELECOMMUNICATION UNION INTERNATIONAL TELECOMMUNICATION UNION ITU-T V.24 TELECOMMUNICATION STANDARDIZATION SECTOR OF ITU (10/96) SERIES V: DATA COMMUNICATION OVER THE TELEPHONE NETWORK Interfaces and voiceband modems List of

More information

IEEE Major Revision of Interconnection Standard

IEEE Major Revision of Interconnection Standard IEEE 1547-2018 - Major Revision of Interconnection Standard NRECA & APA s Emerging Priorities in Energy Research Day, Anchorage, AK Charlie Vartanian PE Secretary, IEEE 1547 Working Group October 31, 2018

More information

Brianna Swenson Alliant Energy Minnesota Power Systems Conference November 8, 2017

Brianna Swenson Alliant Energy Minnesota Power Systems Conference November 8, 2017 Brianna Swenson Alliant Energy Minnesota Power Systems Conference November 8, 2017 Topics Brief history of interties and regulations Who is involved? What exactly are we doing? Why is it important? Project

More information

GUIDE FOR GENERATOR INTERCONNECTION THE WIRES OWNER DISTRIBUTION SYSTEM

GUIDE FOR GENERATOR INTERCONNECTION THE WIRES OWNER DISTRIBUTION SYSTEM DATE: 200/06/2 PAGE 1 of GUIDE FOR GENERATOR INTERCONNECTION TO THE WIRES OWNER DISTRIBUTION SYSTEM The intent of this Guide is to establish the interconnection requirements of Distributed Resources with

More information

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1 PRC-025-1 Generator Relay Loadability A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1 Purpose: To set load-responsive protective relays associated with generation Facilities

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements Section 502.8 SCADA Technical and Operating Applicability 1 Section 502.8 applies to: (a) the legal owner of a generating unit: (i) connected to the transmission facilities in the balancing authority area

More information

System Operating Limit Definition and Exceedance Clarification

System Operating Limit Definition and Exceedance Clarification System Operating Limit Definition and Exceedance Clarification The NERC-defined term System Operating Limit (SOL) is used extensively in the NERC Reliability Standards; however, there is much confusion

More information

INTEGRATED CIRCUITS. AN120 An overview of switched-mode power supplies Dec

INTEGRATED CIRCUITS. AN120 An overview of switched-mode power supplies Dec INTEGRATED CIRCUITS An overview of switched-mode power supplies 1988 Dec Conceptually, three basic approaches exist for obtaining regulated DC voltage from an AC power source. These are: Shunt regulation

More information

Interconnection-Wide Oscillation Analysis: Baselining Oscillation Modes in the North American Power System Objective Purpose

Interconnection-Wide Oscillation Analysis: Baselining Oscillation Modes in the North American Power System Objective Purpose Interconnection-Wide Oscillation Analysis: Baselining Oscillation Modes in the North American Power System NERC Synchronized Measurement Subcommittee (SMS) Scope Document Objective The objective of the

More information

Unit Auxiliary Transformer (UAT) Relay Loadability Report

Unit Auxiliary Transformer (UAT) Relay Loadability Report Background and Objective Reliability Standard, PRC 025 1 Generator Relay Loadability (standard), developed under NERC Project 2010 13.2 Phase 2 of Relay Loadability: Generation, was adopted by the NERC

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements Division 502 Technical Applicability 1(1) Section 502.1 applies to: Expedited Filing Draft August 22, 2017 the legal owner of an aggregated generating facility directly connected to the transmission system

More information

NERC Training Document Understand and Calculate Frequency Response

NERC Training Document Understand and Calculate Frequency Response N E R C Assisting System Personnel In Keeping Current NERC Training Document Understand and Calculate Frequency Response Developed by: NERC Training Resources Working Group February 20, 2003 Subject: Understand

More information

MARKET ANCILLARY SERVICE SPECIFICATION

MARKET ANCILLARY SERVICE SPECIFICATION MARKET ANCILLARY SERVICE SPECIFICATION PREPARED BY: AEMO Systems Performance and Commercial DOCUMENT REF: ESOPP_12 VERSION: 5.0 EFFECTIVE DATE: 30 July 2017 STATUS: FINAL Approved for distribution and

More information

Frequency Response Standard Whitepaper

Frequency Response Standard Whitepaper NORTH AMERICAN ELECTRIC RELIABILITY COUNCIL Princeton Forrestal Village, 116-390 Village Boulevard, Princeton, New Jersey 08540-5731 Frequency Response Standard Whitepaper April 6, 2004 Prepared by the

More information

Agenda Item 3h Attachment 9

Agenda Item 3h Attachment 9 Agenda Item 3h Attachment 9 BALANCING AND FREQUENCY CONTROL (Part 1) A Technical Concepts Document Prepared by the NERC Resources Subcommittee November 9, 2009 Table of Contents Introduction... 3 Background...

More information

Informational Filing Regarding BAL-001-2, Docket No. RM (Errata to Include Attachment)

Informational Filing Regarding BAL-001-2, Docket No. RM (Errata to Include Attachment) VIA ELECTRONIC FILING October 1, 2018 Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C. 20426 Re: Informational Filing Regarding BAL-001-2, Docket

More information

GENERAL REQUIREMENTS FOR TRANSMISSION INTERCONNECTION

GENERAL REQUIREMENTS FOR TRANSMISSION INTERCONNECTION GENERAL REQUIREMENTS FOR TRANSMISSION INTERCONNECTION May 31 st, 2017 Rev. 04 Public Utility District No. 2 of Grant County P.O. Box 878, Ephrata, WA 98823 (509) 754-0500 GENERAL REQUIREMENTS FOR INTERCONNECTION

More information

Oklahoma Gas and Electric Co. Facility Connection Requirements MAINTAINED BY. Transmission Planning Engineering Department

Oklahoma Gas and Electric Co. Facility Connection Requirements MAINTAINED BY. Transmission Planning Engineering Department Oklahoma Gas and Electric Co. Facility Connection Requirements MAINTAINED BY Transmission Planning Engineering Department Table of Contents Transmission and Generation Facility Interconnections... 3 Attachment

More information

INTERNATIONAL TELECOMMUNICATION UNION DATA COMMUNICATION OVER THE TELEPHONE NETWORK

INTERNATIONAL TELECOMMUNICATION UNION DATA COMMUNICATION OVER THE TELEPHONE NETWORK INTERNATIONAL TELECOMMUNICATION UNION ITU-T V.24 TELECOMMUNICATION (03/93) STANDARDIZATION SECTOR OF ITU DATA COMMUNICATION OVER THE TELEPHONE NETWORK LIST OF DEFINITIONS FOR INTERCHANGE CIRCUITS BETWEEN

More information

generation greater than 75 MVA (gross aggregate nameplate rating) Generation in the ERCOT Interconnection with the following characteristics:

generation greater than 75 MVA (gross aggregate nameplate rating) Generation in the ERCOT Interconnection with the following characteristics: A. Introduction 1. Title: Verification of Models and Data for Turbine/Governor and Load Control or Active Power/Frequency Control Functions 2. Number: MOD-027-1 3. Purpose: To verify that the turbine/governor

More information

Procedure for ERO Support of Frequency Response and Frequency Bias Setting Standard. Event Selection Process

Procedure for ERO Support of Frequency Response and Frequency Bias Setting Standard. Event Selection Process This procedure outlines the Electric Reliability Organization (ERO) process for supporting the Frequency Response Standard (FRS). A Procedure revision request may be submitted to the ERO for consideration.

More information

Testing model data usability Excitation Systems PSS Limiters

Testing model data usability Excitation Systems PSS Limiters 1 2016 IEEE/PES General Meeting July 17 th -21 st, 2016 Boston, MA Panel Session Use of the New Revisions of IEEE Std. 421.2 and 421.5 to Satisfy International Grid Code Requirements Testing model data

More information

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR SMALL GENERATION INTERCONNECTIONS

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR SMALL GENERATION INTERCONNECTIONS TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR SMALL GENERATION INTERCONNECTIONS Puget Sound Energy, Inc. PSE-ET-160.60 October 30, 2007 TABLE OF CONTENTS 1. INTRODUCTION...1 1.1 GENERAL

More information

Informational Filing, Frequency Response Annual Analysis Docket No. RM

Informational Filing, Frequency Response Annual Analysis Docket No. RM VIA ELECTRONIC FILING March 20, 2015 Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C. 20426 Re: Informational Filing, Response Annual Analysis Docket

More information

Using Synchrophasors for Frequency Response Analysis in the Western Interconnection. Bonneville Power Administration -- WECC JSIS Chair

Using Synchrophasors for Frequency Response Analysis in the Western Interconnection. Bonneville Power Administration -- WECC JSIS Chair 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2014 Grid of the Future Symposium Using Synchrophasors for Frequency Response Analysis in the Western Interconnection

More information

August 25, Please contact the undersigned if you have any questions concerning this filing.

August 25, Please contact the undersigned if you have any questions concerning this filing. !! August 25, 2017 VIA ELECTRONIC FILING Ms. Erica Hamilton, Commission Secretary British Columbia Utilities Commission Box 250, 900 Howe Street Sixth Floor Vancouver, B.C. V6Z 2N3 Re: North American Electric

More information

August 25, 2017 VIA ELECTRONIC FILING

August 25, 2017 VIA ELECTRONIC FILING !! August 25, 2017 VIA ELECTRONIC FILING Kirsten Walli, Board Secretary Ontario Energy Board P.O Box 2319 2300 Yonge Street Toronto, Ontario, Canada M4P 1E4 Re: North American Electric Reliability Corporation

More information

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. July 2016 Version 4

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. July 2016 Version 4 MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS July 2016 Version 4 This page intentionally blank LEGISLATIVE AUTHORITY Section 15.0.3(1) of The Manitoba Hydro Act (C.C.S.M. c. H190) authorizes

More information

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules. 45-day Formal Comment Period with Initial Ballot June July 2014

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules. 45-day Formal Comment Period with Initial Ballot June July 2014 Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. April 2009 Version 2

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. April 2009 Version 2 MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS April 2009 Version 2 LEGISLATIVE AUTHORITY Section 15(5) of The Manitoba Hydro Act authorizes Manitoba Hydro to set, coordinate and enforce

More information

Frequency Response Initiative Report

Frequency Response Initiative Report Frequency Response Initiative Report The Reliability Role of Frequency Response August 31, 2012 Draft 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com NERC s Mission

More information

Northeast Power Coordinating Council, Inc. Glossary of Terms. Approved by the Reliability Standards Committee

Northeast Power Coordinating Council, Inc. Glossary of Terms. Approved by the Reliability Standards Committee Northeast Power Coordinating Council, Inc. Glossary of Terms Approved by the Reliability Standards Committee October 26, 2011 Revision History Version Date Action Change Tracking (New, Errata or Revisions)

More information

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Load-Frequency Control Service in a Deregulated Environment

Load-Frequency Control Service in a Deregulated Environment Load-Frequency Control Service in a Deregulated Environment A. P. Sakis Meliopoulos Fellow School of Electrical and Computer Engineering Georgia Institute of Technology Atlanta, GA 30332-0250 George J.

More information

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Minutes Frequency Response Initiative Meeting

Minutes Frequency Response Initiative Meeting Minutes Frequency Response Initiative Meeting April 27, 2010 Tucson Electric Co. Office Tucson, Arizona A meeting of the NERC Frequency Response Initiative Team was held on April 27, 2010 at the Ameren

More information

IEEE sion/1547revision_index.html

IEEE sion/1547revision_index.html IEEE 1547 IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces http://grouper.ieee.org/groups/scc21/1547_revi sion/1547revision_index.html

More information

Comparative Testing of Synchronized Phasor Measurement Units

Comparative Testing of Synchronized Phasor Measurement Units Comparative Testing of Synchronized Phasor Measurement Units Juancarlo Depablos Student Member, IEEE Virginia Tech Virgilio Centeno Member, IEEE Virginia Tech Arun G. Phadke Life Fellow, IEEE Virginia

More information

BEFORE THE ALBERTA ELECTRIC SYSTEM OPERATOR

BEFORE THE ALBERTA ELECTRIC SYSTEM OPERATOR BEFORE THE ALBERTA ELECTRIC SYSTEM OPERATOR NORTH AMERICAN ELECTRIC ) RELIABILITY CORPORATION ) NOTICE OF FILING OF THE NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION OF PROPOSED RELIABILITY STANDARD

More information

2015 Frequency Response Annual Analysis

2015 Frequency Response Annual Analysis 2015 Frequency Response Annual Analysis September 16, 2015 I Table of Contents Preface... iii This Report... iv Executive Summary... v Recommendations... v Findings... vi Interconnection Frequency Characteristic

More information

E N G I N E E R I N G M A N U A L

E N G I N E E R I N G M A N U A L 1 1 1.0 PURPOSE The purpose of this document is to define policy and provide engineering guidelines for the AP operating companies (Monongahela Power Company, The Potomac Edison Company, and West Penn

More information

I WP Asset # I ~:2 3. I Review Annual. ~c~~ Date: 'l/j(j/! ZL>IJ,...

I WP Asset # I ~:2 3. I Review Annual. ~c~~ Date: 'l/j(j/! ZL>IJ,... - District Standard - FAC Facility Design, Connections 950.001 and Maintenance CHELAN COUNTY ~ PUBLIC UTILITY DISTRICT Owned By The People~ Serve Facility Connection Requirements Page 1 of 101 EFFECTIVE

More information

GREAT RIVER ENERGY GREAT RIVER ENERGY GENERATION INTERCONNECTION GUIDELINES. Revision 4

GREAT RIVER ENERGY GREAT RIVER ENERGY GENERATION INTERCONNECTION GUIDELINES. Revision 4 GREAT RIVER ENERGY GREAT RIVER ENERGY GENERATION INTERCONNECTION GUIDELINES Revision 4 December, 2010 TABLE OF CONTENTS General Requirements... 1 A, Purpose... 1 B, MISO Interconnection Requirements...2

More information

Southern Company Interconnection Requirements for Inverter-Based Generation

Southern Company Interconnection Requirements for Inverter-Based Generation Southern Company Interconnection Requirements for Inverter-Based Generation September 19, 2016 Page 1 of 16 All inverter-based generation connected to Southern Companies transmission system (Point of Interconnection

More information

( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy (X) Guideline ( ) Report or other ( ) Charter M&VWG. Web URL:

( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy (X) Guideline ( ) Report or other ( ) Charter M&VWG. Web URL: Document name Category Guideline Template Document date June 17, 2015 Adopted/approved by Date adopted/approved Custodian (entity responsible for maintenance and upkeep) Stored/filed Previous name/number

More information