Barlow Solar Energy Centre Acoustic Assessment Report

Size: px
Start display at page:

Download "Barlow Solar Energy Centre Acoustic Assessment Report"

Transcription

1 Barlow Solar Energy Centre Acoustic Assessment Report FINAL DRAFT REPORT Prepared for: Barlow Energy Centre Limited Partnership 53 Jarvis Street, Suite 300 Toronto, Ontario M5C 2H2 Prepared by: Stantec Consulting Ltd Cochrane Drive Markham, ON L3R 0B8 File No January 17, 2017

2 Sign-off Sheet This document entitled Barlow Solar Energy Centre Acoustic Assessment Final Draft Report was prepared by Stantec Consulting Ltd. ( Stantec ) for the account of Barlow Energy Centre Limited Partnership (the Client ). In connection with the Client s application for a Renewable Energy Approval, this document may be reviewed and used by the following entities in the normal course of their review and approval process: (a) the MOECC; (b) the MNRF; (c) the MTCS; and (d) the Environmental Review Tribunal. Except as set forth in (a) through (d) above, any reliance on this document by any third party is strictly prohibited. The material in it reflects Stantec s professional judgment in light of the scope, schedule and other limitations stated in the document and in the contract between Stantec and the Client. The opinions in the document are based on conditions and information existing at the time the document was published and do not take into account any subsequent changes. In preparing the document, Stantec did not verify information supplied to it by others, unless otherwise stated therein. Any use which a third party makes of this document is the responsibility of such third party. Such third party agrees that Stantec shall not be responsible for costs or damages of any kind, if any, suffered by it or any other third party as a result of decisions made or actions taken based on this document. Prepared by (signature) Prabu Surendran, B.Eng. Acoustics, Noise and Vibration Specialist Reviewed by (signature) Kana Ganesh Ph.D., P.Eng. Sr. Acoustics, Noise and Vibration Engineer

3 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT Table of Contents ABBREVIATIONS... I 1.0 INTRODUCTION BACKGROUND FACILITY DESCRIPTION FACILITY LAYOUT OPERATING SCENARIO NOISE SOURCE SUMMARY NOISE SOURCES SOUND CHARACTER ADJUSTMENT POINTS OF RECEPTION NOISE ASSESSMENT CRITERIA MOECC GUIDELINE LIMITS APPLICABLE LIMITS IMPACT ASSESSMENT MODELING METHODOLOGY MODELED SCENARIO RESULTS CONCLUSIONS LIST OF TABLES Table 3.1: Noise Source Summary Table 4.1: Nearby Points of Reception Table 6.1: Noise Impact Table for Existing Points of Reception Table 6.2: Acoustic Assessment Summary Table

4 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT LIST OF APPENDICES APPENDIX A: FIGURES Figure 1: Site Location Figure 2: Site Plan: Conceptual Project Component Layout Figure 3: Source Locations (Polygon Multiple Scenarios) Figure 4: Points of Reception Figure 5: Polygon Multiple Scenario #1: Predicted Equivalent Sound Level Contours Figure 6: Polygon Multiple Scenario #2: Predicted Equivalent Sound Level Contours Figure 7: Polygon Multiple Scenario #3: Predicted Equivalent Sound Level Contours Figure 8: Polygon Multiple Scenario #4: Predicted Equivalent Sound Level Contours APPENDIX B: EQUIPMENT SPECIFICATIONS AND SOUND DATA APPENDIX C: POINTS OF RECEPTION DETAILS AND SUMMARY RESULTS Table C.1: Point of Reception Details Table C.2: Point of Receptions Sound Level Summary APPENDIX D: CADNAA SAMPLE CALCULATIONS APPENDIX E: ZONING INFORMATION APPENDIX F: PREDICTABLE WORST CASE

5 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT Abbreviations AC db dba DC Hydro One ISO Leq Lp Lw km MWac m MOECC NPC-300 POR PWL SPL Stantec TNPI alternating current Decibel Decibel, A-weighted direct current Hydro One Networks Inc. International Organization for Standardization Energy Equivalent Sound Level Sound Pressure Level Sound Power Level kilometre(s) Megawatt alternating current metre Ministry of the Environment and Climate Change (formerly the Ministry of the Environment) Ministry of the Environment and Climate Change Noise Pollution Control Guideline Point of Reception Sound Power Level Sound Pressure Level Stantec Consulting Ltd. Trans Northern Pipelines Inc. i

6 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT Introduction January 17, INTRODUCTION Barlow Energy Centre Limited Partnership (the Proponent), is proposing the development of a 10 megawatt alternating current (MWac) solar energy generating facility, known as the Barlow Solar Energy Centre (the Project) approximately 10 kilometres (km) west of the city of Cornwall. The Project Location is primarily in the Township of South Stormont, United Counties of Stormont, Dundas and Glengarry, Ontario, however the Point of Common Coupling will be located within the road allowance of Cornwall Centre Road, in the City of Cornwall, Ontario. The Project will require a Renewable Energy Approval (REA) as per Ontario Regulation (O. Reg.) 359/09 - Renewable Energy Approvals under Part V.0.1 of the Act, under the Environmental Protection Act (MOECC 2009, amended 2016). The Proponent is proposing to develop, construct and operate the Project on 38 hectares (ha; 94 acres) of land (i.e., size of Project Location) in response to the Government of Ontario s Large Renewable Procurement initiative to promote the development of renewable electricity in the province. The Project will be located on parts of lots 20 and 21, Concession 4 on privately-owned land, leased for a period of 20 or more years. The Project Location is bounded to the south by Cornwall Centre Road, and to the west, north and east by undeveloped woodlands and scrubland. A Trans Northern Pipeline Inc. (TNPI) pipeline and Hydro One Networks Inc. (Hydro One) transmission line bisect the Project. A map showing the location of the Project is provided in Figure 1, Appendix A. Figure 2 shows a conceptual Project component layout (Appendix A). The Proponent has retained Stantec Consulting Ltd. (Stantec) to prepare a REA application, as required under O. Reg. 359/09. The proposed solar PV grid connected system would be considered a Class 3 Solar Facility under O. Reg. 359/09, s. 4. The area surrounding the Project is generally agriculture in nature. The area s acoustical environment is best described as a Class 3 (Rural) area as per MOECC s guideline publication Environmental Noise Guideline (NPC-300). The existing acoustic environment is expected to be dominated by natural ambient noise with sporadic contributions from road and rail sources. This assessment considers 72 receptors within a setback of approximately 1 km of the Project Location boundary as required by the MOECC. 1.1 BACKGROUND As outlined above, the Project will require a REA as per Ontario Regulation (O. Reg.) 359/09 - under Part V.0.1 of the Environmental Protection Act (MOECC 2009, amended 2016), which stipulates requirements for renewable energy projects. According to the project classification provided under Section 4 of O. Reg. 359/09, all ground mounted solar facilities with a name 1.1

7 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT Introduction January 17, 2017 plate capacity greater than 10 kw require a noise study report to support REA applications. Section 13 of O. Reg. 359/09 requires that noise studies for Class 3 facilities should be conducted in accordance with Basic Comprehensive Certificate of Approval, April 2004 and subsequent amendments. This Acoustic Assessment Report has been prepared based on the requirements described in the current MOECC noise forms and guidelines including the following documents: NPC-300, Environmental Noise Guideline. Basic Comprehensive Certificates of Approval, User Guide v2.0, Appendix A, Supporting Information to be Submitted for an Acoustic Assessment Report or Vibration Assessment Report Required by a Basic Comprehensive C of A, April

8 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT Facility Description January 17, FACILITY DESCRIPTION The Project Location is located on up to two parcels of privately-owned land, totaling approximately 38 ha on the north side of Cornwall Centre Road, west of Power Dam Drive. An area map showing the Project Location and property boundaries are provided in Figure 1, Appendix A. Figure 2 shows a conceptual Project component Layout (Appendix A). 2.1 FACILITY LAYOUT The Project is being designed and constructed to generate 10 MW of power. The basic Project components include: solar panels inverters (converting solar panel output from direct current [DC] to alternating current [AC]) inverter step-up transformers (converting AC voltage to grid voltage levels) electrical cabling access roads perimeter fencing parking/storage areas main facility substation and control building. The Project will have a nameplate capacity of 10 MW and will consist of photovoltaic panels. Panels would be installed on galvanized steel and/or aluminum racks in rows to capture sunlight. The orientations of these panels are not expected to contribute to the sound propagation. The generated electrical power from these panels will be routed through a system of inverters and inverter step-up transformers, which are considered noise sources at the facility. The facility will include four (4) stations (each with one or more inverter(s) [2.5 MW each] and inverter step-up transformer(s) [3 MVA each]. Each station is expected to serve the surrounding cluster of solar panels. At each station, the voltage level will be raised to 44 kv (if no main power transformer is integrated in the final project design) or either 27.6 kv or 34.5 kv (if a main power transformer is integrated in the final project design) by the inverter step-up transformers co-located with each inverter. The inverters are modular units prepackaged with their own casing. The electricity will be transported from the inverter stations to a single substation via underground cables. From the substation, the Project will be connected to the distribution grid via the connection line. One 12 MVA main power transformer will also be located within the substation location. Currently, there are 4 solar panel layouts under consideration. These layouts are for ground fixed tilt (GFT) and horizontal single axis trackers (HSAT) racking types. 2.1

9 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT Facility Description January 17, OPERATING SCENARIO The Project will operate throughout the year during the daylight hours. Due to extended daylight hours during summer months, the facility could operate outside guideline daytime period, (i.e., 7:00 AM to 7:00 PM). The facility is expected to operate 7 days a week throughout the year. The sources of noise are the inverters, inverter step-up transformers and a main power transformer located within the substation area. It was conservatively assumed that all equipment units will operate at full rated capacity during the predictable worst case hour. The source locations are shown in Figure 3, Appendix A. There are four possible locations for each of the four inverter stations and substation. These possible locations form a polygon and are considered as a polygon multiple scenario in this assessment. 2.2

10 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT Noise Source Summary January 17, NOISE SOURCE SUMMARY 3.1 NOISE SOURCES The noise sources for the facility are the stations (4 stations, each with one or more inverter[s] and with one or more inverter step-up transformer[s]) and the main power transformer located within the substation. As discussed, the inverters are modular units and housed in a prepackaged casing. The inverter step-up transformer associated with each station is to be located near the inverters. Depending on the orientation of the station, it is expected that the inverter will provide some shielding to the inverter step-up transformer and vice versa. However, this assessment conservatively assumes that inverters or inverter step-up transformers provide no attenuation to inverters or inverter step-up transformers. In other words, the assessment considers inverters and inverter step-up transformers will be placed outside without any shielding from one another. Thus the facility s dominant noise sources would consist of noise radiating from: 4 inverters each with 2.5 MW (Power Electronics HEC 1500V model) inverters 4 inverter step-up transformers rated at 3.0 MVA 1 main power transformer rated at 12 MVA at the substation location. Sound levels for the inverters were based on equipment manufacturer submittals (included in Appendix B). The sound level for the transformers were estimated based on the provided rating, and dimensional data from typical transformer from other similar projects. Each of the inverter units is represented with an overall sound power level of 91.7 A-weighted decibels (dba; including 5 db increase for tonality) and the associated inverter step-up transformer is represented with a sound power level of 82.4 dba (including a 5 db increase for tonality). The sound power level for the 12 MVA main power transformer was estimated at 94.6 dba (including a 5 db increase for tonality). The equipment specifications and data are provided in Appendix B. As discussed, all sources (inverters, inverter step-up transformers and main power transformer) include a tonality penalty as per MOECC s guideline requirements. The solar panels would be installed in arrays at a height of approximately 1 m or more above grade and would be installed at an angle to capture sunlight. Therefore, the lower portions of these noise sources are expected to be shielded by the solar panels. However, the assessment does not consider the shielding provided by these panels to be conservative. Four conceptual layouts were considered; each of these layouts considers different locations for inverter/inverter step-up transformer locations as well as substation locations. These four scenarios were assessed separately under the polygon multiple scenario as follows: 1. Polygon Multiple Scenario #1: All sources are northeast corner of respective polygons 2. Polygon Multiple Scenario #2: All sources are southeast corner of respective polygons 3.1

11 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT Noise Source Summary January 17, Polygon Multiple Scenario #3: All sources are southwest corner of respective polygons 4. Polygon Multiple Scenario #4: All sources are southeast corner of respective polygons This provides a reasonable worst case scenario with respect to the polygon approach. The sources discussed above for this Project are summarized below (Table 3.1) and illustrated in Figure 3 (Appendix A). All sources are assumed to have continuous, steady sound emissions when operating. 3.2 SOUND CHARACTER ADJUSTMENT The MOECC s guideline NPC-104 outlines that the sources with distinct sound characteristics be penalized in the assessment. In accordance with this guideline and recent MOECC communications, the resulting noise emissions associated with inverter step-up transformers and inverters were penalized with a 5 db penalty to account for a potential hum from inverter stepup transformer coils and all inverters. Transformers sometimes exhibit tonal characteristics, which may not be present in small transformers. However, a 5 db penalty was conservatively applied to all inverter step-up transformers in the assessment (i.e., applied to each inverter step-up transformer at each station as well as the 12 MVA main power transformer). 3.2

12 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT Noise Source Summary January 17, 2017 Table 3.1: Noise Source Summary Source ID Source Description UTM Coordinates (Zone 18T) Source Type Sound Power Level* Scenario #1 of the Polygon Multiple Source Location Sound Character Noise Control Measures inv_01_loc_01 Inverter P 92 O T E inv_02_loc_01 Inverter P 92 O T E inv_03_loc_01 Inverter P 92 O T E inv_04_loc_01 Inverter P 92 O T E substation_01_l oc_01 Substation P 95 O T U trans_01_loc_01 Transformer P 82 O T U trans_02_loc_01 Transformer P 82 O T U trans_03_loc_01 Transformer P 82 O T U trans_04_loc_01 Transformer P 82 O T U Scenario #2 of the Polygon Multiple inv_01_loc_02 Inverter P 92 O T E inv_02_loc_02 Inverter P 92 O T E inv_03_loc_02 Inverter P 92 O T E inv_04_loc_02 Inverter P 92 O T E substation_01_l oc_02 Substation P 95 O T U trans_01_loc_02 Transformer P 82 O T U trans_02_loc_02 Transformer P 82 O T U trans_03_loc_02 Transformer P 82 O T U trans_04_loc_02 Transformer P 82 O T U Scenario #3 of the Polygon Multiple inv_01_loc_03 Inverter P 92 O T E inv_02_loc_03 Inverter P 92 O T E 3.3

13 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT Noise Source Summary January 17, 2017 Table 3.1: Noise Source Summary Source ID Source Description UTM Coordinates (Zone 18T) Source Type Sound Power Level* Source Location Sound Character Noise Control Measures inv_03_loc_03 Inverter P 92 O T E inv_04_loc_03 Inverter P 92 O T E substation_01_l Substation oc_03 P O T U trans_01_loc_03 Transformer P 82 O T U trans_02_loc_03 Transformer P 82 O T U trans_03_loc_03 Transformer P 82 O T U trans_04_loc_03 Transformer P 82 O T U Scenario #4 of the Polygon Multiple inv_01_loc_04 Inverter P 92 O T E inv_02_loc_04 Inverter P 92 O T E inv_03_loc_04 Inverter P 92 O T E inv_04_loc_04 Inverter P 92 O T E substation_01_l oc_04 Substation P 95 O T U trans_01_loc_04 Transformer P 82 O T U trans_02_loc_04 Transformer P 82 O T U trans_03_loc_04 Transformer P 82 O T U trans_04_loc_04 Transformer P 82 O T U P = Point Source V = Vertical Source VA = Vertical Area Source Source Location: O = outside of building; I = inside of building Sound Character, per NPC-104: Noise Control Measures: T= Tonal C = Cyclical S = Silencer/Muffler L = Lagging E = Acoustic Enclosure S = Steady Q = Quasi-Steady Impulsive A = Acoustic Lining, plenum O = Other B = Buzzing I = Impulsive U = Uncontrolled B = Barrier 3.4

14 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT Points of Reception January 17, POINTS OF RECEPTION Figure 4 (Appendix A) shows the Project Location and the PORs. The assessment considers a total of 72 PORs (Vacant, Commercial, and Existing PORs) in all directions within approximately 1 km of the Project Location. There was a total of 72 receptors identified; 16 of which are currently used for commercial purposes. However, for the purpose of completeness, these 16 receptors were also identified for the assessment. The receptors are as follows: PORs currently used for commercial purposes are identified as CPOR##, where ## represent a unique identification for the receptors. There are 16 CPORs. Existing residential dwellings are identified as EPOR##, where ## represents a unique identification for the receptors. There are 36 EPORs. Currently vacant lots and are identified as VPOR##, where ## represents a unique identification for the receptors. There are 20 VPORs. Among the receptors, the nearest to the Project is VPOR29 and is a vacant lot receptor (approximately 220 m southeast of the Project Location). All receptors were modeled using a height of 4.5 m above grade. The list of studied receptors is summarized in Appendix C. For the purposes of this report, four PORs are shown in Table 4.1 below. These 4 receptors were selected to represent the closest POR southeast, south, southwest and west of the Project Location. The PORs to the north are well separated and are provided in Appendix C. The locations and distance to the nearest inverter or inverter step-up transformer of these PORs are provided in Table 4.1. Table 4.1: Nearby Points of Reception POR ID Description X Coordinates CPOR18 POR to the West Y Receptor Height (m) Approximate Distance to Nearest Facility Equipment (m) VPOR29 POR to the Southeast VPOR45 POR to the South CPOR46 POR to the Southwest The lands immediately south of the facility (and south of Cornwall Centre Road) are owned by Hydro One (road allowance) and the City of Cornwall (dump or transfer station). The current land use zoning designation does not permit noise sensitive buildings and therefore no receptors are included on these properties (Figure 4 and Appendix E).

15 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT Points of Reception January 17, 2017 Similarly, an abandoned commercial building is located to the southwest within lands zoned commercial (Figure 3 and Appendix E). This property is not considered suitable for a noise sensitive receptor. The property located east of the Project Location (Figure 3 and Appendix E) is currently zoned as flood plain and is not considered suitable for a noise sensitive receptor. Therefore, a vacant lot receptor was not considered. 4.2

16 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT Noise Assessment Criteria January 17, NOISE ASSESSMENT CRITERIA 5.1 MOECC GUIDELINE LIMITS As the facility and a number of surrounding receptors are located adjacent to Cornwall Centre Road, west of Power Dam Drive, the sounds from the traffic are expected to occasionally influence the sound levels on PORs near the roadway. The MOECC noise criteria use the proximity of receptors to human-made sources of sound such as traffic or industry and their presence throughout the day to define the sound level limits for different areas. However, because the traffic noise is expected to be non-constant, the study area would be dominated by the natural ambient sound the majority of the time, with increases in noise during traffic passby events. Receptors within 1 km of the Project Location are considered to be located in a Class 3 (or rural) area. In a Class 3 area, the sounds of the ambient environment are expected to be dominated by natural sounds with little or no road traffic. The MOECC publication NPC-300 provides sound level limits for Class 3 areas. Publication NPC-300 requires that the one-hour equivalent sound level (Leq (1 hour)) in dba from the proposed stationary noise sources should not exceed the applicable sound level limit at a noise-sensitive receptor location. The sound level limit is considered to be the lower of the prescribed exclusionary limit for a Class 3 area, or the background sound level. NPC-300 defines the background sound as the sound level caused by sources other than those under assessment (e.g., road traffic, the sounds of nature, etc.). The exclusionary limits for a Class 3 area are: 45 dba for a facility operating between 0:700 and 19:00 hrs (daytime) 40 dba for a facility operating between 19:00 and 0:700 hrs (night-time) 5.2 APPLICABLE LIMITS Ambient monitoring was not conducted in the vicinity of the proposed facility and therefore the MOECC exclusionary limits were applied for this assessment. Since the Project could operate during day and night time hours (e.g., early morning), and no difference is assumed between these operations, the applicable criterion is considered to be the MOECC nighttime exclusionary limit of 40 dba. This limit is also stated in the MOECC publication on solar facilities for Renewable Energy Approval (PIBS 7234e). 5.1

17 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT Impact Assessment January 17, IMPACT ASSESSMENT 6.1 MODELING METHODOLOGY A predictive analysis was performed using the commercially available software package CADNA/A, a computerized version of the algorithms contained in the ISO and standards. This model includes geometrical divergence (distance attenuation), barrier effects due to intervening structures, ground effects, atmospheric absorption, and topography. The model considers a downwind condition, which, for the purpose of analysis, is always from each source location to each POR location. All sound sources (inverter step-up transformers and inverters) that emit into the environment were modeled as point sources. Topography was included in the model; however, the terrain is relatively flat and topography was not expected to influence the predicted results. No shielding nor obstacles were included in the model; however, the inverters are modular units that may come with prepackaged casing which will offer some shielding. The facility and surrounding ground surfaces were modeled as a combination of reflective and absorptive surfaces due to the nature of the site. The analysis utilized a ground absorption factor of 0.7 to represent the agricultural land and grass (considered absorptive) observed from imagery of the site. Meteorological assumptions that cause maximum noise transmission are also typical of Ontario values and were used in the model. These included a temperature of 10 degrees Centigrade and a relative humidity of 70%. 6.2 MODELED SCENARIO As described in Section 2.2 (Operating Scenario), the modeled scenario for this assessment consists of all sources running at full capacity for a full hour. This modeled operating scenario assumes that the Project, when operating outside of daytime (07:00 to 19:00 hours), could operate at full capacity. Therefore the night-time operation is considered to be the predictable worst-case scenario relative to the applicable criterion, as presented in Section 6.3. An example of the detailed model calculations is included in Appendix D. 6.3 RESULTS The modelled contribution of each source at the nearest PORs during a predictable worst case condition is provided in Table 6.1 for the polygon multiple scenarios. The sum of these individual sound levels at each POR gives the overall predicted sound level from the facility s unmitigated operation. The results of the overall modeling assessment (the 6.1

18 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT Impact Assessment January 17, 2017 total sound level from of all contributing sources) are summarized in Table 6.2 for polygon multiple scenarios. Sound level contours of the predicted noise emanating from the Project are shown in Appendix A as follows: Scenario #1: - Figure 5 Scenario #2: - Figure 6 Scenario #3: - Figure 7 Scenario #4: - Figure 8 Table 6.1: Noise Impact Table for Existing Points of Reception Sound Level [dba] Source ID Source Description CPOR18 VPOR29 VPOR45 CPOR46 SCENARIO #1 OF POLYGON MULTIPLE inv_01_loc_01 Inverter inv_02_loc_01 Inverter inv_03_loc_01 Inverter inv_04_loc_01 Inverter substation_01_loc_01 Substation trans_01_loc_01 Transformer trans_02_loc_01 Transformer trans_03_loc_01 Transformer trans_04_loc_01 Transformer Total SCENARIO #2 OF POLYGON MULTIPLE inv_01_loc_02 Inverter inv_02_loc_02 Inverter inv_03_loc_02 Inverter inv_04_loc_02 Inverter substation_01_loc_02 Substation trans_01_loc_02 Transformer trans_02_loc_02 Transformer trans_03_loc_02 Transformer trans_04_loc_02 Transformer Total

19 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT Impact Assessment January 17, 2017 Table 6.1: Noise Impact Table for Existing Points of Reception Sound Level [dba] Source ID Source Description CPOR18 VPOR29 VPOR45 CPOR46 SCENARIO #3 OF POLYGON MULTIPLE inv_01_loc_01 Inverter inv_02_loc_01 Inverter inv_03_loc_01 Inverter inv_04_loc_01 Inverter substation_01_loc_01 Substation trans_01_loc_01 Transformer trans_02_loc_01 Transformer trans_03_loc_01 Transformer trans_04_loc_01 Transformer Total SCENARIO #4 OF POLYGON MULTIPLE inv_01_loc_04 Inverter inv_02_loc_04 Inverter inv_03_loc_04 Inverter inv_04_loc_04 Inverter substation_01_loc_04 Substation trans_01_loc_04 Transformer trans_02_loc_04 Transformer trans_03_loc_04 Transformer trans_04_loc_04 Transformer Total

20 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT Impact Assessment January 17, 2017 Table 6.2: Acoustic Assessment Summary Table POR ID POR Description Scenario 1 of Polygon Multiple Sound Level at Point of Reception (Leq, dba) Verified by Acoustic Audit (Y/N) CPOR18 POR to the West 26 N Performance Limit (Leq) Compliance with Performance Limit (Y/N) VPOR29 POR to the Southeast 34 N Y 40 VPOR45 POR to the South 31 N Y CPOR46 POR to the Southwest 28 N Y Scenario 2 of Polygon Multiple CPOR18 POR to the West 27 N VPOR29 POR to the Southeast 34 N Y 40 VPOR45 POR to the South 33 N Y CPOR46 POR to the Southwest 30 N Y Scenario 3 of Polygon Multiple CPOR18 POR to the West 29 N VPOR29 POR to the Southeast 31 N Y 40 VPOR45 POR to the South 32 N Y CPOR46 POR to the Southwest 31 N Y Scenario 4 of Polygon Multiple CPOR18 POR to the West 28 N VPOR29 POR to the Southeast 31 N Y 40 VPOR45 POR to the South 30 N Y CPOR46 POR to the Southwest 29 N Y Y Y Y Y In addition, scenarios representing noise sources within polygon multiple at locations closest to PORs to the west, southwest, south and southeast are provided in Appendix F. The sound levels for all scenarios comply with the regulatory limits. 6.4

21 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT 7.0 CONCLUSIONS The predictive analysis based on the polygon multiple scenario presented in this report indicated that the Project noise effects comply with performance limits at all PORs which are situated within 1 km of the Project, without the need for noise control measures. Stantec s conservative assessment predicted that sound levels during the facility s predicted worst case scenario during operation with sources located within the noise polygons presented within this report will meet the MOECC criteria at all applicable PORs. 7.1

22 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT APPENDIX A: FIGURES

23 W:\active\ \drawing\MXD\Atmosphere\ReportFigures\ _Noise_Report\ _NR_Fig1_Site_Location_ mxd Revised: By: AWhite Los Moulinette Road Long Sault Parkw ay Harrisons Corners ey Road County Road 15 Black River Swamp County Road 29 Long Sault UT Stoney Creek County Road 2 Black River South Raisin River Lake St. Lawrence County Road 36 Lakeview Heights UT Valade Road United Countie s Of Stormont, Dundas And Gle ngarry Lake View Marsh Post Road Swamp Atchison Road Richmond Drive United States of America County Road 18 Corn w all Centre Road W. Guindon UT Vincent Massey Drive East Guindon Power Dam Drive Power Dam Swamp Highway 138 City Of Cornwall Township Of South Stormont U T T U UT Canadian National Archies Swamp UT UT UT Riverdale Avenue Mercier Avenue Highway 401 Headline Road Riverdale U T Brookdale Avenue Tollgate Road West Queen Street County Road 42 U Wallrich Avenue Dover Heights Tollgate Road East Pitt Street 13Th Street West 9Th Street West South Branch Road UT T 7Th Street West 2Nd Street West On Mcconnell Avenue tario Street Wa ter Street West 9Th Street East 5Th Street East 3Rd Street East 4Th Street West 4Th Street East International Road Akwesasne Disclaimer: Stantec assumes no responsibility for data supplied in electronic format. The recipient accepts full responsibility for verifying the accuracy and completeness of the data. The recipient releases Stantec, its officers, employees, consultants and agents, from any and all claims arising in any way from the content or provision of the data. Cornwall Centre Churchill Heights Rosedale Terrace Eamers Corners $ ( $ Township Of South Stormont Summerstown Swamp UT Marleau Avenue C o r n w a l l 2Nd Street East 1St Street East Township Of South Glengarry Glenview Heights Grants Corners UT St Felix Street Montreal Road Legend UT Notes 1. Coordinate System: NAD 1983 UTM Zone 18N 2. Base features produced under license with the Ontario Ministry of Natural Resources and Forestry Queen's Printer for Ontario, Waterbody and watercourse mapping within 120 m of the Project Location has been updated based on field studies completed as part of the REA process under O. Reg. 359/09. See the Water Assessment and Water Body Report for details. Ohio Project Location REVC Municipality of United Prepared by AW on Counties Of Stormont, Dundas And Glengarry Client/Project BARLOW ENERGY CENTRE LP BARLOW SOLAR ENERGY CENTRE Figure No. Title Michigan 1 Project Location Highway Major Road Minor Road Railway Hydro One Transmission Line Unknown Pipeline Unknown Transmission Line Watercourse (Intermittent) Watercourse (Permanent) Municipal Boundary, Upper Municipal Boundary, Lower Kilometres 1:50,000 (At original document size of 11x17) Site Location Ontario Toronto Pennsylvania Waterbody Wetland, Provincially Significant Wetland, Other Evaluated Wetland, Not evaluated per OWES Wooded Area First Nation Reserve Québec New York Ottawa

24 W:\active\ \drawing\MXD\APC\ReportFigures\PDR\ _PDR_Fig02_SitePlanProjectComponentLayout.mxd Revised: By: AWhite LOT 24 CON 4 CORNWALL LOT 22 CON 4 CORNWALL LOT 23 CON 4 CORNWALL LOT 21 CON 4 CORNWALL CORNWALL LOT 20 CON 4 CORNWALL LOT 22 CON 3 CORNWALL Canadian National ") LOT 21 CON 3 CORNWALL LOT 19 CON 4 CORNWALL Cornwall Centre Road LOT 20 CON 3 CORNWALL LOT 18 CON 4 CORNWALL Power Dam Drive Barlow Road Disclaimer: Stantec assumes no responsibility for data supplied in electronic format. The recipient accepts full responsibility for verifying the accuracy and completeness of the data. The recipient releases Stantec, its officers, employees, consultants and agents, from any and all claims arising in any way from the content or provision of the data LOT 19 CON 3 CORNWALL LOT 17 CON 4 CORNWALL $ ( $ LOT 18 CON 3 CORNWALL UT Legend metres Notes 1:7,500 (At original document size of 11x17) Winchester Figure No. 2 Title Zone of Investigation (120 m from Project Location) Proposed Project Components ") Point of Common Coupling. Culvert (proposed) Connection Line Inverter Step-up Transformer and Inverter Permanent Access Temporary Access During Construction 300 m from Project Location Temporary Construction Laydown and Parking Area Buildable Area Operations & Maintenance Storage Area Project Location 1. Coordinate System: NAD 1983 UTM Zone 18N 2. Base features and aerial imagery produced under license with the Ontario Ministry of Natural Resources and Forestry Queen's Printer for Ontario, Imagery Source: DRAPE Waterbody and watercourse mapping within 120 m of the Project Location has been updated based on field studies completed as part of the REA process under O. Reg. 359/09. See the Water Assessment and Water Body Report for details. Ontario Iroquois Cardinal Casselman Alexandria Coteau-du-Lac Maxville Grande-Île Finch Chesterville Morrisburg Cornwall New York Site Plan: Conceptual Project Component Layout Solar Panel Area Substation Tree Planting Area Existing / Natural Features Major Road Minor Road. Culvert (existing) Distribution Line (Hydro One) Hydro One Transmission Line Lancaster Saint-Zotique Huntingdon Québec Project Location REVF United Counties of Prepared by AW on Stormont, Dundas and Technical Review by RN on Glengarry Independent Review by RN on Client/Project BARLOW ENERGY CENTRE LIMITED PARTNERSHIP BARLOW SOLAR ENERGY CENTRE UT Other Transmission Line Pipeline Railway Watercourse Property Boundary and PIN Waterbody

25 Inverter 04 %L Transformer 04 %L %L Inverter 04 Transformer 04 %L Inverter 04 Transformer 03 %L Inverter 03 Inverter 03 %L %L Transformer 04 %L Transformer ( $ $ Legend Project Location Major Road Minor Road Railway Point Source Locations %L PM1 Hydro One Transmission Line Watercourse (Permanent) %L PM2 %L PM3 Waterbody %L PM4 GF Substation Polygon Multiple Scenario Barlow Substation Inverter 01 Inverter 02 Inverter 03 Inverter 04 Transformer 01 Transformer 02 Transformer 03 Transformer 04 Inverter 01 %L Transformer 01 %L W:\active\ \drawing\MXD\Atmosphere\ReportFigures\ _Noise_Report\ _NR_Fig3_Source_Locations.mxd Revised: By: AWhite Inverter 01 %L %L Transformer 01 Canadian National Inverter 04 Inverter 03 %L Transformer 03 %L Transformer 04 %L %L Inverter 02 Transformer 02 %L Inverter 01 %L Transformer 01 Barlow Substation 01 GF %L Inverter 03 %L Transformer 03 %L Inverter 02 %L Transformer 02 GF Barlow Substation 04 %L Inverter 02 Inverter 01 %L Transformer 02 GF %L Inverter 02 Barlow Substation 02 Transformer 01 %L Transformer 02 GF Barlow Substation 03 Cornwall Centre Road Disclaimer: Stantec assumes no responsibility for data supplied in electronic format. The recipient accepts full responsibility for verifying the accuracy and completeness of the data. The recipient releases Stantec, its officers, employees, consultants and agents, from any and all claims arising in any way from the content or provision of the data. Notes 1. Coordinate System: NAD 1983 UTM Zone 18N 2. Base features produced under license with the Ontario Ministry of Natural Resources and Forestry Queen's Printer for Ontario, Orthoimagery Drape Waterbody and watercourse mapping within 120 m of the Project Location has been updated based on field studies completed as part of the REA process under O. Reg. 359/09. See the Water Assessment and Water Body Report for details. Ohio Project Location REVB Municipality of United Prepared by AW on Counties Of Stormont, Dundas And Glengarry Client/Project BARLOW ENERGY CENTRE LP BARLOW SOLAR ENERGY CENTRE Figure No. Title Michigan Kilometres 1:5,000 (At original document size of 11x17) Ontario Toronto Pennsylvania Québec New York Ottawa Source Locations (Polygon Multiple Scenarios)

26 W:\active\ \drawing\MXD\Atmosphere\ReportFigures\ _Noise_Report\ _NR_Fig4_Points_of_Reception.mxd Revised: By: AWhite VPOR41 #* EPOR30 EPOR71 EPOR09 ") ") ") ") ") EPOR55 EPOR51 ") EPOR50 VPOR59 #* EPOR23 ") EPOR49 ") ") EPOR74 VPOR42 #* VPOR17 #* VPOR40 #* CPOR18 ( Canadian National EPOR60 ") ( CPOR46 VPOR43 #* County Road 2 Atchison Road R Trillium Drive ichmond Drive Vincent Massey Drive Mcnairn Drive Link Road VPOR19 #* Flood Plain Abandoned Commercial Building EPOR38 ") EPOR52 ") EPOR28 ") EPOR32 ") ") EPOR31 EPOR33 ") EPOR34 ") South Raisin River VPOR45 #* VPOR44 #* ") EPOR22 ( CPOR25 CPOR62 ( CPOR63 VPOR39 ( #* CPOR61 ( VPOR20 #* VPOR21 #* Highway 401 VPOR35 #* EPOR36 ") EPOR37 ") ") EPOR72 CPOR73 ( Hydro One - Right of Way Cornwall Centre Road City of Cornwall - Dump or Transfer Station VPOR16 #* EPOR15 ") EPOR11 ") VPOR26 #* EPOR14 ") ") EPOR13 VPOR27 #* ") EPOR53 EPOR47 VPOR10 ") #* CPOR67 ( #* VPOR48 EPOR12 ") EPOR02 (( ") CPOR06 ") ( ") EPOR05 CPOR68 EPOR07 ") ") EPOR01 ( CPOR58 ") EPOR08 EPOR24 EPOR04 ") ") VPOR69 #* VPOR29 ( CPOR70 #* CPOR64 ( Barlow Road Power Dam Drive CPOR65 ( UT Disclaimer: Stantec assumes no responsibility for data supplied in electronic format. The recipient accepts full responsibility for verifying the accuracy and completeness of the data. The recipient releases Stantec, its officers, employees, consultants and agents, from any and all claims arising in any way from the content or provision of the data. CPOR03 ( Speer Road ( $ $ Highway 401 UT T U Legend Notes 1. Coordinate System: NAD 1983 UTM Zone 18N 2. Base features produced under license with the Ontario Ministry of Natural Resources and Forestry Queen's Printer for Ontario, Orthoimagery First Base Solutions, Imagery Date, Waterbody and watercourse mapping within 120 m of the Project Location has been updated based on field studies completed as part of the REA process under O. Ohio Project Location Municipality of United Counties Of Stormont, Dundas And Glengarry Client/Project Figure No. Title Michigan 4 Project Location Property Boundary Lands Not Suitable for PORs Highway Major Road Minor Road Railway Hydro One Transmission Line UT Receptor Unknown Transmission Line Watercourse (Permanent) Waterbody ") Non-Participating Residence #* Non-Participating Vacant ( Commercial Kilometers 1:12,500 (At original document size of 11x17) Ontario Toronto Pennsylvania BARLOW ENERGY CENTRE LP BARLOW SOLAR ENERGY CENTRE Points of Reception Québec New York Ottawa REVB Prepared by AW on

27 W:\active\ \drawing\MXD\Atmosphere\ReportFigures\ _Noise_Report\ _NR_Fig5-8_Equivalent_Sound_Level_Contours.mxd Revised: By: AWhite Inverter 04 %L Inverter 03 %L %L Transformer 04 %L Transformer 03 CPOR18 ( EPOR60 ") CPOR46 ( Canadian National 40 db %L Inverter 01 %L Transformer 01 Barlow Substation 01 GF Cornwall Centre Road %L Inverter 02 %L Transformer Disclaimer: Stantec assumes no responsibility for data supplied in electronic format. The recipient accepts full responsibility for verifying the accuracy and completeness of the data. The recipient releases Stantec, its officers, employees, consultants and agents, from any and all claims arising in any way from the content or provision of the data VPOR45 #* ( $ $ CPOR25 ( VPOR69 #* VPOR29 #* Legend Kilometres 1:5,000 (At original document size of 11x17) Notes 1. Coordinate System: NAD 1983 UTM Zone 18N 2. Base features produced under license with the Ontario Ministry of Natural Resources and Forestry Queen's Printer for Ontario, Orthoimagery First Base Solutions, Imagery Date, Waterbody and watercourse mapping within 120 m of the Project Location has been updated based on field studies completed as part of the REA process under O. Reg. 359/09. See the Water Assessment and Water Body Report for details. Ohio Project Location REVA Municipality of United Prepared by AW on Counties Of Stormont, Dundas And Glengarry Client/Project BARLOW ENERGY CENTRE LP BARLOW SOLAR ENERGY CENTRE Figure No. Title Michigan 5 Project Location Major Road Minor Road Railway Hydro One Transmission Line GF Watercourse Waterbody Substation Point Source Locations %L PM1 Polygon Multiple Scenario Receptor Barlow Substation Inverter 01 Inverter 02 Inverter 03 Inverter 04 Transformer 01 Transformer 02 Transformer 03 Transformer 04 ") Non-Participating Residence #* Non-Participating Vacant ( Commercial Equivalent Sound Level Contours for Polygon Multiple Scenario - 40 db Ontario Toronto Pennsylvania Québec New York Ottawa Polygon Multiple Scenario #1: Predicted Equivalent Sound Level Contours

28 W:\active\ \drawing\MXD\Atmosphere\ReportFigures\ _Noise_Report\ _NR_Fig5-8_Equivalent_Sound_Level_Contours.mxd Revised: By: AWhite CPOR18 ( EPOR60 ") CPOR46 ( Inverter 04 %L %L Transformer 04 %L Inverter 01 Transformer 01 %L %L Inverter 02 %L Transformer 02 Canadian National Cornwall Centre Road 40 db %L Inverter 03 %L Transformer 03 GF Barlow Substation Disclaimer: Stantec assumes no responsibility for data supplied in electronic format. The recipient accepts full responsibility for verifying the accuracy and completeness of the data. The recipient releases Stantec, its officers, employees, consultants and agents, from any and all claims arising in any way from the content or provision of the data VPOR45 #* ( $ $ CPOR25 ( VPOR69 #* VPOR29 #* Legend Kilometres 1:5,000 (At original document size of 11x17) Notes 1. Coordinate System: NAD 1983 UTM Zone 18N 2. Base features produced under license with the Ontario Ministry of Natural Resources and Forestry Queen's Printer for Ontario, Orthoimagery First Base Solutions, Imagery Date, Waterbody and watercourse mapping within 120 m of the Project Location has been updated based on field studies completed as part of the REA process under O. Reg. 359/09. See the Water Assessment and Water Body Report for details. Ohio Project Location REVA Municipality of United Prepared by AW on Counties Of Stormont, Dundas And Glengarry Client/Project BARLOW ENERGY CENTRE LP BARLOW SOLAR ENERGY CENTRE Figure No. Title Michigan 6 Project Location Major Road Minor Road Railway Hydro One Transmission Line GF Watercourse Waterbody Substation Point Source Locations %L PM2 Polygon Multiple Scenario Receptor Barlow Substation Inverter 01 Inverter 02 Inverter 03 Inverter 04 Transformer 01 Transformer 02 Transformer 03 Transformer 04 ") Non-Participating Residence #* Non-Participating Vacant ( Commercial Equivalent Sound Level Contours for Polygon Multiple Scenario - 40 db Ontario Toronto Pennsylvania Québec New York Ottawa Polygon Multiple Scenario #2: Predicted Equivalent Sound Level Contours

29 W:\active\ \drawing\MXD\Atmosphere\ReportFigures\ _Noise_Report\ _NR_Fig5-8_Equivalent_Sound_Level_Contours.mxd Revised: By: AWhite CPOR18 ( EPOR60 ") Inverter 04 %L Transformer 04 %L CPOR46 ( Inverter 01 %L %L Transformer 01 Canadian National Inverter 03 %L %L Transformer 03 %L Inverter 02 %L Transformer 02 Cornwall Centre Road GF Barlow Substation Disclaimer: Stantec assumes no responsibility for data supplied in electronic format. The recipient accepts full responsibility for verifying the accuracy and completeness of the data. The recipient releases Stantec, its officers, employees, consultants and agents, from any and all claims arising in any way from the content or provision of the data. 40 db VPOR45 #* ( $ $ CPOR25 ( VPOR69 #* VPOR29 #* Legend Kilometres 1:5,000 (At original document size of 11x17) Notes 1. Coordinate System: NAD 1983 UTM Zone 18N 2. Base features produced under license with the Ontario Ministry of Natural Resources and Forestry Queen's Printer for Ontario, Orthoimagery First Base Solutions, Imagery Date, Waterbody and watercourse mapping within 120 m of the Project Location has been updated based on field studies completed as part of the REA process under O. Reg. 359/09. See the Water Assessment and Water Body Report for details. Ohio Project Location REVA Municipality of United Prepared by AW on Counties Of Stormont, Dundas And Glengarry Client/Project BARLOW ENERGY CENTRE LP BARLOW SOLAR ENERGY CENTRE Figure No. Title Michigan 7 Project Location Major Road Minor Road Railway Hydro One Transmission Line GF Watercourse Waterbody Substation Point Source Locations %L PM3 Polygon Multiple Scenario Receptor Barlow Substation Inverter 01 Inverter 02 Inverter 03 Inverter 04 Transformer 01 Transformer 02 Transformer 03 Transformer 04 ") Non-Participating Residence #* Non-Participating Vacant ( Commercial Equivalent Sound Level Contours for Polygon Multiple Scenario - 40 db Ontario Toronto Pennsylvania Québec New York Ottawa Polygon Multiple Scenario #3: Predicted Equivalent Sound Level Contours

30 W:\active\ \drawing\MXD\Atmosphere\ReportFigures\ _Noise_Report\ _NR_Fig5-8_Equivalent_Sound_Level_Contours.mxd Revised: By: AWhite CPOR18 ( EPOR60 ") CPOR46 ( Inverter 01 %L Transformer 01 %L %L Inverter 04 Transformer 04 %L Inverter 03 %L %L Transformer 03 Canadian National 40 db %L Inverter 02 %L Transformer 02 Barlow Substation 04 GF Cornwall Centre Road Disclaimer: Stantec assumes no responsibility for data supplied in electronic format. The recipient accepts full responsibility for verifying the accuracy and completeness of the data. The recipient releases Stantec, its officers, employees, consultants and agents, from any and all claims arising in any way from the content or provision of the data VPOR45 #* ( $ $ CPOR25 ( VPOR69 #* VPOR29 #* Legend Kilometres 1:5,000 (At original document size of 11x17) Notes 1. Coordinate System: NAD 1983 UTM Zone 18N 2. Base features produced under license with the Ontario Ministry of Natural Resources and Forestry Queen's Printer for Ontario, Orthoimagery First Base Solutions, Imagery Date, Waterbody and watercourse mapping within 120 m of the Project Location has been updated based on field studies completed as part of the REA process under O. Reg. 359/09. See the Water Assessment and Water Body Report for details. Ohio Project Location REVA Municipality of United Prepared by AW on Counties Of Stormont, Dundas And Glengarry Client/Project BARLOW ENERGY CENTRE LP BARLOW SOLAR ENERGY CENTRE Figure No. Title Michigan 8 Project Location Major Road Minor Road Railway Hydro One Transmission Line GF Watercourse Waterbody Substation Point Source Locations %L PM4 Polygon Multiple Scenario Receptor Barlow Substation Inverter 01 Inverter 02 Inverter 03 Inverter 04 Transformer 01 Transformer 02 Transformer 03 Transformer 04 ") Non-Participating Residence #* Non-Participating Vacant ( Commercial Equivalent Sound Level Contours for Polygon Multiple Scenario - 40 db Ontario Toronto Pennsylvania Québec New York Ottawa Polygon Multiple Scenario #4: Predicted Equivalent Sound Level Contours

31 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT APPENDIX B: EQUIPMENT SPECIFICATIONS AND SOUND DATA

32 HEC Open field Noise Level SURROUNDING NOISE DETAIL FREESUN SOLAR INVERTER / POWER ELECTRONICS

33 HEC-US1500VDC TECHNICAL CHARACTERISTICS 690VAC - MPPt Window 976V-1250V FRAME 3 FRAME 4 FRAME 5 FRAME 6 FRAME 7 NUMBER OF MODULES REFERENCE FS1275CU15 FS1700CU15 FS2125CU15 FS2550CU15 FS3000CU15 OUTPUT INPUT EFFICIENCY & AUX. SUPPLY CABINET ENVIRON- MENT CONTROL INTERFACE PROTECTIONS CERTI- FICA- TIONS AC Output C AC Output C AC Output C; PF= Max. AC Output Current C Operating Grid Voltage (VAC) 690V ±10% Operating Grid Frequency (Hz) 60Hz Current Harmonic Distortion (THDi) < 3% per IEEE519 Power Factor (cosine phi) [1] 0.0 leading 0.0 lagging / Reactive Power injection at night Power Curtailment (kva) % / 0.1% Steps power (VDC) [2] 976V V Maximum DC voltage 1500V Minimum Start Voltage 1100V - User configurable Max. DC continuous current (A) Max. DC short circuit current (A) Efficiency (Max) (η) / CEC (η) Max. Standby Consumption (Pnight) Control Power Supply Max. Power Consumption Dimensions [WxDxH] [inches] Dimensions [WxDxH] [mm] Weight (lbs) 98.4% / 98.0% (preliminary) < approx. 40W/per module 120V / 208VAC 1kVA power supply available for external equipment Weight (kg) Air Flow Bottom intake. Exhaust top rear vent. - - Type of ventilation Forced air cooling Degree of protection NEMA 3R Permissible Ambient Temperature -22 F to +122 F / -30 C [3] to +50 C, >50 C / Active Power derating (>50 C/122 F) Relative Humidity 4% to 100% Condensing Max. Altitude (above sea level) 1000m / >1000m power derating 1% Sn (kva) per 100m (Max. 4000m) Noise level [4] < 79 dba Interface Graphic Display (inside cabinet) / Optional Freesun App display or Web display Communication protocol Power Plant Controller Keyed ON/OFF switch Digital I/O Modbus RTU, Modbus TCP/IP Optional Standard User configurable Analog I/O User configurable Floating PV array: Isolation Monitoring per MPP Ground Fault Protection NEC2014 Grounded PV Array: GFDI protection Optional PV Array transfer kit: GFDI and Isolation monitoring device Humidity control Active Heating General AC Protection & Disconn. Circuit Breaker General DC Protection & Disconn. External Disconnecting Unit Cabinet Module AC Protection & Disconn. AC contactor & fuses Module DC Protection & Disconn. DC contactor & DC fuses Overvoltage Protection AC and DC protection (type 2) Safety Utility interconnect x37.2 x x37.2 x x37.2 x x37.2 x x37.2 x x945x x945x x945x x945x x945x UL 1741; CSA 22.2 No (Pending) IEEE 1547 with Utility Interactive Control functions NOTES [1] Consult P-Q charts available: Q(kVAr)= (S(kVA) 2 -P(kW) 2 ) [2] Values at 1.00 Vac nom and cos Ф= 1. Consult Power Electronics for derating curves. [3] Heating kit option required below -20 C. [4] Sound pressure level at a distance of 1m from the rear part. POWER ELECTRONICS / SOLAR INVERTER REV. 2.0 / Jan Preliminary

34 HEC-US1500VDC TECHNICAL CHARACTERISTICS 645VAC - MPPt Window 913V-1250V FRAME 3 FRAME 4 FRAME 5 FRAME 6 FRAME 7 NUMBER OF MODULES REFERENCE FS1200CU15 FS1600CU15 FS2000CU15 FS2400CU15 FS2800CU15 OUTPUT INPUT EFFICIENCY & AUX. SUPPLY CABINET ENVIRON- MENT CONTROL INTERFACE PROTECTIONS CERTI- FICA- TIONS AC Output C AC Output C AC Output C; PF= Max. AC Output Current C Operating Grid Voltage (VAC) 645V ±10% Operating Grid Frequency (Hz) 60Hz Current Harmonic Distortion (THDi) < 3% per IEEE519 Power Factor (cosine phi) [1] 0.0 leading 0.0 lagging / Reactive Power injection at night Power Curtailment (kva) % / 0.1% Steps power (VDC) [2] 913V V Maximum DC voltage 1500V Minimum Start Voltage 1075V - User configurable Max. DC continuous current (A) Max. DC short circuit current (A) Efficiency (Max) (η) / CEC (η) Max. Standby Consumption (Pnight) Control Power Supply Max. Power Consumption Dimensions [WxDxH] [inches] Dimensions [WxDxH] [mm] Weight (lbs) 98.4% / 98.0% (preliminary) < approx. 40W/per module 120V / 208VAC 1kVA power supply available for external equipment Weight (kg) Air Flow Bottom intake. Exhaust top rear vent. - - Type of ventilation Forced air cooling Degree of protection NEMA 3R Permissible Ambient Temperature -22 F to +122 F / -30 C [3] to +50 C, >50 C / Active Power derating (>50 C/122 F) Relative Humidity 4% to 100% Condensing Max. Altitude (above sea level) 1000m / >1000m power derating 1% Sn (kva) per 100m (Max. 4000m) Noise level [4] < 79 dba Interface Graphic Display (inside cabinet) / Optional Freesun App display or Web display Communication protocol Power Plant Controller Keyed ON/OFF switch Digital I/O Modbus RTU, Modbus TCP/IP Optional Standard User configurable Analog I/O User configurable Floating PV array: Isolation Monitoring per MPP Ground Fault Protection NEC2014 Grounded PV Array: GFDI protection Optional PV Array transfer kit: GFDI and Isolation monitoring device Humidity control Active Heating General AC Protection & Disconn. Circuit Breaker General DC Protection & Disconn. External Disconnecting Unit Cabinet Module AC Protection & Disconn. AC contactor & fuses Module DC Protection & Disconn. DC contactor & DC fuses Overvoltage Protection AC and DC protection (type 2) Safety Utility interconnect x37.2 x x37.2 x x37.2 x x37.2 x x37.2 x x945x x945x x945x x945x x945x UL 1741; CSA 22.2 No (Pending) IEEE 1547 with Utility Interactive Control functions NOTES [1] Consult P-Q charts available: Q(kVAr)= (S(kVA) 2 -P(kW) 2 ) [2] Values at 1.00 Vac nom and cos Ф= 1. Consult Power Electronics for derating curves. [3] Heating kit option required below -20 C. [4] Sound pressure level at a distance of 1m from the rear part. POWER ELECTRONICS / SOLAR INVERTER REV. 2.0 / Jan Preliminary

35 HEC-US1500VDC TECHNICAL CHARACTERISTICS 600VAC - MPPt Window 849V-1250V FRAME 3 FRAME 4 FRAME 5 FRAME 6 FRAME 7 NUMBER OF MODULES REFERENCE FS1100CU15 FS1475CU15 FS1850CU15 FS2225CU15 FS2600CU15 OUTPUT INPUT EFFICIENCY & AUX. SUPPLY CABINET ENVIRON- MENT CONTROL INTERFACE PROTECTIONS CERTI- FICA- TIONS AC Output C AC Output C AC Output C; PF= Max. AC Output Current C Operating Grid Voltage (VAC) 600V ±10% Operating Grid Frequency (Hz) 60Hz Current Harmonic Distortion (THDi) < 3% per IEEE519 Power Factor (cosine phi) [1] 0.0 leading 0.0 lagging / Reactive Power injection at night Power Curtailment (kva) % / 0.1% Steps power (VDC) [2] 849V V Maximum DC voltage 1500V Minimum Start Voltage 1050V - User configurable Max. DC continuous current (A) Max. DC short circuit current (A) Efficiency (Max) (η) / CEC (η) Max. Standby Consumption (Pnight) Control Power Supply Max. Power Consumption Dimensions [WxDxH] [inches] Dimensions [WxDxH] [mm] Weight (lbs) Weight (kg) 98.4% / 98.0% (preliminary) < approx. 40W/per module 120V / 208VAC 1kVA power supply available for external equipment Air Flow Bottom intake. Exhaust top rear vent. Type of ventilation Forced air cooling Degree of protection NEMA 3R Permissible Ambient Temperature -22 F to +122 F / -30 C [3] to +50 C, >50 C / Active Power derating (>50 C/122 F) Relative Humidity 4% to 100% Condensing Max. Altitude (above sea level) 1000m / >1000m power derating 1% Sn (kva) per 100m (Max. 4000m) Noise level [4] < 79 dba Interface Graphic Display (inside cabinet) / Optional Freesun App display or Web display Communication protocol Power Plant Controller Keyed ON/OFF switch Digital I/O Modbus RTU, Modbus TCP/IP Optional Standard User configurable Analog I/O User configurable Floating PV array: Isolation Monitoring per MPP Ground Fault Protection NEC2014 Grounded PV Array: GFDI protection Optional PV Array transfer kit: GFDI and Isolation monitoring device Humidity control Active Heating General AC Protection & Disconn. Circuit Breaker General DC Protection & Disconn. External Disconnecting Unit Cabinet Module AC Protection & Disconn. AC contactor & fuses Module DC Protection & Disconn. DC contactor & DC fuses Overvoltage Protection AC and DC protection (type 2) Safety Utility interconnect x37.2 x x37.2 x x37.2 x x37.2 x x37.2 x x945x x945x x945x x945x x945x UL 1741; CSA 22.2 No (Pending) IEEE 1547 with Utility Interactive Control functions NOTES [1] Consult P-Q charts available: Q(kVAr)= (S(kVA) 2 -P(kW) 2 ) [2] Values at 1.00 Vac nom and cos Ф= 1. Consult Power Electronics for derating curves. [3] Heating kit option required below -20 C. [4] Sound pressure level at a distance of 1m from the rear part. POWER ELECTRONICS / SOLAR INVERTER REV. 2.0 / Jan Preliminary

36 HEC-US1500VDC TECHNICAL CHARACTERISTICS 565VAC - MPPt Window 800V-1250V FRAME 3 FRAME 4 FRAME 5 FRAME 6 FRAME 7 NUMBER OF MODULES REFERENCE FS1050CU15 FS1400CU15 FS1750CU15 FS2100CU15 FS2450CU15 OUTPUT INPUT EFFICIENCY & AUX. SUPPLY CABINET ENVIRON- MENT CONTROL INTERFACE PROTECTIONS CERTI- FICA- TIONS AC Output C AC Output C AC Output C; PF= Max. AC Output Current C Operating Grid Voltage (VAC) 565V ±10% Operating Grid Frequency (Hz) 60Hz Current Harmonic Distortion (THDi) < 3% per IEEE519 Power Factor (cosine phi) [1] 0.0 leading 0.0 lagging / Reactive Power injection at night Power Curtailment (kva) % / 0.1% Steps power (VDC) [2] 800V V Maximum DC voltage 1500V Minimum Start Voltage 1050V - User configurable Max. DC continuous current (A) Max. DC short circuit current (A) Efficiency (Max) (η) / CEC (η) Max. Standby Consumption (Pnight) Control Power Supply Max. Power Consumption Dimensions [WxDxH] [inches] Dimensions [WxDxH] [mm] Weight (lbs) Weight (kg) 98.4% / 98.0% (preliminary) < approx. 40W/per module 120V / 208VAC 1kVA power supply available for external equipment Air Flow Bottom intake. Exhaust top rear vent. Type of ventilation Forced air cooling Degree of protection NEMA 3R Permissible Ambient Temperature -22 F to +122 F / -30 C [3] to +50 C, >50 C / Active Power derating (>50 C/122 F) Relative Humidity 4% to 100% Condensing Max. Altitude (above sea level) 1000m / >1000m power derating 1% Sn (kva) per 100m (Max. 4000m) Noise level [4] < 79 dba Interface Graphic Display (inside cabinet) / Optional Freesun App display or Web display Communication protocol Power Plant Controller Keyed ON/OFF switch Digital I/O Modbus RTU, Modbus TCP/IP Optional Standard User configurable Analog I/O User configurable Floating PV array: Isolation Monitoring per MPP Ground Fault Protection NEC2014 Grounded PV Array: GFDI protection Optional PV Array transfer kit: GFDI and Isolation monitoring device Humidity control Active Heating General AC Protection & Disconn. Circuit Breaker General DC Protection & Disconn. External Disconnecting Unit Cabinet Module AC Protection & Disconn. AC contactor & fuses Module DC Protection & Disconn. DC contactor & DC fuses Overvoltage Protection AC and DC protection (type 2) Safety Utility interconnect x37.2 x x37.2 x x37.2 x x37.2 x x37.2 x x945x x945x x945x x945x x945x UL 1741; CSA 22.2 No (Pending) IEEE 1547 with Utility Interactive Control functions NOTES [1] Consult P-Q charts available: Q(kVAr)= (S(kVA) 2 -P(kW) 2 ) [2] Values at 1.00 Vac nom and cos Ф= 1. Consult Power Electronics for derating curves. [3] Heating kit option required below -20 C. [4] Sound pressure level at a distance of 1m from the rear part. POWER ELECTRONICS / SOLAR INVERTER REV. 2.0 / Jan Preliminary

37 On-Site Acoustic Testing PO Box 145 Pawlet, VT USA Office Toll Free August 14, 2016 Stephen Giguere Engineering Director POWER ELECTRONICS USA Boston, MA Cell Office Dear Stephen - Thank you for the opportunity to provide your company with these results, detailing the measurement of a HEC- US Inverter, at a client site located in Lancaster, CA. Testing was conducted in accordance with section 47.4 of the Canadian Environmental Protection Act, and an Acoustical Assessment Report has been produced for the device. You will find a description of the services that were provided on subsequent pages of this document. Best Regards, Richard Alan Salz CEO

38 Testing Protocol: All testing was performed to ASTM specifications Testing was conducted at client site in Lancaster, CA on August 4 th 2016 by Richard Alan Salz - CEO Testing was conducted using the Bruel & Kjaer 2270 analyzer running BZ-7222 (Sound Level Meter) and BZ (Frequency Analysis) software packages. This system is of Type 1 precision and the type approvals for the unit are included below:

39 Results of Testing: OTH = One Third Height TTH = Two Thirds Height

40 Results of Testing Testing was conducted at 1/3 height, 2/3 height, and over the top of the unit. dba = 71.9 dbc = Hz Octave Band = Hz Octave Band = Hz Octave Band = Hz Octave Band = Hz Octave Band = Hz Octave Band = Hz Octave Band = kHz Octave Band = kHz Octave Band = kHz Octave Band = kHz Octave Band = kHz Octave Band = 45.6 The above Sound Pressure dba numbers represent average of all test points

41 dba = 79.9 dbc = Hz Octave Band = Hz Octave Band = Hz Octave Band = Hz Octave Band = Hz Octave Band = Hz Octave Band = Hz Octave Band = kHz Octave Band = kHz Octave Band = kHz Octave Band = kHz Octave Band = kHz Octave Band = 53.6 The above Sound Power db numbers represent average of all test points per operational mode and Directivity Factor (Q) of 2, based upon a semi-reflective plane and a 1 meter distance Complete test data is available in accompanying XLSX file. Please contact with any questions you might have regarding the measurement protocol, or these results.

42 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT APPENDIX C: POINTS OF RECEPTION DETAILS AND SUMMARY RESULTS

43 Table C.1: Point of Reception Details Name ID Coordinates Zone Easting (m) Northing (m) Height (m) Point of Receptor 01 EPOR01 18T Point of Receptor 02 EPOR02 18T Point of Receptor 03 CPOR03 18T Point of Receptor 04 EPOR04 18T Point of Receptor 05 EPOR05 18T Point of Receptor 06 CPOR06 18T Point of Receptor 07 EPOR07 18T Point of Receptor 08 EPOR08 18T Point of Receptor 09 EPOR09 18T Point of Receptor 10 VPOR10 18T Point of Receptor 11 EPOR11 18T Point of Receptor 12 EPOR12 18T Point of Receptor 13 EPOR13 18T Point of Receptor 14 EPOR14 18T Point of Receptor 15 EPOR15 18T Point of Receptor 16 VPOR16 18T Point of Receptor 17 VPOR17 18T Point of Receptor 18 CPOR18 18T Point of Receptor 19 VPOR19 18T Point of Receptor 20 VPOR20 18T Point of Receptor 21 VPOR21 18T Point of Receptor 22 EPOR22 18T Point of Receptor 23 EPOR23 18T Point of Receptor 24 EPOR24 18T Point of Receptor 25 CPOR25 18T Point of Receptor 26 VPOR26 18T Point of Receptor 27 VPOR27 18T Point of Receptor 28 EPOR28 18T Point of Receptor 29 VPOR29 18T Point of Receptor 30 EPOR30 18T Point of Receptor 31 EPOR31 18T Point of Receptor 32 EPOR32 18T Point of Receptor 33 EPOR33 18T Point of Receptor 34 EPOR34 18T Point of Receptor 35 VPOR35 18T Point of Receptor 36 EPOR36 18T Point of Receptor 37 EPOR37 18T Point of Receptor 38 EPOR38 18T Point of Receptor 39 VPOR39 18T Point of Receptor 40 VPOR40 18T Point of Receptor 41 VPOR41 18T Point of Receptor 42 VPOR42 18T

44 Point of Receptor 43 VPOR43 18T Point of Receptor 44 VPOR44 18T Point of Receptor 45 VPOR45 18T Point of Receptor 46 CPOR46 18T Point of Receptor 47 EPOR47 18T Point of Receptor 48 VPOR48 18T Point of Receptor 49 EPOR49 18T Point of Receptor 50 EPOR50 18T Point of Receptor 51 EPOR51 18T Point of Receptor 52 EPOR52 18T Point of Receptor 53 EPOR53 18T Point of Receptor 55 EPOR55 18T Point of Receptor 57 EPOR57 18T Point of Receptor 58 CPOR58 18T Point of Receptor 59 VPOR59 18T Point of Receptor 60 EPOR60 18T Point of Receptor 61 CPOR61 18T Point of Receptor 62 CPOR62 18T Point of Receptor 63 CPOR63 18T Point of Receptor 64 CPOR64 18T Point of Receptor 65 CPOR65 18T Point of Receptor 66 CPOR66 18T Point of Receptor 67 CPOR67 18T Point of Receptor 68 CPOR68 18T Point of Receptor 69 VPOR69 18T Point of Receptor 70 CPOR70 18T Point of Receptor 71 EPOR71 18T Point of Receptor 72 EPOR72 18T Point of Receptor 73 CPOR73 18T Point of Receptor 74 EPOR74 18T

45 Table C.2: Point of Reception Sound Level Summary Name ID Scenario 01 Scenario 02 Scenario 03 Scenario 04 Point of Receptor 01 EPOR Point of Receptor 02 EPOR Point of Receptor 03 CPOR Point of Receptor 04 EPOR Point of Receptor 05 EPOR Point of Receptor 06 CPOR Point of Receptor 07 EPOR Point of Receptor 08 EPOR Point of Receptor 09 EPOR Point of Receptor 10 VPOR Point of Receptor 11 EPOR Point of Receptor 12 EPOR Point of Receptor 13 EPOR Point of Receptor 14 EPOR Point of Receptor 15 EPOR Point of Receptor 16 VPOR Point of Receptor 17 VPOR Point of Receptor 18 CPOR Point of Receptor 19 VPOR Point of Receptor 20 VPOR Point of Receptor 21 VPOR Point of Receptor 22 EPOR Point of Receptor 23 EPOR Point of Receptor 24 EPOR Point of Receptor 25 CPOR Point of Receptor 26 VPOR Point of Receptor 27 VPOR Point of Receptor 28 EPOR Point of Receptor 29 VPOR Point of Receptor 30 EPOR Point of Receptor 31 EPOR Point of Receptor 32 EPOR Point of Receptor 33 EPOR Point of Receptor 34 EPOR Point of Receptor 35 VPOR Point of Receptor 36 EPOR Point of Receptor 37 EPOR Point of Receptor 38 EPOR Point of Receptor 39 VPOR Point of Receptor 40 VPOR Point of Receptor 41 VPOR Point of Receptor 42 VPOR Point of Receptor 43 VPOR Point of Receptor 44 VPOR Point of Receptor 45 VPOR

46 Point of Receptor 46 CPOR Point of Receptor 47 EPOR Point of Receptor 48 VPOR Point of Receptor 49 EPOR Point of Receptor 50 EPOR Point of Receptor 51 EPOR Point of Receptor 52 EPOR Point of Receptor 53 EPOR Point of Receptor 55 EPOR Point of Receptor 57 EPOR Point of Receptor 58 CPOR Point of Receptor 59 VPOR Point of Receptor 60 EPOR Point of Receptor 61 CPOR Point of Receptor 62 CPOR Point of Receptor 63 CPOR Point of Receptor 64 CPOR Point of Receptor 65 CPOR Point of Receptor 66 CPOR Point of Receptor 67 CPOR Point of Receptor 68 CPOR Point of Receptor 69 VPOR Point of Receptor 70 CPOR Point of Receptor 71 EPOR Point of Receptor 72 EPOR Point of Receptor 73 CPOR Point of Receptor 74 EPOR

47 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT APPENDIX D: CADNAA SAMPLE CALCULATIONS

48 Configuration Parameter Value General Country (user defined) Max. Error (db) 0.00 Max. Search Radius (m) Min. Dist Src to Rcvr 0.00 Partition Raster Factor 0.50 Max. Length of Section (m) Min. Length of Section (m) 1.00 Min. Length of Section (%) 0.00 Proj. Line Sources On Proj. Area Sources On Ref. Time Reference Time Day (min) Reference Time Night (min) Daytime Penalty (db) 0.00 Recr. Time Penalty (db) 6.00 Night-time Penalty (db) DTM Standard Height (m) 0.00 Model of Terrain Triangulation Reflection max. Order of Reflection 2 Search Radius Src Search Radius Rcvr Max. Distance Source - Rcvr Min. Distance Rvcr - Reflector Min. Distance Source - Reflector 0.10 Industrial (ISO 9613) Lateral Diffraction some Obj Obst. within Area Src do not shield On Screening Excl. Ground Att. over Barrier Dz with limit (20/25) Barrier Coefficients C1,2, Temperature ( C) 10 rel. Humidity (%) 70 Ground Absorption G 0.70 Wind Speed for Dir. (m/s) 3.0 Roads (TNM) Railways (Schall 03 (1990)) Strictly acc. to Schall 03 / Schall-Transrapid Aircraft (???) Strictly acc. to AzB

49 Receiver Name: Point of Receptor 01 ID: EPOR01 X: Y: Z: Point Source, ISO 9613, Name: ''Substation'', ID: ''substation_01_loc_04'' Nr. X Y Z Refl. DEN Freq. Lw l/a Optime K0 Dc Adiv Aatm Agr Afol Ahous Abar Cmet RL Lr (m) (m) (m) (Hz) db(a) db db (db) (db) (db) (db) (db) (db) (db) (db) (db) (db) db(a) DEN A Point Source, ISO 9613, Name: ''Inverter 03'', ID: ''inv_03_loc_04'' Nr. X Y Z Refl. DEN Freq. Lw l/a Optime K0 Dc Adiv Aatm Agr Afol Ahous Abar Cmet RL Lr (m) (m) (m) (Hz) db(a) db db (db) (db) (db) (db) (db) (db) (db) (db) (db) (db) db(a) DEN A Point Source, ISO 9613, Name: ''Inverter 02'', ID: ''inv_02_loc_04'' Nr. X Y Z Refl. DEN Freq. Lw l/a Optime K0 Dc Adiv Aatm Agr Afol Ahous Abar Cmet RL Lr (m) (m) (m) (Hz) db(a) db db (db) (db) (db) (db) (db) (db) (db) (db) (db) (db) db(a) DEN A Point Source, ISO 9613, Name: ''Inverter 04'', ID: ''inv_04_loc_04'' Nr. X Y Z Refl. DEN Freq. Lw l/a Optime K0 Dc Adiv Aatm Agr Afol Ahous Abar Cmet RL Lr (m) (m) (m) (Hz) db(a) db db (db) (db) (db) (db) (db) (db) (db) (db) (db) (db) db(a) DEN A Point Source, ISO 9613, Name: ''Inverter 01'', ID: ''inv_01_loc_04'' Nr. X Y Z Refl. DEN Freq. Lw l/a Optime K0 Dc Adiv Aatm Agr Afol Ahous Abar Cmet RL Lr (m) (m) (m) (Hz) db(a) db db (db) (db) (db) (db) (db) (db) (db) (db) (db) (db) db(a) DEN A Point Source, ISO 9613, Name: ''Transformer 03'', ID: ''trans_03_loc_04'' Nr. X Y Z Refl. DEN Freq. Lw l/a Optime K0 Dc Adiv Aatm Agr Afol Ahous Abar Cmet RL Lr (m) (m) (m) (Hz) db(a) db db (db) (db) (db) (db) (db) (db) (db) (db) (db) (db) db(a) DEN A Point Source, ISO 9613, Name: ''Transformer 02'', ID: ''trans_02_loc_04'' Nr. X Y Z Refl. DEN Freq. Lw l/a Optime K0 Dc Adiv Aatm Agr Afol Ahous Abar Cmet RL Lr (m) (m) (m) (Hz) db(a) db db (db) (db) (db) (db) (db) (db) (db) (db) (db) (db) db(a) DEN A Point Source, ISO 9613, Name: ''Transformer 04'', ID: ''trans_04_loc_04'' Nr. X Y Z Refl. DEN Freq. Lw l/a Optime K0 Dc Adiv Aatm Agr Afol Ahous Abar Cmet RL Lr (m) (m) (m) (Hz) db(a) db db (db) (db) (db) (db) (db) (db) (db) (db) (db) (db) db(a) DEN A Point Source, ISO 9613, Name: ''Transformer 01'', ID: ''trans_01_loc_04'' Nr. X Y Z Refl. DEN Freq. Lw l/a Optime K0 Dc Adiv Aatm Agr Afol Ahous Abar Cmet RL Lr (m) (m) (m) (Hz) db(a) db db (db) (db) (db) (db) (db) (db) (db) (db) (db) (db) db(a) DEN A

50 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT APPENDIX E: ZONING INFORMATION

51

52

53 m Legend: Provincial Highway County Road Municipal Road Unopened/Seasonal Road Allowance Railway Municipal Boundary Lot Line Legal Fabric Drainage Sub-Schedule Boundary Zoning: Residential Serviced - First Residential Serviced - Second Residential Multiples Residential Single Serviced - First Residential Single Serviced - Second Hamlet Private Services - First Hamlet Private Services - Second Rural Residential Private Services - First Rural Residential Private Services - Second Residential Mobile Park General Commercial Highway Commercial Tourist Commercial Recreation Commercial Institutional Light Industrial General Industrial Heavy Industrial Rural Industrial Agricultural Rural Open Space Salvage Yard Waste Management Mineral Aggregate Extractive - Pit Mineral Aggregate Extractive - Quarry Mineral Aggregate Extractive - Reserve Flood Plain Provincially Significant Wetland Areas of Natural and Scientific Interest Development Reserve VPOR56 - Flood Plain Zone Land cannot be used for residential purposes CPOR54 - Rural Industrial Zone Land appears abandoned and contains a single yellow industrial building. See picture below. This drawing is copyright protected and may not be reproduced or used for purposes other than execution of the described work without the express written consent of J.L. Richards & Associates Limited.

54

55 BARLOW SOLAR ENERGY CENTRE ACOUSTIC ASSESSMENT FINAL DRAFT REPORT APPENDIX F: PREDICTABLE WORST CASE

56 Figure F1 - Predictable worst case location for nearest receptor VPOR45

57 Figure F2 - Predictable worst case location for nearest receptor VPOR29 and VPOR69

Acoustic Assessment Report Silvercreek Solar Park Transformer Station Aylmer, Ontario

Acoustic Assessment Report Silvercreek Solar Park Transformer Station Aylmer, Ontario Acoustic Assessment Report Silvercreek Solar Park Transformer Station Aylmer, Ontario Prepared for Silvercreek Solar Park Inc. 49588 Vienna Line Aylmer, Ontario N5H 2R2 Prepared by Petr Chocensky, PhD,

More information

Appendix D: Preliminary Noise Evaluation

Appendix D: Preliminary Noise Evaluation Appendix D: Preliminary Noise Evaluation Acoustics The study of sound and its properties is known as acoustics. By considering basic physical properties of sound and the acoustic environment, the potential

More information

NOISE ASSESSMENT REPORT Fairview Wind Project Township of Clearview (Stayner), Ontario

NOISE ASSESSMENT REPORT Fairview Wind Project Township of Clearview (Stayner), Ontario NOISE ASSESSMENT REPORT Fairview Wind Project Township of Clearview (Stayner), Ontario Prepared for: wpd Canada Corporation 2233 Argentia Road, Suite 102 Mississauga, Ontario, L5N 2X7 Prepared by Dec 04/14

More information

Pre-Construction Sound Study. Velco Jay Substation DRAFT. January 2011 D A T A AN AL Y S IS S OL U T I ON S

Pre-Construction Sound Study. Velco Jay Substation DRAFT. January 2011 D A T A AN AL Y S IS S OL U T I ON S Pre-Construction Sound Study Substation DRAFT January 2011 D A T A AN AL Y S IS S OL U T I ON S TABLE OF CONTENTS 1.0 INTRODUCTION...1 2.0 SOUND LEVEL MONITORING...1 3.0 SOUND MODELING...4 3.1 Modeling

More information

Appendix N. Preliminary Noise Assessment Technical Memorandum

Appendix N. Preliminary Noise Assessment Technical Memorandum Appendix N Preliminary Noise Assessment Technical Memorandum SENES Consultants Limited MEMORANDUM 121 Granton Drive, Unit 12 Richmond Hill, Ontario Canada L4B 3N4 Tel: (905) 764-9380 Fax: (905) 764-9386

More information

APPENDIX M NOISE ANALYSIS

APPENDIX M NOISE ANALYSIS APPENDIX M NOISE ANALYSIS McCORMICK RANKIN CORPORATION 2655 North Sheridan Way, Suite 300 Mississauga, Ontario, L5K 2P8 Tel: (905)823-8500 Fax: (905) 823-8503 E-mail: mrc@mrc.ca Website: www.mrc.ca MEMO

More information

REVISED NOISE IMPACT STUDY

REVISED NOISE IMPACT STUDY REVISED NOISE IMPACT STUDY Benton Boarding and Daycare 5673 Fourth Line Road Ottawa, Ontario City of Ottawa File No. D07-12-13-0024 Integral DX Engineering Ltd. Page 2 of 24 TABLE OF CONTENTS 1.0 INTRODUCTION

More information

NOISE IMPACT STUDY. Benton Boarding and Daycare 5673 Fourth Line Road Ottawa, Ontario City of Ottawa File No. D

NOISE IMPACT STUDY. Benton Boarding and Daycare 5673 Fourth Line Road Ottawa, Ontario City of Ottawa File No. D NOISE IMPACT STUDY Benton Boarding and Daycare 5673 Fourth Line Road Ottawa, Ontario City of Ottawa File No. D07-12-13-0024 Page 2 of 23 TABLE OF CONTENTS 1.0 INTRODUCTION / BACKGROUND INFORMATION...6

More information

WesPac Pittsburg Energy Infrastructure Project. Noise Assessment Report

WesPac Pittsburg Energy Infrastructure Project. Noise Assessment Report WesPac Pittsburg Energy Infrastructure Project Noise Assessment Report Prepared for WesPac Energy Pittsburg LLC And Oiltanking North America LLC Prepared by TRC 1200 Wall Street West, 2 nd Floor Lyndhurst,

More information

TECHNICAL REPORT 2016 IEL ENVIRONMENTAL NOISE SURVEY OF THE DAIRYGOLD CASTLEFARM FACILITY, MITCHELSTOWN, CO. CORK.

TECHNICAL REPORT 2016 IEL ENVIRONMENTAL NOISE SURVEY OF THE DAIRYGOLD CASTLEFARM FACILITY, MITCHELSTOWN, CO. CORK. TECHNICAL REPORT 16 IEL ENVIRONMENTAL NOISE SURVEY OF THE DAIRYGOLD CASTLEFARM FACILITY, MITCHELSTOWN, CO. CORK. FOR Gabriel Kelly Group Environmental Manager Dairygold Food ingredients Castlefarm Mitchelstown

More information

Review of Baseline Noise Monitoring results and Establishment of Noise Criteria

Review of Baseline Noise Monitoring results and Establishment of Noise Criteria Appendix G Review of Baseline Noise Monitoring results and Establishment of Noise Criteria Environmental Management Plan G May 2014 Colton Coal Mine Aldershot, Queensland Review of Baseline Noise Monitoring

More information

ACOUSTIC BARRIER FOR TRANSFORMER NOISE. Ruisen Ming. SVT Engineering Consultants, Leederville, WA 6007, Australia

ACOUSTIC BARRIER FOR TRANSFORMER NOISE. Ruisen Ming. SVT Engineering Consultants, Leederville, WA 6007, Australia ICSV14 Cairns Australia 9-12 July, 2007 ACOUSTIC BARRIER FOR TRANSFORMER NOISE Ruisen Ming SVT Engineering Consultants, Leederville, WA 6007, Australia Roy.Ming@svt.com.au Abstract In this paper, an acoustic

More information

Assured Monitoring Group

Assured Monitoring Group Assured Monitoring Group YARRANLEA SOLAR FARM NOISE & VIBRATION IMPACT ASSESSMENT JANUARY 2017 I3 CONSULTING PTY LTD Project ID. 10734 R_1 DATE OF RELEASE: 15/02/2017 Table 1: Document approval Name Position

More information

BASELINE NOISE MONITORING SURVEY

BASELINE NOISE MONITORING SURVEY t m s environment ltd TMS Environment Ltd 53 Broomhill Drive Tallaght Dublin 24 Phone: +353-1-4626710 Fax: +353-1-4626714 Web: www.tmsenv.ie BASELINE NOISE MONITORING SURVEY UNIVERSITY COLLEGE DUBLIN Report

More information

CENTRAL WASTE MANAGEMENT FACILITY, INAGH, CO. CLARE. ENVIRONMENTAL NOISE MONITORING MAY 2017.

CENTRAL WASTE MANAGEMENT FACILITY, INAGH, CO. CLARE. ENVIRONMENTAL NOISE MONITORING MAY 2017. CENTRAL WASTE MANAGEMENT FACILITY, INAGH, CO. CLARE. ENVIRONMENTAL NOISE MONITORING MAY 2017. Prepared for: CLARE COUNTY COUNCIL ÁRAS CONTAE AN CHLÁIR NEW ROAD ENNIS CO. CLARE 3156 May 16 th, 2017 EPA

More information

Black. LWECS Site Permit. Stearns County. Permit Section:

Black. LWECS Site Permit. Stearns County. Permit Section: PERMIT COMPLIANCE FILING Permittee: Permit Type: Project Location: Docket No: Permit Section: Date of Submission : Black Oak Wind,, LLC LWECS Site Permit Stearns County IP6853/WS-10-1240 and IP6866/WS-11-831

More information

Site Plan Review Application. Interest in the Property (e.g. fee simple, land option, etc.)

Site Plan Review Application. Interest in the Property (e.g. fee simple, land option, etc.) 1. Identification CITY OF FENTON 301 South Leroy Street Fenton, Michigan 48430-2196 (810) 629-2261 FAX (810) 629-2004 Site Plan Review Application Project Name Applicant Name Address City/State/Zip Phone

More information

IS INTERNATIONAL STANDARD. Acoustics - Attenuation of sound during propagation outdoors - Part 2: General method of calculation

IS INTERNATIONAL STANDARD. Acoustics - Attenuation of sound during propagation outdoors - Part 2: General method of calculation INTERNATIONAL STANDARD IS0 9613-2 First edition 1996-I 2-l 5 Acoustics - Attenuation of sound during propagation outdoors - Part 2: General method of calculation Acoustique -Attenuation du son lors de

More information

B.2 MAJOR SUBDIVISION PRELIMINARY PLAN CHECKLIST

B.2 MAJOR SUBDIVISION PRELIMINARY PLAN CHECKLIST B.2 MAJOR SUBDIVISION PRELIMINARY PLAN CHECKLIST YES* GENERAL SUBMISSION ITEMS Does the submission include: 1. Thirteen (13) copies of completed Application Form? 2. Thirteen (13) copies of the Preliminary

More information

Electricity Supply to Africa and Developing Economies. Challenges and opportunities. Planning for the future in uncertain times

Electricity Supply to Africa and Developing Economies. Challenges and opportunities. Planning for the future in uncertain times Electricity Supply to Africa and Developing Economies. Challenges and opportunities. Planning for the future in uncertain times 765 kv Substation Acoustic Noise Impact Study by Predictive Software and

More information

Noise and Ground-Borne Vibration Monitoring

Noise and Ground-Borne Vibration Monitoring 69 Noise and Vibration Study Noise and Ground-Borne Vibration Monitoring Labrador City, Newfoundland Nov, 07 Iron Ore Company of Canada TABLE OF CONTENTS 1.0 INTRODUCTION... 2 1.1 Study Objectives... 2

More information

CHECKLIST PRELIMINARY SUBDIVISION AND PRELIMINARY SITE PLAN

CHECKLIST PRELIMINARY SUBDIVISION AND PRELIMINARY SITE PLAN N/A Waiver (1) Four (4) copies of application form. (2) Fifteen (15) copies of plan (3) Subdivision/site plan application fee & professional review escrow deposit (4) Variance application fee & professional

More information

Cornwall Solar Project. Natural Heritage Assessment Evaluation of Significance Report. June 5, 2012

Cornwall Solar Project. Natural Heritage Assessment Evaluation of Significance Report. June 5, 2012 Cornwall Solar Project Natural Heritage Assessment Evaluation of Significance Report June 5, 2012 Cornwall Solar Inc. Toronto, ON Natural Heritage Assessment Evaluation of Significance Report Cornwall

More information

NOISE IMPACT ASSESSMENT 2016

NOISE IMPACT ASSESSMENT 2016 Panther Environmental Solutions Ltd, Unit 4, Innovation Centre, Institute of Technology, Green Road, Carlow, Ireland. Mobile: 087-8519284 Telephone /Fax: 059-9134222 Email: info@pantherwms.com Website:

More information

CITY OF DES MOINES, IA PERMIT AND DEVELOPMENT CENTER 602 Robert D Ray Drive Des Moines, IA Phone:

CITY OF DES MOINES, IA PERMIT AND DEVELOPMENT CENTER 602 Robert D Ray Drive Des Moines, IA Phone: CITY OF DES MOINES, IA PERMIT AND DEVELOPMENT CENTER 602 Robert D Ray Drive Des Moines, IA 50311 Phone: 515-283-4200 Minor Site Plan list This checklist should be used as a guide in the preparation of

More information

November 12, Mr. Bryan Tripp Canadian Hydro Developers, Inc. 34 Harvard Road Guelph, ON N1G 4V8

November 12, Mr. Bryan Tripp Canadian Hydro Developers, Inc. 34 Harvard Road Guelph, ON N1G 4V8 November 12, 2009 Mr. Bryan Tripp Canadian Hydro Developers, Inc. 34 Harvard Road Guelph, ON N1G 4V8 Re: Summer 2009 Acoustic Audit and Intermediate Verification Measurements Amaranth Transformer Station,

More information

Appendix 8. Draft Post Construction Noise Monitoring Protocol

Appendix 8. Draft Post Construction Noise Monitoring Protocol Appendix 8 Draft Post Construction Noise Monitoring Protocol DRAFT CPV Valley Energy Center Prepared for: CPV Valley, LLC 50 Braintree Hill Office Park, Suite 300 Braintree, Massachusetts 02184 Prepared

More information

AMERICAN UNIVERSITY EAST CAMPUS DEVELOPMENT WASHINGTON, D.C. Environmental Noise Study. Project Number

AMERICAN UNIVERSITY EAST CAMPUS DEVELOPMENT WASHINGTON, D.C. Environmental Noise Study. Project Number AMERICAN UNIVERSITY EAST CAMPUS DEVELOPMENT WASHINGTON, D.C. Environmental Noise Study Project Number 11-107 Douglas P. Koehn, M.S. Senior Consultant 12040 SOUTH LAKES DRIVE, SUITE 104, RESTON, VIRGINIA

More information

Lion s Gate Secondary Wastewater Treatment Plant Pile Driving North Vancouver, BC. Final Report Rev 1

Lion s Gate Secondary Wastewater Treatment Plant Pile Driving North Vancouver, BC. Final Report Rev 1 Lion s Gate Secondary Wastewater Treatment Plant Pile Driving North Vancouver, BC Final Report Rev 1 Noise Impact Assessment RWDI # 1502274 SUBMITTED TO Paul Dufault Project Manager Metro Vancouver 4330

More information

Environment Protection Authority (EPA), Industrial Noise Policy (INP) 2000;

Environment Protection Authority (EPA), Industrial Noise Policy (INP) 2000; 10 October 2017 Suite 6, Level 1,, 146 Hunter Street Newcastle NSW 2300 PO Box 506 Pere Riini Quarry Manager Hanson Construction Materials Pty Ltd Level 5, 75 George Street Parramatta, NSW 2150 Newcastle,

More information

GCG ASSOCIATES, INC. February 8, Mr. Nathaniel Strosberg, Town Planner 101 Main Street Town of Ashland Ashland, MA 01721

GCG ASSOCIATES, INC. February 8, Mr. Nathaniel Strosberg, Town Planner 101 Main Street Town of Ashland Ashland, MA 01721 GCG ASSOCIATES, INC. CIVIL ENGINEERING AND LAND SURVEYING 84 Main Street Wilmington, Massachusetts 01887 Phone: (978) 657-9714 Fax: (978) 657-7915 February 8, 2016 Mr. Nathaniel Strosberg, Town Planner

More information

Quarterly Noise Monitoring Report Austar Coal Mine Middle Road, Paxton NSW January 2007

Quarterly Noise Monitoring Report Austar Coal Mine Middle Road, Paxton NSW January 2007 REPORT 30-1664R1R0 Quarterly Noise Monitoring Report Austar Coal Mine Middle Road, Paxton NSW January 2007 PREPARED FOR P.O Box 806 Cessnock NSW 2325 14 MAY 2007 Quarterly Noise Monitoring Report Austar

More information

The Research on Application of Cadna/A Software in Noise Prediction of Urban Substation

The Research on Application of Cadna/A Software in Noise Prediction of Urban Substation 2016 3 rd International Conference on Engineering Technology and Application (ICETA 2016) ISBN: 978-1-60595-383-0 The Research on Application of Cadna/A Software in Noise Prediction of Urban Substation

More information

Conceptual, Preliminary and Final Site Plan Review in Holladay City

Conceptual, Preliminary and Final Site Plan Review in Holladay City Conceptual, Preliminary and Final Site Plan Review in Holladay City The City of Holladay incorporated in December, 1999 and adopted its own zoning ordinance in May, 2000. All land use decisions are made

More information

Raging River Quarry. Environmental Noise Monitoring Protocol Provisional Operations 11/30/2016

Raging River Quarry. Environmental Noise Monitoring Protocol Provisional Operations 11/30/2016 Raging River Quarry Environmental Noise Monitoring Protocol Provisional Operations 11/30/2016 Introduction The Raging River Quarry operates in unincorporated King County, near Fall City, Washington. King

More information

Pfizer Ireland Pharmaceuticals

Pfizer Ireland Pharmaceuticals Allegro Acoustics Limited, Unit 2A Riverside, Tallaght Business Park, Tallaght, Dublin 24 Tel/Fax: +33 () 1 4148 Pfizer Ireland Pharmaceuticals Pfizer Grange Castle, Grange Castle Business Park, Clondalkin,

More information

OneSteel Recycling Hexham Quarterly Noise Monitoring Report Q2 2017

OneSteel Recycling Hexham Quarterly Noise Monitoring Report Q2 2017 OneSteel Recycling Pty Ltd 14-Jul-2017 60493017 OneSteel Recycling Hexham Quarterly Noise Monitoring Report Q2 2017 NATA ACCREDITATION No. 2778 (14391) Accredited for compliance with ISO/IEC 17025 Testing

More information

Pipeline Blowdown Noise Levels

Pipeline Blowdown Noise Levels Pipeline Blowdown Noise Levels James Boland 1, Henrik Malker 2, Benjamin Hinze 3 1 SLR Consulting, Acoustics and Vibration, Brisbane, Australia 2 Atkins Global, Acoustics, London, United Kingdom 3 SLR

More information

WILTON MANORS, Island City 2020 WILTON DRIVE, WILTON MANORS, FLORIDA 33305

WILTON MANORS, Island City 2020 WILTON DRIVE, WILTON MANORS, FLORIDA 33305 WILTON MANORS, Island City 2020 WILTON DRIVE, WILTON MANORS, FLORIDA 33305 COMMUNITY DEVELOPMENT SERVICES (954) 390-2180 FAX: (954) 567-6069 This package includes: General Submittal Procedures Submittal

More information

Cymbaluk Noise Complaints

Cymbaluk Noise Complaints Decision 20259-D01-2015 Cymbaluk Noise Complaints December 22, 2015 Alberta Utilities Commission Decision 20259-D01-2015 Cymbaluk Noise Complaints Proceeding 20259 Application 20259-A001 December 22, 2015

More information

SECTION SITE SURVEYS

SECTION SITE SURVEYS SECTION 02 21 13 SITE SURVEYS SPEC WRITER NOTE: 1. Delete text between // // not applicable to project. Edit remaining text to suit project. 2. Use this section to specify survey required before design

More information

Application for Site Plan Review

Application for Site Plan Review Application for Site Plan Review 3275 Central Blvd., Hudsonville, Michigan 49426-1450, 616.669.0200 fax 616.669.2330 It is STRONGLY recommended that any application that must go before the Planning Commission

More information

Background Noise Survey Report SANTA ISABEL WIND FARM PROJECT

Background Noise Survey Report SANTA ISABEL WIND FARM PROJECT Background Noise Survey Report SANTA ISABEL WIND FARM PROJECT OCTOBER 2010 Prepared for: Prepared By: TABLE OF CONTENTS 1 INTRODUCTION... 3 2 METHODOLOGY... 5 2.1 Study Area and Noise Receptors... 5 2.2

More information

W For inspection purposes only. This report shall not be reproduced except in full, without the approval of BnM Environmental.

W For inspection purposes only. This report shall not be reproduced except in full, without the approval of BnM Environmental. ANNUAL MONITORING OF ENVIRONMENTAL NOISE AT THE BORD NA MóNA KILBERRY COMPOST FACILITY IN COMPLIANCE WITH IED LICENCE, NO. W0198-01 For the Attention of: Site Work & Report Prepared by: Anua File Ref:

More information

Environment Protection Authority (EPA), Industrial Noise Policy (INP) 2000;

Environment Protection Authority (EPA), Industrial Noise Policy (INP) 2000; 15 December 2017 Suite 6, Level 1, 146 Hunter Street Newcastle NSW 2300 PO Box 506 Pere Riini Quarry Manager Hanson Construction Materials Pty Ltd Level 5, 75 George Street Parramatta, NSW 2150 Newcastle,

More information

3.0 AFFECTED ENVIRONMENT

3.0 AFFECTED ENVIRONMENT 3.0 AFFECTED ENVIRONMENT 3.1 Visual Resources This section provides a discussion of the existing visual resources in the vicinity of the Imperial Valley Solar Energy Center South project site that could

More information

Noise Mitigation Study Pilot Program Summary Report Contract No

Noise Mitigation Study Pilot Program Summary Report Contract No Ohio Turnpike Commission Noise Mitigation Study Pilot Program Summary Report Contract No. 71-08-02 Prepared For: Ohio Turnpike Commission 682 Prospect Street Berea, Ohio 44017 Prepared By: November 2009

More information

Attended Noise Monitoring - Quarter Ending September 2013

Attended Noise Monitoring - Quarter Ending September 2013 Unity Mining Level 10, 350 Collins St Melbourne VIC 3000 Version: Page 2 PREPARED BY: ABN 29 001 584 612 Units 7-8, 26-28 Napier Close Deakin ACT 2600 Australia (PO Box 9344 Deakin ACT 2600 Australia)

More information

APPLICATION FOR PLANNED UNIT DEVELOPMENT (PUD) DEVELOPMENT PLAN

APPLICATION FOR PLANNED UNIT DEVELOPMENT (PUD) DEVELOPMENT PLAN 209 S. Main Street Marysville, Ohio 43040 Phone: (937) 645-7350 Fax: (937) 645-7351 www.marysvilleohio.org APPLICATION FOR PLANNED UNIT DEVELOPMENT (PUD) DEVELOPMENT PLAN *** IMPORTANT INFORMATION ~ Please

More information

City of Massillon Site Plan Checklist

City of Massillon Site Plan Checklist City of Massillon Site Plan Checklist The following information MUST be included with all Site Plans submitted for review and processing in order to constitute a complete Site Plan Package. Incomplete

More information

Bancroft & Piedmont Cellular Facility

Bancroft & Piedmont Cellular Facility Page 1 of 19 Environmental Noise Analysis Bancroft & Piedmont Cellular Facility Berkeley, California BAC Job # 2015-177 Prepared For: Complete Wireless Consulting Attn: Ms. Kim Le 2009 V Street Sacramento,

More information

Southwest Anthony Henday Drive At Wedgewood Heights Residential Neighborhood in Edmonton, AB

Southwest Anthony Henday Drive At Wedgewood Heights Residential Neighborhood in Edmonton, AB aci Acoustical Consultants Inc. 5031-210 Street Edmonton, Alberta, Canada T6M 0A8 Phone: (780) 414-6373 www.aciacoustical.com Environmental Noise Study For Southwest Anthony Henday Drive At Wedgewood Heights

More information

SPECIFICATIONS FOR NEW UNDERGROUND RESIDENTIAL DISTRIBUTION SYSTEMS

SPECIFICATIONS FOR NEW UNDERGROUND RESIDENTIAL DISTRIBUTION SYSTEMS Page: 4-1 4.0 URD Process and Documentation Requirements 4.1 Process Steps The process of developing underground distribution facilities in a residential area consists of 10 major steps, which are summarized

More information

Muswellbrook Coal Company

Muswellbrook Coal Company Muswellbrook Coal Company Environmental ise Monitoring May 2015 Prepared for Muswellbrook Coal Page i Muswellbrook Coal Company Environmental ise Monitoring May 2015 Reference: Report date: 18 June 2015

More information

Assessing the accuracy of directional real-time noise monitoring systems

Assessing the accuracy of directional real-time noise monitoring systems Proceedings of ACOUSTICS 2016 9-11 November 2016, Brisbane, Australia Assessing the accuracy of directional real-time noise monitoring systems Jesse Tribby 1 1 Global Acoustics Pty Ltd, Thornton, NSW,

More information

Acoustic Assessment Report Whittington Wind Farm Project Township of Amaranth (Whittington), Ontario

Acoustic Assessment Report Whittington Wind Farm Project Township of Amaranth (Whittington), Ontario Acoustic Assessment Report Whittington Wind Farm Project Township of Amaranth (Whittington), Ontario Prepared for: wpd Canada Corporation 2233 Argentia Road Suite 102 Mississauga, Ontario L5N 2X7 Prepared

More information

List of Figures. List of Forms

List of Figures. List of Forms City of Columbia Engineering Regulations PART 1: SUBMISSION OF PLANS Table of Contents Paragraph Description Page No. 1.1 General 1-1 1.2 Engineer s Report 1-1 1.3 Plans 1-3 1.4 Revisions to Approved Plan

More information

Ashton Coal. Environmental Noise Monitoring May Prepared for Ashton Coal Operations Pty Ltd

Ashton Coal. Environmental Noise Monitoring May Prepared for Ashton Coal Operations Pty Ltd Ashton Coal Environmental Noise Monitoring May 2018 Prepared for Ashton Coal Operations Pty Ltd Page i Ashton Coal Environmental Noise Monitoring May 2018 Reference: Report date: 5 June 2018 Prepared for

More information

Soltec (Ireland) Limited Mullingar Business Park, Mullingar, Co Westmeath. Annual Noise Report

Soltec (Ireland) Limited Mullingar Business Park, Mullingar, Co Westmeath. Annual Noise Report Mullingar Business Park, Mullingar, Co Westmeath. Annual Noise Report 2013 Licence Number: W0115-01 Report Date: 09 th July 2013 Report Number: 3220-13-03 Version 0 AXIS environmental services 40 Coolraine

More information

580 - NOISE BARRIERS OPSS 580 INDEX

580 - NOISE BARRIERS OPSS 580 INDEX 580 - OPSS 580 INDEX 580.1 GENERAL 580.1.1 Noise Barrier Design Elements 580.1.1.1 Wind-Load Designs 580.1.1.2 Sound-Absorptive Barriers 580.1.1.3 Noise Barrier Colour, Pattern and Texture 580.1.2 Grading

More information

CALGARY SOUTHEAST STONEY TRAIL Detailed Design 17th Avenue SE to Macleod Trail South (Hwy 2A) Calgary, Alberta

CALGARY SOUTHEAST STONEY TRAIL Detailed Design 17th Avenue SE to Macleod Trail South (Hwy 2A) Calgary, Alberta CALGARY SOUTHEAST STONEY TRAIL Detailed Design 17th Avenue SE to Macleod Trail South (Hwy 2A) Calgary, Alberta NOISE REPORT Prepared for: Alberta Infrastructure and Transportation 2 nd Floor, Twin Atria

More information

UC Berkeley Northside Relocation Cellular Facility

UC Berkeley Northside Relocation Cellular Facility Page 1 of 19 Environmental Noise Analysis UC Berkeley Northside Relocation Cellular Facility Berkeley, California BAC Job # 2015-290 Prepared For: Complete Wireless Consulting Attn: Kim Le 2009 V Street

More information

SITE PLAN Application Packet (Required For All Non-Residential Development Projects)

SITE PLAN Application Packet (Required For All Non-Residential Development Projects) SITE PLAN Application Packet (Required For All Non-Residential Development Projects) Community Development Department 90 North Main Street, Tooele, UT 84074 (435) 843-2130 Fax (435) 843-2139 Dear Applicant,

More information

ADMINISTRATIVE DESIGN REVIEW Information

ADMINISTRATIVE DESIGN REVIEW Information Information The following information summarizes the City s Administrative Design Review (ADR) provisions. If you have any questions, please contact the Planning and Development Services Department at

More information

Application Submittal Checklist for a BASIC USE PERMIT (BUP) Planning & Development Department Planning Division

Application Submittal Checklist for a BASIC USE PERMIT (BUP) Planning & Development Department Planning Division Application Submittal Checklist for a BASIC USE PERMIT (BUP) APPLICABILITY. This checklist should be used when submitting an application for a Basic Use Permit. When is a Basic Use Permit required? Section

More information

REP N Bank St. Rooftop Patio Noise Study. N45 Architecture Inc. 852 Bank Street Project Rooftop Patio Environmental Noise Study

REP N Bank St. Rooftop Patio Noise Study. N45 Architecture Inc. 852 Bank Street Project Rooftop Patio Environmental Noise Study 1of7 2014-06-02 Robert Matthews, B.ARCH., O.A.A., A.A.N.B., R.A.I.C. N45 ARCHITECTURE INC. 2nd floor, 43 Eccles Street Ottawa, Ontario Canada K1R 6S3 TEL 613-224-0095 x 234 FAX 613-224-9811 robertm@n45.ca

More information

CHAPTER 48 NOISE POLLUTION

CHAPTER 48 NOISE POLLUTION CHAPTER 48 NOISE POLLUTION 48.01 Purpose 48.06 Sound Equipment and Amplifying Equipment 48.02 Definitions 48.07 Use of Sound Equipment for Commercial 48.03 Application Advertising Prohibited 48.04 Maximum

More information

King Mill Lambert DRI# 2035 Henry County, Georgia

King Mill Lambert DRI# 2035 Henry County, Georgia Transportation Analysis King Mill Lambert DRI# 2035 Henry County, Georgia Prepared for: The Alter Group, Ltd. Prepared by: Kimley-Horn and Associates, Inc. Norcross, GA Kimley-Horn and Associates, Inc.

More information

# Insite RE Inc./ Verizon Wireless Special Use Permit Project Review for Planning and Zoning Commission

# Insite RE Inc./ Verizon Wireless Special Use Permit Project Review for Planning and Zoning Commission #2015-52 Insite RE Inc./ Verizon Wireless Special Use Permit Project Review for Planning and Zoning Commission Meeting Date: October 21, 2015 Request: Location: A Special Use Permit for a wireless communication

More information

Liddell Coal Operations

Liddell Coal Operations Liddell Coal Operations Environmental Noise Monitoring February 2018 Prepared for Liddell Coal Operations Pty Ltd Page i Liddell Coal Operations Environmental Noise Monitoring February 2018 Reference:

More information

CHAPTER 11 PRELIMINARY SITE PLAN APPROVAL PROCESS

CHAPTER 11 PRELIMINARY SITE PLAN APPROVAL PROCESS CHAPTER 11 PRELIMINARY SITE PLAN APPROVAL PROCESS 11.01.00 Preliminary Site Plan Approval 11.01.01 Intent and Purpose 11.01.02 Review 11.01.03 Application 11.01.04 Development Site to be Unified 11.01.05

More information

METHODOLOGY FOR VERIFICATION OF SOFTWARE FOR NOISE ATTENUATION CALCULATION ACCORDING TO ISO STANDARD

METHODOLOGY FOR VERIFICATION OF SOFTWARE FOR NOISE ATTENUATION CALCULATION ACCORDING TO ISO STANDARD METHODOLOGY FOR VERIFICATION OF SOFTWARE FOR NOISE ATTENUATION CALCULATION ACCORDING TO ISO 9613-2 STANDARD Jelena Tomić, Slobodan Todosijević, Nebojša Bogojević, Zlatan Šoškić Faculty of Mechanical and

More information

MINIMUM DRAWING REQUIREMENTS FOR WATER AND SEWER LINE PROJECTS

MINIMUM DRAWING REQUIREMENTS FOR WATER AND SEWER LINE PROJECTS Public Works Department Water & Wastewater Services WATER & WASTEWATER ENGINEERING DIVISION 2555 West Copans Road Pompano Beach, Florida 33369 954-831-0745 FAX 954-831-0798/0925 MINIMUM DRAWING REQUIREMENTS

More information

Appendix L Noise Technical Report. Rehabilitation and Restoration of the Longfellow Bridge

Appendix L Noise Technical Report. Rehabilitation and Restoration of the Longfellow Bridge Appendix L Noise Technical Report Rehabilitation and Restoration of the Longfellow Bridge Noise Technical Report Rehabilitation and Restoration of the Longfellow Bridge Boston, MA May, 2011* Prepared by

More information

PUBLICATION 213. Think Safety First

PUBLICATION 213. Think Safety First PUBLICATION 213 (67 PA CODE, CHAPTER 212) Think Safety First Pub 213 (02-08) Appendix Appendix A - Temporary/Portable

More information

HAMILTON TOWNSHIP Department of Planning and Zoning Application for a Commercial / Industrial Site Plan Review

HAMILTON TOWNSHIP Department of Planning and Zoning Application for a Commercial / Industrial Site Plan Review HAMILTON TOWNSHIP Department of Planning and Zoning Application for a Commercial / Industrial Site Plan Review Date: Application is hereby made for a Site Plan Review for a commercial or industrial use.

More information

INTENT An Administrative Site Plan is required for the following situations, excluding single-family detached development:

INTENT An Administrative Site Plan is required for the following situations, excluding single-family detached development: SECTION 13-400 ADMINISTRATIVE SITE PLAN 13-401 INTENT An Administrative Site Plan is required for the following situations, excluding single-family detached development: A. All development on vacant land

More information

DESIGN REVIEW PROCESS AND APPLICATION

DESIGN REVIEW PROCESS AND APPLICATION DESIGN REVIEW PROCESS AND APPLICATION Design review is the first step in the process of any construction project requiring permits. The Community Redevelopment Agency (CRA) Board is responsible for ensuring

More information

Status: Rev: Comments Date: Author: Reviewer:

Status: Rev: Comments Date: Author: Reviewer: PAKENHAM EAST PRECINCT STRUCTURE PLAN CITY GATE NOISE ASSESSMENT Rp 002 R03 20171135 28 May 2018 Marshall Day Acoustics Pty Ltd ABN: 53 470 077 191 6 Gipps Street Collingwood VIC 3066 Australia T: +613

More information

APPENDIX K NAPIER PORT WHARF NO. 6 FUTURE PORT NOISE MAPS

APPENDIX K NAPIER PORT WHARF NO. 6 FUTURE PORT NOISE MAPS APPENDIX K NAPIER PORT WHARF NO. 6 FUTURE PORT NOISE MAPS PORT OF NAPIER WHARF 6 FUTURE PORT NOISE MAPS (2026) Rp 004 r02 2015784A 20 September 2016 84 Symonds Street PO Box 5811 Wellesley Street Auckland

More information

Survey Requirements. Design Guidelines and Standards. June Office of the University Architect

Survey Requirements. Design Guidelines and Standards. June Office of the University Architect Design Guidelines and Standards Survey Requirements June 2004 Office of the University Architect Construction Management P.O. Box 210181 Cincinnati, Ohio 45221-0181 Table of Contents Survey Requirements

More information

Swan DH Noise Impact Assessment Report

Swan DH Noise Impact Assessment Report Swan 4-64 6-1 3DH Noise Impact Assessment Report April 9, 2018 Prepared for: ConocoPhillips 34501 East Quincy Avenue Watkins, Colorado 80137 Prepared by: Behrens and Associates, Inc. 13806 Inglewood Avenue

More information

Field noise measurement in the huge industrial plants for accurate prediction

Field noise measurement in the huge industrial plants for accurate prediction Field noise measurement in the huge industrial plants for accurate prediction Takahiro HIDA 1 1 JGC Corporation, Japan ABSTRACT Proper noise controls of the industrial plants based on accurate noise prediction

More information

REPORT PERIOD: JANUARY 01 MARCH

REPORT PERIOD: JANUARY 01 MARCH QUARTERLY NOISE MONITORING REPORT FOR EAST GALWAY LANDFILL REPORT PERIOD: JANUARY 01 MARCH 31 2018 IE LICENCE REF. NO. W0178-02 APRIL 2018 QUARTERLY NOISE MONITORING REPORT FOR EAST GALWAY LANDFILL REPORT

More information

Anne Arundel County Dept. of Inspections and Permits Storm Drain Checklist

Anne Arundel County Dept. of Inspections and Permits Storm Drain Checklist Project Name Project Number Engineer Plans are to be designed based on the standards set forth in the Anne Arundel County Design Manual Standards and Specifications, and all other manuals as stipulated

More information

Environmental Noise Propagation

Environmental Noise Propagation Environmental Noise Propagation How loud is a 1-ton truck? That depends very much on how far away you are, and whether you are in front of a barrier or behind it. Many other factors affect the noise level,

More information

ALISO VIEJO RANCH COMMUNITY FACILITIES PROJECT PHOTOMETRIC STUDY

ALISO VIEJO RANCH COMMUNITY FACILITIES PROJECT PHOTOMETRIC STUDY ALISO VIEJO RANCH COMMUNITY FACILITIES PROJECT PHOTOMETRIC STUDY Client: Environmental & Regulatory Specialists 2223 62 nd Street Newport Beach, California 9263 Prepared by Hongjoo Kim Landscape Architects,

More information

Last Name: First Name: M.I:

Last Name: First Name: M.I: ARCHITECTURE DESIGN REVIEW BOARD APPLICATION OFFICE USE ONLY APPLICATION # Permit # Fee Collected $ 1. Filing Status Initial Submission Amendment Withdrawal 2. Cost of Construction (Industry Standards)

More information

Rehab Glassco. Unit 4, Osberstown Industrial Park, Caragh Road, Naas, Co. Kildare. For inspection purposes only.

Rehab Glassco. Unit 4, Osberstown Industrial Park, Caragh Road, Naas, Co. Kildare. For inspection purposes only. Air I Noise I Water I Soil I Environmental Consultancy www.axisenv.ie Unit 5 Caherdavin Business Centre, Ennis Road, Limerick Unit 4, Osberstown Industrial Park, Caragh Road, Naas, Co. Kildare Environmental

More information

NOISE IMPACT STUDY FOR THE SOUTH PIER IMPROVEMENT PROJECT BROOKLYN, NEW YORK. April 2008

NOISE IMPACT STUDY FOR THE SOUTH PIER IMPROVEMENT PROJECT BROOKLYN, NEW YORK. April 2008 NOISE IMPACT STUDY FOR THE SOUTH PIER IMPROVEMENT PROJECT BROOKLYN, NEW YORK April 2008 NOISE IMPACT STUDY FOR THE SOUTH PIER IMPROVEMENT PROJECT BROOKLYN, NEW YORK Prepared for: ESS Group, Inc. 401 Wampanoag

More information

FINAL Acoustic Assessment Report Hydro One Networks Inc. Clarington Transformer Station

FINAL Acoustic Assessment Report Hydro One Networks Inc. Clarington Transformer Station FINAL Acoustic Assessment Report Clarington Transformer Station Prepared for: 483 Bay Street Toronto, ON M5G 2P5 January 7, 2015 Pinchin File: 70337.002 2015 Pinchin Ltd. Company Name: Company Address:

More information

Appendix D. Traffic Noise Analysis Report. I-94 St. Michael to Albertville Minnesota Department of Transportation

Appendix D. Traffic Noise Analysis Report. I-94 St. Michael to Albertville Minnesota Department of Transportation Appendix D Traffic Noise Analysis Report I-94 St. Michael to Albertville Minnesota Department of Transportation Traffic Noise Analysis Report I-94 St. Michael to Albertville Project SP 8680-172 Report

More information

CITY OF EL MIRAGE DEVELOPMENT APPLICATION PROCESS

CITY OF EL MIRAGE DEVELOPMENT APPLICATION PROCESS DEVELOPMENT APPLICATION PROCESS I. Technical Advisory Committee (TAC) 1. Submit TAC Review Application (See Page 3 for TAC Review Application Requirements) 2. Review of TAC Review Application by Technical

More information

CHAPTER ELECTRIC AND MAGNETIC FIELDS

CHAPTER ELECTRIC AND MAGNETIC FIELDS CHAPTER 62-814 ELECTRIC AND MAGNETIC FIELDS 62-814.100 Intent, Findings, Basis of Standards, and Research Needs 62-814.200 Electric and Magnetic Fields; Definitions 62-814.300 General Technical Requirements

More information

PRELIMINARY PLAT CHECK LIST

PRELIMINARY PLAT CHECK LIST Name of Proposed Subdivision: The following items must be included with the initial submittal of a Preliminary Plat: Application, filled out completely Project Narrative Pre-application Conference Report

More information

FACILITY RATINGS METHOD TABLE OF CONTENTS

FACILITY RATINGS METHOD TABLE OF CONTENTS FACILITY RATINGS METHOD TABLE OF CONTENTS 1.0 PURPOSE... 2 2.0 SCOPE... 3 3.0 COMPLIANCE... 4 4.0 DEFINITIONS... 5 5.0 RESPONSIBILITIES... 7 6.0 PROCEDURE... 8 6.4 Generating Equipment Ratings... 9 6.5

More information

Checklist for Minor Plan Modification

Checklist for Minor Plan Modification Checklist for Minor Plan Modification All submittal information shall be provided to the Community Development Department. All submittal information shall be presented along with the Uniform Application,

More information

Environmental Noise Assessment Cambourne to Cambridge options

Environmental Noise Assessment Cambourne to Cambridge options Environmental Noise Assessment Cambourne to Cambridge options CLIENT: Cambridgeshire County Council Major Infrastructure Delivery Box No SH1311 Shire Hall Cambridge CB3 0AP CONTACT: Tim Watkins REPORTED

More information

RESIDENTIAL DEMOLITION PERMIT APPLICANT CHECKLIST

RESIDENTIAL DEMOLITION PERMIT APPLICANT CHECKLIST RESIDENTIAL DEMOLITION PERMIT APPLICANT CHECKLIST The purpose of this form is to inform applicants of: 1) the requirements for building permits and stormwater permits for residential demolition projects;

More information

Boggabri Coal Mine. Environmental Noise Monitoring October Prepared for Boggabri Coal Operations Pty Ltd

Boggabri Coal Mine. Environmental Noise Monitoring October Prepared for Boggabri Coal Operations Pty Ltd Boggabri Coal Mine Environmental Noise Monitoring October 2017 Prepared for Boggabri Coal Operations Pty Ltd Page i Boggabri Coal Mine Environmental Noise Monitoring October 2017 Reference: Report date:

More information