OCCURRENCE OF DELAYED CURRENT ZERO CROSSING DUE TO LINE REACTIVE OVERCOMPENSATION LT CAMPINAS FERNAO DIAS 500 kv.

Size: px
Start display at page:

Download "OCCURRENCE OF DELAYED CURRENT ZERO CROSSING DUE TO LINE REACTIVE OVERCOMPENSATION LT CAMPINAS FERNAO DIAS 500 kv."

Transcription

1 OCCURRENCE OF DELAYED CURRENT ZERO CROSSING DUE TO LINE REACTIVE OVERCOMPENSATION LT CAMPINAS FERNAO DIAS 500 kv. Ricardo André Gonçalves 1 / 17

2 1 - INTRODUCRION Studies conducted on several 500 kv compensated lines indicate that it may have a risk of delayed current zeros during some switching scenarios. Transient studies indicated that under some switching cases, the line and in some instances reactor breakers (if it is switchable), may not see current zero crossings for several cycles. If the line breaker tries to open immediately after line energization, while the line currents are still in a transient state, the breaker currents will be offset with slow decaying DC. It will fail to open if there is no current zero within the interrupting time. The magnitude of the DC offset is governed by the point on the voltage wave where the breaker contacts close, line resistance, line inductance, and reactive shunt compensation. 2 / 17

3 1 - INTRODUCRION The Brazilian Energy Research Company (EPE) defines the expansion of the transmission system of Basic Network. One feature increasingly used in the expansion is dividing an existing line into two to insert a new substation. Such a procedure can eventually cause problems if the original line is compensated. Sectioning alters the degree of compensation of the new sections of the original line affecting the transient requests imposed on the terminal equipment during the transient switching. The new substation Fernao Dias 500 kv will split the previous Campinas Cachoeira Paulista 500 kv transmission line, which originally was 223 km extension, in two new transmission lines. The original line has at the Campinas terminal a switchable reactor of 112 Mvar. With the sectioning the new line Campinas Fernao Dias will have an extension of only 66 km. 3 / 17

4 1 - INTRODUCRION Therefore, when the reactor at Campinas terminal is inserted, the line become overcompensated since the shunt capacitance of the line only generates, in 500 kv, something around 75 Mvar, which in turn makes the line to be 150% compensated. An overcompensated line may eventually provide conditions to enhance delayed current zeros for the currents passing through the circuit breakers at its ends, during the energizing or automatic three phase auto-reclosing switching, as a consequence of the strong DC component. The interruption of these transient currents can cause significant demands on line circuit breakers, which are not covered by the Technical Specification Standards and Tests of high voltage circuit breakers. 4 / 17

5 2 - Description of the Phenomenon This type of problem has already been investigated in some papers. One good example of such an investigation was presented by Eletrobras/Chesf in XXIII SNPTEE, from where the following basic theory is reproduced. FIGURE 1 Equivalent Simplified Circuit Capacitance C represents the total positive sequence capacitance of the transmission line; Inductance L represents the positive sequence equivalent inductance of the line and reactors; Resistance R represents, in simplified form, the combined effect of the equivalent resistance of the total losses in the line and in the reactor and the equivalent resistance of the system X/R ratio at the point of connection. 5 / 17

6 2 - Description of the Phenomenon By manipulating the variables and making the correct equation of the circuit, one arrives in a simplified way (considering typical values for the line parameters and shunt compensation) to the graph shown in Figure 2. Para k sh menor que 0,5, a relação é menor que 1, ou seja, a componente contínua é inferior ao valor de crista da componente alternada. (a) (b) FIGURE 2 Conditions for the Occurrence of Delayed Current Zero Crossing (Zero-missing) T d -> tempo de retardo 6 / 17

7 2 - Description of the Phenomenon Depending on the K sh and Q, if the breaker opens immediately after the energization or three phase auto-reclosing of a compensated transmission line, the breaker poles, in one or more phases, can try to interrupt the current with a high DC component and, depending on the value of the current at the time of separation of the contacts and zero delay time, severe interference can occur at the circuit breaker. Modern SF6 circuit-breakers, suitable for reactor switching with minimum current cut-off voltage, may not be able to interrupt these transient currents, resulting in an extension of arc time with excessive degradation of parts of the fire extinguishing chambers or until the breaker explodes. The arc extension can also cause a reduction in dielectric strength between contacts, causing multiple re-ignitions and arc restarts until a possible burst of the chambers occurs. 7 / 17

8 3 - The 500 kv Transmission Line Campinas - Fernao Dias Study In order to analyse the Phenomena for this line, the following equivalent system was used in ATP 8 / 17

9 3 - The 500 kv Transmission Line Campinas - Fernao Dias Study - ATP Digital Simulations In order to evaluate the risks of occurrence of delayed zeros currents for the circuit breakers, digital simulations were performed using ATP for energization and three phase auto-reclosing, with and without the application of single-phase short circuits, with detailed representation of the transmission system in the area of interest through the previous described modeling suitable for studies of switching surges. For each switching condition, statistical closing times were simulated considering 4 ms of maximum pole spread, with monitoring of the currents in the switched circuit breaker and its integrals, in order to allow the selection of the closing moments of the poles that generate the highest DC component values. 9 / 17

10 3 - The 500 kv Transmission Line Campinas - Fernao Dias Study Ksh =1,5 ENERGIZATION BY CAMPINAS Oscillogram 1 shows the plots of the currents at terminals of the Campinas breakers, without short circuit and with the presence of the pre-insertion resistor 400 Ω. This case corresponds to the largest continuous current component through the circuit breaker, with a degree of compensation of 150% (Campinas reactor connected) and a ratio X0/X1 equal to 1.0 in the reactor. There is a high continuous component in the phase C (blue) current superimposed on a 60 Hz component, so that the resulting current does not reach zero during the entire simulation time, ie the delay time is greater than 30 cycles. Since the breakers have pre-insertion resistors, the effect of the dynamic resistance of the arc between contacts of the circuit breaker was not represented, but in practice this effect should not contribute to increase the damping and reduce the delay time. 10 / 17

11 3 - The 500 kv Transmission Line Campinas - Fernao Dias Study ENERGIZATION BY FERNÃO DIAS Oscillogram 2 shows the plots of the currents at terminals of the Fernão Dias breakers, without short circuit and with the presence of the pre-insertion resistor 400 Ω. There is a hugh DC component in the phase B (green) current superimposed on a 60 Hz component, so that the resulting current does not reach zero during the entire simulation time, ie the delay time is greater than 20 cycles. 11 / 17

12 3 - The 500 kv Transmission Line Campinas - Fernao Dias Study THREE PHASE SUCCESSFULL AUTO-RECLOSING BY CAMPINAS (after a single phase fault) Oscillogram 3 shows the plots of the currents at terminals of the Campinas breakers, with the presence of the 400 Ω pre-insertion resistor. There is a high DC component in the phase A (red) current superimposed on a 60 Hz component, so that the resulting current does not reach zero during the entire simulation time, ie the delay time is greater than 40 cycles. 12 / 17

13 3 - The 500 kv Transmission Line Campinas - Fernao Dias Study THREE PHASE SUCCESSFULL AUTO-RECLOSING BY F. DIAS (after a single phase fault) Oscillogram 4 shows the plots of the currents at terminals of the F. Dias breakers, with the presence of the 400 Ω pre-insertion resistor. There is a high DC component in the phase A (red) current superimposed on a 60 Hz component, so that the resulting current does not reach zero during the entire simulation time, ie the delay time is greater than 40 cycles. 13 / 17

14 4 - Conclusions - Delayed current zero phenomenon associated with the switching of shunt compensated lines has been demonstrated to be a slow decaying transient. This has a number of implications on line energization and three phase auto-reclosing. - Energization of shunt compensated line with over 60% compensation may result in large DC offsets in line breaker currents. Worse conditions are found when the composition is higher than 80%. - The delay in the appearance of current zeros can be as late as a second due to high X/R of shunt reactors. Opening of these breakers immediately following energization of such shunt compensated line will result in line breaker failure due to delayed current zeros. This effect is dependent on the degree of shunt compensation and also on the point on wave switching. 14 / 17

15 4 - Conclusions - The phenomenon depends on the characteristics of the line and its shunt compensation. It is not related to the performance of the circuit breaker and is not covered by the Specification Technical Standards and Tests of high voltage circuit breakers. Attempting to interrupt currents with delayed zeros with modern SF6 circuit breakers can cause excessive degradation of main chambers components, multiple arc re-ignitions, and even breaker explosion, representing a risk not anticipated by transmission agents. - For the line considered in this work, some actions were established in order to avoid the problem. Based on the results found, it was recommended that efforts to obtain authorization by ONS and ANEEL (Brazilian National Electric Agency) in order to relocate the switchable line reactor in Campinas to the same substation busbar. This measure will provide better reliability to the equipment (circuit breakers, reactors, etc.) and to the system, avoiding exposing the installation to failures due to the phenomenon of delayed zeros currents. In addition, it will provide greater flexibility to the system, allowing a better control of voltage in the Campinas 500 kv busbar. 15 / 17

16 4 - Conclusions - While this relocation does not take place, it has been recommended that line be only energized with the line reactor in Campinas out of operation. Moreover, whenever there is a signal of protection being sent to open the circuit breakers of the Campinas - Fernao Dias line, it should also be sent to the line reactor circuit breakers. Thus, in the event of a fault followed by automatic three phase auto-reclosing (500 ms dead time), at the moment of the reclosing, the line reactor would be disconnected, avoiding in such a way possible delayed zero currents conditions to be interrupted. - In the planning studies, whenever there is sectioning of a compensated transmission line to interconnect a new substation, the possible reallocation of terminal reactors to the busbar should be considered as part of the whole project. This situation must be regarded by ANEEL during the Study of Technical-Economic and Socio-Environmental Feasibility (Report R1). 16 / 17

17 I WOULD LIKE TO THANK THE SUPPORT GIVEN BY CIGRÉ THAT HELPED ME TO BE HERE MAKING THIS PRESENTATION OBRIGADO! THANK YOU! 17 / 17

Delayed Current Zero Crossing Phenomena during Switching of Shunt-Compensated Lines

Delayed Current Zero Crossing Phenomena during Switching of Shunt-Compensated Lines Delayed Current Zero Crossing Phenomena during Switching of Shunt-Compensated Lines David K Olson Xcel Energy Minneapolis, MN Paul Nyombi Xcel Energy Minneapolis, MN Pratap G Mysore Pratap Consulting Services,

More information

Delayed Current Zero Crossing Phenomena During Switching of Shunt-Compensated Lines

Delayed Current Zero Crossing Phenomena During Switching of Shunt-Compensated Lines Delayed Current Zero Crossing Phenomena During Switching of Shunt-Compensated Lines David K Olson Paul Nyombi Xcel Energy Pratap G Mysore Pratap Consulting Services Minnesota Power Systems Conference St.

More information

Tab 2 Voltage Stresses Switching Transients

Tab 2 Voltage Stresses Switching Transients Tab 2 Voltage Stresses Switching Transients Distribution System Engineering Course Unit 10 2017 Industry, Inc. All rights reserved. Transient Overvoltages Decay with time, usually within one or two cycles

More information

5. Black box arc modelling

5. Black box arc modelling 1 5. Black box arc modelling Circuit-breaker s performance in power system is analysed by representing the circuit-breaker characteristics by a function of electrical parameters such as current/voltage,

More information

Neutral Reactor Optimization in order to Reduce Arc Extinction Time during Three-Phase Tripping

Neutral Reactor Optimization in order to Reduce Arc Extinction Time during Three-Phase Tripping Neutral Reactor Optimization in order to Reduce Arc Extinction Time during Three-Phase Tripping P. Mestas, M. C. Tavares Abstract. The optimization of the grounding neutral reactor is a common practice

More information

Relevant Factors to a Statistical Analysis of Overvoltages - Application to Three-Phase Reclosing of Compensated Transmission Lines

Relevant Factors to a Statistical Analysis of Overvoltages - Application to Three-Phase Reclosing of Compensated Transmission Lines Energy and Power Engineering, 2013, 5, 1165-1171 doi:10.4236/epe.2013.54b221 Published Online July 2013 (http://www.scirp.org/journal/epe) Relevant Factors to a Statistical Analysis of Overvoltages - Application

More information

SIMPLE SOLUTIONS FOR IMPROVING LIFE OF BREAKERS USED IN TRANSMISSION AND DISTRIBUTION SYSTEMS

SIMPLE SOLUTIONS FOR IMPROVING LIFE OF BREAKERS USED IN TRANSMISSION AND DISTRIBUTION SYSTEMS SIMPLE SOLUTIONS FOR IMPROVING LIFE OF BREAKERS USED IN TRANSMISSION AND DISTRIBUTION SYSTEMS Dr. V. R. Kanetkar and Mr. K. E. Shinde Shreem Electric Limited, Jaysingpur Dist. Kolhapur, Maharashtra State

More information

2. Current interruption transients

2. Current interruption transients 1 2. Current interruption transients For circuit breakers or other switching facilities, transient voltages just after the current interruptions are of great concern with successful current breakings,

More information

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D Electricity Ten Year Statement November 2017 01 Electricity Ten Year Statement November 2017 001 Appendix D 1 Short-circuit currents 02 2 Short-circuit current terminology 04 3 Data requirements 07 4 Fault

More information

Although shunt capacitors

Although shunt capacitors INSIDE PQ The Trouble With Capacitors Part 1 Switching capacitors seems like a simple proposition, but it can lead to some very interesting problems By R. Fehr, P.E., Engineering Consultant Although shunt

More information

Appendix D Fault Levels

Appendix D Fault Levels Appendix D Fault Levels Page 1 Electricity Ten Year Statement November 2013 D.1 Short Circuit Currents Short Circuit Currents Three phase to earth and single phase to earth short circuit current analyses

More information

Shunt Reactor Switching

Shunt Reactor Switching Shunt Reactor Switching Dielectric stresses produced by circuit-breakers to shunt reactors. Presentation made during the IEEE Transformers Committee meeting, Amsterdam, Netherlands, April 2001 Presented

More information

EVALUATION OF DIFFERENT SOLUTIONS OF FAULTED PHASE EARTHING TECHNIQUE FOR AN EARTH FAULT CURRENT LIMITATION

EVALUATION OF DIFFERENT SOLUTIONS OF FAULTED PHASE EARTHING TECHNIQUE FOR AN EARTH FAULT CURRENT LIMITATION EVALUATION OF DIFFERENT SOLUTIONS OF FAULTED PHASE EARTHING TECHNIQUE FOR AN EARTH FAULT CURRENT LIMITATION David TOPOLANEK Petr TOMAN Michal PTACEK Jaromir DVORAK Brno University of Technology - Czech

More information

DC current interruption tests with HV mechanical DC circuit breaker

DC current interruption tests with HV mechanical DC circuit breaker http: //www.cigre.org CIGRÉ A3/B4-124 CIGRÉ Winnipeg 2017 Colloquium Study Committees A3, B4 & D1 Winnipeg, Canada September 30 October 6, 2017 DC current interruption tests with HV mechanical DC circuit

More information

Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017

Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017 Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017 NAME: LOCATION: 1. The primitive self-inductance per foot of length

More information

AORC Technical meeting 2014

AORC Technical meeting 2014 http : //www.cigre.org B4-112 AORC Technical meeting 214 HVDC Circuit Breakers for HVDC Grid Applications K. Tahata, S. Ka, S. Tokoyoda, K. Kamei, K. Kikuchi, D. Yoshida, Y. Kono, R. Yamamoto, H. Ito Mitsubishi

More information

ELECTRICAL POWER TRANSMISSION TRAINER

ELECTRICAL POWER TRANSMISSION TRAINER ELECTRICAL POWER TRANSMISSION TRAINER ELECTRICAL POWER TRANSMISSION TRAINER This training system has been designed to provide the students with a fully comprehensive knowledge in Electrical Power Engineering

More information

System grounding of wind farm medium voltage cable grids

System grounding of wind farm medium voltage cable grids Downloaded from orbit.dtu.dk on: Apr 23, 2018 System grounding of wind farm medium voltage cable grids Hansen, Peter; Østergaard, Jacob; Christiansen, Jan S. Published in: NWPC 2007 Publication date: 2007

More information

Power System Studies

Power System Studies Power System Studies Laois Ballyragget Cable Feasibility Study PE667-F4-R3-1-3 ESBI Engineering Solutions Stephen Court, 18/21 St Stephen s Green, Dublin 2, Ireland Telephone+353-1-73 8 Fax+353-1-661 66

More information

PROTECTION APPLICATION HANDBOOK

PROTECTION APPLICATION HANDBOOK BOOK No 6 Revision 0 Global Organization Innovative Solutions Product & Substation System Business Business PROTECTION APPLICATION HANDBOOK BA THS / BU Transmission Systems and Substations LEC Support

More information

Study of High Voltage AC Underground Cable Systems Silva, Filipe Miguel Faria da; Bak, Claus Leth; Wiechowski, Wojciech T.

Study of High Voltage AC Underground Cable Systems Silva, Filipe Miguel Faria da; Bak, Claus Leth; Wiechowski, Wojciech T. Aalborg Universitet Study of High Voltage AC Underground Cable Systems Silva, Filipe Miguel Faria da; Bak, Claus Leth; Wiechowski, Wojciech T. Published in: Proceedings of the Danish PhD Seminar on Detailed

More information

POWER SYSTEM TRANSIENTS - Switching Overvoltages in Power Systems - Juan A. Martinez-Velasco, Jacinto Martin-Arnedo

POWER SYSTEM TRANSIENTS - Switching Overvoltages in Power Systems - Juan A. Martinez-Velasco, Jacinto Martin-Arnedo SWITCHING OVERVOLTAGES IN POWER SYSTEMS Juan A. Martinez-Velasco Universitat Politècnica de Catalunya, Barcelona, Spain Jacinto Martin-Arnedo Estabanell Energía, Granollers, Spain Keywords: Switching overvoltages,

More information

Switching Restrikes in HVAC Cable Lines and Hybrid HVAC Cable/OHL Lines

Switching Restrikes in HVAC Cable Lines and Hybrid HVAC Cable/OHL Lines Switching Restrikes in HVAC Cable Lines and Hybrid HVAC Cable/OHL Lines F. Faria da Silva, Claus L. Bak, Per B. Holst Abstract--The disconnection of HV underground cables may, if unsuccessful, originate

More information

Analysis of a 405 km transmission line with series compensation

Analysis of a 405 km transmission line with series compensation Analysis of a 405 km transmission line with series compensation by Dr. Rupert Gouws, North-West University This paper presents an investigative case study and energy efficiency analysis of the 405 km,

More information

Power System Stability. Course Notes PART-1

Power System Stability. Course Notes PART-1 PHILADELPHIA UNIVERSITY ELECTRICAL ENGINEERING DEPARTMENT Power System Stability Course Notes PART-1 Dr. A.Professor Mohammed Tawfeeq Al-Zuhairi September 2012 1 Power System Stability Introduction Dr.Mohammed

More information

Analyzing TRV of CBs on Mato Grosso Transmission System (ELETRONORTE) due to the Fixed Series Compensation installation

Analyzing TRV of CBs on Mato Grosso Transmission System (ELETRONORTE) due to the Fixed Series Compensation installation 1 Analyzing TRV of CBs on Mato Grosso Transmission System (ELETRONORTE) due to the Fixed Series Compensation installation A. L. P. de Oliveira Abstract FACTS is the acronym for Flexible AC Transmission

More information

RESONANT TRANSFORMER

RESONANT TRANSFORMER RESONANT TRANSFORMER Whenever the requirement of the test voltage is too much high, a single unit transformer can not produce such high voltage very economically, because for high voltage measurement,

More information

Harmonic filter design for electrified railways

Harmonic filter design for electrified railways filter design for electrified railways DIgSILENT USER GROUP Sydney 5 September 2013 M Jansen, S Hagaman, T George Railway electrification project Adds significant unbalanced non-linear load to the grid

More information

EH27401 Communication and Control in Electric Power Systems Lecture 2. Lars Nordström

EH27401 Communication and Control in Electric Power Systems Lecture 2. Lars Nordström EH27401 Communication and Control in Electric Power Systems Lecture 2 Lars Nordström larsn@ics.kth.se 1 Course map 2 Outline 1. Power System Topologies Transmission Grids vs Distribution grids Radial grids

More information

Chapter -3 ANALYSIS OF HVDC SYSTEM MODEL. Basically the HVDC transmission consists in the basic case of two

Chapter -3 ANALYSIS OF HVDC SYSTEM MODEL. Basically the HVDC transmission consists in the basic case of two Chapter -3 ANALYSIS OF HVDC SYSTEM MODEL Basically the HVDC transmission consists in the basic case of two convertor stations which are connected to each other by a transmission link consisting of an overhead

More information

BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 7T-30A. NORTH COAST INTERCONNECTION: SKEENA BOB QUINN SUBSYSTEM Supersedes OO 7T-30A dated 07 July 2014

BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 7T-30A. NORTH COAST INTERCONNECTION: SKEENA BOB QUINN SUBSYSTEM Supersedes OO 7T-30A dated 07 July 2014 BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 7T-30A NORTH COAST INTERCONNECTION: SKEENA BOB QUINN SUBSYSTEM Supersedes OO 7T-30A dated 07 July 2014 Expiry Year: 2018 APPROVED BY: Original signed by: Paul

More information

How OSHA s New Transient Overvoltage Requirements Affect Work Practices. B.A. YEUNG, H. BRANCO Leidos Engineering, LLC USA

How OSHA s New Transient Overvoltage Requirements Affect Work Practices. B.A. YEUNG, H. BRANCO Leidos Engineering, LLC USA 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium How OSHA s New Transient Overvoltage Requirements Affect Work Practices B.A. YEUNG,

More information

Modelling of Sf6 Circuit Breaker Arc Quenching Phenomena In Pscad

Modelling of Sf6 Circuit Breaker Arc Quenching Phenomena In Pscad Day 2 - Session IV-A High Voltage 163 Modelling of Sf6 Circuit Breaker Arc Quenching Phenomena In Pscad B. Kondala Rao, Gopal Gajjar ABB Ltd., Maneja, Vadodara, India Introduction Circuit breakers play

More information

R10. III B.Tech. II Semester Supplementary Examinations, January POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours

R10. III B.Tech. II Semester Supplementary Examinations, January POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours Code No: R3 R1 Set No: 1 III B.Tech. II Semester Supplementary Examinations, January -14 POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours Max Marks: 75 Answer any FIVE Questions

More information

TECHNICAL REPORT. Insulation co-ordination

TECHNICAL REPORT. Insulation co-ordination TECHNICAL REPORT IEC TR 60071-4 First edition 2004-06 Insulation co-ordination Part 4: Computational guide to insulation co-ordination and modelling of electrical networks IEC 2004 Copyright - all rights

More information

G. KOEPPL Koeppl Power Experts Switzerland

G. KOEPPL Koeppl Power Experts Switzerland PS3: Substation Design: New Solutions and Experiences Bus-Node Substation A Big Improvement in Short-Circuit and Switching Properties at Reduced Substation Costs G. KOEPPL Koeppl Power Experts Switzerland

More information

High voltage engineering

High voltage engineering High voltage engineering Overvoltages power frequency switching surges lightning surges Overvoltage protection earth wires spark gaps surge arresters Insulation coordination Overvoltages power frequency

More information

MODEL POWER SYSTEM TESTING GUIDE October 25, 2006

MODEL POWER SYSTEM TESTING GUIDE October 25, 2006 October 25, 2006 Document name Category MODEL POWER SYSTEM TESTING GUIDE ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy ( ) Guideline ( x ) Report or other ( ) Charter Document date

More information

Do Capacitor Switching Transients Still Cause Problems?

Do Capacitor Switching Transients Still Cause Problems? Do Capacitor Switching Transients Still Cause Problems? Mark McGranaghan We have been evaluating problems related to capacitor switching transients for many years. Capacitor banks have been used on distribution

More information

THE IMPACT OF NETWORK SPLITTING ON FAULT LEVELS AND OTHER PERFORMANCE MEASURES

THE IMPACT OF NETWORK SPLITTING ON FAULT LEVELS AND OTHER PERFORMANCE MEASURES THE IMPACT OF NETWORK SPLITTING ON FAULT LEVELS AND OTHER PERFORMANCE MEASURES C.E.T. Foote*, G.W. Ault*, J.R. McDonald*, A.J. Beddoes *University of Strathclyde, UK EA Technology Limited, UK c.foote@eee.strath.ac.uk

More information

Calculation of Transient Overvoltages by using EMTP software in a 2-Phase 132KV GIS

Calculation of Transient Overvoltages by using EMTP software in a 2-Phase 132KV GIS Calculation of Transient Overvoltages by using EMTP software in a 2-Phase 132KV GIS M. Kondalu, Dr. P.S. Subramanyam Electrical & Electronics Engineering, JNT University. Hyderabad. Joginpally B.R. Engineering

More information

Potential Risk of Failures in Switching EHV Shunt Reactors in Some One-and-a-half Breaker Scheme Substations

Potential Risk of Failures in Switching EHV Shunt Reactors in Some One-and-a-half Breaker Scheme Substations b b International Conference on Power Systems Transients IPST in New Orleans, USA Potential Risk of Failures in Switching EHV Shunt Reactors in Some One-and-a-half Breaker Scheme Substations B. Khodabakhchian,

More information

Switching and Fault Transient Analysis of 765 kv Transmission Systems

Switching and Fault Transient Analysis of 765 kv Transmission Systems Third International Conference on Power Systems, Kharagpur, INDIA December >Paper #< Switching and Transient Analysis of 6 kv Transmission Systems D Thukaram, SM IEEE, K Ravishankar, Rajendra Kumar A Department

More information

Transient recovery voltage analysis for various current breaking mathematical models: shunt reactor and capacitor bank de-energization study

Transient recovery voltage analysis for various current breaking mathematical models: shunt reactor and capacitor bank de-energization study ARCHIVES OF ELECTRICAL ENGINEERING VOL. 64(3), pp. 441-458 (2015) DOI 10.2478/aee-2015-0034 Transient recovery voltage analysis for various current breaking mathematical models: shunt reactor and capacitor

More information

SWITCHING OVERVOLTAGES IN A 400-KV CABLE SYSTEM

SWITCHING OVERVOLTAGES IN A 400-KV CABLE SYSTEM SWITCHING OVERVOLTAGES IN A 4-KV CABLE SYSTEM Mustafa Kizilcay University of Siegen Siegen, Germany kizilcay@uni-siegen.de Abstract This paper deals with the computation of switching overvoltages in a

More information

A Pyrotechnic Fault Current Limiter Model for Transient Calculations in Industrial Power Systems

A Pyrotechnic Fault Current Limiter Model for Transient Calculations in Industrial Power Systems A Pyrotechnic Fault Current Limiter Model for Transient Calculations in Industrial Power Systems T. C. Dias, B. D. Bonatto, J. M. C. Filho Abstract-- Isolated industrial power systems or with high selfgeneration,

More information

HYBRID STATCOM SOLUTIONS IN RENEWABLE SYSTEMS

HYBRID STATCOM SOLUTIONS IN RENEWABLE SYSTEMS HYBRID STATCOM SOLUTIONS IN RENEWABLE SYSTEMS Enrique PÉREZ Santiago REMENTERIA Aitor LAKA Arteche Spain Arteche Spain Ingeteam Power Technology-Spain ep@arteche.es sr@arteche.es Aitor.Laka@ingeteam.com

More information

Utility Interconnection and System Protection

Utility Interconnection and System Protection Utility Interconnection and System Protection Alex Steselboim President, Advanced Power Technologies, Inc. Utility paralleling vs. isolated operation. Isochronous kw load sharing Reactive power (VAR) sharing

More information

Adi Mulawarman, P.E Xcel Energy Minneapolis, MN. Pratap G. Mysore, P.E Pratap Consulting Services, LLC Plymouth, MN

Adi Mulawarman, P.E Xcel Energy Minneapolis, MN. Pratap G. Mysore, P.E Pratap Consulting Services, LLC Plymouth, MN Effectiveness of Surge Capacitors on Transformer Tertiary connected shunt reactors in preventing failures- Field measurements and comparison with Transient study results Pratap G. Mysore, P.E Pratap Consulting

More information

ELECTRICAL POWER ENGINEERING

ELECTRICAL POWER ENGINEERING Introduction This trainer has been designed to provide students with a fully comprehensive knowledge in Electrical Power Engineering systems. The trainer is composed of a set of modules for the simulation

More information

FGJTCFWP"KPUVKVWVG"QH"VGEJPQNQI[" FGRCTVOGPV"QH"GNGEVTKECN"GPIKPGGTKPI" VGG"246"JKIJ"XQNVCIG"GPIKPGGTKPI

FGJTCFWPKPUVKVWVGQHVGEJPQNQI[ FGRCTVOGPVQHGNGEVTKECNGPIKPGGTKPI VGG246JKIJXQNVCIGGPIKPGGTKPI FGJTFWP"KPUKWG"QH"GEJPQNQI[" FGRTOGP"QH"GNGETKEN"GPIKPGGTKPI" GG"46"JKIJ"XQNIG"GPIKPGGTKPI Resonant Transformers: The fig. (b) shows the equivalent circuit of a high voltage testing transformer (shown

More information

Application of Reactive Compensation equipment in industrial systems under aspects of harmonics and switching transients: A study of real case

Application of Reactive Compensation equipment in industrial systems under aspects of harmonics and switching transients: A study of real case Application of Reactive Compensation equipment in industrial systems under aspects of harmonics and switching transients: A study of real case Patrick Roberto de Almeida BREE patrick.almeida@bree.com.br

More information

This is a preview - click here to buy the full publication

This is a preview - click here to buy the full publication CONSOLIDATED VERSION IEC TR 62271-306 Edition 1.1 2018-08 colour inside High-voltage switchgear and controlgear Part 306: Guide to IEC 62271-100, IEC 62271-1 and other IEC standards related to alternating

More information

ANALYSIS OF FAULTS INTERRUPTED BY GENERATOR

ANALYSIS OF FAULTS INTERRUPTED BY GENERATOR ANALYSIS OF FAULTS INTERRUPTED BY GENERATOR CIRCUIT BREAKER SF 6 ING. VÁCLAV JEŽEK PROF. ING. ZDENĚK VOSTRACKÝ, DRSC., DR.H.C. Abstract: This article describes the analysis of faults interrupted by generator

More information

Exercises. 6 Exercises

Exercises. 6 Exercises 6 Exercises The following five computer exercises accompany the course. Alternative Transients Program (ATP-EMTP) will be used to compute electrical transients. First electrical network should be created

More information

Estimation of Re-striking Transient Overvoltages in a 3-Phase 132KV Gas insulated Substation

Estimation of Re-striking Transient Overvoltages in a 3-Phase 132KV Gas insulated Substation Estimation of Re-striking Transient Overvoltages in a 3-Phase 132KV Gas insulated Substation M. Kondalu1, Dr. P.S. Subramanyam2 Electrical & Electronics Engineering, JNT University. Hyderabad. 1 Kondalu_m@yahoo.com

More information

Assessment of Saturable Reactor Replacement Options

Assessment of Saturable Reactor Replacement Options Assessment of Saturable Reactor Replacement Options D.T.A Kho, K.S. Smith Abstract-- The performance of the dynamic reactive power compensation provided by the existing variable static compensation (STC)

More information

DC VACUUM CIRCUIT BREAKER

DC VACUUM CIRCUIT BREAKER DC VACUUM CIRCUIT BREAKER Lars LILJESTRAND Magnus BACKMAN Lars JONSSON ABB Sweden ABB Sweden ABB Sweden lars.liljestrand@se.abb.com magnus.backman@se.abb.com lars.e.jonsson@se.abb.com Marco RIVA ABB Italy

More information

Estimation of Re-striking Transient Over voltages in a 132KV Gas insulated Substation

Estimation of Re-striking Transient Over voltages in a 132KV Gas insulated Substation Estimation of Re-striking Transient Over voltages in a 132KV Gas insulated Substation M. Kondalu1, P.S. Subramanyam2 Electrical & Electronics Engineering, JNT University. Hyderabad. 1 Kondalu_m@yahoo.com

More information

An Introduction to the CSCT as a New Device to Compensate Reactive Power in Electrical Networks

An Introduction to the CSCT as a New Device to Compensate Reactive Power in Electrical Networks An Introduction to the CSCT as a New Device to Compensate Reactive Power in Electrical Networks Mohammad Tavakoli Bina, G.N.Alexandrov and Mohammad Golkhah Abstract A new shunt reactive power compensator,

More information

Level 6 Graduate Diploma in Engineering Electrical Energy Systems

Level 6 Graduate Diploma in Engineering Electrical Energy Systems 9210-114 Level 6 Graduate Diploma in Engineering Electrical Energy Systems Sample Paper You should have the following for this examination one answer book non-programmable calculator pen, pencil, ruler,

More information

EH2741 Communication and Control in Electric Power Systems Lecture 2

EH2741 Communication and Control in Electric Power Systems Lecture 2 KTH ROYAL INSTITUTE OF TECHNOLOGY EH2741 Communication and Control in Electric Power Systems Lecture 2 Lars Nordström larsno@kth.se Course map Outline Transmission Grids vs Distribution grids Primary Equipment

More information

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY 9. INTRODUCTION Control Cabling The protection and control equipment in power plants and substations is influenced by various of environmental conditions. One of the most significant environmental factor

More information

Lab 1. Objectives. Single Line Diagram. Methodology. Observations. Jon Jawnsy Yu 26 October 2009

Lab 1. Objectives. Single Line Diagram. Methodology. Observations. Jon Jawnsy Yu 26 October 2009 Lab 1 Objectives In this lab, our objective is to simulate a simple single machine infinite bus configuration using the PowerWorld Simulator software. We design a local generator system (a synchronous

More information

Great Northern Transmission Line: Behind the (Electrical) Design

Great Northern Transmission Line: Behind the (Electrical) Design Great Northern Transmission Line: Behind the (Electrical) Design November 8, 2017 Christian Winter, P.E. Minnesota Power Sivasis Panigrahi, P.E. POWER Engineers, Inc. What is the Great Northern Transmission

More information

GUIDE FOR APPLICATION OF IEC AND IEC

GUIDE FOR APPLICATION OF IEC AND IEC 305 GUIDE FOR APPLICATION OF IEC 67-00 AND IEC 67- PART MAKING AND BREAKING TESTS Working Group A3. October 006 GUIDE FOR APPLICATION OF IEC 67-00 AND IEC 67- PART MAKING AND BREAKING TESTS Working Group

More information

Transient Recovery Voltage (TRV) and Rate of Rise of Recovery Voltage (RRRV) of Line Circuit Breakers in Over Compensated Transmission Lines

Transient Recovery Voltage (TRV) and Rate of Rise of Recovery Voltage (RRRV) of Line Circuit Breakers in Over Compensated Transmission Lines Transient Recovery Voltage (TRV) and Rate of Rise of Recovery Voltage (RRRV) of Line Circuit Breakers in Over Compensated Transmission Lines Presenter Mark McVey C4/B5.41 INTERNATIONAL COUNCIL ON LARGE

More information

Weidong Zhang, May.9, 2016 Development of Pre-Insertion Resistor for an 800kV GIS Circuit Breaker. ABB Group May 11, 2016 Slide 1

Weidong Zhang, May.9, 2016 Development of Pre-Insertion Resistor for an 800kV GIS Circuit Breaker. ABB Group May 11, 2016 Slide 1 Weidong Zhang, May.9, 2016 Development of Pre-Insertion Resistor for an 800kV GIS Circuit Breaker Group Slide 1 Background & Objects EHV/UHV system: Widely application for long distance transmission from

More information

Cahier technique no. 101

Cahier technique no. 101 Collection Technique... Cahier technique no. 101 The behaviour of SF 6 puffer circuit-breakers under exceptionally severe conditions J.C. Henry G. Perrissin C. Rollier "Cahiers Techniques" is a collection

More information

Simulation of switching overvoltages of 400 kv shunt reactor. Shunt reactor grounded through a neutral reactor in 400/132 kv highvoltage

Simulation of switching overvoltages of 400 kv shunt reactor. Shunt reactor grounded through a neutral reactor in 400/132 kv highvoltage TRENDS SIMULATIONS ABSTRACT Bam 400/132 kv substation in Kerman region, Iran, has a 50 MVAR shunt reactor on 400 kv busbar which is grounded through a 128 kvar neutral reactor. The neutral earthing reactor

More information

High Voltage DC Transmission 2

High Voltage DC Transmission 2 High Voltage DC Transmission 2 1.0 Introduction Interconnecting HVDC within an AC system requires conversion from AC to DC and inversion from DC to AC. We refer to the circuits which provide conversion

More information

EDS FAULT LEVELS

EDS FAULT LEVELS Document Number: EDS 08-1110 Network(s): Summary: EPN, LPN, SPN ENGINEERING DESIGN STANDARD EDS 08-1110 FAULT LEVELS This standard provides guidance on the calculation, application and availability of

More information

In order to minimise distribution (11 and 22 kv) feeder breaker

In order to minimise distribution (11 and 22 kv) feeder breaker Lightning protection for equipment on MV feeders By WJD van Schalkwyk and M du Preez, Eskom This article presents the influence of lightning on MV feeders supplying small power users (400/230 V) with focus

More information

High voltage shunt capacitor banks HIGH VOLTAGE COMPENSATION AND HARMONIC FILTERING PRODUCTS

High voltage shunt capacitor banks HIGH VOLTAGE COMPENSATION AND HARMONIC FILTERING PRODUCTS High voltage shunt capacitor banks Alstom Grid high voltage shunt capacitor bank offering is divided in: By bank construction HV open rack capacitor banks HV enclosed capacitor banks By bank design HV

More information

DIFFERENCE BETWEEN SWITCHING OF MOTORS & GENERATORS WITH VACUUM TECHNOLOGY

DIFFERENCE BETWEEN SWITCHING OF MOTORS & GENERATORS WITH VACUUM TECHNOLOGY DIFFERENCE BETWEEN SWITCHING OF MOTORS & GENERATORS WITH VACUUM TECHNOLOGY Dr. Karthik Reddy VENNA Hong URBANEK Nils ANGER Siemens AG Germany Siemens AG Germany Siemens AG Germany karthikreddy.venna@siemens.com

More information

POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS.

POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS. POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS. This document may be subject to changes. Contact ARTECHE to confirm the characteristics and availability of the products

More information

Harmonic filter design for IEC compliance

Harmonic filter design for IEC compliance Harmonic filter design for IEC 61000 compliance Marius Jansen ALSTOM Grid Power System Compensation Brisbane, Australia marius.jansen@alstom.com Abstract The paper 1 provides a guideline for the selection

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements Division 502 Technical Applicability 1(1) Section 502.1 applies to: Expedited Filing Draft August 22, 2017 the legal owner of an aggregated generating facility directly connected to the transmission system

More information

Autotransformer Inadvertent Energization Through Circuit Breakers Gradient Capacitors

Autotransformer Inadvertent Energization Through Circuit Breakers Gradient Capacitors Autotransformer Inadvertent Through Circuit Breakers Gradient Capacitors E. Martínez M., E. Godoy A., R. Ruelas T. Abstract- This paper discusses the commissioning experience with a 4/23/34.5 kv (primary/secondary/tertiary)

More information

Parameter Study of Ferro-Resonance with Harmonic Balance Method

Parameter Study of Ferro-Resonance with Harmonic Balance Method Parameter Study of Ferro-Resonance with Harmonic Balance Method ALI ERBAY Degree project in Electric Power Systems Second Level, Stockholm, Sweden 2012 XR-EE-ES 2012:010 PARAMETER STUDY OF FERRO RESONANCE

More information

Modelling of Restriking and Reignition Phenomena in Three-phase Capacitor and Shunt Reactor Switching

Modelling of Restriking and Reignition Phenomena in Three-phase Capacitor and Shunt Reactor Switching Modelling of Restriking and Reignition Phenomena in Three-phase Capacitor and Shunt Reactor Switching Shui-cheong Kam School of Engineering Systems Queensland University of Technology Brisbane, Australia

More information

Power Quality and Reliablity Centre

Power Quality and Reliablity Centre Technical Note No. 8 April 2005 Power Quality and Reliablity Centre TRANSIENT OVERVOLTAGES ON THE ELECTRICITY SUPPLY NETWORK CLASSIFICATION, CAUSES AND PROPAGATION This Technical Note presents an overview

More information

A3-308 HIGH SPEED GROUNDING SWITCH FOR EXTRA-HIGH VOLTAGE LINES

A3-308 HIGH SPEED GROUNDING SWITCH FOR EXTRA-HIGH VOLTAGE LINES 21, rue d'artois, F-75008 Paris http://www.cigre.org A3-308 Session 2004 CIGRÉ HIGH SPEED GROUNDING SWITCH FOR EXTRA-HIGH VOLTAGE LINES G.E. Agafonov, I.V. Babkin, B.E. Berlin Y. F. Kaminsky, S. V. Tretiakov,

More information

Effects of Transient Recovery Voltages on Circuit Breaker Ratings

Effects of Transient Recovery Voltages on Circuit Breaker Ratings Effects of Transient Recovery Voltages on Circuit Breaker Ratings Term Project: - EE22 - Power System Transients. Spring 28 Instructor: - Dr. Bruce Mork Team: - Himanshu Bahirat Muhammad Ali Praveen KK

More information

UNIT 4 PRINCIPLES OF CIRCUIT BREAKERS SVCET

UNIT 4 PRINCIPLES OF CIRCUIT BREAKERS SVCET UNIT 4 PRINCIPLES OF CIRCUIT BREAKERS Introduction Where fuses are unsuitable or inadequate, protective relays and circuit breakers are used in combination to detect and isolate faults. Circuit breakers

More information

Fixed Series Compensation

Fixed Series Compensation Fixed Series Compensation High-reliable turnkey services for fixed series compensation NR Electric Corporation The Fixed Series Compensation (FSC) solution is composed of NR's PCS-9570 FSC control and

More information

Course ELEC Introduction to electric power and energy systems. Additional exercises with answers December reactive power compensation

Course ELEC Introduction to electric power and energy systems. Additional exercises with answers December reactive power compensation Course ELEC0014 - Introduction to electric power and energy systems Additional exercises with answers December 2017 Exercise A1 Consider the system represented in the figure below. The four transmission

More information

Analysis of Switching Transients of an EHV Transmission Line Consisting of Mixed Power Cable and Overhead Line Sections

Analysis of Switching Transients of an EHV Transmission Line Consisting of Mixed Power Cable and Overhead Line Sections Analysis of Switching Transients of an EHV Transmission Line Consisting of Mixed Power Cable and Overhead Line Sections M. Kizilcay, K. Teichmann, S. Papenheim, P. Malicki Abstract -- Within the scope

More information

(2) New Standard IEEE P (3) Core : (4) Windings :

(2) New Standard IEEE P (3) Core : (4) Windings : (d) Electrical characteristics (such as short-circuit withstand, commutating reactance, more number of windings, etc); (e) Longer life expectancy; (f) Energy efficiency; (g) more demanding environment.

More information

Long lasting transients in power filter circuits

Long lasting transients in power filter circuits Computer Applications in Electrical Engineering Vol. 12 2014 Long lasting transients in power filter circuits Jurij Warecki, Michał Gajdzica AGH University of Science and Technology 30-059 Kraków, Al.

More information

LIMITS FOR TEMPORARY OVERVOLTAGES IN ENGLAND AND WALES NETWORK

LIMITS FOR TEMPORARY OVERVOLTAGES IN ENGLAND AND WALES NETWORK LIMITS FOR TEMPORARY OEROLTAGES IN ENGLAND AND WALES NETWORK This document is for internal and contract specific use only. Disclaimer NGG and NGET or their agents, servants or contractors do not accept

More information

CHAPTER 4 POWER QUALITY AND VAR COMPENSATION IN DISTRIBUTION SYSTEMS

CHAPTER 4 POWER QUALITY AND VAR COMPENSATION IN DISTRIBUTION SYSTEMS 84 CHAPTER 4 POWER QUALITY AND VAR COMPENSATION IN DISTRIBUTION SYSTEMS 4.1 INTRODUCTION Now a days, the growth of digital economy implies a widespread use of electronic equipment not only in the industrial

More information

A Methodology for the Efficient Application of Controlled Switching to Current Interruption Cases in High-Voltage Networks

A Methodology for the Efficient Application of Controlled Switching to Current Interruption Cases in High-Voltage Networks A Methodology for the Efficient Application of Controlled Switching to Current Interruption Cases in High-Voltage Networks C. D. TSIREKIS Hellenic Transmission System Operator Kastoros 72, Piraeus GREECE

More information

Power Systems Modelling and Fault Analysis

Power Systems Modelling and Fault Analysis Power Systems Modelling and Fault Analysis Theory and Practice Nasser D. Tleis BSc, MSc, PhD, CEng, FIEE AMSTERDAM BOSTON HEIDELBERG LONDON NEW YORK OXFORD PARIS SAN DIEGO SAN FRANCISCO SINGAPORE SYDNEY

More information

Inrush current and Total Harmonic Distortion Transient of Power Transformer with Switching Capacitor Bank

Inrush current and Total Harmonic Distortion Transient of Power Transformer with Switching Capacitor Bank IRACST Engineering Science and Technology: An International Journal (ESTIJ), ISSN: -9, Vol., No., June and Total Harmonic Distortion Transient of Power Transformer with Switching Capacitor Bank ABDELSALAM.

More information

Improving High Voltage Power System Performance. Using Arc Suppression Coils

Improving High Voltage Power System Performance. Using Arc Suppression Coils Improving High Voltage Power System Performance Using Arc Suppression Coils by Robert Thomas Burgess B Com MIEAust CPEng RPEQ A Dissertation Submitted in Fulfilment of the Requirements for the degree of

More information

ANALYSIS OF A FLASHOVER OPERATION ON TWO 138KV TRANSMISSION LINES

ANALYSIS OF A FLASHOVER OPERATION ON TWO 138KV TRANSMISSION LINES ANALYSIS OF A FLASHOVER OPERATION ON TWO 138KV TRANSMISSION LINES Authors: Joe Perez, P.E.: SynchroGrid, College Station, Texas Hung Ming Chou, SynchroGrid, College Station, Texas Mike McMillan, Bryan

More information

Switching Induced Transients:

Switching Induced Transients: Switching Induced Transients: Transformer switching is the most commonly performed operation in any power delivery system and most of the times this operation can be performed without any undesirable consequences.

More information

Analysis and Mitigation Techniques of Switching Overvoltages for A 500 kv Transmission Line

Analysis and Mitigation Techniques of Switching Overvoltages for A 500 kv Transmission Line Vol. 7 (6) No.3, pp. 96-3 ISSN 78-365 Analysis and Mitigation Techniques of Switching Overvoltages for A 5 kv Transmission Line Ahmed S. Shafy *, Ahmed M.Emam**, Samy M. Ghania *, A. H. Hamza* *Electrical

More information

Experimental Investigations and Calculations in 6-35 kv Networks with Various Neutral Conditions

Experimental Investigations and Calculations in 6-35 kv Networks with Various Neutral Conditions PQ20 June 16-18, 2010 Kuressaare Experimental Investigations and Calculations in 6-35 kv Networks with Various Neutral Conditions A. Shirkovets, A. Vasilyeva, A. Telegin LLC BOLID, Novosibirsk, Russia

More information