Analyzing TRV of CBs on Mato Grosso Transmission System (ELETRONORTE) due to the Fixed Series Compensation installation

Size: px
Start display at page:

Download "Analyzing TRV of CBs on Mato Grosso Transmission System (ELETRONORTE) due to the Fixed Series Compensation installation"

Transcription

1 1 Analyzing TRV of CBs on Mato Grosso Transmission System (ELETRONORTE) due to the Fixed Series Compensation installation A. L. P. de Oliveira Abstract FACTS is the acronym for Flexible AC Transmission Systems and it refers to a group of resources used to overcome certain limitations in the static and dynamic transmission capacity of electrical networks. The main purpose of these systems is to supply the network as quickly as possible with inductive or capacitive reactive power that is adapted to its particular requirements, while also improving the transmission quality and the efficiency of the Power Transmission System. The objective of this paper is to present the criteria and conclusions of the Transient Recovery Voltage (TRV) studies realized for the installation and operation of 03 (three) Fixed Series Compensation (FSC) at Barra do Peixe 230 kv Substation, integrated at the Mato Grosso Transmission System (ELETRONORTE). The simulations were accomplished through detailed representations of the power transmission system, as well as the FSCs protection and control system, using as simulation tools the programs Alternative Transient Program (ATP) and PSS Network Torsion Machine (NETOMAC). Index Terms Equipment, High Voltage (HV), Circuit Breaker, Transient Recovery Voltage (TRV), Fixed Series Compensation (FSC), Flexible AC Transmission System (FACTS), Power Transmission System. C I. INTRODUCTION onsidering the environmental and economical difficulties to construction of new transmission lines, the use of Fixed Series Compensation (FSC) has turned into a common practice of power transmission companies in Brazil. The series compensation is presented as the best choice, because not only it makes possible increasing power transmission capacity as well as it stabilizes the interconnected energy nets through reduction of the impedance of the transmission line. The presence of FSCs usually causes rise of the Transient Recovery Voltage (TRV) in the circuit breakers of transmission lines (TL). To be able to assess the impact of the FSCs on the installation of equipment in these circuits, studies of electromagnetic transients simulations were conducted using the programs Alternative Transient Program (ATP) [1] and PSS Network Torsion Machine (NETOMAC) [2]. The 03 (three) FSCs have the following characteristics: André Luiz Pereira de Oliveira is with Siemens Ltda. Energy Sector Power Transmission - Power Transmission Solutions (E T PS), Avenida Mutinga, 3.800, 2 o Floor Pirituba São Paulo/SP ZIP CODE Brazil ( andreluiz.oliveira@siemens.com). FSC C2 [230 kv / 35 MVAr (CD 30%)] installed at Barra do Peixe Rondonópolis 230 kv TL Circuit 1; FSC C3 [230 kv / 120 MVAr (CD 50%)] installed at Barra do Peixe Rondonópolis 230 kv TL Circuit 2; FSC C4 [230 kv / 37 MVAr (CD 30%)] installed at Barra do Peixe Rio Verde 230 kv TL Circuit 1. The main purpose of the realized studies is to verify the adequacy of the high voltage circuit breakers of 03 (three) transmission lines (TLs) of Barra do Peixe 230 kv Substation, that received the installation of these 03 (three) new FSCs. A comparison was made in the power system configurations of all the values obtained without the presence of the new FSCs against the values obtained with the presence of the new FSCs (inserted in the TLs). Several types of faults in different locations of the TLs were simulated, aiming to analyze the higher voltage stresses (worst cases) to the HV circuit breakers. The severity of TRV effect is evaluated through the simulation of the circuit breakers opening for eliminating of defects in the power system. II. TRANSIENT RECOVERY VOLTAGE (TRV) Upon the faults occurrence in the electrical system, during the high voltage circuit breakers s contacts separation to interrupt the short-circuit current, the fault current does not stop instantly due to the presence of an electric arc between the contacts that guarantee the continuity of this current. The industrial frequency sinusoidal component of the short-circuit current has natural crossings through zero, during which this electric arc will be extinguished. The re-ignition of this electric arc may or may not occur during the next semi-cycle of the sinusoidal component, depending on the speed of the dielectric between the contacts recovers the insulating properties [3]-[4]. If the voltage developed across the high voltage circuit breakers contacts during this semi-cycle exceeds the dielectric insulating capacity, the electric arc re-ignition will occur, which will remain in the system until the next zero current crossing. The voltage developed between the circuit breakers contacts after the short-circuit current interruption is known as Transient Recovery Voltage (TRV). Due to the inductive and capacitive system s characteristics, the TRV has, during the initial, high frequency components superimposed on the

2 2 fundamental component, which typically decays within a few cycles. Such components are particularly responsible for exceeding the dielectric capabilities in the circuit breaker contacts [4]. While several academic examples of TRV calculation consider the electrical system represented by RLC circuits, to determine the higher frequency components present in the voltage initial growth period, elements that presents a high complexity degree should be represented, which does not permit a simple RLC network modeling [4]. Naturally the larger the number of information concerning the transmission system under study, the more detailed the representation in simulation tools and more accurate results will be obtained from the TRV. III. MATO GROSSO TRANSMISSION SYSTEM (ELETRONORTE) The Mato Grosso Transmission System (ELETRONORTE) was analyzed in two different configurations, first in the year of Fixed Series Compensation (FSC) energization configuration (in the year of 2007) and second in the future configuration (in the year of 2014). In these two configurations a detailed modeling of 500 kv and 230 kv voltage levels were used, and the external system was modeled by Thevénin equivalents, with the power capacity calculated with the use of specific computer programs. Fig. 1 presents the Configuration 2007 and Fig. 2 presents the Configuration 2014, both highlighting in red color the transmission lines where the Barra do Peixe 230 kv FSCs were installed [5]. Fig. 1. Mato Grosso Transmission System in Configuration 2007 The Configuration 2014 was basically the same as Configuration 2007, but presenting the following main important modifications on the Mato Grosso Transmission System [5]: New 500kV transmission circuit between the Cuiabá Ribeirãozinho Intermediária and Hydroelectric Power Plant Itumbiara (approximated 808 km extension); Insertion of the Hydroelectric Power Plant (HPP) Agua Limpa (13.8 kv / 170 MVA) interconnected to the Barra do Peixe 230 kv Substation; Insertion of the Hydroelectric Power Plant (HPP) Torixoréu (13.8 kv / 102 MVA) interconnected to the Barra do Peixe 230 kv Substation; Insertion of the Hydroelectric Power Plant (HPP) Couto Magalhães (13.8 kv / 72 MVA) interconnected to the Couto Magalhães 230 kv Substation. Fig. 2. Mato Grosso Transmission System in Configuration 2014 IV. TRANSIENT RECOVERY VOLTAGE ANALYSIS: CRITERION AND METHODOLOGY The Transient Recovery Voltage (TRV) analysis has the objective to verify if during the faults occurrence on the electrical system at critical operation conditions, the shortcircuit currents values are sufficient for the Spark Gaps trigger and bypass of the Fixed Series Compensation (FSC). Likewise, we want to examine whether these values in situations where minimum trigger currents do not occur, the high voltage circuit breakers are required to withstand the defects elimination. A. Initial considerations of TRV Analysis Upon the most severe Transmission Line s (TL) internal short-circuits where the FSCs are installed, the protection system will take off (isolate) the FSCs through the Spark Gap trigger and subsequent bypass (circuit breakers closing). In the simulations realized are considered that internal faults near (terminal and Kilometric) to the FSCs where the currents reach the minimum trigger values, the Spark Gaps and bypass breakers will act within milliseconds, whereas the TLs protections and their respective circuit breakers will act at least 02 (two) to 03 (three) cycles, this means tens of milliseconds. This means that the TL s circuit breakers will therefore face the condition of FSC out of the network when eliminating the defects. For more distant faults in relation to the FSCs location (remote), if the minimum trigger current values do not occur, the TL s circuit breakers should support this operational condition and eliminate the internal defects. B. Minimal Short-Circuit Currents for Spark-Gaps Trigger The minimal short-circuit currents for Spark Gap trigger were defined in the FSCs project and are presented below [6]:

3 3 FSC C2 [230 kv / 35 MVAr (CD 30%)]: 1.28 ka; FSC C3 [230 kv / 120 MVAr (CD 50%)]: 1.24 ka; FSC C4 [230 kv / 37 MVAr (CD 30%)]: C. types applied for TRV analysis 1.21 ka. The following fault types were applied to the analysis of Transient Recovery Voltage (TRV) [6]-[7]: Terminal s: those faults very close to the substation where the FSC is installed. In these cases three pole () faults and three pole ground () faults were simulated, because they are defects that provide the most severe demands for the TL s circuit breakers; Kilometric s: those faults just a few Kilometric away (up to 5 km) to the substation where the FSC is installed. In these cases single pole () faults were simulated, because it was possible to coordinate the faults elimination with the TL s circuit breakers last pole opening, thus maximizing the requests severity; Remote s: those faults away from the substation where the FSC is installed. In these cases all fault types were simulated for TL s circuit breakers verification. In the simulations it was considered that all faults are applied to stead state operation and the poles opening is realized for the waveforms analysis. This procedure does not consider the transients that occur immediately after shortcircuits, because the influence of these occur in very specific situations, for example, faults in very short TLs [8]. D. Circuit Breakers Table I presents the TL s circuit breakers nominal data [7]: 230 kv Transm Lines Nomina l Current Short Circuit First Pole Factor TABLE I TRANSMISSION LINES NOMINAL DATA B. Peixe- Rond. C1 (1x636MCM ) B. Peixe- Rond. C2 (2x795MCM ) B. Peixe-Rio Verde C1 (1x556MCM ) A A A 31.5 ka 31.5 ka 31.5 ka 1,3 1,5 1,5 E. TRV according to ABNT NBR IEC :2006 The values of Transient Recovery Voltage (TRV) used as reference for the analysis are the presumed on the standard ABNT NBR IEC :2006 [9] and presented in Tables II and III. TABLE II TRV PRESUMED VALUES FOR TERMINAL FAULTS AT 245 KV Short Circuit Current [%] First ref. Voltage [kv] 100% 60% 30% 10% 195 kv 195 kv Time [µs] 98 µs 65 µs TRV [kv] 364 kv 390 kv 400 kv 398 kv Time [µs] 392 µs 390 µs 80 µs 57 µs Growing Rate [kv/µs] 2 kv/µs 3 kv/µs 5 kv/µs 7 kv/µs TABLE III TRV PRESUMED VALUES FOR KILOMETRIC FAULTS AT 245 KV Short Circuit Current [%] 100% First ref. Voltage [kv] 150 kv Time [µs] 75 µs TRV [kv] 280 kv Time [µs] 300 µs Growing Rate [kv/µs] 2 kv/µs OBS: for kilometric faults ABNT estabilishes an unique TRV value at initial moments, associated to the first voltage levels at the Transmission Lines. V. TRANSIENT RECOVERY VOLTAGE ANALYSIS: THE MATO GROSSO TRANSMISSION SYSTEM RESULTS For the Transient Recovery Voltage (TRV) analysis a 4 (four) parameters representation was used [9]: U1 = first reference voltage in kilovolts (kv); t1 = time to reach the first reference voltage in microseconds (µs); Uc = second reference voltage (TRV peak value) in kilovolts (kv); t2 = time to reach the second reference voltage in microseconds (µs). These parameters determine the TRV waveforms and provide a measure of its severity to the TL s circuit breakers. If the waveform obtained is less than the ABNT Standard definitions (Tables II and III), the circuit breakers are dimensioned to withstand the TRV demands. The 2 (two) Mato Grosso Transmission System s configurations were considered (Fig. 1 - Configuration 2007 and Fig. 2 - Configuration 2014) [5]. Besides the normal system condition of the system (no emergencies), emergencies situations were analyzed in order to verify TRV requests in a system degraded

4 4 condition, reducing the short circuit capacity [7]. The emergencies conditions (informed by ELETRONORTE) were: 2007 Configuration: absence of 230 kv TL Ribeirãozinho Barra do Peixe (double circuit) = ; 2014 Configuration: absence of 230 kv TL Ribeirãozinho Barra do Peixe (double circuit) = ; 2014 Configuration: absence of the future Hydroelectric Power Plant (HPP) Torixoréu (13.8 kv / 102 MVA) =. The short-circuit currents were calculated to verify the Spark Gap trigger and the consequent FSCs bypass. For terminals and kilometric faults the short-circuit currents were sufficient to trigger, and the circuit breakers didn t suffer TRV problems to the defects elimination. Tables IV to VI present the TRV values for the cases which the remote faults calculation didn t reach the minimum Spark Gap trigger current, meaning that the TL s circuit breakers would be required to eliminate the defects with the FSC inserted in the TLs, in both 2007 and 2014 configurations [6] - [7]- [8]. TABLE IV TRV FOR REMOTE FAULTS IN THE 230 KV TL BARRA DO PEIXE RONDONÓPOLIS CIRCUIT 1 - FSC C2 [230 KV / 35 MVAR (CD 30%)] DGF TL stretch [km] until 180 km After 120 km After 120 km Icc [kap] TRV [kvp] Operat. Cond. 2,14 kap 459 kvp ,22 kap 470 kvp ,34 kap 417 kvp ,23 kap 482 kvp ,24 kap 494 kvp ,54 kap 408 kvp ,58 kap 400 kvp ,16 kap 499 kvp ,17 kap 501 kvp ,36 kap 449 kvp ,28 kap 516 kvp ,29 kap 518 kvp ,38 kap 458 kvp 2014 until 195 km 2,31 kap 496 kvp ,93 kap 434 kvp ,33 kap 435 kvp ,42 kap 436 kvp 2014 TABLE V TRV FOR REMOTE FAULTS IN THE 230 KV TL BARRA DO PEIXE RONDONÓPOLIS CIRCUIT 2 - FSC C3 [230 KV / 120 MVAR (CD 50%)] TL stretch [km] After 110 km After 110 km After 110 km until 115 km After 185 km After 185 km After 155 km After 80 km After 200 km After 200 km Icc [kap] TRV [kvp] Operat. Cond. 3,76 kap 605 kvp ,79 kap 607 kvp ,36 kap 512 kvp ,78 kap 663 kvp ,81 kap 666 kvp ,84 kap 563 kvp ,45 kap 568 kvp ,38 kap 569 kvp ,31 kap 496 kvp ,67 kap 471 kvp ,73 kap 682 kvp ,79 kap 684 kvp ,16 kap 636 kvp ,13 kap 470 kvp ,66 kap 439 kvp ,51 kap 613 kvp ,54 kap 614 kvp ,33 kap 492 kvp 2014

5 5 After 80 km until 110 km 4,36 kap 540 kvp ,86 kap 472 kvp 2014 TABLE VI TRV FOR REMOTE FAULTS IN THE 230 KV TL BARRA DO PEIXE RIO VERDE CIRCUIT 1 - FSC C4 [230 KV / 37 MVAR (CD 30%)] TL stretch [km] until 185 km until 241 km After 140 km until 170 km After 140 km until 175 km until 220 km until 220 km until 210 km until 210 km After 140 km until 190 km After 170 km After 170 km until 190 km Icc [kap] TRV [kvp] Operat. Cond. 2,21 kap 469 kvp ,23 kap 471 kvp ,26 kap 483 kvp ,28 kap 498 kvp ,22 kap 511 kvp ,26 kap 505 kvp ,36 kap 481 kvp ,32 kap 517 kvp ,33 kap 518 kvp ,38 kap 482 kvp ,31 kap 500 kvp ,33 kap 495 kvp ,42 kap 461 kvp 2014 The simulations results presented that the Fixed Series Compensation (FSCs) should be bypassed for three pole () remote faults, three pole to ground () remote faults, double pole to ground () remote faults and single pole () faults. Tables VII and VIII presents the TRV results evaluation due to the FSCs installation [10]. TABLE VII TRV EVALUATION DUE TO THE FIXED SERIES COMPENSATIONS (FSCS) INSTALLATION AT 230KV TLS 2007 CONFIGURATION (FIG. 1) 230 kv TL description B.Peixe Ron Stretch with Stretch without (TRV problem) 0 until 145km until 145km until 120km 120 until 180 km 0 until 145km until 145km until 110km until 110km until 140km 140 until 185 km 0 until 140km 140 until 190 km TABLE VIII TRV EVALUATION DUE TO THE FIXED SERIES COMPENSATIONS (FSCS) INSTALLATION AT 230KV TLS 2014 CONFIGURATION (FIG. 2) 230 kv TL description B.Peixe Ron Stretch with Stretch without (TRV problem) 0 until 165km until 165km until 155km until 150km until 185km until 185km until 160km until 155km until 80km 80 until 110 km 0 until 160km 160 until 220 km 0 until 160km 160 until 220 km 0 until 150km 150 until 210 km

6 6 VI. CONCLUSIONS The Brazilian Transmission System is very peculiar, covering great territorial extension and presenting an expressive predominance of the hydroelectric power generation. Those conditions enlarge the transmission importance, which is responsible for the integration between power generation sources and distant load centers. The power transmission systems make possible to gain advantage of diversities, providing energy optimization, increasing system safety and reducing the need of investments in new power generation. Flexible AC Transmission Systems (FACTS) is a technology that responds to these needs. It significantly alters the way power transmission systems are developed and controlled together with improvements in asset utilization, systems flexibility and performance The main purpose of this paper was to present the criteria and conclusions of the Transient Recovery Voltage (TRV) studies realized for the installation and operation of 03 (three) Fixed Series Compensation (FSC) at Barra do Peixe 230 kv Substation, integrated at the Mato Grosso Transmission System (ELETRONORTE). The analysis of the TRV calculation results generated the following conclusions: High Voltage Circuit Breakers of Barra do Peixe Rondonópolis 230 kv Transmission Line - Circuit 1 [FSC C2 / 230 kv / 35 MVAr (CD 30%)]: it is necessary the Spark Gap trigger and FSC bypass before the transmission line circuit breaker trip command, always when three pole () remote faults or double pole () remote faults in both power system configurations (2007 and 2014); \ High Voltage Circuit Breakers of Barra do Peixe Rondonópolis 230 kv Transmission Line - Circuit 2 [FSC C3 / 230 kv / 120 MVAr (CD 50%)]: it is necessary the Spark Gap trigger and FSC bypass before the transmission line circuit breaker trip command, always when three pole () remote faults or double pole () remote faults in both power system configurations (2007 and 2014) and single pole () fault due to HPP Torixoréu and/or duplication of the Itumbiara-Intermediária-Ribeirãozinho-Cuiabá 500 kv Transmission Line on configuration 2014; High Voltage Circuit Breakers of Barra do Peixe Rio Verde 230 kv Transmission Line - Circuit 1 [FSC C4 / 230 kv / 37 MVAr (CD 30%)]: it is necessary the Spark Gap trigger and FSC bypass before the transmission line circuit breaker trip command, always when three pole () remote faults or double pole () remote faults in both power system configurations (2007 and 2014). Logics and delays were inserted in the transmission lines s (TLs) protection system that ensured the Spark Gap trigger and FSCs bypass on the situations above described before the TLs trip command and HV circuit breakers opening. This action was implemented independent of the FSCs Protection and Control System functioning. So there was no need to change the HV circuit breakers already installed in the TLs. Through the 03 (three) new FSCs installation at Barra do Peixe 230 kv Substation, the Mato Grosso Transmission System (ELETRONORTE) had the transmission capacity increased and improved system stability. VII. REFERENCES [1] M. C. D. Tavares, P G. Campos, P. Prado, Alternative Transient Program (ATP) - Practical Summarized Guide (in Portuguese), UNICAMP - Universidade Estadual de Campinas / Faculdade de Engenharia Elétrica e de Computação FEEC / Departamento de Sistemas de Controle e Energia - DSCE, Campinas-SP-Brasil, [2] SIEMENS AG, PSS NETOMAC Professional Network Planning Software Instruction Manual, Power Transmission and Distribution, Erlangen, Germany, [3] ABNT (Brazilian Technical Standards Association) - High Voltage Circuit Breakers, ABNT Standard NBR: 7118:1994, Brazil [4] M. C. Lima, F. R. Alves, S. Henschel, L. Kirschner, Transient Electromagnetic Studies for Impact Assessment of 500 kv Series Capacitor Banks regarding the Transient Recovery Voltage imposed at Operation Equipments (in Portuguese), XVII SNPTEE Seminário Nacional de Produção e Transmissão de Energia Elétrica, Curitiba-PR- Brasil, [5] Norte Sul Engenharia, Mato Grosso (Brazil) Transmission System Barra do Peixe SS 230 kv Fixed Series Compensations Electrical Data and System Parameters (in Portuguese), Norte Sul Engenharia / ELETRONORTE - Centrais Elétricas do Norte do Brasil S.A., Brasília DF Brazil, [6] S. Henschel, G. Khun, M. Moraes, A. L. P. de Oliveira, Eletromagnetic Studies for the Barra do Peixe Power System ELETRONORTE - Brazil, Power Transmission and Distribution Service Power Technologies International PTD SE PTI, Erlangen - Germany, [7] Norte Sul Engenharia, Mato Grosso (Brazil) Transmission System Barra do Peixe SS 230 kv Fixed Series Compensations Studies of Transient Recovery Voltage (TRV) associated to the FSCs (in Portuguese), Norte Sul Engenharia / ELETRONORTE - Centrais Elétricas do Norte do Brasil S.A., Brasília DF Brazil, [8] J. T. Honda, W. S. Pinto, A. D`Juz, C. Machado Junior, E. H. Rose, Evaluation of Transient Recovery Voltage (TRV) for 550 kv Circuit Breakers of HPP Tucuruí Second Phase (in Portuguese), XV SNPTEE Seminário Nacional de Produção e Transmissão de Energia Elétrica, Foz do Iguaçu-PR-Brasil, [9] ABNT (Brazilian Technical Standards Association) - High Voltage Equipments Part 100: HVAC Circuit Breakers, ABNT Standard NBR IEC :2006, Brazil [10] Norte Sul Engenharia, Barra do Peixe SS 230 kv Fixed Series Compensations Minimal Short-Circuits Currents for Spark-gaps Triggers (in Portuguese), Norte Sul Engenharia / ELETRONORTE - Centrais Elétricas do Norte do Brasil S.A., Brasília DF Brazil, VIII. BIOGRAPHY André Luiz Pereira de Oliveira was born in São José do Rio Preto/SP, Brazil in He received his BSEE degree in electrical engineering from the Federal Engineering School of Itajubá (EFEI), Brazil, in Obtained Specialist's title in Power Systems Protection and MSc in Electrical Engineering in 2003 and 2007 respectively, from Federal University of Itajubá (UNIFEI), Brazil. Project Management Professional (PMP ) certified by the Project Management Institute - PMI of the United States of America (USA) since He works at SIEMENS Ltda. as a Project Manager since 2001 at the Energy Sector Power Transmission - Power Transmission Solutions (E T PS), responsible for the supplying of "turn-key" High Voltage Direct Current Systems (HVDC), High Voltage Substations, Protection, Control and Supervision Systems, and Power Compensation Systems (FACTS).

Brazilian Successful Experience in the Usage of Current Limiting Reactors for Short-Circuit Limitation

Brazilian Successful Experience in the Usage of Current Limiting Reactors for Short-Circuit Limitation Brazilian Successful Experience in the Usage of Current Limiting Reactors for Short-Circuit Limitation J. Amon F., P. C. Fernandez, E. H. Rose, A. D Ajuz, A. Castanheira Abstract-- With the deregulation

More information

Transient Recovery Voltage at Series Compensated Transmission Lines in Piauí, Brazil

Transient Recovery Voltage at Series Compensated Transmission Lines in Piauí, Brazil Transient Recovery Voltage at Series Compensated Transmission Lines in Piauí, Brazil S. Henschel L. Kirschner M.C. Lima Abstract As a part of ongoing 500 kv power transmission enhancements in Brazil, several

More information

Transient Recovery Voltage (TRV) and Rate of Rise of Recovery Voltage (RRRV) of Line Circuit Breakers in Over Compensated Transmission Lines

Transient Recovery Voltage (TRV) and Rate of Rise of Recovery Voltage (RRRV) of Line Circuit Breakers in Over Compensated Transmission Lines Transient Recovery Voltage (TRV) and Rate of Rise of Recovery Voltage (RRRV) of Line Circuit Breakers in Over Compensated Transmission Lines Presenter Mark McVey C4/B5.41 INTERNATIONAL COUNCIL ON LARGE

More information

OCCURRENCE OF DELAYED CURRENT ZERO CROSSING DUE TO LINE REACTIVE OVERCOMPENSATION LT CAMPINAS FERNAO DIAS 500 kv.

OCCURRENCE OF DELAYED CURRENT ZERO CROSSING DUE TO LINE REACTIVE OVERCOMPENSATION LT CAMPINAS FERNAO DIAS 500 kv. OCCURRENCE OF DELAYED CURRENT ZERO CROSSING DUE TO LINE REACTIVE OVERCOMPENSATION LT CAMPINAS FERNAO DIAS 500 kv. Ricardo André Gonçalves 1 / 17 1 - INTRODUCRION Studies conducted on several 500 kv compensated

More information

Comparison of metal oxide surge arrester models in overvoltage studies

Comparison of metal oxide surge arrester models in overvoltage studies MultiCraft International Journal of Engineering, Science and Technology Vol. 3, No. 11, 2011, pp. 35-45 INTERNATIONAL JOURNAL OF ENGINEERING, SCIENCE AND TECHNOLOGY www.ijest-ng.com www.ajol.info/index.php/ijest

More information

A Comparison of the Performance of a Conventional Transmission Line and Expanded Bundle Regarding Transient Overvoltages

A Comparison of the Performance of a Conventional Transmission Line and Expanded Bundle Regarding Transient Overvoltages A Comparison of the Performance of a Conventional Transmission Line and Bundle Regarding Transient Overvoltages F. Rodrigues Alves, O. Regis Junior Abstract: This paper presents a comparative analysis

More information

Tab 2 Voltage Stresses Switching Transients

Tab 2 Voltage Stresses Switching Transients Tab 2 Voltage Stresses Switching Transients Distribution System Engineering Course Unit 10 2017 Industry, Inc. All rights reserved. Transient Overvoltages Decay with time, usually within one or two cycles

More information

Fixed Series Compensation

Fixed Series Compensation Fixed Series Compensation High-reliable turnkey services for fixed series compensation NR Electric Corporation The Fixed Series Compensation (FSC) solution is composed of NR's PCS-9570 FSC control and

More information

A Pyrotechnic Fault Current Limiter Model for Transient Calculations in Industrial Power Systems

A Pyrotechnic Fault Current Limiter Model for Transient Calculations in Industrial Power Systems A Pyrotechnic Fault Current Limiter Model for Transient Calculations in Industrial Power Systems T. C. Dias, B. D. Bonatto, J. M. C. Filho Abstract-- Isolated industrial power systems or with high selfgeneration,

More information

DC current interruption tests with HV mechanical DC circuit breaker

DC current interruption tests with HV mechanical DC circuit breaker http: //www.cigre.org CIGRÉ A3/B4-124 CIGRÉ Winnipeg 2017 Colloquium Study Committees A3, B4 & D1 Winnipeg, Canada September 30 October 6, 2017 DC current interruption tests with HV mechanical DC circuit

More information

Relevant Factors to a Statistical Analysis of Overvoltages - Application to Three-Phase Reclosing of Compensated Transmission Lines

Relevant Factors to a Statistical Analysis of Overvoltages - Application to Three-Phase Reclosing of Compensated Transmission Lines Energy and Power Engineering, 2013, 5, 1165-1171 doi:10.4236/epe.2013.54b221 Published Online July 2013 (http://www.scirp.org/journal/epe) Relevant Factors to a Statistical Analysis of Overvoltages - Application

More information

Analysis of Transient Recovery Voltage in Transmission Lines Compsensated with Tpcs-tcsc Considering Accurate Model of Transformer & Generator

Analysis of Transient Recovery Voltage in Transmission Lines Compsensated with Tpcs-tcsc Considering Accurate Model of Transformer & Generator Australian Journal of Basic and Applied Sciences, 5(5): 816-824, 2011 ISSN 1991-8178 Analysis of Transient Recovery Voltage in Transmission Lines Compsensated with Tpcs-tcsc Considering Accurate Model

More information

Neutral Reactor Optimization in order to Reduce Arc Extinction Time during Three-Phase Tripping

Neutral Reactor Optimization in order to Reduce Arc Extinction Time during Three-Phase Tripping Neutral Reactor Optimization in order to Reduce Arc Extinction Time during Three-Phase Tripping P. Mestas, M. C. Tavares Abstract. The optimization of the grounding neutral reactor is a common practice

More information

2. Current interruption transients

2. Current interruption transients 1 2. Current interruption transients For circuit breakers or other switching facilities, transient voltages just after the current interruptions are of great concern with successful current breakings,

More information

ANALYSIS OF FAULTS INTERRUPTED BY GENERATOR

ANALYSIS OF FAULTS INTERRUPTED BY GENERATOR ANALYSIS OF FAULTS INTERRUPTED BY GENERATOR CIRCUIT BREAKER SF 6 ING. VÁCLAV JEŽEK PROF. ING. ZDENĚK VOSTRACKÝ, DRSC., DR.H.C. Abstract: This article describes the analysis of faults interrupted by generator

More information

ONLINE MONITORING OF CONVERTER TRANSFORMERS OF SE IBIÚNA HVDC TRANSMISSION SYSTEM. E. G. PERES W. R. DUSO J. S. LATENEK Furnas Centrais Elétricas S.A.

ONLINE MONITORING OF CONVERTER TRANSFORMERS OF SE IBIÚNA HVDC TRANSMISSION SYSTEM. E. G. PERES W. R. DUSO J. S. LATENEK Furnas Centrais Elétricas S.A. 13 th CIGRÉ Ibero-America Regional Conference Puerto Iguazú, Argentina - 24 al 28 de Mayo de 2009 ONLINE MONITORING OF CONVERTER TRANSFORMERS OF SE IBIÚNA HVDC TRANSMISSION SYSTEM E. G. PERES W. R. DUSO

More information

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D Electricity Ten Year Statement November 2017 01 Electricity Ten Year Statement November 2017 001 Appendix D 1 Short-circuit currents 02 2 Short-circuit current terminology 04 3 Data requirements 07 4 Fault

More information

AORC Technical meeting 2014

AORC Technical meeting 2014 http : //www.cigre.org B4-112 AORC Technical meeting 214 HVDC Circuit Breakers for HVDC Grid Applications K. Tahata, S. Ka, S. Tokoyoda, K. Kamei, K. Kikuchi, D. Yoshida, Y. Kono, R. Yamamoto, H. Ito Mitsubishi

More information

Copyright 2008 IEEE.

Copyright 2008 IEEE. Copyright 2008 IEEE. Paper presented at IEEE PES 2008 T&D Chicago meeting, Apr. 21 24, 2008 This material is posted here with permission of the IEEE. Such permission of the IEEE does not in any way imply

More information

Adi Mulawarman, P.E Xcel Energy Minneapolis, MN. Pratap G. Mysore, P.E Pratap Consulting Services, LLC Plymouth, MN

Adi Mulawarman, P.E Xcel Energy Minneapolis, MN. Pratap G. Mysore, P.E Pratap Consulting Services, LLC Plymouth, MN Effectiveness of Surge Capacitors on Transformer Tertiary connected shunt reactors in preventing failures- Field measurements and comparison with Transient study results Pratap G. Mysore, P.E Pratap Consulting

More information

A TECHNICAL REVIEW ON CAPACITOR BANK SWITCHING WITH VACUUM CIRCUIT BREAKERS

A TECHNICAL REVIEW ON CAPACITOR BANK SWITCHING WITH VACUUM CIRCUIT BREAKERS A TECHNICAL REVIEW ON CAPACITOR BANK SWITCHING WITH VACUUM CIRCUIT BREAKERS Shashi Kumar 1, Brajesh Kumar Prajapati 2, Vikramjeet Singh 3 1, 2 Students, Electrical Engineering Department Greater Noida

More information

Electrical Transient Interaction between Transformers and Power System. Brazilian Experience

Electrical Transient Interaction between Transformers and Power System. Brazilian Experience Electrical Transient Interaction between Transformers and Power System Brazilian Experience Ulisses R. R. Massaro, Ricardo Antunes On behalf of Cigré-Brazil Joint Working Group JWG A2/C4-03 Electrical

More information

5. Black box arc modelling

5. Black box arc modelling 1 5. Black box arc modelling Circuit-breaker s performance in power system is analysed by representing the circuit-breaker characteristics by a function of electrical parameters such as current/voltage,

More information

THREE-PHASE SHORT-CIRCUIT TESTING OF HIGH-VOLTAGE CIRCUIT-BREAKERS USING SYNTHETIC CIRCUITS

THREE-PHASE SHORT-CIRCUIT TESTING OF HIGH-VOLTAGE CIRCUIT-BREAKERS USING SYNTHETIC CIRCUITS Denis DUFOURNET Head of CERDA High Power and High Voltage Laboratories in Villeurbanne, France. Georges MONTILLET Dead Tank Circuit Breakers Product Manager Development, Charleroi, PA USA. Charleston,

More information

Appendix D Fault Levels

Appendix D Fault Levels Appendix D Fault Levels Page 1 Electricity Ten Year Statement November 2013 D.1 Short Circuit Currents Short Circuit Currents Three phase to earth and single phase to earth short circuit current analyses

More information

Application of SVCs to Satisfy Reactive Power Needs of Power Systems

Application of SVCs to Satisfy Reactive Power Needs of Power Systems 1 Application of SVCs to Satisfy Reactive Power Needs of Power Systems H. K. Tyll, Senior Member, IEEE Abstract In the early days of power transmission problems like voltage deviation during load changes

More information

A Guide to the DC Decay of Fault Current and X/R Ratios

A Guide to the DC Decay of Fault Current and X/R Ratios A Guide to the DC Decay of Fault Current and X/R Ratios Introduction This guide presents a guide to the theory of DC decay of fault currents and X/R ratios and the calculation of these values in Ipsa.

More information

Solving Customer Power Quality Problems Due to Voltage Magnification

Solving Customer Power Quality Problems Due to Voltage Magnification PE-384-PWRD-0-11-1997 Solving Customer Power Quality Problems Due to Voltage Magnification R. A. Adams, Senior Member S. W. Middlekauff, Member Duke Power Company Charlotte, NC 28201 USA E. H. Camm, Member

More information

Transient Performance for a Series- Compensation in a High Voltage Transmission System

Transient Performance for a Series- Compensation in a High Voltage Transmission System 1 Transient Performance for a Series- Compensation in a High Voltage Transmission System Alfredo A. Cuello-Reyna, Daniel A. Rodríguez-Delgado, Student Member, IEEE, and Lionel Orama- Exclusa, Member, IEEE

More information

Methodology for MMIC Layout Design

Methodology for MMIC Layout Design 17 Methodology for MMIC Layout Design Fatima Salete Correra 1 and Eduardo Amato Tolezani 2, 1 Laboratório de Microeletrônica da USP, Av. Prof. Luciano Gualberto, tr. 3, n.158, CEP 05508-970, São Paulo,

More information

A Methodology for the Efficient Application of Controlled Switching to Current Interruption Cases in High-Voltage Networks

A Methodology for the Efficient Application of Controlled Switching to Current Interruption Cases in High-Voltage Networks A Methodology for the Efficient Application of Controlled Switching to Current Interruption Cases in High-Voltage Networks C. D. TSIREKIS Hellenic Transmission System Operator Kastoros 72, Piraeus GREECE

More information

Protection Scheme for Single-Phase Fault along a Half Wavelength Transmission Trunk Using Conventional Relay

Protection Scheme for Single-Phase Fault along a Half Wavelength Transmission Trunk Using Conventional Relay Protection Scheme for Single-Phase Fault along a Half Wavelength Transmission Trunk Using Conventional Relay Elson C. Gomes, Maria C. Tavares, Carlos A. Floriano Abstract This paper presents a proposal

More information

DIFFERENCE BETWEEN SWITCHING OF MOTORS & GENERATORS WITH VACUUM TECHNOLOGY

DIFFERENCE BETWEEN SWITCHING OF MOTORS & GENERATORS WITH VACUUM TECHNOLOGY DIFFERENCE BETWEEN SWITCHING OF MOTORS & GENERATORS WITH VACUUM TECHNOLOGY Dr. Karthik Reddy VENNA Hong URBANEK Nils ANGER Siemens AG Germany Siemens AG Germany Siemens AG Germany karthikreddy.venna@siemens.com

More information

G. KOEPPL Koeppl Power Experts Switzerland

G. KOEPPL Koeppl Power Experts Switzerland PS3: Substation Design: New Solutions and Experiences Bus-Node Substation A Big Improvement in Short-Circuit and Switching Properties at Reduced Substation Costs G. KOEPPL Koeppl Power Experts Switzerland

More information

Studies for the Integration of a TCSC in a Transmission System

Studies for the Integration of a TCSC in a Transmission System 2004 International Conference on Power System Technology - POWECON 2004 Singapore, 21-24 November 2004 Studies for the Integration of a TCSC in a Transmission System Lutz Kirschner, Gerhard. Thumm Abstract--

More information

P. Larivière, Hydro-Québec, D. Vinet, SNC-Lavalin Inc.

P. Larivière, Hydro-Québec, D. Vinet, SNC-Lavalin Inc. An evaluation of the short-circuit transient current on circuit breakers for the Hydro-Québec sub-transmission network in the presence of subsynchronous phenomenon of the 735 kv series compensated transmission

More information

Unit Auxiliary Transformer (UAT) Relay Loadability Report

Unit Auxiliary Transformer (UAT) Relay Loadability Report Background and Objective Reliability Standard, PRC 025 1 Generator Relay Loadability (standard), developed under NERC Project 2010 13.2 Phase 2 of Relay Loadability: Generation, was adopted by the NERC

More information

Adaptive Autoreclosure to Increase System Stability and Reduce Stress to Circuit Breakers

Adaptive Autoreclosure to Increase System Stability and Reduce Stress to Circuit Breakers Adaptive Autoreclosure to Increase System Stability and Reduce Stress to Circuit Breakers 70 th Annual Conference for Protective Relay Engineers Siemens AG 2017 All rights reserved. siemens.com/energy-management

More information

SHORT CIRCUIT ANALYSIS OF 220/132 KV SUBSTATION BY USING ETAP

SHORT CIRCUIT ANALYSIS OF 220/132 KV SUBSTATION BY USING ETAP SHORT CIRCUIT ANALYSIS OF 220/132 KV SUBSTATION BY USING ETAP Kiran V. Natkar 1, Naveen Kumar 2 1 Student, M.E., Electrical Power System, MSS CET/ Dr. B.A.M. University, (India) 2 Electrical Power System,

More information

Revision of TRV Requirements for the Application of Generator Circuit-Breakers

Revision of TRV Requirements for the Application of Generator Circuit-Breakers Revision of TRV Requirements for the Application of Generator Circuit-Breakers M. Palazzo, M. Popov, A. Marmolejo and M. Delfanti Abstract-- The requirements imposed on generator circuitbreakers greatly

More information

Delayed Current Zero Crossing Phenomena During Switching of Shunt-Compensated Lines

Delayed Current Zero Crossing Phenomena During Switching of Shunt-Compensated Lines Delayed Current Zero Crossing Phenomena During Switching of Shunt-Compensated Lines David K Olson Paul Nyombi Xcel Energy Pratap G Mysore Pratap Consulting Services Minnesota Power Systems Conference St.

More information

Transient Recovery Voltage Analysis on a Series Power Flow Control Device

Transient Recovery Voltage Analysis on a Series Power Flow Control Device Transient Recovery Voltage Analysis on a Series Power Flow Control Device L. V. Trevisan, G. Cappai, G. Álvarez Cordero Abstract-- In the frame of the Seventh Framework Program, TWENTIES project [1], it

More information

CHAPTER 4 POWER QUALITY AND VAR COMPENSATION IN DISTRIBUTION SYSTEMS

CHAPTER 4 POWER QUALITY AND VAR COMPENSATION IN DISTRIBUTION SYSTEMS 84 CHAPTER 4 POWER QUALITY AND VAR COMPENSATION IN DISTRIBUTION SYSTEMS 4.1 INTRODUCTION Now a days, the growth of digital economy implies a widespread use of electronic equipment not only in the industrial

More information

Modelling of Sf6 Circuit Breaker Arc Quenching Phenomena In Pscad

Modelling of Sf6 Circuit Breaker Arc Quenching Phenomena In Pscad Day 2 - Session IV-A High Voltage 163 Modelling of Sf6 Circuit Breaker Arc Quenching Phenomena In Pscad B. Kondala Rao, Gopal Gajjar ABB Ltd., Maneja, Vadodara, India Introduction Circuit breakers play

More information

Protection Scheme Half Wavelength Transmission Trunk Using Conventional Relay

Protection Scheme Half Wavelength Transmission Trunk Using Conventional Relay Energy and Power Engineering, 2013, 5, 1259-1265 doi:10.4236/epe.2013.54b239 Published Online July 2013 (http://www.scirp.org/journal/epe) Protection Scheme Half Wavelength Transmission Trunk Using Conventional

More information

StarSine Power Quality Products

StarSine Power Quality Products StarSine Power Quality Products Medium Voltage Static Voltage Regulator ( MV SVR ) MV SVR PROTECTS THE WHOLE FACILITY LOADS FROM VOLTAGE SAGS CAUSED BY UTILITY GRID FAULTS Voltage sags, whether due to

More information

Medium voltage circuit breaker technical guide

Medium voltage circuit breaker technical guide IEC 56-1987 - ANSI C37-06 1987 COMPARISON CONTENTS page 1 - Rated voltage 3 2 - Rated isolating level 3 3 - Rated voltage during normal running 4 4 - Allowable short time current 4 5 - Allowable current

More information

Effects of Transient Recovery Voltages on Circuit Breaker Ratings

Effects of Transient Recovery Voltages on Circuit Breaker Ratings Effects of Transient Recovery Voltages on Circuit Breaker Ratings Term Project: - EE22 - Power System Transients. Spring 28 Instructor: - Dr. Bruce Mork Team: - Himanshu Bahirat Muhammad Ali Praveen KK

More information

Sizing the neutral wire cross-section and minimization of neutral currents using microgeneration in low voltage networks

Sizing the neutral wire cross-section and minimization of neutral currents using microgeneration in low voltage networks Sizing the neutral wire cross-section and minimization of neutral currents using microgeneration in low voltage networks André Braga Instituto Superior Técnico Av. Rovisco Pais, 1049-001 Lisbon, Portugal

More information

When surge arres t ers are installed close to a power transformer, overvoltage TRANSFORMER IN GRID ABSTRACT KEYWORDS

When surge arres t ers are installed close to a power transformer, overvoltage TRANSFORMER IN GRID ABSTRACT KEYWORDS TRANSFORMER IN GRID When surge arres t ers are installed close to a power transformer, they provide protection against lightning overvoltage ABSTRACT The aim of this research article is to determine the

More information

Effects of Phase-Shifting Transformers, and Synchronous Condensers on Breaker Transient Recovery Voltages

Effects of Phase-Shifting Transformers, and Synchronous Condensers on Breaker Transient Recovery Voltages Effects of Phase-Shifting Transformers, and Synchronous Condensers on Breaker Transient Recovery Voltages Waruna Chandrasena, Bruno Bisewski, and Jeff Carrara Abstract-- This paper describes several system

More information

Improving High Voltage Power System Performance. Using Arc Suppression Coils

Improving High Voltage Power System Performance. Using Arc Suppression Coils Improving High Voltage Power System Performance Using Arc Suppression Coils by Robert Thomas Burgess B Com MIEAust CPEng RPEQ A Dissertation Submitted in Fulfilment of the Requirements for the degree of

More information

Autotransformer Inadvertent Energization Through Circuit Breakers Gradient Capacitors

Autotransformer Inadvertent Energization Through Circuit Breakers Gradient Capacitors Autotransformer Inadvertent Through Circuit Breakers Gradient Capacitors E. Martínez M., E. Godoy A., R. Ruelas T. Abstract- This paper discusses the commissioning experience with a 4/23/34.5 kv (primary/secondary/tertiary)

More information

Abstract. 1 Introduction

Abstract. 1 Introduction Energy Production and Management in the 21st Century, Vol. 1 345 Investigation of the electrical strength of a contact gap of the high voltage live tank circuit breaker 126 kv class using an intelligent

More information

Medium voltage products. Field Application Support Analysis and calculations in Medium-Voltage electrical networks

Medium voltage products. Field Application Support Analysis and calculations in Medium-Voltage electrical networks Medium voltage products Field Application Support Analysis and calculations in Medium-Voltage electrical networks Concept The electrical installation of an industrial site is a complex structure. Analyzing

More information

Power Conditioning Equipment for Improvement of Power Quality in Distribution Systems M. Weinhold R. Zurowski T. Mangold L. Voss

Power Conditioning Equipment for Improvement of Power Quality in Distribution Systems M. Weinhold R. Zurowski T. Mangold L. Voss Power Conditioning Equipment for Improvement of Power Quality in Distribution Systems M. Weinhold R. Zurowski T. Mangold L. Voss Siemens AG, EV NP3 P.O. Box 3220 91050 Erlangen, Germany e-mail: Michael.Weinhold@erls04.siemens.de

More information

Delayed Current Zero Crossing Phenomena during Switching of Shunt-Compensated Lines

Delayed Current Zero Crossing Phenomena during Switching of Shunt-Compensated Lines Delayed Current Zero Crossing Phenomena during Switching of Shunt-Compensated Lines David K Olson Xcel Energy Minneapolis, MN Paul Nyombi Xcel Energy Minneapolis, MN Pratap G Mysore Pratap Consulting Services,

More information

Projects and Applications of Synchrophasors in Brazil

Projects and Applications of Synchrophasors in Brazil International Conference in World-Wide Area Measurement Systems Projects and Applications of Synchrophasors in Brazil I.C. Decker D. Dotta A.S. e Silva M.N. Agostini A.L. Bettiol S.L. Zimath ARLAN LUIZ

More information

each time the Frequency is above 51Hz. Continuous operation is required

each time the Frequency is above 51Hz. Continuous operation is required GC0101 EXTRACT OF EUROPEAN CONNECTION CONDITIONS LEGAL TEXT DATED 08/01/2018. ECC.6 ECC.6.1 ECC.6.1.1 ECC.6.1.2 ECC.6.1.2.1 ECC.6.1.2.1.1 ECC.6.1.2.1.2 ECC.6.1.2.1.3 TECHNICAL, DESIGN AND OPERATIONAL CRITERIA

More information

MARCEL A. ARAÚJO, ROGÉRIO A. FLAUZINO, OURESTE E. BATISTA, LUCAS A. MORAES

MARCEL A. ARAÚJO, ROGÉRIO A. FLAUZINO, OURESTE E. BATISTA, LUCAS A. MORAES APPLYING A FUZZY SYSTEM FOR LIGHTNING LOCATION AND PROTECTION OF DISTRIBUTION SYSTEMS AGAINST OVERVOLTAGE BY SURGE ARRESTERS MARCEL A. ARAÚJO, ROGÉRIO A. FLAUZINO, OURESTE E. BATISTA, LUCAS A. MORAES LABORATÓRIO

More information

Switching Induced Transients:

Switching Induced Transients: Switching Induced Transients: Transformer switching is the most commonly performed operation in any power delivery system and most of the times this operation can be performed without any undesirable consequences.

More information

EVALUATION OF DIFFERENT SOLUTIONS OF FAULTED PHASE EARTHING TECHNIQUE FOR AN EARTH FAULT CURRENT LIMITATION

EVALUATION OF DIFFERENT SOLUTIONS OF FAULTED PHASE EARTHING TECHNIQUE FOR AN EARTH FAULT CURRENT LIMITATION EVALUATION OF DIFFERENT SOLUTIONS OF FAULTED PHASE EARTHING TECHNIQUE FOR AN EARTH FAULT CURRENT LIMITATION David TOPOLANEK Petr TOMAN Michal PTACEK Jaromir DVORAK Brno University of Technology - Czech

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements Division 502 Technical Applicability 1(1) Section 502.1 applies to: Expedited Filing Draft August 22, 2017 the legal owner of an aggregated generating facility directly connected to the transmission system

More information

Impact of Harmonic Resonance and V-THD in Sohar Industrial Port C Substation

Impact of Harmonic Resonance and V-THD in Sohar Industrial Port C Substation Impact of Harmonic Resonance and V-THD in Sohar Industrial Port C Substation R. S. Al Abri, M. H. Albadi, M. H. Al Abri, U. K. Al Rasbi, M. H. Al Hasni, S. M. Al Shidi Abstract This paper presents an analysis

More information

Methodology Utilized in Black-Start Studies on EHV Power Networks

Methodology Utilized in Black-Start Studies on EHV Power Networks Methodology Utilized in Black-Start Studies on EHV Power Networks C. Saldaña / G. Calzolari Av. Millán 4016 - Montevideo 11700 - Uruguay gracclau@adinet.com.uy Abstract - This article presents the methodology

More information

MODEL POWER SYSTEM TESTING GUIDE October 25, 2006

MODEL POWER SYSTEM TESTING GUIDE October 25, 2006 October 25, 2006 Document name Category MODEL POWER SYSTEM TESTING GUIDE ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy ( ) Guideline ( x ) Report or other ( ) Charter Document date

More information

GIS Disconnector Switching Operation VFTO Study

GIS Disconnector Switching Operation VFTO Study GIS Disconnector Switching Operation VFTO Study Mariusz Stosur, Marcin Szewczyk, Wojciech Piasecki, Marek Florkowski, Marek Fulczyk ABB Corporate Research Center in Krakow Starowislna 13A, 31-038 Krakow,

More information

SWITCHING OVERVOLTAGES IN A 400-KV CABLE SYSTEM

SWITCHING OVERVOLTAGES IN A 400-KV CABLE SYSTEM SWITCHING OVERVOLTAGES IN A 4-KV CABLE SYSTEM Mustafa Kizilcay University of Siegen Siegen, Germany kizilcay@uni-siegen.de Abstract This paper deals with the computation of switching overvoltages in a

More information

Shunt Reactor Switching

Shunt Reactor Switching Shunt Reactor Switching Dielectric stresses produced by circuit-breakers to shunt reactors. Presentation made during the IEEE Transformers Committee meeting, Amsterdam, Netherlands, April 2001 Presented

More information

Analysis and modeling of thyristor controlled series capacitor for the reduction of voltage sag Manisha Chadar

Analysis and modeling of thyristor controlled series capacitor for the reduction of voltage sag Manisha Chadar Analysis and modeling of thyristor controlled series capacitor for the reduction of voltage sag Manisha Chadar Electrical Engineering department, Jabalpur Engineering College Jabalpur, India Abstract:

More information

SURGES TRANSFERRED TO THE LOW-VOLTAGE NETWORK VIA TRANSFORMER THE INFLUENCE OF THE LOAD CONNECTED TO THE SECONDARY

SURGES TRANSFERRED TO THE LOW-VOLTAGE NETWORK VIA TRANSFORMER THE INFLUENCE OF THE LOAD CONNECTED TO THE SECONDARY GROUND and 3 rd WAE International Conference on Grounding and Earthing & 3 rd Brazilian Workshop on Atmospheric Electricity Rio de Janeiro - Brazil November -7, SURGES TRANSFERRED TO THE LOW-VOLTAGE NETWORK

More information

High-Power Testing of Circuit Breakers

High-Power Testing of Circuit Breakers High-Power Testing of Circuit Breakers Prof. Dr. Rene Smeets KEMA T&D Testing The Netherlands rene.smeets@kema.com IEEE Tutorial on Design and Application of High-Voltage Circuit Breakers July 2008 1 categories

More information

DEVELOPMENTS IN EHV/UHV CIRCUIT BREAKER TESTING

DEVELOPMENTS IN EHV/UHV CIRCUIT BREAKER TESTING DEVELOPMENTS IN EHV/HV CIRCIT BREAKER TESTING ABSTRACT R.P.P. Smeets, A.B. Hofstee, M. Dekker DNV GL, KEMA Laboratories trechtseweg 310, 6812 AR Arnhem, the Netherlands rene.smeets@dnvgl.com Nowadays,

More information

A First Approach on the Fault Impedance Impact on Voltage Sags Studies

A First Approach on the Fault Impedance Impact on Voltage Sags Studies International Conference on Renewable Energies and Power Quality (ICREPQ 15) La Coruña (Spain), 25 th to 27 th March, 215 Renewable Energy and Power Quality Journal (RE&PQJ) ISSN 2172-38 X, No.13, April

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements Applicability 1(1) Section 502.1 applies to the ISO, and subject to the provisions of subsections 1(2), (3) and (4) to any: (a) a new wind aggregated generating facility to be connected to the transmission

More information

EMC Philosophy applied to Design the Grounding Systems for Gas Insulation Switchgear (GIS) Indoor Substation

EMC Philosophy applied to Design the Grounding Systems for Gas Insulation Switchgear (GIS) Indoor Substation EMC Philosophy applied to Design the Grounding Systems for Gas Insulation Switchgear (GIS) Indoor Substation Marcos Telló Department of Electrical Engineering Pontifical Catholic University of Rio Grande

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

Testing 320 kv HVDC XLPE Cable System

Testing 320 kv HVDC XLPE Cable System Testing 320 kv HVDC XLPE Cable System H. He, W. Sloot DNV GL, KEMA Laboratories Arnhem, The Netherlands Abstract Two unique test requirements in testing of a high- voltage direct- current (HVDC) cable

More information

Protecting Harmonic Filters in a ±600 kv HVDC Installation

Protecting Harmonic Filters in a ±600 kv HVDC Installation Protecting Harmonic Filters in a ±600 kv HVDC Installation Eduardo Brandi Furnas Ricardo Abboud and Fernando Calero Schweitzer Engineering Laboratories, Inc. Presented at the 42nd Annual Western Protective

More information

Installation of PMU for Improving the Supervision of Interconnected Brazilian Transmission System (SIN)

Installation of PMU for Improving the Supervision of Interconnected Brazilian Transmission System (SIN) 1 Installation of PMU for Improving the Supervision of Interconnected Brazilian Transmission System (SIN) By Prof. Robson Pires robson.c.pires@gmail.com Federal University of Itajubá UNIFEI, MG BRAZIL

More information

Compact Systems for HVDC Applications Dr. Denis Imamovic

Compact Systems for HVDC Applications Dr. Denis Imamovic 13. Symposium Energieinnovation, 12. -14. February 2014, Graz Compact Systems for HVDC Applications Dr. Denis Imamovic Answers for energy. Agenda Main Drivers 3 Fault Clearing in HVDC Multi- Terminals

More information

Course ELEC Introduction to electric power and energy systems. Additional exercises with answers December reactive power compensation

Course ELEC Introduction to electric power and energy systems. Additional exercises with answers December reactive power compensation Course ELEC0014 - Introduction to electric power and energy systems Additional exercises with answers December 2017 Exercise A1 Consider the system represented in the figure below. The four transmission

More information

Analysis of Circuit Breaker Application Based on Transient Recovery Voltage Using Frequency Domain Techniques

Analysis of Circuit Breaker Application Based on Transient Recovery Voltage Using Frequency Domain Techniques Analysis of Circuit Breaker Application Based on Transient Recovery Voltage Using Frequency Domain Techniques D. Sinder, A. C. S. Lima, S. Carneiro Jr., A. C. Carvalho Abstract this paper addresses the

More information

Effect of Series Capacitor on Line Protection - A Case Study

Effect of Series Capacitor on Line Protection - A Case Study 112 NATIONAL POWER SYSTEMS CONFERENCE, NPSC 22 Effect of Series Capacitor on Line Protection - A Case Study Anand Mohan, Vikas Saxena, Mukesh Khanna & V.Thiagarajan Abstract: Series compensation is a time

More information

Lightning Performance of Transmission Lines with Tall Sections

Lightning Performance of Transmission Lines with Tall Sections Lightning Performance of Transmission Lines with Tall Sections A. J. G. Pinto, E. C. M. Costa, J. H. A. Monteiro, S. Kurokawa, J. Pissolato Abstract An analysis is proposed on the lightning performance

More information

Power Systems Modelling and Fault Analysis

Power Systems Modelling and Fault Analysis Power Systems Modelling and Fault Analysis Theory and Practice Nasser D. Tleis BSc, MSc, PhD, CEng, FIEE AMSTERDAM BOSTON HEIDELBERG LONDON NEW YORK OXFORD PARIS SAN DIEGO SAN FRANCISCO SINGAPORE SYDNEY

More information

Facilitating Bulk Wind Power Integration Using LCC HVDC

Facilitating Bulk Wind Power Integration Using LCC HVDC 21, rue d Artois, F-758 PARIS CIGRE US National Committee http : //www.cigre.org 213 Grid of the Future Symposium Facilitating Bulk Wind Power Integration Using LCC HVDC A. HERNANDEZ * R.MAJUMDER W. GALLI

More information

Assessment of Saturable Reactor Replacement Options

Assessment of Saturable Reactor Replacement Options Assessment of Saturable Reactor Replacement Options D.T.A Kho, K.S. Smith Abstract-- The performance of the dynamic reactive power compensation provided by the existing variable static compensation (STC)

More information

Great Northern Transmission Line: Behind the (Electrical) Design

Great Northern Transmission Line: Behind the (Electrical) Design Great Northern Transmission Line: Behind the (Electrical) Design November 8, 2017 Christian Winter, P.E. Minnesota Power Sivasis Panigrahi, P.E. POWER Engineers, Inc. What is the Great Northern Transmission

More information

HIGH VOLTAGE CIRCUIT BREAKERS

HIGH VOLTAGE CIRCUIT BREAKERS HIGH VOLTAGE CIRCUIT BREAKERS Design and Applications Second Edition, Revised and Expanded RUBEN D. GARZON Square D Co. Smyrna, Tennessee MARCEL Ш D E К К E R MARCEL DEKKER, INC. NEW YORK BASEL CONTENTS

More information

System grounding of wind farm medium voltage cable grids

System grounding of wind farm medium voltage cable grids Downloaded from orbit.dtu.dk on: Apr 23, 2018 System grounding of wind farm medium voltage cable grids Hansen, Peter; Østergaard, Jacob; Christiansen, Jan S. Published in: NWPC 2007 Publication date: 2007

More information

TRV OVERVIEW FOR REACTANCE LIMITED FAULTS

TRV OVERVIEW FOR REACTANCE LIMITED FAULTS The Electrical Power Engineers Qual-Tech Engineers, Inc. 201 Johnson Road Building #1 Suite 203 Houston, PA 15342-1300 Phone 724-873-9275 Fax 724-873-8910 www.qualtecheng.com TRV OVERVIEW FOR REACTANCE

More information

Control of Over-voltages on Hydro-Québec 735-kV Series-Compensated System During a Major Electro-mechanical Transient Disturbance.

Control of Over-voltages on Hydro-Québec 735-kV Series-Compensated System During a Major Electro-mechanical Transient Disturbance. Paper number: #014 Control of Over-voltages on Hydro-Québec 735-kV Series-Compensated System During a Major Electro-mechanical Transient Disturbance. Que Bui-Van Michel Rousseau Bui_Van.Que@hydro.qc.ca

More information

Coordination of surge arresters in DC 3 kv railway traction system field tests

Coordination of surge arresters in DC 3 kv railway traction system field tests Coordination of surge arresters in DC 3 kv railway traction system field tests Miroslaw Zielenkiewicz Tomasz Maksimowicz Center of Protection against Overvoltages and Electromagnetic Interferences RST

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

POWER SYSTEM TRANSIENTS - Switching Overvoltages in Power Systems - Juan A. Martinez-Velasco, Jacinto Martin-Arnedo

POWER SYSTEM TRANSIENTS - Switching Overvoltages in Power Systems - Juan A. Martinez-Velasco, Jacinto Martin-Arnedo SWITCHING OVERVOLTAGES IN POWER SYSTEMS Juan A. Martinez-Velasco Universitat Politècnica de Catalunya, Barcelona, Spain Jacinto Martin-Arnedo Estabanell Energía, Granollers, Spain Keywords: Switching overvoltages,

More information

GUIDE FOR APPLICATION OF IEC AND IEC

GUIDE FOR APPLICATION OF IEC AND IEC 305 GUIDE FOR APPLICATION OF IEC 67-00 AND IEC 67- PART MAKING AND BREAKING TESTS Working Group A3. October 006 GUIDE FOR APPLICATION OF IEC 67-00 AND IEC 67- PART MAKING AND BREAKING TESTS Working Group

More information

Condition Assessment of High Voltage Insulation in Power System Equipment. R.E. James and Q. Su. The Institution of Engineering and Technology

Condition Assessment of High Voltage Insulation in Power System Equipment. R.E. James and Q. Su. The Institution of Engineering and Technology Condition Assessment of High Voltage Insulation in Power System Equipment R.E. James and Q. Su The Institution of Engineering and Technology Contents Preface xi 1 Introduction 1 1.1 Interconnection of

More information

Table of Contents. Introduction... 1

Table of Contents. Introduction... 1 Table of Contents Introduction... 1 1 Connection Impact Assessment Initial Review... 2 1.1 Facility Design Overview... 2 1.1.1 Single Line Diagram ( SLD )... 2 1.1.2 Point of Disconnection - Safety...

More information

Effects of Braking Resistor on Circuit Breaker Operations

Effects of Braking Resistor on Circuit Breaker Operations Effects of Braking Resistor on Circuit Breaker Operations Allahverdi Azadrou Department of Electrical Engineering, Salmas Branch, Islamic Azad University, Salmas, Iran Azadrou.elec@gmail.com Abstract This

More information