G. KOEPPL Koeppl Power Experts Switzerland

Size: px
Start display at page:

Download "G. KOEPPL Koeppl Power Experts Switzerland"

Transcription

1 PS3: Substation Design: New Solutions and Experiences Bus-Node Substation A Big Improvement in Short-Circuit and Switching Properties at Reduced Substation Costs G. KOEPPL Koeppl Power Experts Switzerland SUMMARY The Bus-Node -concept (BN-concept) for air-insulated substations (AIS) is characterized by: Separated phase layout and HV-cables connecting the feeder bays to the overhead lines and to the transformers. It enables an extremely compact layout for AIS (about 1/3 of land compared to conventional AIS) resulting in a total cost reduction of 30% for a 245kV Double BN substation. The report at hand analyses the conditions regarding short-circuit currents, transient recovery voltage (TRV) and the disconnector bus-transfer switching in such BN-substations. The analysis is based on theoretical considerations and simulations. It shows that 3- and 2-phase fault currents are inexistent in BN-substations. Only single-phase faults may occur, however, at clearly smaller probability of occurrence. The cable capacitance at each feeder bay causes a time delay t d of 4 s in the TRV, compared to 2 s given in the IEC Standard. In sum the BN-concept is a substantial improvement in substation design. Keywords Air-insulated substations, Short-circuit current, Fault interruption, Transient recovery voltage, Bus transfer switching. Georg Koeppl, gskoeppl@bluewin.ch 1

2 1. INTRODUCTION A novel HV-substation concept, the so-called Bus-Node -concept (BN-concept) for air-insulated substations (AIS) was presented recently [1]. The characteristic features of this concept are: Separated phase layout, i.e. no crossings of conductors in the air-insulated area HV-cables connecting the feeder bays to the overhead lines and to the transformers Conventional HV-apparatus and components can be used. The BN-concept enables an extremely compact layout for AIS, i.e. about 1/3 of land area occupied compared to conventional AIS with long busbars. Considering also the substantial savings in conductor material, supporting structures, foundations and earthing grid, a total cost reduction of 30% has been calculated for a 245kV Double Bus-Node substation. Figure 1 shows one phase of a 245kV AIS, 8 feeder bays with double bus-node, Figure 2 a perspective view of the total double bus-node substation [1]. It goes without saying that bus-couplers (not shown in the figure) and even longitudinal bus-sectionalizers are feasible. Figure 1: One Phase of a Double Bus-Node AIS, 245kV, 8 Feeders 2

3 Figure 2: Double Bus-Node AIS, 245kV, 8 Feeders Three- and two-phase short-circuits are no longer possible in such a substation due to phase separation; single phase faults are possible but with a significantly reduced probability. These features and their consequences are dealt with in more detail in the paper at hand. 1. SHORT CIRCUIT CONDITIONS IN BUS-NODE SUBSTATIONS COMPARED TO CONVENTIONAL SUBSTATIONS 1.1 Two Distinct Zones Regarding Fault Consequences There are two areas in the layout of a substation, which determine the fault consequences: (1) The busbar area and the connections between busbar and circuit-breakers (CB) (2) The area between CBs and overhead lines or transformers, respectively Zone (1) is the utmost critical one: a fault there is a busbar fault; it necessarily causes interruption of all feeders connected to this busbar as well as substantial down-time of the substation; if 3- or 2-phase, it mostly leads to heavy damages. A fault in zone (2) is a feeder fault; the busbar is unaffected and only one feeder must be disconnected. Again 3- and 2-phase faults mostly cause substantial damage. The area beyond zone (2) contains the overhead lines and transformers. It is practically identical for the layout of a BN-AIS and a conventional AIS. 3

4 1.2 Short-Circuit Currents in Those Zones Zone (1): Obviously 2- and 3-phase short-circuits in zone (1) of a BN-substation cannot happen due to the separated phase layout. Only single phase faults are possible there but with a significantly reduced probability due to shorter conductor lengths. The length of the phase conductors possibly affected by a busbar fault is determined by the number of busbars, the busbar length and the distance from busbar to CB. In the 8-feeder double BN-AIS described in [1] (see also Figure 1 and 2) the sum of these conductor lengths is about 100m per phase. For the corresponding conventional double busbar AIS compared in [1] this number is 546m per phase. This ratio of 100/546 = is roughly valid also for AIS with other numbers of feeders. It seems to be realistic to assess the probability of a fault occurrence to be proportional to the conductor length (same insulation qualities and overvoltage stresses provided). That means in a Double BN-AIS the probability of a single-phase fault at the bus-bar is less than 20% of a conventional AIS. Here the BN-AIS exhibits a substantial technical advantage. Additionally in favour of the BN-AIS is the fact, that in such a substation there are no conductor crossings, another possible source of short-circuits. These conductor crossings in a conventional AIS are predominantly in the critical zone (1). Zone (2): Again 2- and 3-phase faults are inexistent in zone (2) of a BN-AIS, in contrast to a conventional AIS. The conductor length per phase is given by the number of feeders and the distance from CBs to the overhead lines and to the transformers respectively. These distances are approximately the same for BN-AIS (air-insulated feeder plus HV-cable) and for conventional AIS (air-insulated feeder plus air-insulated connection to overhead line). In this less critical zone (2) the advantage of the BN-AIS is absence of 2- and 3-phase faults and the reduced damage in case of a single phase fault, which might easily develop to a multi-phase fault in a conventional AIS. Short-circuit currents on the overhead lines or in the transformers are obviously not influenced by the substation design. 2. TRANSIENT RECOVERY VOLTAGES at CBs in BUS-NODE-AIS The short-circuit currents in all cases considered in paragraph 2 must be cleared by the CBs next to the fault. In the Bus-Node AIS, the corresponding transient recovery voltage (TRV) of the CB is very positively influenced by the cable sections connected to each feeder bay. This is valid for all fault cases. 2.1 Terminal Faults Since 2- and 3-phase faults are not possible in a BN-substation, only single phase faults must be considered. According to [2], Table 28 the corresponding peak value uc,sp of the TRV is 1.3 times smaller than for the first-phase-to-clear of a 3-phase fault. This is already a substantial alleviation in switching duty. The only conceivable 3-phase fault in a BN-AIS would be closing on a bolted fault which hopefully should be an extremely rare event in a HV-substation however. In this case the damage consequences are zero (no electric fault arc) and the fault is in the less critical zone (2). This extreme case was simulated for the first-phase-to-clear of a CB 245kV, 60Hz, with a rated short-circuit-breaking current of 50kA in a BN-AIS. The corresponding simulation scheme is given in Figure 3. 4

5 Current injector Feeder Bus Feeder Cable Overhead line Net equivalent 10m Z=260 Z=31.5 Z 1 =390 Z 0 =780 X 1 X 0 22m 37m 15km 6x CB B0 B1 Z=260 10m Figure 3: Simulation Scheme for a Bolted 3-Phase Fault 50kA in a Double Bus-Node AIS, 245kV, 8 Feeders The TRV corresponds to the voltage response to a current injector into the ungrounded CB terminal with a current steepness of π 60 A/s. Decisive is the correct modelling of the electrical components in the close electrical vicinity of the CB; this area determines the initial course of the TRV. The more distant components are responsible for the later course of the TRV; they have been chosen to represent the corresponding reference line of the specified TRV of the IEC Standards [2]. Since the considered 3-phase fault is bolted, i.e. rigidly grounded, the connected components on the grounded side may be disregarded (not shown in the scheme). The ungrounded terminal of the CB is connected to an air insulated feeder connection (CB to busbar) of 10m with a typical surge impedance of 260. The very short busbar (10m) is connected to 6 parallel air insulated feeders of 22m (busbar to cable termination) and further on to 6 parallel HV cables (Z = 35.1, l = 37m) of the BN-AIS. Then come 6 parallel overhead lines of 15km length. The components connected to these overhead lines provide a TRV shape which corresponds to the later course of the reference line of the specified TRV [2]. Figure 4 shows the voltage across the first pole-to-clear a short-circuit-breaking current of 50kA, 60Hz for the conditions described above and calculated by means of [3]. Figure 4a gives the total shape compared to the reference line according to [2]; rate of rise of recovery voltage (RRRV) equals to 2kV/ s and the peak value corresponds well to 364kV of the Standard. More interesting is the initial course of the TRV shown in Figure 4b. Reference line of specified TRV Reference line of specified TRV IEC Delay line of specified TRV, td = 2 s td 4 s Figure 4a: TRV First-Phase-to-Clear, Bolted Fault Figure 4b: TRV First-Phase-to-Clear, Initial Course The TRV in red is shaped by the number of (short) cables connected to the feeder bays and by the very compact substation layout with short conductor lengths between bus and cable sealing ends. There is 5

6 practically no initial transient recovery voltage (ITRV) and the delay time td is in the range of 4 s compared to 2 s given in the Standards. Simplified, this delay time is t d = Z C where Z is the resulting surge impedance of the overhead lines and C is the resulting capacitance of the HV-cables between bus-node and overhead lines. The voltage response to a linearly rising current injector di/dt = const. into a parallel Z and C is given by which depicts very well the initial course of the simulated TRV. The resulting surge impedance of overhead lines lies in a rather narrow range (370 to 450 per overhead line). Hence basically the cable lengths determine t d. In our practical case the average cable length is 37m; with C = F/km this yields F, resulting in t d = 3.9 to 4.7 s. With longer cable connections t d would rise. Since this combination of cable capacitance and surge impedance of OH line is valid for each feeder in a BN- AIS, this delay time is valid for any number of feeders and consequently for any magnitude of 100% short-circuit breaking current. It goes without saying that also interruption of single phase faults in a BN-AIS is characterized by this delay time and by the absence of any ITRV. Such an initial shape of the TRV which is inherent to a BN-AIS facilitates substantially the thermal mode of current interruption in a CB. 2.2 Short-Line Faults Even short-line faults near a BN-AIS are easier to be cleared due to the cable capacitance between feeder and overhead line, which is also shown by simulation. The model of Figure 3 is supplemented by a 3-phase cable section and a 3-phase overhead line showing a fault-to-ground in one phase (the overhead lines in the other 2 phases are on-going). The current to be interrupted is 37.5kA according to test duty L75 of [2], based on 50kA, 60Hz. The voltage responses on both CB terminals to ground and across the CB are given in Figure 5a and Figure 5b. TRV across CB TRV source side Reference line of specified TRV TRV across CB TRV source side td 4 s TRV line side Reference line of specified TRV TRV line side Figure 5a: TRV Short-Line Fault L75 Figure 5b: TRV Short-Line Fault L75, Initial Course The line side voltage of the CB terminal (in green) starts from the voltage u 0 (62.3kV) and goes in an oscillatory shape to zero. The shape is not saw-tooth like as in the classical short-line-fault but shows rounded peaks due to the cable capacitance at the beginning of the line. The corresponding time delay t d of 4 s is clearly visible in the initial course of Figure 5b. Also the source side voltage of the CB terminal (in red) exhibits the same time delay due to the effect described in paragraph 2.1. Of course 6

7 this is valid too for the difference of these voltages i.e. the voltage across the CB terminals (in blue). Again no ITRV is discernible on the voltages at both CB terminals. That means that a BN-AIS is synonymous with a tremendously easier CB duty also at short-line faults. 2.3 T60 to T10 Faults, OP1 OP2 Faults (IEC ) The favourable influence of the cable capacitances in a BN-AIS is effective in all fault- and fault switching cases. In [2] Table 26 the TRV requirements for faults with breaking currents less than the 100% rated breaking current (cases T60 to T10) are given. The TRV peaks in all those cases are generally higher than for the 100% case and rise with decreasing fault current. They are all referred to the first-pole-to-clear of a 3-phase fault and use a first-pole to-clear factor of 1.3. Due to the inexistence of 3- and 2-phase faults in a BN-AIS a phase factor of only 1.0 applies to all of such faults providing a substantial safety margin when clearing such faults. Cases T60 to T10 of [2] are characterized by RRRVs 2kV/ s, growing with decreasing current. The reason for this is the assumption that only a transformer or a combination of transformer and 1 or 2 overhead lines might feed the fault. The surge impedance of the transformer being about 5 to 10 times higher than that of an overhead line then is responsible for the higher RRRV. What was deduced in paragraph 2.1 and 2.2 regarding the time delay t d of about 4 s in a BN-AIS is also valid for any other fault case as long as the feeders are overhead lines. If the only feeder is a transformer however (as implied for case T10), then the corresponding surge impedance of a transformer determines the time delay t d = C Z. This is taken into consideration in [2] by higher time delays for T60 to T10 basing on 2 s for T100. If the base t d in a BN-AIS is 4 s however then the corresponding delay times for fault cases T60 to T10 are higher than given in [2] which results in an additional alleviation regarding breaking duty (the absence of ITRV is given here too). Out-of-phase breaking duties are covered by the test duties OP1 and OP2 of [2]. It should be mentioned that out-of-phase faults may be excluded if no generators are connected to the bus or if the generators are synchronized via generator CBs. This condition is fulfilled in many substations. Should out-of-phase switching occur in a BN-AIS, again the cable capacitances connected to the feeders guarantee a slow initial rise of the TRV across the CB. The corresponding time delays at both CB terminals may be easily deduced from the actual feeders affected by the out-of-phase conditions. 3. DISCONNECTORS AT BUS-TRANSFER CURRENT SWITCHING In [4] the duties of disconnectors at bus-transfer current switching are dealt with, i.e. opening and closing of disconnectors under load when this load is not interrupted, but transferred from one bus to a parallel bus. For AIS relatively long loop lengths are assumed in the Standard, e.g. typically 400m for rated voltages 245kV. From this the rated bus-transfer voltages at typical bus impedances are deduced resulting in 175Vrms for 245kV and a rated current of 2000A. It is obvious that the rated bustransfer voltages rise proportionally with the rated currents of the disconnectors. Since in a BN-AIS the disconnectors are immediately connected to the extremely short bus the corresponding loop length is drastically diminished to less than 15m for the 245kV substation described in [1] and shown in Figure 1 and 2. This allows to reduce the rated bus-transfer voltage from 175 Vrms to less than 10Vrms for a rated current of 2000A. The consequences of such a small bus-transfer voltage are: - no problems with bus-transfer current switching 7

8 - practically no wear and tear at the disconnector contacts due to arcing in a BN-AIS - no necessity for bus-transfer current switching tests. 4. CONCLUSIONS The technical properties of a novel and very economic HV-substation concept, the so-called Bus- Node -concept [1] for AIS have been analysed. The most striking quality of such a BN-AIS is the nonexistence of 2- and 3-phase faults (with heavy damages) due to phase separation. Only single phase faults are possible; the most critical zone however where a fault leads to a busbar fault, is in a BN-AIS about 5 times smaller than in a conventional AIS. A correspondingly reduced fault probability for single phase faults may be expected. A further substantial advantage is the easier TRV shape for all faults to be cleared by the CBs in a BN- AIS. The only possible single phase faults show TRV peaks by a factor 1.3 times smaller. The initial shape of the TRV is characterized by the cable capacitance between feeder bay and overhead line or transformer respectively which increases the delay time t d for the TRV rise from 2 s according to [2] to 4 s and more. These cable capacitances and the extremely compact substation layout are responsible for the very smooth rise of the TRV, i.e. there is no ITRV. This applies to all sort of faults, even to short-line faults. Also the delay times given in [2] for breaking currents smaller than the 100% breaking current (Test duties T60 to T10) may be doubled for a BN-AIS. These effects facilitate substantially the thermal mode of current interruption. Bus-transfer current switching is the duty of disconnectors in a multi-bus substation. Here too the BN- AIS offers a great improvement: the usual loop lengths of up to 400m in conventional AIS are reduced to about 15m in a BN-AIS resulting in rated bus-transfer voltages of less than 10V. This means practically no wear and tear at bus-transfer current switching. All these alleviations contribute to a significant increase in substation reliability and availability of a BN-AIS compared to a conventional AIS. BIBLIOGRAPHY [1] G. Koeppl, Th. Aschwanden, P. Zinniker, CIGRE Session 2016, Paris, Paper B3-208 [2] IEC : High-voltage switchgear and controlgear - Part 100: Alternating-current circuit-breakers [3] Alternative Transients Program (ATP), Rule Book, Canadian / American User Group [4] IEC Ed 2: High-voltage switchgear and controlgear - Part 102: Alternatingcurrent disconnectors and earthing switches 8

Revision of TRV Requirements for the Application of Generator Circuit-Breakers

Revision of TRV Requirements for the Application of Generator Circuit-Breakers Revision of TRV Requirements for the Application of Generator Circuit-Breakers M. Palazzo, M. Popov, A. Marmolejo and M. Delfanti Abstract-- The requirements imposed on generator circuitbreakers greatly

More information

ANALYSIS OF FAULTS INTERRUPTED BY GENERATOR

ANALYSIS OF FAULTS INTERRUPTED BY GENERATOR ANALYSIS OF FAULTS INTERRUPTED BY GENERATOR CIRCUIT BREAKER SF 6 ING. VÁCLAV JEŽEK PROF. ING. ZDENĚK VOSTRACKÝ, DRSC., DR.H.C. Abstract: This article describes the analysis of faults interrupted by generator

More information

Modelling of Sf6 Circuit Breaker Arc Quenching Phenomena In Pscad

Modelling of Sf6 Circuit Breaker Arc Quenching Phenomena In Pscad Day 2 - Session IV-A High Voltage 163 Modelling of Sf6 Circuit Breaker Arc Quenching Phenomena In Pscad B. Kondala Rao, Gopal Gajjar ABB Ltd., Maneja, Vadodara, India Introduction Circuit breakers play

More information

5. Black box arc modelling

5. Black box arc modelling 1 5. Black box arc modelling Circuit-breaker s performance in power system is analysed by representing the circuit-breaker characteristics by a function of electrical parameters such as current/voltage,

More information

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY 9. INTRODUCTION Control Cabling The protection and control equipment in power plants and substations is influenced by various of environmental conditions. One of the most significant environmental factor

More information

Tab 2 Voltage Stresses Switching Transients

Tab 2 Voltage Stresses Switching Transients Tab 2 Voltage Stresses Switching Transients Distribution System Engineering Course Unit 10 2017 Industry, Inc. All rights reserved. Transient Overvoltages Decay with time, usually within one or two cycles

More information

GIS Disconnector Switching Operation VFTO Study

GIS Disconnector Switching Operation VFTO Study GIS Disconnector Switching Operation VFTO Study Mariusz Stosur, Marcin Szewczyk, Wojciech Piasecki, Marek Florkowski, Marek Fulczyk ABB Corporate Research Center in Krakow Starowislna 13A, 31-038 Krakow,

More information

2. Current interruption transients

2. Current interruption transients 1 2. Current interruption transients For circuit breakers or other switching facilities, transient voltages just after the current interruptions are of great concern with successful current breakings,

More information

MODIFICATION OF THE ARRESTER ARRANGEMENT WHEN CONVERTING THE METHOD OF NEUTRAL TREATMENT

MODIFICATION OF THE ARRESTER ARRANGEMENT WHEN CONVERTING THE METHOD OF NEUTRAL TREATMENT MODIFICATION OF THE ARRESTER ARRANGEMENT WHEN CONVERTING THE METHOD OF NEUTRAL TREATMENT Claus NEUMANN Darmstadt University of Technology Germany claus.neumann@amprion.net Klaus WINTER Swedish Neutral

More information

Transient Recovery Voltage (TRV) and Rate of Rise of Recovery Voltage (RRRV) of Line Circuit Breakers in Over Compensated Transmission Lines

Transient Recovery Voltage (TRV) and Rate of Rise of Recovery Voltage (RRRV) of Line Circuit Breakers in Over Compensated Transmission Lines Transient Recovery Voltage (TRV) and Rate of Rise of Recovery Voltage (RRRV) of Line Circuit Breakers in Over Compensated Transmission Lines Presenter Mark McVey C4/B5.41 INTERNATIONAL COUNCIL ON LARGE

More information

Modeling insulation in high-voltage substations

Modeling insulation in high-voltage substations 38 ABB REVIEW DESIGNED FOR SAFETY DESIGNED FOR SAFETY Modeling insulation in high-voltage substations The goal of insulation coordination is to determine the dielectric strength of transformers and other

More information

GUIDE FOR APPLICATION OF IEC AND IEC

GUIDE FOR APPLICATION OF IEC AND IEC 305 GUIDE FOR APPLICATION OF IEC 67-00 AND IEC 67- PART MAKING AND BREAKING TESTS Working Group A3. October 006 GUIDE FOR APPLICATION OF IEC 67-00 AND IEC 67- PART MAKING AND BREAKING TESTS Working Group

More information

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D Electricity Ten Year Statement November 2017 01 Electricity Ten Year Statement November 2017 001 Appendix D 1 Short-circuit currents 02 2 Short-circuit current terminology 04 3 Data requirements 07 4 Fault

More information

ELECTRICAL POWER TRANSMISSION TRAINER

ELECTRICAL POWER TRANSMISSION TRAINER ELECTRICAL POWER TRANSMISSION TRAINER ELECTRICAL POWER TRANSMISSION TRAINER This training system has been designed to provide the students with a fully comprehensive knowledge in Electrical Power Engineering

More information

Appendix D Fault Levels

Appendix D Fault Levels Appendix D Fault Levels Page 1 Electricity Ten Year Statement November 2013 D.1 Short Circuit Currents Short Circuit Currents Three phase to earth and single phase to earth short circuit current analyses

More information

THREE-PHASE SHORT-CIRCUIT TESTING OF HIGH-VOLTAGE CIRCUIT-BREAKERS USING SYNTHETIC CIRCUITS

THREE-PHASE SHORT-CIRCUIT TESTING OF HIGH-VOLTAGE CIRCUIT-BREAKERS USING SYNTHETIC CIRCUITS Denis DUFOURNET Head of CERDA High Power and High Voltage Laboratories in Villeurbanne, France. Georges MONTILLET Dead Tank Circuit Breakers Product Manager Development, Charleroi, PA USA. Charleston,

More information

DIFFERENCE BETWEEN SWITCHING OF MOTORS & GENERATORS WITH VACUUM TECHNOLOGY

DIFFERENCE BETWEEN SWITCHING OF MOTORS & GENERATORS WITH VACUUM TECHNOLOGY DIFFERENCE BETWEEN SWITCHING OF MOTORS & GENERATORS WITH VACUUM TECHNOLOGY Dr. Karthik Reddy VENNA Hong URBANEK Nils ANGER Siemens AG Germany Siemens AG Germany Siemens AG Germany karthikreddy.venna@siemens.com

More information

MAJOR ADVANCES IN MV/LV SUBSTATIONS. Th.Grima et JF.Faltermeier. Groupe CAHORS, France SUMMARY

MAJOR ADVANCES IN MV/LV SUBSTATIONS. Th.Grima et JF.Faltermeier. Groupe CAHORS, France SUMMARY MJOR DVNCES IN MV/LV SUSTTIONS Th.Grima et JF.Faltermeier Groupe CHORS, France SUMMRY Improvements on the reliability of the components of the network, combined with a well-considered policy of cost reduction

More information

LIGHTNING OVERVOLTAGES AND THE QUALITY OF SUPPLY: A CASE STUDY OF A SUBSTATION

LIGHTNING OVERVOLTAGES AND THE QUALITY OF SUPPLY: A CASE STUDY OF A SUBSTATION LIGHTNING OVERVOLTAGES AND THE QUALITY OF SUPPLY: A CASE STUDY OF A SUBSTATION Andreas SUMPER sumper@citcea.upc.es Antoni SUDRIÀ sudria@citcea.upc.es Samuel GALCERAN galceran@citcea.upc.es Joan RULL rull@citcea.upc.es

More information

Power System Studies

Power System Studies Power System Studies Laois Ballyragget Cable Feasibility Study PE667-F4-R3-1-3 ESBI Engineering Solutions Stephen Court, 18/21 St Stephen s Green, Dublin 2, Ireland Telephone+353-1-73 8 Fax+353-1-661 66

More information

PREVENTING FLASHOVER NEAR A SUBSTATION BY INSTALLING LINE SURGE ARRESTERS

PREVENTING FLASHOVER NEAR A SUBSTATION BY INSTALLING LINE SURGE ARRESTERS 29 th International Conference on Lightning Protection 23 rd 26 th June 2008 Uppsala, Sweden PREVENTING FLASHOVER NEAR A SUBSTATION BY INSTALLING LINE SURGE ARRESTERS Ivo Uglešić Viktor Milardić Božidar

More information

ELECTRICAL POWER ENGINEERING

ELECTRICAL POWER ENGINEERING Introduction This trainer has been designed to provide students with a fully comprehensive knowledge in Electrical Power Engineering systems. The trainer is composed of a set of modules for the simulation

More information

DC current interruption tests with HV mechanical DC circuit breaker

DC current interruption tests with HV mechanical DC circuit breaker http: //www.cigre.org CIGRÉ A3/B4-124 CIGRÉ Winnipeg 2017 Colloquium Study Committees A3, B4 & D1 Winnipeg, Canada September 30 October 6, 2017 DC current interruption tests with HV mechanical DC circuit

More information

Weidong Zhang, May.9, 2016 Development of Pre-Insertion Resistor for an 800kV GIS Circuit Breaker. ABB Group May 11, 2016 Slide 1

Weidong Zhang, May.9, 2016 Development of Pre-Insertion Resistor for an 800kV GIS Circuit Breaker. ABB Group May 11, 2016 Slide 1 Weidong Zhang, May.9, 2016 Development of Pre-Insertion Resistor for an 800kV GIS Circuit Breaker Group Slide 1 Background & Objects EHV/UHV system: Widely application for long distance transmission from

More information

When surge arres t ers are installed close to a power transformer, overvoltage TRANSFORMER IN GRID ABSTRACT KEYWORDS

When surge arres t ers are installed close to a power transformer, overvoltage TRANSFORMER IN GRID ABSTRACT KEYWORDS TRANSFORMER IN GRID When surge arres t ers are installed close to a power transformer, they provide protection against lightning overvoltage ABSTRACT The aim of this research article is to determine the

More information

Calculation of Transient Overvoltages by using EMTP software in a 2-Phase 132KV GIS

Calculation of Transient Overvoltages by using EMTP software in a 2-Phase 132KV GIS Calculation of Transient Overvoltages by using EMTP software in a 2-Phase 132KV GIS M. Kondalu, Dr. P.S. Subramanyam Electrical & Electronics Engineering, JNT University. Hyderabad. Joginpally B.R. Engineering

More information

PRACTICAL PROBLEMS WITH SUBSTATION EARTHING

PRACTICAL PROBLEMS WITH SUBSTATION EARTHING 1 PRACTICAL PROBLEMS WITH SUBSTATION EARTHING Dr Hendri Geldenhuys Craig Clark Eskom Distribution Technology This paper considers the issues around substation sites where the soil resistivity is of particularly

More information

Earthing of Electrical Devices and Safety

Earthing of Electrical Devices and Safety Earthing of Electrical Devices and Safety JOŽE PIHLER Faculty of Electrical Engineering and Computer Sciences University of Maribor Smetanova 17, 2000 Maribor SLOVENIA joze.pihler@um.si Abstract: - This

More information

EDS FAULT LEVELS

EDS FAULT LEVELS Document Number: EDS 08-1110 Network(s): Summary: EPN, LPN, SPN ENGINEERING DESIGN STANDARD EDS 08-1110 FAULT LEVELS This standard provides guidance on the calculation, application and availability of

More information

Adi Mulawarman, P.E Xcel Energy Minneapolis, MN. Pratap G. Mysore, P.E Pratap Consulting Services, LLC Plymouth, MN

Adi Mulawarman, P.E Xcel Energy Minneapolis, MN. Pratap G. Mysore, P.E Pratap Consulting Services, LLC Plymouth, MN Effectiveness of Surge Capacitors on Transformer Tertiary connected shunt reactors in preventing failures- Field measurements and comparison with Transient study results Pratap G. Mysore, P.E Pratap Consulting

More information

2 Grounding of power supply system neutral

2 Grounding of power supply system neutral 2 Grounding of power supply system neutral 2.1 Introduction As we had seen in the previous chapter, grounding of supply system neutral fulfills two important functions. 1. It provides a reference for the

More information

Switching Induced Transients:

Switching Induced Transients: Switching Induced Transients: Transformer switching is the most commonly performed operation in any power delivery system and most of the times this operation can be performed without any undesirable consequences.

More information

EH27401 Communication and Control in Electric Power Systems Lecture 2. Lars Nordström

EH27401 Communication and Control in Electric Power Systems Lecture 2. Lars Nordström EH27401 Communication and Control in Electric Power Systems Lecture 2 Lars Nordström larsn@ics.kth.se 1 Course map 2 Outline 1. Power System Topologies Transmission Grids vs Distribution grids Radial grids

More information

EE 741. Primary & Secondary Distribution Systems

EE 741. Primary & Secondary Distribution Systems EE 741 Primary & Secondary Distribution Systems Radial-Type Primary Feeder Most common, simplest and lowest cost Example of Overhead Primary Feeder Layout Example of Underground Primary Feeder Layout Radial-Type

More information

This is a preview - click here to buy the full publication

This is a preview - click here to buy the full publication CONSOLIDATED VERSION IEC TR 62271-306 Edition 1.1 2018-08 colour inside High-voltage switchgear and controlgear Part 306: Guide to IEC 62271-100, IEC 62271-1 and other IEC standards related to alternating

More information

High voltage engineering

High voltage engineering High voltage engineering Overvoltages power frequency switching surges lightning surges Overvoltage protection earth wires spark gaps surge arresters Insulation coordination Overvoltages power frequency

More information

Effects of Transient Recovery Voltages on Circuit Breaker Ratings

Effects of Transient Recovery Voltages on Circuit Breaker Ratings Effects of Transient Recovery Voltages on Circuit Breaker Ratings Term Project: - EE22 - Power System Transients. Spring 28 Instructor: - Dr. Bruce Mork Team: - Himanshu Bahirat Muhammad Ali Praveen KK

More information

Session Four: Practical Insulation Co-ordination for Lightning Induced Overvoltages

Session Four: Practical Insulation Co-ordination for Lightning Induced Overvoltages Session Four: ractical Insulation Co-ordination Session Four: ractical Insulation Co-ordination for Lightning Induced Overvoltages Jason Mayer Technical Director, Energy Services, Aurecon Introduction

More information

Analysis of Electromagnetic Transients in Secondary Circuits due to Disconnector Switching in 400 kv Air-Insulated Substation

Analysis of Electromagnetic Transients in Secondary Circuits due to Disconnector Switching in 400 kv Air-Insulated Substation Analysis of Electromagnetic Transients in Secondary Circuits due to Switching in 400 k Air-Insulated Substation I. Uglešić, B. Filipović-Grčić,. Milardić, D. Filipović-Grčić Abstract-- The paper describes

More information

A short introduction to Protection and Automation Philosophy

A short introduction to Protection and Automation Philosophy Training Center A short introduction to Protection and Automation Philosophy Philippe Goossens & Cédric Moors Training Center Contents Definitions and basic concepts Differential and distance protection

More information

Numbering System for Protective Devices, Control and Indication Devices for Power Systems

Numbering System for Protective Devices, Control and Indication Devices for Power Systems Appendix C Numbering System for Protective Devices, Control and Indication Devices for Power Systems C.1 APPLICATION OF PROTECTIVE RELAYS, CONTROL AND ALARM DEVICES FOR POWER SYSTEM CIRCUITS The requirements

More information

A TECHNICAL REVIEW ON CAPACITOR BANK SWITCHING WITH VACUUM CIRCUIT BREAKERS

A TECHNICAL REVIEW ON CAPACITOR BANK SWITCHING WITH VACUUM CIRCUIT BREAKERS A TECHNICAL REVIEW ON CAPACITOR BANK SWITCHING WITH VACUUM CIRCUIT BREAKERS Shashi Kumar 1, Brajesh Kumar Prajapati 2, Vikramjeet Singh 3 1, 2 Students, Electrical Engineering Department Greater Noida

More information

Testing of 400 kv GIS

Testing of 400 kv GIS Testing of 400 kv GIS Robert le Roux, Dermot Dorgan, Brian Perry ESB International - Ireland Paper 028 1 Introduction The 400 kv transmission is designed for critical periods of low loading. Due to critical

More information

Transmission Line Transient Overvoltages (Travelling Waves on Power Systems)

Transmission Line Transient Overvoltages (Travelling Waves on Power Systems) Transmission Line Transient Overvoltages (Travelling Waves on Power Systems) The establishment of a potential difference between the conductors of an overhead transmission line is accompanied by the production

More information

University of Zagreb Faculty of Electrical Engineering and Computing

University of Zagreb Faculty of Electrical Engineering and Computing Journal of Energy VOLUME 64 2015 journal homepage: http://journalofenergy.com/ Viktor Milardić viktor.milardic@fer.hr Ivica Pavić ivica.pavic@fer.hr University of Zagreb Faculty of Electrical Engineering

More information

DEVELOPMENTS IN EHV/UHV CIRCUIT BREAKER TESTING

DEVELOPMENTS IN EHV/UHV CIRCUIT BREAKER TESTING DEVELOPMENTS IN EHV/HV CIRCIT BREAKER TESTING ABSTRACT R.P.P. Smeets, A.B. Hofstee, M. Dekker DNV GL, KEMA Laboratories trechtseweg 310, 6812 AR Arnhem, the Netherlands rene.smeets@dnvgl.com Nowadays,

More information

A Methodology for the Efficient Application of Controlled Switching to Current Interruption Cases in High-Voltage Networks

A Methodology for the Efficient Application of Controlled Switching to Current Interruption Cases in High-Voltage Networks A Methodology for the Efficient Application of Controlled Switching to Current Interruption Cases in High-Voltage Networks C. D. TSIREKIS Hellenic Transmission System Operator Kastoros 72, Piraeus GREECE

More information

Insulation Co-ordination For HVDC Station

Insulation Co-ordination For HVDC Station Insulation Co-ordination For HVDC Station Insulation Co-ordination Definitions As per IEC 60071 Insulation Coordination is defined as selection of dielectric strength of equipment in relation to the operating

More information

MV network design & devices selection EXERCISE BOOK

MV network design & devices selection EXERCISE BOOK MV network design & devices selection EXERCISE BOOK EXERCISES 01 - MV substation architectures 02 - MV substation architectures 03 - Industrial C13-200 MV substation 04 - Max. distance between surge arrester

More information

Single Line Diagram of Substations

Single Line Diagram of Substations Single Line Diagram of Substations Substations Electric power is produced at the power generating stations, which are generally located far away from the load centers. High voltage transmission lines are

More information

Dielectric, Switching and System Requirements under Out-of-Phase Conditions, during Synchronisation and under Comparable Stresses.

Dielectric, Switching and System Requirements under Out-of-Phase Conditions, during Synchronisation and under Comparable Stresses. Journal of Energy VOLUME 59 2010 journal homepage: http://journalofenergy.com/ Dielectric, Switching and System Requirements under Out-of-Phase Conditions, during Synchronisation and under Comparable Stresses.

More information

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System Company Directive STANDARD TECHNIQUE: SD7F/2 Determination of Short Circuit Duty for Switchgear on the WPD Distribution System Policy Summary This document provides guidance on calculation of fault levels

More information

Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017

Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017 Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017 NAME: LOCATION: 1. The primitive self-inductance per foot of length

More information

Earth Fault Protection

Earth Fault Protection Earth Fault Protection Course No: E03-038 Credit: 3 PDH Velimir Lackovic, Char. Eng. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800 F: (877) 322-4774

More information

Grounding System Theory and Practice

Grounding System Theory and Practice Grounding System Theory and Practice Course No. E-3046 Credit: 3 PDH Grounding System Theory and Practice Velimir Lackovic, Electrical Engineer System grounding has been used since electrical power systems

More information

Fault Current Limiter Selection Considerations for Utility Engineers

Fault Current Limiter Selection Considerations for Utility Engineers 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http: //www.cigre.org 2014 Grid of the Future Symposium Fault Current Limiter Selection Considerations for Utility Engineers K. TEKLETSADIK,

More information

Fast Protection of Strong Power System With Fault Current Limiters and PLL - Aided Fault Detection

Fast Protection of Strong Power System With Fault Current Limiters and PLL - Aided Fault Detection Fast Protection of Strong Power System With Fault Current Limiters and PLL - Aided Fault Detection Shaik Abdul Razak P.G. Scholar, Dept. of EEE Ch Durga Prasad P.G.Scholar, Dept. of EEE UDJV Prasad Associate

More information

Switching Restrikes in HVAC Cable Lines and Hybrid HVAC Cable/OHL Lines

Switching Restrikes in HVAC Cable Lines and Hybrid HVAC Cable/OHL Lines Switching Restrikes in HVAC Cable Lines and Hybrid HVAC Cable/OHL Lines F. Faria da Silva, Claus L. Bak, Per B. Holst Abstract--The disconnection of HV underground cables may, if unsuccessful, originate

More information

Ferroresonances during Black Starts - Criterion for Feasibility of Scenarios

Ferroresonances during Black Starts - Criterion for Feasibility of Scenarios Ferroresonances during Black Starts - Criterion for Feasibility of Scenarios Lubomir KOCIS EGU HV Laboratory, a.s. kocis@egu-vvn.cz Czech Republic Abstract --After large black-out events in the USA and

More information

How to maximize reliability using an alternative distribution system for critical loads

How to maximize reliability using an alternative distribution system for critical loads White Paper WP024001EN How to maximize reliability using an alternative distribution system for critical loads Executive summary The electric power industry has several different distribution topologies

More information

Simulation and Analysis of Lightning on 345-kV Arrester Platform Ground-Leading Line Models

Simulation and Analysis of Lightning on 345-kV Arrester Platform Ground-Leading Line Models International Journal of Electrical & Computer Sciences IJECS-IJENS Vol:15 No:03 39 Simulation and Analysis of Lightning on 345-kV Arrester Platform Ground-Leading Line Models Shen-Wen Hsiao, Shen-Jen

More information

Validation of a Power Transformer Model for Ferroresonance with System Tests on a 400 kv Circuit

Validation of a Power Transformer Model for Ferroresonance with System Tests on a 400 kv Circuit Validation of a Power Transformer Model for Ferroresonance with System Tests on a 4 kv Circuit Charalambos Charalambous 1, Z.D. Wang 1, Jie Li 1, Mark Osborne 2 and Paul Jarman 2 Abstract-- National Grid

More information

CONTENTS. 1. Introduction Generating Stations 9 40

CONTENTS. 1. Introduction Generating Stations 9 40 CONTENTS 1. Introduction 1 8 Importance of Electrical Energy Generation of Electrical Energy Sources of Energy Comparison of Energy Sources Units of Energy Relationship among Energy Units Efficiency Calorific

More information

Lightning test in lab. Symmetrical fault and protection. Olof Samuelsson

Lightning test in lab. Symmetrical fault and protection. Olof Samuelsson Lightning test in lab Symmetrical fault and protection Olof Samuelsson Outline Three-phase short-circuit fault current Network representation Circuit breakers and disconnectors Measurement transformers

More information

R10. IV B.Tech I Semester Regular/Supplementary Examinations, Nov/Dec SWITCH GEAR AND PROTECTION. (Electrical and Electronics Engineering)

R10. IV B.Tech I Semester Regular/Supplementary Examinations, Nov/Dec SWITCH GEAR AND PROTECTION. (Electrical and Electronics Engineering) R10 Set No. 1 Code No: R41023 1. a) Explain how arc is initiated and sustained in a circuit breaker when the CB controls separates. b) The following data refers to a 3-phase, 50 Hz generator: emf between

More information

AORC Technical meeting 2014

AORC Technical meeting 2014 http : //www.cigre.org B4-112 AORC Technical meeting 214 HVDC Circuit Breakers for HVDC Grid Applications K. Tahata, S. Ka, S. Tokoyoda, K. Kamei, K. Kikuchi, D. Yoshida, Y. Kono, R. Yamamoto, H. Ito Mitsubishi

More information

TRV OVERVIEW FOR REACTANCE LIMITED FAULTS

TRV OVERVIEW FOR REACTANCE LIMITED FAULTS The Electrical Power Engineers Qual-Tech Engineers, Inc. 201 Johnson Road Building #1 Suite 203 Houston, PA 15342-1300 Phone 724-873-9275 Fax 724-873-8910 www.qualtecheng.com TRV OVERVIEW FOR REACTANCE

More information

Protection of Electrical Networks. Christophe Prévé

Protection of Electrical Networks. Christophe Prévé Protection of Electrical Networks Christophe Prévé This Page Intentionally Left Blank Protection of Electrical Networks This Page Intentionally Left Blank Protection of Electrical Networks Christophe Prévé

More information

DC Chopper Based Test Circuit for High Voltage DC Circuit Breakers

DC Chopper Based Test Circuit for High Voltage DC Circuit Breakers DC Chopper Based Test Circuit for High Voltage DC Circuit Breakers D. Jovcic*, M.H. Hedayati *University of Aberdeen,UK, d.jovcic@abdn.ac.uk University of Aberdeen,UK, mhh@abdn.ac.uk Keywords: High Voltage

More information

A Study on Ferroresonance Mitigation Techniques for Power Transformer

A Study on Ferroresonance Mitigation Techniques for Power Transformer A Study on Ferroresonance Mitigation Techniques for Power Transformer S. I. Kim, B. C. Sung, S. N. Kim, Y. C. Choi, H. J. Kim Abstract--This paper presents a comprehensive study on the ferroresonance mitigation

More information

INTERNATIONAL STANDARD

INTERNATIONAL STANDARD INTERNATIONAL STANDARD IEC 62271-100 Edition 1.1 2003-05 Edition 1:2001 consolidated with amendment 1:2002 High-voltage switchgear and controlgear Part 100: High-voltage alternating-current circuit-breakers

More information

ABSTRACTS of SESSION 6

ABSTRACTS of SESSION 6 ABSTRACTS of SESSION 6 Paper n 1 Lightning protection of overhead 35 kv lines by antenna-module long flashover arresters Abstract: A long-flashover arrester (LFA) of a new antenna-module type is suggested

More information

IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 50, NO. 5, SEPTEMBER/OCTOBER

IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 50, NO. 5, SEPTEMBER/OCTOBER IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 50, NO. 5, SEPTEMBER/OCTOBER 2014 2989 Circuit Breaker Transient Recovery Voltage Requirements for Medium-Voltage Systems With NRG Rasheek Rifaat, Senior

More information

Fast Front Transients in Transformer Connected to Gas Insulated Substations: (White+Black) Box Models and TDSF Monitoring

Fast Front Transients in Transformer Connected to Gas Insulated Substations: (White+Black) Box Models and TDSF Monitoring Fast Front Transients in Transformer Connected to Gas Insulated Substations: (White+Black) Box Models and TDSF Monitoring Luis ROUCO 1, Xose M. LÓPEZ-FERNÁNDEZ 2, 3, Casimiro ALVAREZ-MARIÑO 3 and Hugo

More information

Effects of Phase-Shifting Transformers, and Synchronous Condensers on Breaker Transient Recovery Voltages

Effects of Phase-Shifting Transformers, and Synchronous Condensers on Breaker Transient Recovery Voltages Effects of Phase-Shifting Transformers, and Synchronous Condensers on Breaker Transient Recovery Voltages Waruna Chandrasena, Bruno Bisewski, and Jeff Carrara Abstract-- This paper describes several system

More information

Coordination of surge arresters in DC 3 kv railway traction system field tests

Coordination of surge arresters in DC 3 kv railway traction system field tests Coordination of surge arresters in DC 3 kv railway traction system field tests Miroslaw Zielenkiewicz Tomasz Maksimowicz Center of Protection against Overvoltages and Electromagnetic Interferences RST

More information

Hamdy Faramawy Senior Application Specialist ABB Sweden

Hamdy Faramawy Senior Application Specialist ABB Sweden Design, Engineering and Application of New Firm Capacity Control System (FCCS) Mohammed Y. Tageldin, MSc. MIET Senior Protection Systems Engineer ABB United Kingdom mohammed.tageldin@gb.abb.com Hamdy Faramawy

More information

RAIDK, RAIDG, RAPDK and RACIK Phase overcurrent and earth-fault protection assemblies based on single phase measuring elements

RAIDK, RAIDG, RAPDK and RACIK Phase overcurrent and earth-fault protection assemblies based on single phase measuring elements RAIDK, RAIDG, RAPDK and RACIK Phase overcurrent and earth-fault protection assemblies based on single phase measuring elements User s Guide General Most faults in power systems can be detected by applying

More information

VI 3 - i TABLE OF CONTENTS

VI 3 - i TABLE OF CONTENTS VI 3 - i TABLE OF CONTENTS 3 PROJECT SPECIFIC DATA... 1 3.1 DEFINITIONS... 1 3.1.1 Design Data, High and Medium Voltage... 1 3.1.2 Design Data, Low Voltage Equipment... 2 3.1.3 Phase Relationship... 3

More information

VFTO STUDIES DUO TO THE SWITCHING OPERATION IN GIS 132KV SUBSTATION AND EFFECTIVE FACTORS IN REDUCING THESE OVER VOLTAGES

VFTO STUDIES DUO TO THE SWITCHING OPERATION IN GIS 132KV SUBSTATION AND EFFECTIVE FACTORS IN REDUCING THESE OVER VOLTAGES VFTO STUDIES DUO TO THE SWITCHING OPERATION IN GIS 132KV SUBSTATION AND EFFECTIVE FACTORS IN REDUCING THESE OVER VOLTAGES Shohreh Monshizadeh Islamic Azad University South Tehran Branch (IAU), Tehran,

More information

GIS Instrument Transformers: EMC Conformity Tests for a Reliable Operation in an Upgraded Substation

GIS Instrument Transformers: EMC Conformity Tests for a Reliable Operation in an Upgraded Substation GIS Instrument Transformers: EMC Conformity Tests for a Reliable Operation in an Upgraded Substation W. Buesch 1) G. Palmieri M.Miesch J. Marmonier O. Chuniaud ALSTOM LTD 1) ALSTOM LTD High Voltage Equipment

More information

EVALUATION OF DIFFERENT SOLUTIONS OF FAULTED PHASE EARTHING TECHNIQUE FOR AN EARTH FAULT CURRENT LIMITATION

EVALUATION OF DIFFERENT SOLUTIONS OF FAULTED PHASE EARTHING TECHNIQUE FOR AN EARTH FAULT CURRENT LIMITATION EVALUATION OF DIFFERENT SOLUTIONS OF FAULTED PHASE EARTHING TECHNIQUE FOR AN EARTH FAULT CURRENT LIMITATION David TOPOLANEK Petr TOMAN Michal PTACEK Jaromir DVORAK Brno University of Technology - Czech

More information

Fatima Michael college of Engineering and Technology

Fatima Michael college of Engineering and Technology Fatima Michael college of Engineering and Technology DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING EE2303 TRANSMISSION AND DISTRIBUTION SEM: V Question bank UNIT I INTRODUCTION 1. What is the electric

More information

Modeling and Analysis of a 3-Phase 132kv Gas Insulated Substation

Modeling and Analysis of a 3-Phase 132kv Gas Insulated Substation Modeling and Analysis of a 3-Phase 132kv Gas Insulated Substation M. Kondalu1, Dr. P.S. Subramanyam2 Electrical & Electronics Engineering, JNT University. Hyderabad. Joginpally B.R. Engineering College,

More information

EE 1402 HIGH VOLTAGE ENGINEERING

EE 1402 HIGH VOLTAGE ENGINEERING EE 1402 HIGH VOLTAGE ENGINEERING Unit 5 TESTS OF INSULATORS Type Test To Check The Design Features Routine Test To Check The Quality Of The Individual Test Piece. High Voltage Tests Include (i) Power frequency

More information

Overvoltage Protection of Light Railway Transportation Systems

Overvoltage Protection of Light Railway Transportation Systems Overvoltage Protection of Light Railway Transportation Systems F. Delfino, R. Procopio, Student Member, IEEE, and M. Rossi, Student Member, IEEE Abstract In this paper the behavior of the power supply

More information

Transient Recovery Voltage Analysis on a Series Power Flow Control Device

Transient Recovery Voltage Analysis on a Series Power Flow Control Device Transient Recovery Voltage Analysis on a Series Power Flow Control Device L. V. Trevisan, G. Cappai, G. Álvarez Cordero Abstract-- In the frame of the Seventh Framework Program, TWENTIES project [1], it

More information

SYNCHRONISING AND VOLTAGE SELECTION

SYNCHRONISING AND VOLTAGE SELECTION SYNCHRONISING AND VOLTAGE SELECTION This document is for Relevant Electrical Standards document only. Disclaimer NGG and NGET or their agents, servants or contractors do not accept any liability for any

More information

TECHNICAL DESCRIPTION TD-77A/3 170 KV COMPACT GAS INSULATED INTEGRATED SUBSTATION MODULES

TECHNICAL DESCRIPTION TD-77A/3 170 KV COMPACT GAS INSULATED INTEGRATED SUBSTATION MODULES INDEPENDENT POWER TRANSMISSION OPERATOR S.A. TNPRD/ SUBSTATION SPECIFICATION & EQUIPMENT SECTION October 2014 TECHNICAL DESCRIPTION 170 KV COMPACT GAS INSULATED INTEGRATED SUBSTATION MODULES I. SCOPE This

More information

How OSHA s New Transient Overvoltage Requirements Affect Work Practices. B.A. YEUNG, H. BRANCO Leidos Engineering, LLC USA

How OSHA s New Transient Overvoltage Requirements Affect Work Practices. B.A. YEUNG, H. BRANCO Leidos Engineering, LLC USA 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium How OSHA s New Transient Overvoltage Requirements Affect Work Practices B.A. YEUNG,

More information

Transformers connected via a cable Overvoltage protection

Transformers connected via a cable Overvoltage protection A P P L I C AT I O N N OT E 2. 1 Transformers connected via a cable Overvoltage protection The APPLICATION NOTES (AN) are intended to be used in conjunction with the APPLICATION GUIDELINES Overvoltage

More information

Novel Simulation Method to Quantify Induced Voltage & Current between Parallel or Partially Parallel Proximity AC Transmission Circuits

Novel Simulation Method to Quantify Induced Voltage & Current between Parallel or Partially Parallel Proximity AC Transmission Circuits 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2015 Grid of the Future Symposium Novel Simulation Method to Quantify Induced Voltage & Current between Parallel or Partially

More information

TS RES - OUTSTANDING ISSUES

TS RES - OUTSTANDING ISSUES TS RES - OUTSTANDING ISSUES This document has been officially issued as DRAFT until the following outstanding issues have been resolved. At that time the document will be officially reissued as the next

More information

Medium voltage circuit breaker technical guide

Medium voltage circuit breaker technical guide IEC 56-1987 - ANSI C37-06 1987 COMPARISON CONTENTS page 1 - Rated voltage 3 2 - Rated isolating level 3 3 - Rated voltage during normal running 4 4 - Allowable short time current 4 5 - Allowable current

More information

Electrical Protection System Design and Operation

Electrical Protection System Design and Operation ELEC9713 Industrial and Commercial Power Systems Electrical Protection System Design and Operation 1. Function of Electrical Protection Systems The three primary aims of overcurrent electrical protection

More information

PERFORMANCE ANALYSIS OF SURGE CURRENT PROTECTION USING SUPERCONDUCTORS

PERFORMANCE ANALYSIS OF SURGE CURRENT PROTECTION USING SUPERCONDUCTORS PERFORMANCE ANALYSIS OF SURGE CURRENT PROTECTION USING SUPERCONDUCTORS Engr. Makinde K Department Of Electrical Engineering Federal Polytechnic Bida, Niger State Dr. Enemuoh F. O Department Of Electrical

More information

The Many Uses of Transmission Line Arresters

The Many Uses of Transmission Line Arresters Introduction It was not realized at the time, but the 1992 introduction of the polymer-housed transmission line arrester (TLA) was clearly a game changer in the practice of lightning protection of transmission

More information

A3-308 HIGH SPEED GROUNDING SWITCH FOR EXTRA-HIGH VOLTAGE LINES

A3-308 HIGH SPEED GROUNDING SWITCH FOR EXTRA-HIGH VOLTAGE LINES 21, rue d'artois, F-75008 Paris http://www.cigre.org A3-308 Session 2004 CIGRÉ HIGH SPEED GROUNDING SWITCH FOR EXTRA-HIGH VOLTAGE LINES G.E. Agafonov, I.V. Babkin, B.E. Berlin Y. F. Kaminsky, S. V. Tretiakov,

More information

SPTS 1 - Ratings and General Requirements for Plant, Equipment and Apparatus for The ScottishPower System and Connection Points to it.

SPTS 1 - Ratings and General Requirements for Plant, Equipment and Apparatus for The ScottishPower System and Connection Points to it. 1. SCOPE The requirements of this document apply to all Plant, Equipment and Apparatus that are part of, or are Directly connected to, the Company network. Requirements contained herein may be modified

More information

Unit 2. Single Line Diagram of Substations

Unit 2. Single Line Diagram of Substations Unit 2 Single Line Diagram of Substations Substations Electric power is produced at the power generating stations, which are generally located far away from the load centers. High voltage transmission

More information