1 International Journal of Mechanical Engineering and Technology (IJMET) Volume 10, Issue 02, February 2019, pp , Article ID: IJMET_10_02_042 Available online at ISSN Print: and ISSN Online: IAEME Publication Scopus Indexed SYNCHRONIZING ASSEMBLY LINE OPERATIONS IN COTTON GINNING INDUSTRIES TOWARDS REDUCED CYCLE TIME Dr. Ashok G. Matani Associate Professor -Mechanical Engineering Department, Government College of Engineering, Amravati- [M.S.] India Mohd. Sohail Ansari 2 nd Year M.Tech. Production, Government College of Engineering, Amravati [M.S.] Dr. S. K. Doifode HOD - Chemistry Department, Government College of Engineering, Amravati [M.S.] India ABSTRACT Problem-solving and ongoing procedure enhancements are key elements to obtaining quality improvement in business operations. Many process and machine improvement strategies have been suggested and implemented in organizations, where define, measure, analysis, improve and control is mostly applied. Here we aimed at improving the machine productivity of assembly line in a cotton ginning assembly line in an Industry. The tool which is used to improve the productivity of assembly line are time study and method study. Based on this, the study provides data of time required for each assembly processes, sequence of each operations and flow of the product in assembly line. The present study has been done at an industry, a leading manufacturer of cotton ginning machine. The aim of the study is to identify the various problems on the assembly line which causes unnecessary delay in the operations. The problem is found in the assembly line and is solved by work study techniques and it is found that cycle time of bottle neck operation was reduced by 33.05% per trolley Keywords: machine improvement strategies editor@iaeme.com
2 Synchronizing Assembly Line Operations in Cotton Ginning Industries Towards Reduced Cycle Time Cite this Article: Dr. Ashok G. Matani, Mohd. Sohail Ansari and Dr. S. K. Doifode, Synchronizing Assembly Line Operations in Cotton Ginning Industries Towards Reduced Cycle Time, International Journal of Mechanical Engineering and Technology, 10(2), 2019, pp INTRODUCTION 1.1. Productivity Improvement Productivity improvement means reduction in wastage of resources like men, time, material, capital etc. It is the human efforts to produce more profit in terms of less wastage of material, less time consumption in assembly of manufacturing with less inputs of resources provided so that the benefits will become maximum for the organization. Productivity improvement is the key to do the right thing better & improve it continuously. Therefore, it is important to adopt adequate or efficient productivity improvement technique to maximize the machine output with a less consumption of resources Work study Work study investigates the work done in acompany/organization and it aim to find the best andmost efficient way of using all the resources which areavailable i.e. material, man, machine, money etc.work study techniques involve a) Method study and b) Time study techniques Method Study Method study targets at finding the best way of doing thework. Method study involves systematic investigation(which involves recording and critical investigation) of thecurrent method of doing the job so that easy, fast, whichcauses less fatigue to the worker, safe, economical way ofdoing the work can be developed and installed at low cost.this is basically achieved by eliminating the unnecessarymotions which are involved in a procedure of doing thework and the same can also be achieved by changing thesequence of operations or process itself Time study Time study is a technique of work measurement used toestablish time for a qualified worker to carry out specifiedtask under specified conditions and at defined level ofperformance. 2. CASE STUDY The study has been done at an industry, a leading manufacturer of Cotton Ginning Machine. The aim of the study is to identify the various problems on the assembly line which causes unnecessary delay in the operations. The problem is found in the assembly line having six work stations where it is found that there are various operations creating bottle neck on the assembly line. It is desirable that 40 Cotton Ginning machine to be assembled on the assembly line but it is observed that 75% of cotton ginning machine are assembled a day. Thus the concern of this paper is to present the ideas which can beused by the industry to reduce its cycle time of theoperations in its assembly line to enhance theefficiency of the system editor@iaeme.com
3 Dr. Ashok G. Matani, Mohd. Sohail Ansari and Dr. S. K. Doifode 3. OBJECTIVE To identify the operations causing bottle neck in the assembly line. By using the method study technique, identify the problem work stations in the assembly line. Develop a method to solve the problem which is causing unnecessary delay in the assembly line. Conduct time study in the assembly line after implementation of the new method for trial period of 10 days. Suggest new method to the concern personnel in the organisation. 4. STUDIES AT INDUSTRY First step is to determine the operation sequence in each work stations on the assembly line. Observe and identify the cycle time for each operations on all work stations. It is found that sub assembly of the seed channel of the cotton ginning machine took around minutes and the time should be around 10.5 minutes for a trolley in a work station. The problem associated with present method is that the sub assembly of seed channel fitting or tightening of bolts and nuts on workstation 2 are done manually by spanners and cannot be tightened by the torque wrench due to the design constraint. Thus it is observed that due to this manual operation, the overall work station time of the workstation 2 is around minutes which is far greater than the other work stations and also the work station time of station 1 is the least around 3.4 minutes shown in the graph below. Now it is observed that by loose fitting of seed channels at the workstation 1 and manually tightening of the nut and bolts are done in the workstation 2 can decrease workstation time of station 2 to 9.32 minutes and simultaneously increases the workstation time of station 1 to 7.93 minutes i.e. total decrease in time of 4.6 minutes from station 2 and increase in the same on station 1. By implementing the new method, line efficiency of the assembly line increases editor@iaeme.com
4 Synchronizing Assembly Line Operations in Cotton Ginning Industries Towards Reduced Cycle Time Figure Assembly Line Layout of the industry Tables for the cycle time and Work Stations Time with sequence of operations before implementation of the new method. WORK STATION 1 1 Side Frame Cross bar fitting Rail fitting Total workstation time WORK STATION 2 1 Seed channel 1 fitting Seed channel 2 fitting Total workstation time WORK STATION 3 1 Back knife fitting Knife holder fitting Fix knife fitting Seed Guard Jumbo fitting Total workstation time editor@iaeme.com
5 Dr. Ashok G. Matani, Mohd. Sohail Ansari and Dr. S. K. Doifode WORK STATION 4 1 Ratchet fitting Side plate fitting Beater assembly fitting Total workstation time WORK STATION 5 1 Weight lever fitting Gear box fitting Total workstation time WORK STATION 6 1 Gear box plate cover fitting Tables for the cycle time and Work Stations Time with sequence of operations after implementation of the new method. WORK STATION 1 1 Side Frame Cross bar fitting Rail fitting Seed channel loose fitting Total workstation time WORK STATION 2 1 Seed channel 1 tightening Seed channel 2 tightening Total workstation time editor@iaeme.com
6 TIME (IN SECONDS) TIME (IN SECONDS) Synchronizing Assembly Line Operations in Cotton Ginning Industries Towards Reduced Cycle Time Three readings of all six work stations in assembly line before implemenation of new method w/s time (reading 1) w/s time (reading 2) w/s time (reading 3) W/S 1 W/S 2 W/S 3 W/S 4 W/S 5 W/S 6 w/s time (reading 1) w/s time (reading 2) w/s time (reading 3) WORK STATIONS (W/S) Three readings of all six work stations in assembly line after implemenation of new method w/s 1 (reading 1) w/s 2 (reading 2) w/s 3 (reading 3) w/s 1 w/s 2 w/s 3 w/s 4 w/s 5 w/s 6 w/s 1 (reading 1) w/s 2 (reading 2) w/s 3 (reading 3) WORKSTATIONS editor@iaeme.com
7 time (in seconds) Dr. Ashok G. Matani, Mohd. Sohail Ansari and Dr. S. K. Doifode Cycle time of each operations in the work stations and work station time are given above in the table. Thus by using the above table we can calculate line efficiency of the assembly line. Number of work stations = 6 Capacity of assembly line = 40 units per shift per day Total shift time = 480 minutes Unproductive time or worker allowances = 60 minutes Actual production time = Total shift time - Unproductive time or worker allowances = = 420 minutes. For full capacity, time required by one workstation for one trolley = Actual production time = Capacity of plant = 10.5 minutes Therefore, line efficiency before implementation of new method = Actual production time number of workstations largest workstation time 420 = = % Line efficiency after implementation of new method 420 = = % Thus by implementing line new method, line efficiency increases from 50.28% to 71.57%. 600 comparision of the workstation 1 before and after implementation of new method w/s 1 (reading 1) w/s 2 (reading 2) w/s 3 (reading 3) workstation 1 readings w/s time before improvement w/s time after improvement editor@iaeme.com
8 time (in seconds) Synchronizing Assembly Line Operations in Cotton Ginning Industries Towards Reduced Cycle Time comparision of the workstation 2 before and after implementation of new method w/s 1 (reading 1) w/s 1 (reading 2) w/s 1 (reading 3) workstation 2 readings w/s time before improvement w/s time after improvement editor@iaeme.com
9 Dr. Ashok G. Matani, Mohd. Sohail Ansari and Dr. S. K. Doifode It can be seen and compared from the above two graphs that the workstation time of workstation 1 is increased and workstation time of w/s 2 is decreased by changing the operation in the process sheetand thus reducing w/s time of the workstation CONCLUSIONS The results can be concluded that the time required to complete the sub assembly of seed channel in the work station -2 is reduced to 9.32 minutes from minutes. Percentage decrease in time by above study is = = % Thus the productivity of the assembly line of the cotton ginning machine is improved and the line efficiency are increased by the application of work study and change in operation in the process sheet. REFERENCES [1] Ashish Kalra, Sachin Marwah, Productivity improvement in assembly line of automobile industry by reducing cycle time of operations, International Journal of Engineering Research & Technology, 5(5): [2] Swapnil T. Firake, Dr. K. H. Inamdar, Productivity improvement of automotive assembly line through line balancing, International Journal of Technical Research and Applications, 2(3): [3] Cengiz Durana, Aysel Cetindereb, Yunus Emre Aksuc, Productivity improvement by work and time study technique for earth energy-glass manufacturing company, 4 th World Conference on Business, Economics and Management, WCBEM, Science Direct, Procedia Economics and Finance 26(2015),pp editor@iaeme.com
10 Synchronizing Assembly Line Operations in Cotton Ginning Industries Towards Reduced Cycle Time [4] Mayourshikha Pancholi (Bhatnagar), Productivity improvement in chassis assembly line of automative industry by using work study methods, International Journal of Engineering Sciences & Research Technology, pp [5] Shamuvel V.Pandit, Sunil J Kadam, Avinash Kharat, Chetan U Nayakawade, Productivity improvement by application of line balancing, International Journal of Innovative Research in Science, Engineering and Technology, 3(4): [6] Nikhil Verma, Pulkit Trivedi, Vivek Agnihotri, Productivity Improvement in assembly line of an automobile industry, IOSR Journal of Mechanical and Civil Engineering (IOSR- JMCE), 12(4): [7] Dr. A. G. Matani, (2006), Improving water use efficiency by effective water conservation techniques, Indian Journal of Environmental Protection, 26(3): [8] Dr. A.G. Matani, S. K. Doifode, (2015), Effective industrial waste utilization technologies towards cleaner environment, International Journal of Chemical and Physical Sciences, 491(1): [9] Dr. A.G. Matani,(2006), Strategies for better waste management in industrial estates, Journal of Industrial Pollution Control, 22(1): [10] Dr. S. K. Doifode Dr. A. G. Matani (2015), Advanced environment protection techniques by industries: potential for corporate social responsibility activities, Journal of The International Association of Advanced Technology and Science, 15(3):1-8 [11] P Saurabh Jha and Mohd Salman Khan. An Experimental Study on the Automotive Production Line Using Assembly Line Balancing Techniques. International Journal of Mechanical Engineering and Technology, 8(3), 2017, pp [12] Madasamy alias PrabuNivas.C, Venkatesh. J and Kannan. K, Implementation of Special Product & Process Characteristic (Sppc) in A Clutch Cover Assembly Line, International Journal of Mechanical Engineering and Technology, 9(11), 2018, pp [13] S.K. Gupta, Dr. V.K. Mahna, Dr. R.V. Singh and Rajender Kumar, Mixed Model Assembly Line Balancing: Strategic Tool to Improve Line Efficiency in Real World, International Journal of Industrial Engineering Research and Development (IJIERD), Volume 3, Issue 1, January- June (2012), pp [14] K. Parthiban, M. Kumaresan, M. Shantharaj and N.M. Vijay Aravindhan, Reducing the Run out Defect in Cover Assembly Line of Clutch Plate, International Journal of Mechanical Engineering and Technology, 9(11), 2018, pp editor@iaeme.com
DESIGN AND FABRICATION OF DRILL JIG FOR THE COMPONENT ''AILERON LEVER FRAME 6 UPPER'' FOR ''HAWK MK-132'' AN ADVANCED JET TRAINER
International Journal of Mechanical Engineering and Technology (IJMET) Volume 8, Issue 4, April 2017, pp. 372 379, Article ID: IJMET_08_04_039 Available online at http://www.iaeme.com/ijmet/issues.asp?jtype=ijmet&vtype=8&itype=4
More informationPRODUCTIVITY IMPROVEMENT OF A PRESTRESS CONCRETE POLE PLANT USING WORK STUDY TECHNIQUE
PRODUCTIVITY IMPROVEMENT OF A PRESTRESS CONCRETE POLE PLANT USING WORK STUDY TECHNIQUE Rupesh.S. Raut 1, H.M.Deshmukh 2 1 M.E. Student, Production Technology and Management Department, Prof. Ram Meghe
More informationIncreasing in Productivity by Using Work Study in a Manufacturing Industry
Increasing in Productivity by Using Work Study in a Manufacturing Industry Shantideo Gujar 1, Dr. Achal S. Shahare 2 1Student, Department of Mechanical Engineering, G. H. Raisoni Academy of Engineering
More informationSTUDY OF PERFORMANCE OF BITUMINOUS CONCRETE WITH ADDITION OF COIR/COCONUT FIBER
International Journal of Mechanical Engineering and Technology (IJMET) Volume 8, Issue 7, July 2017, pp. 1793 1799, Article ID: IJMET_08_07_198 Available online at http://www.iaeme.com/ijmet/issues.asp?jtype=ijmet&vtype=8&itype=7
More informationDIAGNOSIS OF GEARBOX FAULT USING ACOUSTIC SIGNAL
International Journal of Mechanical Engineering and Technology (IJMET) Volume 9, Issue 4, April 2018, pp. 258 266, Article ID: IJMET_09_04_030 Available online at http://www.iaeme.com/ijmet/issues.asp?jtype=ijmet&vtype=9&itype=4
More informationImplementation of Improved Jigs and Fixtures in the Production of Non-Active Rotary Paddy Weeder
DOI: http://dx.doi.org/10.4314/star.v3i4.22 ISSN: 2226-7522(Print) and 2305-3372 (Online) Science, Technology and Arts Research Journal Sci. Technol. Arts Res. J., Oct-Dec 2014, 3(4): 152-157 Journal Homepage:
More informationREDUCING THE REJECTION RATE OF PISTONS DURING MACHINING
International Journal of Mechanical Engineering and Technology (IJMET) Volume 8, Issue 9, September 207, pp. 237 243, Article ID: IJMET_08_09_024 Available online at http://www.iaeme.com/ijmet/issues.asp?jtype=ijmet&vtype=8&itype=9
More informationA Novel Approach for Disc Shaped Sheet Metal Cutting by Semi Automated Rig
International Journal of ChemTech Research CODEN (USA): IJCRGG, ISSN: 0974-4290, ISSN(Online):2455-9555 Vol.10 No.14, pp 101-105, 2017 A Novel Approach for Disc Shaped Sheet Metal Cutting by Semi Automated
More informationDESIGN IMPLEMENTATION AND ANALYSIS OF AUTOMATIC BURR REMOVAL IN A FIXTURE TOOL
International Journal of Mechanical Engineering and Technology (IJMET) Volume 9, Issue 11, November2018, pp. 1089 1098, Article ID: IJMET_09_11_112 Available online at http://www.iaeme.com/ijmet/issues.asp?jtype=ijmet&vtype=9&itype=11
More informationNumerical Optimization of Grey C.I. Casting using Simulation
IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-issn: 2278-1684,p-ISSN: 2320-334X PP. 47-51 www.iosrjournals.org Numerical Optimization of Grey C.I. Casting using Simulation M. N. Jadhav,
More information3000 SERIES STEPGUARD
3000 SERIES STEPGUARD GRILLE GUARD ASSEMBLY INSTRUCTIONS PART NO. 3295B & 3295C 2015 FORD F-150 Do not attempt to install this product on any vehicle other than the one it is designed for and listed above!
More informationAUTOMATION OF LATHE USING PNEUMATIC ACTUATORS
International Journal of Mechanical Engineering and Technology (IJMET) Volume 8, Issue 3, March 2017, pp. 419 425 Article ID: IJMET_08_03_046 Available online at http://www.iaeme.com/ijmet/issues.asp?jtype=ijmet&vtype=8&itype=3
More informationDEVELOPMENT OF AN EXPERT SYSTEM FOR CONDITION MONITORING OF SUBMARINES USING IR THERMOGRAPHY
International Journal of Mechanical Engineering and Technology (IJMET) Volume 8, Issue 4, April 2017, pp. 26 33 Article ID: IJMET_08_04_004 Available online at http://www.iaeme.com/ijmet/issues.asp?jtype=ijmet&vtype=8&itype=4
More informationBIBECHANA. Implementation of designed jigs and fixtures for hand operated press in production of mainframe for paddy-weeder
Publisher: Research Council of Science and Technology, Biratnagar, Nepal p. 104 O BIBECHANA C R N S T A Multidisciplinary Journal of Science, Technology and Mathematics ISSN 2091-0762 (print), 2382-5340
More informationEXPLORATION ON POWER DELAY PRODUCT OF VARIOUS VLSI MULTIPLIER ARCHITECTURES
International Journal of Mechanical Engineering and Technology (IJMET) Volume 9, Issue 1, January 2018, pp. 53 59, Article ID: IJMET_09_01_006 Available online at http://www.iaeme.com/ijmet/issues.asp?jtype=ijmet&vtype=9&itype=1
More informationTAILSTOCK SEMI - AUTOMATION FOR HEAVY DUTY LATHE MACHINE
ISSN 395-161 TAILSTOCK SEMI - AUTOMATION FOR HEAVY DUTY LATHE MACHINE #1 P.R.RAUT, # S.D.SHINDE, #3 V.U.SUBHEDAR, # P.G.SULE, #5 Dr.V.A.PHARANDE, #6 Asst.Prof.Gholap P.C. #13 Student Dept. of mechanical
More information121PB - PRO UNEVEN BARS
Sales & Service sasportonline.com Head Office 135 Forestview Road P.O. Box 40 Orillia, Ontario Canada L3V 6H9 Toll Free (800) 563-6479 Phone (705) 325-2274 Fax (705) 325-1485 USA Office 7879 Will Rogers
More informationI. INTRODUCTION II. BUSINESS OBJECTIVES. A. To optimize cylinder block cell that has maximum rejection records in the plant.
ISSN: 2321-7782 (Online) Impact Factor: 6.047 Volume 4, Issue 10, October 2016 International Journal of Advance Research in Computer Science and Management Studies Research Article / Survey Paper / Case
More informationIncrease in productivity by attachment of grinding setup On lathe machine
Increase in productivity by attachment of grinding setup On lathe machine Prof.Aslam Hirani 1,Shohin Naik 2,Toufik Pathan 3,Vaibhav Patil 4, Swarupanand Lugade 5 1,2,3,4,5 Mechanical Engineering, Mumbai
More informationTANGENTIAL STRESS FACTOR COMPUTATION IN POINT MOUNTED STRUCTURAL GLASS
International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 8, August 2017, pp. 833 840, Article ID: IJCIET_08_08_086 Available online at http://http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=8&itype=8
More informationINTERNATIONAL JOURNAL OF MECHANICAL ENGINEERING AND TECHNOLOGY (IJMET)
INTERNATIONAL JOURNAL OF MECHANICAL ENGINEERING AND TECHNOLOGY (IJMET) International Journal of Mechanical Engineering and Technology (IJMET), ISSN 0976 6340(Print), ISSN 0976 6340 (Print) ISSN 0976 6359
More informationCONTROL METHOD FOR LCC CURRENT OUTPUT RESONANT CONVERTER
International Journal of Electrical Engineering & Technology (IJEET) Volume 8, Issue 2, March- April 2017, pp. 101 107, Article ID: IJEET_08_02_012 Available online at http://www.iaeme.com/ijeet/issues.asp?jtype=ijeet&vtype=8&itype=1
More informationTHE ROLE OF TECHNOLOGY MANAGEMENT ON INNOVATION SUCCESS AND PERFORMANCE OF ORGANIZATION- EMPIRICAL STUDY
International Journal of Civil Engineering and Technology (IJCIET) Volume 9, Issue 13, December 2018, pp. 819-826, Article ID: IJCIET_09_13_080 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=9&itype=13
More informationIJMEIT// Vol.04 Issue 03//March//Page No: //ISSN x 2016
Rapid Entire Body and Rapid Upper Limb Assessment of Operator for Multipurpose Wheel Lathe Machine Authors P. A. Ingale 1, Prof. P. V. Salunke 2 1 Department of Mechanical Engineering, Walchand Institute
More informationIJRASET: All Rights are Reserved. UG Scholars, Department of Mechanical Engineering, SNS College of engineering, Coimbatore
Fixture for bundle cutting of tubes and rods in saw cutting machine Mr.R.Pradeep Kumar 1, U.Rupesh Kiran 2, R. Sanjhay 3, G.Subramanian 4, R.Vijayakumar 5 1 Assistant Professor, Department of Mechanical
More informationIMPROVEMENT OF YAGI UDA ANTENNA RADIATION PATTERN
International Journal of Mechanical Engineering and Technology (IJMET) Volume 8, Issue 7, July 2017, pp. 636 641, Article ID: IJMET_08_07_071 Available online at http://www.iaeme.com/ijmet/issues.asp?jtype=ijmet&vtype=8&itype=7
More informationIDR assembly instructions:
IDR assembly instructions: Required Tools: 2 X 12mm Open End Wrench 14mm open end wrench #2 Phillips Head Screw Driver (Drill with adjustable torque clutch recommended) 8mm nut driver (Supplied in IDR-AK)
More informationPERFECT AND STATUS IN SINGLE VALUED NEUTROSOPHIC GRAPHS
International Journal of Mechanical Engineering and Technology (IJMET) Volume 9, Issue 1, January 2018, pp 1124 1132, Article ID: IJMET_09_01_120 Available online at http://wwwiaemecom/ijmet/issuesasp?jtype=ijmet&vtype=9&itype=1
More informationIMPROVEMENT OF SHEAR STRENGTH OF SOIL USING BITUMEN EMULSION
International Journal of Civil Engineering and Technology (IJCIET) Volume 7, Issue 6, November-December 216, pp. 156 165, Article ID: IJCIET_7_6_17 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=7&itype=6
More informationReal Time Monitoring of SF6 Gas Pressure for Optimization Point on Wave Switching of SF6 Circuit Breaker
Real Time Monitoring of SF6 Gas Pressure for Optimization Point on Wave Switching of SF6 Circuit Breaker Ashish Maheshwari 1, Sunil Kumar Singla 2 1 PG Scholar, EIE Department, Thapar University Patiala,
More informationFabrication & Testing of composite tractor trolley chassis Mr. Ashish Azade 1 Mr.Tushar B.Shinde 2
Fabrication & Testing of composite tractor trolley chassis Mr. Ashish Azade 1 Mr.Tushar B.Shinde 2 1 PG Scholar, Department of Mechanical Engineering, Sahyadri Valley College of Engineering and Technology,
More informationLabour Productivity of Precast Construction in Housing Projects
e-issn 2455 1392 Volume 2 Issue 2, February 2016 pp. 101-106 Scientific Journal Impact Factor : 3.468 http://www.ijcter.com Labour Productivity of Precast Construction in Housing Projects Pratik Vaid,
More informationIMPROVING SAFETY PERFORMANCE IN CONSTRUCTION INDUSTRY
International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 8, August 2017, pp. 1515 1520, Article ID: IJCIET_08_08_165 Available online at http://http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=8&itype=8
More informationCTTR Tire Rack Required tools
CTTR Tire Rack Required tools Torque wrench, ratchet, 9/16 socket, tape measure, and square edge. ASSEMBLY REQUIREMENTS *Torque all T-bolt nuts to 35-40 foot pounds. Failure to follow the assembly instructions
More informationAssistant Professor, Department of Mechanical Engineering, Institute of Engineering & Technology, DAVV University, Indore, Madhya Pradesh, India
IJESRT INTERNATIONAL JOURNAL OF ENGINEERING SCIENCES & RESEARCH TECHNOLOGY Analysis of Spur Gear Faults using Frequency Domain Technique Rishi Kumar Sharma 1, Mr. Vijay Kumar Karma 2 1 Student, Department
More information4Post and 2Post Rails for Dell PowerEdge R810
4Post and 2Post Rails for Dell PowerEdge R810 Patent(s) Pending 4Post Page 2 2Post Center Page 4 2Post Flush Page 6 Installation Instructions Kit P/N: 109-1737 109-1841 Kit Contents Kit Contents: (1) Right
More informationINSTALLATION INSTRUCTIONS
Do not attempt to install this product on any vehicle other than the one it is designed for and listed above! Parts List 10 3/8 X 1 1/4 Hex Bolt 10 3/8 Lock Washer 4 3/8 Hex Nut 4 3/8 Flat Washer 2 3169)
More informationDesign of Dual-band Minkowski Fractal Antenna by using Coupling for Wireless Communication System
Design of Dual-band Minkowski Fractal Antenna by using Coupling for Wireless Communication System Shanu Patel 1, D.C. Dhubkaria 2 M.Tech, Department of Electronics and Communication Engineering, BIET Jhansi,
More informationReplacing the Reciprocator on an SWF Multi-head.
Replacing the Reciprocator on an SWF Multi-head. Follow the instructions below to replace the reciprocator in the SWF multi-head machines. The tools required are found in the tool kit that came with the
More informationINSTALLATION INSTRUCTIONS
INSTALLATION INSTRUCTIONS SPORTSMAN WINCH MOUNT GRILLE GUARD APPLICATION: 2016-2018 Toyota Tacoma PART NUMBER: 40-93885, 45-93880, 46-23885 ITEM QUANTITY DESCRIPTION TOOLS NEEDED 1 1 WINCH TRAY 15MM SOCKET
More informationTheft Intimation of Electrical Power over SMS
Theft Intimation of Electrical Power over SMS Mr. Pruthviraj P. Patil 1, Dr. B. T. Salokhe 2, Mr. A.S. Mali 3. M. E. Student, Dept. of Eln. Engg, Tatyasaheb Kore Insti. of Engg. & Tech. Warananagar. Professor,
More informationEFFECT OF WIRE-EDM PROCESS PARAMETERS ON CUTTING SPEED OF AL6061 HYBRID COMPOSITE
International Journal of Mechanical Engineering and Technology (IJMET) Volume 8, Issue 10, October 2017, pp. 185 189, Article ID: IJMET_08_10_023 Available online at http://www.iaeme.com/ijmet/issues.asp?jtype=ijmet&vtype=8&itype=10
More informationBadminton Result (Men)
Badminton Result (Men) League Results (Best of 3 games) Reebok Mukesh Gagandeep Singh 11-02, 11-04 Jagannath Rohit Bhatt 11-02, 11-02 Gagandeep Singh & Rohit Bhatt 11-03, 11-03 Amit Aggarwal Sandeep (06-11),
More informationAnnexure D-I EVEN. Mapping of Courses vs CLOs vs PLOs
Mapping of Courses vs s vs Spring Semester (EVEN) TE 111 Textile Chemistry Process sufficient knowledge of Chemistry required to pursue in chemical processing. PO1 Determine physical/chemical properties
More informationOWNER S MANUAL AMERICA S PREMIER EXERCISE EQUIPMENT RHL-305WS. High/Low Pulley W/200 Lbs Steel Wt Stack (for RPR-265) 84" 59" 50 3/4"
OWNER S MANUAL 84" RHL-0WS 0 /4" 9" High/Low Pulley W/200 Lbs Steel Wt Stack (for RPR-26) AMERICA S PREMIER EXERCISE EQUIPMENT RHL-0WS Rev0 Revision Date -0-2007 Introduction About the RHL-0WS High/Low
More informationErgonomic assessment of press machine using RULA method
Ergonomic assessment of press machine using RULA method Mr.Pushpraj Nathsaheb Kale, Mr.Ravindra T. Vyavahare 1 PG Student, Department of Mechanical Engineering, SKN Sinhgad College of Engineering, Korti,
More informationOPTIMIZATION OF MULTIGATE RUNNER IN LONG CASTINGS: A SIMULATION APPROACH
913 OPTIMIZATION OF MULTIGATE RUNNER IN LONG CASTINGS: A SIMULATION APPROACH IRFAN AHMAD ASARI (Mechanical engineering department Aligarh Muslim University, Aligarh U.P Email: mechirfaan@gmail.com) The
More informationCondition Monitoring of Rotationg Equpiment s using Vibration Signature Analysis- A Review
Condition Monitoring of Rotationg Equpiment s using Vibration Signature Analysis- A Review Murgayya S B, Assistant Professor, Department of Automobile Engineering, DSCE, Bangalore Dr. H.N Suresh, Professor
More informationDesign, Development and Analysis of Clamping Force of a Cylinder of Fixture for Casing of Differential
Design, Development and Analysis of Clamping of a Cylinder of Fixture for Casing of Differential R.Akshay 1, Dr.B.N.Ravikumar 2 1PG Student, Department of Mechanical Engineering Bangalore Institute of
More informationDesign a Low Power High Speed Full Adder Using AVL Technique Based on CMOS Nano-Technology
IOSR Journal of Electronics and Communication Engineering (IOSR-JECE) e-issn: 2278-2834,p- ISSN: 2278-8735. Volume 8, Issue 1 (Sep. - Oct. 2013), PP 19-26 Design a Low Power High Speed Full Adder Using
More informationRUN-IN SHED INSTRUCTIONS
RUN-IN SHED INSTRUCTIONS 14321 5th Line Nassagaweya, Rockwood, ON, N0B 2K0 Phone 519-856-9959 ~ Fax 519-856-4141 Toll Free 1-800-461-3362 ~ Email sales@systemhorse.com Website www.systemfence.com RUN-IN
More informationDesign and Assembly of Special Purpose Leak Testing Machine I. INTRODUCTION
Design and Assembly of Special Purpose Leak Testing Machine Prof. Prashant Vavhal #1 #Mechanical Engineering Department, Savitribai Phule Pune University 1 Assistant Professor, P. K. Techanical Campus,
More informationSwaroop S. Magdum 1, Baliram R. Jadhav 2 1 Student, M.Tech, Department of Mechanical Engineering, RIT, Sakharale, Sangli, Maharashtra, India.
Design and Development of Casting by Simulation Technique for Yield Improvement in Foundry Industry Swaroop S. Magdum 1, Baliram R. Jadhav 2 1 Student, M.Tech, Department of Mechanical Engineering, RIT,
More informationMANUFACTURING OF SERVO MOTORS
Profile No.: 11 NIC Code: 29109 MANUFACTURING OF SERVO MOTORS 1. INTRODUCTION: Servo motors (or servos) are self-contained electric devices that rotate or push parts of a machine with great precision.
More informationFord Ranger t6 winch plate WPFR001
Ford Ranger t6 winch plate WPFR001 INSTALL TIME: 30 mins IMPORTANT WARNING! IT IS CRITICAL THAT ALL FRONT RUNNER PRODUCTS BE PROPERLY AND SECURELY ASSEMBLED AND ATTACHED TO YOUR VEHICLE. IMPROPER ATTACHMENT
More informationContents 2012 ESG AND CITIZENSHIP REPORT: CASE STUDY ARCHIVE. Magma Fincorp: Investing in Solutions. NY Office Green Team Reduces Waste and Costs
ARCHIVE Contents Magma Fincorp: Investing in Solutions NY Office Green Team Reduces Waste and Costs Sponsors for Educational Opportunities: Reaching Underserved Youth Toys R Us: Building Tools to Build
More informationMinimization of Non Productive Time in Drilling Rig Operation
International Journal of Engineering Trends and Technology (IJETT) Volume-44 Number-1 -February 217 Minimization of Non Productive Time in Drilling Rig Operation Nabo Jyoti Modak 1#, Diganta Kalita 2#,
More informationINSTALLATION INSTRUCTIONS
PART NO. 3373MB 3373MC 3373MH PRODUCT DESCRIPTION: 3000 SERIES STEP GUARD BLACK (GRILLE GUARD & BRUSH GUARDS) 3000 SERIES STEP GUARD CHROMED (GRILLE GUARD & BRUSH GUARDS) 3000 SERIES STEP GUARD BLACK/CHROMED
More informationCalibration of Hollow Operating Shaft Natural Frequency by Non-Contact Impulse Method
IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-issn: 2278-1684,p-ISSN: 2320-334X, Volume 13, Issue 2 Ver. I (Mar. - Apr. 2016), PP 54-60 www.iosrjournals.org Calibration of Hollow Operating
More informationCONCRETE ACCESSORIES BAR-LOCK REBAR COUPLER SYSTEM
CONCRETE ACCESSORIES BAR-LOCK REBAR COUPLER SYSTEM quick and easy to install no special installation equipment high strength excellent for new construction and rehab projects Bar-Lock Coupler System* ICBO
More informationFORMULIZE CONSTRUCTION AND OPERATION MANAGEMENT BY INTEGRATING BIM AND LEAN
International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue 4, April 2017, pp. 991-1001, Article ID: IJCIET_08_04_113 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=8&itype=4
More informationDESIGN AND ANALYSIS OF INDEXING TYPE DRILL JIG FOR A MISSSILE COMPONENT
International Journal of Mechanical Engineering and Technology (IJMET) Volume 8, Issue 11, November 2017, pp. 889 898, Article ID: IJMET_08_11_090 Available online at http://www.iaeme.com/ijmet/issues.asp?jtype=ijmet&vtype=8&itype=11
More informationLow Cost Automation(LCA): A Case Study
Low Cost Automation(LCA): A Case Study Sameer S. Gajmal 1, Prof. Sudhir.G Bhatwadekar 2 1 Assistant Professor, Department of Mechanical Engineering, Gharda Institute of Technology, Lavel 2 Associate Professor,
More informationElectric Mid-Drive. Installation and Assembly Instructions for Catrike 26 and 700c
Electric Mid-Drive Installation and Assembly Instructions for Catrike 26 and 700c copyright 2009, EcoSpeed LLC http://www.ecospeed.com/docs/emd22_assy_rev1.01 Revision 1.01 p/n 7-10-22 1 2 Electric Mid-Drive
More informationAutomation Techniques and it s an Industrial Application: A Review
Automation Techniques and it s an Industrial Application: A Review Umesh S. Patharkar 1 and J.J.Salunke 2 1 PG Student Mechanical Engineering Department, Deogiri Institute of Engineering & Management Studies,
More informationTRIUMPH TIGER 800 PD NERF
TRIUMPH TIGER 800 PD NERF 0505-0 Step Before you begin, place the bike on a hard level surface where you have room to work. Lay out the parts included in this kit and compare to the parts list on page
More informationTRACK VOLTAGE APPROACH USING CONVENTIONAL PI AND FUZZY LOGIC CONTROLLER FOR PERFORMANCE COMPARISON OF BLDC MOTOR DRIVE SYSTEM FED BY CUK CONVERTER
International Journal of Mechanical Engineering and Technology (IJMET) Volume 9, Issue 12, December 2018, pp. 778 786, Article ID: IJMET_09_12_078 Available online at http://www.ia aeme.com/ijmet/issues.asp?jtype=ijmet&vtype=
More informationIndustrial Technology Metals and Engineering Industries
Centre Number Student Number 2007 HIGHER SCHOOL CERTIFICATE EXAMINATION Industrial Technology Metals and Engineering Industries General Instructions Reading time 5 minutes Working time 1 2 1 hours Write
More informationSTANDARD AND METRIC CHART EPUB
03 February, 2018 STANDARD AND METRIC CHART EPUB Document Filetype: PDF 387.23 KB 0 STANDARD AND METRIC CHART EPUB Atlanta Rod chart showing standard thread pitch. Four Slide Products' Fractional and Metric
More informationTABLE MKI small with Basin and under rack brackets kit
TABLE MKI small with Basin and under rack brackets kit TBRA024 INSTALL TIME: 15 mins IMPORTANT WARNING! IT IS CRITICAL THAT ALL FRONT RUNNER PRODUCTS BE PROPERLY AND SECURELY ASSEMBLED AND ATTACHED TO
More informationANTATEX HEALD FRAMES
ANTATEX HEALD FRAMES INSTRUCTION MANUAL USE WISELY FOR LONGER SERVICE LIFE Thank you very much for purchasing Antatex heald frame. Cautions! Cautions for storage 1. Store in a well ventilated indoor place.
More informationOptimization of Process Parameters of Plasma Arc Cutting Using Taguchi s Robust Design Methodology
IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-issn: 2278-1684, p-issn : 2320 334X PP 124-128 www.iosrjournals.org Optimization of Process Parameters of Plasma Arc Cutting Using Taguchi
More informationFBX-PA-2AC. Third edition : April No
FBX-PA-2AC Third edition : April 2006 No. 060058 INTRODUCTION Thank you very much for purchasing Kansai Special FBX series. Read and study this Instruction Manual carefully before you start any of the
More informationDesign and Fabrication of Automatic Wood Drilling Machine
Design and Fabrication of Automatic Wood Drilling Machine Deepak Devasagayam #1 Anthony Ignatious #2, Jason Kalathingal *3, Joy Kakde #4, *5 Mechanical Engineering Department, Fr. C.R.I.T., Vashi. Navi
More informationSOCCER TABLE. Assembly Instructions
Updated: 9/30/2015 SOCCER TABLE Assembly Instructions Table of Contents Parts Identifier... 3 Hardware Identifier. 4 Table Assembly Instructions... 5 Table Assembly Pictures..... 6, 7, 8 2 Page Parts Identifier
More informationJUDGE'S STAND INST TOOLS: Hammer, Tape Measure, Phillips Screwdriver, 7/16" Wrench, 1/2" Wrench, 9/16" Wrench X2
888--8. Check all parts against parts list to ensure that all parts and hardware are available to complete the installation. 0 0 900 JUDGE'S STAND TOOLS: Hammer, Tape Measure, Phillips Screwdriver, /"
More informationRayport G Eco Dealer Kit
Rayport G Eco Dealer Kit Installation Guide Contents 1. Installer Notes..... P2 2. Parts List........ P3-7 3. Tool List.... P8 4. Assembly.... P9-19 www.aetenergy.com Supporting a Cleaner, Greener Tomorrow
More informationAssembly, Installation, Operation and Maintenance Instructions Kit, Base Rail Bracket Part # 31852
. Assembly, Installation, Operation and Maintenance Instructions Kit, Base Rail Bracket Part # 31852 Dealer / Installer: Provide a copy of these instructions to the end user of this product. These instructions
More informationSERVICE BULLETIN. No. SB-CR-017 Rev.: - Date: Page: 1 of 7 Date: -
Page: 1 of 7 Date: - MODEL AFFECTED: SUBJECT: AIRCRAFT AFFECTED: COMPLIANCE: PS-28 Cruiser / SportCruiser / PiperSport Replacement of rivets for bolts in the area of the main landing gear attachment. All
More informationtable brackets for mki table incl latch TBRA020
table brackets for mki table incl latch TBRA020 INSTALL TIME: 15 mins IMPORTANT WARNING! IT IS CRITICAL THAT ALL FRONT RUNNER PRODUCTS BE PROPERLY AND SECURELY ASSEMBLED AND ATTACHED TO YOUR VEHICLE. IMPROPER
More informationImplementing the concept of paint before assembly to the typical assembly line
Implementing the concept of paint before assembly to the typical assembly line Rayappa Mahale * M.Tech., Student IP&E Dept BVBCET, Hubli Dr. V.N.Gaitonde Professor IP&E Dept BVBCET, Hubli Abstract This
More informationR & D Projects
R & D Projects 2017-18 1. GOVERNMENT SPONSORED PROJECTS 1.1 Completed projects (i) Project title : Development of fabric smoothness tester (Sponsored by Ministry of Textiles, Govt. of India) Objectives
More informationMECHANICAL AND TRIBOLOGICAL BEHAVIOR OF HEMP FIBER REINFORCED POLYMERIC COMPOSITE
International Journal of Mechanical Engineering and Technology (IJMET) Volume 9, Issue 11, November2018, pp. 1061 1066, Article ID: IJMET_09_11_108 Available online at http://www.iaeme.com/ijmet/issues.asp?jtype=ijmet&vtype=9&itype=11
More informationINSTRUCTIONS INSTRUCCIONES CONSIGNES
AUTOMOTIVE PRODUCTS, INC. INSTRUCTIONS INSTRUCCIONES CONSIGNES APPLICATION: 2007-2010 CHEVY/GMC SILVERADO/SIERRA 2500/3500 (EXCLUDES CLASSIC) APP PART #46-23715, 40-92315/45-92310 MAX WINCH TRAY, SPORTSMAN
More informationRBS Industrial Solution. Providing the best and world Class Solutions for all type of Industries
RBS Industrial Solution Providing the best and world Class Solutions for all type of Industries RBS Industrial Solution is one of the India s fastest growing companies. Since its creation in 2016. We keeping
More informationWhat is a fastener? A device to locate or hold parts
What is a fastener? A device to locate or hold parts As a repair technician you will become skilled at removing, reconditioning, replacing, and installing fasteners. An important skill to learn is how
More informationMay 14, Installation Manual
May 14, 2012 Installation Manual Contents MAG TRACKER Components...1 Mount Installation...7 Module Installation & Grounding...11 Maintenance...14 Warranty......14 Contact Information......14 May 14, 2012
More informationINSTALLATION MANUAL for KLINGER gaskets
INSTALLATION MANUAL for KLINGER gaskets INSTALLATION TIPS FOR KLINGER GASKETS SUITABILITY Check on chemical resistance STORAGE Check on storage conditions PT-DIAGRAMS Review the pt-diagrams INSTALLATION
More informationTrade of Toolmaking. Module 5: Press Tools, Jigs & Fixtures, Mouldmaking Unit 10: Mould Assembly Phase 2. Published by
Trade of Toolmaking Module 5: Press Tools, Jigs & Fixtures, Mouldmaking Unit 10: Mould Assembly Phase 2 Published by SOLAS 2014 Unit 9 1 Table of Contents Document Release History... 3 Unit Objective...
More informationCYCLE TIME REDUCTION STUDIES IN THREADING
International Journal of Mechanical and Production Engineering Research and Development (IJMPERD) ISSN (P): 2249-6890; ISSN (E): 2249-8001 Vol. 8, Issue 2, Apr 2018, 149-156 TJPRC Pvt. Ltd. CYCLE TIME
More informationA STUDY OF IMPACT OF USE OF IT ON ACADEMIC LIBRARIES IN INDIA
International Journal of Library & Information Science (IJLIS) Volume 5, Issue 1, Jan- April 2016, pp. 36-40, Article ID: IJLIS_05_01_005 Available online at http://www.iaeme.com/ijlis/issues.asp?jtype=ijlis&vtype=5&itype=1
More informationDairy Cap Chuck. Service & Installation Instructions. An Altra Industrial Motion Company P-2021-WE
Dairy Cap Chuck P-2021-WE Service & Installation Instructions An Altra Industrial Motion Company Setting Application Torque 1. Determine initial clutch setting from torque chart below. Recommended Maintenance
More informationInstalling BACKRACK Cab Guards on Ford F ft Bed
Installing BACKRACK Cab Guards on 2004-2012 Ford F-150 5.5 ft Bed In the past, the 5.5 ft bed F-150 was installed by drilling holes through the top plastic of the truck bed rail ( 10512 SC ) The installation
More informationA 130-NM CMOS 400 MHZ 8-BIT LOW POWER BINARY WEIGHTED CURRENT STEERING DAC
A 130-NM CMOS 400 MHZ 8-BIT LOW POWER BINARY WEIGHTED CURRENT STEERING DAC Ashok Kumar Adepu and Kiran Kumar Kolupuri Department of Electronics and communication Engineering,MVGR College of Engineering,
More informationInternational Journal of Science and Engineering Research (IJ0SER), Vol 3 Issue 3 March , (P) X
Design And Optimization Techniques Using In Turning Fixture M Rajmohan 1, K S Sakthivel 1, S Sanjay 1, A Santhosh 1, P Satheesh 2 1 ( UG Student ) 2 (Assistant professor)mechanical Department, Jay Shriram
More informationSIGN STRUCTURE BOLT TESTING AND INSPECTION! WHAT HAVE WE FOUND AND WHAT ARE WE DOING
The Golden Anniversary of the Mid-Atlantic Quality Assurance Workshop SIGN STRUCTURE BOLT TESTING AND INSPECTION! WHAT HAVE WE FOUND AND WHAT ARE WE DOING Maryland State Highway Administration Bruce L.
More informationPRODUCTIVITY IMPROVEMENT USING MTTR AND MTBF METHODOLOGY
International Journal of Mechanical Engineering and Technology (IJMET) Volume 8, Issue 7, July 2017, pp. 1338-1347, Article ID: IJMET_08_07_144 Available online at http://www.iaeme.com/ijmet/issues.asp?jtype=ijmet&vtype=8&itype=7
More informationSales & Service. JFK - Just For Kids. sasportonline.com. 135 Forestview Road 7879 Will Rogers Blvd.
Sales & Service sasportonline.com SA Sport (Canada) SA Sport (U.S.A.) 135 Forestview Road 7879 Will Rogers Blvd. P.O. Box 40 Fort Worth, Texas Orillia, Ontario USA 76140 Canada L3V 6H9 Telephone: (705)
More informationRAPID CONSTRUCTION-INOVATIVE APPROCH OF PREFABRICATED CONSTRUCTION
RAPID CONSTRUCTION-INOVATIVE APPROCH OF PREFABRICATED CONSTRUCTION Krushil K. Ponkiya 1, Dhyey K. Shah 2, Rushabh A. Shah 3 PG. Student, SNPIT & RC, Umrakh, Gujarat, India 1 PG. Student SNPIT & RC, Umrakh,
More informationDESIGN OF LOW POWER HIGH SPEED ERROR TOLERANT ADDERS USING FPGA
International Journal of Advanced Research in Engineering and Technology (IJARET) Volume 10, Issue 1, January February 2019, pp. 88 94, Article ID: IJARET_10_01_009 Available online at http://www.iaeme.com/ijaret/issues.asp?jtype=ijaret&vtype=10&itype=1
More information