Lecturer: Dr. J B E AL-ATRASH No. of Pages: 4

Size: px
Start display at page:

Download "Lecturer: Dr. J B E AL-ATRASH No. of Pages: 4"

Transcription

1 Philadelphia University Faculty of Engineering Dept. of Electrical Engineering Student Name: Student Number: Final Exam Course Title: Design of T&D System Date: 15 th June 2016 Course No: / Time Allowed:120 Minutes Lecturer: Dr. J B E AL-ATRASH No. of Pages: 4 Question 1: (10 Marks) Objectives: (Fundamental information in T& D design) Choose the correct answer? (2 Marks x 5) 1. The SIL of transmission line working at 750 KV (double circuit) is a) 750 MW b) 1875 MW c) 3750 MW d) 1500 MW Answer: c 2. The height of H.V transmission working on 400 KV is a) 28 m b) 35 m c) 48 m d) 75 m Answer: c 3. The short circuit level at any bus in the power system is given by MVAs.c=MVAb/Xs.c Where a) MVAb in MVA and Xsc in p.u from that bus up to the Xs of the source b) MVAb in MVA and Xsc in ohm from that bus up to the Xs of the source c) MVAb in MVA and Xsc in p.u from that bus up to and including the Xs of the source Answer: c 4. Typical area of land needed to build indoor substation 132/33 KV is a) 2600 m 2 b) 500 m 2 c) between m 2 Answer: a 5. The characteristic impedance for a transmission line is equal to a) LC b) L/C c) LC d) L/C Answer: b Question 2: (10 Mark) Objectives: (Tie connection between two neighboring power system) If two neighboring power systems are to be connected together to exchange power during MD of 500 MW (unity power factor) at a distance of 500 km. Calculate a) The level of voltage at which this transmission line should operate on to permit the required power exchange?(4 Marks) Solution SIL 400KV =(400 KV) 2 /300=533.3 MW Then choose operating voltage of 400 KV 1

2 b) Discuss the design and configuration (draw) of both the towers and conductors to be used in this transmission line? Give the approximate height of the tower, the insulator level voltage and the distance between successive towers?(6 Marks) Double circuit Bundled twin conductor Single earth wire The tower should be designed as double circuit (bundled) with single earth wire. The approximate height is 48 m for each tower. The insulators voltage level is 15 KV The distance between successive towers=500 m. I L =S/( 3xV L )=500 MVA/( 3x400KV)=721.7 Amps Then choose c.s.a of 650 mm 2 X T.L = 500x(0.05+j0.18)=25+j90 Ω For D.L X T.L =+J45 Ω Question 3: (10 Marks) Objectives: (Calculation of annual energy, MD and load factor) 2

3 Fig 1: Daily load curve of the national grid. The load measurements are given in Table 1 Time (hrs) P (MW) Time (hrs) P (MW) Table 1 (A) The daily load curve of the Jordan national power system is given in Fig 1 shows that the MD was 3300 MW during the day between a.m at the 9 th August Calculate the daily load factor for that day? (6 Marks) (B) Calculate the energy consumed in the year 2015 given that the annual energy factor (ALF) = 0.62? (4 Marks) Solution 3

4 DLF= Actual energy consumed/ Energy consumed in that period assuming the maximum demand prevailing all the time = [2600x1+2x ( ) +2700x1]/3300 x 24 = /79200 =0.84 B) Calculate the energy consumed given that the annual energy factor (ALF) = 0.65? (4 Marks) Energy consumed = ALF x MD X 8760=0.62 x 3300 x 8760 = GWh Question 4: Objectives: (Design transmission power system) (10 Marks) If it is required to supply a new project which has Maximum Demand of 400 MW at unity power factor at the end of the next 10 years; and the nearest point of connection is at distance of 35 km, 400 KV and at fault level of MVA Then calculate 1. The number and the rating of the transformers near the sight of the project? (2 marks) 2. The rating of different circuit breakers (in MVA and KA) used to supply this new load? (4 marks) 3. The short circuit level at the high voltage side and low voltage side of the suggested substation? (4 marks) 400 kv 2 x 400 MVA 132 kv The MVA SC at 400 KV = MVA I L = (400/1.0) /( 3 x 400)= 577 A 4

5 Then choose 600 mm 2 X of 10 km = 0.22 x 10=2.2 Ω Z base = (400) 2 /100 = 1600 Ω X p.u = (2.2/1600) x ½ = p.u Xsource= 100/15000 = The fault level at 400 kv (the point of connection after 10 km) is MVA s.c = 100/( ) = 100/( ) = MVA In this case C.B s at 400 kv are MVA, 30.3 ka The fault level at 132 kv is MVA s.c = 100/[ (100/400)0.14// (100/400)0.14] =100/[ // 0.035] =100/(0.0247) = MVA Then use MVA C.B, 25 ka Table 1 Switchgear Fault Ratings System Voltage BS 116 Rating LE.C Rating kv MVA ka Table 2: Electrical characteristics of bare aluminum conductors steel-reinforced c.s.a(mm 2 ) R (Ω/km) X (Ω/km) Ampers Table 3: Three phase transformer group Ratio KV Rating MVA Reactance % 5

6 33/11 132/33 400/

Level 6 Graduate Diploma in Engineering Electrical Energy Systems

Level 6 Graduate Diploma in Engineering Electrical Energy Systems 9210-114 Level 6 Graduate Diploma in Engineering Electrical Energy Systems Sample Paper You should have the following for this examination one answer book non-programmable calculator pen, pencil, ruler,

More information

ETAP PowerStation. Electrical Transient Analyzer Program. ETAP PowerStation. Short Circuit Analysis. ANSI Standard 3-Phase Fault Currents

ETAP PowerStation. Electrical Transient Analyzer Program. ETAP PowerStation. Short Circuit Analysis. ANSI Standard 3-Phase Fault Currents Page: 1 Electrical Transient Analyzer Program Short Circuit Analysis ANSI Standard 3-Phase Fault Currents Number of Buses: Swing Generator Load Total 1 0 4 5 Number of Branches: XFMR2 XFMR3 Reactor Line/Cable

More information

Single Line Diagram of Substations

Single Line Diagram of Substations Single Line Diagram of Substations Substations Electric power is produced at the power generating stations, which are generally located far away from the load centers. High voltage transmission lines are

More information

In Class Examples (ICE)

In Class Examples (ICE) In Class Examples (ICE) 1 1. A 3φ 765kV, 60Hz, 300km, completely transposed line has the following positive-sequence impedance and admittance: z = 0.0165 + j0.3306 = 0.3310 87.14 o Ω/km y = j4.67 410-6

More information

BE Semester- VI (Electrical Engineering) Question Bank (E 605 ELECTRICAL POWER SYSTEM - II) Y - Y transformer : 300 MVA, 33Y / 220Y kv, X = 15 %

BE Semester- VI (Electrical Engineering) Question Bank (E 605 ELECTRICAL POWER SYSTEM - II) Y - Y transformer : 300 MVA, 33Y / 220Y kv, X = 15 % BE Semester- V (Electrical Engineering) Question Bank (E 605 ELECTRCAL POWER SYSTEM - ) All questions carry equal marks (10 marks) Q.1 Explain per unit system in context with three-phase power system and

More information

Unit 2. Single Line Diagram of Substations

Unit 2. Single Line Diagram of Substations Unit 2 Single Line Diagram of Substations Substations Electric power is produced at the power generating stations, which are generally located far away from the load centers. High voltage transmission

More information

SAMPLE EXAM PROBLEM PROTECTION (6 OF 80 PROBLEMS)

SAMPLE EXAM PROBLEM PROTECTION (6 OF 80 PROBLEMS) SAMPLE EXAM PROBLEM PROTECTION (6 OF 80 PROBLEMS) SLIDE In this video, we will cover a sample exam problem for the Power PE Exam. This exam problem falls under the topic of Protection, which accounts for

More information

Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017

Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017 Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017 NAME: LOCATION: 1. The primitive self-inductance per foot of length

More information

R10. III B.Tech. II Semester Supplementary Examinations, January POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours

R10. III B.Tech. II Semester Supplementary Examinations, January POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours Code No: R3 R1 Set No: 1 III B.Tech. II Semester Supplementary Examinations, January -14 POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours Max Marks: 75 Answer any FIVE Questions

More information

SDCS-03 DISTRIBUTION NETWORK GROUNDING CONSTRUCTION STANDARD (PART-I) UNDERGROUND NETWORK GROUNDING. Rev. 01

SDCS-03 DISTRIBUTION NETWORK GROUNDING CONSTRUCTION STANDARD (PART-I) UNDERGROUND NETWORK GROUNDING. Rev. 01 SDCS-03 DISTRIBUTION NETWORK GROUNDING CONSTRUCTION STANDARD (PART-I) UNDERGROUND NETWORK GROUNDING Rev. 01 This specification is property of SEC and subject to change or modification without any notice

More information

Chapter # : 17 Symmetrical Fault Calculations

Chapter # : 17 Symmetrical Fault Calculations Chapter # : 17 Symmetrical Fault Calculations Introduction Most of the faults on the power system lead to a short-circuit condition. The short circuit current flows through the equipment, causing considerable

More information

Course ELEC Introduction to electric power and energy systems. Additional exercises with answers December reactive power compensation

Course ELEC Introduction to electric power and energy systems. Additional exercises with answers December reactive power compensation Course ELEC0014 - Introduction to electric power and energy systems Additional exercises with answers December 2017 Exercise A1 Consider the system represented in the figure below. The four transmission

More information

Three-phase short-circuit current (Isc) calculation at any point within a LV installation using impedance method

Three-phase short-circuit current (Isc) calculation at any point within a LV installation using impedance method Three-phase short-circuit current (Isc) calculation at any point within a LV installation using impedance method Calculation of Isc by the impedance method In a 3-phase installation Isc at any point is

More information

Analysis of a 405 km transmission line with series compensation

Analysis of a 405 km transmission line with series compensation Analysis of a 405 km transmission line with series compensation by Dr. Rupert Gouws, North-West University This paper presents an investigative case study and energy efficiency analysis of the 405 km,

More information

Exercises on overhead power lines (and underground cables)

Exercises on overhead power lines (and underground cables) Exercises on overhead power lines (and underground cables) 1 From the laws of Electromagnetism it can be shown that l c = 1 v 2 where v is the speed of propagation of electromagnetic waves in the environment

More information

Transmission of Electrical Energy

Transmission of Electrical Energy Transmission of Electrical Energy Electrical energy is carries by conductors such as overhead transmission lines and underground cables. The conductors are usually aluminum cable steel reinforced (ACSR),

More information

3-phase short-circuit current (Isc) at any point within a LV installation

3-phase short-circuit current (Isc) at any point within a LV installation 3-phase short-circuit current (Isc) at any point within a LV installation In a 3-phase installation Isc at any point is given by: where U 20 = phase-to-phase voltage of the open circuited secondary windings

More information

EL 403 MODEL TEST PAPER - 1 POWER SYSTEMS. Time: Three Hours Maximum Marks: 100

EL 403 MODEL TEST PAPER - 1 POWER SYSTEMS. Time: Three Hours Maximum Marks: 100 POWER SYSTEMS Time: Three Hours Maximum Marks: 0 Answer five questions, taking ANY TWO from Group A, any two from Group B and all from Group C. All parts of a question (a, b, etc. ) should be answered

More information

The Italy - Malta interconnection. Morris Brenna

The Italy - Malta interconnection. Morris Brenna The Italy - Malta interconnection Introduction The Republic of Malta has an area of 316 km2 and a population of about 410 thousands with an energy annual consumption of about 2.3 TWh. The Maltese electric

More information

Fatima Michael college of Engineering and Technology

Fatima Michael college of Engineering and Technology Fatima Michael college of Engineering and Technology DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING EE2303 TRANSMISSION AND DISTRIBUTION SEM: V Question bank UNIT I INTRODUCTION 1. What is the electric

More information

PROTECTION APPLICATION HANDBOOK

PROTECTION APPLICATION HANDBOOK BOOK No 6 Revision 0 Global Organization Innovative Solutions Product & Substation System Business Business PROTECTION APPLICATION HANDBOOK BA THS / BU Transmission Systems and Substations LEC Support

More information

EARTH FAULT PROTECTION VIS-A-VIS GENERATOR GROUNDING SYSTEM

EARTH FAULT PROTECTION VIS-A-VIS GENERATOR GROUNDING SYSTEM EARTH FAULT PROTECTION VIS-A-VIS GENERATOR GROUNDING SYSTEM BY MR. H. C. MEHTA AT 1 ST INDIA DOBLE PROTECTION AND AUTOMATION CONFERENCE, NOV 2008 POWER-LINKER Wisdom is not Virtue but Necessity hcmehta@powerlinker.org

More information

EN Assignment No.1 - TRANSFORMERS

EN Assignment No.1 - TRANSFORMERS EN-06 - Assignment No.1 - TRANSFORMERS Date : 13 th Jan 01 Q1) A 0kVA 00/0 Volts, 60Hz, single phase transformer is found to have the following equivalent circuit parameter referred to the high potential

More information

Impedance protection on power transformer.

Impedance protection on power transformer. Impedance protection on power transformer www.siemens.com/siprotec5 SIPROTEC 5 Application Impedance Protection on Power Transformer APN-045, Edition 1 Content 1...3 1.1 Introduction...3 1.2 Application

More information

POWER UPGRADATION AND POSSIBILITY OF SMALL POWER TAPPING FROM COMPOSITE AC- DC TRANSMISSION SYSTEM

POWER UPGRADATION AND POSSIBILITY OF SMALL POWER TAPPING FROM COMPOSITE AC- DC TRANSMISSION SYSTEM Int. J. Elec&Electr.Eng&Telecoms. 2013 K Shobha Rani and C N Arpitha, 2013 Research Paper ISSN 2319 2518 www.ijeetc.com Vol. 2, No. 3, July 2013 2013 IJEETC. All Rights Reserved POWER UPGRADATION AND POSSIBILITY

More information

SYSTEM STUDIES for HVDC

SYSTEM STUDIES for HVDC INTRODUCTION The design of HVDC requires Careful study coordination, which must be achieved in compliance with the Owner s requirements. To achieve these objectives, number of highly interactive system

More information

EE 741. Primary & Secondary Distribution Systems

EE 741. Primary & Secondary Distribution Systems EE 741 Primary & Secondary Distribution Systems Radial-Type Primary Feeder Most common, simplest and lowest cost Example of Overhead Primary Feeder Layout Example of Underground Primary Feeder Layout Radial-Type

More information

POWER SYSTEM PRINCIPLES APPLIED IN PROTECTION PRACTICE. Professor Akhtar Kalam Victoria University

POWER SYSTEM PRINCIPLES APPLIED IN PROTECTION PRACTICE. Professor Akhtar Kalam Victoria University POWER SYSTEM PRINCIPLES APPLIED IN PROTECTION PRACTICE Professor Akhtar Kalam Victoria University The Problem Calculate & sketch the ZPS, NPS & PPS impedance networks. Calculate feeder faults. Calculate

More information

A Guide to the DC Decay of Fault Current and X/R Ratios

A Guide to the DC Decay of Fault Current and X/R Ratios A Guide to the DC Decay of Fault Current and X/R Ratios Introduction This guide presents a guide to the theory of DC decay of fault currents and X/R ratios and the calculation of these values in Ipsa.

More information

, ,54 A

, ,54 A AEB5EN2 Ground fault Example Power line 22 kv has the partial capacity to the ground 4,3.0 F/km. Decide whether ground fault currents compensation is required if the line length is 30 km. We calculate

More information

UPGRADING SUBSTATION RELAYS TO DIGITAL RECLOSERS AND THEIR COORDINATION WITH SECTIONALIZERS

UPGRADING SUBSTATION RELAYS TO DIGITAL RECLOSERS AND THEIR COORDINATION WITH SECTIONALIZERS UPGRADING SUBSTATION RELAYS TO DIGITAL RECLOSERS AND THEIR COORDINATION WITH SECTIONALIZERS 1 B. RAMESH, 2 K. P. VITTAL Student Member, IEEE, EEE Department, National Institute of Technology Karnataka,

More information

1 Comparison of Approaches (SESTLC, ROW & HIFREQ) for AC Interference Study

1 Comparison of Approaches (SESTLC, ROW & HIFREQ) for AC Interference Study 1 Comparison of Approaches (SESTLC, ROW & HIFREQ) for AC Interference Study 1 Comparison of Approaches (SESTLC, ROW & HIFREQ) for AC Interference Study 1.1 Introduction Yexu Li and Simon Fortin Three independent

More information

a) Determine the smallest, standard-sized circuit breaker that should be used to protect this branch circuit.

a) Determine the smallest, standard-sized circuit breaker that should be used to protect this branch circuit. ECET4520 Exam II Sample Exam Problems Instructions: This exam is closed book, except for the reference booklet provided by your instructor and one (8.5 x11 ) sheet of handwritten notes that may not contain

More information

IEC Standard Caledonian Offshore & Marine Cables

IEC Standard Caledonian Offshore & Marine Cables Power Copper s According to IEC 60228 Tinned conductors Cross section cl.2 cl.5 Cross section cl.2 cl.5 mm² Ohm/km Ohm/km mm² Ohm/km Ohm/km 1.0 18.2 20 70 0.270 0.277 1.5 12.2 13.7 95 0.195 0.210 2.5 7.56

More information

Dynamic Model Of 400 Kv Line With Distance Relay. Director Research, The MRPC Company, Hyderabad, India 2

Dynamic Model Of 400 Kv Line With Distance Relay. Director Research, The MRPC Company, Hyderabad, India 2 Dynamic Model Of 400 Kv Line With Distance Relay Ramleela Khare 1, Dr Filipe Rodrigues E Melo 2 1 Director Research, The MRPC Company, Hyderabad, India 2 Assoc. Professor Commerce, St. Xavier s College

More information

ADVANCED CONTROLS FOR MITIGATION OF FLICKER USING DOUBLY-FED ASYNCHRONOUS WIND TURBINE-GENERATORS

ADVANCED CONTROLS FOR MITIGATION OF FLICKER USING DOUBLY-FED ASYNCHRONOUS WIND TURBINE-GENERATORS ADVANCED CONTROLS FOR MITIGATION OF FLICKER USING DOUBLY-FED ASYNCHRONOUS WIND TURBINE-GENERATORS R. A. Walling, K. Clark, N. W. Miller, J. J. Sanchez-Gasca GE Energy USA reigh.walling@ge.com ABSTRACT

More information

G. KOEPPL Koeppl Power Experts Switzerland

G. KOEPPL Koeppl Power Experts Switzerland PS3: Substation Design: New Solutions and Experiences Bus-Node Substation A Big Improvement in Short-Circuit and Switching Properties at Reduced Substation Costs G. KOEPPL Koeppl Power Experts Switzerland

More information

Chapter 2: Transformers

Chapter 2: Transformers Chapter 2: Transformers 2-1. The secondary winding of a transformer has a terminal voltage of v s (t) = 282.8 sin 377t V. The turns ratio of the transformer is 100:200 (a = 0.50). If the secondary current

More information

Chapter G Sizing and protection of conductors

Chapter G Sizing and protection of conductors Chapter G Sizing and protection of conductors 1 2 3 4 5 6 7 8 Contents General 1.1 Methodology and definition G2 1.2 Overcurrent protection principles G4 1.3 Practical values for a protective scheme G4

More information

Chapter 6. WIRING SYSTEMS Safe Electrical Design

Chapter 6. WIRING SYSTEMS Safe Electrical Design Chapter 6 WIRING SYSTEMS Safe Electrical Design Topic 6-3 CABLE SELECTION BASED ON CURRENT CARRYING CAPACITY REQUIREMENTS INSTALLATION CONDITIONS Current carrying capacity (CCC) is the maximum continuous

More information

Utility Interconnection and System Protection

Utility Interconnection and System Protection Utility Interconnection and System Protection Alex Steselboim President, Advanced Power Technologies, Inc. Utility paralleling vs. isolated operation. Isochronous kw load sharing Reactive power (VAR) sharing

More information

SWITCHING OVERVOLTAGES IN A 400-KV CABLE SYSTEM

SWITCHING OVERVOLTAGES IN A 400-KV CABLE SYSTEM SWITCHING OVERVOLTAGES IN A 4-KV CABLE SYSTEM Mustafa Kizilcay University of Siegen Siegen, Germany kizilcay@uni-siegen.de Abstract This paper deals with the computation of switching overvoltages in a

More information

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell Power Plant and Transmission System Protection Coordination Phase Distance (21) and Voltage-Controlled or Voltage-Restrained Overcurrent Protection (51V) NERC Protection Coordination Webinar Series June

More information

Power System Studies

Power System Studies Power System Studies Laois Ballyragget Cable Feasibility Study PE667-F4-R3-1-3 ESBI Engineering Solutions Stephen Court, 18/21 St Stephen s Green, Dublin 2, Ireland Telephone+353-1-73 8 Fax+353-1-661 66

More information

Cork Institute of Technology. Autumn 2008 Electrical Energy Systems (Time: 3 Hours)

Cork Institute of Technology. Autumn 2008 Electrical Energy Systems (Time: 3 Hours) Cork Institute of Technology Bachelor of Science (Honours) in Electrical Power Systems - Award Instructions Answer FIVE questions. (EELPS_8_Y4) Autumn 2008 Electrical Energy Systems (Time: 3 Hours) Examiners:

More information

The calculation of short-circuit current in the electrical design of traction substation

The calculation of short-circuit current in the electrical design of traction substation Advances in Engineering Research (AER), volume 82 2016 International Conference on Engineering and Advanced Technology (ICEAT-16) The calculation of short-circuit current in the electrical design of traction

More information

VI 3 - i TABLE OF CONTENTS

VI 3 - i TABLE OF CONTENTS VI 3 - i TABLE OF CONTENTS 3 PROJECT SPECIFIC DATA... 1 3.1 DEFINITIONS... 1 3.1.1 Design Data, High and Medium Voltage... 1 3.1.2 Design Data, Low Voltage Equipment... 2 3.1.3 Phase Relationship... 3

More information

UNIVERSITY OF SWAZILAND

UNIVERSITY OF SWAZILAND UNVERSTY OF SWAZLAND SUPPLEMENTARY EXAMNATON, SECOND SEMESTER MAY 2017 FACULTY OF SCENCE AND ENGNEERNG DEPARTMENT OF ELECTRCAL AND ELECTRONC ENGNEERNG TTLE OF PAPER: Switchgear and Protection COURSE CODE

More information

Case Study 1. Power System Planning and Design: Power Plant, Transmission Lines, and Substations

Case Study 1. Power System Planning and Design: Power Plant, Transmission Lines, and Substations Case Study 1 Power System Planning and Design: Power Plant, Transmission Lines, and Substations Lindsay Thompson, 5203120 Presented to Riadh Habash ELG 4125 11/10/2013 1.0 ABSTRACT A power plant delivers

More information

Roll No. :... Invigilator s Signature :.. CS/B.TECH(EE)/SEM-5/EE-502/ POWER SYSTEM-I. Time Allotted : 3 Hours Full Marks : 70

Roll No. :... Invigilator s Signature :.. CS/B.TECH(EE)/SEM-5/EE-502/ POWER SYSTEM-I. Time Allotted : 3 Hours Full Marks : 70 Name : Roll No. :.... Invigilator s Signature :.. CS/B.TECH(EE)/SEM-5/EE-502/2011-12 2011 POWER SYSTEM-I Time Allotted : 3 Hours Full Marks : 70 The figures in the margin indicate full marks. Candidates

More information

R10. IV B.Tech I Semester Regular/Supplementary Examinations, Nov/Dec SWITCH GEAR AND PROTECTION. (Electrical and Electronics Engineering)

R10. IV B.Tech I Semester Regular/Supplementary Examinations, Nov/Dec SWITCH GEAR AND PROTECTION. (Electrical and Electronics Engineering) R10 Set No. 1 Code No: R41023 1. a) Explain how arc is initiated and sustained in a circuit breaker when the CB controls separates. b) The following data refers to a 3-phase, 50 Hz generator: emf between

More information

QUESTIONNAIRE for Wind Farm Power Stations only

QUESTIONNAIRE for Wind Farm Power Stations only TRANSMISSION SYSTEM OPERATOR QUESTIONNAIRE for Wind Farm Power Stations only To be submitted by the Generation Licensees together with the Application for Connection Certificate according to IEC 61400-21

More information

MV network design & devices selection EXERCISE BOOK

MV network design & devices selection EXERCISE BOOK MV network design & devices selection EXERCISE BOOK EXERCISES 01 - MV substation architectures 02 - MV substation architectures 03 - Industrial C13-200 MV substation 04 - Max. distance between surge arrester

More information

Adaptive Relaying of Radial Distribution system with Distributed Generation

Adaptive Relaying of Radial Distribution system with Distributed Generation Adaptive Relaying of Radial Distribution system with Distributed Generation K.Vijetha M,Tech (Power Systems Engineering) National Institute of Technology-Warangal Warangal, INDIA. Email: vijetha258@gmail.com

More information

Voltage Sag Index Calculation Using an Electromagnetic Transients Program

Voltage Sag Index Calculation Using an Electromagnetic Transients Program International Conference on Power Systems Transients IPST 3 in New Orleans, USA Voltage Sag Index Calculation Using an Electromagnetic Transients Program Juan A. Martinez-Velasco, Jacinto Martin-Arnedo

More information

Notes 1: Introduction to Distribution Systems

Notes 1: Introduction to Distribution Systems Notes 1: Introduction to Distribution Systems 1.0 Introduction Power systems are comprised of 3 basic electrical subsystems. Generation subsystem Transmission subsystem Distribution subsystem The subtransmission

More information

The Analysis Results of Lightning Overvoltages by EMTP for Lightning Protection Design of 500 kv Substation

The Analysis Results of Lightning Overvoltages by EMTP for Lightning Protection Design of 500 kv Substation The Analysis Results of Lightning Overvoltages by EMTP for Lightning Protection Design of 500 kv Substation J. W. Woo, J. S. Kwak, H. J. Ju, H. H. Lee, J. D. Moon Abstract--To meet increasing power demand,

More information

INVESTIGATION OF ENERGY LOSS IN A TRANSMISSION SUBSTATION USING ONITSHA 330/132KV AS A CASE STUDY F.O. Enemuoh, T.L. Alumona and C.H.

INVESTIGATION OF ENERGY LOSS IN A TRANSMISSION SUBSTATION USING ONITSHA 330/132KV AS A CASE STUDY F.O. Enemuoh, T.L. Alumona and C.H. INVESTIGATION OF ENERGY LOSS IN A TRANSMISSION SUBSTATION USING ONITSHA 330/132KV AS A CASE STUDY F.O. Enemuoh, T.L. Alumona and C.H. Aliche 1,2 nnamdi azikiwe university, awka, anambra state, nigeria.

More information

The Study of Medium Voltage Source Change Effect to Voltage Sag in Low Voltage Customer in Distribution System

The Study of Medium Voltage Source Change Effect to Voltage Sag in Low Voltage Customer in Distribution System The Study of Medium Voltage Source Change Effect to Voltage Sag in Low Voltage Customer in Distribution System NAT SONGKRAM Power Quality Section Provincial Electricity Authority Provincial Electricity

More information

CONTENTS. 1. Introduction Generating Stations 9 40

CONTENTS. 1. Introduction Generating Stations 9 40 CONTENTS 1. Introduction 1 8 Importance of Electrical Energy Generation of Electrical Energy Sources of Energy Comparison of Energy Sources Units of Energy Relationship among Energy Units Efficiency Calorific

More information

{40C54206-A3BA D8-8D8CF }

{40C54206-A3BA D8-8D8CF } Informative Annex D Incident Energy and Arc Flash Boundary Calculation Methods This informative annex is not a part of the requirements of this NFPA document but is included for informational purposes

More information

System grounding of wind farm medium voltage cable grids

System grounding of wind farm medium voltage cable grids Downloaded from orbit.dtu.dk on: Apr 23, 2018 System grounding of wind farm medium voltage cable grids Hansen, Peter; Østergaard, Jacob; Christiansen, Jan S. Published in: NWPC 2007 Publication date: 2007

More information

Summary of Relaying Reviews Reporting

Summary of Relaying Reviews Reporting Revised Attachment B (Agenda Item 6) Summary of Relaying Reviews -- 12-31-04 Reporting This form shall be used without modification to provide a summary of relaying reviews performed by each Transmisission

More information

Session Four: Practical Insulation Co-ordination for Lightning Induced Overvoltages

Session Four: Practical Insulation Co-ordination for Lightning Induced Overvoltages Session Four: ractical Insulation Co-ordination Session Four: ractical Insulation Co-ordination for Lightning Induced Overvoltages Jason Mayer Technical Director, Energy Services, Aurecon Introduction

More information

Need for grounding Codes and Standards for grounding Wind Turbine Generator grounding design Foundation + Horizontal Electrode grounding design

Need for grounding Codes and Standards for grounding Wind Turbine Generator grounding design Foundation + Horizontal Electrode grounding design IEEE PES Transmission and Distribution Conference 2008 Panel Session Large Wind Plant Collector Design Wind Farm Collector System Grounding by Steven W. Saylors, P.E. Chief Electrical Engineer Vestas Americas

More information

POWER SYSTEM ANALYSIS TADP 641 SETTING EXAMPLE FOR OVERCURRENT RELAYS

POWER SYSTEM ANALYSIS TADP 641 SETTING EXAMPLE FOR OVERCURRENT RELAYS POWER SYSTEM ANALYSIS TADP 641 SETTING EXAMPLE FOR OVERCURRENT RELAYS Juan Manuel Gers, PhD Example - Single Line Example 1 - Data Calculate the following: 1. The three phase short circuit levels on busbars

More information

THE ELECTRICAL CHARACTERISTICS OF LONG

THE ELECTRICAL CHARACTERISTICS OF LONG Active and Passive Elec. Comp.. 1990, Vol. 14, pp. 17-23 Reprints available directly from the publisher Photocopying permitted by license only (C) 1990 Gordon and Breach Science Publishers, Inc. Printed

More information

ELEC Transmission i and

ELEC Transmission i and ELEC-1104 Lecture 5: Transmission i and Distribution ib ti Power System Layout Transmission and Distribution The transmission system is to transmit a large amount of energy from the power stations s to

More information

Protective earthing, protective conductor and automatic disconnection in case of a fault (Fault protection)

Protective earthing, protective conductor and automatic disconnection in case of a fault (Fault protection) Protective earthing, protective conductor and automatic disconnection in case of a fault (Fault protection) FIGURE 1.2 Fig.1 Earth fault loop path. Figure 1 shows the earth fault system which provides

More information

Module 10. Initiation Code RELIABILITY ACCOUNTABILITY

Module 10. Initiation Code RELIABILITY ACCOUNTABILITY Module 10 Initiation Code 1 M10 Initiation Code This is not the Initiating cause code The Outage Initiation Codes describe where an Automatic Outage was initiated on the power system. Element-Initiated

More information

Constant Terminal Voltage. Working Group Meeting 4 19 th September 2014

Constant Terminal Voltage. Working Group Meeting 4 19 th September 2014 Constant Terminal Voltage Working Group Meeting 4 19 th September 014 Overview Options summary System under investigation Options analysis Discussion Options Option 1 Constant Terminal Voltage controlled

More information

Design of SVPWM Based Inverter for Mitigation of Harmonics in Power System

Design of SVPWM Based Inverter for Mitigation of Harmonics in Power System Design of SVPWM Based Inverter for Mitigation of Harmonics in Power System 1 Leena N C, 2 B. Rajesh Kamath, 3 Shri Harsha 1,2,3 Department of EEE, Sri Siddhartha Institute of Technology, Tumkur-572105,

More information

ARC FLASH PPE GUIDELINES FOR INDUSTRIAL POWER SYSTEMS

ARC FLASH PPE GUIDELINES FOR INDUSTRIAL POWER SYSTEMS The Electrical Power Engineers Qual-Tech Engineers, Inc. 201 Johnson Road Building #1 Suite 203 Houston, PA 15342-1300 Phone 724-873-9275 Fax 724-873-8910 www.qualtecheng.com ARC FLASH PPE GUIDELINES FOR

More information

Collection of standards in electronic format (PDF) 1. Copyright

Collection of standards in electronic format (PDF) 1. Copyright Collection of standards in electronic format (PDF) 1. Copyright This standard is available to staff members of companies that have subscribed to the complete collection of SANS standards in accordance

More information

Transient Recovery Voltage (TRV) and Rate of Rise of Recovery Voltage (RRRV) of Line Circuit Breakers in Over Compensated Transmission Lines

Transient Recovery Voltage (TRV) and Rate of Rise of Recovery Voltage (RRRV) of Line Circuit Breakers in Over Compensated Transmission Lines Transient Recovery Voltage (TRV) and Rate of Rise of Recovery Voltage (RRRV) of Line Circuit Breakers in Over Compensated Transmission Lines Presenter Mark McVey C4/B5.41 INTERNATIONAL COUNCIL ON LARGE

More information

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System Company Directive STANDARD TECHNIQUE: SD7F/2 Determination of Short Circuit Duty for Switchgear on the WPD Distribution System Policy Summary This document provides guidance on calculation of fault levels

More information

EMC Philosophy applied to Design the Grounding Systems for Gas Insulation Switchgear (GIS) Indoor Substation

EMC Philosophy applied to Design the Grounding Systems for Gas Insulation Switchgear (GIS) Indoor Substation EMC Philosophy applied to Design the Grounding Systems for Gas Insulation Switchgear (GIS) Indoor Substation Marcos Telló Department of Electrical Engineering Pontifical Catholic University of Rio Grande

More information

PRACTICAL PROBLEMS WITH SUBSTATION EARTHING

PRACTICAL PROBLEMS WITH SUBSTATION EARTHING 1 PRACTICAL PROBLEMS WITH SUBSTATION EARTHING Dr Hendri Geldenhuys Craig Clark Eskom Distribution Technology This paper considers the issues around substation sites where the soil resistivity is of particularly

More information

LIGHTNING OVERVOLTAGES AND THE QUALITY OF SUPPLY: A CASE STUDY OF A SUBSTATION

LIGHTNING OVERVOLTAGES AND THE QUALITY OF SUPPLY: A CASE STUDY OF A SUBSTATION LIGHTNING OVERVOLTAGES AND THE QUALITY OF SUPPLY: A CASE STUDY OF A SUBSTATION Andreas SUMPER sumper@citcea.upc.es Antoni SUDRIÀ sudria@citcea.upc.es Samuel GALCERAN galceran@citcea.upc.es Joan RULL rull@citcea.upc.es

More information

Generation Interconnection Study Data Sheet Synchronous Machines

Generation Interconnection Study Data Sheet Synchronous Machines FOR INTERNAL USE ONLY GTC Project Number: Queue Date: Generation Interconnection Study Data Sheet Synchronous Machines Customers must provide the following information in its entirety. GTC will not proceed

More information

Lab 1. Objectives. Single Line Diagram. Methodology. Observations. Jon Jawnsy Yu 26 October 2009

Lab 1. Objectives. Single Line Diagram. Methodology. Observations. Jon Jawnsy Yu 26 October 2009 Lab 1 Objectives In this lab, our objective is to simulate a simple single machine infinite bus configuration using the PowerWorld Simulator software. We design a local generator system (a synchronous

More information

INCENTIVE FOR TRANSMISSION EFFICIENCY

INCENTIVE FOR TRANSMISSION EFFICIENCY INCENTIVE FOR TRANSMISSION EFFICIENCY - T. UMESH, SEE, RETD. KPTCL - & - N. RAGHUPRAKASH, EE, RA, KPTCL IN THIS SESSION Brief introduction to Transmission System Efficiency Parameters in Transmission Activity

More information

EE 340 Transmission Lines. Spring 2012

EE 340 Transmission Lines. Spring 2012 EE 340 Transmission Lines Spring 2012 Physical Characteristics Overhead lines An overhead transmission line usually consists of three conductors or bundles of conductors containing the three phases of

More information

Conventional Paper-II-2013

Conventional Paper-II-2013 1. All parts carry equal marks Conventional Paper-II-013 (a) (d) A 0V DC shunt motor takes 0A at full load running at 500 rpm. The armature resistance is 0.4Ω and shunt field resistance of 176Ω. The machine

More information

Transmission Lines and Feeders Protection Pilot wire differential relays (Device 87L) Distance protection

Transmission Lines and Feeders Protection Pilot wire differential relays (Device 87L) Distance protection Transmission Lines and Feeders Protection Pilot wire differential relays (Device 87L) Distance protection 133 1. Pilot wire differential relays (Device 87L) The pilot wire differential relay is a high-speed

More information

Simulations of open phase conditions on the high voltage side of YNd05-power plant transformers

Simulations of open phase conditions on the high voltage side of YNd05-power plant transformers Simulations of open phase conditions on the high voltage side of YNd05-power plant transformers Disclaimer: All information presented in the report, the results and the related computer program, data,

More information

UBC Technical Guidelines Section Edition Medium-Voltage Transformers Page 1 of 5

UBC Technical Guidelines Section Edition Medium-Voltage Transformers Page 1 of 5 Page 1 of 5 1.0 GENERAL 1.1 Coordination Requirements.1 UBC Energy & Water Services.2 UBC Building Operations 1.2 Description.1 UBC requirements for Substation Transformers. 2.0 MATERIAL AND DESIGN REQUIREMENTS

More information

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: IDAHO POWER COMPANY Designated Contact Person: Jeremiah Creason Address: 1221 W. Idaho Street, Boise ID 83702 Telephone

More information

Functional Specification Revision History

Functional Specification Revision History Functional Specification Revision History Revision Description of Revision By Date V1D1 For Comments Yaoyu Huang October 27, 2016 V1 For Issuance Yaoyu Huang November 21, 2016 Section 5.3 updated Transformer

More information

PRELIMINARIES. Generators and loads are connected together through transmission lines transporting electric power from one place to another.

PRELIMINARIES. Generators and loads are connected together through transmission lines transporting electric power from one place to another. TRANSMISSION LINES PRELIMINARIES Generators and loads are connected together through transmission lines transporting electric power from one place to another. Transmission line must, therefore, take power

More information

ISLANDING DETECTION FOR DISTRIBUTED GENERATION SYSTEM USING VARIOUS METHODS

ISLANDING DETECTION FOR DISTRIBUTED GENERATION SYSTEM USING VARIOUS METHODS ISLANDING DETECTION FOR DISTRIBUTED GENERATION SYSTEM USING VARIOUS METHODS *Megha Patel, **Dr. B. R. Parekh, ***Mr. Keval Velani * Student, Department of Electrical Engineering (Electrical power system),

More information

Reduction in Load (Copper) loss Due to Overhauling of Power Transformer or OLTC

Reduction in Load (Copper) loss Due to Overhauling of Power Transformer or OLTC Reduction in Load (Copper) loss Due to Overhauling of Power Transformer or OLTC by Neeraj Khare BSES RAJDHANI POWER LTD. Neeraj.khare@relianceada.com, Khareneeraj974@gmail.com, BSES Rajdhani Power Limited

More information

1. general. 1.1 methodology and definitions. methodology

1. general. 1.1 methodology and definitions. methodology 1. general 1.1 methodology and definitions component parts of an electric circuit and its protection are determined such, that all normal and abnormal operating constraints are satisfied. methodology Following

More information

Group F : Sl. No. - 1) 33/0.403 KV, 100 KVA Station Transformer GUARANTEED & OTHER TECHNICAL PARTICULARS. Table : A

Group F : Sl. No. - 1) 33/0.403 KV, 100 KVA Station Transformer GUARANTEED & OTHER TECHNICAL PARTICULARS. Table : A Group F : No. - 1) 33/0.403 KV, 100 KVA Station Transformer GUARANTEED & OTHER TECHNICAL PARTICULARS Table : A No. Description 1. Make & Manufacturer 2. Place of Manufacturer 3. Voltage Ratio 4. Rating

More information

Line Loadability in Indian Perspective

Line Loadability in Indian Perspective Line Loadability in Indian Perspective P.Pentayya, U.K Verma, P. Mukhopadhyay, Gopal Mitra, GM (WRLDC) GM (ERLDC) AGM (ERLDC) DGM (ERLDC) S.Bannerjee M.Thakur, S.Sahay CM (ERLDC Sr.Eng, (ERLDC) Eng, (ERLDC)

More information

Computer Aided Analysis and Design of EHV-AC Transmission line

Computer Aided Analysis and Design of EHV-AC Transmission line Computer Aided Analysis and Design of EHV-AC Transmission line 1 Mr. Parth R. Mishra, 2 Mrs. Dharmishta Makwana 1 Student, 2 Assistant Professor Department of electrical engineering, Kalol institute of

More information

High voltage engineering

High voltage engineering High voltage engineering Overvoltages power frequency switching surges lightning surges Overvoltage protection earth wires spark gaps surge arresters Insulation coordination Overvoltages power frequency

More information

Tab 2 Voltage Stresses Switching Transients

Tab 2 Voltage Stresses Switching Transients Tab 2 Voltage Stresses Switching Transients Distribution System Engineering Course Unit 10 2017 Industry, Inc. All rights reserved. Transient Overvoltages Decay with time, usually within one or two cycles

More information

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D Electricity Ten Year Statement November 2017 01 Electricity Ten Year Statement November 2017 001 Appendix D 1 Short-circuit currents 02 2 Short-circuit current terminology 04 3 Data requirements 07 4 Fault

More information

ETAP PowerStation 4.0

ETAP PowerStation 4.0 ETAP PowerStation 4.0 User Guide Copyright 2001 Operation Technology, Inc. All Rights Reserved This manual has copyrights by Operation Technology, Inc. All rights reserved. Under the copyright laws, this

More information