Session Four: Practical Insulation Co-ordination for Lightning Induced Overvoltages

Size: px
Start display at page:

Download "Session Four: Practical Insulation Co-ordination for Lightning Induced Overvoltages"

Transcription

1 Session Four: ractical Insulation Co-ordination Session Four: ractical Insulation Co-ordination for Lightning Induced Overvoltages Jason Mayer Technical Director, Energy Services, Aurecon Introduction This paper provides guidance on how to undertake insulation co-ordination simulations in high voltage systems, using time domain software. There are a number of methods used in industry to complete this task. Some are simplified approximations, others involve statistical analysis. This is just one method, but it is a practical means of assessing the level of protection afforded by surge arresters in high voltage systems, against lightning strokes to exposed conductors. The paper does not consider overvoltages from switching transients or other sources, although some of the principles presented could be used in this area. What is insulation co-ordination? For the purposes of this paper, insulation co-ordination is defined as the process of determining the appropriate placement and selection of surge arresters (or other surge protective devices), such that lightning induced overvoltages do not exceed the impulse withstand level (aka BIL) of installed equipment. When a lightning stroke hits an exposed conductor, large currents flow along the conductors, causing significant overvoltages. If the resulting overvoltages exceed the BIL of installed equipment, it is likely that damage to the insulation will occur. It is only likely because BIL is a statistical parameter. The BIL of insulation is defined as the voltage at which there is a 90% probability that the insulation will not flashover or fail. Insulation may fail at voltages lower than its BIL, or it might pass with voltages above its BIL. However in practical terms, we assess an insulation failure as an exceedence of the BIL value, and apply some statistical analysis to the probability of this failure occurring. This provides a reasonably objective assessment of the risk of failure. Case study system At this point it is useful to introduce a case study network, in order to understand what we are trying to achieve with an insulation co-ordination simulation. 203 Earthing, Lightning & Surge rotection IDC Technologies

2 Session Four: ractical Insulation Co-ordination Figure shows a typical 32 kv double circuit transmission line. Half way long this feeder, a simple 32/33 kv substation is established, with a single circuit tee connection into the substation. Within the substation a 32 kv busbar system connects the transmission line to a 5 MVA 32/33 kv transformer. The busbar is provided to allow future expansion of the substation to a conventional two transformer, two feeder substation. At this point there are only disconnectors, surge arresters, CVT and the busbar. It is assumed the CT s are in the transformer bushings. Transmission line 32 kv 33 kv Figure Case study network line diagram It is proposed that surge arresters be placed at the line entry to the substation, as well as on the transformer high voltage bushings. This is a conventional arrangement. The system is effectively earthed, so for earth faults, the healthy phases will not rise more than.4 pu. The maximum normal phase to phase voltage will not exceed 45 kv. Therefore the maximum phase to earth voltage occurring on a healthy phase during an earth fault is: Therefore 20 kv 3HSRE arresters are selected, with a maximum continuous operating voltage (MCOV) of 98 kv and a temporary overvoltage rating of 45 kv. They will not conduct during a 32 kv system earth fault. The time domain simulation is required to assess whether this particular combination of surge arresters and their location with respect to the transformer, is appropriate. 203 Earthing, Lightning & Surge rotection IDC Technologies 2

3 747_ 747_2 747_3 747_4 747_5 747_6 747_7 747_8 Dropper2 Downlead2 Downlead4 Downlead2 Downlead3 Downlead2 Downlead3 Downlead3 Downlead4 Downlead4 Bus_ A Bus_2 2.0E-3 [uf] 2.0E-3 [uf] Bus_2 Bus_2 C 2.0E-3 [uf] Bus_3 Downlead Downlead Downlead Session Four: ractical Insulation Co-ordination Time domain models In order to undertake a time domain simulation it is necessary to understand how to model each component in the system. Insulation co-ordination models differ greatly from conventional power frequency power system models used for load flow and fault analysis. These time domain models must deal with travelling waves and therefore must be accurate at a wide range of frequencies, not at 50 Hz. SCAD/EMTDC software is a typical software package that can be used to determine lightning surge overvoltages. EMTDC is an electro-magnetic transient program which can represent and solve the differential equations of electromagnetic and electromechanical systems in the time domain. The solutions are calculated based on a fixed time step. The software also allows for the creation and analysis of control systems independent or in conjunction with the electromagnetic or electromechanical systems. This type of software allows the complex interactions between components to be included and the frequency dependent characteristics of components to be modelled. This is where it dramatically differs from conventional steady state load-flow and fault analysis software packages. EMTDC can be used for various specialised studies including fast front surge studies (lightning surge studies), including the modelling of non-linear metal oxide surge arresters. SCAD is a very powerful graphical front-end to EMTDC which has single line diagram capability and a very easy to use interface to the EMTDC component models. There are other software packages such as AT and EMT-RV that can also be used for this type of study. The model Figure 2 shows a completed model for this case study. Isurge 747_ 747_ 747_2 747_2 747_3 747_3 747_4 747_4 747_5 747_5 747_6 747_6 747_7 747_7 747_8 747_8 A C Transmission Line A Dropper2 Dropper2 Bus_ Bus_ C Bus_3 Bus_3 3.2E-3 [uf] 3.2E-3 [uf] 32/33kV 5 MVA Transformer 3.2E-3 [uf] Droppers into substation VdiscAVdiscBVdiscC CVT VtrfA VtrfB VtrfC 20 kv Arrester 20 kv Arrester 3HSRE 3HSRE 20 kv Arrester 20 kv Arrester 3HSRE 3HSRE 20 kv Arrester 3HSRE 20 kv Arrester 3HSRE Substation.0 [ohm] Substation Earth Figure 2 Case study SCAD model 203 Earthing, Lightning & Surge rotection IDC Technologies 3

4 Downlead2 Downlead3 Downlead4 Downlead Downlead2 Downlead3 Downlead4 Downlead 2.0E-3 [uf] 2.0E-3 [uf] 2.0E-3 [uf] A C Bus_2 Bus_2 Session Four: ractical Insulation Co-ordination The transmission line can be seen, along with the tee connection into the substation and the various components in the substation. Figure 3 shows the substation part of the model in more detail. A C Busbars Transformer Bus_2 A Dropper2 Dropper2 Dropper2 Bus_ Bus_ Bus_ C Bus_3 Bus_3 Bus_3 3.2E-3 [uf] 3.2E-3 [uf] 32/33kV 5 MVA Transformer 3.2E-3 [uf] VtrfA VtrfB VtrfC VdiscAVdiscBVdiscC CVT Droppers 20 kv Arrester 3HSRE CVT 20 kv Arrester 3HSRE 20 kv Arrester 20 kv Arrester 3HSRE 3HSRE 20 kv Arrester 3HSRE Surge arresters and down leads to earth 20 kv Arrester 3HSRE Substation earth Downlea... Downlea... Downlea... Downlea... Substation Earth.0 [ohm] Figure 3 Case study SCAD model Transmission line conductors The transmission line conductors need to be modeled with a surge impedance and a travel time, not a conventional impedance. This is because the stroke currents and associate surge voltages are actually travelling waves that move along the conductors and split and reflect from points of different surge impedance. This creates numerous travelling waves back and forth, which summate or subtract as they meet. When such travelling waves summate at a junction or line end, this can cause significant overvoltages. In time domain software such as SCAD/EMTDC, the transmission line is modelled using a frequency dependent travelling wave model with the frequency fitting curve from 00 Hz to 000 MHz with the steady state frequency set to MHz. The transmission lines models are constructed using conductor data and line geometry information. To demonstrate how a conductor responds to a lightning stroke, Figure 4 shows the voltages at the stroke location (blue) and the end of the conductor (green), for a 6 ka stroke current injected km from the end of a 2km long line (which is open ended). The opposite end of the line is far enough away to not 203 Earthing, Lightning & Surge rotection IDC Technologies 4

5 Surge Voltage (kv) Session Four: ractical Insulation Co-ordination influence the results (ie it is 20km away no reflections come back from the other end in the time frame considered). The surge current travels at slightly less than the speed of light (approx 300m per us). The surge impedance of a typical transmission line conductor is generally between 400 and 500 ohms. A surge current 6 ka in this example, results in a surge voltage of approximately.5 MV shortly after the application of the current. It can be seen that approximately 3.3 us after the initial strike, a surge voltage appears at the end of the line (000m at 300m/us), but because the line is open, the surge reflects back on itself, causing a doubling of the voltage. The reflected surge then travels back to the strike location. Therefore at 6.6 us after the initial strike the voltage at the strike location is still high due to surge current still being injected, however the returning surge from the end arrives and causes almost a doubling in voltage. This assumes a conductor in air, with no flashover of insulators, so the surge current will reflect back and forth until it eventually attenuates. 3.5k 3.0k 2.5k Stroke Main : Surge Voltages - o Tow er Models End 2.0k.5k.0k 0.5k k -.0k Time m 0.020m 0.030m 0.040m 0.050m 0.060m Figure 4 Surge voltages on a conductor In a cable the situation is very similar, except that the surge impedance of a cable is closer to 30 ohms and the travel time is approximately ⅓ of the speed of light. This is because surge impedance is calculated using the inductance (L) and capacitance (C) of the conductor or cable. An overhead line tends to have higher L and lower C, where a cable has lower L and higher C. Transmission line towers The transmission line model needs to include back flashover models of the transmission towers and insulators. It also needs the tower structure and 203 Earthing, Lightning & Surge rotection IDC Technologies 5

6 Session Four: ractical Insulation Co-ordination earthing of the overhead earthwire included. The purpose of an overhead earthwire is to minimise the number of lightning strokes that terminate on the phase conductors. When a lightning stroke hits an overhead earthwire, the voltages on the struck conductor and tower top build up very quickly and if the insulation strength of the air gap between conductors or of the insulator/crossarm combination is exceeded, a flashover will occur and the surge current will propagate into the phase conductors. This event is called a back flashover. This effect is included in the model by creating flashover switches which measure the phase to tower voltages and determine the strength of the air gap. The insulation strength of the air is modelled using the time dependent characteristics described in [2]. The time dependent characteristics are shown in Figure 5. The air gap strength drops with respect to time in microseconds after the surge arrives at the insulator. The lower value of insulation strength reflects a higher probability of back flashover to the phase conductors. Figure 5 Insulator strength characteristics [2] Figure 6 shows the tower model from the SCAD file for the case study. ote that the mast footing resistance is modelled using a variable resistance that takes the soil ionisation into account when the surge current dissipates into the soil via the mast, as described in []. The masts are modelled as travelling wave models with a surge impedance and a propagation velocity as described in [] and some other related references. 203 Earthing, Lightning & Surge rotection IDC Technologies 6

7 Rt + BRKC + StringCap BRKB + StringCap BRKA + StringCap Session Four: ractical Insulation Co-ordination G2 G Overhead earthwire connections Th + StringCap TH2 A2 B2 C2 BRKA2 BRKB2 BRKC2 Th3 Th4 A B C StringCap StringCap + + Conductor connections Travelling wave tower segment models Footing resistance Tower Footing Resistance Figure 6 Typical 32 kv transmission tower geometry 203 Earthing, Lightning & Surge rotection IDC Technologies 7

8 Surge Voltage (kv) Session Four: ractical Insulation Co-ordination The tower models are added to the transmission line conductor models. Comparing Figure 4 to that of Figure 7 below, the effect of the tower model can be seen. The same current is injected into the earthwire of a transmission line km from the open end. The surge voltages are significantly lower because the current can split and travel down the towers to earth. otice that the waveforms are heavily distorted. This is because of the numerous reflections that occur between the conductor, towers, earth, and the end of the line. In this particular graph there is no insulator flashover, because the surge current to the earthwire is only 6 ka. 300 Stroke Main : Surge Voltages - With Tow er Models End Time m 0.020m 0.030m 0.040m 0.050m 0.060m Figure 7 Surge voltages on a conductor with towers modelled Surge arresters Surge arresters are modelled as non-linear elements using SCAD s metal oxide surge arrester component along with R, L and C components in line with the IEEE fast front arrester model described in [3]. Refer to Figure 8 for details. The surge arrester models are tested with various stroke currents and matched to the residual voltage values in the manufacturers datasheets. The surge arresters are modelled with downleads to the earth grid. The downleads are modelled as travelling wave models with a surge impedance and a propagation velocity as described in []. 203 Earthing, Lightning & Surge rotection IDC Technologies 8

9 Session Four: ractical Insulation Co-ordination Surge Arrester: 20 kv 3HSRE (D is length in metres) D =.428 metres R0(ohms)=00.D L0(uH)=0.2*D 42.8 [ohm].285e-6 [H] R(ohms)=65.D L(uH)=5*D 92.8 [ohm] 2.4E-6 [H] 70E-6 [uf] A0 A C(pF)=00/D Figure 8 Fast front surge arrester model Transformers Under lightning conditions the transformers act as surge capacitances. Hence for modelling purposes, transformers are represented by the winding surge capacitance between each phase and earth. The transformer surge capacitances are determined by the transformer size in MVA and the transformer BIL rating as described in []. The transformer BIL rating for the case study is assumed to be 650 kv, which is typical for 32 kv systems. Voltage transformers and other equipment Under lightning conditions the other equipment in the substation such as disconnector insulators, CVT s station post insulators etc, act as surge capacitances. Hence for modelling purposes, they are represented by surge capacitance between each phase and earth. Typical surge capacitances are described in [5]. Lightning surges Extensive study of lightning surge behaviour has been undertaken over many years by various international bodies, such as the IEEE and CIGRE. Lightning strokes are most basically described in terms of two values, crest current and front steepness. The crest current is the maximum current value that the stroke achieves (measured in ka). Front steepness is essentially how quickly the stroke current reaches the crest current (measured in ka/us). Strictly speaking front steepness is the time taken for the stroke current to rise from 0% to 90% of the crest current. The stroke current and front steepness values can vary and follow a probability function. According to [] the CIGRE probability data is considered to be superior to other data. 203 Earthing, Lightning & Surge rotection IDC Technologies 9

10 robability Session Four: ractical Insulation Co-ordination The probability functions are of the form: I is the stroke current in ka or front steepness in ka/us, M is the median value of stroke current or front steepness and B is the log standard deviation of the stroke current or front steepness The CIGRE data suggests that the median value of stroke current crest is 34 ka and the log standard deviation is The median front steepness value is considered to be 24.3 ka/us with a log standard deviation of 0.6. The following graphs detail the crest current and front steepness probability functions based on the above data. robability of Lightning Stroke Current Crest Current (ka) Figure 9 robability of a particular stroke current occurrence 203 Earthing, Lightning & Surge rotection IDC Technologies 0

11 robability robability of Exceeding Abscissa (%) Session Four: ractical Insulation Co-ordination robability of Lightning Stroke Current Crest Current (ka) Figure 0 robability of a stroke current exceeding a particular value robability of Front Steepness Steepness (ka/us) Figure robability of a particular front steepness occurrence 203 Earthing, Lightning & Surge rotection IDC Technologies

12 robability of Exceeding Abscissa (%) Session Four: ractical Insulation Co-ordination robability of Front Steepness Steepness (ka/us) Figure 2 robability of front steepness exceeding a particular value Therefore a range of stroke current combinations needs to be selected to enable software simulation of case scenarios. Based on this data and various other sources [4], it can be established that larger crest currents tend to have slower front times than lower crest currents. The commonly used values that Aurecon uses for insulation coordination are as follows: 30 ka.2/50 us (high probability crest value with fast front time) 70 ka 4.5/50 us (% probability of exceedence crest value with slower front time) These two stroke current combinations represent both a high probability stroke event and a worst possible case (hence low probability) stroke event. This is considered an acceptable methodology to assess scenarios. Both of these values are used to simulate strokes to overhead earthwires and unshielded phase conductors. Strokes to shielded phase conductors are discussed in the following section. Shielding failures Some shielding failures are expected to occur as it is not possible to prevent all lightning strokes from reaching the phase conductors, unless the phase conductors are completely surrounded by earthwires. Shielding failure currents are calculated based on Eriksson s modified model as stated in []. Figure 3 shows the input to Eriksson s method graphically. 203 Earthing, Lightning & Surge rotection IDC Technologies 2

13 Session Four: ractical Insulation Co-ordination Earthwire b c Rs h a Rc hase conductor y Figure 3 Shielding failure calculation inputs Depending on the transmission line design, the shielding failure current is typically between 6 ka and 0 ka. This means a stroke of 0 ka or less can terminate on the phase conductor as the earthwire fails to provide protection. Scenarios and results The following simulations were undertaken on the case study model: 70 ka stroke to the earthwire at the nearest tower 30 ka stroke to the earthwire at the nearest tower 6 ka shielding failure to the A phase conductor at the nearest tower The results show the overvoltages at the line entry to the substation and at the transformer terminals. It would be beneficial to check other locations within the substation also, such as locations distant from the surge arresters. In order to keep this paper as short as possible, only the above results are shown. It is necessary to add the peak of the 50 Hz voltage waveform to these values to ensure that if the stroke occurs at the peak of the voltage waveform, the BIL is still not exceeded. This is 08 kv for a 32 kv system. This is not an exhaustive list of scenarios and others should be considered, such as mid span strokes, strokes at more distant towers, strokes to the busbar due to shielding failure. The intention is to determine the worst case scenarios to determine if they cause an exceedence of the BIL. 203 Earthing, Lightning & Surge rotection IDC Technologies 3

14 (kv) (kv) Session Four: ractical Insulation Co-ordination 300 Main : Disconnector and Transformer Voltages VdiscA VdiscB VdiscC VtrfA VtrfB VtrfC m 0.020m 0.030m 0.040m 0.050m 0.060m 0.070m 0.080m Figure 4 70 ka stroke to earthwire In Figure 4 it can be seen that a back flashover occurs on A phase, but the overvoltage stays under 300 kv. Allowing for 08 kv power frequency voltage on top of this still gives quite some margin to the 650 kv BIL of the transformer insulation. 300 Main : Disconnector and Transformer Voltages VdiscA VdiscB VdiscC VtrfA VtrfB VtrfC m 0.020m 0.030m 0.040m 0.050m 0.060m 0.070m 0.080m 0.090m 0.00m 0.0m Figure 5 30 ka stroke to earthwire In Figure 5, there is no back flashover of the insulators on the tower and therefore the earthwire is very effective at providing protection of the phase conductors. There is some minor surge overvoltage noticeable due to induction and capacitive coupling between the conductors. 203 Earthing, Lightning & Surge rotection IDC Technologies 4

15 (kv) Session Four: ractical Insulation Co-ordination 350 Main : Disconnector and Transformer Voltages VdiscA VdiscB VdiscC VtrfA VtrfB VtrfC m 0.020m 0.030m 0.040m 0.050m 0.060m 0.070m 0.080m Figure 6 6 ka shielding failure stroke to the A phase conductor In Figure 6 a direct stroke to the phase conductor causes the highest overvoltage. However even allowing the 08 kv power frequency voltage on top of this, gives a margin to the 650 kv BIL. Therefore, the surge protection is effective at protecting against the scenarios considered. In this particular case study, lightning strokes to the transmission line twin earthwires can split five ways and disperse readily without causing back flashovers except in the worst case stroke currents. Other designs can perform quite differently, such as single circuit dedicated radial lines to a substation. Generally at high voltage substations (32 kv and above) surge protection against lightning strokes is quite effective. At lower voltages (33 kv and below) surge protection can be quite challenging because of the much lower equipment BIL ratings. Lightning is probabilistic in nature and therefore it should be noted that the probability of seeing the calculated overvoltages is actually very small. It is outside the scope of this paper to describe the calculation process, but there are references [4] which show statistically what the ground flash density is at a particular location each year. The probability of a critical stroke scenario occurring can be calculated. The probability of this stroke current being above, the critical value within a particular distance of the substation can be estimated. This can then give an indicative probability of insulation failure per year, or a time between failures. This gives an indicative risk that can be assessed, in order to determine if additional surge protection is required. One other final point to note is that software packages such as SCAD can determine the arrester energy dissipation and this needs to be checked. If an arrester exceeds its energy dissipation rating during a lightning stroke it may fail. 203 Earthing, Lightning & Surge rotection IDC Technologies 5

16 Session Four: ractical Insulation Co-ordination References [] A. J. Hileman, Insulation Co-ordination for ower Systems, Marcel Dekker Inc, 999 [2] IEEE Std 998 Guide for Direct Stroke Shielding of Substations [3] IEEE Working Group 3.4., Modelling of Metal Oxide Surge Arresters IEEE Transactions on ower Delivery, Vol 7 o., January 992 [4] AS/ZS Lightning rotection, Standards Australia, 2003 [5] IEEE Std 37.0 IEEE Guide for Transient Recovery Voltage for AC High Voltage Circuit Breakers 203 Earthing, Lightning & Surge rotection IDC Technologies 6

Modeling insulation in high-voltage substations

Modeling insulation in high-voltage substations 38 ABB REVIEW DESIGNED FOR SAFETY DESIGNED FOR SAFETY Modeling insulation in high-voltage substations The goal of insulation coordination is to determine the dielectric strength of transformers and other

More information

PREVENTING FLASHOVER NEAR A SUBSTATION BY INSTALLING LINE SURGE ARRESTERS

PREVENTING FLASHOVER NEAR A SUBSTATION BY INSTALLING LINE SURGE ARRESTERS 29 th International Conference on Lightning Protection 23 rd 26 th June 2008 Uppsala, Sweden PREVENTING FLASHOVER NEAR A SUBSTATION BY INSTALLING LINE SURGE ARRESTERS Ivo Uglešić Viktor Milardić Božidar

More information

2000 Mathematics Subject Classification: 68Uxx/Subject Classification for Computer Science. 281, 242.2

2000 Mathematics Subject Classification: 68Uxx/Subject Classification for Computer Science. 281, 242.2 ACTA UNIVERSITATIS APULENSIS Special Issue SIMULATION OF LIGHTNING OVERVOLTAGES WITH ATP-EMTP AND PSCAD/EMTDC Violeta Chiş, Cristina Băla and Mihaela-Daciana Crăciun Abstract. Currently, several offline

More information

Analysis of lightning performance of 132KV transmission line by application of surge arresters

Analysis of lightning performance of 132KV transmission line by application of surge arresters Analysis of lightning performance of 132KV transmission line by application of surge arresters S. Mohajer yami *, A. Shayegani akmal, A.Mohseni, A.Majzoobi High Voltage Institute,Tehran University,Iran

More information

When surge arres t ers are installed close to a power transformer, overvoltage TRANSFORMER IN GRID ABSTRACT KEYWORDS

When surge arres t ers are installed close to a power transformer, overvoltage TRANSFORMER IN GRID ABSTRACT KEYWORDS TRANSFORMER IN GRID When surge arres t ers are installed close to a power transformer, they provide protection against lightning overvoltage ABSTRACT The aim of this research article is to determine the

More information

Utility System Lightning Protection

Utility System Lightning Protection Utility System Lightning Protection Many power quality problems stem from lightning. Not only can the high-voltage impulses damage load equipment, but the temporary fault that follows a lightning strike

More information

ABSTRACTS of SESSION 6

ABSTRACTS of SESSION 6 ABSTRACTS of SESSION 6 Paper n 1 Lightning protection of overhead 35 kv lines by antenna-module long flashover arresters Abstract: A long-flashover arrester (LFA) of a new antenna-module type is suggested

More information

B2-301 IMPROVING DOUBLE CIRCUIT TRANSMISSION LINE RELIABILITY THROUGH LIGHTNING DESIGN

B2-301 IMPROVING DOUBLE CIRCUIT TRANSMISSION LINE RELIABILITY THROUGH LIGHTNING DESIGN 21, rue d'artois, F-7008 Paris http://www.cigre.org B2-301 Session 200 CIGRÉ IMPROVING DOUBLE CIRCUIT TRANSMISSION LINE RELIABILITY THROUGH LIGHTNING DESIGN J. A. (TONY) GILLESPIE & GLENN STAPLETON Powerlink

More information

The Many Uses of Transmission Line Arresters

The Many Uses of Transmission Line Arresters Introduction It was not realized at the time, but the 1992 introduction of the polymer-housed transmission line arrester (TLA) was clearly a game changer in the practice of lightning protection of transmission

More information

Lightning performance of a HV/MV substation

Lightning performance of a HV/MV substation Lightning performance of a HV/MV substation MAHMUD TAINBA, LAMBOS EKONOMOU Department of Electrical and Electronic Engineering City University London Northampton Square, London EC1V HB United Kingdom emails:

More information

High voltage engineering

High voltage engineering High voltage engineering Overvoltages power frequency switching surges lightning surges Overvoltage protection earth wires spark gaps surge arresters Insulation coordination Overvoltages power frequency

More information

Substation Insulation Coordination Study

Substation Insulation Coordination Study [Type the document title] Substation nsulation Coordination Study MEG Energy Christina Lake Regional Project nsulation Coordination Schematic X0057 15km Lines TWR3 TWR2 TWR1 Afrm1 16 230k Source CCT 100

More information

Parameters Affecting the Back Flashover across the Overhead Transmission Line Insulator Caused by Lightning

Parameters Affecting the Back Flashover across the Overhead Transmission Line Insulator Caused by Lightning Proceedings of the 14 th International Middle East Power Systems Conference (MEPCON 10), Cairo University, Egypt, December 19-21, 2010, Paper ID 111. Parameters Affecting the Back Flashover across the

More information

ABSTRACT 1 INTRODUCTION

ABSTRACT 1 INTRODUCTION ELECTROMAGNETIC ANALYSIS OF WIND TURBINE GROUNDING SYSTEMS Maria Lorentzou*, Ian Cotton**, Nikos Hatziargyriou*, Nick Jenkins** * National Technical University of Athens, 42 Patission Street, 1682 Athens,

More information

ABSTRACT 1.0 INTRODUCTION LIST OF SYMBOLS

ABSTRACT 1.0 INTRODUCTION LIST OF SYMBOLS Lightning protection of pole-mounted transformers and its applications in Sri Lanka Prof. J R Lucas* and D A J Nanayakkara # *University of Moratuwa, # Lanka Transformers Limited ABSTRACT This paper presents

More information

Comparison between Different InstallationLocations of Surge Arresters at Transmission Line Using EMTP-RV

Comparison between Different InstallationLocations of Surge Arresters at Transmission Line Using EMTP-RV No. E-13-HVS-2308 Comparison between Different InstallationLocations of Surge Arresters at Transmission Line Using EMT-RV Soheil Derafshi Beigvand, Mohammad Morady Electrical Engineering Department, Engineering

More information

Power Quality and Reliablity Centre

Power Quality and Reliablity Centre Technical Note No. 8 April 2005 Power Quality and Reliablity Centre TRANSIENT OVERVOLTAGES ON THE ELECTRICITY SUPPLY NETWORK CLASSIFICATION, CAUSES AND PROPAGATION This Technical Note presents an overview

More information

LIGHTNING OVERVOLTAGES AND THE QUALITY OF SUPPLY: A CASE STUDY OF A SUBSTATION

LIGHTNING OVERVOLTAGES AND THE QUALITY OF SUPPLY: A CASE STUDY OF A SUBSTATION LIGHTNING OVERVOLTAGES AND THE QUALITY OF SUPPLY: A CASE STUDY OF A SUBSTATION Andreas SUMPER sumper@citcea.upc.es Antoni SUDRIÀ sudria@citcea.upc.es Samuel GALCERAN galceran@citcea.upc.es Joan RULL rull@citcea.upc.es

More information

Lightning overvoltage and protection of power substations

Lightning overvoltage and protection of power substations Lightning overvoltage and protection of power substations Mahmud Trainba 1, Christos A. Christodoulou 2, Vasiliki Vita 1,2, Lambros Ekonomou 1,2 1 Department of Electrical and Electronic Engineering, City,

More information

CHOICE OF MV FEEDER BIL TO MAXIMIZE QOS AND MINIMIZE EQUIPMENT FAILURE

CHOICE OF MV FEEDER BIL TO MAXIMIZE QOS AND MINIMIZE EQUIPMENT FAILURE CHOICE OF MV FEEDER BIL TO MAXIMIZE QOS AND MINIMIZE EQUIPMENT FAILURE Willem DIRKSE VAN SCHALKWYK ESKOM - South Africa vschalwj@eskom.co.za ABSTRACT A high BIL (300 kv) on a MV feeder ensures that no

More information

The relationship between operating maintenance and lightning overvoltage in distribution networks based on PSCAD/EMTDC

The relationship between operating maintenance and lightning overvoltage in distribution networks based on PSCAD/EMTDC The relationship between operating maintenance and lightning overvoltage in distribution networks based on PSCAD/EMTDC Xiaojun Chena *, Wenjie Zhengb, Shu Huangc, Hui Chend Electric Power Research Institute

More information

Insulation Co-ordination For HVDC Station

Insulation Co-ordination For HVDC Station Insulation Co-ordination For HVDC Station Insulation Co-ordination Definitions As per IEC 60071 Insulation Coordination is defined as selection of dielectric strength of equipment in relation to the operating

More information

TECHNICAL NOTE 2.0. Overvoltages origin and magnitudes Overvoltage protection

TECHNICAL NOTE 2.0. Overvoltages origin and magnitudes Overvoltage protection ECHNICAL NOE 2.0 Overvoltages origin and magnitudes Overvoltage protection he ECHNICAL NOES (N) are intended to be used in conjunction with the APPLICAION GIDELINES Overvoltage protection Metaloxide surge

More information

Computation of Lightning Impulse Backflashover Outages Rates on High Voltage Transmission Lines

Computation of Lightning Impulse Backflashover Outages Rates on High Voltage Transmission Lines www.ijape.org International Journal of Automation and Power Engineering (IJAPE) Volume Issue, January DOI:./ijape... omputation of Lightning Impulse Backflashover Outages Rates on High Voltage Transmission

More information

Calculation of Transient Overvoltages by using EMTP software in a 2-Phase 132KV GIS

Calculation of Transient Overvoltages by using EMTP software in a 2-Phase 132KV GIS Calculation of Transient Overvoltages by using EMTP software in a 2-Phase 132KV GIS M. Kondalu, Dr. P.S. Subramanyam Electrical & Electronics Engineering, JNT University. Hyderabad. Joginpally B.R. Engineering

More information

INSTALLATION OF LSA ON A 400 KV DOUBLE-CIRCUIT LINE IN RUSSIA

INSTALLATION OF LSA ON A 400 KV DOUBLE-CIRCUIT LINE IN RUSSIA Application of Line Surge Arresters in Power Distribution and Transmission Systems COLLOQUIUM Cavtat 2008 INSTALLATION OF LSA ON A 400 KV DOUBLE-CIRCUIT LINE IN RUSSIA L. STENSTRÖM 1), J. TAYLOR, N.T.

More information

Evaluating the Response of Surge Arresters

Evaluating the Response of Surge Arresters 1 Jens Schoene Chandra Pallem Tom McDermott Reigh Walling Evaluating the Response of Surge Arresters to Temporary Overvoltages Panel Session of the IEEE Wind and Solar Collector Design Working Group 2014

More information

Tab 2 Voltage Stresses Switching Transients

Tab 2 Voltage Stresses Switching Transients Tab 2 Voltage Stresses Switching Transients Distribution System Engineering Course Unit 10 2017 Industry, Inc. All rights reserved. Transient Overvoltages Decay with time, usually within one or two cycles

More information

Simulation and Analysis of Lightning on 345-kV Arrester Platform Ground-Leading Line Models

Simulation and Analysis of Lightning on 345-kV Arrester Platform Ground-Leading Line Models International Journal of Electrical & Computer Sciences IJECS-IJENS Vol:15 No:03 39 Simulation and Analysis of Lightning on 345-kV Arrester Platform Ground-Leading Line Models Shen-Wen Hsiao, Shen-Jen

More information

MODIFICATION OF THE ARRESTER ARRANGEMENT WHEN CONVERTING THE METHOD OF NEUTRAL TREATMENT

MODIFICATION OF THE ARRESTER ARRANGEMENT WHEN CONVERTING THE METHOD OF NEUTRAL TREATMENT MODIFICATION OF THE ARRESTER ARRANGEMENT WHEN CONVERTING THE METHOD OF NEUTRAL TREATMENT Claus NEUMANN Darmstadt University of Technology Germany claus.neumann@amprion.net Klaus WINTER Swedish Neutral

More information

In order to minimise distribution (11 and 22 kv) feeder breaker

In order to minimise distribution (11 and 22 kv) feeder breaker Lightning protection for equipment on MV feeders By WJD van Schalkwyk and M du Preez, Eskom This article presents the influence of lightning on MV feeders supplying small power users (400/230 V) with focus

More information

Transmission of Electrical Energy

Transmission of Electrical Energy Transmission of Electrical Energy Electrical energy is carries by conductors such as overhead transmission lines and underground cables. The conductors are usually aluminum cable steel reinforced (ACSR),

More information

Insulation Coordination Fundamentals Where Arrester and Insulator Characteristics Meet

Insulation Coordination Fundamentals Where Arrester and Insulator Characteristics Meet ArresterWorks Insulation Coordination Fundamentals Where Arrester and Insulator Characteristics Meet 6/23/2012 Jonathan Woodworth Transient overvoltages are a fact of life on power systems. Arresters can

More information

ArresterFacts 024. Separation Distance for Substations. ArresterFacts 024 Separation Distance for Substations. September 2014 Rev 7 Jonathan Woodworth

ArresterFacts 024. Separation Distance for Substations. ArresterFacts 024 Separation Distance for Substations. September 2014 Rev 7 Jonathan Woodworth ArresterWorks ArresterFacts 024 Separation Distance for Substations Separation Distance for Substations September 2014 Rev 7 Jonathan Woodworth ArresterFacts 024 Copyright ArresterWorks 2014 Page 1 for

More information

Lightning Overvoltage Performance of 110 kv Air-Insulated Substation

Lightning Overvoltage Performance of 110 kv Air-Insulated Substation Lightning Overvoltage Performance of 11 kv Air-Insulated Substation B. Filipović-Grčić, B. Franc, I. glešić, V. Milardić, A. Tokić Abstract--This paper presents the analysis of lightning overvoltage performance

More information

Tab 8 Surge Arresters

Tab 8 Surge Arresters s en em Tab 8 Surge Arresters Si Distribution System Engineering Course Unit 10 2017 Industry Inc., All Rights Reserved Surge Arresters The main protective devices against system transient overvoltages.

More information

A Case Study on Selection and Application of Lightning Arrester and Designing its Suitable Grounding Grid

A Case Study on Selection and Application of Lightning Arrester and Designing its Suitable Grounding Grid A Case Study on Selection and Application of Lightning Arrester and Designing its Suitable Grounding Grid 1 Arpan K. Rathod, 2 Chaitanya H. Madhekar Students Electrical Engineering, VJTI, Mumbai, India

More information

GIS Disconnector Switching Operation VFTO Study

GIS Disconnector Switching Operation VFTO Study GIS Disconnector Switching Operation VFTO Study Mariusz Stosur, Marcin Szewczyk, Wojciech Piasecki, Marek Florkowski, Marek Fulczyk ABB Corporate Research Center in Krakow Starowislna 13A, 31-038 Krakow,

More information

Transmission Line Transient Overvoltages (Travelling Waves on Power Systems)

Transmission Line Transient Overvoltages (Travelling Waves on Power Systems) Transmission Line Transient Overvoltages (Travelling Waves on Power Systems) The establishment of a potential difference between the conductors of an overhead transmission line is accompanied by the production

More information

Introduce system protection relays like underfrequency relays, rate of change of frequency relays, reverse - power flow

Introduce system protection relays like underfrequency relays, rate of change of frequency relays, reverse - power flow Module 1 : Fundamentals of Power System Protection Lecture 3 : Protection Paradigms - System Protection Objectives In this lecture we will: Overview dynamics in power systems. Introduce system protection

More information

Computer Based Model for Design Selection of Lightning Arrester for 132/33kV Substation

Computer Based Model for Design Selection of Lightning Arrester for 132/33kV Substation IOSR Journal of Engineering (IOSRJEN) ISSN (e): 2250-3021, ISSN (p): 2278-8719 Vol. 04, Issue 05 (May. 2014), V2 PP 32-36 www.iosrjen.org Computer Based Model for Design Selection of Lightning Arrester

More information

Simulation of line fault locator on HVDC Light electrode line

Simulation of line fault locator on HVDC Light electrode line August 10, 2010 Simulation of line fault locator on HVDC Light electrode line Andreas Hermansson BACHELOR S THESIS Electrical Engineering, Electric Power Technology Department of Engineering Science BACHELOR

More information

University of Zagreb Faculty of Electrical Engineering and Computing

University of Zagreb Faculty of Electrical Engineering and Computing Journal of Energy VOLUME 64 2015 journal homepage: http://journalofenergy.com/ Viktor Milardić viktor.milardic@fer.hr Ivica Pavić ivica.pavic@fer.hr University of Zagreb Faculty of Electrical Engineering

More information

The line-lightning performance and mitigation studies of shielded steelstructure

The line-lightning performance and mitigation studies of shielded steelstructure The line-lightning performance and mitigation studies of shielded steelstructure distribution lines ASNAWI MOHD BUSRAH, MALIK MOHAMAD Energy System Group TNB Research Sdn Bhd No 1, Lorong Ayer Hitam, 43000

More information

Lightning Flashover Rate of an Overhead Transmission Line Protected by Surge Arresters

Lightning Flashover Rate of an Overhead Transmission Line Protected by Surge Arresters IEEE PES General Meeting June 23-27, 27, 2007, Tampa Lightning Flashover Rate of an Overhead Transmission Line Protected by Surge Arresters Juan A. Martinez Univ. Politècnica Catalunya Barcelona, Spain

More information

Electric Stresses on Surge Arrester Insulation under Standard and

Electric Stresses on Surge Arrester Insulation under Standard and Chapter 5 Electric Stresses on Surge Arrester Insulation under Standard and Non-standard Impulse Voltages 5.1 Introduction Metal oxide surge arresters are used to protect medium and high voltage systems

More information

Modeling for the Calculation of Overvoltages Stressing the Electronic Equipment of High Voltage Substations due to Lightning

Modeling for the Calculation of Overvoltages Stressing the Electronic Equipment of High Voltage Substations due to Lightning Modeling for the Calculation of Overvoltages Stressing the Electronic Equipment of High Voltage Substations due to Lightning M. PSALIDAS, D. AGORIS, E. PYRGIOTI, C. KARAGIAΝNOPOULOS High Voltage Laboratory,

More information

Effect of High Frequency Cable Attenuation on Lightning-Induced Overvoltages at Transformers

Effect of High Frequency Cable Attenuation on Lightning-Induced Overvoltages at Transformers Voltage (kv) Effect of High Frequency Cable Attenuation on Lightning-Induced Overvoltages at Transformers Li-Ming Zhou, Senior Member, IEEE and Steven Boggs, Fellow, IEEE Abstract: The high frequency attenuation

More information

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY 9. INTRODUCTION Control Cabling The protection and control equipment in power plants and substations is influenced by various of environmental conditions. One of the most significant environmental factor

More information

The Analysis Results of Lightning Overvoltages by EMTP for Lightning Protection Design of 500 kv Substation

The Analysis Results of Lightning Overvoltages by EMTP for Lightning Protection Design of 500 kv Substation The Analysis Results of Lightning Overvoltages by EMTP for Lightning Protection Design of 500 kv Substation J. W. Woo, J. S. Kwak, H. J. Ju, H. H. Lee, J. D. Moon Abstract--To meet increasing power demand,

More information

X International Symposium on Lightning Protection

X International Symposium on Lightning Protection X International Symposium on Lightning Protection 9 th -13 th November, 2009 Curitiba, Brazil LIGHTNING SURGES TRANSFERRED TO THE SECONDARY OF DISTRIBUTION TRANSFORMERS DUE TO DIRECT STRIKES ON MV LINES,

More information

TECHNICAL REPORT. Insulation co-ordination

TECHNICAL REPORT. Insulation co-ordination TECHNICAL REPORT IEC TR 60071-4 First edition 2004-06 Insulation co-ordination Part 4: Computational guide to insulation co-ordination and modelling of electrical networks IEC 2004 Copyright - all rights

More information

PRACTICAL PROBLEMS WITH SUBSTATION EARTHING

PRACTICAL PROBLEMS WITH SUBSTATION EARTHING 1 PRACTICAL PROBLEMS WITH SUBSTATION EARTHING Dr Hendri Geldenhuys Craig Clark Eskom Distribution Technology This paper considers the issues around substation sites where the soil resistivity is of particularly

More information

GIS Instrument Transformers: EMC Conformity Tests for a Reliable Operation in an Upgraded Substation

GIS Instrument Transformers: EMC Conformity Tests for a Reliable Operation in an Upgraded Substation GIS Instrument Transformers: EMC Conformity Tests for a Reliable Operation in an Upgraded Substation W. Buesch 1) G. Palmieri M.Miesch J. Marmonier O. Chuniaud ALSTOM LTD 1) ALSTOM LTD High Voltage Equipment

More information

Overvoltage Protection of Light Railway Transportation Systems

Overvoltage Protection of Light Railway Transportation Systems Overvoltage Protection of Light Railway Transportation Systems F. Delfino, R. Procopio, Student Member, IEEE, and M. Rossi, Student Member, IEEE Abstract In this paper the behavior of the power supply

More information

Effect of Shielded Distribution Cables on Lightning-Induced Overvoltages in a Distribution System

Effect of Shielded Distribution Cables on Lightning-Induced Overvoltages in a Distribution System IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 17, NO. 2, APRIL 2002 569 Effect of Shielded Distribution Cables on Lightning-Induced Overvoltages in a Distribution System Li-Ming Zhou, Senior Member, IEEE,

More information

Power System Studies

Power System Studies Power System Studies Laois Ballyragget Cable Feasibility Study PE667-F4-R3-1-3 ESBI Engineering Solutions Stephen Court, 18/21 St Stephen s Green, Dublin 2, Ireland Telephone+353-1-73 8 Fax+353-1-661 66

More information

VFTO STUDIES DUO TO THE SWITCHING OPERATION IN GIS 132KV SUBSTATION AND EFFECTIVE FACTORS IN REDUCING THESE OVER VOLTAGES

VFTO STUDIES DUO TO THE SWITCHING OPERATION IN GIS 132KV SUBSTATION AND EFFECTIVE FACTORS IN REDUCING THESE OVER VOLTAGES VFTO STUDIES DUO TO THE SWITCHING OPERATION IN GIS 132KV SUBSTATION AND EFFECTIVE FACTORS IN REDUCING THESE OVER VOLTAGES Shohreh Monshizadeh Islamic Azad University South Tehran Branch (IAU), Tehran,

More information

OVERVOLTAGE PROTECTION OF POLE MOUNTED DISTRIBUTION TRANSFORMERS

OVERVOLTAGE PROTECTION OF POLE MOUNTED DISTRIBUTION TRANSFORMERS PERODCA POLYTECHNCA SER. EL. ENG. VOL. 41, NO. 1, PP. 27-40 (1997) OVERVOLTAGE PROTECTON OF POLE MOUNTED DSTRBUTON TRANSFORMERS Attila SOMOGY and Lasz16 VZ Department of Electric Power Systems Technical

More information

Overview of Grounding for Industrial and Commercial Power Systems Presented By Robert Schuerger, P.E.

Overview of Grounding for Industrial and Commercial Power Systems Presented By Robert Schuerger, P.E. Overview of Grounding for Industrial and Commercial Power Systems Presented By Robert Schuerger, P.E. HP Critical Facility Services delivered by EYP MCF What is VOLTAGE? Difference of Electric Potential

More information

Maximum Lightning Overvoltage along a Cable due to Shielding Failure

Maximum Lightning Overvoltage along a Cable due to Shielding Failure Maximum Lightning Overvoltage along a Cable due to Shielding Failure Thor Henriksen Abstract--This paper analyzes the maximum lightning overvoltage due to shielding failure along a cable inserted in an

More information

Simulation of Lightning Transients on 110 kv overhead-cable transmission line using ATP-EMTP

Simulation of Lightning Transients on 110 kv overhead-cable transmission line using ATP-EMTP Simulation of Lightning Transients on 110 kv overhead-cable transmission line using ATP-EMTP Kresimir Fekete 1, Srete Nikolovski 2, Goran Knezević 3, Marinko Stojkov 4, Zoran Kovač 5 # Power System Department,

More information

Modeling and Analysis of a 3-Phase 132kv Gas Insulated Substation

Modeling and Analysis of a 3-Phase 132kv Gas Insulated Substation Modeling and Analysis of a 3-Phase 132kv Gas Insulated Substation M. Kondalu1, Dr. P.S. Subramanyam2 Electrical & Electronics Engineering, JNT University. Hyderabad. Joginpally B.R. Engineering College,

More information

Transformers connected via a cable Overvoltage protection

Transformers connected via a cable Overvoltage protection A P P L I C AT I O N N OT E 2. 1 Transformers connected via a cable Overvoltage protection The APPLICATION NOTES (AN) are intended to be used in conjunction with the APPLICATION GUIDELINES Overvoltage

More information

Lightning Protection of Distribution Substations by Using Metal Oxide Gapless Surge Arresters Connected in Parallel

Lightning Protection of Distribution Substations by Using Metal Oxide Gapless Surge Arresters Connected in Parallel International Journal of Power and Energy Research, Vol. 1, No. 1, April 2017 https://dx.doi.org/10.22606/ijper.2017.11001 1 Lightning Protection of Distribution Substations by Using Metal Oxide Gapless

More information

ROEVER ENGINEERING COLLEGE ELAMBALUR, PERAMBALUR DEPARTMENT OF ELECTRICAL & ELECTRONICS ENGINEERING

ROEVER ENGINEERING COLLEGE ELAMBALUR, PERAMBALUR DEPARTMENT OF ELECTRICAL & ELECTRONICS ENGINEERING ROEVER ENGINEERING COLLEGE ELAMBALUR, PERAMBALUR 621 212 DEPARTMENT OF ELECTRICAL & ELECTRONICS ENGINEERING EE1003 HIGH VOLTAGE ENGINEERING QUESTION BANK UNIT-I OVER VOLTAGES IN ELECTRICAL POWER SYSTEM

More information

Effect of Surge Arrester on Overhead Transmission Lines as Shield against Over Voltage

Effect of Surge Arrester on Overhead Transmission Lines as Shield against Over Voltage Effect of Surge Arrester on Overhead Transmission Lines as Shield against Over Voltage Swati Agrawal Assistant Professor, MATS University, Raipur (C.G) Abstract: This paper describes the usage of surge

More information

G. KOEPPL Koeppl Power Experts Switzerland

G. KOEPPL Koeppl Power Experts Switzerland PS3: Substation Design: New Solutions and Experiences Bus-Node Substation A Big Improvement in Short-Circuit and Switching Properties at Reduced Substation Costs G. KOEPPL Koeppl Power Experts Switzerland

More information

EMC Philosophy applied to Design the Grounding Systems for Gas Insulation Switchgear (GIS) Indoor Substation

EMC Philosophy applied to Design the Grounding Systems for Gas Insulation Switchgear (GIS) Indoor Substation EMC Philosophy applied to Design the Grounding Systems for Gas Insulation Switchgear (GIS) Indoor Substation Marcos Telló Department of Electrical Engineering Pontifical Catholic University of Rio Grande

More information

Lumped Network Model of a Resistive Type High T c fault current limiter for transient investigations

Lumped Network Model of a Resistive Type High T c fault current limiter for transient investigations Lumped Network Model of a Resistive Type High T c fault current limiter for transient investigations Ricard Petranovic and Amir M. Miri Universität Karlsruhe, Institut für Elektroenergiesysteme und Hochspannungstechnik,

More information

Investigation into Transient SFO, FFO, VFTO Overvoltage Characteristics for Typical Gas Insulated Substations

Investigation into Transient SFO, FFO, VFTO Overvoltage Characteristics for Typical Gas Insulated Substations nvestigation into Transient SFO, FFO, VFTO Overvoltage Characteristics for Typical Gas nsulated Substations L. Czumbil, J. Kim, H. Nouri Abstract--Overvoltage characteristics of typical single bus, double

More information

Chapter 1. Overvoltage Surges and their Effects

Chapter 1. Overvoltage Surges and their Effects Chapter 1 Overvoltage Surges and their Effects 1.1 Introduction Power equipment are often exposed to short duration impulse voltages of high amplitude produced by lightning or switching transients. These

More information

The Lightning Event. White Paper

The Lightning Event. White Paper The Lightning Event White Paper The Lightning Event Surge Protection Solutions for PTC 1 The Lightning Event There are volumes of information available on what we believe lightning is and how we think

More information

A Study on Lightning Overvoltage Characteristics of Grounding Systems in Underground Distribution Power Cables

A Study on Lightning Overvoltage Characteristics of Grounding Systems in Underground Distribution Power Cables J Electr Eng Technol Vol. 9, No. 2: 628-634, 2014 http://dx.doi.org/10.5370/jeet.2014.9.2.628 ISSN(Print) 1975-0102 ISSN(Online) 2093-7423 A Study on Lightning Overvoltage Characteristics of Grounding

More information

Pre location: Impulse-Current-Method (ICE)

Pre location: Impulse-Current-Method (ICE) 1 ICE (Impulse current method three phased 2 1.1 Ionisation delay time 2 1.2 DIRECT MODE 2 1.3 Output impedance of the generator 2 Surge generator as impulse source 3 High voltage test set as impulse source

More information

DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING QUESTION BANK SUBJECT CODE & NAME : EE 1402 HIGH VOLTAGE ENGINEERING UNIT I

DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING QUESTION BANK SUBJECT CODE & NAME : EE 1402 HIGH VOLTAGE ENGINEERING UNIT I DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING QUESTION BANK SUBJECT CODE & NAME : EE 1402 HIGH VOLTAGE ENGINEERING YEAR / SEM : IV / VII UNIT I OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS 1. What

More information

Lightning Performance Improvement of 115 kv and 24 kv Circuits by External Ground in MEA s Distribution System

Lightning Performance Improvement of 115 kv and 24 kv Circuits by External Ground in MEA s Distribution System Lightning Performance Improvement of 115 kv and 24 kv Circuits by External Ground in MEA s Distribution System A. Phayomhom and S. Sirisumrannukul Abstract This paper presents the guidelines for preparing

More information

EXPERIMENTAL ISSUES OF OVERVOLTAGE COORDINATION

EXPERIMENTAL ISSUES OF OVERVOLTAGE COORDINATION EXPERIMENTAL ISSUES OF OVERVOLTAGE COORDINATION Gábor GÖCSEI Bálint NÉMETH Richárd CSELKÓ BUTE, Hungary BUTE, Hungary BUTE, Hungary gocsei.gabor@vet.bme.hu nemeth.balint@vet.bme.hu cselko.richard@vet.bme.hu

More information

Effects of Phase-Shifting Transformers, and Synchronous Condensers on Breaker Transient Recovery Voltages

Effects of Phase-Shifting Transformers, and Synchronous Condensers on Breaker Transient Recovery Voltages Effects of Phase-Shifting Transformers, and Synchronous Condensers on Breaker Transient Recovery Voltages Waruna Chandrasena, Bruno Bisewski, and Jeff Carrara Abstract-- This paper describes several system

More information

Insulation Coordination Study of 275kV AIS Substation in Malaysia

Insulation Coordination Study of 275kV AIS Substation in Malaysia Insulation Coordination Study of 275kV AIS Substation in Malaysia Hazlie Mokhlis, Ab.Halim Abu Bakar, Hazlee Azil Illias, Mohd.Fakrolrazi Shafie University of Malaya Power nergy Dedicated Advanced Center

More information

A Guide to the DC Decay of Fault Current and X/R Ratios

A Guide to the DC Decay of Fault Current and X/R Ratios A Guide to the DC Decay of Fault Current and X/R Ratios Introduction This guide presents a guide to the theory of DC decay of fault currents and X/R ratios and the calculation of these values in Ipsa.

More information

Analysis of MOV Surge Arrester Models by using Alternative Transient Program ATP/EMTP

Analysis of MOV Surge Arrester Models by using Alternative Transient Program ATP/EMTP IJSTE - International Journal of Science Technology & Engineering Volume 3 Issue 2 August 216 ISSN (online): 2349-784X Analysis of MOV Surge Arrester Models by using Alternative Transient Program ATP/EMTP

More information

How OSHA s New Transient Overvoltage Requirements Affect Work Practices. B.A. YEUNG, H. BRANCO Leidos Engineering, LLC USA

How OSHA s New Transient Overvoltage Requirements Affect Work Practices. B.A. YEUNG, H. BRANCO Leidos Engineering, LLC USA 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium How OSHA s New Transient Overvoltage Requirements Affect Work Practices B.A. YEUNG,

More information

Analysis of current distribution among long-flashover arresters for 10 kv overhead line protection against direct lightning strikes

Analysis of current distribution among long-flashover arresters for 10 kv overhead line protection against direct lightning strikes 2014 International onference on Lightning Protection (ILP), Shanghai, hina nalysis of current distribution among long-flashover arresters for 10 kv overhead line protection against direct lightning strikes

More information

EE 1402 HIGH VOLTAGE ENGINEERING

EE 1402 HIGH VOLTAGE ENGINEERING EE 1402 HIGH VOLTAGE ENGINEERING Unit 5 TESTS OF INSULATORS Type Test To Check The Design Features Routine Test To Check The Quality Of The Individual Test Piece. High Voltage Tests Include (i) Power frequency

More information

Lightning current field measurement on a transmission line, comparison with electromagnetic transient calculations

Lightning current field measurement on a transmission line, comparison with electromagnetic transient calculations Lightning current field measurement on a transmission line, comparison with electromagnetic transient calculations A. Xemard, M. Mesic, T. Sadovic, D. Marin, S. Sadovic Abstract- A lightning experiment

More information

Switching Restrikes in HVAC Cable Lines and Hybrid HVAC Cable/OHL Lines

Switching Restrikes in HVAC Cable Lines and Hybrid HVAC Cable/OHL Lines Switching Restrikes in HVAC Cable Lines and Hybrid HVAC Cable/OHL Lines F. Faria da Silva, Claus L. Bak, Per B. Holst Abstract--The disconnection of HV underground cables may, if unsuccessful, originate

More information

CHAPTER 2. v-t CHARACTERISTICS FOR STANDARD IMPULSE VOLTAGES

CHAPTER 2. v-t CHARACTERISTICS FOR STANDARD IMPULSE VOLTAGES 23 CHAPTER 2 v-t CHARACTERISTICS FOR STANDARD IMPULSE VOLTAGES 2.1 INTRODUCTION For reliable design of power system, proper insulation coordination among the power system equipment is necessary. Insulation

More information

Research on Lightning Over-voltage and Lightning Protection of 500kV. HGIS Substation

Research on Lightning Over-voltage and Lightning Protection of 500kV. HGIS Substation International Conference on Manufacturing Science and Engineering (ICMSE 2015) Research on Lightning Over-voltage and Lightning Protection of 500kV HGIS Substation Tong Wang1, a *and Youping Fan1, b 1

More information

Analysis of Arrester Energy for 132kV Overhead Transmission Line due to Back Flashover and Shielding Failure

Analysis of Arrester Energy for 132kV Overhead Transmission Line due to Back Flashover and Shielding Failure nalysis of rrester Energy for 132kV Overhead ransmission Line due to Back Flashover and Shielding Failure Nor Hidayah Nor Hassan 1,a, b. Halim bu Bakar 2,b, Hazlie Mokhlis 1, Hazlee zil Illias 1 1 Department

More information

ON-LINE PARTIAL DISCHARGE TESTING OF SOME OF THE WORST PERFORMING CIRCUITS ON A UTILITY DISTRIBUTION SYSTEM

ON-LINE PARTIAL DISCHARGE TESTING OF SOME OF THE WORST PERFORMING CIRCUITS ON A UTILITY DISTRIBUTION SYSTEM ON-LINE PARTIAL DISCHARGE TESTING OF SOME OF THE WORST PERFORMING CIRCUITS ON A UTILITY DISTRIBUTION SYSTEM D. Clark¹ R. Mackinlay² M. Seltzer-Grant² S. Goodfellow² Lee Renforth² Jamie McWilliam³ and Roger

More information

Modeling of overhead transmission lines with line surge arresters for lightning overvoltages. Poland

Modeling of overhead transmission lines with line surge arresters for lightning overvoltages. Poland Application of Line Surge Arresters in Power Distribution and Transmission Systems COLLOQUIUM Cavtat 2008 Modeling of overhead transmission lines with line surge arresters for lightning overvoltages M.

More information

Choosing the right Pico Technology active differential probe

Choosing the right Pico Technology active differential probe Pico Technology offers many active s covering a wide range of voltages, category (CAT) ratings and bandwidths. As the name suggests, these probes have two major features: Active: Active probes achieve

More information

Effective Elimination Factors to the Generated Lightning Flashover in High Voltage Transmission Network

Effective Elimination Factors to the Generated Lightning Flashover in High Voltage Transmission Network International Journal on Electrical Engineering and Informatics - Volume 9, Number, September 7 Effective Elimination Factors to the Generated Lightning Flashover in High Voltage Transmission Network Abdelrahman

More information

The Effect of Lightning Parameters on Induced Voltages Caused by Nearby Lightning on Overhead Distribution Conducting Line.

The Effect of Lightning Parameters on Induced Voltages Caused by Nearby Lightning on Overhead Distribution Conducting Line. The Effect of Lightning Parameters on Induced Voltages Caused by Nearby Lightning on Overhead Distribution Conducting Line. J.O. Adepitan, Ph.D. 1 and Prof. E.O. Oladiran 2 1 Department of Physics and

More information

Research Article A Simplified High Frequency Model of Interleaved Transformer Winding

Research Article A Simplified High Frequency Model of Interleaved Transformer Winding Research Journal of Applied Sciences, Engineering and Technology 10(10): 1102-1107, 2015 DOI: 10.19026/rjaset.10.1879 ISSN: 2040-7459; e-issn: 2040-7467 2015 Maxwell Scientific Publication Corp. Submitted:

More information

Comparison of switching surges and basic lightning impulse surges at transformer in MV cable grids

Comparison of switching surges and basic lightning impulse surges at transformer in MV cable grids Comparison of switching surges and basic lightning impulse surges at transformer in MV cable grids Tarik Abdulahović #, Torbjörn Thiringer # # Division of Electric Power Engineering, Department of Energy

More information

Sensitivity Analysis of Maximum Overvoltage on Cables with Considering Forward and Backward Waves

Sensitivity Analysis of Maximum Overvoltage on Cables with Considering Forward and Backward Waves Sensitivity Analysis of Maximum Overvoltage on Cables with Considering Forward and Backward Waves Hamed Touhidi 1,Mehdi Shafiee 2, Behrooz Vahidi 3, Seyed Hossein Hosseinian 4 1 Islamic Azad University,

More information

Electrical Power and Energy Systems

Electrical Power and Energy Systems Electrical Power and Energy Systems 33 (2011) 1536 1541 Contents lists available at ScienceDirect Electrical Power and Energy Systems journal homepage: www.elsevier.com/locate/ijepes Analysis of lightning-caused

More information

Section 11: Power Quality Considerations Bill Brown, P.E., Square D Engineering Services

Section 11: Power Quality Considerations Bill Brown, P.E., Square D Engineering Services Section 11: Power Quality Considerations Bill Brown, P.E., Square D Engineering Services Introduction The term power quality may take on any one of several definitions. The strict definition of power quality

More information