BCS UPDATE. j. welch 2/9/17

Size: px
Start display at page:

Download "BCS UPDATE. j. welch 2/9/17"

Transcription

1 BCS UPDATE j. welch 2/9/17

2 TOPICS RP requirements Shutoff path Beam loss detection scheme Beam loss detectors and FPGAs Current monitors Dumps

3 RP REQUIREMENTS Revised BCS PRD was circulated Tuesday for comments. Still to come: RP requirements for rastering, final protection collimators, auto-bypass for Undulator Complex zone, and bremsstrahlung in the FEE. Selected highlights BCS fault requires shutoff of RF in L0,L1, L2, and L3. MCMs on the laser heater dipoles Shutoff Gun RF if loss near gun exceeds 100 W. More generous overall shutoff times > Choice of continuous LBLM coverage or ACM comparator for S11-S27 BYD magnets are in series with BTH dogleg dipoles

4 BCS SHUTOFF PATH When a (BCS) fault is detected, all beams must be shut off by three independent methods. * 1. Acousto-optic or Electo-optic rep-rate control (pulse picker) device triggers are removed. 2. Mechanical shutter 3. gets complicated * Radiation Safety Systems Technical Basis Document

5 AOM Mech. Shutter Gun L0 L0,L1, L2, L3 up to 1 hr recovery Option 2 inexpensive, reasonable recovery expensive to implement because of number SSAs, reasonable recovery Concerns have been expressed possible gun and or cavity field emission hazards would persist even if the photo beam is turned off successfully if laser heater chicane magnets are off the gun current would reach L1 and be accelerated. RP s BCS PRD under review says turn off Gun, L0, L1, L2, L3 We are going over the details with RP.

6 OPTION 2 Fill time is 10 ms, so beam would go off in ~1 ms when the energy drops below the acceptance. Cryo load change is small and mostly balanced by load resistors that should come on. Recovery time for cavities to ramp up gradient while keeping in resonance is seconds (not minutes)

7 Linac RF Shutoff Mechanisms Control System PPS Fault LLRF 24 V interlock out BCS Fault PPS Breaker 480 VAC 480 VAC Breaker SSA 24 V interlock in 120 VAC SSA shuts down if 480 VAC is out of range

8 OPTION 2 HAZARDS Gun field emission causing radiation in the laser room, or (during gun only running) downstream of the temporary shielding wall. Cavity field emission from L1, L2, L3 causing radiation in the laser room or in the klystron gallery Cavity field emission causing damage to stoppers, protection collimators or dumps.

9 GUN FIELD EMISSION UNDER OPTION 2 SHUTOFF Example of dark current. CM01 is powered in this simulation. (C. Mayes) Gun dark current would mostly get absorbed on the vacuum pipes and in the CM01 cryomodule. Some would reach the laser heater chicane where it would be absorbed because of the ~100x energy mis-match with the laser heater chicane. Power is likely to be very small: 400 na (max) x 750 kv = 0.3 W

10 WORST CASE GUN FIELD EMISSION 10 μa emission: original emitted up to 6 μa. This is possible but unlikely and is less than 5 W. 60 kw emission: theoretical SSA power supply limit (1/2 of 120 kw). Voltage goes to 0.5 MV. This is theoretically possible, but almost certainly will never happen. Working with J. Blaha to define mis-steering case and MCI.

11 CAVITY FIELD EMISSION UNDER OPTION 2 Normal configuration - chicanes trap captured field emission current because of the energy mis-match (forward direction) or wrong sign (backward direction) of the chicane magnets. Field emission currents are expected to be low. For operation 1 na/cm acceptance ( ~ few W) 10 na from worst case CM ( ~ few W) MCI - (maximum credible incident, or, minimal incredible incident?) all chicanes straight, all CM emitting simultaneously 1000 na for a total of 70 kw Not protected by BCS system - it already tripped Shielding was designed for this case. (3 Rem event, 25 R/hr) PPS would likely trip which shuts down all RF. Looks OK to RP at this point, but they are still looking at it.

12 LINAC SAFE STATE C. Adolphson suggested to alternately reverse phase adjacent cavities to put linac in a safe but ready state - no acceleration Fast - a fraction of a second Keeps gradients constant, no ramp up, no cryo change Uses computer control (matlab?) - not hardwired safety systems. Backup measure to prevent the possibility of acceleration. Auto- and operator controlled.

13 BEAM LOSS DETECTION PRD is out: Radiation Detection Requirements for the BCS and MPS, LCLSII-2.4-PR-0868-R0 Selected highlights: Common detectors for MPS and BCS: LBLMs, PBLMs, and IBLMs Complete machine coverage for MPS: gun to FEE Local detectors, PBLMs, to protect safety system items

14 Trip Levels and Response Times

15 PBLMs (diamond detectors, ionization chambers, PMTs)

16 LBLMs (fibers, LIONs) Pairs 100 m long with some overlap

17 CALIBRATION still open issue: More than 200 installed PBLMs and LBPMs that need periodic calibration checking. PRD says use local sources, but hottest portable source at SLAC is a useless 25 mrem/hr. Trip levels are expected to be 1-10 R/hr or higher. Plan B is use the beam to generate pulsed radiation for calibration Need systematic method for making beam get lost in a known way - say every 10 m. Chao thinks it is possible. => ~1000 measurements Need RP modeling of each of those loses to see what radiation reaches the detector

18 DETECTORS (A. FISHER) 100 m fiber and several diamond detectors were installed in Sector 24 in October last year. Beam losses were forced during a machine studies in November and signals studied with good results. ==> Archive data was collected for both LIONs and fibers. It is not yet analyzed. Fibers and diamonds were brought to JLAB and measured radiation during processing of SC cavities. Good signals and much cleaner than JLAB detectors. Next step is to set up approval process with RSC for BCS loss detection, that includes new detectors and FPGAs. (J. Dehong) BLM:LI24:707:QDCRAW BLM fiber 707 () Correlation Plot 16 Nov :29:15 BLM:LI24:707:QDCRAW *5e9*1.6e 19*(c d) () Watts loss calculated from tmits

19 Testing fibers and diamond detectors at JLAB A. Fisher, January 2017

20 FPGA to be used with ACMs, PBLMs, and LBLMs to provide fast digital averaging and diagnostics. match IEC safety criteria redundant FPGAs check each other each line is documented new to SLAC safety systems - expect a vigorous workout to get accepted example:

21 CURRENT MONITORS Average Current Monitors (ACMs) monitor current in various beam lines and cause a BCS trip if the current exceeds a pre-set limit. Average current is defined as the charge in the last 25 μs divided by 25 μs. FPGAs are used to perform the calculation. Digital modeling underway: temperature sensitivity, signal size, loaded Q, rep rate, and bunch charge

22 ACM MODELING EXAMPLE signals at various stages of processing Output of the FPGA averager to be compared with trip level

23 DUMPS Two 120 kw dumps for the undulators, one 250 kw dump in the BSY for idle beam. FDR held December - no report yet guessing more work on intervention plan and shielding, but otherwise ok Next steps are to finish designs and start fabrication Rastering of BSYDUMP is still in conceptual stage.

24 THE END

Physics Requirements Document Document Title: SCRF 1.3 GHz Cryomodule Document Number: LCLSII-4.1-PR-0146-R0 Page 1 of 7

Physics Requirements Document Document Title: SCRF 1.3 GHz Cryomodule Document Number: LCLSII-4.1-PR-0146-R0 Page 1 of 7 Document Number: LCLSII-4.1-PR-0146-R0 Page 1 of 7 Document Approval: Originator: Tor Raubenheimer, Physics Support Lead Date Approved Approver: Marc Ross, Cryogenic System Manager Approver: Jose Chan,

More information

ALICE SRF SYSTEM COMMISSIONING EXPERIENCE A. Wheelhouse ASTeC, STFC Daresbury Laboratory

ALICE SRF SYSTEM COMMISSIONING EXPERIENCE A. Wheelhouse ASTeC, STFC Daresbury Laboratory ALICE SRF SYSTEM COMMISSIONING EXPERIENCE A. Wheelhouse ASTeC, STFC Daresbury Laboratory ERL 09 8 th 12 th June 2009 ALICE Accelerators and Lasers In Combined Experiments Brief Description ALICE Superconducting

More information

A Facility for Accelerator Physics and Test Beam Experiments

A Facility for Accelerator Physics and Test Beam Experiments A Facility for Accelerator Physics and Test Beam Experiments Experimental Program Advisory Committee Roger Erickson for the SABER Design Team December 4, 2006 The Problem: FFTB is gone! The Final Focus

More information

Beam Diagnostics, Low Level RF and Feedback for Room Temperature FELs. Josef Frisch Pohang, March 14, 2011

Beam Diagnostics, Low Level RF and Feedback for Room Temperature FELs. Josef Frisch Pohang, March 14, 2011 Beam Diagnostics, Low Level RF and Feedback for Room Temperature FELs Josef Frisch Pohang, March 14, 2011 Room Temperature / Superconducting Very different pulse structures RT: single bunch or short bursts

More information

Beam Loss Monitoring (BLM) System for ESS

Beam Loss Monitoring (BLM) System for ESS Beam Loss Monitoring (BLM) System for ESS Lali Tchelidze European Spallation Source ESS AB lali.tchelidze@esss.se March 2, 2011 Outline 1. BLM Types; 2. BLM Positioning and Calibration; 3. BLMs as part

More information

ECRH on the Levitated Dipole Experiment

ECRH on the Levitated Dipole Experiment ECRH on the Levitated Dipole Experiment S. Mahar, J. Kesner, A.C. Boxer, J.E. Ellsworth, I. Karim, A. Roach MIT PSFC A.K. Hansen, D.T. Garnier, M.E. Mauel, E.E.Ortiz Columbia University Presented at the

More information

INSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM

INSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM INSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM FOR THE EUROPEAN XFEL Julien Branlard, for the LLRF team TALK OVERVIEW 2 Introduction Brief reminder about the XFEL LLRF system Commissioning goals

More information

Beam Loss monitoring R&D. Arden Warner Fermilab MPS2014 Workshop March 5-6, 2014

Beam Loss monitoring R&D. Arden Warner Fermilab MPS2014 Workshop March 5-6, 2014 Beam Loss monitoring R&D Arden Warner Fermilab MPS2014 Workshop March 5-6, 2014 Outline PXIE Technical Concerns PXIE Study plans Preliminary scvd R&D Cold Ionization chambers 2 MPS2014; Arden Warner Loss

More information

RF System LSD Work. William Merz

RF System LSD Work. William Merz RF System LSD Work William Merz LSD Re-Baseline Review Jefferson Lab Thomas Jefferson National Accelerator Facility Page 1 Outline What I will talk about 12 GEV RF power system installation and commissioning

More information

14 Radiological Considerations

14 Radiological Considerations 14 Radiological Considerations Technical Synopsis This chapter describes the radiation protection requirements and radiological considerations for LCLS-II. Experience with LCLS-I and dedicated Monte Carlo

More information

Initial Beam Phasing of the SRF Cavities in LCLS-II

Initial Beam Phasing of the SRF Cavities in LCLS-II Introduction Initial Beam Phasing of the SRF Cavities in LCLS-II P. Emma Nov. 28, 2016 One of the more challenging aspects of commissioning the LCLS-II accelerator is in the initial phasing of the SRF

More information

Commissioning of the ALICE SRF Systems at Daresbury Laboratory Alan Wheelhouse, ASTeC, STFC Daresbury Laboratory ESLS RF 1 st 2 nd October 2008

Commissioning of the ALICE SRF Systems at Daresbury Laboratory Alan Wheelhouse, ASTeC, STFC Daresbury Laboratory ESLS RF 1 st 2 nd October 2008 Commissioning of the ALICE SRF Systems at Daresbury Laboratory Alan Wheelhouse, ASTeC, STFC Daresbury Laboratory ESLS RF 1 st 2 nd October 2008 Overview ALICE (Accelerators and Lasers In Combined Experiments)

More information

Low-Level RF. S. Simrock, DESY. MAC mtg, May 05 Stefan Simrock DESY

Low-Level RF. S. Simrock, DESY. MAC mtg, May 05 Stefan Simrock DESY Low-Level RF S. Simrock, DESY Outline Scope of LLRF System Work Breakdown for XFEL LLRF Design for the VUV-FEL Cost, Personpower and Schedule RF Systems for XFEL RF Gun Injector 3rd harmonic cavity Main

More information

Supporting Planning and Engineering Processes at XFEL Examples, Benefits and Experience

Supporting Planning and Engineering Processes at XFEL Examples, Benefits and Experience Supporting Planning and Engineering Processes at XFEL Examples, Benefits and Experience Lars Hagge, Benno List SLAC, 31.03.2014 Agenda > Introduction: Collaborative Engineering > Collaborative Design &

More information

HIGHER ORDER MODES FOR BEAM DIAGNOSTICS IN THIRD HARMONIC 3.9 GHZ ACCELERATING MODULES *

HIGHER ORDER MODES FOR BEAM DIAGNOSTICS IN THIRD HARMONIC 3.9 GHZ ACCELERATING MODULES * HIGHER ORDER MODES FOR BEAM DIAGNOSTICS IN THIRD HARMONIC 3.9 GHZ ACCELERATING MODULES * N. Baboi #, N. Eddy, T. Flisgen, H.-W. Glock, R. M. Jones, I. R. R. Shinton, and P. Zhang # # Deutsches Elektronen-Synchrotron

More information

F- 9 72) PROTECTION IN THE ~ L TEST AT SLAC

F- 9 72) PROTECTION IN THE ~ L TEST AT SLAC 1 CON SLAC-PUB-7491 May 1997 F- 9 72)503--973 PROTECTION IN THE ~ L TEST C ACCELERATOR t S r l AT SLAC Theodore L. Lavine and Vaclav Vylet Accelerator Center, Stanford University, Stanford, California

More information

THz Pump Beam for LCLS. Henrik Loos. LCLS Hard X-Ray Upgrade Workshop July 29-31, 2009

THz Pump Beam for LCLS. Henrik Loos. LCLS Hard X-Ray Upgrade Workshop July 29-31, 2009 Beam for LCLS Henrik Loos Workshop July 29-31, 29 1 1 Henrik Loos Overview Coherent Radiation Sources Timing THz Source Performance 2 2 Henrik Loos LCLS Layout 6 MeV 135 MeV 25 MeV 4.3 GeV 13.6 GeV σ z.83

More information

TECHNICAL CHALLENGES OF THE LCLS-II CW X-RAY FEL *

TECHNICAL CHALLENGES OF THE LCLS-II CW X-RAY FEL * TECHNICAL CHALLENGES OF THE LCLS-II CW X-RAY FEL * T.O. Raubenheimer # for the LCLS-II Collaboration, SLAC, Menlo Park, CA 94025, USA Abstract The LCLS-II will be a CW X-ray FEL upgrade to the existing

More information

Performance of the Prototype NLC RF Phase and Timing Distribution System *

Performance of the Prototype NLC RF Phase and Timing Distribution System * SLAC PUB 8458 June 2000 Performance of the Prototype NLC RF Phase and Timing Distribution System * Josef Frisch, David G. Brown, Eugene Cisneros Stanford Linear Accelerator Center, Stanford University,

More information

Interfaces with MPS/PSS

Interfaces with MPS/PSS Interfaces with / European Spallation Source Accelerator Division TB, 16 November 2016, Lund, Sweden / interfaces 1/21 Outline 1 Introduction 2 3 4 Conclusions / interfaces 2/21 Outline 1 Introduction

More information

R.Bachimanchi, IPAC, May 2015, Richmond, VA

R.Bachimanchi, IPAC, May 2015, Richmond, VA 1 new module C100 Cryomodule Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint Fundamental frequency f 0 Accelerating gradient E acc 1497 MHz >

More information

R&D Toward Brighter X-ray FELs

R&D Toward Brighter X-ray FELs Some R&D Toward Brighter X-ray FELs Zhirong Huang (SLAC) March 6, 2012 FLS2012 Workshop, Jefferson Lab Outline Introduction Seeding for temporal coherence Hard x-rays Soft x-rays Push for higher power

More information

C100 Cryomodule. Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint

C100 Cryomodule. Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint 1 new module C100 Cryomodule Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint Fundamental frequency f 0 Accelerating gradient E acc 1497 MHz >

More information

Does the short pulse mode need energy recovery?

Does the short pulse mode need energy recovery? Does the short pulse mode need energy recovery? Rep. rate Beam power @ 5GeV 1nC @ 100MHz 500MW Absolutely 1nC @ 10MHz 1nC @ 1MHz 50MW 5MW Maybe 1nC @ 100kHz 0.5MW No Most applications we have heard about

More information

Hall C Polarimetry at 12 GeV Dave Gaskell Hall C Users Meeting January 14, 2012

Hall C Polarimetry at 12 GeV Dave Gaskell Hall C Users Meeting January 14, 2012 Hall C Polarimetry at 12 GeV Dave Gaskell Hall C Users Meeting January 14, 2012 1. Møller Polarimeter 2. Compton Polarimeter Hall C 12 GeV Polarimetry Møller Polarimeter 6 GeV operation: uses 2 quads to

More information

Superstructures; First Cold Test and Future Applications

Superstructures; First Cold Test and Future Applications Superstructures; First Cold Test and Future Applications DESY: C. Albrecht, V. Ayvazyan, R. Bandelmann, T. Büttner, P. Castro, S. Choroba, J. Eschke, B. Faatz, A. Gössel, K. Honkavaara, B. Horst, J. Iversen,

More information

Feedback Requirements for SASE FELS. Henrik Loos, SLAC IPAC 2010, Kyoto, Japan

Feedback Requirements for SASE FELS. Henrik Loos, SLAC IPAC 2010, Kyoto, Japan Feedback Requirements for SASE FELS Henrik Loos, SLAC, Kyoto, Japan 1 1 Henrik Loos Outline Stability requirements for SASE FELs Diagnostics for beam parameters Transverse: Beam position monitors Longitudinal:

More information

Status of the European XFEL Accelerator Construction Project. Reinhard Brinkmann, DESY

Status of the European XFEL Accelerator Construction Project. Reinhard Brinkmann, DESY Status of the European XFEL Accelerator Construction Project Reinhard Brinkmann, DESY European XFEL Introduction Some specifications Photon energy 0.3-24 kev Pulse duration ~ 10-100 fs Pulse energy few

More information

ELECTRON BEAM DIAGNOSTICS AND FEEDBACK FOR THE LCLS-II*

ELECTRON BEAM DIAGNOSTICS AND FEEDBACK FOR THE LCLS-II* THB04 Proceedings of FEL2014, Basel, Switzerland ELECTRON BEAM DIAGNOSTICS AND FEEDBACK FOR THE LCLS-II* Josef Frisch, Paul Emma, Alan Fisher, Patrick Krejcik, Henrik Loos, Timothy Maxwell, Tor Raubenheimer,

More information

Short-Pulse X-ray at the Advanced Photon Source Overview

Short-Pulse X-ray at the Advanced Photon Source Overview Short-Pulse X-ray at the Advanced Photon Source Overview Vadim Sajaev and Louis Emery Accelerator Operations and Physics Group Accelerator Systems Division Mini-workshop on Methods of Data Analysis in

More information

CEBAF waveguide absorbers. R. Rimmer for JLab SRF Institute

CEBAF waveguide absorbers. R. Rimmer for JLab SRF Institute CEBAF waveguide absorbers R. Rimmer for JLab SRF Institute Outline Original CEBAF HOM absorbers Modified CEBAF loads for FEL New materials for replacement loads High power loads for next generation FELs

More information

Study the Compact Photon Source Radiation Using FLUKA

Study the Compact Photon Source Radiation Using FLUKA Study the Compact Photon Source Radiation Using FLUKA Jixie Zhang, Donal Day, Rolf Ent Nov 30, 2017 This is a summary of radiation studies done for both the UVa target alone (for electron and photon beams)

More information

CEBAF Overview June 4, 2010

CEBAF Overview June 4, 2010 CEBAF Overview June 4, 2010 Yan Wang Deputy Group Leader of the Operations Group Outline CEBAF Timeline Machine Overview Injector Linear Accelerators Recirculation Arcs Extraction Systems Beam Specifications

More information

BEAM LOSS MONITORS DEPENDABILITY

BEAM LOSS MONITORS DEPENDABILITY BEAM LOSS MONITORS DEPENDABILITY STATE OF ART 1/18 Basic Concepts System fault events BLM are designed to prevent the Magnet Disruption (MaDi) due to an high loss ( ~30 downtime days). BLM should avoid

More information

The FERMI Elettra: radiation protection and safety issues

The FERMI Elettra: radiation protection and safety issues The FERMI project @ Elettra: radiation protection and safety issues G.Tromba 1, K.Casarin 1, E. La Torre 1, F.Longo 1,2, E.Quai 1, and A.Vascotto 1 1 Sincrotrone Trieste SCpA, Strada Statale S.S.14 km

More information

Using Higher Order Modes in the Superconducting TESLA Cavities for Diagnostics at DESY

Using Higher Order Modes in the Superconducting TESLA Cavities for Diagnostics at DESY Using Higher Order Modes in the Superconducting TESLA Cavities for Diagnostics at FLASH @ DESY N. Baboi, DESY, Hamburg for the HOM team : S. Molloy 1, N. Baboi 2, N. Eddy 3, J. Frisch 1, L. Hendrickson

More information

Spaceborne Electron Accelerators

Spaceborne Electron Accelerators Spaceborne Electron Accelerators J.W. Lewellen, C. Buechler, G. Dale, N.A. Moody, D.C. Nguyen LINAC 2016 26 September 2016 Acknowledgements LANL Program Development and Pathfinder funding LANL team members

More information

FLASH at DESY. FLASH. Free-Electron Laser in Hamburg. The first soft X-ray FEL operating two undulator beamlines simultaneously

FLASH at DESY. FLASH. Free-Electron Laser in Hamburg. The first soft X-ray FEL operating two undulator beamlines simultaneously FLASH at DESY The first soft X-ray FEL operating two undulator beamlines simultaneously Katja Honkavaara, DESY for the FLASH team FEL Conference 2014, Basel 25-29 August, 2014 First Lasing FLASH2 > First

More information

RF Design of Normal Conducting Deflecting Cavity

RF Design of Normal Conducting Deflecting Cavity RF Design of Normal Conducting Deflecting Cavity Valery Dolgashev (SLAC), Geoff Waldschmidt, Ali Nassiri (Argonne National Laboratory, Advanced Photon Source) 48th ICFA Advanced Beam Dynamics Workshop

More information

FLASH Operation at DESY From a Test Accelerator to a User Facility

FLASH Operation at DESY From a Test Accelerator to a User Facility FLASH Operation at DESY From a Test Accelerator to a User Facility Michael Bieler FLASH Operation at DESY WAO2012, SLAC, Aug. 8, 2012 Vocabulary DESY: Deutsches Elektronen-Synchrotron, Hamburg, Germany

More information

Normal-conducting high-gradient rf systems

Normal-conducting high-gradient rf systems Normal-conducting high-gradient rf systems Introduction Motivation for high gradient Order of 100 GeV/km Operational and state-of-the-art SwissFEL C-band linac: Just under 30 MV/m CLIC prototypes: Over

More information

Installation of the Optical Replica Synthesizer (ORS) at FLASH

Installation of the Optical Replica Synthesizer (ORS) at FLASH Installation of the Optical Replica Synthesizer (ORS) at FLASH Who and What? G. Angelova, V. Ziemann- Task: Modulator and radiator undulators, participating in the Theoretical simulations with Genesis

More information

1.0 Introduction. 2.0 Scope

1.0 Introduction. 2.0 Scope 1.0 Introduction The LCLS project requires one horizontal kicker magnet (BXKIK) to be installed at sector 25-3d. Nominal LCLS beam energy at that location is 4.8 GeV. The BXKIK magnet is planned to be

More information

Overview of ERL Projects: SRF Issues and Challenges. Matthias Liepe Cornell University

Overview of ERL Projects: SRF Issues and Challenges. Matthias Liepe Cornell University Overview of ERL Projects: SRF Issues and Challenges Matthias Liepe Cornell University Overview of ERL projects: SRF issues and challenges Slide 1 Outline Introduction: SRF for ERLs What makes it special

More information

J. Jacob: Status of the ESRF RF upgrade

J. Jacob: Status of the ESRF RF upgrade 17th ESLS RF Meeting 2013 HZB BESSY 18th 19th September Status of the ESRF RF upgrade J. Jacob J.-M. Mercier V. Serrière M. Langlois G. Gautier [CINEL] 1 RF upgrade phase 1 until 2015 - reminder Replacement

More information

BESSY VSR: SRF challenges and developments for a variable pulse-length next generation light source

BESSY VSR: SRF challenges and developments for a variable pulse-length next generation light source BESSY VSR: SRF challenges and developments for a variable pulse-length next generation light source Institut SRF - Wissenschaft und Technologie (FG-ISRF) Adolfo Vélez et al. SRF17 Lanzhou, 17-21/7/2017

More information

Cryogenic Operations at SLAC

Cryogenic Operations at SLAC Cryogenic Operations at SLAC J. G. Weisend II, A. Candia, W.W. Craddock, E. Thompson CryoOps 2006 5/30/2006 J. G. Weisend II 1 What Do We Do? Cryogenics at SLAC involve: Large scale He refrigerator operation

More information

SNS LLRF Design Experience and its Possible Adoption for the ILC

SNS LLRF Design Experience and its Possible Adoption for the ILC SNS LLRF Design Experience and its Possible Adoption for the ILC Brian Chase SNS - Mark Champion Fermilab International Linear Collider Workshop 11/28/2005 1 Why Consider the SNS System for ILC R&D at

More information

RF STATUS OF SUPERCONDUCTING MODULE DEVELOPMENT SUITABLE FOR CW OPERATION: ELBE CRYOSTATS

RF STATUS OF SUPERCONDUCTING MODULE DEVELOPMENT SUITABLE FOR CW OPERATION: ELBE CRYOSTATS RF STATUS OF SUPERCONDUCTING MODULE DEVELOPMENT SUITABLE FOR CW OPERATION: ELBE CRYOSTATS J. Teichert, A. Büchner, H. Büttig, F. Gabriel, P. Michel, K. Möller, U. Lehnert, Ch. Schneider, J. Stephan, A.

More information

Software Requirements Specification for LLRF Applications at FLASH Version 1.0 Prepared by Zheqiao Geng MSK, DESY Nov. 06, 2009

Software Requirements Specification for LLRF Applications at FLASH Version 1.0 Prepared by Zheqiao Geng MSK, DESY Nov. 06, 2009 Software Specification for LLRF Applications at FLASH Version 1.0 Prepared by Zheqiao Geng MSK, DESY Nov. 06, 2009 Copyright 2009 by Zheqiao Geng. Any change of this document should be agreed by the development

More information

Demonstration of exponential growth and saturation at VUV wavelengths at the TESLA Test Facility Free-Electron Laser. P. Castro for the TTF-FEL team

Demonstration of exponential growth and saturation at VUV wavelengths at the TESLA Test Facility Free-Electron Laser. P. Castro for the TTF-FEL team Demonstration of exponential growth and saturation at VUV wavelengths at the TESLA Test Facility Free-Electron Laser P. Castro for the TTF-FEL team 100 nm 1 Å FEL radiation TESLA Test Facility at DESY

More information

SPS Crab Cavity Validation Run ( )

SPS Crab Cavity Validation Run ( ) SPS Crab Cavity Validation Run (2017-2018) Alick Macpherson BE-RF-SRF Acknowledgments Marton Ady, Vincent Baglin, Philippe Baudrenghien, Krzyzstof Brodzinski, Rama Calaga, Ofelia Capatina, Frederic Galleazzi,

More information

Attosecond Diagnostics of Muti GeV Electron Beams Using W Band Deflectors

Attosecond Diagnostics of Muti GeV Electron Beams Using W Band Deflectors Attosecond Diagnostics of Muti GeV Electron Beams Using W Band Deflectors V.A. Dolgashev, P. Emma, M. Dal Forno, A. Novokhatski, S. Weathersby SLAC National Accelerator Laboratory FEIS 2: Femtosecond Electron

More information

12 GeV Upgrade Project DESIGN SOLUTIONS DOCUMENT. Upgrade Hall A

12 GeV Upgrade Project DESIGN SOLUTIONS DOCUMENT. Upgrade Hall A 12 GeV Upgrade Project DESIGN SOLUTIONS DOCUMENT Upgrade Hall A Version 1.2 July 28, 2010 DESIGN SOLUTIONS DOCUMENT Upgrade Hall A APPROVALS Approved by: 12 GeV Upgrade Control Account Manager, Hall A

More information

Improvement in High-Frequency Properties of Beam Halo Monitor using Diamond Detectors for SPring-8 XFEL

Improvement in High-Frequency Properties of Beam Halo Monitor using Diamond Detectors for SPring-8 XFEL 32 nd International Free Electron Laser Conference FEL 2010 Improvement in High-Frequency Properties of Beam Halo Monitor using Diamond Detectors for SPring-8 XFEL August 26, 2010 Thursday, THOC4 1 Hideki

More information

BNL Collider Complex Overview. MPS at the collider accelerator department (C-AD) RHIC Accelerator Protection Elements

BNL Collider Complex Overview. MPS at the collider accelerator department (C-AD) RHIC Accelerator Protection Elements MPS Experience at BNL-RHIC BNL Collider Complex Overview MPS at the collider accelerator department (C-AD) RHIC Accelerator Protection Elements Operational Experience Summary BNL Collider Complex Overview

More information

Status of the APEX Project at LBNL

Status of the APEX Project at LBNL at LBNL Fernando Sannibale K. Baptiste, B. Bailey, D. Colomb, C. Cork, J. Corlett, S. De Santis, J. Feng, D. Filippetto, G.Huang, R. Kraft, S. Kwiatkowski, D. Li, M. Messerly, R. Muller, W. E. Norum, H.

More information

XFEL Cryo System. Project X Collaboration Meeting, FNAL September 8-9, 2010 Bernd Petersen DESY MKS (XFEL WP10 & WP13) 1 st stage. Possible extension

XFEL Cryo System. Project X Collaboration Meeting, FNAL September 8-9, 2010 Bernd Petersen DESY MKS (XFEL WP10 & WP13) 1 st stage. Possible extension XFEL Cryo System Possible extension 1 st stage Project X Collaboration Meeting, FNAL September 8-9, 2010 (XFEL WP10 & WP13) Outline 2 XFEL accelerator structure TESLA technology Basic cryogenic parameters

More information

Main linac starting gradient, upgrade gradient, and upgrade path Results of WG5 discussions

Main linac starting gradient, upgrade gradient, and upgrade path Results of WG5 discussions Q3 Main linac starting gradient, upgrade gradient, and upgrade path Results of WG5 discussions 1 Three Upgrade Options 1 : Half-Empty Build tunnel long enough (41km) for one TeV, but install only 500 GeV

More information

Check the LCLS Project website to verify 2 of 7 that this is the correct version prior to use.

Check the LCLS Project website to verify 2 of 7 that this is the correct version prior to use. 1. Introduction: The XTOD Offset System (OMS) is designed to direct the LCLS FEL beam to the instruments and experimental stations, while substantially reducing the flux of unwanted radiation which accompanies

More information

Orbit Stability Challenges for Storage Rings. Glenn Decker Advanced Photon Source Beam Diagnostics March 8, 2012

Orbit Stability Challenges for Storage Rings. Glenn Decker Advanced Photon Source Beam Diagnostics March 8, 2012 Orbit Stability Challenges for Storage Rings Glenn Decker Advanced Photon Source Beam Diagnostics March 8, 2012 Outline Beam stability requirements RF beam position monitor technology NSLS II developments

More information

The ILC Accelerator Complex

The ILC Accelerator Complex The ILC Accelerator Complex Nick Walker DESY/GDE UK LC meeting 3 rd September 2013 Oxford University, UK. 1 ILC in a Nutshell 200-500 GeV E cm e + e - collider L ~2 10 34 cm -2 s -1 upgrade: ~1 TeV central

More information

Superconducting RF System. Heung-Sik Kang

Superconducting RF System. Heung-Sik Kang Design of PLS-II Superconducting RF System Heung-Sik Kang On behalf of PLS-II RF group Pohang Accelerator Laboratory Content 1. Introduction 2. Physics design 3. Cryomodules 4. Cryogenic system 5. High

More information

THE CRYOGENIC SYSTEM OF TESLA

THE CRYOGENIC SYSTEM OF TESLA THE CRYOGENIC SYSTEM OF TESLA S. Wolff, DESY, Notkestr. 85, 22607 Hamburg, Germany for the TESLA collaboration Abstract TESLA, a 33 km long 500 GeV centre-of-mass energy superconducting linear collider

More information

IR HOM Issues. Collection of HOM effects. Sasha Novokhatski SLAC, Stanford University. Parallel Session: RF, HOM, Power June 15, 2006

IR HOM Issues. Collection of HOM effects. Sasha Novokhatski SLAC, Stanford University. Parallel Session: RF, HOM, Power June 15, 2006 IR HOM Issues Collection of HOM effects Sasha Novokhatski SLAC, Stanford University Parallel Session: RF, HOM, Power June 15, 2006 Luminosity and wake fields We need high current beams of short bunches

More information

ELECTRON CLOUD MITIGATION INVESTIGATIONS AT CESR-TA

ELECTRON CLOUD MITIGATION INVESTIGATIONS AT CESR-TA Proceedings of ECLOUD1, Ithaca, New York, USA MIT1 ELECTRON CLOUD MITIGATION INVESTIGATIONS AT CESR-TA J.R. Calvey, J. Makita, M.A. Palmer, R.M. Schwartz, C.R. Strohman, CLASSE, Cornell University, Ithaca,

More information

Hall C Infrastructure Projects Update

Hall C Infrastructure Projects Update Hall C Infrastructure Projects Update Outline Targets Input from tgt group Polarimetry Input from Dave G. Some Other Stuff Greg Smith JLab Jan. 2006 Target Upgrade- Basic Philosophy Need smaller SC for

More information

HIGH POWER COUPLER FOR THE TESLA TEST FACILITY

HIGH POWER COUPLER FOR THE TESLA TEST FACILITY Abstract HIGH POWER COUPLER FOR THE TESLA TEST FACILITY W.-D. Moeller * for the TESLA Collaboration, Deutsches Elektronen-Synchrotron DESY, D-22603 Hamburg, Germany The TeV Energy Superconducting Linear

More information

Radiation Detection by Cerenkov Emission in. Optical Fibers at TTF

Radiation Detection by Cerenkov Emission in. Optical Fibers at TTF Tesla-Report 2-27 Radiation Detection by Cerenkov Emission in Optical Fibers at TTF by E. Janata 1, M. Körfer 2 1 Hahn-Meitner-Institut Berlin, Bereich Solarenergieforschung, D-1419 Berlin 2 Deutsches

More information

REVIEW OF HIGH POWER CW COUPLERS FOR SC CAVITIES. S. Belomestnykh

REVIEW OF HIGH POWER CW COUPLERS FOR SC CAVITIES. S. Belomestnykh REVIEW OF HIGH POWER CW COUPLERS FOR SC CAVITIES S. Belomestnykh HPC workshop JLAB, 30 October 2002 Introduction Many aspects of the high-power coupler design, fabrication, preparation, conditioning, integration

More information

ESS RF Development at Uppsala University. Roger Ruber for the FREIA team Uppsala University

ESS RF Development at Uppsala University. Roger Ruber for the FREIA team Uppsala University ESS RF Development at Uppsala University Roger Ruber for the FREIA team Uppsala University ESS-UU Collaboration 2009 ESS and UU start discussion on 704 MHz RF development proposal for ESS dedicated test

More information

LLRF Operation and Performance of the European XFEL. An overview

LLRF Operation and Performance of the European XFEL. An overview LLRF Operation and Performance of the European XFEL. An overview Mathieu Omet LLRF, Barcelona, 16.10.2017 Contents > Introduction > LLRF commissioning > Energy Reach > LLRF performance > Summary / Outlook

More information

INSTRUMENTATION AND CONTROL SYSTEM FOR THE INTERNATIONAL ERL CRYOMODULE

INSTRUMENTATION AND CONTROL SYSTEM FOR THE INTERNATIONAL ERL CRYOMODULE INSTRUMENTATION AND CONTROL SYSTEM FOR THE INTERNATIONAL ERL CRYOMODULE S. M. Pattalwar, R. Bate, G. Cox, P.A. McIntosh and A. Oates, STFC, Daresbury Laboratory, Warrington, UK Abstract ALICE is a prototype

More information

Calibrating the Cavity Voltage. Presentation of an idea

Calibrating the Cavity Voltage. Presentation of an idea Calibrating the Cavity Voltage. Presentation of an idea Stefan Wilke, DESY MHF-e 21st ESLS rf meeting Kraków, 15th/16th nov 2017 Accelerators at DESY. linear and circular Page 2 Accelerators at DESY. linear

More information

3 General layout of the XFEL Facility

3 General layout of the XFEL Facility 3 General layout of the XFEL Facility 3.1 Introduction The present chapter provides an overview of the whole European X-Ray Free-Electron Laser (XFEL) Facility layout, enumerating its main components and

More information

Message from the Americas

Message from the Americas Message from the Americas G. Dugan, Cornell Univ. for the United States Linear Collider Steering Group (USLCSG) First ILC Workshop KEK, Tsukuba, Japan Nov. 13, 2004 Outline Perspectives on the ILC from

More information

Uppsala, June 17 th - 19 th, 2013

Uppsala, June 17 th - 19 th, 2013 TIARA Workshop on RF Power Generation for Accelerators Uppsala, June 17 th - 19 th, 2013 Massamba DIOP, R. LOPES, P. MARCHAND, F. RIBEIRO SSA operation at SOLEIL BOOSTER 35 kw STORAGE RING 180 kw SOLEIL

More information

Mitigation Plans for the Microbunching-Instability-Related COTR at ASTA/FNAL

Mitigation Plans for the Microbunching-Instability-Related COTR at ASTA/FNAL 1 Mitigation Plans for the Microbunching-Instability-Related COTR at ASTA/FNAL 1.1.1 Introduction A.H. Lumpkin, M. Church, and A.S. Johnson Mail to: lumpkin@fnal.gov Fermi National Accelerator Laboratory,

More information

BEAM DIAGNOSTICS AT THE VUV-FEL FACILITY

BEAM DIAGNOSTICS AT THE VUV-FEL FACILITY BEAM DIAGNOSTICS AT THE VUV-FEL FACILITY J. Feldhaus, D. Nölle, DESY, D-22607 Hamburg, Germany Abstract The free electron laser (FEL) at the TESLA Test facility at DESY, now called VUV-FEL, will be the

More information

Engineering Challenges and Solutions for MeRHIC. Andrew Burrill for the MeRHIC Team

Engineering Challenges and Solutions for MeRHIC. Andrew Burrill for the MeRHIC Team Engineering Challenges and Solutions for MeRHIC Andrew Burrill for the MeRHIC Team Key Components Photoinjector Design Photocathodes & Drive Laser Linac Cavities 703.75 MHz 5 cell cavities 3 rd Harmonic

More information

ERLP Status. Mike Dykes

ERLP Status. Mike Dykes ERLP Status Mike Dykes Content ASTeC RF & Diagnostics Group Work of the Group 4GLS ERLP Photo-injector Accelerating Modules Summary High Power RF Engineering Andy Moss SRS Support; DIAMOND; ERLP; MICE;

More information

PREX- 2 Issues. April 11, Kent Paschke

PREX- 2 Issues. April 11, Kent Paschke PREX- 2 Issues April 11, 2014 Kent Paschke What We Learned in PREX-I What Worked: New Septum We now know how to tune it to optimize FOM A T false asymmetry A T is small (

More information

Resonant Excitation of High Order Modes in the 3.9 GHz Cavity of LCLS-II Linac

Resonant Excitation of High Order Modes in the 3.9 GHz Cavity of LCLS-II Linac Resonant Excitation of High Order Modes in the 3.9 GHz Cavity of LCLS-II Linac LCLS-II TN-16-05 9/12/2016 A. Lunin, T. Khabiboulline, N. Solyak, A. Sukhanov, V. Yakovlev April 10, 2017 LCLSII-TN-16-06

More information

FLASH. FLASH Training: RF Gun. FLASH: the first soft X-ray FEL operating two undulator beamlines simultaneously. Siegfried Schreiber, DESY

FLASH. FLASH Training: RF Gun. FLASH: the first soft X-ray FEL operating two undulator beamlines simultaneously. Siegfried Schreiber, DESY FLASH Training: RF Gun FLASH: the first soft X-ray FEL operating two undulator beamlines simultaneously Siegfried Schreiber, DESY FLASH Training DESY 17-Mar-2017 FLASH1 RF Gun History RF Guns operated

More information

Commissioning the Echo-Seeding Experiment ECHO-7 at NLCTA

Commissioning the Echo-Seeding Experiment ECHO-7 at NLCTA Commissioning the Echo-Seeding Experiment ECHO-7 at NLCTA Stephen Weathersby for the ECHO-7 team D. Xiang, E. Colby, M. Dunning, S. Gilevich, C. Hast, K. Jobe, D. McCormick, J. Nelson, T.O. Raubenheimer,

More information

Dark Current Kicker Studies at FLASH

Dark Current Kicker Studies at FLASH Dark Current Kicker Studies at FLASH F. Obier, J. Wortmann, S. Schreiber, W. Decking, K. Flöttmann FLASH Seminar, DESY, 02 Feb 2010 History of the dark current kicker 2005 Vertical kicker was installed

More information

Electron Cloud Mitigation Investigations at CesrTA

Electron Cloud Mitigation Investigations at CesrTA Electron Cloud Mitigation Investigations at CesrTA Joseph Calvey 8/9/2010 Introduction The density and distribution of the electron cloud can depend strongly on several parameters that can vary substantially

More information

LC Technology Hans Weise / DESY

LC Technology Hans Weise / DESY LC Technology Hans Weise / DESY All you need is... Luminosity! L σ 2 N e x σ y σ y σ x L n b f rep Re-writing reflects the LC choices... L P E b c. m. N e σ σ x y... beam power... bunch population... Ac-to-beam

More information

LUSI Pulse Picker System

LUSI Pulse Picker System ENGINEERING SPECIFICATION DOCUMENT (ESD) Doc. No. SP-391-001-50 R0 LUSI SUB-SYSTEM DCO LUSI Pulse Picker System Rick Jackson Design Engineer, Author Signature Date Marc Campell DCO Design Engineer Signature

More information

ERL based FELs. Todd I Smith Hansen Experimental Physics Laboratories (HEPL) Stanford University Stanford, CA

ERL based FELs. Todd I Smith Hansen Experimental Physics Laboratories (HEPL) Stanford University Stanford, CA ERL based FELs Todd I Smith Hansen Experimental Physics Laboratories (HEPL) Stanford University Stanford, CA 94305-4085 Todd.Smith@Stanford.edu Electrostatic ERL-FELs University of California Santa Barbara

More information

SARAF commissioning & safety issues. L. Weissman on behalf of the SARAF team SPIRAL week 2010

SARAF commissioning & safety issues. L. Weissman on behalf of the SARAF team SPIRAL week 2010 SARAF commissioning & safety issues L. Weissman on behalf of the SARAF team SPIRAL week 2010 1 Outline commissioning of SARAF project : RFQ status Cryomodule status Accumulated beam operation experience

More information

Behavior of the TTF2 RF Gun with long pulses and high repetition rates

Behavior of the TTF2 RF Gun with long pulses and high repetition rates Behavior of the TTF2 RF Gun with long pulses and high repetition rates J. Baehr 1, I. Bohnet 1, J.-P. Carneiro 2, K. Floettmann 2, J. H. Han 1, M. v. Hartrott 3, M. Krasilnikov 1, O. Krebs 2, D. Lipka

More information

Compact Radio Frequency Technology for Applications in Cargo and Global

Compact Radio Frequency Technology for Applications in Cargo and Global Compact Radio Frequency Technology for Applications in Cargo and Global Security Peter McIntosh STFC Daresbury Laboratory CLASP Security Event Tuesday 5 th July 2011, London Compact RF Technologies S-band

More information

Pulsed 5 MeV standing wave electron linac for radiation processing

Pulsed 5 MeV standing wave electron linac for radiation processing PHYSICAL REVIEW SPECIAL TOPICS - ACCELERATORS AND BEAMS, VOLUME 7, 030101 (2004) Pulsed 5 MeV standing wave electron linac for radiation processing L. Auditore, R. C. Barnà, D. De Pasquale, A. Italiano,

More information

BaBar and PEP II. Physics

BaBar and PEP II. Physics BaBar and PEP II BaBar SVT DCH DIRC ECAL IFR Trigger Carsten Hast LAL Orsay December 8th 2000 Physics Main Goal: CP Violation sin2β,sin2α PEP II Performance Backgrounds December 8th 2000 Carsten Hast PEP

More information

REAL-TIME DISPLAY SYSTEM FOR THE OPTICAL FIBER BEAM LOSS MONITOR FOR THE PHIL AND THOMX FACILITIES

REAL-TIME DISPLAY SYSTEM FOR THE OPTICAL FIBER BEAM LOSS MONITOR FOR THE PHIL AND THOMX FACILITIES REAL-TIME DISPLAY SYSTEM FOR THE OPTICAL FIBER BEAM LOSS MONITOR FOR THE PHIL AND THOMX FACILITIES I. Chaikovska, N. Delerue, A. Variola, Laboratoire de l Accélérateur Linéaire, CNRS-IN2P3, Université

More information

Nonintercepting Diagnostics for Transverse Beam Properties: from Rings to ERLs

Nonintercepting Diagnostics for Transverse Beam Properties: from Rings to ERLs Nonintercepting Diagnostics for Transverse Beam Properties: from Rings to ERLs Alex H. Lumpkin Accelerator Operations Division Advanced Photon Source Presented at Jefferson National Accelerator Laboratory

More information

1.8 MW Upgrade of the PSI Proton Accelerator Facility

1.8 MW Upgrade of the PSI Proton Accelerator Facility 1.8 MW Upgrade of the PSI Proton Accelerator Facility Pierre A. Schmelzbach for the PSI Accelerator Divisions This talk: analyzes the potential for improvements from the ion source to the spallation target

More information

Preliminary Plan for a Hadron Production Facility at the SLAC A-Line and End Station A

Preliminary Plan for a Hadron Production Facility at the SLAC A-Line and End Station A Preliminary Plan for a Hadron Production Facility at the SLAC A-Line and End Station A R. Arnold, T. Fieguth, C. Hast, M. Woods, D. Walz ILC-SLACESA TN-2007-2 October 3, 2007 1. Overview A facility for

More information

SIMULATION OF A SIGNAL IN THE BEAM LOSS

SIMULATION OF A SIGNAL IN THE BEAM LOSS RADIATION ASPECTS OF LHC SIMULATION OF A SIGNAL IN THE BEAM LOSS MONITORS OF THE MOMENTUM CLEANING INSERTION FOR THE NEW COLLIMATOR JAWS DESIGN IHEP, Protvino, Russia Summary of the presentation Page 1

More information