1 PROJECT MANUAL P R O P E R T Y M A N A G E M E N T F A L L O N C O U N T Y Proposal P.O. Box 846 Baker, MT P R E C A S T R E I N F O R C E D C O N C R E T E B O X C U L V E R T F O R W E S T M O R E A N D D R Y F O R K R O A D S Project No.: M13B199 & M13B53

2

3 QUOTE Proposal of (hereinafter called "BIDDER"), organized and existing under the laws of the State of, doing business as * to the Fallon County commission (hereinafter called "OWNER"). In compliance with your Advertisement for Quotes, BIDDER hereby proposes to Fabricate, Store, & Deliver various PRECAST REINFORCED CONCRETE BOX CULVERTS WITH END SECTIONS; in strict accordance with the CONTRACT DOCUMENTS, within the time set forth therein, and at the prices stated below. By submission of this QUOTE, each BIDDER certifies and in the case of a joint QUOTE, each party thereto certifies as to his own organization, that this QUOTE has been arrived at independently, without consultation, communication, or agreement as to any matter relating to this QUOTE with any other BIDDER or with any competitor. The Precast Reinforced Concrete Box Culvert shall be completed and available for delivery by July 1, BIDDER acknowledges receipt of the following ADDENDUM: *Insert Corporation, Partnership, or Individual, as applicable.

4 BIDDER agrees to perform all the work described in the CONTRACT DOCUMENTS for the following unit prices or lump sum: NOTE: QUOTE shall include shipping, sales tax, and all other applicable taxes and fees. Bidder may provide quote for Schedule I, Schedule II, or both. Owner reserves the right to award one, both, or neither Schedules. Award will be made to the lowest responsible Bidder for each Schedule. SCHEDULE I WESTMORE REINFORCED CONCRETE BOX CULVERT ITEM DESCRIPTION UNIT UNIT PRICE EXTENDED PRICE 1. SINGLE 14 X 11 PRECAST RCB CULVERT 2. SINGLE 14 X 11 PRECAST RCBC END SECTION 198 FT 6 EACH TOTAL $ SCHEDULE II DRY FORK ROAD REINFORCED CONCRETE BOX CULVERT ITEM DESCRIPTION UNIT UNIT PRICE EXTENDED PRICE 1. SINGLE 14 X 14 PRECAST RCB CULVERT 2. SINGLE 14 X 14 PRECAST RCBC END SECTION 3. DBL 14 X 14 PRECAST RCB CULVERT 4. DBL 14 X 14 PRECAST RCBC END SECTION 52 FT 2 EACH 52 FT 2 EACH TOTAL $

5 Respectfully submitted: Signature Address Title Date License Number (If Applicable) (SEAL * If QUOTE is by a Corporation) Attest:

6 SPECIFICATIONS The Precast Reinforced Concrete Box Culverts shall conform to requirements as specified in the Standard Specifications for Road and Bridge Construction of the Montana Department of Transportation, 2014 Edition. DESIGN MIX OF CONCRETE 1. The design minimum 28 day compressive strength of concrete shall be as per fabricator s design, however shall not be less than 4,500 psi. 2. Type V Cement shall be used. GENERAL NOTES Design shall be in accordance with Section 554 of the Specifications, with the following criteria: 1. Box culvert and box culvert end section design shall conform to the AASHTO LRFD Bridge Designs Specifications, 2014 Edition with 2015 interims. 2. Design Live Load: HL The design of the barrel sections shall be based on a minimum fill height of 1 foot and include all subsequent fill heights up to and including the maximum fill height of 5 foot over the box culvert. 4. Minimum inside corner fillet shall be 6 inches. 5. Minimum precast barrel section length shall be 4 feet. 6. The Contractor shall stencil the structure with the date of construction. 7. Contractor shall provide a minimum of four (4) Galvanized Hidden Tie Bolts for between each end section and each full barrel section of the RCB Culvert. 8. Contractor shall provide Galvanized Sleeves, Type IV Epoxy, and #5 Epoxy Coated Rebar 16 inches in length in floor of box for cutoff walls. Galvanized Sleeves shall be cast into the upstream and downstream most end sections with a minimum of five (5) Sleeves required per barrel section at the upstream and downstream ends. 9. Contractor shall provide EZ-STIK Joint Sealant by Press-Seal for all joints. 10. Contractor shall provide Sealwrap Primer and Sealwrap by Mar Mac for all joints, lifting holes, and pulling holes.

7 11. Contractor shall provide Non-shrink Grout for all lifting and pulling holes. 12. Contractor shall provide Panel Hooks, Eye Bolts, and Concrete Inserts for the RCB Culvert as shown on the Fence Anchor Details. 13. Cutoff Walls and Parapets shall be provided as shown on the General Layout Drawing and included with the quote price per each for the various types of End Section. DELIVERY AND STORAGE 1. All costs for storage, loading, transporting, and delivery to the project site shall be included in the quote for the Precast Concrete Box Culvert. SHOP PLANS 1. The fabricator shall submit shop drawings in accordance with the specifications to Brosz Engineering Inc., PO Box 357, Bowman, ND for review. Include design and check design with initial submittal. After review, corrections (if necessary), and approval by Brosz Engineering Inc., the Engineer will authorize fabrication.

8

9

10

11

12

SECTION G ESTIMATE OF QUANTITIES

SECTION G ESTIMATE OF QUANTITIES PROJECT STATE OF SOUTH DAKOTA NH 2115(45)87 SHEET G2 TOTAL SHEETS G27 SECTION G ESTIMATE OF QUANTITIES BID ITEM NUMBER ITEM QUANTITY UNIT 009E0010 Mobilization Lump Sum LS 560E0068 7'x3' Precast Concrete

More information

SPECIFICATIONS FOR THE MANUFACTURE AND DESIGN OF PRECAST THREE SIDED ARCH STRUCTURES, WINGWALLS AND HEADWALLS

SPECIFICATIONS FOR THE MANUFACTURE AND DESIGN OF PRECAST THREE SIDED ARCH STRUCTURES, WINGWALLS AND HEADWALLS SPECIFICATIONS FOR THE MANUFACTURE AND DESIGN OF PRECAST THREE SIDED ARCH STRUCTURES, WINGWALLS AND HEADWALLS 1. DESCRIPTION THESE SPECIFICATIONS ARE FOR A PRECAST THREE SIDED ARCH STRUCTURE, HEADWALLS

More information

Standard Specifications

Standard Specifications Standard Specifications PART 1.00 GENERAL 1.01 DECRIPTION SECTION 02620 PRECAST REINFORCED CONCRETE SANITARY MANHOLES A. Work included: The Contractor shall furnish all labor, materials, equipment, and

More information

BID DOCUMENTS FOR THE PURCHASE OF PRECAST CONCRETE BOX CULVERT

BID DOCUMENTS FOR THE PURCHASE OF PRECAST CONCRETE BOX CULVERT February 04, 2016 BID DOCUMENTS FOR THE PURCHASE OF PRECAST CONCRETE BOX CULVERT The Bid Documents that are included as part of the above bid package include the following: 1). Instructions to bidders

More information

CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT

CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT ADDENDUM NO. 1 TO REQUEST FOR PROPOSALS For EQUIPMENT FOR THE 2014 CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT WASTEWATER TREATMENT PLANT IMPROVEMENT PROJECT:

More information

SECTION PRECAST CONCRETE SECTIONAL MANHOLES

SECTION PRECAST CONCRETE SECTIONAL MANHOLES SECTION 02545 PRECAST CONCRETE SECTIONAL MANHOLES PART 1 - GENERAL 1.01 SUMMARY A. Section Includes: 1. Precast reinforced concrete cylindrical sectional manholes, complete with openings, inserts, hardware,

More information

SECTION 58 PRECAST CONCRETE BOX CULVERT. This work consists of furnishing and installing Pre-cast Concrete Box Culverts.

SECTION 58 PRECAST CONCRETE BOX CULVERT. This work consists of furnishing and installing Pre-cast Concrete Box Culverts. SECTION 58 PRECAST CONCRETE BOX CULVERT 58.1 DESCRIPTION A. General This work consists of furnishing and installing Pre-cast Concrete Box Culverts. B. Related Work Section 51 Section 52 Section 53 Section

More information

SECTION 1085 PRECAST REINFORCED CONCRETE BOX CULVERT

SECTION 1085 PRECAST REINFORCED CONCRETE BOX CULVERT 1085.1 1085.2(k) SECTION 1085 PRECAST REINFORCED CONCRETE BOX CULVERT 1085.1 DESCRIPTION This work is the manufacture, storage, delivery, installation, and assembly of precast reinforced concrete box culvert

More information

A. Extent of structural precast concrete work is shown on drawings and in schedules.

A. Extent of structural precast concrete work is shown on drawings and in schedules. SECTION 03 41 00 - STRUCTURAL PRECAST CONCRETE PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 specification

More information

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION Sheet 1 of 5 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION NOTE: This special provision is generally written in the imperative mood. The subject, "the

More information

CHAPTER 10 MICHIGAN DESIGN MANUAL BRIDGE DESIGN (SI) SHOP DRAWING REVIEW TYPES OF SHOP DRAWINGS Structural Steel

CHAPTER 10 MICHIGAN DESIGN MANUAL BRIDGE DESIGN (SI) SHOP DRAWING REVIEW TYPES OF SHOP DRAWINGS Structural Steel CHAPTER 10 SHOP DRAWING REVIEW 10.01 TYPES OF SHOP DRAWINGS 10.01.01 Structural Steel 10.01.02 Prestressed Concrete 10.01.03 Bearings 10.01.04 Metal Stay - In - Place Forms () 10.01.05 Expansion Joints

More information

OHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. BROAD ST., COLUMBUS, OHIO

OHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. BROAD ST., COLUMBUS, OHIO OHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. BROAD ST., COLUMBUS, OHIO 43216-0899 July 20, 2012 To: Users of the Standard Bridge Drawings From: Tim Keller, Administrator, Office of Structural

More information

2016 Specification Treads, Base, Stringers and other Amenities Wausau Tile Precast Epoxy Terrazzo

2016 Specification Treads, Base, Stringers and other Amenities Wausau Tile Precast Epoxy Terrazzo 2016 Specification Treads, Base, Stringers and other Amenities 09400 Wausau Tile Precast Epoxy Terrazzo PART 1 - GENERAL 1.1 SUMMARY A. Perform all work required to complete, as indicated by the Contract

More information

MANHOLES PART I: GENERAL. A. Precast Concrete Manholes

MANHOLES PART I: GENERAL. A. Precast Concrete Manholes MANHOLES PART I: GENERAL A. Precast Concrete Manholes 1) Manholes shall be made of precast concrete sections of which the top section shall be eccentric or flat slab top. The bottom section shall be a

More information

MH Table of Contents Standard Title/Scope Page Table of Contents SCE Public

MH Table of Contents Standard Title/Scope Page Table of Contents SCE Public MH Table of Contents Standard Title/Scope MH 300 MH 310 MH 318 MH 320 MH 325 MH 330 MH 335 MH 340 MH 350 Manholes Requirements MH 300.1 Manholes Requirements...........................................

More information

STATE OF TEXAS Agreement of Sale COUNTY OF TARRANT

STATE OF TEXAS Agreement of Sale COUNTY OF TARRANT STATE OF TEXAS Agreement of Sale COUNTY OF TARRANT This agreement is made and entered into by and between MORREL STUDIOS INC., ( Artist or Studios ), a New York corporation and the CITY OF ARLINGTON, TEXAS

More information

3400 Tectura Designs Precast Concrete

3400 Tectura Designs Precast Concrete 3400 Tectura Designs Precast Concrete PART 1 - GENERAL 1.1 SUMMARY A. Perform all work required to furnish and complete the proper installation of precast concrete. B. Types of Precast Concrete work include:

More information

PROCEDURE FOR PROCESSING WORKING DRAWINGS

PROCEDURE FOR PROCESSING WORKING DRAWINGS PROCEDURE FOR PROCESSING WORKING DRAWINGS MAY 2005 Procedure for Processing Working Drawings GENERAL: The procedure for the review and processing of working drawings provide for two primary types of drawings,

More information

Manholes Table of Contents

Manholes Table of Contents Standard MH 300 Title Manholes Requirements MH 300.1 Manholes Requirements Manholes Table of Contents Underground Structures Standards MH 310 MH 318 MH 320 MH 325 MH 330 MH 335 MH 340 MH 350 Precast Tub-Type

More information

WAL-MART SUPERCENTER # ; Milwaukie, OR: SPECIFICATIONS. Revisions to Specification Fence

WAL-MART SUPERCENTER # ; Milwaukie, OR: SPECIFICATIONS. Revisions to Specification Fence MILWAUKIE OR #3144-00 ADDENDUM #5 NARRATIVE: 11-08-12 WAL-MART SUPERCENTER #3144-00; Milwaukie, OR: SPECIFICATIONS SPECIFICATIONS Revisions to Specification 02822 Fence Spec division 02822 has been revised

More information

SECTION STEEL LIGHTING STANDARDS. 1. Electrical conduit and fittings; Section

SECTION STEEL LIGHTING STANDARDS. 1. Electrical conduit and fittings; Section 02760-1 of 5 SECTION 02760 STEEL LIGHTING STANDARDS 02760.01 GENERAL A. Description Steel lighting standards shall include, but not necessarily be limited to, furnishing and installing steel lighting poles,

More information

shawprecastsolutions.com BEBO Arch Systems PRODUCT GUIDE & TECHNICAL REFERENCE MANUAL Providing the right solutions.

shawprecastsolutions.com BEBO Arch Systems PRODUCT GUIDE & TECHNICAL REFERENCE MANUAL Providing the right solutions. shawprecastsolutions.com BEBO Arch Systems PRODUCT GUIDE & TECHNICAL REFERENCE MANUAL Providing the right solutions. BEBO ARCH SYSTEMS BEBO ARCH units are high quality, low maintenance precast structures

More information

10930 W. Sam Houston Parkway N., Suite 900

10930 W. Sam Houston Parkway N., Suite 900 ADDENDUM NO. 1 10930 W Sam Houston Pkwy. North Suite 900 Houston, Texas 77064 281.664.1900 281.664.1912 (f) www.salasobrien.com March 21, 2018 Project: Prepared by: Taylor Career Center Welding Labs Beaumont

More information

Utility Structures. Utility vaults, trenches, transformer pads Electrical Pole Bases and switching cubicles

Utility Structures. Utility vaults, trenches, transformer pads Electrical Pole Bases and switching cubicles Utility Structures Utility vaults, trenches, transformer pads Electrical Pole Bases and switching cubicles PRODUCT GUIDE & TECHNICAL REFERENCE MANUAL Providing the right solutions. UTILITY STRUCTURES Perfect

More information

CITY OF PITTSBURG ENGINEERING DEPARTMENT CONTRACT NO A WATER TREATEMENT PLANT CAPITAL IMPROVEMENTS PHASE 1A ADDENDUM #1 FENCE AND DITCH AUGUST

CITY OF PITTSBURG ENGINEERING DEPARTMENT CONTRACT NO A WATER TREATEMENT PLANT CAPITAL IMPROVEMENTS PHASE 1A ADDENDUM #1 FENCE AND DITCH AUGUST CITY OF PITTSBURG ENGINEERING DEPARTMENT CONTRACT NO. 2012-16A WATER TREATEMENT PLANT CAPITAL IMPROVEMENTS PHASE 1A ADDENDUM #1 FENCE AND DITCH AUGUST 2014 CHAIN LINK FENCE SPECIFICATIONS Chain link fence,

More information

SECTION METAL FABRICATIONS

SECTION METAL FABRICATIONS SECTION 05100 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for metal fabrications, including minimum requirements for fabricator, and galvanizing. 1.02 REFERENCE STANDARDS A. ASTM

More information

HOME STRENGTHENING GUIDE HOW TO ECONOMICALLY STRENGTHEN YOUR HOUSE AGAINST EARTHQUAKES AND HURRICANES

HOME STRENGTHENING GUIDE HOW TO ECONOMICALLY STRENGTHEN YOUR HOUSE AGAINST EARTHQUAKES AND HURRICANES HOME STRENGTHENING GUIDE HOW TO ECONOMICALLY STRENGTHEN YOUR HOUSE AGAINST EARTHQUAKES AND HURRICANES Grenville W Phillips II BSc, BEng, MASc, MURP, CEng, FIStructE, FCIHT, MAPM, MCSCE, MBAPE Chartered

More information

White Lake Township Building Dept Highland Rd. (248) White Lake, MI Fax (248)

White Lake Township Building Dept Highland Rd. (248) White Lake, MI Fax (248) White Lake Township Building Dept. 7525 Highland Rd. (248) 698-3300 SUBMITTAL REQUIREMENTS FOR SINGLE FAMILY HOMES, ADDITIONS, GARAGES AND RENOVATIONS --NEW-- Package for new residences must include $

More information

SECTION MANHOLES

SECTION MANHOLES SECTION 02601 MANHOLES PART 1 GENERAL 1.01 SCOPE OF WORK A. WORK required under this section consists of all materials, accessories, equipment, tools, and labor required to install precast concrete standard

More information

Digitally Signed 06/02/2015

Digitally Signed 06/02/2015 Digitally Signed 06/0/05 Digitally Signed 06/0/05 Digitally Signed 06/0/05 FED. ROAD DIST. NO. STATE FED. AID PROJ. NO. SHEET NO. TOTAL SHEETS 6--5 6 ARK. JOB NO. 08057 6 8 075 QUANTITIES 5706 SUMMARY

More information

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES SECTION 01334 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES PART 1 GENERAL 1.01 SUMMARY A. Submit to the ENGINEER for review, such working drawings, shop drawings, test reports and data on materials and equipment

More information

SPECIFICATIONS PROPOSAL & BID DOCUMENT

SPECIFICATIONS PROPOSAL & BID DOCUMENT Cerro Gordo County Department of Public Health LEAD-BASED PAINT HAZARD CONTROL PROGRAM IALHB0628-16 SPECIFICATIONS PROPOSAL & BID DOCUMENT Property: 13 N Monroe Tenant s Relocating: Yes No Lead Based Paint

More information

StormTrap Guide Specification. StormTrap SingleTrap on Pad Foundation Groundwater BELOW Invert Revised 11/21/18

StormTrap Guide Specification. StormTrap SingleTrap on Pad Foundation Groundwater BELOW Invert Revised 11/21/18 StormTrap Guide Specification StormTrap SingleTrap on Pad Foundation Groundwater BELOW Invert Revised 11/21/18 This product guide specification is written according to the Construction Specifications Institute

More information

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENT 1073 PRECAST CONCRETE CERTIFICATION PROGRAM JULY 20, 2018

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENT 1073 PRECAST CONCRETE CERTIFICATION PROGRAM JULY 20, 2018 STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENT 1073 PRECAST CONCRETE CERTIFICATION PROGRAM JULY 20, 2018 1073.01 Program Overview 1073.02 Qualification 1073.03 Documentation Phase 1073.04 Documentation

More information

SECTION PRECAST CONCRETE STRUCTURES

SECTION PRECAST CONCRETE STRUCTURES SECTION 02605 PRECAST CONCRETE STRUCTURES PART 1 GENERAL 1.01 DESCRIPTION A. CONTRACTOR shall provide all professional services, labor, materials, equipment and incidentals as shown, specified and required

More information

SECTION STRUCTURAL STEEL. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION STRUCTURAL STEEL. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 051200 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

BPDL Architectural precast concrete specifications USA TESTING AND INSPECTION A. Testing by Independent Agency : Materials and workmanship furn

BPDL Architectural precast concrete specifications USA TESTING AND INSPECTION A. Testing by Independent Agency : Materials and workmanship furn BPDL Architectural precast concrete specifications USA 01 PART 1 General 1.1 DESCRIPTION OF WORK The work includes, but is not limited to : 1. Architectural precast concrete 2. Structural design, fabrication,

More information

November 16, 2017 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA. Y CH / Addendum #6 SHERRY DRIVE BRIDGE REPLACEMENT

November 16, 2017 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA. Y CH / Addendum #6 SHERRY DRIVE BRIDGE REPLACEMENT November 16, 2017 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA Y18-703-CH / Addendum #6 SHERRY DRIVE BRIDGE REPLACEMENT REVISED BID OPENING DATE: DECEMBER 5, 2017 This addendum is hereby incorporated

More information

PART MATERIALS. Section Fencing Materials. Description

PART MATERIALS. Section Fencing Materials. Description PART 03000 - MATERIALS Section 03010 - Fencing Materials Description 03010.00 Scope - This section consists of the test requirements, specifications and tolerances for barbed wire, woven wire and chain

More information

Pipe Product Catalog Table of Contents

Pipe Product Catalog Table of Contents Pipe Product Catalog Table of Contents Section A: Drawing #: Page Description A1 Reinforced Concrete Pipe A3 Storm Manhole Sizing Chart (48" - 96") A3.1 Storm Manhole Sizing Chart (108" - 144") A4 48"

More information

Large Scale CalArc Pavers for Sand-Set Pedestrian Use Installations

Large Scale CalArc Pavers for Sand-Set Pedestrian Use Installations The following specification refers to the Stepstone, Inc. product known as: Large Scale CalArc Pavers for Sand-Set Pedestrian Use Installations Large Scale CalArc Pavers are part of the California Architectural

More information

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 422 MAY 1993 CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS 422.01 SCOPE 422.02 REFERENCES 422.03 DEFINITIONS

More information

SECTION COUNTERTOPS ecox PART 1 GENERAL

SECTION COUNTERTOPS ecox PART 1 GENERAL SECTION 11456 COUNTERTOPS ecox PART 1 GENERAL 1.1 SECTION INCLUDES A. Countertops B. Bar tops C. Vanity tops D. Table tops E. Reception counters F. Cash/back wraps G. Transaction counters H. Service counters

More information

EMMEGI ARCHITECTURAL FENCING MASTER SPECIFICATION SECTION METAL FENCING, GATES & RAILING SYSTEM PART 1 GENERAL

EMMEGI ARCHITECTURAL FENCING MASTER SPECIFICATION SECTION METAL FENCING, GATES & RAILING SYSTEM PART 1 GENERAL EMMEGI ARCHITECTURAL FENCING MASTER SPECIFICATION SECTION 05720 METAL FENCING, GATES & RAILING SYSTEM PART 1 GENERAL EMMEGI ARCHITECTURAL FENCING is a high quality steel fencing system comprised of a hybrid

More information

SECTION CHAIN LINK FENCING AND GATES AND SOFTBALL BACKSTOP

SECTION CHAIN LINK FENCING AND GATES AND SOFTBALL BACKSTOP 1 1 1 0 1 0 1 0 1 SECTION 1 1 CHAIN LINK FENCING AND GATES AND SOFTBALL BACKSTOP BASED ON DFD MASTER SPECIFICATION DATED /01/ P A R T 1 - G E N E R A L SCOPE The work under this section shall consist of

More information

B. Bidders shall acknowledge receipt of this Addendum in writing on his Proposal Form.

B. Bidders shall acknowledge receipt of this Addendum in writing on his Proposal Form. McKee and Associates Architecture and Interior Design Addendum No. THREE Date: 12.11.17 Project: A NEW BUILDING FOR THE GREATER LIMESTONE COUNTY CHAMBER OF COMMERCE ATHENS, ALABAMA A3.1 GENERAL PROJECT

More information

SUBMITTAL REQUIREMENTS FOR COMMERCIAL SIGNAGE PROJECTS

SUBMITTAL REQUIREMENTS FOR COMMERCIAL SIGNAGE PROJECTS SUBMITTAL REQUIREMENTS FOR COMMERCIAL SIGNAGE PROJECTS When submitting your application for Commercial projects please include the following: 1. Completed Building Permit Application with page 2 stamped

More information

ADDENDUM NO. 2. Furnace Bridge - Installation. Essex County, NY. July 29, 2015

ADDENDUM NO. 2. Furnace Bridge - Installation. Essex County, NY. July 29, 2015 ADDENDUM NO. 2 Furnace Bridge - Installation Essex County, NY July 29, 2015 TO ALL HOLDERS OF BIDDING DOCUMENTS: This Addendum, issued to bid document holders of record, indicates clarifications to the

More information

Edgerail Aluminum Bridge Railing System Specification & Installation Instructions

Edgerail Aluminum Bridge Railing System Specification & Installation Instructions Edgerail System Specification & Installation Instructions Hill & Smith, Inc 1000 Buckeye Park Road Columbus, Ohio 43207 Tel: 614-340-6294 Fax: 614-340-6296 www.hillandsmith.com Section A System Specification

More information

UNDERGROUND UTILITY TRENCHES AND VAULTS Page 1 of 6 ADDENDUM #1

UNDERGROUND UTILITY TRENCHES AND VAULTS Page 1 of 6 ADDENDUM #1 Page 1 of 6 ADDENDUM #1 PART 1 GENERAL 1.01 PRINCIPAL WORK IN THIS SECTION A. The requirements of the Owner's General Conditions, Supplementary Conditions, Special Conditions, and Division 1 - General

More information

SECTION PRECAST HOLLOW CORE PLANKS

SECTION PRECAST HOLLOW CORE PLANKS PART 1 GENERAL 1.1 SECTION INCLUDES A. Roof planks. B. Floor planks. C. Accessories. 1.2 RELATED REQUIREMENTS A. Division 01 General Requirements. SECTION 03 4113 PRECAST HOLLOW CORE PLANKS B. Section

More information

UCCS University Hall Fire Sprinkler System Upgrade March 1, 2011 RTA SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL

UCCS University Hall Fire Sprinkler System Upgrade March 1, 2011 RTA SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 3300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

SECTION CHAIN LINK FENCING AND GATES

SECTION CHAIN LINK FENCING AND GATES PART 1 GENERAL 1.01 SCOPE OF WORK A. The Contractor shall furnish and install all materials, labor, equipment and incidentals required to provide chain link fencing and gates as Shown on the Contract Drawings

More information

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES SECTION 01340 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES PART 1 GENERAL 1.01 SUMMARY A. Section Includes: Shop drawings, manufacturer's catalog cuts, product data, samples, and attached Shop Drawing/ Catalog

More information

STANDARD SPECIFICATIONS SECTION SUBMITTAL PROCEDURES

STANDARD SPECIFICATIONS SECTION SUBMITTAL PROCEDURES STANDARD SPECIFICATIONS SECTION 01330 SUBMITTAL PROCEDURES PART 1 GENERAL 1.1 DESCRIPTION A. Section includes general requirements and procedures related to preparation and transmittal of Submittals to

More information

Construction Phase Project Management and Documentation

Construction Phase Project Management and Documentation Construction Phase Project Management and Documentation Bill Mason CDM Smith Outline Design Bidding Construction Start-up & Closeout 2 DESIGN Design Preliminary Engineering Report Plans Specifications

More information

ADDENDUM NO. 3 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO COM.00030

ADDENDUM NO. 3 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO COM.00030 ADDENDUM NO. 3 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO. 2018-008-COM.00030 To: Prospective Bidders of Record Date: January 8, 2019 The following changes, additions, revisions, and/or deletions

More information

SECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 013300 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

Section 914. JOINT AND WATERPROOFING MATERIALS

Section 914. JOINT AND WATERPROOFING MATERIALS 914.01 Section 914. JOINT AND WATERPROOFING MATERIALS 914.01. General Requirements. Joint and waterproofing material for use in concrete construction must meet the requirements of this section. 914.02.

More information

To: New York State Department of Transportation ENGINEERING INSTRUCTION. Approved:

To: New York State Department of Transportation ENGINEERING INSTRUCTION. Approved: To: New York State Department of Transportation ENGINEERING INSTRUCTION Title: PRECAST CONCRETE PAVEMENT SLAB SYSTEMS STANDARD SPECIFICATION Distribution: Manufacturers (18) Local Govt. (31) Agencies (32)

More information

NITTERHOUSE CONCRETE PRODUCTS, INC Molly Pitcher Highway South Chambersburg, PA

NITTERHOUSE CONCRETE PRODUCTS, INC Molly Pitcher Highway South Chambersburg, PA NITTERHOUSE CONCRETE PRODUCTS, INC. 2655 Molly Pitcher Highway South Chambersburg, PA 17201 717-267-4505 GUIDE SPECIFICATION FOR ARCHITECTURAL PRECAST CONCRETE INDEX Page PART I - GENERAL...1 A. DESCRIPTION...1

More information

GENERAL ISOMETRIC LAYOUT

GENERAL ISOMETRIC LAYOUT EXISTING OR PROPOSED WIPER WALL SUPPORT STRUCTURE GATE LID CARBATHAN HG 0 WEB GRAY LOWER PAN GRATING ALUMINUM WIPER WALL CARBATHANE HG, 90 GRAY STRUCTURAL SPECIFICATIONS:. FLOODGATE MATERIAL TO BE ALUMINUM

More information

GRICE-TRIVERS JOINT VENTURE ARCHITECTS PAGE 1 PROJECT NO

GRICE-TRIVERS JOINT VENTURE ARCHITECTS PAGE 1 PROJECT NO PAGE PROJECT NO. 0-0 0 0 0 0 0 DATE: PROJECT: GATEWAY STEM ATHLETICE FIELD ALTERATIONS GATEWAY STEM HIGH SCHOOL - ST. LOUIS PUBLIC SCHOOLS 0 MCRTEE AVENUE ST. LOUIS, MISSOURI 0 TO BID DOCUMENTS DATED DECEMBER,

More information

SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS SECTION 01 33 00 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

INVITATION FOR BID (IFB) IFB NO. GSWA

INVITATION FOR BID (IFB) IFB NO. GSWA INVITATION FOR BID (IFB) IFB NO. GSWA-005-16 AGAT AND MALOJLOJ RESIDENTIAL TRANSFER STATION IMPROVEME AND DEDEDO RESIDENTIAL TRANSFER STATION CLOSURE ADDENDUM NO. 6 September 22, 2016 ALL BIDDERS MUST

More information

Taylor County July 2011 SECTION SHOP DRAWINGS, WORKING DRAWINGS AND SAMPLES

Taylor County July 2011 SECTION SHOP DRAWINGS, WORKING DRAWINGS AND SAMPLES SECTION 01340 SHOP DRAWINGS, WORKING DRAWINGS AND SAMPLES PART 1 - GENERAL 1.1 REQUIREMENTS INCLUDED A. Contractor shall submit to the Architect/Engineer for review and exception, if any, such working

More information

SUBSTATION SECURITY WALL INSTALLATION MANUAL

SUBSTATION SECURITY WALL INSTALLATION MANUAL SUBSTATION SECURITY WALL INSTALLATION MANUAL JULY 26, 2016 OLDCASTLE PRECAST, INC. 3000 New McEver Rd, Acworth, Ga 30101 Substation Security Wall Installation Manual This Installation Manual is intended

More information

Working Drawing Manual

Working Drawing Manual Working Drawing Manual 2012 Table of Contents Section 1 Working Drawing Types... 1 1.1 General... 1 Section 2 Processing Steps... 1 2.1 Project Manager... 1 2.2 Engineering Document Unit... 2 2.3 Contractor...

More information

Special Provision No. 999F29 March 2018 REQUIREMENTS FOR INSTALLATION OF METALLIC DOWELS INTO CONCRETE

Special Provision No. 999F29 March 2018 REQUIREMENTS FOR INSTALLATION OF METALLIC DOWELS INTO CONCRETE DOWELS INTO CONCRETE - Item No. Special Provision No. 999F29 March 2018 REQUIREMENTS FOR INSTALLATION OF METALLIC DOWELS INTO CONCRETE 1.0 SCOPE This Special Provision covers the performance requirements

More information

APPLICATION FOR PLANNED UNIT DEVELOPMENT (PUD) DEVELOPMENT PLAN

APPLICATION FOR PLANNED UNIT DEVELOPMENT (PUD) DEVELOPMENT PLAN 209 S. Main Street Marysville, Ohio 43040 Phone: (937) 645-7350 Fax: (937) 645-7351 www.marysvilleohio.org APPLICATION FOR PLANNED UNIT DEVELOPMENT (PUD) DEVELOPMENT PLAN *** IMPORTANT INFORMATION ~ Please

More information

SECTION SHEET METAL FLASHING AND TRIM

SECTION SHEET METAL FLASHING AND TRIM SECTION 07620 SHEET METAL FLASHING AND TRIM PART 1 GENERAL 1.1 SUMMARY A. Section includes flashings and counterflashings, sheet metal roofing and fabricated sheet metal items, as indicated in Schedule.

More information

StormTrap Guide Specification. StormTrap 2 SingleTrap on Aggregate Foundation Groundwater BELOW Invert Revised 11/30/17

StormTrap Guide Specification. StormTrap 2 SingleTrap on Aggregate Foundation Groundwater BELOW Invert Revised 11/30/17 StormTrap Guide Specification StormTrap 2 SingleTrap on Aggregate Foundation Groundwater BELOW Invert Revised 11/30/17 This product guide specification is written according to the Construction Specifications

More information

Chapter 1 General Design Information

Chapter 1 General Design Information Chapter 1 General Information Introduction The primary aim in both designing and checking is to produce a structure that will safely carry the anticipated loads. The design team, consisting of the designers,

More information

SECTION STRUCTURAL STEEL FRAMING PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION STRUCTURAL STEEL FRAMING PART 1 - GENERAL 1.1 RELATED DOCUMENTS SECTION 05 12 00 - STRUCTURAL STEEL FRAMING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

Efficient Tactics of Project Management

Efficient Tactics of Project Management Ohio Structure Steel & Architectural Metals Association Efficient Tactics of Project Management Friday, June 23, 2017 Mark V. Holland, P.E. Chief Engineer Paxton & Veirling Steel Co. How to get paid. This

More information

SECTION MANHOLES

SECTION MANHOLES SECTION 33 05 13 MANHOLES PART 1 GENERAL 1.01 SECTION INCLUDES A. CONTRACTOR shall furnish and install precast concrete manhole base, sections, adjusting rings, steps, and manhole ring and cover, complete.

More information

Special Provision No. 999S29 May 2010

Special Provision No. 999S29 May 2010 DOWELS INTO CONCRETE - Item No. Special Provision No. 999S29 May 2010 1.0 SCOPE This special provision covers the requirements for the installation and acceptance of metallic dowels in concrete. 2.0 REFERENCES

More information

SITE PLAN, SUBDIVISION & EXTERIOR DESIGN REVIEW PROCESS

SITE PLAN, SUBDIVISION & EXTERIOR DESIGN REVIEW PROCESS INCORPORATED VILLAGE OF ROCKVILLE CENTRE BUILDING DEPARTMENT SITE PLAN, SUBDIVISION & EXTERIOR DESIGN REVIEW PROCESS Presubmission - Prior to a formal submission, the applicant should meet in person with

More information

TOWN OF GRAND FALLS-WINDSOR TENDER FOR SUPPLY OF BRONZE PLAQUES MEMORIAL GROUNDS CENOTAPH TENDER #

TOWN OF GRAND FALLS-WINDSOR TENDER FOR SUPPLY OF BRONZE PLAQUES MEMORIAL GROUNDS CENOTAPH TENDER # TOWN OF GRAND FALLS-WINDSOR TENDER FOR SUPPLY OF BRONZE PLAQUES MEMORIAL GROUNDS CENOTAPH TENDER #16010601 General Conditions 1. All taxes must be included. 2. Tenders which are incomplete, conditional,

More information

Answer: Qualification statement should be provided with the bid.

Answer: Qualification statement should be provided with the bid. Little Diversified Architectural Consulting, Inc. 5815 Westpark Drive Charlotte, North Carolina 28217 Phone: 704-525-6350 Fax: 704-561-8700 Lincoln County Probation Renovation 208 N. Government Street

More information

Midwest Roadside Safety Facility

Midwest Roadside Safety Facility B 64" 1626 602'-8 1/16" 183695 548'-0" 167030 1 2 3 4 5 6 7 8 9 10 11 12 14 15 16 17 18 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 373839 40 25 IMPACT 1500A 48" 12 27'-5" 8355 [] 3x7 CL A Galvanized

More information

UNION COUNTY VOCATIONAL-TECHNICAL SCHOOLS West Hall Addition Project Raritan Road, Scotch Plains, NJ

UNION COUNTY VOCATIONAL-TECHNICAL SCHOOLS West Hall Addition Project Raritan Road, Scotch Plains, NJ SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 General

More information

INSTALLATION GUIDE PermaTrak. Patented Product: U.S. Patent #5,906,084 #8,302,362 #8,522,505 #8,839,588 #9,096,975

INSTALLATION GUIDE PermaTrak. Patented Product: U.S. Patent #5,906,084 #8,302,362 #8,522,505 #8,839,588 #9,096,975 INSTALLATION GUIDE 2009-2017 PermaTrak. Patented Product: U.S. Patent #5,906,084 #8,302,362 #8,522,505 #8,839,588 #9,096,975 Table of Contents Project Overview Forward, Acceptability Criteria, Safety,

More information

RAIL PANEL AT TRANSITION SECTION PLAN - POST DETAIL PLAN - TUBE SPLICE. Colorado Department of Transportation. Staff Bridge Branch

RAIL PANEL AT TRANSITION SECTION PLAN - POST DETAIL PLAN - TUBE SPLICE. Colorado Department of Transportation. Staff Bridge Branch Limits of pay length for Bridge RailType 10M (For post spacing, see Dwg. No. B ) B60610 (Use with B60610A) 8 min. 1 max. 8 min. 1 max. 10 0 Max. 10 0 Max. post spacing 10 0 Max. 2 5 Post 1 x 1 slotted

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS

SECTION 39 - MANHOLES TABLE OF CONTENTS SECTION 39 - MANHOLES TABLE OF CONTENTS Section Page 39-1 GENERAL... 39.1 39-2 PRECAST CONCRETE MANHOLES... 39.1 39-2.01 Precast Concrete Sewer Manholes... 39.1 39-2.02 Precast Concrete Storm Drain Manholes...

More information

A. Deviation from this standard must be approved by the Project Architect.

A. Deviation from this standard must be approved by the Project Architect. September 2012, rev. 00 26 5600 Exterior Lighting PART 1. GENERAL 1.01 Related Documents A. Deviation from this standard must be approved by the Project Architect. B. Drawings and general provisions of

More information

BUILDING PLANS. BUILDING INSPECTIONS DEPARTMENT

BUILDING PLANS. BUILDING INSPECTIONS DEPARTMENT BUILDING PLANS BUILDING INSPECTIONS DEPARTMENT 507-537-6773 www.ci.marshall.mn.us This handout is intended only as a guide to the subject matter covered herein and is based in part on the 2015 Minnesota

More information

City of Keizer Floodplain/Greenway Development Application

City of Keizer Floodplain/Greenway Development Application City of Keizer Floodplain/Greenway Development Application If there are any questions about this application, who should be contacted (Agent)? Name: Address: Daytime Phone Number(s): Fax: Email: 1. Applicant

More information

DIVISION 11 EQUIPMENT SECTION PHOTO DARKROOM FUME EXHAUST VENT-HOODS

DIVISION 11 EQUIPMENT SECTION PHOTO DARKROOM FUME EXHAUST VENT-HOODS DIVISION 11 EQUIPMENT SECTION PHOTO DARKROOM FUME EXHAUST VENT-HOODS PART 1 GENERAL 1.01 Scope of Work A. Provide material, accessories, tools, equipment and labor as required for the complete fabrication

More information

SECTION ARCHITECTURAL PRECAST CONCRETE PART 1 - GENERAL

SECTION ARCHITECTURAL PRECAST CONCRETE PART 1 - GENERAL SECTION 03450 - ARCHITECTURAL PRECAST CONCRETE PART 1 - GENERAL 1.01 DESCRIPTION A. Work of this section is subject to requirements of the Contract Documents including the General Conditions and Supplementary

More information

CITY OF TOMBALL. Section FIRE HYDRANTS 1.01 SECTION INCLUDES. A. Fire hydrants. B. Adjustment of fire hydrants and gate valves.

CITY OF TOMBALL. Section FIRE HYDRANTS 1.01 SECTION INCLUDES. A. Fire hydrants. B. Adjustment of fire hydrants and gate valves. Section 02520 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Fire hydrants. B. Adjustment of fire hydrants and gate valves. 1.02 MEASUREMENT AND PAYMENT A. Unit Prices. 1. Payment is on a unit price basis

More information

24" B B Joint X501 Joint See MARKINGS Note PCB-RXX-350-TL3 " X501 Y301 (Typ.) " A PLAN (reinforced casting option shown) A " dia. Hinge Bar (Typ.) NOT

24 B B Joint X501 Joint See MARKINGS Note PCB-RXX-350-TL3  X501 Y301 (Typ.)  A PLAN (reinforced casting option shown) A  dia. Hinge Bar (Typ.) NOT B B Joint Joint See MARKINGS Note PCB-RXX-350-TL3 " Y301 (Typ.) " A PLAN (reinforced casting option shown) A " dia. Hinge Bar (Typ.) NOTES GENERAL: This barrier may be manufactured with reinforcing steel

More information

CITY AND COUNTY OF SAN FRANCISCO PUBLIC UTILITIES COMMISSION WASTEWATER ENTERPRISE

CITY AND COUNTY OF SAN FRANCISCO PUBLIC UTILITIES COMMISSION WASTEWATER ENTERPRISE San Francisco Water Power Sewer SOUTHEAST WATER POLLUTION CONTROL PLANT BUILDINGS 040, 041, 044, 060, 061, 062, 925, AND 960 MECHANICAL IMPROVEMENTS CONTRACT NO. WW-654 ADDENDUM NO. 3 Signatures: 9i;,.,,:.._\

More information

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA If project is not administered in PRISM, coordinate use of Exhibit 6 submittal schedule with this section. SECTION 01 33 23 SHOP DRAWINGS, PRODUCT DATA AND SAMPLES PART 1 - GENERAL 1.1 REQUIREMENTS INCLUDED

More information

4.1. Foremen 4.2. Concrete plant manager 4.3. Concrete plant operator 4.4. Personnel performing saw cutting and joint sealing

4.1. Foremen 4.2. Concrete plant manager 4.3. Concrete plant operator 4.4. Personnel performing saw cutting and joint sealing 10-1. JOINTED PLAIN CONCRETE PAVEMENT GENERAL Summary This work includes constructing jointed plain concrete pavement. Comply with Section 40, "Concrete Pavement," of the Standard Specifications. Submittals

More information

Section Meetings Section Material and Equipment. None Required

Section Meetings Section Material and Equipment. None Required January 2000 Page 1 of 8 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED WORK PART 2 PRODUCTS The General Conditions of the Contract, General Requirements and Supplemental

More information

Anti-Trust Statement

Anti-Trust Statement Anti-Trust Statement http://www.concrete-pipe.org/ A joint effort of the Texas Concrete Pipe Association and the Texas Department of Transportation What brought this about? The TxDOT organization consists

More information

Section COUPLINGS AND COUPLING ADAPTERS. This Section covers couplings and coupling adapters for ductile iron and steel pipe.

Section COUPLINGS AND COUPLING ADAPTERS. This Section covers couplings and coupling adapters for ductile iron and steel pipe. PART 1 GENERAL 1.01 SUMMARY Section 15155 This Section covers couplings and coupling adapters for ductile iron and steel pipe. 1.02 MEASUREMENT AND PAYMENT A. No separate payment for Work performed under

More information