Wind Requirements and Testing for Steady-State Voltage and Frequency Control

Size: px
Start display at page:

Download "Wind Requirements and Testing for Steady-State Voltage and Frequency Control"

Transcription

1 1 Wind Requirements and Testing for Steady-State Voltage and Frequency Control IEEE PES General Meeting, Boston: July 18, 2016 Steven Saylors, P.E. Senior Specialist Vestas Wind Systems

2 2 Voltage Control The central wind generation must not produce voltage variation higher than 5% at the connection point in case of partial or full maneuvering, timely or not, the generation complex. (ONS Submodulo 3.6-Section 8.3.1) Voltage Control is performed through reactive power operations from the WTGs and any additional compensation equipment (Capacitor/Reactor Banks, SVC, STATCOM, & OLTC of Substation Transformer) located at the substation. Voltage control can be performed in two different ways: the Slope voltage controller the PI voltage controller.

3 Voltage Control 3

4 4 Voltage Control The voltage controller dynamic response can be tuned according to the Grid Code interconnection requirements from the power off-taker.

5 Voltage Control 5

6 6 Commission Testing From ERCOT Nodal Protocol Section 8 Performance Monitoring July 1, 2015 The Resource Entity shall perform the Automatic Voltage Regulator (AVR) tests and shall supply AVR data as specified in the Operating Guides. The AVR tests must be performed on initial qualification. The AVR tests must be conducted at a time agreed on in advance by the Resource Entity, its QSE, the applicable TSP and ERCOT. Lagging Reactive Testing (a) It is recommended, but not required, that lagging reactive tests be performed when system voltage is within the voltage profile, such as during high load periods {specified using the Summer/Fall voltage profile}. (b) Lagging tests should meet the following performance criteria: (i) Lagging Test 1: Test at or above 95% of the unit s High Sustained Limit (HSL) for at least 15 minutes. IRRs should test at or above 60% of their HSL. Testing acceptance criteria is met if the unit achieved no less than 90% of the unit s most recent CURL. (ii) Lagging Test 2: Test at the unit s HSL for at least one hour. IRRs should test with at least 90% of photovoltaic inverters or wind turbines online. Testing acceptance criteria is met if the unit achieved at least 50% of the units CURL for one hour. Leading Reactive Testing (a) It is recommended, but not required, that leading reactive tests be performed when system voltage is within the voltage profile, such as during low load periods {specified using the Winter/Spring voltage profile}. (b) Leading tests should meet the following performance criteria: (i) Leading Test 1: Test at the unit s normally expected maximum real power output during system light load conditions for at least 15 minutes. IRRs should test at or below 60% of their HSL. Testing acceptance criteria is met if the unit achieved no less than 90% of the unit s original manufacturer reactive curve or most recent CURL.

7 7 Test 5.3: Voltage Control S.NO Voltage Reference Droop Test Test Test Test Test Test Test Test Voltage reference changed to kv Voltage reference changed to kv Voltage reference changed to kv Voltage reference changed to kv Voltage reference changed to 142 kv Voltage reference changed to 141 kv Voltage reference changed to 140 kv Voltage reference changed to 141 kv Error within +/-10% tolerance band 4% 4% 4% 4% 8% 8% 8% 8%

8 8 Frequency Control The role of the frequency control is to make a wind power plant contribute to the system-wide frequency regulation scheme put in place by the TSO. The active power reference to the WTG is reduced by over-frequency or increased by under-frequency events.

9 P [pu] f [Hz] 9 Frequency (Governor) Response Simulated grid frequency excursions are fed to central plant controller and control response command is then distributed to all turbines operating at the time 51.0 Hz 50.0 Hz 0.9 pu Individual wind turbines respond by pitching blades and/or controlling variable frequency converters to produce aggregated plant response at PCC 0.2 pu

10 10 Commission Testing From ERCOT Nodal Protocol Section 8(C) Turbine Governor Speed Tests Feb. 11, 2014 INTERMITTENT RENEWABLE RESOURCE (IRR) FREQUENCY RESPONSE TEST PROCEDURE 1. The frequency response function of the Intermittent Renewable Resource (IRR) is tested On-Line at a Load level that allows the IRRs to increase or decrease Load without reaching low operating limits or high operating limits. 2. The test is performed by adding a frequency offset signal that exceeds the Governor Dead-Band value to the measured frequency signal. This should create immediate step change in the measured frequency signal. 3. The test starts at time t 0 when the frequency Dead-Band is exceeded. 4. The MW output signal should be recorded at least every two seconds. 5. The duration of the test is 100 seconds. After 100 seconds, the offset signal should be removed and the IRR should return to pretest power output. 6. The test should be conducted both with positive and negative frequency offsets. 7. The test is considered successful after the signal becomes active if at least 70% of the calculated MW contribution is delivered within 16 seconds and the response is maintained for an additional 30 seconds. 8. Droop shall be set not to exceed 5% with a maximum frequency Dead-Band of +/ Hz (per BAL-001-TRE-1). 9. IRRs located behind one Point of Interconnection (POI), metered by one ERCOT-Polled Settlement (EPS) Meter, and operated as an integrated Facility may combine IRRs for the purposes of this test.

11 Test 4: Power Reduction during Frequency Change 11 S.NO Test 4.1 Test 4.2 Test 4.3 Test 4.4 Test 4.5 Test 4.6 Test 4.7 Test 4.8 Test Case Frequency reference stepped from 50 Hz to 50.5 Hz Frequency reference stepped from 50.5 Hz to 51 Hz Frequency reference stepped from 51 Hz to 51.5 Hz Frequency reference stepped from 51.5 Hz to 52 Hz Frequency reference stepped from 52 Hz to 51.5 Hz Frequency reference stepped from 51.5 Hz to 51 Hz Frequency reference stepped from 51 Hz to 50.5 Hz Frequency reference stepped from 50.5 Hz to 50 Hz Error within +/-10% tolerance band

12 Thank you for your attention 12

13 1 Renewable Energy Resource Requirements for Fault Ride Through and Fault Current Response Dr.-Ing Claudia Rahmann Msc. Ing. Jorge Vega University of Chile

14 Introduction 2 Grid Code Requirements Transmission system operators (TSO) are responsible for the satisfactory operation of their power systems during normal operation and contingencies TSO set minimum requirements regarding power system performance and define technical requirements that all actors connected to their networks must fulfill Grid code requirements Grid Code Requirements During normal operation During contingencies Fault Ride Through Capability Voltage stability support

15 FRT 3 Fault Ride Through (FRT) Requirements In a first stage of RER development, the requirements were defined without considering the impacts on power system operation WTs were allowed/forced to be disconnected in case of voltage dips and no contribution to system stability was required Frequency stability problems in countries with high levels of wind power Grid codes have started to include technical requirements regarding the dynamic performance of RER during contingencies Disconnection of RER in case of voltage dips is usually not admitted anymore Grid codes require an uninterrupted operation under fault conditions based on voltage time profiles (FRT capability curves) Unbalanced short-circuits: Possible over-voltages in some of the phases High voltage ride through requirements are sometimes also defined Less common, but present explicitly in some grid codes like South Africa and Germany

16 FRT 4 FRT-curves and V I q curves Typical voltage time profile (FRT capability curves) V [p. u. ] 1,0 0,8 0,6 0,4 0, ,3 1,0 15 Time [sec] Certain grid codes also impose requirements regarding reactive power response of RER during and after short circuits These requirements are in the form of V I q curves Improvement of system stability Supply I q In Absorption V Vn

17 Review 5 Considered countries In total, 11 countries were selected

18 FRT by country 6 FRT curves for RER Europe 1,0 0,9 0,8 0,7 0,6 0,5 0,4 0,3 0,2 Voltage [p.u.] 0 0 0,15 0,5 1,0 1, ,25 15 Time [sec] Germany (TenneT) Denmark (WT) England (WT off-shore) Spain Denmark (PV)

19 FRT requirements for RER 7 FRT curves for RER America 1,0 0,9 0,8 0,7 0,6 0,5 0,4 0,3 0,2 Voltage [p.u.] 0 0 0,15 0,3 0,5 1,0 1,5 3 4 Mexico Canada (AESO) (WT) 0,65 5 Brazil Canada (Hydro Québec) (WT) Chile 15 Time [sec]

20 FRT by country 8 FRT curves for RER Others 1,0 0,9 0,8 0,7 0,6 0,5 0,4 0,3 0,2 Voltage [p.u.] 0 0 0,15 0, Time [sec] China (WT) India (400 kv) (WT) China (PV) South Africa

21 FRT requirements for RER 9 FRT Requirements for RER Comments Some grid codes require different FRT-curves depending on the voltage level Mexico: the maximum time to ride through a voltage dip is 150 ms only for voltage levels between 69 and 161 kv: For voltage levels of 230 kv the time is 100 ms and for voltage levels of 400 kv is 80 ms India: the maximum time to ride through a voltage dip depends on the voltage level: For 400 kv the time is 100 ms for installations with voltages between 110 kv and 220 kv is 160 ms Other grid codes require different FRT-characteristics depending on the short-circuit type Spain: a less severe profile is required during two-phase short-circuits, with a lowest value of voltage of 0.5 p.u. Voltage in the FRT-curves (or measuring point) not always well specified Spain: voltage at the connection point Chile: phase to ground voltage at the connection point Denmark: voltage at the point of connection (line-to-line voltages for the 50 Hz component) ( PV) and smallest line-to-line voltage for the 50 Hz component ( WT) Significant differences between FRT requirements among the countries

22 Summary 10 Characteristics of selected requirements (1) Country Fault duration (ms) Minimum voltage (p.u.) Includes Off-shore? Includes WT PV? Includes V I q requirements? RER (%) Spain Germany *(TenneT) Denmark (Energinet) England * China (PV) 500 (WT) (WT) 150 (PV) 0.1 (PV) 0.2 (WT) (offshore) Ambiguously established India South Africa * Includes FRT requirements for CGU

23 Summary 11 Characteristics of selected requirements (2) Country Canada (Alberta) Fault duration (ms) Minimum voltage (p.u.) Includes Off-shore? Includes WT PV? Includes V I q requirements? RER (%) Chile Mexico Only required in case of twophase short circuits Ambiguously established Brazil

24 Voltage Support Requirements for RER 12 Voltage Support Requirements for RER (1) Germany: TenneT requires that RER support grid voltage with additional reactive current during a voltage dip, as shown in the figure. The voltage control must take place within 20 ms after fault recognition by providing a reactive current on the low-voltage side of the RER transformer Supply I q In Absorption V Vn V Denmark: the wind power plant must have a control function capable of controlling the reactive current component during voltage dips as specified in the figure Area A Area C (disconnection) I q In

25 Voltage Support Requirements for RER 13 Voltage Support Requirements for RER Spain: the wind power plants are required to be able to inject reactive power within 150 ms of grid recovery as shown in the figure South Africa: the RER must supply I q according to the figure (within its technical design limitations) so as to ensure that the RER helps to stabilize the voltage V Area A Area B Area E I q In

26 Conclusions 14 Outlook (1) Different criteria are applied when defining the requirements for RER within the grid codes RER penetration level and its location in the network, energy policies, network robustness, system characteristics, utility practices, among others Requirements may vary considerable from operator to operator and thus from one country to another Difficulties in their direct comparison Diversity of requirements poses important burdens on RER manufacturers Interpretation of the underlying meaning of the grid code documents, managing the differences in formats (terminology and definitions) Development of hardware and software solutions for the specific requirements of each grid code Diversity of requirements increases the costs of RER

27 Conclusions 15 Outlook (2) Need of harmonization? Harmonization process has been proposed by Wind Europe (ex EWEA) in a two-step scheme: Structural harmonization Generic grid code format (structure, designations, figures, method of specification, definitions and units) Technical harmonization Standardization from a technical viewpoint is difficult since the requirements depend on the technical characteristics of each power system Structural harmonization in the sense of a generic grid code format should be possible to implement Consistency in the grid codes would assist RER manufacturers to move from market-oriented solutions to universal ones Efforts should be made to move towards this objective

28 16 Thank you!!! Do you have any question??

29 Requirements for Modeling and Validation of Power System Models for Wind Generation Boston, Frank Martin, Siemens Wind Power A/S

30 2 Why requirements for modeling and validation? Need for (validated) simulation models: Enable system operator to perform grid integration studies Enable WPP developer to perform studies to verify compliance of the WPP with grid code requirements / design WPP equipment...

31 Wind Turbine vs. Wind Power Plant modeling and validation Wind Turbine Wind Turbine Generator Converter 0.69 /33 kv WTG Trafo 33 kv Busbar 132/400 kv 400/16 kv Fault Ride Through Wind Turbine Generator Converter 0.69 /33 kv WTG Trafo 33 kv Busbar 33 kv Busbar 33/132 kv Park Trafo 132 kv Busbar 132 kv PCC Power Station Power Quality Harmonics Wind Turbine Generator Converter 0.69 /33 kv WTG Trafo 33 kv Busbar HPPP 132/50 kv 50/10 kv 10/0.4 kv Flicker Control Features Consumer PQ Capability P(f) Function Protection

32 Wind Turbine vs. Wind Power Plant modeling and validation Wind Turbine Generator Converter 0.69 /33 kv WTG Trafo 33 kv Busbar Wind Power Plant 132/400 kv 400/16 kv Wind Turbine Generator Converter 0.69 /33 kv WTG Trafo 33 kv Busbar 33 kv Busbar 33/132 kv Park Trafo 132 kv Busbar 132 kv PCC Power Station Active Power Response Wind Turbine Generator Converter 0.69 /33 kv WTG Trafo 33 kv Busbar HPPP 132/50 kv 50/10 kv 10/0.4 kv Ramp rates Frequency Control Consumer LFSM FSM V, Q, PF Control WPP features

33 5 Requirements for simulation models / studies TenneT Offshore [1] (Source: TenneT TSO GmbH) NGET Grid Code[2] (Source: National Grid ) Commission Regulation (EU) NC RfG [3] (Source: European Commission) Hydro Quebec [4] (Source: Hydro Quebec) TCC High-Voltage [5] (Source: VDE)

34 6 Requirements for simulation models / studies Grid Code TenneT Offshore Scope (studies) Time step? RMS vs. EMT Validation and accuracy Blackbox vs. open model + both o - Generic model vs. manufacturer specific? Tool dependency NETOMAC, PSCAD NGET + RMS o - no ENTSO-E NC RfG Hydro Quebec TCC High- Voltage) o Both + Both o o - no + PSS/E, EMTP- RV o RMS + - no

35 7 Electrical simulation models Simulation models are available: Generic WT and WPP controller models WECC IEC (CD) Manufacturer specific WT and WPP controller models in relevant simulation tools RMS e.g. PSS/E, DIgSILENT Power Factory,... EMT e.g. PSCAD, EMTP-RV,... Models for other type of studies (e.g. harmonics)

36 8 Electrical simulation models necessary investigations / studies Steady state investigations e.g. load flow, loading of cables and transformers, voltage drop, reactive power capability Dynamic stability investigations e.g. verify if WPP stays connected and support the grid during UVRT as well as OVRT situations Short Circuit Studies and protection design Harmonics analysis and stability Transient investigations e.g insulation coordination, detailed transient studies

37 Requirements for model validation - example FRT SWT-3.0 / 3.2 MW DD 2000 tests SWT-4.0 MW 2200 tests SWT-6.0 MW DD 900 test

38 10 Requirements for model validation - example FRT Requirements and guidelines for model validation: Grid codes (generic) WECC IEC (approach without success criteria) FGW TR4 (approach and success criteria, FRT) PVVC (approach and success criteria, FRT)

39 Requirements for model validation - example FRT (IEC ) 11 No individual values for the error in the standard (Source: IEC )

40 Reactive Power [Mvar] +Ve Sequence Voltage [pu] Active Power [MW] Reactive Current [ka] Active Current [ka] D3 Platform Model Validation Grid Modeling Measured Simulation Measured Simulation Measured Simulation Measured Simulation Measured Simulation

41 LV Side +Ve Sq. Voltage [kv] Reactive Power [MVAr] MV Side +Ve Sq. Voltage [kv] Active Power [MW] Reactive Current [ka] Active Current [ka] D3 Platform Model Validation Playback 4 3 Measured Simulation Time [s] 4 3 Measured LV Simulation ref Time [s] Measured Simulation Measured Simulation Measured Simulation 0.2 Measured Simulation Time [s]

42 Requirements for model validation other than FRT Model validation focus on FRT Other aspects: Reactive Power Control function and features Harmonics... Model validation for EMT models

43 Frequency [Hz] Active Power [MW] Wind Power Plant Frequency Control Model Validation Measured Simulation

44 Points for Discussion Models for what kind of studies Validation requirements mostly unclear (e.g. tolerances, EMT model) Will an generic model (IEC / -2) be used

45 Thank you for your kind attention!

46 Further information: Frank Martin Siemens Wind Power A/S Grid Connection Elektrovej 325 DK-2800 Kgs. Lyngby Denmark Mobile:

47 Disclaimer This document contains forward-looking statements and information that is, statements related to future, not past, events. These statements may be identified either orally or in writing by words as expects, anticipates, intends, plans, believes, seeks, estimates, will or words of similar meaning. Such statements are based on our current expectations and certain assumptions, and are, therefore, subject to certain risks and uncertainties. A variety of factors, many of which are beyond Siemens control, affect its operations, performance, business strategy and results and could cause the actual results, performance or achievements of Siemens worldwide to be materially different from any future results, performance or achievements that may be expressed or implied by such forward-looking statements. For us, particular uncertainties arise, among others, from changes in general economic and business conditions, changes in currency exchange rates and interest rates, introduction of competing products or technologies by other companies, lack of acceptance of new products or services by customers targeted by Siemens worldwide, changes in business strategy and various other factors. More detailed information about certain of these factors is contained in Siemens filings with the SEC, which are available on the Siemens website, and on the SEC s website, Should one or more of these risks or uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in the relevant forward-looking statement as anticipated, believed, estimated, expected, intended, planned or projected. Siemens does not intend or assume any obligation to update or revise these forward-looking statements in light of developments which differ from those anticipated. Trademarks mentioned in this document are the property of Siemens AG, it's affiliates or their respective owners.

Grid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017

Grid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017 Grid codes and wind farm interconnections CNY Engineering Expo Syracuse, NY November 13, 2017 Purposes of grid codes Grid codes are designed to ensure stable operating conditions and to coordinate the

More information

How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements

How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements Robert Nelson Senior Expert Engineering Manager and Manager of Codes, Standards, and Regulations Siemens Wind Turbines -

More information

Fault Ride Through Technical Assessment Report Template

Fault Ride Through Technical Assessment Report Template Fault Ride Through Technical Assessment Report Template Notes: 1. This template is intended to provide guidelines into the minimum content and scope of the technical studies required to demonstrate compliance

More information

Wind Power Facility Technical Requirements CHANGE HISTORY

Wind Power Facility Technical Requirements CHANGE HISTORY CHANGE HISTORY DATE VERSION DETAIL CHANGED BY November 15, 2004 Page 2 of 24 TABLE OF CONTENTS LIST OF TABLES...5 LIST OF FIGURES...5 1.0 INTRODUCTION...6 1.1 Purpose of the Wind Power Facility Technical

More information

Harmonizing the Changing Resource Mix Keeping the Grid Together

Harmonizing the Changing Resource Mix Keeping the Grid Together Harmonizing the Changing Resource Mix Keeping the Grid Together Robert W. Cummings Senior Director of Engineering and Reliability Initiatives i-pcgrid March 30, 2017 NERC-IEEE Memorandum of Understanding

More information

each time the Frequency is above 51Hz. Continuous operation is required

each time the Frequency is above 51Hz. Continuous operation is required GC0101 EXTRACT OF EUROPEAN CONNECTION CONDITIONS LEGAL TEXT DATED 08/01/2018. ECC.6 ECC.6.1 ECC.6.1.1 ECC.6.1.2 ECC.6.1.2.1 ECC.6.1.2.1.1 ECC.6.1.2.1.2 ECC.6.1.2.1.3 TECHNICAL, DESIGN AND OPERATIONAL CRITERIA

More information

WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS

WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS WFPS1.1 INTRODUCTION 2 WFPS1.2 OBJECTIVE 2 WFPS1.3 SCOPE 3 WFPS1.4 FAULT RIDE THROUGH REQUIREMENTS 4 WFPS1.5 FREQUENCY REQUIREMENTS 5 WFPS1.6 VOLTAGE

More information

Requirements for Offshore Grid Connections. in the. Grid of TenneT TSO GmbH

Requirements for Offshore Grid Connections. in the. Grid of TenneT TSO GmbH Requirements for Offshore Grid Connections in the Grid of TenneT TSO GmbH Bernecker Straße 70, 95448 Bayreuth Updated: 5th October 2010 1/10 Requirements for Offshore Grid Connections in the Grid of TenneT

More information

Intermittent Renewable Resources (Wind and PV) Distribution Connection Code (DCC) At Medium Voltage (MV)

Intermittent Renewable Resources (Wind and PV) Distribution Connection Code (DCC) At Medium Voltage (MV) Intermittent Renewable Resources (Wind and PV) Distribution Connection Code (DCC) At Medium Voltage (MV) IRR-DCC-MV 1. Introduction 1 IRR-DCC-MV 2. Scope 1 IRR-DCC-MV 2.1. General 1 IRR-DCC-MV 2.2. Affected

More information

Southern Company Interconnection Requirements for Inverter-Based Generation

Southern Company Interconnection Requirements for Inverter-Based Generation Southern Company Interconnection Requirements for Inverter-Based Generation September 19, 2016 Page 1 of 16 All inverter-based generation connected to Southern Companies transmission system (Point of Interconnection

More information

DNVGL-ST-0125 Edition March 2016

DNVGL-ST-0125 Edition March 2016 STANDARD DNVGL-ST-0125 Edition March 2016 Grid code compliance The electronic pdf version of this document found through http://www.dnvgl.com is the officially binding version. The documents are available

More information

Final ballot January BOT adoption February 2015

Final ballot January BOT adoption February 2015 Standard PRC-024-21(X) Generator Frequency and Voltage Protective Relay Settings Standard Development Timeline This section is maintained by the drafting team during the development of the standard and

More information

IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces

IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces IEEE PES Boston Chapter Technical Meeting IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces P1547 Chair David

More information

The EU Network Code on Requirements for Generators A Summary

The EU Network Code on Requirements for Generators A Summary The EU Network Code on Requirements for Generators A Summary Tanguy Hubert, PhD thubert@epri.com PDU Fall Advisory Meeting Hollywood, FL; September 20, 2016 Existing interconnection requirements in Europe

More information

IEEE sion/1547revision_index.html

IEEE sion/1547revision_index.html IEEE 1547 IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces http://grouper.ieee.org/groups/scc21/1547_revi sion/1547revision_index.html

More information

Transmission Interconnection Requirements for Inverter-Based Generation

Transmission Interconnection Requirements for Inverter-Based Generation Transmission Requirements for Inverter-Based Generation June 25, 2018 Page 1 Overview: Every generator interconnecting to the transmission system must adhere to all applicable Federal and State jurisdictional

More information

Wind Power Plants and future Power System Frequency Stability

Wind Power Plants and future Power System Frequency Stability Wind Power Plants and future Power System Frequency Stability Peter W. Christensen Vestas Technology R&D, Denmark Event on Future Power System Operation Lund University, Sweden, June 12, 2012 1 Agenda

More information

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction A. Introduction 1. Title: Generator Frequency and Voltage Protective Relay Settings 2. Number: PRC-024-1 3. Purpose: Ensure Generator Owners set their generator protective relays such that generating units

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements Division 502 Technical Applicability 1(1) Section 502.1 applies to: Expedited Filing Draft August 22, 2017 the legal owner of an aggregated generating facility directly connected to the transmission system

More information

Indication of Dynamic Model Validation Process

Indication of Dynamic Model Validation Process Indication of Dynamic Model Validation Process Document Identifier Written by David Cashman Document Version Draft Checked by Date of Current Issue November 2013 Approved by Jon O Sullivan Disclaimer EirGrid,

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements Applicability 1(1) Section 502.1 applies to the ISO, and subject to the provisions of subsections 1(2), (3) and (4) to any: (a) a new wind aggregated generating facility to be connected to the transmission

More information

Requirements for Generators European Network Code High Level Implementation Issues

Requirements for Generators European Network Code High Level Implementation Issues Requirements for Generators European Network Code High Level Implementation Issues Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be

More information

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC A. Introduction 1. Title: Generator Frequency and Voltage Protective Relay Settings 2. Number: PRC-024-2 3. Purpose: Ensure Generator Owners set their generator protective relays such that generating units

More information

DRAFT PROPOSAL FOR STORAGE CONNECTION REQUIREMENTS

DRAFT PROPOSAL FOR STORAGE CONNECTION REQUIREMENTS DRAFT PROPOSAL FOR STORAGE CONNECTION REQUIREMENTS December 2017 Contents 1 Background and reading instructions... 2 2 Definitions and applicability... 2 3 SPM categories types... 3 4 SPM Type A... 4 4.1

More information

Wind Power Plant Voltage Control Optimization with Embedded Application of Wind Turbines and Statcom

Wind Power Plant Voltage Control Optimization with Embedded Application of Wind Turbines and Statcom Downloaded from orbit.dtu.dk on: Aug 3, 018 Wind Power Plant Voltage Control Optimization with Embedded Application of Wind Turbines and Statcom Wu, Qiuwei; Solanas, Jose Ignacio Busca; Zhao, Haoran; Kocewiak,

More information

Target Mchunu and Themba Khoza Eskom Transmission Division, System Operator Grid Code Management

Target Mchunu and Themba Khoza Eskom Transmission Division, System Operator Grid Code Management GRID CONNECTION CODE FOR RENEWABLE POWER PLANTS (RPPs) CONNECTED TO THE ELECTRICITY TRANSMISSION SYSTEM (TS) OR THE DISTRIBUTION SYSTEM (DS) IN SOUTH AFRICA Target Mchunu and Themba Khoza Eskom Transmission

More information

Parameters related to voltage issues

Parameters related to voltage issues Parameters related to voltage issues EN-E guidance document for national implementation for network codes on grid connection 16 November 2016 EN-E AISBL Avenue de Cortenbergh 100 1000 Brussels Belgium

More information

TABLE 1 COMPARISION OF ENTSO-E RfG TO GB GRID CODE

TABLE 1 COMPARISION OF ENTSO-E RfG TO GB GRID CODE TABLE 1 Comparison to ENTSO-E RfG (Comparison based on Issue 5 Revision 11 only and ENSTO - E RFG Version dated 14 January 2014) (Note Does not include other Industry Codes) Table 1 compares the ENTSO-E

More information

Short Circuit Modeling for Inverter-Based Resources

Short Circuit Modeling for Inverter-Based Resources Short Circuit Modeling for Inverter-Based Resources Evangelos Farantatos Sr. Technical Leader Transmission Operations & Planning NERC Power Plant Modeling & Verification Task Force (PPMVTF) November 6

More information

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: IDAHO POWER COMPANY Designated Contact Person: Jeremiah Creason Address: 1221 W. Idaho Street, Boise ID 83702 Telephone

More information

Fault current contribution from PPMS & HVDC

Fault current contribution from PPMS & HVDC Fault current contribution from PPMS & HVDC ENTSO-E guidance document for national implementation for network codes on grid connection 16 November 2016 Table of Contents DESCRIPTION...3 Code(s) &...3 Introduction...3

More information

Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing Methods

Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing Methods Proceedings of the th WSEAS International Conference on Power Systems, Beijing, China, September -, 200 Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing

More information

POWER CORPORATION. Power Quality. Specifications and Guidelines for Customers. Phone: Fax:

POWER CORPORATION. Power Quality. Specifications and Guidelines for Customers. Phone: Fax: POWER CORPORATION Power Quality Specifications and Guidelines for Customers Phone: 403-514-3700 Fax: 403-514-3719 1 GENERAL OVERVIEW........................................ 1.1 WHAT DOES THIS SPECIFICATION

More information

SELECTING NATIONAL MW BOUNDARIES

SELECTING NATIONAL MW BOUNDARIES SELECTING NATIONAL MW BOUNDARIES ENTSO-E guidance document for national implementation for network codes on grid connection 16 November 2016 Table of Contents DESCRIPTION...2 Codes(s) and Article(s)...2

More information

Deleted: 9 4 anuary ... [1] Deleted: much more. Formatted ... [2] Formatted Table. Formatted: Indent: Left: 0.06 cm

Deleted: 9 4 anuary ... [1] Deleted: much more. Formatted ... [2] Formatted Table. Formatted: Indent: Left: 0.06 cm (Comparison based on GB Grid Code Issue 4 Revision 13 only and ENSTO - E RFG Internal Version dated 6 June 01) (Note Does not include other Industry Codes) Table compares the GB Grid Code with the ENTSO-E

More information

POWER QUALITY SPECIFICATIONS AND GUIDELINES FOR CUSTOMERS ENGINEERING STANDARDS CITY OF LETHBRIDGE ELECTRIC

POWER QUALITY SPECIFICATIONS AND GUIDELINES FOR CUSTOMERS ENGINEERING STANDARDS CITY OF LETHBRIDGE ELECTRIC CITY OF LETHBRIDGE ELECTRIC ENGINEERING STANDARDS POWER QUALITY SPECIFICATIONS AND GUIDELINES FOR CUSTOMERS The City of Lethbridge acknowledges the use of other utility industry and industry committee

More information

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF GENERATION FACILITIES NOT SUBJECT TO FERC JURISDICTION

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF GENERATION FACILITIES NOT SUBJECT TO FERC JURISDICTION TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF GENERATION FACILITIES NOT SUBJECT TO FERC JURISDICTION Document 9022 Puget Sound Energy, Inc. PSE-TC-160.70 December

More information

RENEWABLE ENERGY SUB-CODE for Distribution Network connected Variable Renewable Energy Power Plants in Ghana

RENEWABLE ENERGY SUB-CODE for Distribution Network connected Variable Renewable Energy Power Plants in Ghana RENEWABLE ENERGY SUB-CODE for Distribution Network connected Variable Renewable Energy Power Plants in Ghana JANUARY 2015 i Table of Content PART A: 1 1 Introduction 1 1.1 Scope 1 1.2 Status 1 1.3 Terms

More information

Inverter-Based Resource Disturbance Analysis

Inverter-Based Resource Disturbance Analysis Inverter-Based Resource Disturbance Analysis Key Findings and Recommendations Informational Webinar February 15, 2018 August 16, 2016 Blue Cut Fire Disturbance Key Findings and Recommendations 2 Western

More information

POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS.

POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS. POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS. This document may be subject to changes. Contact ARTECHE to confirm the characteristics and availability of the products

More information

1200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report

1200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report 1200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report Rich Bauer Associate Director Reliability Risk Management / Event Analysis Mid C Seminar July 19, 2017 Western Interconnection

More information

Influence of Wind Generators in Voltage Dips

Influence of Wind Generators in Voltage Dips Influence of Wind Generators in Voltage Dips E. Belenguer, N. Aparicio, J.L. Gandía, S. Añó 2 Department of Industrial Engineering and Design Universitat Jaume I Campus de Riu Sec, E-27 Castelló (Spain)

More information

Offshore AC Grid Management for an AC Integrated VSC-HVDC Scheme with Large WPPs

Offshore AC Grid Management for an AC Integrated VSC-HVDC Scheme with Large WPPs Offshore AC Grid Management for an AC Integrated VSC-HVDC Scheme with Large WPPs Rakibuzzaman Shah, Member, IEEE, Mike Barnes, Senior Member, IEEE, and Robin Preece, Member, IEEE School of Electrical and

More information

Compliance activities

Compliance activities DOCUMENTLOCATIE SO-SOC 13-141 PAGINA 1 van 28 Compliance activities Compliance activities in relation to Connection Requirements Wind Farms System Operations - Version V3.0 January 2014 - PAGINA 2 van

More information

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control Spring 2014 Instructor: Kai Sun 1 References Saadat s Chapters 12.6 ~12.7 Kundur s Sections

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

MEASUREMENT CAMPAIGN AND ASSESSMENT OF THE QUALITY OF SUPPLY IN RES AND DG FACILITIES IN SPAIN

MEASUREMENT CAMPAIGN AND ASSESSMENT OF THE QUALITY OF SUPPLY IN RES AND DG FACILITIES IN SPAIN MEASUREMENT CAMPAIGN AND ASSESSMENT OF THE QUALITY OF SUPPLY IN RES AND DG FACILITIES IN SPAIN Eugenio PEREA*, Eduardo ZABALA*, J. Emilio RODRÍGUEZ*, Asier GIL DE MURO*, Hugo GAGO * * * Fundación LABEIN,

More information

Operationalizing Phasor Technology. Model Validation. Webinar. Ken Martin. March 4, Presented by. Page 0

Operationalizing Phasor Technology. Model Validation. Webinar. Ken Martin. March 4, Presented by. Page 0 Operationalizing Phasor Technology Model Validation Webinar March 4, 2014 Presented by Ken Martin Page 0 Model Use and Validation for Operations and Planning Compare System Performance with Model Prediction

More information

IEEE Major Revision of Interconnection Standard

IEEE Major Revision of Interconnection Standard IEEE 1547-2018 - Major Revision of Interconnection Standard NRECA & APA s Emerging Priorities in Energy Research Day, Anchorage, AK Charlie Vartanian PE Secretary, IEEE 1547 Working Group October 31, 2018

More information

Max voltage in 400 kv Networks

Max voltage in 400 kv Networks Max voltage in 400 kv Networks ENTSO-E GC ESC, 08, Brussels 1 Summary NEED TO WITHSTAND WIDE VOLTAGE RANGE 3 EXISTING CONNECTION RULES 4 KEMA REPORT ON RFG 5 STUDIES ABOUT TOV 6 REFERENCE TO EU NC REGULATIONS

More information

SUMMARY. KEYWORDS Advanced Control, Type 4 WTG, Offshore, HVDC, Grid Access, Diode Rectifier Unit. 21, rue d Artois, F PARIS B4-121 CIGRE 2016

SUMMARY. KEYWORDS Advanced Control, Type 4 WTG, Offshore, HVDC, Grid Access, Diode Rectifier Unit. 21, rue d Artois, F PARIS B4-121 CIGRE 2016 21, rue d Artois, F-75008 PARIS B4-121 CIGRE 2016 http : //www.cigre.org Diode-Rectifier HVDC link to onshore power systems: Dynamic performance of wind turbine generators and Reliability of liquid immersed

More information

CONTROLLABILITY OF WIND POWER PLANTS CAPABILITIES REGARDING VOLTAGE CONTROL AND DATA EXCHANGE

CONTROLLABILITY OF WIND POWER PLANTS CAPABILITIES REGARDING VOLTAGE CONTROL AND DATA EXCHANGE CONTROLLABILITY OF WIND POWER PLANTS CAPABILITIES REGARDING VOLTAGE CONTROL AND DATA EXCHANGE Konstantinos PIERROS Nuno TAVEIRA Eike ERDMANN ENERCON GmbH UK ENERCON GmbH Germany ENERCON GmbH Germany Konstantinos.Pierros@enercon.de

More information

BPS-Connected Inverter-Based Resource Performance

BPS-Connected Inverter-Based Resource Performance 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Reliability Guideline BPS-Connected Inverter-Based Resource Performance May 2018 20 21 22 23 24 25 26 27 28 29 NERC Report Title Report Date I 30 31 32 33

More information

Lessons Learned in Model Validation for NERC Compliance

Lessons Learned in Model Validation for NERC Compliance Lessons Learned in Model Validation for NERC Compliance usa.siemens.com/digitalgrid NERC Modeling, Data, and Analysis MOD 025 2: Generator Real and Reactive Power Capability Demonstration MOD 026 1: Verification

More information

Analysis of the Effectiveness of Grid Codes for Offshore Wind Farms Connected to Onshore Grid via VSC-Based HVDC

Analysis of the Effectiveness of Grid Codes for Offshore Wind Farms Connected to Onshore Grid via VSC-Based HVDC Conference of the Wind Power Engineering Community Analysis of the Effectiveness of Grid Codes for Offshore Wind Farms Connected to Onshore Grid via VSC-Based HVDC Moritz Mittelstaedt, Andreas Roehder,.Hendrik

More information

FREQUENCY and VOLTAGE, ranges and durations

FREQUENCY and VOLTAGE, ranges and durations Eurelectric 10 September 2013 Proposals to amend the Draft RfG Code This paper includes informal proposals to amend the RfG Code regarding some critical requirements taking into account the content of

More information

DRAFT PROPOSAL FOR NC HVDC REQUIREMENTS OF GENERAL APPLICATION

DRAFT PROPOSAL FOR NC HVDC REQUIREMENTS OF GENERAL APPLICATION DRAFT PROPOSAL FOR NC REQUIREMENTS OF GENERAL APPLICATION December 2017 TABLE OF CONTENTS Table of Contents... 2 Introduction... 6 1. Scope of application... 8 2. TITLE II: General s for connections...

More information

Constant Terminal Voltage. Working Group Meeting 4 19 th September 2014

Constant Terminal Voltage. Working Group Meeting 4 19 th September 2014 Constant Terminal Voltage Working Group Meeting 4 19 th September 014 Overview Options summary System under investigation Options analysis Discussion Options Option 1 Constant Terminal Voltage controlled

More information

ENTSO-E Draft Network Code on High Voltage Direct Current Connections and DCconnected

ENTSO-E Draft Network Code on High Voltage Direct Current Connections and DCconnected ENTSO-E Draft Network Code on High Voltage Direct Current Connections and DCconnected Power Park Modules 30 April 2014 Notice This document reflects the work done by ENTSO-E in line with ACER s framework

More information

Fault Ride-through Capability Test Unit for Wind Turbines

Fault Ride-through Capability Test Unit for Wind Turbines WIND ENERGY Wind Energ. 2008; 11:3 12 Published online 7 November 2007 in Wiley Interscience (www.interscience.wiley.com).255 Research Article Fault Ride-through Capability Test Unit for Wind Turbines

More information

GRID CONNECTION CODE FOR RENEWABLE POWER PLANTS (RPPs)

GRID CONNECTION CODE FOR RENEWABLE POWER PLANTS (RPPs) GRID CONNECTION CODE FOR RENEWABLE POWER PLANTS (RPPs) 1.0 GRID CONNECTION CODE BASIS 1.1 LEGISLATION 1.1.1 The legal basis for this RPP Code (RPP Code) is specified in terms of the [Electricity] Act 2016

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

HARDWARE BASED CHARACTERISATION OF LV INVERTER FAULT RESPONSE

HARDWARE BASED CHARACTERISATION OF LV INVERTER FAULT RESPONSE HARDWARE BASED CHARACTERISATION OF LV INVERTER FAULT RESPONSE Ibrahim ABDULHADI Federico COFFELE Power Networks Demonstration Centre - UK ibrahim.f.abdulhadi@strath.ac.uk federico.coffele@strath.ac.uk

More information

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES Highgate Converter Overview Prepared by Joshua Burroughs & Jeff Carrara IEEE PES Highgate Converter Abstract Introduction to HVDC Background on Highgate Operation and Control schemes of Highgate 22 Why

More information

Open Access Simulation Toolbox for Wind Power Transmission using High Voltage Direct Current Technology

Open Access Simulation Toolbox for Wind Power Transmission using High Voltage Direct Current Technology Open Access Simulation Toolbox for Wind Power Transmission using High Voltage Direct Current Technology Daniel Adeuyi (Cardiff University, Wales) Sheng WANG, Carlos UGALDE-LOO (Cardiff University, Wales);

More information

Integration of Wind Generation into Weak Grids

Integration of Wind Generation into Weak Grids Integration of Wind Generation into Weak Grids Jason MacDowell GE Energy Consulting NERC ERSTF Atlanta, GA December 10-11, 2014 Outline Conventional and Power Electronic (PE) Sources Stability limitations

More information

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF LARGE GENERATION FACILITIES. Document 9020

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF LARGE GENERATION FACILITIES. Document 9020 TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF LARGE GENERATION FACILITIES Document 9020 Puget Sound Energy, Inc. PSE-TC-160.50 December 19, 2016 TABLE OF CONTENTS

More information

Revised IEEE 1547 Standard for Interconnecting Distributed Energy Resources with Electric Power Systems- National Grid Solar Program

Revised IEEE 1547 Standard for Interconnecting Distributed Energy Resources with Electric Power Systems- National Grid Solar Program 1 Revised IEEE 1547 Standard for Interconnecting Distributed Energy Resources with Electric Power Systems- National Grid Solar Program Babak Enayati, PhD, PE Lead Engineer, National Grid Waltham, MA Email:

More information

1

1 Guidelines and Technical Basis Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive

More information

Grid Converters for Photovoltaic

Grid Converters for Photovoltaic Grid Converters for Photovoltaic and Wind Power Systems by R. Teodorescu, M. Liserre and P. Rodriguez ISBN: 978 0 470 05751 3 Copyright Wiley 2011 Chapter 3 Grid Requirements for PV Grid connection requirements

More information

Technical Requirements for Connecting Small Scale PV (sspv) Systems to Low Voltage Distribution Networks

Technical Requirements for Connecting Small Scale PV (sspv) Systems to Low Voltage Distribution Networks 2014 Technical Requirements for Connecting Small Scale PV (sspv) Systems to Low Voltage Distribution Networks This document specifies the technical requirement for connecting sspv to the low voltage distribution

More information

Version 2.6 October Comments to this document can be forwarded to:

Version 2.6 October Comments to this document can be forwarded to: GRID CONNECTION CODE REQUIREMENTS FOR RENEWABLE POWER PLANTS (RPPs) CONNECTED TO THE TRANSMISSION SYSTEM (TS) OR THE DISTRIBUTION SYSTEM (DS) IN SOUTH AFRICA Version 2.6 October 2012 Comments to this document

More information

Industry Webinar. Reactive Power Planning. NERC System Analysis and Modeling Subcommittee (SAMS) March 2017

Industry Webinar. Reactive Power Planning. NERC System Analysis and Modeling Subcommittee (SAMS) March 2017 Industry Webinar Reactive Power Planning NERC System Analysis and Modeling Subcommittee (SAMS) March 2017 Webinar Topics Reliability Guideline on Reactive Power Planning Webinar Topics Fundamentals of

More information

HYBRID STATCOM SOLUTIONS IN RENEWABLE SYSTEMS

HYBRID STATCOM SOLUTIONS IN RENEWABLE SYSTEMS HYBRID STATCOM SOLUTIONS IN RENEWABLE SYSTEMS Enrique PÉREZ Santiago REMENTERIA Aitor LAKA Arteche Spain Arteche Spain Ingeteam Power Technology-Spain ep@arteche.es sr@arteche.es Aitor.Laka@ingeteam.com

More information

Robert W. Cummings - NERC Director of System Analysis and Reliability Initiatives William Herbsleb - Chairman of Frequency Response Standard Drafting

Robert W. Cummings - NERC Director of System Analysis and Reliability Initiatives William Herbsleb - Chairman of Frequency Response Standard Drafting Generator Governor and Information Settings Webinar Robert W. Cummings - NERC Director of System Analysis and Reliability Initiatives William Herbsleb - Chairman of Frequency Response Standard Drafting

More information

Control of multiple VSC-HVDC converters within an offshore AC-hub

Control of multiple VSC-HVDC converters within an offshore AC-hub Control of multiple VSC-HVDC converters within an offshore AC-hub Jonathan Stevens, Student Member, IEEE, Daniel Rogers, Member, IEEE, Institute of Energy Cardiff University Cardiff, UK AbstractThe offshore

More information

Parameters related to frequency stability

Parameters related to frequency stability Parameters related to frequency stability EN-E guidance document for national implementation for network codes on grid connection 16 November 2016 EN-E AISBL Avenue de Cortenbergh 100 1000 Brussels Belgium

More information

GRID CONNECTION CODE FOR RENEWABLE POWER PLANTS

GRID CONNECTION CODE FOR RENEWABLE POWER PLANTS GRID CONNECTION CODE FOR RENEWABLE POWER PLANTS (RPPs) CONNECTED TO THE ELECTRICITY TRANSMISSION SYSTEM (TS) OR THE DISTRIBUTION SYSTEM (DS) IN SOUTH AFRICA Version 2.9 (July 2016) This document is approved

More information

Performance of Distributed Energy Resources During and After System Disturbance Voltage and Frequency Ride-Through Requirements

Performance of Distributed Energy Resources During and After System Disturbance Voltage and Frequency Ride-Through Requirements Performance of Distributed Energy Resources During and After System Disturbance Voltage and Frequency Ride-Through Requirements A report by the Integration of Variable Generation Task Force (Task 1-7)

More information

Phase-phase/phase-neutral: 24/13.8 kv star, 13.8 kv delta, 12/6.9 kv star.

Phase-phase/phase-neutral: 24/13.8 kv star, 13.8 kv delta, 12/6.9 kv star. Summary Of Interconnection Technical Guidelines for Renewable Energy Systems 0-100 kw under Standard Offer Contract (Extract from JPS Guide to Interconnection of Distributed Generation) This document is

More information

Active Power Sharing and Frequency Control of Multiple Distributed Generators in A Microgrid

Active Power Sharing and Frequency Control of Multiple Distributed Generators in A Microgrid IOSR Journal of Electrical and Electronics Engineering (IOSR-JEEE) e-issn: 2278-1676,p-ISSN: 2320-3331, PP 01-07 www.iosrjournals.org Active Power Sharing and Frequency Control of Multiple Distributed

More information

Demonstration of PFR Improvement September ERCOT Operations Planning

Demonstration of PFR Improvement September ERCOT Operations Planning Demonstration of PFR Improvement September 2017 ERCOT Operations Planning Agenda Overview BAL-001-TRE-1 Standard Applicability to Alternative Resources Ancillary Service Products & Dispatch Improvements

More information

Improvement of Islanding Detector Using Interharmonics Current Injection Method and Its Applications

Improvement of Islanding Detector Using Interharmonics Current Injection Method and Its Applications FEATURED TOPIC Improvement of Islanding Detector Using Interharmonics Current Injection Method and Its Applications Sadayuki ISHIKURA*, Hideyuki NAKATANI, Junya TAKAGI, Tsutomu FUKADA, Shoji NISHIMURA

More information

Transformer energisation after network blackout

Transformer energisation after network blackout Transformer energisation after network blackout Impact on network restoration and improvement of its process ABSTRACT According to ENTSO-E Network policy 5, responsibility for system restoration after

More information

Netzkurzschlussverhalten von umrichterbetriebenen regenerativen Energieerzeugern und -speichern

Netzkurzschlussverhalten von umrichterbetriebenen regenerativen Energieerzeugern und -speichern October 25 Netzkurzschlussverhalten von umrichterbetriebenen regenerativen Energieerzeugern und -speichern Dr. Georg Möhlenkamp 5MOP8_EN-(Netzkurzschlussverhalten-Energieerzeuger).PPT / Dr.MÖHLENKAMP Overview

More information

On the Evaluation of Power Quality Indices in Distribution Systems with Dispersed Generation

On the Evaluation of Power Quality Indices in Distribution Systems with Dispersed Generation European Association for the Development of Renewable Energies, Environment and Power Quality International Conference on Renewable Energies and Power Quality (ICREPQ 09) Valencia (Spain), 1th to 17th

More information

North-West University, 2 Eskom SOC South Africa

North-West University, 2 Eskom SOC South Africa Electricity Supply to Africa and Developing Economies. Challenges and opportunities. Technology solutions and innovations for developing economies Advances in Power Quality Requirements for RPPs MG BOTHA

More information

The Impact of Connecting Distributed Generation to the Distribution System E. V. Mgaya, Z. Müller

The Impact of Connecting Distributed Generation to the Distribution System E. V. Mgaya, Z. Müller The Impact of Connecting Distributed Generation to the Distribution System E. V. Mgaya, Z. Müller This paper deals with the general problem of utilizing of renewable energy sources to generate electric

More information

Technical Information Short-Circuit Currents Information on short-circuit currents of SMA PV inverters

Technical Information Short-Circuit Currents Information on short-circuit currents of SMA PV inverters Technical Information Short-Circuit Currents Information on short-circuit currents of SMA PV inverters Content During grid failures as for example voltage dips, all PV inverters may generate currents that

More information

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting Document C-29 Procedures for System Modeling: January 5 th, 2016 TFSS Revisions Clean Open Process Posting Prepared by the SS-37 Working Group on Base Case Development for the Task Force on System Studies.

More information

PROPOSAL FOR NC RFG REQUIREMENTS OF GENERAL APPLICATION

PROPOSAL FOR NC RFG REQUIREMENTS OF GENERAL APPLICATION PROPOSAL FOR NC RFG REQUIREMENTS OF GENERAL APPLICATION Public consultation 15 March 23 April 2018 Contents 1 Introduction... 3 2 Proposal for determination of significance [Art 5]... 5 2.1 Conditions

More information

Fault Ride Through Principles. and. Grid Code Proposed Changes

Fault Ride Through Principles. and. Grid Code Proposed Changes Fault Ride Through Principles and Grid Code Proposed Changes Document identifier: FRT Principles and Proposals Authored by: Jonathan O Sullivan / Alan Rogers Document version: Ver 1.3 Checked by: Anne

More information

ELEMENTS OF FACTS CONTROLLERS

ELEMENTS OF FACTS CONTROLLERS 1 ELEMENTS OF FACTS CONTROLLERS Rajiv K. Varma Associate Professor Hydro One Chair in Power Systems Engineering University of Western Ontario London, ON, CANADA rkvarma@uwo.ca POWER SYSTEMS - Where are

More information

Generation and Load Interconnection Standard

Generation and Load Interconnection Standard Generation and Load Interconnection Standard Rev. 0 DRAFT Name Signature Date Prepared: Approved: VP Acceptance APEGGA Permit to Practice P-08200 TABLE OF CONTENTS 1.0 INTRODUCTION...5 1.1 Purpose...5

More information

Generation and Load Interconnection Standard

Generation and Load Interconnection Standard Generation and Load Interconnection Standard Rev. 0A DRAFT Name Signature Date Prepared: Approved: VP Acceptance APEGGA Permit to Practice P-08200 TABLE OF CONTENTS 1.0 INTRODUCTION...5 1.1 Purpose...5

More information

INTERIM ARRANGEMENTS FOR GRID TIED DISTRIBUTED ENERGY RESOURCES. Technical Requirements for Grid-Tied DERs

INTERIM ARRANGEMENTS FOR GRID TIED DISTRIBUTED ENERGY RESOURCES. Technical Requirements for Grid-Tied DERs INTERIM ARRANGEMENTS FOR GRID TIED DISTRIBUTED ENERGY RESOURCES Technical Requirements for Grid-Tied DERs Projects Division 6/29/2017 Contents 1 Definitions and Acronyms... 1 2 Technical Interconnection

More information

Solar inverter interactions with DC side

Solar inverter interactions with DC side Solar inverter interactions with DC side Some Regulatory Challenges Jennifer Crisp, Ravidutt Sharma, Tim George, Scott Hagaman DIgSILENT Pacific Brisbane, Australia Abstract The DC voltage on the photovoltaic

More information

POWER QUALITY IMPACTS AND MITIGATION OF DISTRIBUTED SOLAR POWER

POWER QUALITY IMPACTS AND MITIGATION OF DISTRIBUTED SOLAR POWER POWER QUALITY IMPACTS AND MITIGATION OF DISTRIBUTED SOLAR POWER Presented by Ric Austria, Principal at Pterra Consulting to the IEEE San Francisco Chapter Feb 17, 2016 California Public Utilities Commission,

More information

5 Summary test results and additional findings

5 Summary test results and additional findings LOW VOLTAGE RIDE THROUGH WITH HIGH CURRENT INJECTION 1 2 3 4 Motivation Future Requirements Test results for symmetrical failures Test results for asymmetrical failures 5 Summary test results and additional

More information

Implementation of Revised IEEE Standard 1547

Implementation of Revised IEEE Standard 1547 MAY 31, 2017 HOLYOKE, MASSACHUSETTS Implementation of Revised IEEE Standard 1547 Presentation to ISO-TO Operations Committee David Forrest Key Points As New England adds significant amounts of Distributed

More information