System Requirements for Wind Farms and Distributed Generation. Giuseppe Di Marzio

Size: px
Start display at page:

Download "System Requirements for Wind Farms and Distributed Generation. Giuseppe Di Marzio"

Transcription

1 ystem Requirements for Wind Farms and Distributed Generation Giuseppe Di Marzio 1

2 Contents Grid interconnection schemes Power quality requirements Fault Level considerations Protection schemes New grid code connection requirements My contribution within the project 2

3 Interconnection to MV and HV grids < 5 MW Existing MV feeder (e.g. 15 or 20 V) reinforcement possibly required < 20 MW directly to MV busbar of MV/HV sub station via dedicated feeder > 20 MW to HV system via dedicated TR in existing MV/HV sub station or via dedicated sub station ource tavaros A. Papathanassiou 3

4 teady tate Voltage Variations implified evaluation 10 min average values EN stipulates ±10% limit for MV systems 2% limit is set by utilities ε (%) 100 = 100 R cos(ψ n cos(ψ + Φ) 2% + Φ) = Where the short-circuit ratio R is defined as: R = n 4

5 teady tate Voltage Variations Detailed evaluation Procedure: Perform the load flow in 4 cases 1. Min load Min generation 2. Min load Max generation 3. Max load Min generation 4. Max load Max generation Determine U max, U min for each node Chec the deviation limits for all the nodes Median value within ±5% of the nominal voltage Deviation around the median value < ± 2% Can be corrected via the fixed taps of MV/HV transformers Ensures that LV networ voltage always remains within 10% of the nominal voltage 5

6 Rapid Voltage Variations witching operation of a single WT (IEC ) d max (%) = 100 u (ψ ) 100 = R (ψ Where (ψ ) is the voltage change factor u n u ); If the voltage change factor is unavailable, the starting current can be used: Magnitude limits (IEC ) r (hour -1 ) r 1 1 r r r 1000 MV d max (%) HV u ( ψ ) I I start n for ynch. gen for Asynch. gen for DFIG No summation effect needs to be taen into account 6

7 Harmonics & flicer emissions Evaluating principle: 1. pecify acceptable disturbance level (planning level) Acceptable distortion or fluctuation level of system voltage, caused by all consumers or producers connected to the system. Generic values, specified by the utility; 2. Allocate them to individual WFs The limit for each DG (or consumer) is a fraction of the planning level, proportional to the ratio of its agreed power to the available system capacity; 3. Chec the emissions of a specific WF against its allocated limit Calculate expected harmonic distortion or flicer of the system voltage at the PCC due to a specific DG and compare to its allocated limit; If the system is fully loaded and all the consumers are injecting their individual limits, the total disturbance level will be equal to the planning levels. 7

8 Harmonic emissions Examined only in normal operation Planning level for LV, MV and HV networs (IEC ) Compatibility levels for harmonic voltages in LV,MV and HV systems in % of the nominal voltage: At high frequencies (>2 Hz), no standards exist. Utilities demand U h < 0.2 regardless of the type of generator 8

9 Harmonics emissions in MV systems For each harmonic order, the actual harmonic voltage in MV system results from the vectorial combination of the harmonic voltage from the upstream HV system and the harmonic voltage resulting from all the non-linear loads connected to the MV system. It should hot exceed the planning level of the MV system T hhm L hhm HV G hmv = α L α hmv (T hhm L hhv ) α Distortion transmitted from HV system ummation exponent WF MV Global emission in the MV system (may be assessed from the harmonic current times source impedance Planning level of the hth Harmonic in the MV system Rated (agreed) power of the WF Individual emission limit E Uhi = G hmv α i MV 1 F MV Coincident factor for MV Loads (0.4 1) Total power of the loads supplied at MV/HV transformer 9

10 Flicer emissions in MV systems Examined for normal and switching operations MV compatibility planning levels P st =0.9 and P lt =0.7 Assessment of flicer emissions from WTs during normal operations ingle WT Networ impedance angle at PCC Annual average wind speed P st = Plt = c ( ψ, v a ) n Rated apparent power of the WT hort circuit apparent power at PCC Flicer coefficient (WT certificate) P 1 Aggregate wind farm N 2 st Σ = Plt Σ = ( c i ( ψ, va ) n,i) i= 1 10

11 Fault level: tatement of the problem Distribution networs are characterized by a design short-circuit capacity (max fault current) Distributed generation resources, as wind farms connected to distribution networs contribute to the total fault level of the networ (sum of upstream grid + local contributions) The short-circuit capacity of existing distribution networs is close to the design maximum value Little margin for the connection of new power installation Fault level frequently is the main limitation for high WP penetration into the grid The at PCC to the MV-networ shall be at least 50 times the apparent rated power of the wind power installation 11

12 The IEC method for the calculation of the short-circuit currents Advantages tandardized, reliable, widely accepted Easily applicable in radial networs Pre-fault operating conditions not needed Disadvantages Not adapted to distributed generation as Wind power Lac of standardized treatment of the DG sources Correction factors derived for conventional generation 12

13 Fault current contribution of the DG sources (IEC 60909) ynchronous generators directly coupled to grid: Z = K Z = K R + jx ) GK G G G ( G d Asynchronous generators directly coupled to grid: Z G = I LR 1 I rg U rg 3I DFIG with power in the rotor circuit K 2 rg U c n max G = (impedance correction factor) UrG 1+ x d sinϕrg ame as for asynchronous generator (I 5 I rated ) Power converter interfaced units rg = I LR 1 I rg U rg As constant current injection (I 1.2 p.u. usually) 13

14 olutions for fault level management Increase the design maximum fault level Reduce the prospective short-circuit current of the grid Networ reconfiguration Install current limiting reactors Increase transformer impedance Reduce the prospective short-circuit current of the DG Use equipment (gen) with increased short current impedance Install current limiting reactors Connect the grid via power converters 14

15 Protection functions Objectives Over-current protection (phase and ground protection, as in any consumer installation) Protect the DG installation from abnormal operating conditions (voltage/frequency) Prevent islanding of the DGs with part of the networ Prevent operating the DGs from experiencing re-closing of networ breaers upervise the re-synchronization of the installation with the grid 15

16 Protection schemes: Basic functions Inst Opening 0.1s Automatic re-closing after 0.5 s Relaxed settings ource tavaros A. Papathanassiou 16

17 Protection schemes Considerations and remars Increasing the sensitivity and speed of disconnection protects the installation more effectively but increases the number of unnecessary trips Networ with re-closing schemes The DG must be disconnected before the first re-closing of the line breaer Preferably the DG should be disconnected as soon as the line breaer trips, to avoid feeding the fault In networ with short interruption/fast re-closing schemes, the DG must be disconnected in less than 0.5 sec. mall island networs with large WP penetration is a special case The protection system settings are relaxed in order to avoid the loss of large amounts of generations 17

18 Grid code requirements EON requirements Deepest voltage allowed on gen. terminal side about 0.3 p.u. Frequency band Hz Different power factors (over/under-excited mode) FRT capability at PCC (relay setting at WT 0.3 p.u. ) Reactive Current into the networ 18

19 My contribution within the project Main focus on voltage and angle stability constraints, and special emphasis is put on power systems incorporating large scale wind power integration. Large cale Wind Power Integration, Voltage stability Limits and Modal Analysis (PCC05) Fundamental nature of low frequency inter-area modes of oscillations and power system damping; mall signal and voltage stability are performed as a combined study; WF modeled as an asynchronous machine improves the damping of the inter-area mode of oscillation; With synchronous generators local mode of oscillations might be the limiting factor in relation to the power produced; A Proposed Model for tability Assessment of Electrical Power ystem with Large cale Wind Power Integration (WWEC05) The method adopted is based on the systematic analysis both static and dynamic of power systems; It gives some insights into a systematic method to follow in WP stability assessments which enhances the WP integration in electrical power systems; It is shown that in some cases the disconnection of the WF can be convenient reducing the reactive power consumption and stabilizing the voltage; 19

IEEE sion/1547revision_index.html

IEEE sion/1547revision_index.html IEEE 1547 IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces http://grouper.ieee.org/groups/scc21/1547_revi sion/1547revision_index.html

More information

Technical Requirements for Connecting Small Scale PV (sspv) Systems to Low Voltage Distribution Networks

Technical Requirements for Connecting Small Scale PV (sspv) Systems to Low Voltage Distribution Networks 2014 Technical Requirements for Connecting Small Scale PV (sspv) Systems to Low Voltage Distribution Networks This document specifies the technical requirement for connecting sspv to the low voltage distribution

More information

IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces

IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces IEEE PES Boston Chapter Technical Meeting IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces P1547 Chair David

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements Division 502 Technical Applicability 1(1) Section 502.1 applies to: Expedited Filing Draft August 22, 2017 the legal owner of an aggregated generating facility directly connected to the transmission system

More information

Intermittent Renewable Resources (Wind and PV) Distribution Connection Code (DCC) At Medium Voltage (MV)

Intermittent Renewable Resources (Wind and PV) Distribution Connection Code (DCC) At Medium Voltage (MV) Intermittent Renewable Resources (Wind and PV) Distribution Connection Code (DCC) At Medium Voltage (MV) IRR-DCC-MV 1. Introduction 1 IRR-DCC-MV 2. Scope 1 IRR-DCC-MV 2.1. General 1 IRR-DCC-MV 2.2. Affected

More information

A STUDY CASE ON HARMONIC DISTORTION CREATED BY WIND TURBINES

A STUDY CASE ON HARMONIC DISTORTION CREATED BY WIND TURBINES C I R E D 8 th International Conference on Electricity Distribution Turin, 6-9 June 5 A STUDY CASE ON HARMONIC DISTORTION CREATED BY WIND TURBINES Stavros PAPATHANASSIOU Michael PAPADOPOULOS National Technical

More information

How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements

How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements Robert Nelson Senior Expert Engineering Manager and Manager of Codes, Standards, and Regulations Siemens Wind Turbines -

More information

Wind Power Facility Technical Requirements CHANGE HISTORY

Wind Power Facility Technical Requirements CHANGE HISTORY CHANGE HISTORY DATE VERSION DETAIL CHANGED BY November 15, 2004 Page 2 of 24 TABLE OF CONTENTS LIST OF TABLES...5 LIST OF FIGURES...5 1.0 INTRODUCTION...6 1.1 Purpose of the Wind Power Facility Technical

More information

EH2741 Communication and Control in Electric Power Systems Lecture 2

EH2741 Communication and Control in Electric Power Systems Lecture 2 KTH ROYAL INSTITUTE OF TECHNOLOGY EH2741 Communication and Control in Electric Power Systems Lecture 2 Lars Nordström larsno@kth.se Course map Outline Transmission Grids vs Distribution grids Primary Equipment

More information

Experience in the application of IEC/TR to harmonic allocation in transmission systems

Experience in the application of IEC/TR to harmonic allocation in transmission systems University of Wollongong Research Online Faculty of Engineering and Information Sciences - Papers: Part A Faculty of Engineering and Information Sciences 2006 Experience in the application of IEC/TR 61000-3-6

More information

LARGE-SCALE WIND POWER INTEGRATION, VOLTAGE STABILITY LIMITS AND MODAL ANALYSIS

LARGE-SCALE WIND POWER INTEGRATION, VOLTAGE STABILITY LIMITS AND MODAL ANALYSIS LARGE-SCALE WIND POWER INTEGRATION, VOLTAGE STABILITY LIMITS AND MODAL ANALYSIS Giuseppe Di Marzio NTNU giuseppe.di.marzio@elkraft.ntnu.no Olav B. Fosso NTNU olav.fosso@elkraft.ntnu.no Kjetil Uhlen SINTEF

More information

A robust voltage unbalance allocation methodology based on the IEC/TR guidelines

A robust voltage unbalance allocation methodology based on the IEC/TR guidelines University of Wollongong Research Online Faculty of Engineering - Papers (Archive) Faculty of Engineering and Information Sciences 2009 A robust voltage unbalance allocation methodology based on the IEC/TR

More information

POWER QUALITY IMPACTS AND MITIGATION OF DISTRIBUTED SOLAR POWER

POWER QUALITY IMPACTS AND MITIGATION OF DISTRIBUTED SOLAR POWER POWER QUALITY IMPACTS AND MITIGATION OF DISTRIBUTED SOLAR POWER Presented by Ric Austria, Principal at Pterra Consulting to the IEEE San Francisco Chapter Feb 17, 2016 California Public Utilities Commission,

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

Phase-phase/phase-neutral: 24/13.8 kv star, 13.8 kv delta, 12/6.9 kv star.

Phase-phase/phase-neutral: 24/13.8 kv star, 13.8 kv delta, 12/6.9 kv star. Summary Of Interconnection Technical Guidelines for Renewable Energy Systems 0-100 kw under Standard Offer Contract (Extract from JPS Guide to Interconnection of Distributed Generation) This document is

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements Applicability 1(1) Section 502.1 applies to the ISO, and subject to the provisions of subsections 1(2), (3) and (4) to any: (a) a new wind aggregated generating facility to be connected to the transmission

More information

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76 PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion

More information

Grid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017

Grid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017 Grid codes and wind farm interconnections CNY Engineering Expo Syracuse, NY November 13, 2017 Purposes of grid codes Grid codes are designed to ensure stable operating conditions and to coordinate the

More information

Embedded Generation Connection Application Form

Embedded Generation Connection Application Form Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed

More information

The Impact of Connecting Distributed Generation to the Distribution System E. V. Mgaya, Z. Müller

The Impact of Connecting Distributed Generation to the Distribution System E. V. Mgaya, Z. Müller The Impact of Connecting Distributed Generation to the Distribution System E. V. Mgaya, Z. Müller This paper deals with the general problem of utilizing of renewable energy sources to generate electric

More information

DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation

DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation Technical Requirements for Interconnection and Parallel Operation of Distributed Generation Single Phase

More information

Embedded Generation Connection Application Form

Embedded Generation Connection Application Form Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed

More information

Embedded Generation Connection Application Form

Embedded Generation Connection Application Form Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed

More information

IEEE sion/1547revision_index.html

IEEE sion/1547revision_index.html IEEE 1547 IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces http://grouper.ieee.org/groups/scc21/1547_revi sion/1547revision_index.html

More information

Impact Assessment Generator Form

Impact Assessment Generator Form Impact Assessment Generator Form This connection impact assessment form provides information for the Connection Assessment and Connection Cost Estimate. Date: (dd/mm/yyyy) Consultant/Developer Name: Project

More information

Adaptive Relaying of Radial Distribution system with Distributed Generation

Adaptive Relaying of Radial Distribution system with Distributed Generation Adaptive Relaying of Radial Distribution system with Distributed Generation K.Vijetha M,Tech (Power Systems Engineering) National Institute of Technology-Warangal Warangal, INDIA. Email: vijetha258@gmail.com

More information

POWER TRANSFORMER SPECIFICATION, DESIGN, QUALITY CONTROL AND TESTING 18 MARCH 2009

POWER TRANSFORMER SPECIFICATION, DESIGN, QUALITY CONTROL AND TESTING 18 MARCH 2009 POWER TRANSFORMER SPECIFICATION, DESIGN, QUALITY CONTROL AND TESTING 18 MARCH 2009 Nkosinathi Buthelezi Senior Consultant: Power Transformers and Reactors Presentation Content Standardization of Power

More information

Southern Company Power Quality Policy

Southern Company Power Quality Policy Southern Company Power Quality Policy Alabama Power Georgia Power Gulf Power Mississippi Power i Table of Contents: Southern Company Power Quality Policy SCOPE AND PURPOSE... 1 DEFINITIONS... 2 I. HARMONICS...

More information

Table of Contents. Introduction... 1

Table of Contents. Introduction... 1 Table of Contents Introduction... 1 1 Connection Impact Assessment Initial Review... 2 1.1 Facility Design Overview... 2 1.1.1 Single Line Diagram ( SLD )... 2 1.1.2 Point of Disconnection - Safety...

More information

Connection of Embedded Generating Plant up to 5MW

Connection of Embedded Generating Plant up to 5MW Engineering Recommendation No.3 of the Electricity Distribution Code Connection of Embedded Generating Plant up to 5MW Version 1.0 30th November 2005 Prepared by: Al Ain Distribution Company, Abu Dhabi

More information

Grid Converters for Photovoltaic

Grid Converters for Photovoltaic Grid Converters for Photovoltaic and Wind Power Systems by R. Teodorescu, M. Liserre and P. Rodriguez ISBN: 978 0 470 05751 3 Copyright Wiley 2011 Chapter 3 Grid Requirements for PV Grid connection requirements

More information

Impact of limiting reactors for voltage sag mitigation in distribution utilities

Impact of limiting reactors for voltage sag mitigation in distribution utilities Elektrotehniški vestnik 71(5): 31-37, 24 Electrotechnical Review; Ljubljana, lovenija Impact of limiting reactors for voltage sag mitigation in distribution utilities tefano Quaia, imone Castellan Department

More information

ECE 528 Understanding Power Quality

ECE 528 Understanding Power Quality ECE 528 Understanding Power Quality http://www.ece.uidaho.edu/ee/power/ece528/ Paul Ortmann portmann@uidaho.edu 208-733-7972 (voice) Lecture 19 1 Today Flicker Power quality and reliability benchmarking

More information

MEASUREMENT CAMPAIGN AND ASSESSMENT OF THE QUALITY OF SUPPLY IN RES AND DG FACILITIES IN SPAIN

MEASUREMENT CAMPAIGN AND ASSESSMENT OF THE QUALITY OF SUPPLY IN RES AND DG FACILITIES IN SPAIN MEASUREMENT CAMPAIGN AND ASSESSMENT OF THE QUALITY OF SUPPLY IN RES AND DG FACILITIES IN SPAIN Eugenio PEREA*, Eduardo ZABALA*, J. Emilio RODRÍGUEZ*, Asier GIL DE MURO*, Hugo GAGO * * * Fundación LABEIN,

More information

RENEWABLE ENERGY SUB-CODE for Distribution Network connected Variable Renewable Energy Power Plants in Ghana

RENEWABLE ENERGY SUB-CODE for Distribution Network connected Variable Renewable Energy Power Plants in Ghana RENEWABLE ENERGY SUB-CODE for Distribution Network connected Variable Renewable Energy Power Plants in Ghana JANUARY 2015 i Table of Content PART A: 1 1 Introduction 1 1.1 Scope 1 1.2 Status 1 1.3 Terms

More information

On the Evaluation of Power Quality Indices in Distribution Systems with Dispersed Generation

On the Evaluation of Power Quality Indices in Distribution Systems with Dispersed Generation European Association for the Development of Renewable Energies, Environment and Power Quality International Conference on Renewable Energies and Power Quality (ICREPQ 09) Valencia (Spain), 1th to 17th

More information

Comparison of methodologies for assessment of harmonic current emission limits for large installations connected to LV networks

Comparison of methodologies for assessment of harmonic current emission limits for large installations connected to LV networks University of Wollongong Research Online Faculty of Engineering and Information Sciences - Papers: Part A Faculty of Engineering and Information Sciences 212 Comparison of methodologies for assessment

More information

ADVANCED CONTROLS FOR MITIGATION OF FLICKER USING DOUBLY-FED ASYNCHRONOUS WIND TURBINE-GENERATORS

ADVANCED CONTROLS FOR MITIGATION OF FLICKER USING DOUBLY-FED ASYNCHRONOUS WIND TURBINE-GENERATORS ADVANCED CONTROLS FOR MITIGATION OF FLICKER USING DOUBLY-FED ASYNCHRONOUS WIND TURBINE-GENERATORS R. A. Walling, K. Clark, N. W. Miller, J. J. Sanchez-Gasca GE Energy USA reigh.walling@ge.com ABSTRACT

More information

Islanding Detection Method Based On Impedance Measurement

Islanding Detection Method Based On Impedance Measurement Islanding Detection Method Based On Impedance Measurement Chandra Shekhar Chandrakar 1, Bharti Dewani 2 Department of Electrical and Electronics Engineering Chhattisgarh Swami Vivekananda Technical University

More information

Comparison of the Behaviour of Wind Farms and Conventional Power Stations during Grid Failure Conditions

Comparison of the Behaviour of Wind Farms and Conventional Power Stations during Grid Failure Conditions May 4 Comparison of the Behaviour of Wind Farms and Conventional Power Dr. Martin Janßen APCG / 4MJA5_Wind-Farms-IEEE_13-5-4_EN.PPT Overview Introduction Grid Faults Requirements for Grid Stability Fault

More information

WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS

WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS WFPS1.1 INTRODUCTION 2 WFPS1.2 OBJECTIVE 2 WFPS1.3 SCOPE 3 WFPS1.4 FAULT RIDE THROUGH REQUIREMENTS 4 WFPS1.5 FREQUENCY REQUIREMENTS 5 WFPS1.6 VOLTAGE

More information

Southern Company Interconnection Requirements for Inverter-Based Generation

Southern Company Interconnection Requirements for Inverter-Based Generation Southern Company Interconnection Requirements for Inverter-Based Generation September 19, 2016 Page 1 of 16 All inverter-based generation connected to Southern Companies transmission system (Point of Interconnection

More information

Application for A Sub-harmonic Protection Relay. ERLPhase Power Technologies

Application for A Sub-harmonic Protection Relay. ERLPhase Power Technologies Application for A Sub-harmonic Protection Relay ERLPhase Power Technologies 1 Outline Introduction System Event at Xcel Energy Event Analysis Microprocessor based relay hardware architecture Sub harmonic

More information

POWER QUALITY REPORT

POWER QUALITY REPORT Power Quality Research Lab., I-7, Wyb. Wyspiaoskiego 27, 50-370 Wrocław, Poland phone +48713202626, fax +48713202006, email: zbigniew.leonowicz@pwr.wroc.pl Facility: XXX POWER QUALITY REPORT Start Monitoring:

More information

Energy Networks Association

Energy Networks Association The Voice of the Networks Version 1 (ISSUED) Energy Networks Association Insert presentation title here ENA EREC P28 Issue 2 2018 Key Technical Modifications Grid Code and SQSS Mods Name Position Date

More information

Optimal sizing of battery energy storage system in microgrid system considering load shedding scheme

Optimal sizing of battery energy storage system in microgrid system considering load shedding scheme International Journal of Smart Grid and Clean Energy Optimal sizing of battery energy storage system in microgrid system considering load shedding scheme Thongchart Kerdphol*, Yaser Qudaih, Yasunori Mitani,

More information

Control of Wind Power Plant for Cooperation with Conventional Power Generation Unit and HVDC Classic Link

Control of Wind Power Plant for Cooperation with Conventional Power Generation Unit and HVDC Classic Link Control of Wind Power Plant for Cooperation with Conventional Power Generation Unit and HVDC Classic Link Li-Jun Cai*, Simon Jensen **, Vincenz Dinkhauser***, István Erlich**** REpower Systems SE,. Albert-Betz-Strasse,

More information

Harmonic Planning Levels for Australian Distribution Systems

Harmonic Planning Levels for Australian Distribution Systems Abstract Harmonic Planning Levels for Australian Distribution Systems V.J. Gosbell 1, V.W. Smith 1, D. Robinson 1 and W. Miller 2 1 Integral Energy Power Quality Centre, University of Wollongong 2 Standards

More information

Connection Impact Assessment Application

Connection Impact Assessment Application Connection Impact Assessment Application This form is for generators applying for Connection Impact Assessment (CIA) and for generators with a project size >10 kw. Please return the completed form by email,

More information

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC A. Introduction 1. Title: Generator Frequency and Voltage Protective Relay Settings 2. Number: PRC-024-2 3. Purpose: Ensure Generator Owners set their generator protective relays such that generating units

More information

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction A. Introduction 1. Title: Generator Frequency and Voltage Protective Relay Settings 2. Number: PRC-024-1 3. Purpose: Ensure Generator Owners set their generator protective relays such that generating units

More information

Power Quality Summary

Power Quality Summary Power Quality Summary This article provides an overview of how voltage harmonic distortion is managed on the distribution network and focuses on the current at future issues surround the connection of

More information

Power Quality Requirements for Connection to the Transmission System

Power Quality Requirements for Connection to the Transmission System Power Quality Requirements for Connection to the Transmission System Revision: 1.0 Date: September 2015 Introduction and Purpose of this Document The purpose of this document is to provide clarity to Customers

More information

Standards Developments for Fault Current Limiters

Standards Developments for Fault Current Limiters tandards Developments for Fault Current Limiters Dr. Michael Mischa teurer steurer@caps.fsu.edu Center for Advanced Power ystems (CAP) Florida tate University 2000 Levy Avenue, Building A, Tallahassee,

More information

ECE 528 Understanding Power Quality

ECE 528 Understanding Power Quality ECE 528 Understanding Power Quality http://www.ece.uidaho.edu/ee/power/ece528/ Paul Ortmann portmann@uidaho.edu 208-733-7972 (voice) Lecture 22 1 Today Homework 5 questions Homework 6 discussion More on

More information

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control Spring 2014 Instructor: Kai Sun 1 References Saadat s Chapters 12.6 ~12.7 Kundur s Sections

More information

Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing Methods

Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing Methods Proceedings of the th WSEAS International Conference on Power Systems, Beijing, China, September -, 200 Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing

More information

Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at

Use only for doing work with or for BC Hydro. Complete Legal Acknowledgement is at Reviewed: Sergey Kryuchkov Distribution Engineering Scott Merriman Distribution Standards Valentina Dabic Distribution Planning Warren Quan Distribution Operations, FVO Raj Solanki Distribution Engineering

More information

Influence of Wind Generators in Voltage Dips

Influence of Wind Generators in Voltage Dips Influence of Wind Generators in Voltage Dips E. Belenguer, N. Aparicio, J.L. Gandía, S. Añó 2 Department of Industrial Engineering and Design Universitat Jaume I Campus de Riu Sec, E-27 Castelló (Spain)

More information

The development of the SA grid code on Power Quality emission. Dr. Gerhard Botha 2017/08/08

The development of the SA grid code on Power Quality emission. Dr. Gerhard Botha 2017/08/08 The development of the SA grid code on Power Quality emission Dr. Gerhard Botha 2017/08/08 Overview What is the Grid Code? What is Power Quality? Power Quality Management Principles Differences Challenges

More information

DG TRANSFER CONNECTION SCHEME IN ACTIVE DISTRIBUTION NETWORKS

DG TRANSFER CONNECTION SCHEME IN ACTIVE DISTRIBUTION NETWORKS DG TRANSFER CONNECTION SCHEME IN ACTIVE DISTRIBUTION NETWORKS Abdelrahman AKILA Ahmed HELAL Hussien ELDESOUKI SDEDCO Egypt AASTMT Egypt AASTMT Egypt Abdurrahman.akela@gmail.com ahmedanas@aast.edu hdesouki@aast.edu

More information

INTERIM ARRANGEMENTS FOR GRID TIED DISTRIBUTED ENERGY RESOURCES. Technical Requirements for Grid-Tied DERs

INTERIM ARRANGEMENTS FOR GRID TIED DISTRIBUTED ENERGY RESOURCES. Technical Requirements for Grid-Tied DERs INTERIM ARRANGEMENTS FOR GRID TIED DISTRIBUTED ENERGY RESOURCES Technical Requirements for Grid-Tied DERs Projects Division 6/29/2017 Contents 1 Definitions and Acronyms... 1 2 Technical Interconnection

More information

THE IMPACT OF NETWORK SPLITTING ON FAULT LEVELS AND OTHER PERFORMANCE MEASURES

THE IMPACT OF NETWORK SPLITTING ON FAULT LEVELS AND OTHER PERFORMANCE MEASURES THE IMPACT OF NETWORK SPLITTING ON FAULT LEVELS AND OTHER PERFORMANCE MEASURES C.E.T. Foote*, G.W. Ault*, J.R. McDonald*, A.J. Beddoes *University of Strathclyde, UK EA Technology Limited, UK c.foote@eee.strath.ac.uk

More information

POWER QUALITY IMPROVEMENT IN A GRID CONNECTED WIND ENERGY CONVERSION SYSTEM USING DYNAMIC VOLTAGE RESTORER

POWER QUALITY IMPROVEMENT IN A GRID CONNECTED WIND ENERGY CONVERSION SYSTEM USING DYNAMIC VOLTAGE RESTORER POWER QUALITY IMPROVEMENT IN A GRID CONNECTED WIND ENERGY CONVERION YTEM UING DYNAMIC VOLTAGE RETORER PG cholar, Electrical and Electronics Engineering, K.L.N.College of Engineering, ivagangai. adhithyan.karthi@gmail.com

More information

Technical information Grid Support Utility Interactive Inverters for Sunny Central-US and Sunny Central Storage-US

Technical information Grid Support Utility Interactive Inverters for Sunny Central-US and Sunny Central Storage-US Technical information Grid Support Utility Interactive Inverters for Sunny Central-US and Sunny Central Storage-US ENGLISH SC-US-GridServices-TI-en-10 Version 1.0 Table of Contents SMA Solar Technology

More information

Chapter -3 ANALYSIS OF HVDC SYSTEM MODEL. Basically the HVDC transmission consists in the basic case of two

Chapter -3 ANALYSIS OF HVDC SYSTEM MODEL. Basically the HVDC transmission consists in the basic case of two Chapter -3 ANALYSIS OF HVDC SYSTEM MODEL Basically the HVDC transmission consists in the basic case of two convertor stations which are connected to each other by a transmission link consisting of an overhead

More information

COMPARATIVE PERFORMANCE OF SMART WIRES SMARTVALVE WITH EHV SERIES CAPACITOR: IMPLICATIONS FOR SUB-SYNCHRONOUS RESONANCE (SSR)

COMPARATIVE PERFORMANCE OF SMART WIRES SMARTVALVE WITH EHV SERIES CAPACITOR: IMPLICATIONS FOR SUB-SYNCHRONOUS RESONANCE (SSR) 7 February 2018 RM Zavadil COMPARATIVE PERFORMANCE OF SMART WIRES SMARTVALVE WITH EHV SERIES CAPACITOR: IMPLICATIONS FOR SUB-SYNCHRONOUS RESONANCE (SSR) Brief Overview of Sub-Synchronous Resonance Series

More information

1

1 Guidelines and Technical Basis Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive

More information

THE ROLE OF SYNCHROPHASORS IN THE INTEGRATION OF DISTRIBUTED ENERGY RESOURCES

THE ROLE OF SYNCHROPHASORS IN THE INTEGRATION OF DISTRIBUTED ENERGY RESOURCES THE OLE OF SYNCHOPHASOS IN THE INTEGATION OF DISTIBUTED ENEGY ESOUCES Alexander APOSTOLOV OMICON electronics - USA alex.apostolov@omicronusa.com ABSTACT The introduction of M and P class Synchrophasors

More information

POWER CORPORATION. Power Quality. Specifications and Guidelines for Customers. Phone: Fax:

POWER CORPORATION. Power Quality. Specifications and Guidelines for Customers. Phone: Fax: POWER CORPORATION Power Quality Specifications and Guidelines for Customers Phone: 403-514-3700 Fax: 403-514-3719 1 GENERAL OVERVIEW........................................ 1.1 WHAT DOES THIS SPECIFICATION

More information

Renewable Interconnection Standard & Experimental Tests. Yahia Baghzouz UNLV Las Vegas, NV, USA

Renewable Interconnection Standard & Experimental Tests. Yahia Baghzouz UNLV Las Vegas, NV, USA Renewable Interconnection Standard & Experimental Tests Yahia Baghzouz UNLV Las Vegas, NV, USA Overview IEEE Std 1547 Voltage limitations Frequency limitations Harmonic limitations Expansion of IEEE Std

More information

Tasmanian Networks Pty Ltd Guideline. Technical Requirements for the Connection of Embedded Generation

Tasmanian Networks Pty Ltd Guideline. Technical Requirements for the Connection of Embedded Generation Tasmanian Networks Pty Ltd Guideline Technical Requirements for the Connection of Embedded Generation Revision 08 November 2017 Disclaimer This document has been prepared for the purposes of informing

More information

Feeder Protection Challenges with High Penetration of Inverter Based Distributed Generation

Feeder Protection Challenges with High Penetration of Inverter Based Distributed Generation Feeder Protection Challenges with High Penetration of Inverter Based Distributed Generation Harag Margossian 1, Florin Capitanescu 2, Juergen Sachau 3 Interdisciplinary Centre for Security, Reliability

More information

BED INTERCONNECTION TECHNICAL REQUIREMENTS

BED INTERCONNECTION TECHNICAL REQUIREMENTS BED INTERCONNECTION TECHNICAL REQUIREMENTS By Enis Šehović, P.E. 2/11/2016 Revised 5/19/2016 A. TABLE OF CONTENTS B. Interconnection Processes... 2 1. Vermont Public Service Board (PSB) Rule 5.500... 2

More information

Real-time Monitoring of Power Oscillations and Modal Damping in the European ENTSO-E System

Real-time Monitoring of Power Oscillations and Modal Damping in the European ENTSO-E System Mats Larsson, ABB CRC Switzerland; Luis-Fabiano Santos, ABB SAS Switzerland; Galina Antonova, AB B SA Canada, Reynaldo Nuqui, ABB CRC USA NASPI meeting, February 20, 2013 Real-time Monitoring of Power

More information

Power System Stability. Course Notes PART-1

Power System Stability. Course Notes PART-1 PHILADELPHIA UNIVERSITY ELECTRICAL ENGINEERING DEPARTMENT Power System Stability Course Notes PART-1 Dr. A.Professor Mohammed Tawfeeq Al-Zuhairi September 2012 1 Power System Stability Introduction Dr.Mohammed

More information

Generation and Load Interconnection Standard

Generation and Load Interconnection Standard Generation and Load Interconnection Standard Rev. 0A DRAFT Name Signature Date Prepared: Approved: VP Acceptance APEGGA Permit to Practice P-08200 TABLE OF CONTENTS 1.0 INTRODUCTION...5 1.1 Purpose...5

More information

Transient Stability Improvement Of Power System With Phase Shifting Transformer

Transient Stability Improvement Of Power System With Phase Shifting Transformer INTERNATIONAL JOURNAL OF TECHNOLOGY ENHANCEMENTS AND EMERGING ENGINEERING RESEARCH, VOL 3, ISSUE 3 19 Transient Stability Improvement Of Power System With Phase Shifting Transformer Jyothi Varanasi, Aditya

More information

Constant Terminal Voltage. Working Group 1 29 st January 2014

Constant Terminal Voltage. Working Group 1 29 st January 2014 Constant Terminal Voltage Working Group 1 29 st January 2014 Overview Objectives of Working Group ENTSO-E RfG Implications Options Summary Discussion 2 Objectives of Work Group National Grid in consultation

More information

Some European experiences with renewable installations

Some European experiences with renewable installations Some European experiences with renewable Waveform distortion Ana Maria Blanco, Jan Meyer, Sascha Müller, Anantaram Varatharajan 08.08.2017 Content 1. Introduction 2. Distributed PV inverters (

More information

Implementation of Revised IEEE Standard 1547

Implementation of Revised IEEE Standard 1547 MAY 31, 2017 HOLYOKE, MASSACHUSETTS Implementation of Revised IEEE Standard 1547 Presentation to ISO-TO Operations Committee David Forrest Key Points As New England adds significant amounts of Distributed

More information

Transmission Interconnection Requirements for Inverter-Based Generation

Transmission Interconnection Requirements for Inverter-Based Generation Transmission Requirements for Inverter-Based Generation June 25, 2018 Page 1 Overview: Every generator interconnecting to the transmission system must adhere to all applicable Federal and State jurisdictional

More information

Public Consultation on the Regulatory Framework for Small Scale Grid Connected Solar PV Systems Standards Technical Standards

Public Consultation on the Regulatory Framework for Small Scale Grid Connected Solar PV Systems Standards Technical Standards Consultation Paper: 1/2017 (i) Public Consultation on the Regulatory Framework for Small Scale Grid Connected Solar PV Systems Standards Technical Standards Issued on 19 January 2017 Contents 1. Introduction

More information

Company Directive STANDARD TECHNIQUE: SD1E/2. Technical Requirements for Customer Export Limiting Schemes

Company Directive STANDARD TECHNIQUE: SD1E/2. Technical Requirements for Customer Export Limiting Schemes Company Directive STANDARD TECHNIQUE: SD1E/2 Technical Requirements for Customer Export Limiting Schemes Policy Summary This Standard Technique specifies the requirements for customer owned Export Limitation

More information

QUESTIONNAIRE for Wind Farm Power Stations only

QUESTIONNAIRE for Wind Farm Power Stations only TRANSMISSION SYSTEM OPERATOR QUESTIONNAIRE for Wind Farm Power Stations only To be submitted by the Generation Licensees together with the Application for Connection Certificate according to IEC 61400-21

More information

ELEMENTS OF FACTS CONTROLLERS

ELEMENTS OF FACTS CONTROLLERS 1 ELEMENTS OF FACTS CONTROLLERS Rajiv K. Varma Associate Professor Hydro One Chair in Power Systems Engineering University of Western Ontario London, ON, CANADA rkvarma@uwo.ca POWER SYSTEMS - Where are

More information

ESB National Grid Transmission Planning Criteria

ESB National Grid Transmission Planning Criteria ESB National Grid Transmission Planning Criteria 1 General Principles 1.1 Objective The specific function of transmission planning is to ensure the co-ordinated development of a reliable, efficient, and

More information

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES Highgate Converter Overview Prepared by Joshua Burroughs & Jeff Carrara IEEE PES Highgate Converter Abstract Introduction to HVDC Background on Highgate Operation and Control schemes of Highgate 22 Why

More information

Final ballot January BOT adoption February 2015

Final ballot January BOT adoption February 2015 Standard PRC-024-21(X) Generator Frequency and Voltage Protective Relay Settings Standard Development Timeline This section is maintained by the drafting team during the development of the standard and

More information

Fuel cell power system connection. Dynamics and Control of Distributed Power Systems. DC storage. DC/DC boost converter (1)

Fuel cell power system connection. Dynamics and Control of Distributed Power Systems. DC storage. DC/DC boost converter (1) Dynamics and Control of Distributed Power Systems Fuel cell power system connection Ian A. Hiskens University of Wisconsin-Madison ACC Workshop June 12, 2006 This topology is fairly standard, though there

More information

2012 Grid of the Future Symposium. Impacts of the Decentralized Photovoltaic Energy Resources on the Grid

2012 Grid of the Future Symposium. Impacts of the Decentralized Photovoltaic Energy Resources on the Grid 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2012 Grid of the Future Symposium Impacts of the Decentralized Photovoltaic Energy Resources on the Grid B. ENAYATI, C.

More information

Technical information SUNNY TRIPOWER CORE1-US

Technical information SUNNY TRIPOWER CORE1-US Technical information SUNNY TRIPOWER CORE1-US Grid Support Utility Interactive Inverters ENGLISH STP50-US-40-GridServices-TI-en-10 Version 1.0 Table of Contents SMA Solar Technology America LLC Table of

More information

Wavelet Transform Based Islanding Characterization Method for Distributed Generation

Wavelet Transform Based Islanding Characterization Method for Distributed Generation Fourth LACCEI International Latin American and Caribbean Conference for Engineering and Technology (LACCET 6) Wavelet Transform Based Islanding Characterization Method for Distributed Generation O. A.

More information

Course ELEC Introduction to electric power and energy systems. Additional exercises with answers December reactive power compensation

Course ELEC Introduction to electric power and energy systems. Additional exercises with answers December reactive power compensation Course ELEC0014 - Introduction to electric power and energy systems Additional exercises with answers December 2017 Exercise A1 Consider the system represented in the figure below. The four transmission

More information

Anti-Islanding Protection of Distributed Generation Resources Using Negative Sequence Component of Voltage

Anti-Islanding Protection of Distributed Generation Resources Using Negative Sequence Component of Voltage POWERENG 2007, April 12-14, 2007, Setúbal, Portugal Anti-Islanding Protection of Distributed Generation Resources Using Negative Sequence Component of Voltage Amin Helmzadeh, Javad Sadeh and Omid Alizadeh

More information

Application of Low-Impedance 7SS601 Busbar Differential Protection

Application of Low-Impedance 7SS601 Busbar Differential Protection Application of Low-Impedance 7SS601 Busbar Differential Protection 1. Introduction Utilities have to supply power to their customers with highest reliability and minimum down time. System disturbances,

More information

Generation and Load Interconnection Standard

Generation and Load Interconnection Standard Generation and Load Interconnection Standard Rev. 0 DRAFT Name Signature Date Prepared: Approved: VP Acceptance APEGGA Permit to Practice P-08200 TABLE OF CONTENTS 1.0 INTRODUCTION...5 1.1 Purpose...5

More information

Testing model data usability Excitation Systems PSS Limiters

Testing model data usability Excitation Systems PSS Limiters 1 2016 IEEE/PES General Meeting July 17 th -21 st, 2016 Boston, MA Panel Session Use of the New Revisions of IEEE Std. 421.2 and 421.5 to Satisfy International Grid Code Requirements Testing model data

More information

GRID INTERCONNECTION OF EMBEDDED GENERATION. Part 2: Small-scale embedded generation

GRID INTERCONNECTION OF EMBEDDED GENERATION. Part 2: Small-scale embedded generation ISBN 978-0-626-29938-5 NRS 097-2-3:2014 Edition 1 GRID INTERCONNECTION OF EMBEDDED GENERATION Part 2: Small-scale embedded generation Section 3: Simplified utility connection criteria for low-voltage connected

More information

Technical information SUNNY BOY 3.0-US / 3.8-US / 5.0-US / 6.0-US / 7.0-US / 7.7-US

Technical information SUNNY BOY 3.0-US / 3.8-US / 5.0-US / 6.0-US / 7.0-US / 7.7-US Technical information SUNNY BOY 3.0-US / 3.8-US / 5.0-US / 6.0-US / 7.0-US / 7.7-US Grid Support Utility Interactive Inverters ENGLISH SBxx-1XP-US-40-GridServices-TI-en-15 Version 1.5 Table of Contents

More information