Endorsed Assignments from ERS Framework

Similar documents
ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

Fault Ride Through Technical Assessment Report Template

Industry Webinar. Reactive Power Planning. NERC System Analysis and Modeling Subcommittee (SAMS) March 2017

Lessons Learned in Model Validation for NERC Compliance

Forward Looking Frequency Trends Technical Brief ERS Framework 1 Measures 1, 2, and 4: Forward Looking Frequency Analysis

Harmonizing the Changing Resource Mix Keeping the Grid Together

Real Time Stability Analysis at Peak Reliability. Slaven Kincic, Hongming Zhang JSIS May 2017, SLC

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event

Integration of Wind Generation into Weak Grids

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

Distributed Energy Resources

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF LARGE GENERATION FACILITIES. Document 9020

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

Keeping it up to Speed Off-Nominal Frequency Operations. CETAC 2018 San Ramon

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC

Response of Grid Interconnected Solar PV inverters to Transmission System Faults

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF GENERATION FACILITIES NOT SUBJECT TO FERC JURISDICTION

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

Southern Company Interconnection Requirements for Inverter-Based Generation

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting

Loss of Solar Resources during Transmission Disturbances due to Inverter Settings II

Transmission Interconnection Requirements for Inverter-Based Generation

Unit Auxiliary Transformer (UAT) Relay Loadability Report

Final ballot January BOT adoption February 2015

1

Grid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017

Standard MOD Verification of Models and Data for Generator Excitation Control System or Plant Volt/Var Control Functions

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES

How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements

Target Mchunu and Themba Khoza Eskom Transmission Division, System Operator Grid Code Management

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control

VOLTAGE STABILITY OF THE NORDIC TEST SYSTEM

1200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report

Facilitating Bulk Wind Power Integration Using LCC HVDC

Wind Power Facility Technical Requirements CHANGE HISTORY

Operationalizing Phasor Technology. Model Validation. Webinar. Ken Martin. March 4, Presented by. Page 0

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction

Generation and Load Interconnection Standard

Analysis of Effect on Transient Stability of Interconnected Power System by Introduction of HVDC Link.

Stability Enhancement for Transmission Lines using Static Synchronous Series Compensator

generation greater than 75 MVA (gross aggregate nameplate rating) Generation in the ERCOT Interconnection with the following characteristics:

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number: Address:

IEEE Std Bulk System Opportunities from New Distributed Energy Resource Interconnection and Interoperability Standards

ESB National Grid Transmission Planning Criteria

Implementation of Revised IEEE Standard 1547

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications

Level 6 Graduate Diploma in Engineering Electrical Energy Systems

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. July 2016 Version 4

Short-Circuit Modeling and System Strength

Generation and Load Interconnection Standard

BPS-Connected Inverter-Based Resource Performance

RELIABILITY: Our Advantages, Challenges, and Opportunities

Central Hudson Gas & Electric Corporation. Transmission Planning Guidelines

Doãn Văn Đông, College of technology _ Danang University. 2. Local Techniques a. Passive Techniques

Bulk Electric System Definition Reference Document

NVESTIGATIONS OF RECENT BLACK-

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications

Recently, the SS38 Working Group on Inter-Area Dynamic Analysis completed two study reports on behalf of the UFLS Regional Standard Drafting Team.

DER_A Benchmark Update

Standard MOD Verification of Models and Data for Generator Excitation Control Sys tem or Plant Volt/Var Control Functions

EH2741 Communication and Control in Electric Power Systems Lecture 2

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1

Modeling of Distributed Generation under Next Generation Interconnection Requirements. Anna Edwards. A thesis. Submitted in partial fulfillment of the

PRC Disturbance Monitoring and Reporting Requirements

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. April 2009 Version 2

Unit Auxiliary Transformer Overcurrent Relay Loadability During a Transmission Depressed Voltage Condition

AMEREN s (On Behalf of Its Transmission Owning Affiliates, Including Ameren Missouri, Ameren Illinois, and Ameren Transmission Company of Illinois)

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY

CAISO Restricted - Do Not Distribute Outside of RC Project LOI and NDA Entities Page 1 of 24

Bulk Electric System Definition Reference Document

Inverter-Based Resource Disturbance Analysis

Lessons Learned in Model Validation for NERC Compliance

Power Plant and Transmission System Protection Coordination

Interconnection-Wide Oscillation Analysis: Baselining Oscillation Modes in the North American Power System Objective Purpose

EE 742 Power System Components. Y. Baghzouz ECE Department UNLV

System Protection and Control Subcommittee

Possible Future Modifications to IEEE 1547

Robert W. Cummings - NERC Director of System Analysis and Reliability Initiatives William Herbsleb - Chairman of Frequency Response Standard Drafting

Power Conditioning Equipment for Improvement of Power Quality in Distribution Systems M. Weinhold R. Zurowski T. Mangold L. Voss

TTC Study for: the PEGS-Ambrosia Lake 230 kv Line and the PEGS-Bluewater 115 kv Line

( ) usable, minor formatting/editing required ( ) modification needed ( ) superseded by ( ) other ( ) obsolete/archived)

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell

CHAPTER 4 POWER QUALITY AND VAR COMPENSATION IN DISTRIBUTION SYSTEMS

Transmission System Phase Backup Protection

Harnessing of wind power in the present era system

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

Using Synchrophasors for Frequency Response Analysis in the Western Interconnection. Bonneville Power Administration -- WECC JSIS Chair

Modeling and Evaluation of Geomagnetic Storms in the Electric Power System

each time the Frequency is above 51Hz. Continuous operation is required

MidAmerican Energy Company Reliability Planning Criteria for 100 kv and Above

HISTORY: How we got to where we are. March 2015 Roy Boyer 1

Intermittent Renewable Resources (Wind and PV) Distribution Connection Code (DCC) At Medium Voltage (MV)

Stability Issues of Smart Grid Transmission Line Switching

Fault Induced Delayed Voltage Recovery (FIDVR) Advisory

Voltage and Frequency Dependency

OPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS

Power Plant and Transmission System Protection Coordination

Transcription:

ERSTF Completion Endorsed Assignments from ERS Framework Ref Number Title ERS Recommendatio n Ongoing Responsibility 1 Synch Inertia at Interconnection Level Measure 2 Initial Frequency Deviation Measure 3 Synch Inertia at BA Level Measure 4 Freq Response at Interconnection Level Measure RS & FWG + MISO IDC SMEs + Rich Hydzik (other members in WI) + Julia Matevosyan (ERCOT) Current Data: EI IDC Data tentatively by June. WI RS to reach out to Peak RC ERCOT No Action HQ Francis Monette in RS data covered NERC IT Pooja Future Data: June 2016 5 Real Time Inertial Model Industry Practice BA 6 Net Demand Ramping Variability Measure RAS 7 Reactive Capability on the System Measure PAS & SAMS It is the output of Measure 3 results RAS Layne will bring it back to RAS for incorporation John will work with PAS to get granular data. John will socialize the Reactive White Paper with his subgroup and collect thoughts on future aspect RAS Meeting April 12-13 PAS conference call Mar 24, Meeting April 6-7, and SAMS meeting May 2-3 1 RELIABILITY ACCOUNTABILITY On going through Event

DERTF Work Plan 2/22/2016 1. What are Distributed Energy Resources? Brian Evans-Mongeon, Layne Brown, Sylvester Toe, Tony Jankowski, Gary Keenan a. Definitions i. Functional Model - NERC b. Behind the Meter Generation (BTMG) i. Size/scale ii. Net metering arrangements iii. Customer owned c. Distributed Generation (DG) i. Directly connected to utility distribution facilities ii. Interconnected generator resource d. Typical resources? Solar, small hydro, wind, what? ERS Meeting Update Brian designed a strawman for definitions. I would like to offer a cut at the definitions for BTMG and DG. I am suggesting a strong link to existing definitions in order to keep things relatively close to determinants like BES and such. BTMG: A generating unit or multiple generating units at a single location (regardless of ownership), of any nameplate size, on the customer s side of the retail meter that serve all or part of the customer s retail Load with electric energy. All electrical equipment from and including the generation set up to the metering point is considered to be behind-the-meter. DER: Resource(s) with gross individual nameplate rating less than or equal to 20 MVA or gross plant/facility aggregate nameplate rating less than or equal to 75 MVA including the generator terminals through the high-side of the step-up transformer(s) connected at a voltage of under 100 kv including interconnections with a utility s distribution facilities. What about storage? 2. How are Distributed Energy Resources connected? Sylvester Toe a. Low voltage BTMG NEC code and utility requirements b. Distributed Generation NESC and utility requirements 3. How are Distributed Energy Resources modeled? Jens Boemer, Gary Keenan, Barry Mather, Quoc Le, Dariush Shirmohammadi a. Distribution load is netted at source bus on present models b. Is it being modeled discretely anywhere? c. When does it become significant? 4. What are Distributed Energy Resources operating characteristics? Jason MacDowell, Rich Hydzik, Dariush Shirmohammadi a. IEEE 1547 Requirements 1

i. Now ii. Future b. Frequency and voltage ride through (pending NERC PRC-024-2) c. Active fault source? d. Can it run independently of utility connection? e. Smart or passive? f. Governor action 5. What effects to Distributed Energy Resources have on the Bulk Electric System (BES)? Tony Jankowski, Gary Keenan, Charlie Smith, Dariush Shirmohammadi a. Planning What is the net load? What is the peak load to serve? b. Operations MSSC how big is it? c. Negative distribution load? Flow up the transformer? Fault source? d. Balancing Authority Load i. DER nets with load from BA perspective ii. Steady or variable? iii. Predictable in BA load forecast? iv. How does it affect operating reserve requirements? e. X 6. Applicable NERC Reliability Standards Jason MacDowell, Gary Keenan a. MOD-010-0 Steady State Data for Modeling and Simulation of Interconnected Transmission System b. MOD-012-0 Dynamics Data for Modeling and Simulation of the Interconnected Transmission System c. MOD-016-1.1 Documentation of Data Reporting Requirements for Actual and Forecast Demands, Net Energy for Load, and Controllable Demand-Side Management d. MOD-017-0.1 Aggregated Actual and Forecast Demands and Net Energy for Load e. MOD-019-0.1 Reporting of Interruptible Demands and Direct Control Load Management f. MOD-020-0 Providing Interruptible Demands and Direct Load Control Management Data to System Operators and Reliability Coordinators g. MOD-021-1 Documentation of the Accounting Methodology for the Effects of Demand- Side Management in Demand and Energy Forecasts h. MOD-031 is pending i. MOD-032 replaces MOD-010 j. MOD-033 replaces MOD-012 k. PRC-006 UFLS l. PRC-0?? UVLS schemes m. PRC-019 n. PRC-024-2 (pending) Generator Voltage and Frequency Coordination 7. Recommendations a. Connection requirements b. Modeling 2

c. Performance requirements? d. Accounting Load/Gen? e. Modifications to any NERC Standards? 8. Membership 9. X 3

Transient Stability Analysis of an all Converter Interfaced Generation (CIG) WECC system Deepak Ramasubramanian Ph.D. Student Vijay Vittal John Undrill Arizona State University

Premise and assumptions Voltage source representation of the converter used All conventional generating units (2592 units) replaced by converter model of appropriate MVA rating Active power droop enabled on CIG when present on replaced conventional generating unit. Same value of droop coefficient used P max of converter assumed to be P max of turbine of replaced conventional generating unit 5% reactive power droop enabled on all CIG Terminal voltage control enabled on all CIG 2

Voltage source representation of the converter E d = V td0 + i d R f i q X f E q = V tq0 + i q R f + i d X f (1) 3

Voltage source representation of the converter R f and X f represent the resistance and reactance of the converter coupling filter and/or generation step up transformer between the converter and point of connection to the grid They have a value of 0.004pu and 0.05pu on a converter MVA base A steady state PWM amplitude modulation ratio (m) of 0.6 has been assumed. V T is the amplitude of the triangular carrier wave for generating the switching pulses 4

Control model Reactive power controller Active power controller 5

Features of control model Change in electrical frequency (Δω) calculated by rate of change of bus voltage angle Value of Q max adjusted according to change in terminal voltage while value of P max adjusted accordingly to maintain MVA of the converter Hard current trip at I max = 1.7pu Overvoltage trip if terminal voltage rises 0.15pu above the steady state voltage for more than 0.1s All time constants have a value of 0.01s except T frq which has a default software established value of 0.05s 6

System studied Simulation run on the WECC 2012 system: Number of buses: 18205 Number of conventional generating units: 2592 Number of induction motor loads: 5380 Around 90% of total load is voltage dependent. 7

Simulation results Five generating units across the system observed Plant E Five key buses identified across to system to observe the voltage Bus 2 Bus 1 Bus 5 Plant D Plant F The interaction between the northern and southern regions of the system studied Controller gains used: Bus 3 K p = 1.0, K i = 5.0 Generating units Key Buses Plant C Bus 4 Plant B Plant A K ip = 10.0, K iq = 10.0 K ip = 10.0, K iq = 120 (only for Plant A units) Simulations carried out in GE- PSLF 8

Generation outage Two of the three units at Plant A in Arizona tripped at t=15s. Loss of 2755 MW of generation 9

The frequency is calculated as rate of change of voltage phase angle 10

Analysis of results Arizona exports close to 4000 MW of power to California Large electrical separation between northern and southern regions of WECC 2755 MW generation outage causes phase angles to move away from each other in the first 0.5s after disturbance System separation prevented by increased inflow of power, due to droop control, from Northwest area to central northern California 11

Voltage at the key buses shows that as phase separation increases, the voltage at around the center of the north-south interface (Bus 3), decreases. 12

Total pre-disturbance active power generation is 172670 MW Total post-disturbance active power generation is 172300 MW 86.5% of the lost generation (due to trip of two Plant A units) is recovered through droop control Remaining 13.5% of the lost generation is recovered through voltage dependent loads 13

Third unit at Plant A is electrically closest to the outage Converter response to the outage is quick Converter current is within limits Voltage control loop brings the voltage back to the pre-disturbance value Very little reserve margin available as Plant A units operate close to their maximum active power limit 14

Effect of R p on generation outage With the trip of the two Plant A units, the system behavior with active power droop coefficient as 2R p and R p /2 has been observed Individual CIG units would still have different values of droop The droop coefficient in the previous study was considered to be R p 15

Active power droop coefficient was 2R p in this scenario. 16

Active power droop coefficient was R p /2 in this scenario. 17

Change in active power droop coefficient changes the settling time and final steady state value. Large value of droop coefficient corresponds to smaller proportional gain in the active loop and thus results in a longer settling time with greater oscillatory behavior. Simulation Metrics: With droop coefficient R p, a 40 second simulation run took 8.10 minutes with the first 20 seconds of simulation taking 3.52 minutes. Simulation time step: 0.0041s Computer specifications: i7 processor, 16.0 gb of RAM. 18

DC voltage dip and subsequent recovery Assumption of a battery as a constant source of power for all units is not realistic Disturbance in the network would cause dc capacitor voltage to vary Magnitude of ac voltage produced by converter generally falls in proportion to its dc voltage Two units of Plant A tripped followed by a 10% reduction in dc voltage 0.02s later dc voltage gradually restored over the next 10s dc voltage reduced only in Arizona and Southern California 19

Drop in dc voltage does not increase the phase separation between the two areas. 20

The transient decrease in bus voltage is however greater when compared to the transient decrease with constant dc voltage 21

Analysis of results The dc voltage was reduced only in the southern region of the system Reduction in terminal voltage along with loss of generation, increases power flow along northsouth interfaced Increased power flow causes the voltage at the center to decrease With predominant voltage dependent load, continuous change in dc voltage (over a period of 10s after disturbance) causes load to continuously change and thus more pronounced oscillatory behavior 22

Line fault followed by outage Three phase fault applied at midpoint of a line between Arizona and Southern California areas Fault cleared and line tripped in 0.05s Initial flow of power on the line: 1408.6 MW and 134.4 MVAR from the Arizona side Active power generation in both areas and behavior of one unit of Plant A observed 23

Arizona active power generation Southern California active power generation 24

Terminal voltage of one unit of Plant A Current of one unit of Plant A 25

Line closure Closure of a transmission line should not cause excessive current and voltage transients Power flow solved with major line open resulting in angle difference of 40.23 between the buses to which the line was connected The line was closed during simulation 26

Current of a CIG unit located near the line Current of a CIG unit located one bus away 27

Conclusion An all CIG WECC system, if required, is viable The system operates in a stable manner for various contingencies Long proven principle of droop relationships works Important to consider the source behind the dc bus and incorporate its model into positive sequence simulations A coordinated well designed wide area control structure may also be required 28