Response of Grid Interconnected Solar PV inverters to Transmission System Faults
|
|
- Mervyn Manning
- 6 years ago
- Views:
Transcription
1 Response of Grid Interconnected Solar PV inverters to Transmission System Faults David Piper, P.E. Operations Planning & Analysis SCE Grid Control Center July 18,
2 OVERVIEW 1. Overview of the event that raised awareness of fault induced loss of PV generation 2. Overview of Subsequent Events 3. Identified Causes: 1. Frequency Miscalculation 2. Momentary Cessation 4. Review of PV Models 5. Simulation 6. Key Findings 2
3 FAULT INDUCED LOSS OF PV GENERATION In August 2016 the Blue Cut Fire caused twelve faults on the South of Lugo 500 kv corridor Four of these faults resulted in an unexpected reduction in PV generation throughout the SCE system The most severe fault resulted in the temporary loss of approximately 1,178 MW of transmission connected PV NERC/WECC created a joint task force to determine the root cause
4 OVERVIEW Since August 2016, a total of twelve transmission faults have resulted in a temporary loss of generation from PV resources 1400 Reduction in PV Output Per Event PV Resource Loss (MW) Event # All faults cleared normally, within 4 cycles. Inverters typically resumed normal operation within 5-7 minutes. 4
5 MEASURED FREQUENCY DURING 1178 MW EVENT SCE s PMU system indicated that frequency remained above Hz Hz Hz 5
6 Total Solar Output (MW) IDENTIFIED CAUSE #1: INVERTER MISCALCULATION OF FREQUENCY The task force discovered that inverters from one manufacturer can miscalculate frequency during transmission faults. Many of these inverters calculated frequency below 57 Hz or above 61.7 Hz These inverters tripped due to over/under frequency protection and remained offline for 5-7 minutes 8/16/ :45 Event Time (HH:MM) As of July, 2017 these inverters make up 34% of PV inverters connected to SCE s transmission system 6
7 MITIGATION OF FREQUENCY TRIPPING The manufacturer developed revised inverter protection settings. These revisions include a definite time delay to the frequency trip set points. Low frequency trip setting: seconds High frequency trip setting: seconds Reduce the total restoration time to 150 seconds if a trip does occur. 68 NERC High Frequency Limit 66 NERC Low Frequency Limit 64 Manufacturer High Frequency Setting Frequency (Hz) No Trip Zone Manufacturer Low Frequency Setting Trip Time (s) 7
8 IDENTIFIED CAUSE #2 MOMENTARY CESSATION DUE TO VOLTAGE SAG Most commercial inverters are designed to momentarily cease the production of electric power if voltage exceeds the normal operating voltage range of 0.9 pu to 1.1 pu. After voltage returns within the operating range, these inverters will start increasing output in a ramped manner. The inverter s ramp rate limiter is set during commissioning and is usually configurable. Typical values range from 134% per second to 10% per minute. SCADA systems can mask this behavior because the full recovery (or some portion of it) can occur faster than one sampling interval 8
9 MOMENTARY CESSATION EXAMPLE Diagram shows the real and reactive power output of the plant, as measured by the digital fault recorder at the point of interconnection. Most inverters shut down and remained offline for approximately 750 ms The inverters resumed normal output approximately 1.5 seconds after the fault cleared
10 REVIEW OF PV DYNAMIC MODELS
11 REGC_A MODEL REVIEW lvpl1: LVPL* breakpoint Maximum pu output at LVPL breakpoint e.g pu 0.9 pu voltage (brkpt) brkpt: LVPL characteristic breakpoint voltage Voltage point that relates to lvpl1 Defines start of blocking characteristic zerox: LVPL characteristic zero crossing Voltage at which point inverters are completely blocked lvplsw: LVPL switch If lvplsw=1, then LVPL is enabled If lvplsw=0, then LVPL is disabled rrpwr: LVPL rate rate limit (pu) Defines ramp rate of return from momentary cessation *LVPL=Low Voltage Power Logic 11
12 REEC_A MODEL REVIEW Several flags determine the plant reactive power control mode 12
13 WT4G WIND TYPE 4 (FULL CONVERTER) Legacy model Should not be used for future interconnections Existing models should be replaced by 2 nd generation models 13
14 ANALYSIS OF MODELS IN WECC BASECASE Many PV plants are still modeled as WT4G Many PV plants have LVRT logic disabled Many PV plants are using default blocking voltages (zerox = 0.4 pu) Many PV plants are using default ramp rate limit values (rrpwr=10pu) 14
15 SIMULATION
16 SIMULATION Simulations were performed to evaluate the impact of momentary cessation. GE s PSLF software was used to simulate the worst case fault 3 phase, normally cleared 500 kv bus fault. Assumptions Load: Light spring Generation Mix: Maximum 2017 level of PV in the southwest United States California synchronous generation sources were minimized. Various ramp rate limit settings were evaluated to determine the impact that the recovery ramp rate has on system frequency.
17 Total Power (MW) SIMULATION RESULTS s 2s 4s 6s 8s 10s Frequency (Hz) Time (s) The worst-case fault caused the temporary shutdown of 5563 MW of PV generation. The ramp rate limiter has a significant impact on system frequency. 1s 2s 4s 6s 8s 10s
18 Simulation: PV Models: KEY FINDINGS Transmission system faults may cause widespread temporary shutdown and/or tripping of PV inverters. Some inverters have been identified to miscalculate frequency, a condition that is currently being fixed. Most other inverters have been identified to momentarily cease the production of electric power when voltage exceeds the normal operating voltage A high ramp rate limit after momentary cessation can help to reduce the impact of this lost generation on the system. DFR and PMU records can allow Power System Planners to compare models to real events Models can be evaluated to determine if reactive power control strategy and blocking characteristics accurately reflect reality. 18
19 Questions? 19
1200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report
1200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report Rich Bauer Associate Director Reliability Risk Management / Event Analysis Mid C Seminar July 19, 2017 Western Interconnection
More informationInverter-Based Resource Disturbance Analysis
Inverter-Based Resource Disturbance Analysis Key Findings and Recommendations Informational Webinar February 15, 2018 August 16, 2016 Blue Cut Fire Disturbance Key Findings and Recommendations 2 Western
More information900 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report
900 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report Southern California Event: October 9, 2017 Joint NERC and WECC Staff Report February 2018 NERC Report Title Report Date
More information1,200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report
1,200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report Southern California 8/16/2016 Event June 2017 NERC Report Title Report Date I Version 1.0 June 8, 2017 Version 1.1 June
More informationImplementation of Revised IEEE Standard 1547
MAY 31, 2017 HOLYOKE, MASSACHUSETTS Implementation of Revised IEEE Standard 1547 Presentation to ISO-TO Operations Committee David Forrest Key Points As New England adds significant amounts of Distributed
More informationLoss of Solar Resources during Transmission Disturbances due to Inverter Settings II
Loss of Solar Resources during Transmission Disturbances due to Inverter Settings II Informational Webinar on Level 2 NERC Alert Ryan Quint, Senior Manager, Advanced Analytics and Modeling Rich Bauer,
More informationPossible Future Modifications to IEEE 1547
California Rule 21 SWIG Possible Future Modifications to IEEE 1547 Michael Sheehan, P.E IREC mikes@irecusa.com PV Significant Trends Installed prices for distributed PV installations fell by at least 11
More informationIntegration of Wind Generation into Weak Grids
Integration of Wind Generation into Weak Grids Jason MacDowell GE Energy Consulting NERC ERSTF Atlanta, GA December 10-11, 2014 Outline Conventional and Power Electronic (PE) Sources Stability limitations
More informationBPS-Connected Inverter-Based Resource Performance
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Reliability Guideline BPS-Connected Inverter-Based Resource Performance May 2018 20 21 22 23 24 25 26 27 28 29 NERC Report Title Report Date I 30 31 32 33
More information( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy (X) Guideline ( ) Report or other ( ) Charter M&VWG. Web URL:
Document name Category Guideline Template Document date June 17, 2015 Adopted/approved by Date adopted/approved Custodian (entity responsible for maintenance and upkeep) Stored/filed Previous name/number
More informationModeling of GE Wind Turbine-Generators for Grid Studies
Modeling of GE Wind Turbine-Generators for Grid Studies Prepared by: Kara Clark Nicholas W. Miller Juan J. Sanchez-Gasca Version 4.5 April 16, 2010 General Electric International, Inc. One River Road Schenectady,
More informationEndorsed Assignments from ERS Framework
ERSTF Completion Endorsed Assignments from ERS Framework Ref Number Title ERS Recommendatio n Ongoing Responsibility 1 Synch Inertia at Interconnection Level Measure 2 Initial Frequency Deviation Measure
More informationGrid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017
Grid codes and wind farm interconnections CNY Engineering Expo Syracuse, NY November 13, 2017 Purposes of grid codes Grid codes are designed to ensure stable operating conditions and to coordinate the
More informationFault Induced Delayed Voltage Recovery (FIDVR) Advisory
Fault Induced Delayed Voltage Recovery (FIDVR) Advisory NERC Synchronized Measurement Subcommittee (SMS) NASPI Engineering Analysis Task Team (EATT) July 2015 Why the Advisory? The goal of this advisory
More informationPRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75
PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion
More informationTransmission Interconnection Requirements for Inverter-Based Generation
Transmission Requirements for Inverter-Based Generation June 25, 2018 Page 1 Overview: Every generator interconnecting to the transmission system must adhere to all applicable Federal and State jurisdictional
More informationWECC CMPLDW Phase 2 Study update. LMTF April 18 th, 2017 Atlanta, GA
WECC CMPLDW Phase 2 Study update LMTF April 18 th, 2017 Atlanta, GA Background CMPLDW load model phase 1 has been in approved WECC cases since 2013, it s the best available model to capture system oscillations,
More informationStandard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC
A. Introduction 1. Title: Generator Frequency and Voltage Protective Relay Settings 2. Number: PRC-024-2 3. Purpose: Ensure Generator Owners set their generator protective relays such that generating units
More informationHarmonizing the Changing Resource Mix Keeping the Grid Together
Harmonizing the Changing Resource Mix Keeping the Grid Together Robert W. Cummings Senior Director of Engineering and Reliability Initiatives i-pcgrid March 30, 2017 NERC-IEEE Memorandum of Understanding
More informationSynchrophasor Technology PMU Use Case Examples
1 IEEE Tutorial on Use of Synchrophasors in Grid Operations - Oscillation Source Detection and Operational Use of Synchrophasors Synchrophasor Technology PMU Use Case Examples Sarma (NDR) Nuthalapati,
More informationPRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76
PRC-025-1 Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive general discussion
More informationIEEE Major Revision of Interconnection Standard
IEEE 1547-2018 - Major Revision of Interconnection Standard NRECA & APA s Emerging Priorities in Energy Research Day, Anchorage, AK Charlie Vartanian PE Secretary, IEEE 1547 Working Group October 31, 2018
More informationSarma (NDR) Nuthalapati, PhD
SYNCHROPHASOR TECHNOLOGY PMU USE CASE EXAMPLES Sarma (NDR) Nuthalapati, PhD Research Scientist Texas A&M University, College Station, TX Control Room Solutions Task Team NASPI Work Group meeting and first
More information1
Guidelines and Technical Basis Introduction The document, Power Plant and Transmission System Protection Coordination, published by the NERC System Protection and Control Subcommittee (SPCS) provides extensive
More informationTechnical information SUNNY BOY 3.0-US / 3.8-US / 5.0-US / 6.0-US / 7.0-US / 7.7-US
Technical information SUNNY BOY 3.0-US / 3.8-US / 5.0-US / 6.0-US / 7.0-US / 7.7-US Grid Support Utility Interactive Inverters ENGLISH SBxx-1XP-US-40-GridServices-TI-en-15 Version 1.5 Table of Contents
More informationTechnical information Grid Support Utility Interactive Inverters for Sunny Central-US and Sunny Central Storage-US
Technical information Grid Support Utility Interactive Inverters for Sunny Central-US and Sunny Central Storage-US ENGLISH SC-US-GridServices-TI-en-10 Version 1.0 Table of Contents SMA Solar Technology
More informationFinal ballot January BOT adoption February 2015
Standard PRC-024-21(X) Generator Frequency and Voltage Protective Relay Settings Standard Development Timeline This section is maintained by the drafting team during the development of the standard and
More informationStandard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction
A. Introduction 1. Title: Generator Frequency and Voltage Protective Relay Settings 2. Number: PRC-024-1 3. Purpose: Ensure Generator Owners set their generator protective relays such that generating units
More informationGeneration and Load Interconnection Standard
Generation and Load Interconnection Standard Rev. 0A DRAFT Name Signature Date Prepared: Approved: VP Acceptance APEGGA Permit to Practice P-08200 TABLE OF CONTENTS 1.0 INTRODUCTION...5 1.1 Purpose...5
More informationTechnical information SUNNY TRIPOWER CORE1-US
Technical information SUNNY TRIPOWER CORE1-US Grid Support Utility Interactive Inverters ENGLISH STP50-US-40-GridServices-TI-en-10 Version 1.0 Table of Contents SMA Solar Technology America LLC Table of
More informationReliability Guideline
Reliability Guideline Distributed Energy Resource Modeling September 2017 NERC Report Title Report Date I Table of Contents Preface... iii Preamble... iv Executive Summary...1 Chapter 1: DER Dynamic Load
More informationReliability Guideline
Reliability Guideline Distributed Energy Resource Modeling September 2017 DRAFT NERC Report Title Report Date I Table of Contents Preface... iii Preamble... iv Purpose...1 Chapter 1: DER Dynamic Load Modeling
More informationUse of Synchrophasors to Detect Control System and Circuit Breaker Reclosing Issues
Use of Synchrophasors to Detect Control System and Circuit Breaker Reclosing Issues Pramila Nirbhavane Senior Grid Operations Engineer September 26, 2017 Outline PMUs Locations in NYISO PMU Applications
More informationRevised IEEE 1547 Standard for Interconnecting Distributed Energy Resources with Electric Power Systems- National Grid Solar Program
1 Revised IEEE 1547 Standard for Interconnecting Distributed Energy Resources with Electric Power Systems- National Grid Solar Program Babak Enayati, PhD, PE Lead Engineer, National Grid Waltham, MA Email:
More informationWind Power Facility Technical Requirements CHANGE HISTORY
CHANGE HISTORY DATE VERSION DETAIL CHANGED BY November 15, 2004 Page 2 of 24 TABLE OF CONTENTS LIST OF TABLES...5 LIST OF FIGURES...5 1.0 INTRODUCTION...6 1.1 Purpose of the Wind Power Facility Technical
More informationOperationalizing Phasor Technology. Model Validation. Webinar. Ken Martin. March 4, Presented by. Page 0
Operationalizing Phasor Technology Model Validation Webinar March 4, 2014 Presented by Ken Martin Page 0 Model Use and Validation for Operations and Planning Compare System Performance with Model Prediction
More informationGeneration and Load Interconnection Standard
Generation and Load Interconnection Standard Rev. 0 DRAFT Name Signature Date Prepared: Approved: VP Acceptance APEGGA Permit to Practice P-08200 TABLE OF CONTENTS 1.0 INTRODUCTION...5 1.1 Purpose...5
More informationReliability Guideline: Generating Unit Operations During Complete Loss of Communications
1 1 1 1 1 1 1 1 0 1 0 1 0 1 Reliability Guideline: Generating Unit Operations During Complete Loss of Communications Preamble: It is in the public interest for the North American Electric Reliability Corporation
More informationSDG&E Transmission Synchrophasor Project Update
SDG&E Transmission Synchrophasor Project Update Joint Synchronized Information Subcommittee (JSIS) Meeting Tariq Rahman, May 22-25, 2017 2006 San Diego Gas & Electric Company. All copyright and trademark
More informationTexas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event
Texas Reliability Entity Event Analysis Event: May 8, 2011 Loss of Multiple Elements Category 1a Event Texas Reliability Entity July 2011 Page 1 of 10 Table of Contents Executive Summary... 3 I. Event
More informationReliability Guideline: Generating Unit Operations During Complete Loss of Communications
1 1 1 1 1 1 1 1 0 1 0 1 0 1 Reliability Guideline: Generating Unit Operations During Complete Loss of Communications Preamble It is in the public interest for the North American Electric Reliability Corporation
More informationProtecting Feeders With Distributed Resource Scott Elling HDR Inc HDR, all rights reserved.
Protecting Feeders With Distributed Resource Scott Elling HDR Inc. 2015 HDR, all rights reserved. Background Several Hundred Mega Watts of distributed PV Distribution Grid is no longer radial Protection
More informationUse of the Power System Outlook (PSO) and SMART 1 Programs to View PSLF Dynamic Simulation Data Files
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2014 Grid of the Future Symposium Use of the Power System Outlook (PSO) and SMART 1 Programs to View PSLF Dynamic Simulation
More informationLessons Learned in Model Validation for NERC Compliance
Lessons Learned in Model Validation for NERC Compliance usa.siemens.com/digitalgrid NERC Modeling, Data, and Analysis MOD 025 2: Generator Real and Reactive Power Capability Demonstration MOD 026 1: Verification
More informationHighgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES
Highgate Converter Overview Prepared by Joshua Burroughs & Jeff Carrara IEEE PES Highgate Converter Abstract Introduction to HVDC Background on Highgate Operation and Control schemes of Highgate 22 Why
More informationModeling of Distributed Generation under Next Generation Interconnection Requirements. Anna Edwards. A thesis. Submitted in partial fulfillment of the
Modeling of Distributed Generation under Next Generation Interconnection Requirements Anna Edwards A thesis Submitted in partial fulfillment of the requirements for the degree of: Master of Science in
More informationInverter Source Requirement Document of ISO New England (ISO-NE)
Inverter Source Requirement Document of ISO New England (ISO-NE) This Source Requirement Document applies to inverters associated with specific types of generation for projects that have applied for interconnection
More informationTesting model data usability Excitation Systems PSS Limiters
1 2016 IEEE/PES General Meeting July 17 th -21 st, 2016 Boston, MA Panel Session Use of the New Revisions of IEEE Std. 421.2 and 421.5 to Satisfy International Grid Code Requirements Testing model data
More informationISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements
Division 502 Technical Applicability 1(1) Section 502.1 applies to: Expedited Filing Draft August 22, 2017 the legal owner of an aggregated generating facility directly connected to the transmission system
More informationDER_A Benchmark Update
DER_A Benchmark Update Deepak Ramasubramanian, EPRI Anish Gaikwad, EPRI Pouyan Pourbeik, PEACE NERC LMTF October 31 st 2017 Austin, TX DISCLAIMER The DER_A model is still a beta model under test and development
More informationFault Ride Through Technical Assessment Report Template
Fault Ride Through Technical Assessment Report Template Notes: 1. This template is intended to provide guidelines into the minimum content and scope of the technical studies required to demonstrate compliance
More informationISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements
Applicability 1(1) Section 502.1 applies to the ISO, and subject to the provisions of subsections 1(2), (3) and (4) to any: (a) a new wind aggregated generating facility to be connected to the transmission
More informationLessons Learned in Model Validation for NERC Compliance
Lessons Learned in Model Validation for NERC Compliance usa.siemens.com/digitalgrid NERC Modeling, Data, and Analysis MOD 025 2: Generator Real and Reactive Power Capability Demonstration MOD 026 1: Verification
More informationJonathan (Xiangmin) Gao - GE Grid Solutions Douglas Rust - Dandsco LLC Presented by: Tom Ernst GE Grid Solutions
Jonathan (Xiangmin) Gao - GE Grid Solutions Douglas Rust - Dandsco LLC Presented by: Tom Ernst GE Grid Solutions PRC-001: System protection coordination PRC-019: Coordination with voltage regulating control
More informationArizona Public Service Company and the Transmission Partnership for National Electric Power Company of Jordan
Arizona Public Service Company and the Transmission Partnership for National Electric Power Company of Jordan Mark Hackney October 5-8, 2009 Amman, Jordan Energy Control Center Layout 2 Energy Control
More informationIDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)
IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: IDAHO POWER COMPANY Designated Contact Person: Jeremiah Creason Address: 1221 W. Idaho Street, Boise ID 83702 Telephone
More informationWide-Area Measurements to Improve System Models and System Operation
Wide-Area Measurements to Improve System Models and System Operation G. Zweigle, R. Moxley, B. Flerchinger, and J. Needs Schweitzer Engineering Laboratories, Inc. Presented at the 11th International Conference
More informationPost-Event Analysis of a Compound Event in the ERCOT System Using Synchrophasor Data
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2014 Grid of the Future Symposium Post-Event Analysis of a Compound Event in the ERCOT System Using Synchrophasor Data
More informationITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/
ITC Holdings Planning Criteria Below 100 kv * Category: Planning Type: Policy Eff. Date/Rev. # 12/09/2015 000 Contents 1. Goal... 2 2. Steady State Voltage & Thermal Loading Criteria... 2 2.1. System Loading...
More informationReal Time Stability Analysis at Peak Reliability. Slaven Kincic, Hongming Zhang JSIS May 2017, SLC
Real Time Stability Analysis at Peak Reliability Slaven Kincic, Hongming Zhang JSIS May 2017, SLC Overview: Overview of Peak s DSA Application; o Set up o User Cases Transient Stability Criteria; TSAT
More informationRenewable Interconnection Standard & Experimental Tests. Yahia Baghzouz UNLV Las Vegas, NV, USA
Renewable Interconnection Standard & Experimental Tests Yahia Baghzouz UNLV Las Vegas, NV, USA Overview IEEE Std 1547 Voltage limitations Frequency limitations Harmonic limitations Expansion of IEEE Std
More informationShort Circuit Modeling for Inverter-Based Resources
Short Circuit Modeling for Inverter-Based Resources Evangelos Farantatos Sr. Technical Leader Transmission Operations & Planning NERC Power Plant Modeling & Verification Task Force (PPMVTF) November 6
More informationIEEE sion/1547revision_index.html
IEEE 1547 IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces http://grouper.ieee.org/groups/scc21/1547_revi sion/1547revision_index.html
More informationSynchrophasors and the Smarter Grid
Synchrophasors and the Smarter Grid Synchrophasor A synchrophasor is a phasor measurement with respect to an absolute time reference. With this measurement we can determine the absolute phase relationship
More informationRENEWABLE ENERGY SUB-CODE for Distribution Network connected Variable Renewable Energy Power Plants in Ghana
RENEWABLE ENERGY SUB-CODE for Distribution Network connected Variable Renewable Energy Power Plants in Ghana JANUARY 2015 i Table of Content PART A: 1 1 Introduction 1 1.1 Scope 1 1.2 Status 1 1.3 Terms
More informationHARDWARE BASED CHARACTERISATION OF LV INVERTER FAULT RESPONSE
HARDWARE BASED CHARACTERISATION OF LV INVERTER FAULT RESPONSE Ibrahim ABDULHADI Federico COFFELE Power Networks Demonstration Centre - UK ibrahim.f.abdulhadi@strath.ac.uk federico.coffele@strath.ac.uk
More informationPRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1
PRC-025-1 Generator Relay Loadability A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1 Purpose: To set load-responsive protective relays associated with generation Facilities
More informationSYNCHROPHASOR TECHNOLOGY GLOSSARY Revision Date: April 24, 2011
SYNCHROPHASOR TECHNOLOGY GLOSSARY Revision Date: April 24, 2011 Baselining using large quantities of historical phasor data to identify and understand patterns in interconnection-wide grid behavior, to
More informationVOLTAGE STABILITY OF THE NORDIC TEST SYSTEM
1 VOLTAGE STABILITY OF THE NORDIC TEST SYSTEM Thierry Van Cutsem Department of Electrical and Computer Engineering University of Liège, Belgium Modified version of a presentation at the IEEE PES General
More informationFacilitating Bulk Wind Power Integration Using LCC HVDC
21, rue d Artois, F-758 PARIS CIGRE US National Committee http : //www.cigre.org 213 Grid of the Future Symposium Facilitating Bulk Wind Power Integration Using LCC HVDC A. HERNANDEZ * R.MAJUMDER W. GALLI
More informationVoltage Stability Assessment at the EMS
Voltage Stability Assessment at the EMS Jay Giri i-pcgrid San Francisco, March 26 th, 2013 GRID EMS Overview DSA Integration Load Load (area) meas. Forecast SCADA AGC Division Load & Loss Status & Analog
More informationWFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS
WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS WFPS1.1 INTRODUCTION 2 WFPS1.2 OBJECTIVE 2 WFPS1.3 SCOPE 3 WFPS1.4 FAULT RIDE THROUGH REQUIREMENTS 4 WFPS1.5 FREQUENCY REQUIREMENTS 5 WFPS1.6 VOLTAGE
More informationConext CL125 Inverter - Active and Reactive Power Control and LVRT/HVRT
Conext CL125 Inverter - Active and Reactive Power Control and LVRT/HVRT http://solar.schneider-electric.com 976-0406-01-01/A May 2018 Application Note EXCLUSION FOR DOCUMENTATION UNLESS SPECIFICALLY AGREED
More informationLow Frequency Demand Disconnection Summary
Low Frequency Demand Disconnection Summary This article assesses the suitability of current low frequency protection on the network as more distributed generation is connected to WPD s network. DSOF June
More informationAmeren Illinois Company d/b/a Ameren Illinois Smart Inverter Specifications
1. SCOPE OF WORK 1.1 Purpose This document is formulated to provide guidance to SMART inverter installers in Illinois. The document provides the minimum specification for inverters that interconnect with
More informationIEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces
IEEE PES Boston Chapter Technical Meeting IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces P1547 Chair David
More informationDER Ride-Through Performance Categories and Trip Settings Presentation at PJM Ride-Through Workshop, Philadelphia, PA, October 1-2, 2018
DER Ride-Through Performance Categories and Trip Settings Presentation at PJM Ride-Through Workshop, Philadelphia, PA, October 1-2, 2018 Dr. Jens C. Boemer, Principal Technical Leader, EPRI Reigh Walling,
More informationHow Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements
How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements Robert Nelson Senior Expert Engineering Manager and Manager of Codes, Standards, and Regulations Siemens Wind Turbines -
More informationGenerator Parameter Validation (GPV)
Generator Parameter Validation (GPV) NASPI Engineering Analysis Task Team Burlingame, CA March 23, 2015 Kevin Chen, Neeraj Nayak and Wayne Schmus of EPG Ryan D. Quint of Dominion Virginia Power Outline
More informationINTERIM ARRANGEMENTS FOR GRID TIED DISTRIBUTED ENERGY RESOURCES. Technical Requirements for Grid-Tied DERs
INTERIM ARRANGEMENTS FOR GRID TIED DISTRIBUTED ENERGY RESOURCES Technical Requirements for Grid-Tied DERs Projects Division 6/29/2017 Contents 1 Definitions and Acronyms... 1 2 Technical Interconnection
More informationBED INTERCONNECTION TECHNICAL REQUIREMENTS
BED INTERCONNECTION TECHNICAL REQUIREMENTS By Enis Šehović, P.E. 2/11/2016 Revised 5/19/2016 A. TABLE OF CONTENTS B. Interconnection Processes... 2 1. Vermont Public Service Board (PSB) Rule 5.500... 2
More informationStandard MOD Verification of Models and Data for Generator Excitation Control System or Plant Volt/Var Control Functions
Standard MOD-026-1 Verification of Models and Data for Generator Excitation Control System or Plant Volt/Var Control Functions A. Introduction 1. Title: Verification of Models and Data for Generator Excitation
More informationModel Verification Examples
UWIG/EnerNex DOE Wind Turbine Documentation Project Model Verification Examples Juan J. Sanchez-Gasca GE Energy Jason MacDowell GE Energy Albany, NY July, 2011 Model Verification Tests 2 EMTP-type model
More informationARC FLASH PPE GUIDELINES FOR INDUSTRIAL POWER SYSTEMS
The Electrical Power Engineers Qual-Tech Engineers, Inc. 201 Johnson Road Building #1 Suite 203 Houston, PA 15342-1300 Phone 724-873-9275 Fax 724-873-8910 www.qualtecheng.com ARC FLASH PPE GUIDELINES FOR
More information( ) usable, minor formatting/editing required ( ) modification needed ( ) superseded by ( ) other ( ) obsolete/archived)
Document name Category Model Validation Report for May 16, 2014 RAS Event ( ) Regional Reliability Standard ( ) Regional Criteria ( ) Policy ( ) Guideline (X) Report or other ( ) Charter Document date
More informationIEEE Std Bulk System Opportunities from New Distributed Energy Resource Interconnection and Interoperability Standards
IEEE Std 1547-2018 Bulk System Opportunities from New Distributed Energy Resource Interconnection and Interoperability Standards Clayton Stice, ERCOT Jens C. Boemer, EPRI (on behalf of SCC21) NERC SPIDER
More informationOperationalizing Phasor Technology
ELECTRIC POWER GROUP WEBINAR SERIES Operationalizing Phasor Technology Operationalizing Phasor Technology System Events Deciphering the Heartbeat of the Power Grid July 16, 2013 Webinar John W. Ballance
More informationGeneration Interconnection Requirements at Voltages 34.5 kv and Below
Generation Interconnection Requirements at Voltages 34.5 kv and Below 2005 March GENERATION INTERCONNECTION REQUIREMENTS AT 34.5 KV AND BELOW PAGE 1 OF 36 TABLE OF CONTENTS 1. INTRODUCTION 5 1.1. Intent
More informationMinnesota Power Systems Conference 2015 Improving System Protection Reliability and Security
Minnesota Power Systems Conference 2015 Improving System Protection Reliability and Security Steve Turner Senior Application Engineer Beckwith Electric Company Introduction Summarize conclusions from NERC
More informationCOMPARATIVE PERFORMANCE OF SMART WIRES SMARTVALVE WITH EHV SERIES CAPACITOR: IMPLICATIONS FOR SUB-SYNCHRONOUS RESONANCE (SSR)
7 February 2018 RM Zavadil COMPARATIVE PERFORMANCE OF SMART WIRES SMARTVALVE WITH EHV SERIES CAPACITOR: IMPLICATIONS FOR SUB-SYNCHRONOUS RESONANCE (SSR) Brief Overview of Sub-Synchronous Resonance Series
More informationSynchroPhasor use at OG&E. Austin D. White P.E. Steven E. Chisholm Oklahoma Gas & Electric
SynchroPhasor use at OG&E Austin D. White P.E. Steven E. Chisholm Oklahoma Gas & Electric Outline Hardware/Software Overview Current Deployment Status Use at OG&E Problems Solved & Interesting Findings
More informationUnit Auxiliary Transformer Overcurrent Relay Loadability During a Transmission Depressed Voltage Condition
Unit Auxiliary Transformer Overcurrent Relay Loadability During a Transmission Depressed Voltage Condition NERC System Protection and Control Subcommittee March 2016 NERC Report Title Report Date I Table
More informationProtective Relaying for DER
Protective Relaying for DER Rogerio Scharlach Schweitzer Engineering Laboratories, Inc. Basking Ridge, NJ Overview IEEE 1547 general requirements to be met at point of common coupling (PCC) Distributed
More informationMicro-synchrophasors (µpmus) in Electric Power Distribution Systems 5/29/15 SF PES Chapter Workshop
Micro-synchrophasors (µpmus) in Electric Power Distribution Systems 5/29/15 SF PES Chapter Workshop Dr. Alexandra (Sascha) von Meier Co-Director, Electric Grid Research, California Institute for Energy
More informationAnalysis of Effect on Transient Stability of Interconnected Power System by Introduction of HVDC Link.
Analysis of Effect on Transient Stability of Interconnected Power System by Introduction of HVDC Link. Mr.S.B.Dandawate*, Mrs.S.L.Shaikh** *,**(Department of Electrical Engineering, Walchand College of
More informationForward Looking Frequency Trends Technical Brief ERS Framework 1 Measures 1, 2, and 4: Forward Looking Frequency Analysis
Forward Looking Frequency Trends Technical Brief ERS Framework 1 Measures 1, 2, and 4: Forward Looking Frequency Analysis The NERC Planning Committee and Operating Committee jointly created the Essential
More informationPRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1
A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1 Purpose: To set load-responsive protective relays associated with generation Facilities at a level to prevent unnecessary tripping
More informationPSSE PV INVERTER AND POWER PLANT CONTROLLER MODELS
PSSE PV INVERTER AND POWER PLANT CONTROLLER MODELS BASED ON GEPV MODELS PowerElectronics Revision Table Version Date Author Revised by Approved by 3.0 Nov 2015 Antonio Jiménez PAGE 1 of 39 Revision History
More informationTesting Advanced Photovoltaic Inverters Conforming to IEEE Standard 1547 Amendment 1
> REPLACE THIS LINE WITH YOUR PAPER IDENTIFICATION NUMBER (DOUBLE-CLICK HERE TO EDIT) < Testing Advanced Photovoltaic Inverters Conforming to IEEE Standard 547 Amendment Anderson Hoke, Student Member,
More informationImpact of High PV Penetration on Grid Operation. Yahia Baghzouz Professor of Electrical engineering University of Nevada Las Vegas
Impact of High PV Penetration on Grid Operation Yahia Baghzouz Professor of Electrical engineering University of Nevada Las Vegas Overview Introduction/Background Effects of High PV Penetration on Distribution
More information