Lessons Learned in Model Validation for NERC Compliance

Similar documents
Lessons Learned in Model Validation for NERC Compliance

Unit Auxiliary Transformer (UAT) Relay Loadability Report

Operationalizing Phasor Technology. Model Validation. Webinar. Ken Martin. March 4, Presented by. Page 0

Generator Parameter Validation (GPV)

Robert W. Cummings - NERC Director of System Analysis and Reliability Initiatives William Herbsleb - Chairman of Frequency Response Standard Drafting

Harmonizing the Changing Resource Mix Keeping the Grid Together

VOLTAGE STABILITY OF THE NORDIC TEST SYSTEM

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting

Reliability Considerations for PPMV. Ryan Quint, NERC Dmitry Kosterev, BPA NASPI-NERC PPMV Tools Workshop October 2016

Energy-Based Damping Evaluation for Exciter Control in Power Systems

Uses of Synchrophasor BD NSF Workshop 2017

Endorsed Assignments from ERS Framework

Demonstration of PFR Improvement September ERCOT Operations Planning

Indication of Dynamic Model Validation Process

Frequency Response Initiative Industry Advisory Generator Governor Frequency Response

Industry Webinar. Reactive Power Planning. NERC System Analysis and Modeling Subcommittee (SAMS) March 2017

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

Synchrophasor Technology PMU Use Case Examples

Reliability Guideline

generation greater than 75 MVA (gross aggregate nameplate rating) Generation in the ERCOT Interconnection with the following characteristics:

Testing model data usability Excitation Systems PSS Limiters

Sarma (NDR) Nuthalapati, PhD

Generation Interconnection Study Data Sheet Synchronous Machines

INTERCONNECTION REQUEST FOR A LARGE GENERATING FACILITY

Real Time Stability Analysis at Peak Reliability. Slaven Kincic, Hongming Zhang JSIS May 2017, SLC

NARUC. Summer Committee Meetings. Staff Subcommittees on Electricity & Electric Reliability

APPENDIX 1 to LGIP INTERCONNECTION REQUEST FOR A LARGE GENERATING FACILITY

Forward Looking Frequency Trends Technical Brief ERS Framework 1 Measures 1, 2, and 4: Forward Looking Frequency Analysis

Analysis of Effect on Transient Stability of Interconnected Power System by Introduction of HVDC Link.

Operational Modeling and Model Inputs

How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications

Setting and Verification of Generation Protection to Meet NERC Reliability Standards

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

SDG&E Transmission Synchrophasor Project Update

Grid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017

Jonathan (Xiangmin) Gao - GE Grid Solutions Douglas Rust - Dandsco LLC Presented by: Tom Ernst GE Grid Solutions

Generation and Load Interconnection Standard

Transmission Interconnection Requirements for Inverter-Based Generation

Integration of Variable Renewable Energy

NERC / TVA STABILITY WORKSHOP

Wide-Area Monitoring and Control of Power Systems using Real-Time Hardware-in-the-Loop Simulations

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications

Wind Power Facility Technical Requirements CHANGE HISTORY

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction

Standard MOD Verification of Models and Data for Generator Excitation Control System or Plant Volt/Var Control Functions

Synchrophasor Technology at BPA: from Wide-Area Monitoring to Wide-Area Control

Imperial Irrigation District System Planning ATTACHMENT A

Generation and Load Interconnection Standard

Southern Company Interconnection Requirements for Inverter-Based Generation

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

Generator Voltage Protective Relay Settings

Interconnection-Wide Oscillation Analysis: Baselining Oscillation Modes in the North American Power System Objective Purpose

Wind Requirements and Testing for Steady-State Voltage and Frequency Control

Modeling of Three-phase or Bank of Three Single Phase Three Winding Transformers Zero-phase-sequence Leakage Impedance in PSS E Short Circuit Module

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC

Response of Grid Interconnected Solar PV inverters to Transmission System Faults

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

EXCITATION SYSTEM MODELS OF GENERATORS OF BALTI AND EESTI POWER PLANTS

Power Plant and Transmission System Protection Coordination

Integration of Wind Generation into Weak Grids

LARGE-SCALE WIND POWER INTEGRATION, VOLTAGE STABILITY LIMITS AND MODAL ANALYSIS

Power Plant and Transmission System Protection Coordination

Simulations of open phase conditions on the high voltage side of YNd05-power plant transformers

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

Study of Frequency Response in Power System with Renewable Generation and Energy Storage

Tertiary Winding Design in wye-wye Connected Transformers Restricted Siemens Energy 2013 All rights reserved.

WECC Data Preparation Manual

Standard MOD Verification of Models and Data for Generator Excitation Control Sys tem or Plant Volt/Var Control Functions

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event

A Fundamental Study of Applying Wind Turbines for Power System Frequency Control

Standard PRC Coordination of Generating Unit or Plant Voltage Regulating Controls with Generating Unit or Plant Capabilities and Protection

Synchrophasor Solutions Deployment at PG&E Off-Line Analysis

Excitation systems and automatic voltage regulators

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. July 2016 Version 4

Final ballot January BOT adoption February 2015

Power Plant and Transmission System Protection Coordination Fundamentals

Application Of Power System Stabilizer At Serir Power Plant

Post-Event Analysis of a Compound Event in the ERCOT System Using Synchrophasor Data

Overview of Synchrophasor Applications. Dmitry Kosterev Bonneville Power Administration

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. April 2009 Version 2

Use of the Power System Outlook (PSO) and SMART 1 Programs to View PSLF Dynamic Simulation Data Files

IEEE sion/1547revision_index.html

WECC Data Preparation Manual

An Introduction to Completing a NERC PRC-019 Study for Traditional and Distributed Generation Sources

Initial Application Form for Connection of Distributed Generation (>10kW)

GMD Voltage Collapse Study

Kestrel Power Engineering

DER_A Benchmark Update

Kestrel Power Engineering

FACILITY CONNECTION REQUIREMENTS

IJSER. Fig-1: Interconnection diagram in the vicinity of the RajWest power plant

Step-Response Tests of a Unit at Atatürk Hydro Power Plant and Investigation of the Simple Representation of Unit Control System

Deleted: 9 4 anuary ... [1] Deleted: much more. Formatted ... [2] Formatted Table. Formatted: Indent: Left: 0.06 cm

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1

Low Frequency Local mode Oscillations in NER Grid, Validation using Model based analysis and Mitigation

Deployment and Initial Experience with Oscillation Detection Application at Bonneville Power Administration

Power Plant and Transmission System Protection Coordination of-field (40) and Out-of. of-step Protection (78)

GOV/AVR Model Validation Process

Transcription:

Lessons Learned in Model Validation for NERC Compliance usa.siemens.com/digitalgrid

NERC Modeling, Data, and Analysis MOD 025 2: Generator Real and Reactive Power Capability Demonstration MOD 026 1: Verification of Models for Generator Excitation Control Systems MOD 027 1: Verification of Models for Turbine/Governor and Load Control Functions, including validation of turbine droop and determination of governor s deadband MOD-033-1: Steady-State and Dynamic Power System Model Validation Page 2

Unit Size for NERC Model Validation Requirement (MVA) ERCOT Eastern Interconnection WECC Individual Unit Plant Individual Unit Plant Individual Unit Plant MOD-25-2 >20 >75 >20 >75 >20 >75 MOD-26-1 >50 >75 >100 >100 >75 >75 MOD-27-1 >50 >75 >100 >100 >75 >75 Page 3

Siemens PTI Services Onsite technical assistance for performing the tests Field tests data processing Model validation (PSS E/PSLF) Verification of generator OC excitation curve and generating unit inertia constant Adjustment of controllers parameters AVR and PSS tuning Over- and Under-excitation limiter adjustment V/Hz limiter adjustment Development of user-written models Page 4

MOD-025-2 Generator Tests Estimated and Operating capability curve (D-curve) Page 5

MOD-025-2 Generator Tests Measurements: Active & reactive power, voltage at unit terminals (point A) Active & reactive power, voltage at the high voltage side of the GSU (point F) Active & reactive power through the high voltage side of the auxiliary transformer (point B) Voltage at the low voltage side of the tertiary winding (point C) Active and reactive power at the high voltage side of the GSU of the other units (point D) Page 6

MOD-026-1 Generator Excitation Control System Model Verification Open-circuit dynamic response calibration Interconnected dynamic performance calibration Validate model parameters by comparing field test records against current PSS E or PSLF dynamic models Page 7

MOD-026-1 Generator Excitation Control System Model Verification Open-circuit dynamic response calibration Interconnected dynamic performance calibration Validate model parameters by comparing field test records against current PSS E or PSLF dynamic models Page 8

MOD-027-1 Turbine/Governor and Load Control Functions Model Verification Validation of the speed governor response for an on-line perturbation test with synthetic speed signal of ±0.2Hz Page 9

Governor Modeling Improvements for Stability and Frequency Response Studies MISO Experience usa.siemens.com/digitalgrid

Result of NERC MOD-033 System Model Validation performed by MISO MISO uses the Eastern Interconnect Wide Model for Transient Stability Analysis. These models predicts system frequency response settling at a higher value. This difference between the simulated and the PMU recording is due to lack of deadband in the governor model. This modeling issue has been a known for a long time. Frequency in Hz 60.0200 60.0000 59.9800 59.9600 59.9400 59.9200 59.9000 Frequency nadir differs 59.8800 59.8600 Gen trip simulated at 0.5 sec Settling frequency is optimistic. Frequency with Current Models PMU Synchrophasor data Frequency comparison on 345 kv Bus near the generator 0.00 0.28 0.55 0.83 1.09 1.37 1.64 1.92 2.19 2.47 2.74 3.02 3.29 3.57 3.84 4.12 4.39 4.67 4.94 5.22 5.49 5.77 6.04 6.32 6.59 6.87 7.14 7.42 7.69 7.97 8.24 8.52 8.79 9.07 9.34 9.62 9.89 10.17 10.44 10.72 10.99 11.27 11.54 11.82 12.09 12.37 12.65 12.92 13.20 13.47 13.75 14.02 14.30 14.57 14.85 15.12 15 40 TIme in sec Page 11

Governor Dadband Modeling Improvement 14 governor models with deadband blocks were released in PSS E versions 33.10 and 34.2 MISO did extensive testing of these new models on the Eastern Interconnection with very encouraging results IEEEG1* asymmetrical dead-band IEEEG1SDU* Page 12

MISO Test Results of 2020 Summer Dynamic case with New Governor Models, compared to Real Time Data 60.010 60.000 59.990 Green trace represents base case with current governor models. Incorrect model prediction. 59.980 59.970 Hz 59.960 59.950 PMU : Frequency at 345 kv Bus near Fermi Generating Plant Unit Frequency, New Governor Type, 2020SUM Frequency, Base Model, 2020SUM 59.940 59.930 59.920 Settling frequency in simulation (red trace) closer to Real time data (purple trace), which is critical for any frequency related studies. Note :Some difference expected as case represents an out year scenario, not the actual system condition pre-event. 0.0 0.4 0.7 1.1 1.4 1.8 2.2 2.5 2.9 3.2 3.6 4.0 4.3 4.7 5.0 5.4 5.8 6.1 6.5 6.9 7.2 7.6 7.9 8.3 8.7 9.0 9.4 9.8 10.1 10.5 10.8 11.2 11.6 11.9 12.3 12.7 13.0 13.4 13.7 14.1 14.5 14.8 15.2 15.6 15.9 16.3 16.6 17.0 17.4 17.7 18.1 18.5 18.8 19.2 19.6 19.9 seconds Page 13 *MISO Dynamics model Wind at 15.6% of Pmax in MISO

Power Plant Model Validation using PSS E Playback Model usa.siemens.com/digitalgrid

PSS E Playback Model PLBVFU1 Overview The PLBVFU1 model plays back a known set of voltage and frequency signals The PLBVFU1 model acts as a generator model (with no excitation system or turbine-governor models) The played-in voltage and frequency signals must be included in a data input file Page 15

PSS E Playback Model Playback Model for Voltage Signal Page 16

PSS E Playback Model Playback Model for Frequency Signal Page 17

PSS E Playback Model Playback Model Example Test System Unit to be tested Playback generator Page 18

PSS E Playback Model Playback Model PMU data vs. PSS E simulation results Page 19

Contact Us Carlos Grande-Moran Principal Consultant Siemens Power Technologies International E-mail: carlos.grande@siemens.com Dinemayer Silva Staff Consultant Siemens Power Technologies International E-mail: dinemayer.silva@siemens.com usa.siemens.com/digitalgrid Page 20