ADDENDUM No. 4 Page 1 of 8 (includes attachment)

Similar documents
NIAGARA REGIONAL HOUSING MZE FILE NO

Notre Dame High Addition/Renovation Addendum 3 Page 1

ADDENDUM NO. TWO. To the Plans and Specifications for: PALM COAST READINESS CENTER PALM COAST, FL For FLORIDA DEPT. OF MILITARY AFFAIRS

INVITATION TO TENDER ITT No. PS FIRE HALL 5 + HOUSING CONSTRUCTION. ADDENDUM No. 2 and AMENDMENT No. 2

KidsAbility Guelph Hub Renovation ADDENDUM #2 Project No.:

MPA Project No. M495-C1 Refrigerated Container Storage Improvements Project Location: Conley Terminal, Boston, MA

RENOVATION OF THE FARMERS MARKET Reference Number:

HIA AIR CARGO HAMILTON ADDENDUM #3. Addendum No. A03 (Architectural) o Text 1 page o SK-10a o SK-10b o SK-11

ADDENDUM NOTICE INTERIOR RENOVATIONS AT THE BATHURST CLARK RESOURCE LIBRARY, 900 CLARK AVENUE WEST, VAUGHAN, ON

Addendum. Windsor Hall Renovations Date: October 12, 2017 Addendum No: 3 GENERAL. 1! Addendum #4 will be issued 2:00 PM Tuesday October 17, 2017.

Attached is Addendum No. 2 to SEPTA Sealed Bid APES, Install DC Stinger Distribution System - SEPTA Fern Rock Car House.

MPA Project No. M495-C1 Refrigerated Container Storage Improvements Project Location: Conley Terminal, Boston, MA

MTJ Outdoor Baggage Claim

BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX: BID PACKAGE D

Answer: Only to ChurchWoods, LLC.

ADDENDUM #1. April 29, 2009

COUNTY OF NORTHUMBERLAND Addendum No. 3 Request for Quotations To Renovate the Grafton Recreation Centre for a Licensed Child Care Centre

ADDENDUM #01. PROJECT: Saint Mary s University Student Centre Reorganization PROJECT N o : DATE:

December 31, 2015 A. THE BID OPENING DATE IS UNCHANGED. B. Questions, Additions, and Deletions

Addendum No. 3 Tender Call No Revised Closing: 12:00 NOON (LOCAL TIME), April 24, 2017

1. Attached is a copy of addendum #4 issued by Diamond Schmitt Architects, dated

PROCUREMENT SERVICES th St, SW Calgary, AB T2R 0L4 Telephone: (403) Fax: (403)

Marshall Truck Station Laboratory Addition Project No. TZ MnDOT

Specifications: Other: sign in sheet

ADDENDUM NO. 02 July 31, 2012

The following items are updated to reflect revisions and are hereby incorporated into the Inquiry Documents, Inquiry No. 17-WDI-031.

ADDENDA ADDENDUM NO. 1 DATE: MARCH 1, 2016

B. Bidders shall acknowledge receipt of this Addendum in writing on his Proposal Form.

The following information supplements and/or supersedes the bid documents issued on July 10, 2017.

HAYES VALLEY PLAYGROUND AND CLUBHOUSE PROJECT NO.: SAN FRANCISCO PARKS AND RECREATIONS SAN FRANCISCO, CA

ADDENDUM NO. 4 TO THE CONTRACT DOCUMENTS SUPPLEMENTAL INFORMATION

ADDENDUM NO. 2. Germania Club Renovation Phase 2. Saginaw County Community Mental Health Authority WILLIAM A. KIBBE & ASSOCIATES, INC.

ARCHITECTS SUPPLEMENTAL INSTRUCTIONS (ASI)

PORT OF ST. HELENS SCAPPOOSE INDUSTRIAL AIRPARK PARALLEL TAXIWAY B RELOCATON AIP PROJECT ADDENDUM NO. 1

Chapter 25. Lighting Plans

Wayne State University. Prentis Building Renovation. NM Project Number: Niagara Murano 2215 Cole Street Birmingham, Michigan, 48009

Spec Section: , Complete Elec, Comm, and Fire Alarm , Complete Elec, Comm, and Fire Alarm Data Sheets RAN/GCAN

B. Manufacturers: Square-D, G.E. or Westinghosue.

Can you please issue the most recent Soils Report as prepared by Strata? Updated Soils Report to be posted to Christenson Corporation web site

Merrick Pet Care New Distribution Center Hereford, Texas

HOENER ASSOCIATES INC. ARCHITECTS

PLAN SUBMITTAL REQUIREMENTS

SECTION LOW-VOLTAGE ELECT. DIST. DESIGN AND CONSTRUCTION STANDARDS _ February 2015 PART I: GENERAL

FAB GSE Remodel ITB Solicitation #1538 Invitation to Bid (ITB) for General Contracting Services. ADDENDUM #4 December 5, 2014

Procurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202

CHABOT-LAS POSITAS COMMUNITY COLLEGE DISTRICT CHABOT COLLEGE CAMPUS MASTER SIGN PROGRAM, PHASE 2 BID NO

PROGRAMMING SCHEMATIC DESIGN DESIGN DEVELOPMENT CONSTRUCTION DOCUMENTS. room) Scalable bubble diagrams schedules describing programmatic

Single-Family Dwelling Submittal Requirements

Software Services, Section 16748, Add as an attachment to this section Attachment A enclosed with this addendum.

To the Drawings and/or Specifications for. Board of Education of Harford County Lancaster, PA 17603

NZQA unit standard version 3 Page 1 of 5. Install and maintain telecommunications radio frequency systems

This addendum forms a part of the Contract Documents dated: August 10, 2012.

Montclair, NJ ADDENDUM NO. 1 Issue Date: May 15, 2017

SUPERIOR COURT OF CALIFORNIA NORTH BUTTE COUNTY COURTHOUSE JBCP201205BR ADDENDUM NO. 5. February 25, 2013

Addendum to Description of Services for Building and Planning, Digital Design. The Association of of Consulting Engineers

SECTION PANELBOARDS

IFB PAINTING AT HAYDON ELEMENTARY ADDENDUM #1

February 18, Re: Zephyr Lakes Amenity Center Zephyrhills, Florida

State College Area School District

9. Pay for the power consumed until the project has been accepted as substantially complete.

TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION. 7:00 P.M. 494 Main Street AGENDA

September 6, 2018 CITY OF BERKELEY SHATTUCK RECONFIGURATION AND PEDESTRIAN SAFETY PROJECT SPECIFICATION NO C ADDENDUM NO.

TELEPHONE: (215) Addendum No Cooling Plant Replacement SDP Contracts No. B-080C, B-081C and B-082 of 2017/18

Summary of Modifications/Changes in this Update

TG Glazing Design-Build

This is being reviewed, additional comment to follow Marmoleum tile has been removed and replaced with a biobased VCT.

CHARLES COUNTY GOVERNMENT ITB NO ST. MARK S PUMP STATION UPGRADE

Residential Construction Checklist Single and Two Family Construction

Bid No. B14-02 Building 100 HVAC Improvements

APPLICATION FORM FOR INFRASTRUCTURE NOC

CITY OF RICHMOND Notice of Public Opening. Contract: Richmond Speed Skating Oval Interior/ Exterior Signage Package

Bidding Trades shall bring this Addendum to the attention of all sub-trades and suppliers from whom they may be receiving quotations.

Customer Connection Guide Updates Effective May 2017

SECTION OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY

City of St. Charles School District New Addition and Renovation at George M. Null Elementary School 435 Yale Boulevard St. Charles, Missouri 63301

ADDENDUM NO. 1 TO THE CONTRACT DOCUMENTS AND SPECIFICATIONS DATED JULY 2017 FLORIDA GOVERNMENTAL UTILITY AUTHORITY PROJECT NO.

COMMONWEALTH OF KENTUCKY DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION

SECTION PROJECT COORDINATION VIA BIM

REVISION #1. Section. fire alarm B. C. the hot. intent of. required. manufacturer. materials. C. Warranty

NEW SEVICE CENTER BOB HART CHEVROLET. 495 S. 7th St. E:\RE Smith New Logo.jpg VINITA, OK RE SMITH BOB HART CHEVROLET NEW SERVICE CENTER

TRIBAL BUILDING AND DEVELOPMENT Plan Check Submittal

4. Special Systems Design: including Fire Alarm and Security. C. Electrical and Telecommunications Ductbanks: Refer to Section 16118

SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2011 PROPOSITION A BOND PROGRAM SOTA-AAS HIGH SCHOOL MODERNIZATION ADDENDUM NO. 2

ADDENDUM NO. 1. November 6, 2016 BIDDING AND CONTRACT DOCUMENTS FOR

June 10, 2014 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA

James W. Moore, PE / Brandon D. Enevold, PE / Kjersten E. Kuhta, PE Dylan J. Cunningham, PE / Jacob L. Deering, PE / Joel R.

ADDENDUM 4 BID OPPORTUNITY NO

ADDENDUM NUMBER ONE (1) For. Occoquan Regional Park Jean R. Packard Center 1608 Room Exhibit Fabrication & Installation

DESIGN CHECKLIST INTRODUCTION

B422 - PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS - OPSS 422

ADDENDUM #2 September 12, 2018

YSD 400 Sliding Door System Installation Manual

CHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT

ADDENDUM NO. 1. Behlen Laboratory High Power Laser Science Collaboratory.2 RE-BID

ADDENDUM NO. 2. Furnace Bridge - Installation. Essex County, NY. July 29, 2015

ALL PLAN HOLDERS NANCY MAGER, NPSR ARCHITECTS, INC. DATE: November 29, Lea County General Service Building PROJECT NO: ADDENDUM NO: 1

2. What are the estimated volumes for the Residuum Harvesting See response to Question 1

HAMMEL ASSOCIATES ARCHITECTS, LLC 2 5 E A S T G R A N T S T R E E T, S U I T E L A N C A S T E R, P E N N S Y L V A N I A

ADDENDUM_04. > narrative objective Addendum 04 Revision Changes Defined. > narrative content. end of memo. 5Gstudio_collaborative.

Acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may disqualify Bidder.

Transcription:

ADDENDUM No. 4 Page 1 of 8 (includes attachment) Date Issued: November 27, 2017 Project: TOWNSHIP OF NORWICH FIRE SERVICE STATION No: 3 BURGESSVILLE, ONTARIO 385435 HIGHWAY 59, BUGESSVILLE, ONTARIO N0J 1CO This Addendum forms part of the Contract Documents and amends the original Drawings, Specifications, Schedules and Details issued for tender on November 2, 2017, Addendum No: 1 issued November 10, 2017, Addendum No: 2 issued November 17, 2017 and Addendum No: 3 issued November 23, 2017. RECEIPT OF ADDENDA MUST BE ACKNOWLEDGED ON THE FORM OF TENDER 1.0 RESPONSE TO QUESTIONS Q1 A1 Q2 A2 Q3 A3 Q4 A4 Q5 A5 Q6 A6 Q7 A7 Q8 A8 Washroom Accessories: Please clarify bench sizes Men s specified at 3 0 long but plans show 3 6. Women s specified at 5 0 long but plans show 8 6? Bench lengths shall be as per the specifications. We don t show bench dimensions on the plans. Sliding glass displays: Please provide location of DTB? DTB shall be located in the Truck Bay Room. Mounted on concrete block wall. The Elite Locker has since replaced the GSS Eclipse Locker as specified in this tender. The Elite Locker replacement is acceptable. As per spec 2.1.1, locker size to be 15 x20 x72, however, GSS can only manufacture locker depths at 12, 15, 18, 21, & 24. Therefore, please advise if 18 deep or 21 deep is acceptable. Revise locker size from 15 wide x 20 deep x 72 high to 12 wide x 18 deep x 72 high. Spec 2.1.3 calls for doors without pockets, yet spec 2.2.6 calls for pocket with hasp. Please clarify if pocket required or not? Pocket is required. Do the lockers require a slope top? Slope top is required. Do the lockers require a 4 Galvanneal base? Yes, including lockers that are deemed equal. Colours to be selected from manufacturer s standard colour chart? Yes. 2 Talbot Street North Simcoe, ON N3Y 3W4 Phone 519-426-6270 Fax 519-426-6277 www.gdvallee.ca

TOWNSHIP OF NORWICH FIRE SERVICE STATION No: 3 BURGESSVILLE, ONTARIO 385435 HIGHWAY 59, BUGESSVILLE, ONTARIO N0J 1CO ADDENDUM No. 4 Page 2 of 8 Q9 A9 Q10 A10 Q11 A11 Q12 Are we required to install silt fence in the right of way for the storm sewer? See Drawing 16-052-SP Erosion Control Notes. Because the site requires a lot of fill to bring up the grades can we use clay fill or does it have to be granular? See specification 02225 Site Filling and Backfilling, section 2.1.1.1 Site Fill Material. Please see attached specs and re-submit for which radiant heater model (with specs) to use! Radiant heat schedule, Sec. 2.1.2, and Sec. 2.2.1 show different models. Are they single or 2 stage? Are they fully stainless or just the burner? As per front page, job is closing Thursday Nov 30th. Correct model number is Schwank STW-JZ-130-40 or approved equal. Input 125 MBH. The reference to the SET model is incorrect. 2-stage. Stainless steel tubes not required. Yes, job is closing November 30 th (Thursday) before 2:00pm. Series 325 window is 3 ¼ frame and requires the full sill to be positioned on the stud. Your detail has the window moved past the stud towards the outside. Can you provide extra blocking beyond the stud to make sure the window is fully supported or should we add an extender 1 5/8 beyond the window which can travel beyond the sill? A12 Q13 A13 Provide extender. 2. 2.1 Manufactured Units.4 Glazing..... in accordance with applicable OBC SB-10 (I-P) for U-value of 0.250 and SHGC value of 0.35.... Can we use the following glazing: 6mm Cardinal 272 (2), Argon, Super Spacer >> Uvalue: 0.24 and SHGC value 0f 0.40 We are interpretting your specification to be only referencing the glass performance and note the full window assembly. If you do require the full assembly to meet SB10 please advise U-value of 0.25 and 0.35 SHGC is required. Yes, this applies to the full window assembly. 2 Talbot Street North Simcoe, ON N3Y 3W4 Phone 519-426-6270 Fax 519-426-6277 www.gdvallee.ca

TOWNSHIP OF NORWICH FIRE SERVICE STATION No: 3 BURGESSVILLE, ONTARIO 385435 HIGHWAY 59, BUGESSVILLE, ONTARIO N0J 1CO ADDENDUM No. 4 Page 3 of 8 2.0 DRAWINGS 1. REFERENCE CIVIL DRAWINGS 1. Top of cisterns are to be elevation 277.15. Add the following general note: The contractor is solely responsible to determine the need for and design of any anti-flotation measures for the underground cisterns. The design shall include attachment details to the cisterns in accordance with the manufacturers recommendations. Contractor shall provide calculations confirming the need or not and drawings of anti-flotation system if determined that a system is required. The drawings and calculations shall be stamped by a Professional Engineer licensed in the Province of Ontario. The determination of the need for anti-flotation is to be made on the information available in the geotechnical report provided. 3.0 ELECTRICAL ADDENDUM 1. Refer to attached Electrical Addendum No. 2 as prepared by Seguin Engineering Inc. for Town of Norwich Fire Station No: 3, Burgessville, Ontario (Dated November 22, 2017). The attached Electrical Addendum No. 2 forms part of this Addendum No. 4. END OF ADDENDUM No: 4 H:\Projects\2016\16-052 Burgessville Fire Station\Tender\Addendums\Addendum No 4\Addendum No. 4 - Burgessville Fire Service Station No 3.docx 2 Talbot Street North Simcoe, ON N3Y 3W4 Phone 519-426-6270 Fax 519-426-6277 www.gdvallee.ca

Electrical Addendum No. 02 Project: Town of Norwich Fire Station No. 3, Burgessville, Ontario Project No.: 16-167 Date: November 22, 2017 This Addendum forms part of the Contract Documents and is to be read, interpreted and coordinated with all other parts. The cost of all work contained herein shall be included in the Contract Sum. The following revisions supersede the information contained in the original drawings and specifications issued for the above named project to the extent referenced and shall become part thereof. Contactor Inquiries: Is there to be under cabinet lighting? It is not shown on the lighting drawings, but there is a layout on drawing E701. No, there is no under cabinet lighting. Typical installation detail provided, refer to plans and specifications and provide and install devices and equipment outlined on plans, disregard any equipment shown on detail that is not identified on plans. The number of wall packs on E200 and E100 are different, which drawing should be referenced? Refer to Drawing E200 for quantities of building mounted exterior light fixtures. Is there a security system to be installed? I noticed door contacts on all exterior doors, and overhead doors. Are we to carry these? All door contacts (with the exception of the universal washroom door) have been deleted in this Addendum. See below. Should the wire for 1-UG400N be a parallel run? As per Wire and Conduit Schedule, the wiring is identified as a single run. Shall a contractor choose to run parallel feeders it can be done with a parallel run of 3 conductor #3/0 CU RWU90 feeders as per detail D11-2. Is there any cable tray required? There is a diagram 5 on E700 that shows some but there is no layout or spec. 12 Argyle St. N, Caledonia, ON, N3W 1B6 www.sei-ee.com T:(289)284-0954

Detail 5 on Drawing E700 is a standard mounting detail and may include items not indicated on plans. Disregard reference to cable trays as they are not used on this project. Who will be supplying ceiling fans, and what is the spec. for them? Ceiling fans in Truck Bays have been revised in this Addendum (see below). Ceiling fan will be supplied and installed by Division 23 with final power connection by Electrical Contractor. Variable speed controller for fan to be supplied and installed by Electrical Contractor. What are the keyed pump control panel power requirements? Keyed pump control panel is to control the pumps in cisterns for truck fill. The power requirements shall much the supplied pumps along with associated overcurrent protection device. Control panel is intended for control of the pumps. There is two different routes for secondary feeders and communication conduits one on E100 and one on E300. Which should be referenced? For clarification, reference Drawing E100 revision E for routing of secondary feeders and communication conduits. Are door push button stations, main control panel, and photo electric beams supplied by the door contractor, and what is the location of the main control panel? All components for overhead doors are to be supplied by door supplier. Electrical Contractor is to provide all required rough-in along with pull string to facilitate installation and final wiring of devices and equipment by others. Main Overhead Door Control Panel is to be located in Repairs 103 on furred out wall covering the column at gridline D-4. Drawing M101, note 10 refers to a duplex pump set SP-3a, b in chamber c/w flat switches and lift out rail system. Refer to drawing E100, this drawing does not show any power running to this pump. I believe the pump will need power and this should be shown on drawing E100 so electrical trades include this in their price. Electrical contractor shall ensure all addendums and latest drawings have been received for his bidding purposes. Refer to drawings revision E issued as part of Addendum 1. Drawing M101 note 2 and note 4 refer to pumps for the well and truck fill pump at the cistern. The electrical drawing E100 does not show power running to these pumps. I assume they would need power operate and should be shown on drawing E100 so electrical trades include this in their price. 12 Argyle St. N, Caledonia, ON, N3W 1B6 www.sei-ee.com T:(289)284-0954

Electrical contractor shall ensure all addendums and latest drawings have been received for his bidding purposes. Refer to drawings revision E issued as part of Addendum 1. Regarding Section 5. Computer/Telecom Cabling System, under 5.6 Recommended Product Manufacturers we would like to have Leviton added as manufacturer for 5.6.1 Category 6 Twisted Pair Cable and 5.6.2 Computer Infrastructure Components. Refer to section 5.6 of the specifications on Drawings E050 and E051, and add the following as part of approved equal products; 1. Leviton extreme Cat 6 U/UTP Cables and Patch Cords 2. Leviton Patch Panels and computer infrastructure components. 3. Leviton P1000 series rack power distribution units. Leviton termination equipment along with associated wallplates. Installing contractor shall carry certification of the components manufacturer. Drawings: 1. Reference Drawing E050 1.1. Refer to section 5.6 of the specifications and add the following as part of approved equal products; 1.1.1. Leviton extreme Cat 6 U/UTP Cables and Patch Cords 1.1.2. Leviton Patch Panels and computer infrastructure components. 1.1.3. Leviton P1000 series rack power distribution units. 1.2. Leviton termination equipment along with associated wallplates. 2. Reference Drawing E200 2.1. Delete four (4) Type OS-4 occupancy sensors in Truck Bays 102 along gridline B and gridline C. 2.2. Add four (4) Type OS-3 occupancy sensors on columns in Truck Bays 102 at Gridline C and Gridline 3, Gridline B and Gridline 3, Gridline C and Gridline 5, Gridline B and Gridline 5. 3. Reference Drawing E300 3.1. Revise secondary feeder and communication conduits to reflect routing shown on Drawing E100. 3.2. Delete one (1) ceiling fan in Truck Bays 102. 3.3. Relocate remaining ceiling fan in Truck Bays 102 between Gridline B and C and revise connection to be 240V, single phase. Connect to new 15A-2P branch breaker A-22/24. 3.4. The following revisions are required to door hardware: 3.4.1. Door 100, Exterior to Vestibule 100: 3.4.1.1. Delete rough-in for door contact 12 Argyle St. N, Caledonia, ON, N3W 1B6 www.sei-ee.com T:(289)284-0954

3.4.1.2. Connect Automatic Door Operator (ADO) to spare 15A-1P branch breaker A-71. 3.4.1.3. Add power connection to door power supply. Connect to spare 15A-1P branch breaker A-71. Add junction box as required. 3.4.1.4. Add rough-in for keypad on exterior wall adjacent to door. 3.4.1.5. Add rough-in for current transfer hinge. 3.4.2. Door 108A, Exterior to Training Room 108: 3.4.2.1. Delete rough-in for door contact. 3.4.3. Door 102A, 102B, 102C, 102E, 102F, 102G, Exterior to Truck Bays 102: 3.4.3.1. Delete rough-in for six (6) overhead door contacts. 3.4.4. Door 102D, Exterior to Truck Bays 102: 3.4.4.1. Delete rough-in for door contact. 3.4.5. Door 102H, Exterior to Truck Bays 102: 3.4.5.1. Delete rough-in for door contact. 3.4.6. Door 102K, Exterior to Truck Bays 102: 3.4.6.1. Delete rough-in for door contact. 3.4.7. Door 116, Corridor 104 to Universal Washroom 116: 3.4.7.1. Connect Automatic Door Operator (ADO) to spare 15A-1P branch breaker A-73. 3.4.7.2. Add power connection to door power supply. Connect to spare 15A-1P branch breaker A-73. Add junction box as required. 4. Reference Drawing E500 4.1. Delete two (2) 15A-1P breakers on branch circuits A-22 and A-24. 4.2. Add one (1) 15A-2P branch breaker on branch circuit A-22/24 for ceiling fan in Truck Bays 102. 5. Reference Drawing E700 and sketch ESK-E700.1 5.1. Reference Drawing E700 and sketch ESK-E700.1 for typical cord real installation detail and all associated components. End of Addendum 02 12 Argyle St. N, Caledonia, ON, N3W 1B6 www.sei-ee.com T:(289)284-0954

12 Argyle Street N., Caledonia, ON, N3W 1B6 www.sei-ee.com