Using Synchrophasors for Frequency Response Analysis in the Western Interconnection. Bonneville Power Administration -- WECC JSIS Chair

Similar documents
Synchrophasor Technology at BPA: from Wide-Area Monitoring to Wide-Area Control

Use of the Power System Outlook (PSO) and SMART 1 Programs to View PSLF Dynamic Simulation Data Files

Real Time Stability Analysis at Peak Reliability. Slaven Kincic, Hongming Zhang JSIS May 2017, SLC

Deployment and Initial Experience with Oscillation Detection Application at Bonneville Power Administration

SDG&E Transmission Synchrophasor Project Update

( ) usable, minor formatting/editing required ( ) modification needed ( ) superseded by ( ) other ( ) obsolete/archived)

Step-Response Tests of a Unit at Atatürk Hydro Power Plant and Investigation of the Simple Representation of Unit Control System

Overview of Synchrophasor Applications. Dmitry Kosterev Bonneville Power Administration

Synchronized Measurement Data for Frequency Response Analysis

Keeping it up to Speed Off-Nominal Frequency Operations. CETAC 2018 San Ramon

SYNCHROPHASOR TECHNOLOGY GLOSSARY Revision Date: April 24, 2011

POWER SYSTEM OSCILLATIONS

Post-Event Analysis of a Compound Event in the ERCOT System Using Synchrophasor Data

generation greater than 75 MVA (gross aggregate nameplate rating) Generation in the ERCOT Interconnection with the following characteristics:

Using Synchrophasor System Data for Establishing Operating Range for Operators Guidance and Detection and Analysis of Significant Events

Harmonizing the Changing Resource Mix Keeping the Grid Together

Measurement tools at heart of Smart Grid need calibration to ensure reliability

Table of Contents Error! Bookmark not defined.

Frequency Response Standard Background Document November, 2012

Robert W. Cummings - NERC Director of System Analysis and Reliability Initiatives William Herbsleb - Chairman of Frequency Response Standard Drafting

Operationalizing Phasor Technology. Model Validation. Webinar. Ken Martin. March 4, Presented by. Page 0

Frequency Response Initiative Industry Advisory Generator Governor Frequency Response

Operational Modeling and Model Inputs

Monitoring and Situational Awareness Conference. Improving EMS Reliability Denver, CO September 18, 2013

Frequency Response Characteristic Survey Training Document

Overview. The Principles of Power System Operation module presents the following topics:

Industry Webinar. Reactive Power Planning. NERC System Analysis and Modeling Subcommittee (SAMS) March 2017

Testing model data usability Excitation Systems PSS Limiters

Table of Contents. NERC 2016 Frequency Response Annual Analysis September 2016 ii

Forward Looking Frequency Trends Technical Brief ERS Framework 1 Measures 1, 2, and 4: Forward Looking Frequency Analysis

Phasor Measurements in the WECC

Wide-Area Measurements to Improve System Models and System Operation

Frequency Response Initiative Report

Endorsed Assignments from ERS Framework

Phase Angle Monitoring:

Reliability Considerations for PPMV. Ryan Quint, NERC Dmitry Kosterev, BPA NASPI-NERC PPMV Tools Workshop October 2016

Use of Synchronized Phasor Measurements for Model Validation in ERCOT

Success Story: Practical Use of Synchrophasor Technology in ISO-NE Operations

Analysis of Effect on Transient Stability of Interconnected Power System by Introduction of HVDC Link.

Operationalizing Phasor Technology

GRID RELIABILITY MONITORING

Interconnection-Wide Oscillation Analysis: Baselining Oscillation Modes in the North American Power System Objective Purpose

Sarma (NDR) Nuthalapati, PhD

Lecture 15 EMS Application II Automatic Generation Contol. Davood Babazadeh

2013 Grid of the Future Symposium. Effect of GIC and GIC Capability of EHV Power Transformers A Case Study on an AEP 765 kv Power Transformer Design

Power System Reliability and Transfer Capability Improvement by VSC- HVDC (HVDC Light )

Procedure for ERO Support of Frequency Response and Frequency Bias Setting Standard. Event Selection Process

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

Final ballot January BOT adoption February 2015

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications

Grid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017

Alberta Reliability Standard Frequency Response and Frequency Bias Setting BAL-003-AB-1.1

Alberta Electric System Operator (AESO) Oscillatory dynamics and corridor stress in the Alberta electric system

NARUC. Summer Committee Meetings. Staff Subcommittees on Electricity & Electric Reliability

1

In addition to wide-area monitoring systems, synchrophasors offer an impressive range of system benefits, including:

Synchrophasor Technology PMU Use Case Examples

ROSE - Real Time Analysis Tool for Enhanced Situational Awareness

2018 Frequency Response Annual Analysis

Practical PMU Applications for Utilities

ESB National Grid Transmission Planning Criteria

CAISO Restricted - Do Not Distribute Outside of RC Project LOI and NDA Entities Page 1 of 24

CHAPTER 1 INTRODUCTION

Massive Transient Stability Based Cascading Analysis and On-line Identification of Critical Cascades

Use of a Sub Harmonic Protection Relay to Detect SSO Conditions Associated with Type-III Windfarms and Series Compensated Transmission Systems

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC

Facilitating Bulk Wind Power Integration Using LCC HVDC

Recent Progress on Forced Oscillation Detection and Source Locating Findings at Peak Reliability. NASPI Work Group Meeting

Frequency Response Standard Whitepaper

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction

A New Approach Applied to Adaptive Centralized Load Shedding Scheme

Minutes Frequency Response Initiative Meeting

A Real-Time Regulator, Turbine and Alternator Test Bench for Ensuring Generators Under Test Contribute to Whole System Stability

The Pacific DC Intertie Wide Area Damping Controller

Learning Lessons from the Past Power System Blackouts and using Advanced System Technologies to prevent future ones

VOLTAGE STABILITY OF THE NORDIC TEST SYSTEM

C Use of Synchronized Phasor measurement System for Enhancing AC-DC Power System Transmission Reliability and Capability

Informational Filing, Frequency Response Annual Analysis Docket No. RM

GOV/AVR Model Validation Process

Informational Filing, Frequency Response Annual Analysis Docket No. RM

Micro-synchrophasors (µpmus) in Electric Power Distribution Systems 5/29/15 SF PES Chapter Workshop

Use of Synchrophasors to Detect Control System and Circuit Breaker Reclosing Issues

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

WSAT Online Tool for Assessment of Secure Level of Wind Generation on the System

1200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report

Fault Current Limiter Selection Considerations for Utility Engineers

Response of Grid Interconnected Solar PV inverters to Transmission System Faults

Agenda Item 3h Attachment 9

Demonstration of PFR Improvement September ERCOT Operations Planning

PIER INTERIM PROJECT REPORT MODAL ANALYSIS FOR GRID OPERATIONS (MANGO): MODEL AND METHODOLOGY

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/

Synchrophasors and the Smarter Grid

Events Captured and Findings To Date. John Ballance and Abhijeet Agarwal EPG John Adams and Jian Chen ERCOT

Controlled Islanding Followed by Load Shedding Based on Rate of Frequency Decline

Informational Filing Regarding 2017 Frequency Response Annual Analysis Report Docket No. RM

Reference Document Balancing Authority Area Footprint Change Tasks

Unit Auxiliary Transformer Overcurrent Relay Loadability During a Transmission Depressed Voltage Condition

Real-time Monitoring of Power Oscillations and Modal Damping in the European ENTSO-E System

Transcription:

21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2014 Grid of the Future Symposium Using Synchrophasors for Frequency Response Analysis in the Western Interconnection D. KOSTEREV 1, D. DAVIES 2, P. ETINGOV 3, A. SILVERSTEIN 4, J. ETO 5 1 Bonneville Power Administration -- WECC JSIS Chair 2 Western Electricity Coordinating Council 3 Pacific Northwest National Laboratory 4 North American SynchroPhasor Initiative 5 Lawrence Berkeley National Laboratory -- CERTS Manager United States of America SUMMARY Frequency response has received a lot of attention in recent years at the national level, which culminated in the development and approval of NERC BAL-003-1 Frequency Response and Frequency Bias Setting Reliability Standard. WECC JSIS, NASPI, BPA, CERTS and PNNL collaborate on the common goals to deliver to the industry applications for frequency response analysis at interconnection, Balancing Authority and individual power plant levels. This paper describes a Frequency Response Analysis Tool that has been used for establishing a frequency response baseline for the Western Interconnection. It describes how synchrophasor data are used in determining generator response characteristics frequency responsive, under load control, or baseloaded. This paper also discusses and provides an example of how the distribution of frequency response across a region can impact power pick-up on major transmission paths. KEYWORDS Frequency response, Frequency Response Analysis Tool, Synchrophasor data application, NERC BAL-003-1 Lead Author: dnkosterev@bpa.gov

I. Background Federal Energy Regulatory Commission (FERC) states in [1]: Frequency response is a measure of an Interconnection s ability to stabilize frequency immediately following the sudden loss of generation or load, and is a critical component of the reliable operation of the power system, particularly during disturbances and recoveries. Frequency response has received much attention in recent years at the national level, culminating in the development and approval of the NERC BAL-003-1 Frequency Response and Frequency Bias Setting Reliability Standard [2]. The Standard determines the amount of frequency response required in each interconnection and the allocation of Frequency Response Obligation among Balancing Authorities. The Standard is largely based on technical work done in the NERC Frequency Response Initiative [3] and LBNL-led work on frequency response metrics [4]. The reliability implications of frequency response are much broader than the scope of NERC BAL- 003-1 Reliability Standard, whose main goal is to prevent under-frequency load shedding for credible resource loss contingencies in an interconnection. Frequency response distribution can have significant implications on power pick-up on major transmission paths [5,6]. Excessive governor pick-up on certain transmission paths can lead to overloads and voltage instability, and thereby impact transmission reliability margins. Impacts of frequency governing on damping of inter-area oscillations should be taken into account, as experienced in the Western Interconnection, when aggressive tuning of hydro-governor tuning and deficient response from thermal governing can result in poorly dampened oscillations [7]. Finally, certain governing characteristics are required for stable islanded operation and black-start capabilities. The Western Electricity Coordinating Council (WECC) has a long history of frequency response monitoring. WECC made several attempts to develop its own regional Frequency Responsive Reserve (FRR) standard or criteria [5], well before the NERC Standard. WECC s objectives were to: (a) ensure that an adequate amount and quality of frequency responsive reserves are carried in the interconnection, and (b) achieve even distribution of frequency response across the interconnection to mitigate the frequency response impacts on transmission paths. WECC has used synchrophasor data to monitor frequency response in the Western Interconnection. Accurate models are required for reliable and economic power system operations. WECC has been conducting model validation studies at power plant and system-wide for well over a decade [8, 9, 10]. In the early 2000 s, the validation studies indicated significant differences between the simulated and actual frequency responses, which led to the development of thermal governor modelling recommendations and a process where Generator Operators classify their units as frequency responsive, under load control, or baseloaded. Bonneville Power Administration (BPA) implemented the practice of using synchrophasor data for governor response validation [10]. These efforts greatly improved the accuracy of frequency response representation in power system studies, as evident from a number of system-wide validation studies. II. Goals of Frequency Response Analysis The Consortium for Electric Reliability Technology Solutions (CERTS) was formed in 1999 to research, develop, and disseminate new methods, tools and technologies to enhance the reliability of U.S. electric power system and efficiency of competitive electricity markets. The North American SynchroPhasor Initiative (NASPI) is a collaborative effort between the U.S. Department of Energy, North American utilities and grid operators, vendors, national labs and researchers to improve power system reliability through wide-area synchronized measurement and control and the use of synchrophasor technology. The WECC Joint Synchronized Information Subcommittee (JSIS) was formed in 2009 as the successor to the WECC Disturbance Monitoring and the WECC Wide Area Measurement groups, to provide technical guidance for management of synchronized wide-area data in the Western Interconnection, as well as development and deployment of applications that use synchronized wide-area measurements. 1

WECC JSIS, NASPI, BPA, CERTS and the Pacific Northwest National Lab (PNNL) collaborate in the common goal to deliver applications to the industry for frequency response analysis at the interconnection, Balancing Authority and individual power plant levels. Their efforts include: Develop and deploy applications for interconnection-wide frequency response analysis, Develop and deploy applications that enable Balancing Authorities to calculate Frequency Response Measure per NERC BAL-003-1from synchrophasor and SCADA data, Baseline historic frequency response performance for an interconnection, Balancing Authorities, and power plants, Develop and deploy applications for monitoring and validation of frequency response of power plants to help a Balancing Authority to determine its inventory of frequency-responsive resources, Baseline power pick-up on major transmission paths due to frequency response, and Research new methods in frequency response analysis beyond NERC BAL-003-1. III. Frequency Response Analysis Tool Figure 1 shows a typical frequency recording following a resource loss in the Western Interconnection. Point A is frequency prior to a resource loss, calculated as an average frequency over 16 seconds prior to an event. Point B is the settling frequency, calculated as an average frequency from 20 to 52 seconds following a resource loss. Point C is the minimum (nadir) frequency. NERC Frequency Response Measure (FRM) is calculated at point B. Reference [4] considered nadir-based frequency response measurement at point C. 60.02 60 A Frequency (Hz) 59.98 59.96 59.94 59.92 59.9 B 59.88 C 59.86-20 -10 0 10 20 30 40 50 60 Time (sec) Figure 1: system frequency following resource loss Nadir-based frequency response is a better measure of the primary frequency response. WECC uses PMU measurements to calculate both, the nadir and Point B frequency responses. However, the nadir response measurement at BA level requires synchronized high resolution PMU measurements of BA frequency and interchange power flows. Most BAs in NERC footprint use 4-second non-synchronized data, making the nadir frequency response nadir measurement not feasible. Therefore, frequency response at Point B is used as a practical alternative in NERC BAL-003-1 Reliability Standard. WECC JSIS worked with CERTS and PNNL to develop a Frequency Response Analysis Tool (FRAT) to manage the database of under-frequency events and calculate the frequency response baseline. The application can use both PMU data, where available, and SCADA data. Frequency response calculations are consistent with Frequency Response Measure (FRM) in NERC BAL-003-1 for an interconnection and Balancing Authority. In addition to NERC FRM, the application calculates the nadir frequency response. The frequency response metrics are saved in an extensive database, with information going back to 2008, thereby providing a unique baseline of Western Interconnection system frequency response. Figure 2 shows an interactive display of the Frequency Response 2

Analysis Tool. The primary users of the Frequency Response Application Tool are Balancing Authorities and Reliability Coordinators. Frequency response is calculated for an interconnection, as well as for a Balancing Authority. BA calculation requires interchange measurements. Unfortunately very few interchange points have PMUs today, so the BA frequency response calculations use SCADA data. SCADA measurements are not time-synchronized and the result of such skew is seen in the area interchange (see the second plot in top right corner of the display in Figure 2). SCADA data also lags PMU measurements by several seconds. Thus, at present those BAs that are using SCADA data for frequency response monitoring are likely to be reporting response values that are not precisely synchronized with interconnection-wide frequency response values measured using PMUs. It will be highly desirable to have PMUs or relay-enabled PMUs at all tie-lines for measurement synchronization, to obtain better quality frequency measurements. Database of historic events Event details and system performance Frequency Response Measure Baseline Figure 2: Frequency Response Analysis Tool With the database of frequency events developed, a variety of plots can be made for frequency response analysis. Figure 3 shows a baseline of frequency response in the Western Interconnection. Red dots represent frequency response measure calculated using the NERC FRM methodology. Blue diamonds represent frequency response measure at nadir frequency. The size of the dots is proportional to amount of generation lost during an event. Similar baseline plots are also available for individual Balancing Authorities. Let us make a few observations on WECC frequency response baseline: - the interconnection response is very consistent over the years, particularly for large events, - Western Interconnection performance averages about 1,400 to 1,600 MW per 0.1 Hz, which is well above NERC Western interconnection frequency response obligation of about 950 MW per 0.1 Hz - nadir response, as discussed earlier, is more consistent measure of the frequency response 3

2000 Frequency Response Measure for Western Interconnection 1800 Frequency Response (MW per 0.1 Hz) 1600 1400 1200 1000 800 600 400 200 0 2008 2009 2010 2011 2012 2013 2014 2015 Year Figure 3: Frequency response baseline for Western Interconnection (The size of a dot is proportional to amount of generation lost; red dots are measured at settling frequency per NERC FRM; blue diamonds are measured at the frequency nadir) Figure 4 shows a relationship between the frequency response metrics and size of the disturbance event. Red dots represent NERC FRM calculations at the settling frequency, and blue diamonds represent the response at the frequency nadir. NERC FRM is consistent for larger events, while there is wide variability in measured frequency response for smaller events. Frequency response at the nadir appears to be more consistent over a wide range of events. 2000 Frequency Response Measure for Western Interconnection 1800 Frequency Response (MW per 0.1 Hz) 1600 1400 1200 1000 800 600 400 200 0 500 1000 1500 2000 2500 3000 Event Size (MW) Figure 4: Relationship between event size and historic Frequency Response Measure (The size of a dot is proportional to date of event, so large dots = more recent events) Figure 5 shows a relationship between frequency deviations at nadir (C) and settling (B) points. The ratio appears to increase with larger events, as expected from the system physics. 4

2.5 Frequency Nadir to Settle Ratio for Western Interconnection Frequency Nadir to Settle Ratio 2 1.5 1 0.5 0 500 1000 1500 2000 2500 3000 Event Size (MW) Figure 5: Ratio between frequency deviations at nadir (C) and settling (B) points WECC-performed studies suggest that interconnecting a large amount of electronically coupled generation in the West will affect the system frequency response. The developed Frequency Response Analysis Tool has provisions to correlate the frequency response metrics with interconnection and BA generation mix hydro, thermal, wind and solar generation. IV. Power Plant Frequency Response Monitoring To meet its Frequency Response Obligation, a Balancing Authority needs to acquire frequency response from generators and other providers. The Balancing Authority needs to have monitoring applications in place to verify that the procured amount of frequency response is delivered. BPA has been using PMUs to monitor frequency response since 2000 [10]. Today, BPA can perform assessment of generator performance within minutes following a system event. In 2002, WECC conducted a comprehensive analysis of governor responses of power plants, classifying them as frequency-responsive, under load control or baseloaded [9]. Synchrophasor data are very effective for identifying frequency response types, as illustrated in Figure 6. A frequency responsetype flag is entered as a part of generator data in WECC base cases, which are later used in dynamic simulations and governor powerflow studies. Synchrophasor data are preferred for power plant frequency analysis because of its high time granularity. SCADA, AGC or plant controller data, measured at two-second speeds, may be used for general assessment of the response shape. However, it is often difficult to make a definitive conclusion from SCADA data because of the data resolution and time skew. While two-second SCADA data may be marginally useful, four to six-second SCADA data can be very misleading for power plant response analysis. As more PMUs are deployed at power plant points of interconnection, frequency response monitoring and validation will improve. 5

Frequency (Hz) Power (MW) Power (MW) Power (MW) Power (MW) 60 59.9 System Frequency 59.8 245 240 235 Frequency Responsive Power Plant 230 345 340 335 330 Combined Cycle Power Plant Under Load Control 325 610 600 590 610 600 590 Steam-Turbine Generator Under Load Control Baseloaded (Non-responsive) Steam-Turbine Generator Time (sec) Figure 6: Types of frequency responses V. Analysis of path power pick-up As discussed in the FERC AD-13-8 Docket, frequency response distribution can impact the System Operating Limits (SOLs) on major transmission paths. The SOL of the California-Oregon Intertie (COI), a 4,800 MW path in the Western Interconnection, is voltage-stability limited in post-transient time frame because of excessive power pick-up to resource losses in Pacific Southwest. Most of the frequency-responsive hydro generation is located in the Pacific Northwest, while most of the baseloaded thermal generators are in the South, thereby creating a frequency response imbalance within the interconnection. When a generator trip occurs in South, majority of governor response comes from Pacific Northwest and British Columbia, which increases COI loading. 6

Figure 7 shows a typical COI pick-up for a 1,350 MW generation outage in southern part of WECC. COI voltages declined with the power pick-up on COI due to governor response until dispatchers took corrective actions. 4100 4000 3900 3800 3700 3600 3500 3400 COI Power Governor Response 3300 100 120 140 160 180 200 220 240 260 280 300 555 550 545 540 535 530 525 System Frequency 60.02 60 59.98 59.96 59.94 59.92 59.9 59.88 59.86 59.84 59.82 100 120 140 160 180 200 220 240 260 280 300 COI Voltages Declining Voltages 520 100 120 140 160 180 200 220 240 260 280 300 Figure 7 : Frequency response impact on power pick-up and voltages on COI BPA and CAISO baseline COI power pick-up for generation outages in South, and then use the baseline to benchmark the planning and operational models used for setting System Operating Limits. VI. Future Work in Frequency Response Simplicity is a key advantage of NERC BAL-003-1 Reliability Standard. At the same time, simplicity is also its major limitation. The applicability of the BAL-003-1 methods for complex events that include sequential loss of generation is not obvious. The requirement for linearity of the frequency response, i.e. providing the same response rate for large and small events, is also questionable. As seen in Figures 4 and 5, NERC FRM is highly variable for small events and does not extrapolate well to large events. While calculating frequency response at nadir is better at the interconnection level, as it produces more consistent and relevant results, allocating such response to Balancing Authorities may be problematic because of the quality of interchange SCADA measurements. In addition, we believe that the linear response requirement disadvantages non-conventional frequency response providers, such as loads, which could be used as frequency responsive reserves for large frequency deviations. It will be desirable to acquire some frequency response from loads for large and infrequent off-nominal frequency events. While NERC BAL-003-1 is here to stay for the foreseeable future, 7

additional research into alternative practical methods of measuring and delivering reliabilityenhancing frequency response is needed. VII. Acknowledgments The authors are thankful to: - John Undrill, Bill Mittelstadt, Bob Cummings and Bart McManus for discussions on frequency response fundamentals, - Vickie VanZandt (Peak Reliability RC) for putting together the unprecedented Western Interconnection Synchrophasor Program, - Jeff Dagle (PNNL) for supporting development of Frequency Response Analysis Tool, - Les Pereira, Shawn Patterson (US Bureau of Reclamation), Armando Salazar (SCE), John Kehler (Alberta ESO), Eric Bakie (Idaho Power) and Steve Yang (BPA) for frequency response monitoring and modelling. Initial development of the Frequency Response Analysis Tool was funded by American Recovery and Reinvestment Act of 2009, award # M610000584. Further development is funded by Bonneville Power Administration. BIBLIOGRAPHY [1] Federal Energy Regulatory Commission, Docket RM13-11, Frequency Response and Frequency Bias Setting Reliability Standard, 144 FERC 61,057 (July 18, 2013) (NOPR). [2] NERC BAL-003-1 Frequency Response and Frequency Bias Setting Reliability Standard, www.nerc.com. [3] NERC Frequency Response Initiative Report, http://www.nerc.com/docs/pc/fri%20report%209-16-12%20draft.pdf. [4] J.H. Eto et al, Use of Frequency Response Metrics to Assess the Planning and Operating Requirements for Reliable Integration of Variable Renewable Generation (Lawrence Berkeley National Lab report LBNL-4142E, December 2010). http://www.ferc.gov/industries/electric/indus-act/reliability/frequencyresponsemetricsreport.pdf. [5] WECC White Paper on Frequency Response Standard (2004 http://www.wecc.biz/standards/development/wecc0044/shared%20documents/posted%20for% 20OC%20Approval/FRR%20White%20Paper%20v12_Tables_8-9.doc). [6] Federal Energy Regulatory Commission, Docket AD13-8, Market Implications of Frequency Response and Frequency Bias Setting Requirements (144 FERC 61,058, July 18, 2013). [7] A. Schlief & A. Wilbor, The Coordination of Hydraulic Turbine Governors for Power System Operation (IEEE Transactions on Power Apparatus and Systems, vol. PAS-85, No.7, July 1966, pages 750-758). [8] L.Pereira, J. Undrill, D. Kosterev, D. Davies & S. Patterson, A New Thermal Governor Modeling Approach in WECC (IEEE Transactions on Power Systems 18, No.2, May 2003, pages 819 829). [9] D. Kosterev, D. Davies, System Model Validation Studies in WECC (IEEE Power Engineering Society Meeting, July 2010, http://ieeexplore.ieee.org/xpls/abs_all.jsp?arnumber=5589797). [10] D. Kosterev, Hydro-Turbine Model Validation in Pacific Northwest (IEEE Transactions on Power Systems, vol.19, no. 2, May 2004, pages 1144 1149). 8