Phase Shifting Transformers. Presented by

Size: px
Start display at page:

Download "Phase Shifting Transformers. Presented by"

Transcription

1 Phase Shifting Transformers Presented by

2 Phase Shifting Transformers (PST s) (a.k.a. Phase Angle Regulators) VS φ S P V V S = X L L X L sin( φ φ ) L S VL φ L PST s are power flow control devices between synchronous systems. VS φ S P X PST V + α VL + X S = S L X PST L X L sin( φ φ + α) VL φ L The phase angle α governs the flow of power.

3 Active vs. Reactive Power Transfer

4 Uses of PST s To control power flow in electrical systems To correct for phase angle differences - Network coupling by enabling power transfer under acceptable parameters G φ1 > φ2 G G φ2 Design power flow Block parasitic power flow due to phase angle differences in feeding network(s) Distribute power to different customers in a defined way G Avoid circulating power flows

5 Uses of PST s To allow for optimum loading of parallel lines a) without PST The natural current distribution is dependent on the impedance of each line. if X 1 > X 2, then I 1 < I 2 and I 2 may drive its line to its thermal or dynamic stability limits b) with PST With the introduction of V PST, a circulating current i is generated to equalize the currents on both lines.

6 Definition of Advance and Retard Phase Angles V L V S voltage at source side α adv0 0 V L0 voltage at load side at no load V S V S α adv0 advance phase angle at no load, load voltage leads source voltage. This sign is defined as positive in IEEE C and IEC α ret0 retard phase angle at no load, α ret0 V L 0 load voltage lags source voltage. This sign is defined as negative

7 Phase Shift under Load (retard)

8 Phase Shift under Load (advance)

9 Impact of PST Impedance on Phase Shift

10 Types of PST s Single Core Designs - Polygon squashed delta - Asymmetrical extended delta - Symmetrical extended delta - Full wye-wye Two Core Designs - Quadrature booster - Symmetrical grounded wye (most common and most flexible) Options: With addition of voltage regulation Combined transformer and phase shifting function

11 ATCO Electric s Two Core Design PST (with symmetric voltages) V 1S V 2S Main (exciting) unit Series unit V 1L V 2L V 3S V 3L

12 Phasor Diagram to illustrate Quadrature Voltage

13 Regulating windings Technical Issues - OLTC max. voltage range of 85 kv - large space and size requirements for regulation windings (designed to handle not just a certain % of the rated power) - capacitive coupling of large portions of the regulating windings can lead to high recovery voltages during OLTC operation Tap changer capacity - max. regulation voltage range of 85 kv - max. # of operating positions < 35 - max. tap voltage < 4-5 kv / tap - max. rated through current of 3000 A - max. of 6 MVA / tap - lightning impulse voltage across regulation range < kv - short circuit thermal limit of ka for 2 secs. - small step voltage --> many operations

14 Protection Issues Source and load current exhibit same phase shift as voltages Regular transformer differential relay would trip! Special differential protection schemes needed More information in: - Protection of Phase Angle Regulating Transformers A report to the Substation Subcommittee of the IEEE Power System Relaying Committee prepared by Working Group K1 - IEEE C57.135

15 Topologies

16 Energization and operating issues during bypass Peak voltage of 140% of applied impulse at crossover 1.2 x 50 s lightning impulse

17 Cores for ST and ET

18 Core Insulation & Cooling Ducts

19 Tank Fabrication

20 Throat connecting ST&ET Tanks

21 Foundation - Winding assembly

22 Winding processing & sliding

23 Coil Nesting and lead processing

24 Top Yoke Assembly

25 Top Frame Installation

26 Tap leads

27 Tap leads routing to LTC

28 LTC Connections

29 Tanking Active Part

30 Photos of PST s in Factory 450 MVA 138 kv ± 58 single-core design with reactors 550 tons Length of internal connections ~ 5 km

31 Photos of PST s in Factory Active part, HV side of 500 MVA 400 / 132 kv + 22 in ± 3 x 7 steps, ± 12 % in ± 13 steps on HV

32 Photos of PST s in Factory Active part, HV side of 500 MVA 400 / 132 kv + 22 in ± 3 x 7 steps, ± 12 % in ± 13 steps on HV

33 2750 MVA Quadbooster in Test

34 2750 MVA Quadbooster at Site

35 Acceptance Tests in the Factory

36 Challenges in Transport (240 t for the Shunt Unit)

37 Challenging Transport

38 Extensive Acceptance Tests on Site

39 Extensive Acceptance Tests on Site

40 Transformer Short Circuit

Phase Shifter Application Workshop. Siemens Energy, Inc.

Phase Shifter Application Workshop. Siemens Energy, Inc. Phase Shifter Application Workshop Siemens Energy, Inc. PJM Power Pool, March, 2015 siemens.com/energy Phase Shifter Application Workshop Phase Shifting Transformers Principles, Design Aspects and Operation

More information

Dietrich Bonmann, ABB Monselice Transformer Days, May 5, 2010 Optimized AC transmission solutions with phase-shifting transformers and shunt reactors

Dietrich Bonmann, ABB Monselice Transformer Days, May 5, 2010 Optimized AC transmission solutions with phase-shifting transformers and shunt reactors Dietrich Bonmann, ABB Monselice Transformer Days, May 5, 2010 Optimized AC transmission solutions with phase-shifting transformers and shunt reactors May 11, 2010 Slide 1 Why phase-shifting transformers

More information

Training Fees 3,300$ per participant including Materials/Handouts, Tea/Coffee Refreshments & International Buffet Lunch.

Training Fees 3,300$ per participant including Materials/Handouts, Tea/Coffee Refreshments & International Buffet Lunch. Training Title POWER TRANSFORMERS Training Duration 5 days Training Venue and Dates Power transformers 5 20-24 May $3,300 Abu Dhabi In any of the 5 star hotel. The exact venue will be informed soon. Training

More information

DIFFERENTIAL PROTECTION METHODOLOGY FOR ARBITRARY THREE-PHASE POWER TRANSFORMERS

DIFFERENTIAL PROTECTION METHODOLOGY FOR ARBITRARY THREE-PHASE POWER TRANSFORMERS DFFERENTAL PROTECTON METHODOLOGY FOR ARBTRARY THREE-PHASE POWER TRANSFORMERS Z. Gaji ABB AB-SA Products, Sweden; zoran.gajic@se.abb.com Keywords: power transformer, phase shifting transformer, converter

More information

Transformer Protection

Transformer Protection Transformer Protection Transformer Protection Outline Fuses Protection Example Overcurrent Protection Differential Relaying Current Matching Phase Shift Compensation Tap Changing Under Load Magnetizing

More information

STRAY FLUX AND ITS INFLUENCE ON PROTECTION RELAYS

STRAY FLUX AND ITS INFLUENCE ON PROTECTION RELAYS 1 STRAY FLUX AND ITS INFLUENCE ON PROTECTION RELAYS Z. GAJIĆ S. HOLST D. BONMANN D. BAARS ABB AB, SA Products ABB AB, SA Products ABB AG, Transformers ELEQ bv Sweden Sweden Germany Netherlands zoran.gajic@se.abb.com

More information

Discipline Electrical Testing Issue Date Certificate Number T-2837 Valid Until Last Amended on - Page 1 of 6 LOCATION 1

Discipline Electrical Testing Issue Date Certificate Number T-2837 Valid Until Last Amended on - Page 1 of 6 LOCATION 1 Post: Last Amended on - Page 1 of 6 LOCATION 1 I. TRANSFORMERS AND REACTORS 1. 500 MVA, 765 kv 500 MVA, 400 kv Ratio & Polarity Check Magnetic Balance & Magnetizing Current Measurement at Low Voltage Vector

More information

Differential Protection Optimal differential protection for phase shifter transformers and special transformers

Differential Protection Optimal differential protection for phase shifter transformers and special transformers Differential Protection Optimal differential protection for phase shifter transformers and special transformers Due to the energy transition, a demand for renewable energy sources integration into power

More information

Pomona, CA May 24 & 25, LTC Applications - Location, Series & Preventative Auto Transformers

Pomona, CA May 24 & 25, LTC Applications - Location, Series & Preventative Auto Transformers Pomona, CA May 24 & 25, 2016 LTC Applications - Location, Series & Preventative Auto s siemens.com/answers Introduction Tap changer at active part Example of 3-phase tapchanger Page 2 Winding Configurations

More information

Problems connected with Commissioning of Power Transformers

Problems connected with Commissioning of Power Transformers Problems connected with Commissioning of Power Transformers ABSTRACT P Ramachandran ABB India Ltd, Vadodara, India While commissioning large Power Transformers, certain abnormal phenomena were noticed.

More information

MOBILE SUBSTATIONS 2015 MINNESOTA POWER SYSTEMS CONFERENCE

MOBILE SUBSTATIONS 2015 MINNESOTA POWER SYSTEMS CONFERENCE MOBILE SUBSTATIONS 2015 MINNESOTA POWER SYSTEMS CONFERENCE Scott Storrar Contributors: Bill Hansen, Kyle Reddell, Tom McGrath Basic Mobile Sub Design Equipment mounted on semi-trailer Power transformer

More information

La protection sélective des réseaux électriques

La protection sélective des réseaux électriques La protection sélective des réseaux électriques ULG 21. 11. 2012 The T&D grids Generation Transmission Distribution Industry The electricity network ensure an efficient supply of energy High Voltage Transformers

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements Division 502 Technical Applicability 1(1) Section 502.1 applies to: Expedited Filing Draft August 22, 2017 the legal owner of an aggregated generating facility directly connected to the transmission system

More information

R10. IV B.Tech I Semester Regular/Supplementary Examinations, Nov/Dec SWITCH GEAR AND PROTECTION. (Electrical and Electronics Engineering)

R10. IV B.Tech I Semester Regular/Supplementary Examinations, Nov/Dec SWITCH GEAR AND PROTECTION. (Electrical and Electronics Engineering) R10 Set No. 1 Code No: R41023 1. a) Explain how arc is initiated and sustained in a circuit breaker when the CB controls separates. b) The following data refers to a 3-phase, 50 Hz generator: emf between

More information

Regional Technical Seminar TAP CHANGERS

Regional Technical Seminar TAP CHANGERS Regional Technical Seminar TAP CHANGERS SPX Transformer Solutions, Inc. September 4, 2018 De-Energized and Load Tap Changers Jason Varnell Lead Design Engineer jason.varnell@spx.com SPX Transformer Solutions,

More information

Tertiary Winding Design in wye-wye Connected Transformers Restricted Siemens Energy 2013 All rights reserved.

Tertiary Winding Design in wye-wye Connected Transformers Restricted Siemens Energy 2013 All rights reserved. Pomona, CA, May 24 & 25, 2016 Tertiary Winding Design in wye-wye Connected Transformers Scope of Presentation > Tertiary vs. Stabilizing Winding? Tertiary vs. Stabilizing Winding? Need for Stabilizing

More information

Shunt Reactors. Global Top Energy, Machinery & Plant Solution Provider

Shunt Reactors. Global Top Energy, Machinery & Plant Solution Provider Shunt Reactors Global Top Energy, Machinery & Plant Solution Provider Our Business Brief introduction of Hyosung Power & Industrial Systems PG While Hyosung is an established name for world-class electrical

More information

HV AC TESTING OF SUPER-LONG CABLES

HV AC TESTING OF SUPER-LONG CABLES HV AC TESTING OF SUPER-LONG CABLES Stefan SCHIERIG, (Germany), schierig@highvolt.de Peter COORS, (Germany), coors@highvolt.de Wolfgang HAUSCHILD, IEC, CIGRE, (Germany), hauschild@highvolt.de ABSTRACT The

More information

Modeling and electromagnetic transients study of two 1800MVA phase shifting transformers in the Italian transmission network

Modeling and electromagnetic transients study of two 1800MVA phase shifting transformers in the Italian transmission network Modeling and electromagnetic transients study of two 18MVA phase shifting transformers in the Italian transmission network Luigi Colla, Vincenzo Iuliani, Francesco Palone, Massimo Rebolini, Stefano Zunino

More information

Cork Institute of Technology. Autumn 2008 Electrical Energy Systems (Time: 3 Hours)

Cork Institute of Technology. Autumn 2008 Electrical Energy Systems (Time: 3 Hours) Cork Institute of Technology Bachelor of Science (Honours) in Electrical Power Systems - Award Instructions Answer FIVE questions. (EELPS_8_Y4) Autumn 2008 Electrical Energy Systems (Time: 3 Hours) Examiners:

More information

Transformer Winding Design. The Design and Performance of Circular Disc, Helical and Layer Windings for Power Transformer Applications

Transformer Winding Design. The Design and Performance of Circular Disc, Helical and Layer Windings for Power Transformer Applications The Design and Performance of Circular Disc, Helical and Layer Windings for Power Transformer Applications Minnesota Power Systems Conference November 3 5, 2009 Earl Brown Heritage Center University of

More information

TABLE OF CONTENT

TABLE OF CONTENT Page : 1 of 34 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia TABLE OF CONTENT SCOPE 3 REFERENCES

More information

Transformer protection IED RET 670

Transformer protection IED RET 670 Gunnar Stranne Transformer protection IED RET 670 Santiago Septiembre 5, 2006 1 Transformer protection IED RET670 2 Introduction features and applications Differential protection functions Restricted Earth

More information

Notes 1: Introduction to Distribution Systems

Notes 1: Introduction to Distribution Systems Notes 1: Introduction to Distribution Systems 1.0 Introduction Power systems are comprised of 3 basic electrical subsystems. Generation subsystem Transmission subsystem Distribution subsystem The subtransmission

More information

R10. III B.Tech. II Semester Supplementary Examinations, January POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours

R10. III B.Tech. II Semester Supplementary Examinations, January POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours Code No: R3 R1 Set No: 1 III B.Tech. II Semester Supplementary Examinations, January -14 POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours Max Marks: 75 Answer any FIVE Questions

More information

TRANSFORMER TECHNOLOGY GPT

TRANSFORMER TECHNOLOGY GPT Core-Form TRANSFORMER TECHNOLOGY GlobalPT Corporation performs research and engineering developments and co-ordination of works of technical partners in the field of technological progress and commercial

More information

Impact Assessment Generator Form

Impact Assessment Generator Form Impact Assessment Generator Form This connection impact assessment form provides information for the Connection Assessment and Connection Cost Estimate. Date: (dd/mm/yyyy) Consultant/Developer Name: Project

More information

Arrowhead Station Special Equipment Operation. Dudley Maki Minnesota Power

Arrowhead Station Special Equipment Operation. Dudley Maki Minnesota Power Arrowhead Station Special Equipment Operation Dudley Maki Minnesota Power Arrowhead - Equipment Operation Non-Standard Equipment at Arrowhead 345 kv Phase Shifting Transformer (8TR) Voltage Regulating

More information

CHAPTER 4. Distribution Transformers

CHAPTER 4. Distribution Transformers CHAPTER 4 Distribution Transformers Introduction A transformer is an electrical device that transfers energy from one circuit to another purely by magnetic coupling. Relative motion of the parts of the

More information

Understanding and Extracting Valuable Information from Basic and Advanced Power Transformer Testing Techniques

Understanding and Extracting Valuable Information from Basic and Advanced Power Transformer Testing Techniques Understanding and Extracting Valuable Information from Basic and Advanced Power Transformer Testing Techniques Charles Sweetser, Services Manager, PRIM Engineering, Waltham, Mass. Topics of Discussion

More information

Regional Technical Seminar

Regional Technical Seminar Regional Technical Seminar LOAD TAP CHANGERS (LTCS) DESIGN, OPERATION, AND MAINTENANCE CONSIDERATIONS SPX Dallas Facility Damon Jones General Manager SPX Transformer Solutions Components Group Cell: 214-422-8979

More information

Transient Stability Improvement Of Power System With Phase Shifting Transformer

Transient Stability Improvement Of Power System With Phase Shifting Transformer INTERNATIONAL JOURNAL OF TECHNOLOGY ENHANCEMENTS AND EMERGING ENGINEERING RESEARCH, VOL 3, ISSUE 3 19 Transient Stability Improvement Of Power System With Phase Shifting Transformer Jyothi Varanasi, Aditya

More information

Transformer Technology Seminar Winding Selection

Transformer Technology Seminar Winding Selection Pomona, CA May 24 25, 2016 Transformer Technology Seminar Siemens AG Transformers siemens.com/answers Windings: Page 2 Example GSU 274/464MVA H0 H1 H2 H3 U U I I H L H L N = N N = N L H H L HV: 405kV ±8x1.25%

More information

Power System Protection. Dr. Lionel R. Orama Exclusa, PE Week 3

Power System Protection. Dr. Lionel R. Orama Exclusa, PE Week 3 Power System Protection Dr. Lionel R. Orama Exclusa, PE Week 3 Operating Principles: Electromagnetic Attraction Relays Readings-Mason Chapters & 3 Operating quantities Electromagnetic attraction Response

More information

CHAPTER 3 REVIEW OF POWER TRANSFORMER PROTECTION SCHEMES

CHAPTER 3 REVIEW OF POWER TRANSFORMER PROTECTION SCHEMES CHAPTER 3 REVIEW OF POWER TRANSFORMER PROTECTION SCHEMES 3.1. Introduction Power Transformer is the nerve centre of any power distribution system. The capacity of power transformers is generally decided

More information

Keywords: Power Transformer, On-load Tap Changer, AVR, Low Voltage Variation, Change Positions, OLTC Control.

Keywords: Power Transformer, On-load Tap Changer, AVR, Low Voltage Variation, Change Positions, OLTC Control. www.semargroup.org, www.ijsetr.com ISSN 2319-8885 Vol.03,Issue.11 June-2014, Pages:2487-2493 Advance OLTC Control for Improving Power System Voltage Stability NWE NWE SOE 1, KYAW SAN LWIN 2 1 Dept of Electrical

More information

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES Highgate Converter Overview Prepared by Joshua Burroughs & Jeff Carrara IEEE PES Highgate Converter Abstract Introduction to HVDC Background on Highgate Operation and Control schemes of Highgate 22 Why

More information

Understanding the Value of Electrical Testing for Power Transformers. Charles Sweetser, OMICRON electronics Corp. USA

Understanding the Value of Electrical Testing for Power Transformers. Charles Sweetser, OMICRON electronics Corp. USA Understanding the Value of Electrical Testing for Power Transformers Charles Sweetser, OMICRON electronics Corp. USA Understanding the Value of Electrical Testing for Power Transformers Charles Sweetser,

More information

Regional Technical Seminar SHORT CIRCUIT FORCES

Regional Technical Seminar SHORT CIRCUIT FORCES Regional Technical Seminar SHORT CIRCUIT FORCES Short Circuit Forces Wallace Exum Electrical Design Engineer wallace.exum@spx.com Agenda 1. What is Short Circuit 2. Types of Faults 3. How to Calculate

More information

BE Semester- VI (Electrical Engineering) Question Bank (E 605 ELECTRICAL POWER SYSTEM - II) Y - Y transformer : 300 MVA, 33Y / 220Y kv, X = 15 %

BE Semester- VI (Electrical Engineering) Question Bank (E 605 ELECTRICAL POWER SYSTEM - II) Y - Y transformer : 300 MVA, 33Y / 220Y kv, X = 15 % BE Semester- V (Electrical Engineering) Question Bank (E 605 ELECTRCAL POWER SYSTEM - ) All questions carry equal marks (10 marks) Q.1 Explain per unit system in context with three-phase power system and

More information

Embedded Generation Connection Application Form

Embedded Generation Connection Application Form Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed

More information

Power Measurements and Basic Electrical Diagnostic Tests

Power Measurements and Basic Electrical Diagnostic Tests Power Measurements and Basic Electrical Diagnostic Tests Instrument Basics Burden VA Sources V and I Meters V and I KVL and KCL Kelvin Connection KVL and KCL Kelvin Connection 4-Wire Technique Exclude

More information

POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS.

POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS. POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS. This document may be subject to changes. Contact ARTECHE to confirm the characteristics and availability of the products

More information

Substation Preventive Maintenance

Substation Preventive Maintenance Substation Preventive Maintenance PROVINCIAL ELECTRICITY AUTHORITY 1 Presentation Contents 1) A kind of substation 2) Electrical equipment details of AIS substation 3) Electrical equipment details of GIS

More information

DATA SHEET FOR LIGHTING TRANSFORMER APPD. BY VDV PROJECT NO

DATA SHEET FOR LIGHTING TRANSFORMER APPD. BY VDV PROJECT NO PART - A : SPECIFIC REQUIREMENTS THIS DATA SHEET IS APPLICABLE FOR IN BOILER A CLIMATIC CONDITIONS PACKAGE 1 DESIGN AMBIENT TEMPERATURE 45 C 2 ALTITUDE ( ABOVE MSL ) 6.71 MTRS. 3 RELATIVE HUMIDITY 74 %

More information

Benefits of SFRA - Case Studies

Benefits of SFRA - Case Studies 6 th International Conference on Large Power Transformers- Modern Trends Benefits of SFRA - Case Studies B B Ahir Gujarat Energy Transmission Corporation Limited 1 Outline Condition Monitoring in GETCO

More information

MFAC. Grid Solutions. High Impedance Differential Relay. MFAC Types. Key Benefits. Application. Description. Imagination at work

MFAC. Grid Solutions. High Impedance Differential Relay. MFAC Types. Key Benefits. Application. Description. Imagination at work GE Grid Solutions MFAC High Impedance Differential Relay MFAC relays provide high speed differential protection for various types of power systems plants including generators, reactors, busbars, motors

More information

Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian institute of Technology, Kharagpur

Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian institute of Technology, Kharagpur Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian institute of Technology, Kharagpur Lecture - 10 Transmission Line Steady State Operation Voltage Control (Contd.) Welcome

More information

On-Load Tap Changer Type M

On-Load Tap Changer Type M On-Load Tap Changer Type M OLTC type model M III 500 Y, U m = 123 Kv, 500A, ± 9 steps The type M On Load tap changers are used to vary the ratio of oil-immersed transformers under load.in general they

More information

Distribution System Development & Preliminary Studies

Distribution System Development & Preliminary Studies Distribution System Development & Preliminary Studies IEEE CED January 27, 2016 (second night) 2016 KBR, Inc. All Rights Reserved. Agenda Distribution System Development Modeling Data Studies Overview

More information

Transformer Factory Testing

Transformer Factory Testing Transformer Factory Testing John J. Foschia Test Engineer John.Foschia@spx.com September 2018 Reasons for Testing Compliance with user specifications Assessment of quality and reliability Verification

More information

KNOW MORE ABOUT THE TRANSFORMERS. Glossary Transformers

KNOW MORE ABOUT THE TRANSFORMERS. Glossary Transformers KNOW MORE ABOUT THE TRANSFORMERS Glossary Transformers Ambient temperature The existing temperature of the atmosphere surrounding a transformer installation. Ampere The practical unit of electric current.

More information

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: IDAHO POWER COMPANY Designated Contact Person: Jeremiah Creason Address: 1221 W. Idaho Street, Boise ID 83702 Telephone

More information

Code No: R Set No. 1

Code No: R Set No. 1 Code No: R05310204 Set No. 1 III B.Tech I Semester Regular Examinations, November 2007 ELECTRICAL MACHINES-III (Electrical & Electronic Engineering) Time: 3 hours Max Marks: 80 Answer any FIVE Questions

More information

Jason Harchick, P.E. Sr. Manager, System Planning and Protection Ryan Young Manager, Substation Engineering

Jason Harchick, P.E. Sr. Manager, System Planning and Protection Ryan Young Manager, Substation Engineering DLC s Brady IIB Project Jason Harchick, P.E. Sr. Manager, System Planning and Protection Ryan Young Manager, Substation Engineering Project Need In 2007, PJM and Duquesne Light Company (DLC) transmission

More information

Technical Questionnaire 9.101/6 Transformer Test System. Personal Data. Application. Test of. Delivery scope

Technical Questionnaire 9.101/6 Transformer Test System. Personal Data. Application. Test of. Delivery scope Date: Page: 1 / 10 Personal Data Name: Company / institution: Phone: E-mail: Fax: Application Quotation number: (will be filled in by HIGHVOLT) Test field, stationary research institute mobile on-site

More information

, ,54 A

, ,54 A AEB5EN2 Ground fault Example Power line 22 kv has the partial capacity to the ground 4,3.0 F/km. Decide whether ground fault currents compensation is required if the line length is 30 km. We calculate

More information

Embedded Generation Connection Application Form

Embedded Generation Connection Application Form Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed

More information

MEDIUM & HIGH VOLTAGE

MEDIUM & HIGH VOLTAGE MEDIUM & HIGH VOLTAGE TESTING EQUIPMENT VOLTAGE WITHSTAND SGM Series Resonant Systems The SGM series are used for generating high AC voltages at a fixed frequency (mainly 50 or 60 Hz) by means of an excited

More information

Case Study 1. Power System Planning and Design: Power Plant, Transmission Lines, and Substations

Case Study 1. Power System Planning and Design: Power Plant, Transmission Lines, and Substations Case Study 1 Power System Planning and Design: Power Plant, Transmission Lines, and Substations Lindsay Thompson, 5203120 Presented to Riadh Habash ELG 4125 11/10/2013 1.0 ABSTRACT A power plant delivers

More information

Single-Core Symmetrical Phase Shifting Transformer Protection Using Multi-Resolution Analysis

Single-Core Symmetrical Phase Shifting Transformer Protection Using Multi-Resolution Analysis IJEEE, Volume 3, Spl. Issue (1) Single-Core Symmetrical Phase Shifting Transformer Protection Using Multi-Resolution Analysis Meenakshi Sahu 1, Mr. Rahul Rahangdale 1, Department of ECE, School of Engineering

More information

System Protection and Control Subcommittee

System Protection and Control Subcommittee Power Plant and Transmission System Protection Coordination Reverse Power (32), Negative Sequence Current (46), Inadvertent Energizing (50/27), Stator Ground Fault (59GN/27TH), Generator Differential (87G),

More information

GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW

GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW ELECTRIC UTILITY CONTACT INFORMATION Consumers Energy Interconnection Coordinator 1945

More information

RAIDK, RAIDG, RAPDK and RACIK Phase overcurrent and earth-fault protection assemblies based on single phase measuring elements

RAIDK, RAIDG, RAPDK and RACIK Phase overcurrent and earth-fault protection assemblies based on single phase measuring elements RAIDK, RAIDG, RAPDK and RACIK Phase overcurrent and earth-fault protection assemblies based on single phase measuring elements User s Guide General Most faults in power systems can be detected by applying

More information

ECE 528 Understanding Power Quality

ECE 528 Understanding Power Quality ECE 528 Understanding Power Quality http://www.ece.uidaho.edu/ee/power/ece528/ Paul Ortmann portmann@uidaho.edu 208-733-7972 (voice) Lecture 22 1 Today Homework 5 questions Homework 6 discussion More on

More information

EPS AUSTRALIA SERVICES HV TESTING & COMMISSIONING CAPABILITY

EPS AUSTRALIA SERVICES HV TESTING & COMMISSIONING CAPABILITY EPS AUSTRALIA SERVICES HV TESTING & COMMISSIONING CAPABILITY EPS AUSTRALIA SERVICES COMPANY OVERVIEW EPS is a recognised company specialising in Electrical, Instrumentation, Structural, Mechanical and

More information

In Class Examples (ICE)

In Class Examples (ICE) In Class Examples (ICE) 1 1. A 3φ 765kV, 60Hz, 300km, completely transposed line has the following positive-sequence impedance and admittance: z = 0.0165 + j0.3306 = 0.3310 87.14 o Ω/km y = j4.67 410-6

More information

EH2741 Communication and Control in Electric Power Systems Lecture 2

EH2741 Communication and Control in Electric Power Systems Lecture 2 KTH ROYAL INSTITUTE OF TECHNOLOGY EH2741 Communication and Control in Electric Power Systems Lecture 2 Lars Nordström larsno@kth.se Course map Outline Transmission Grids vs Distribution grids Primary Equipment

More information

PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016

PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016 PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016 Prepared by System Planning Division Transmission Planning Department PJM 2016 Table of Contents Table of Contents Approval...6

More information

The measurement of winding resistance is useful in detecting a number of types of fault in a transformer. Malfunctioning tap changer mechanisms

The measurement of winding resistance is useful in detecting a number of types of fault in a transformer. Malfunctioning tap changer mechanisms Why Measure Winding Resistance? The measurement of winding resistance is useful in detecting a number of types of fault in a transformer. Malfunctioning tap changer mechanisms Partial or dead short-circuited

More information

Utility Interconnection and System Protection

Utility Interconnection and System Protection Utility Interconnection and System Protection Alex Steselboim President, Advanced Power Technologies, Inc. Utility paralleling vs. isolated operation. Isochronous kw load sharing Reactive power (VAR) sharing

More information

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY 9. INTRODUCTION Control Cabling The protection and control equipment in power plants and substations is influenced by various of environmental conditions. One of the most significant environmental factor

More information

Power Transformers Basics

Power Transformers Basics Power Transformers Basics Transformer Basic Objective Introduce Basic Transformer Theory as it Relates to Diagnostics Provide a Better Understanding of the Diagnostic Test Environment Identify Important

More information

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control Spring 2014 Instructor: Kai Sun 1 References Saadat s Chapters 12.6 ~12.7 Kundur s Sections

More information

TRANSFORMER THEORY. Mutual Induction

TRANSFORMER THEORY. Mutual Induction Transformers Transformers are used extensively for AC power transmissions and for various control and indication circuits. Knowledge of the basic theory of how these components operate is necessary to

More information

Understanding the Value of Electrical Testing for Power Transformers. Charles Sweetser - OMICRON

Understanding the Value of Electrical Testing for Power Transformers. Charles Sweetser - OMICRON Understanding the Value of Electrical Testing for Power Transformers Charles Sweetser - OMICRON Transformers Diagnostic Testing - OVERALL DGA Oil Screen Power Factor / Capacitance Exciting Current Transformer

More information

N. TEST TEST DESCRIPTION

N. TEST TEST DESCRIPTION Multi function system for testing substation equipment such as: current, voltage and power transformers, all type of protection relays, energy meters and transducers Primary injection testing capabilities

More information

Sequence Networks p. 26 Sequence Network Connections and Voltages p. 27 Network Connections for Fault and General Unbalances p. 28 Sequence Network

Sequence Networks p. 26 Sequence Network Connections and Voltages p. 27 Network Connections for Fault and General Unbalances p. 28 Sequence Network Preface p. iii Introduction and General Philosophies p. 1 Introduction p. 1 Classification of Relays p. 1 Analog/Digital/Numerical p. 2 Protective Relaying Systems and Their Design p. 2 Design Criteria

More information

ELECTRICAL POWER ENGINEERING

ELECTRICAL POWER ENGINEERING Introduction This trainer has been designed to provide students with a fully comprehensive knowledge in Electrical Power Engineering systems. The trainer is composed of a set of modules for the simulation

More information

Wind Power Facility Technical Requirements CHANGE HISTORY

Wind Power Facility Technical Requirements CHANGE HISTORY CHANGE HISTORY DATE VERSION DETAIL CHANGED BY November 15, 2004 Page 2 of 24 TABLE OF CONTENTS LIST OF TABLES...5 LIST OF FIGURES...5 1.0 INTRODUCTION...6 1.1 Purpose of the Wind Power Facility Technical

More information

Generation Interconnection Study Data Sheet Synchronous Machines

Generation Interconnection Study Data Sheet Synchronous Machines FOR INTERNAL USE ONLY GTC Project Number: Queue Date: Generation Interconnection Study Data Sheet Synchronous Machines Customers must provide the following information in its entirety. GTC will not proceed

More information

Embedded Generation Connection Application Form

Embedded Generation Connection Application Form Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed

More information

T/3000 T/3000. Substation Maintenance and Commissioning Test Equipment

T/3000 T/3000. Substation Maintenance and Commissioning Test Equipment T/3000 Substation Maintenance and Commissioning Test Equipment MULTI FUNCTION SYSTEM FOR TESTING SUBSTATION EQUIPMENT SUCH AS: CURRENT, VOLTAGE AND POWER TRANSFORMERS, ALL TYPE OF PROTECTION RELAYS, ENERGY

More information

GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 2 MW

GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 2 MW GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 2 MW Electric Utility Contact Information DTE Energy Interconnection Coordinator One Energy Plaza, SB

More information

REPORT ON INVESTIGATION OF FAILURE OF 100 MVA, 220/66-33/11 KV POWER TRANSFORMER AT 220KV GEETA COLONY SUBSTATION OF DELHI TRANSCO LTD.

REPORT ON INVESTIGATION OF FAILURE OF 100 MVA, 220/66-33/11 KV POWER TRANSFORMER AT 220KV GEETA COLONY SUBSTATION OF DELHI TRANSCO LTD. REPORT ON INVESTIGATION OF FAILURE OF 100 MVA, 220/66-33/11 KV POWER TRANSFORMER AT 220KV GEETA COLONY SUBSTATION OF DELHI TRANSCO LTD. (DTL) 1.0 Introduction: 1.1 DTL vide letter No. F.DTL/206/2015-16/Mgr(T)O&M-E-2/22

More information

High-Voltage Capacitive Compensation Unit for Transformer and Shunt Reactor Testing, Type HVCC

High-Voltage Capacitive Compensation Unit for Transformer and Shunt Reactor Testing, Type HVCC HIGHVOLT Prüftechnik Dresden GmbH Marie-Curie-Straße 1 1139 Dresden, Germany Phone +49 351 8425-7 Fax +49 351 8425-679 E-mail sales@highvolt.de Website www.highvolt.de Data Sheet 8.81-1/1 High-Voltage

More information

Numbering System for Protective Devices, Control and Indication Devices for Power Systems

Numbering System for Protective Devices, Control and Indication Devices for Power Systems Appendix C Numbering System for Protective Devices, Control and Indication Devices for Power Systems C.1 APPLICATION OF PROTECTIVE RELAYS, CONTROL AND ALARM DEVICES FOR POWER SYSTEM CIRCUITS The requirements

More information

PRODUCT PORTFOLIO TEST AND MEASURING SYSTEMS

PRODUCT PORTFOLIO TEST AND MEASURING SYSTEMS PRODUCT PORTFOLIO TEST AND MEASURING SYSTEMS n Quality made in Germany n Standardized and customized solutions n Turn key projects, all from one hand 0.1-1/1 Product Portfolio Test and Measuring Systems

More information

Catastrophic Relay Misoperations and Successful Relay Operation

Catastrophic Relay Misoperations and Successful Relay Operation Catastrophic Relay Misoperations and Successful Relay Operation Steve Turner (Beckwith Electric Co., Inc.) Introduction This paper provides detailed technical analysis of several catastrophic relay misoperations

More information

Generation and Load Interconnection Standard

Generation and Load Interconnection Standard Generation and Load Interconnection Standard Rev. 0 DRAFT Name Signature Date Prepared: Approved: VP Acceptance APEGGA Permit to Practice P-08200 TABLE OF CONTENTS 1.0 INTRODUCTION...5 1.1 Purpose...5

More information

(2) New Standard IEEE P (3) Core : (4) Windings :

(2) New Standard IEEE P (3) Core : (4) Windings : (d) Electrical characteristics (such as short-circuit withstand, commutating reactance, more number of windings, etc); (e) Longer life expectancy; (f) Energy efficiency; (g) more demanding environment.

More information

Level 6 Graduate Diploma in Engineering Electrical Energy Systems

Level 6 Graduate Diploma in Engineering Electrical Energy Systems 9210-114 Level 6 Graduate Diploma in Engineering Electrical Energy Systems Sample Paper You should have the following for this examination one answer book non-programmable calculator pen, pencil, ruler,

More information

SHORT CIRCUIT ANALYSIS OF 220/132 KV SUBSTATION BY USING ETAP

SHORT CIRCUIT ANALYSIS OF 220/132 KV SUBSTATION BY USING ETAP SHORT CIRCUIT ANALYSIS OF 220/132 KV SUBSTATION BY USING ETAP Kiran V. Natkar 1, Naveen Kumar 2 1 Student, M.E., Electrical Power System, MSS CET/ Dr. B.A.M. University, (India) 2 Electrical Power System,

More information

ABB Power Products Service

ABB Power Products Service Raben Naidoo, Technology days, May 21-22th, 2014, Cape Town, South Africa, Enhanced availability of transformers via transformer remote monitoring - TEC ABB Power Products Service Why a session on availability?

More information

Functional Specification Revision History

Functional Specification Revision History Functional Specification Revision History Revision Description of Revision By Date V1D1 For Comments Yaoyu Huang October 27, 2016 V1 For Issuance Yaoyu Huang November 21, 2016 Section 5.3 updated Transformer

More information

Generation and Load Interconnection Standard

Generation and Load Interconnection Standard Generation and Load Interconnection Standard Rev. 0A DRAFT Name Signature Date Prepared: Approved: VP Acceptance APEGGA Permit to Practice P-08200 TABLE OF CONTENTS 1.0 INTRODUCTION...5 1.1 Purpose...5

More information

Application for A Sub-harmonic Protection Relay. ERLPhase Power Technologies

Application for A Sub-harmonic Protection Relay. ERLPhase Power Technologies Application for A Sub-harmonic Protection Relay ERLPhase Power Technologies 1 Outline Introduction System Event at Xcel Energy Event Analysis Microprocessor based relay hardware architecture Sub harmonic

More information

TesTIng of Power. Transformers are the largest, most. feature. By brandon dupuis

TesTIng of Power. Transformers are the largest, most. feature. By brandon dupuis feature By brandon dupuis An Introduction to Electrical diagnostic TesTIng of Power Transformers 38 Transformers are the largest, most expensive, and highly critical components of most utility substations.

More information

Generator Protection GENERATOR CONTROL AND PROTECTION

Generator Protection GENERATOR CONTROL AND PROTECTION Generator Protection Generator Protection Introduction Device Numbers Symmetrical Components Fault Current Behavior Generator Grounding Stator Phase Fault (87G) Field Ground Fault (64F) Stator Ground Fault

More information

PUBLIC POWER CORPORATION ENGINEERING & CONSTRUCTION OF TRANSMISSION PROJECTS DEPARTMENT

PUBLIC POWER CORPORATION ENGINEERING & CONSTRUCTION OF TRANSMISSION PROJECTS DEPARTMENT PUBLIC POWER CORPORATION ENGINEERING & CONSTRUCTION OF TRANSMISSION PROJECTS DEPARTMENT SPECIFICATION SS-25 / 14 POWER TRANSFORMERS 150/15.75-21kV, 40/50 MVA WITH AUTOMATIC LOAD-RATIO CONTROL CONNECTION

More information