MILJÖREDOVISNING BILAGA 5

Size: px
Start display at page:

Download "MILJÖREDOVISNING BILAGA 5"

Transcription

1 MILJÖREDOVISNING BILAGA 5 MODELLING OF SEDIMENT SPILL IN SWEDEN DOCUMENT ID: W-PE-EIA-PSE-REP EN-06

2 Intended for Nord Stream 2 AG Date September, 2016 Document number W-PE-EIA-PSE-REP EN-06 NORD STREAM 2 MODELLING OF SEDIMENT SPILL IN SWEDEN

3 NORD STREAM 2 Modelling of sediment spill in Sweden Revision 06 Date Document ID Ref W-PE-EIA-PSE-REP EN / PO Revision Record: Revision Date Made by Checked Approved by Approved by (discipline lead) (Project Manager) EAB/HSN JAN HSN MIBR EAB JAN HSN MIBR JAN JLA HSN MIBR JAN JLA HSN MIBR JAN JLA HSN MIBR JAN JLA HSN MIBR by Ramboll Hannemanns Allé 53 DK-2300 Copenhagen S Denmark T F

4 CONTENTS 1. INTRODUCTION 1 2. SEDIMENT CHARACTERISTICS Trenching locations Rock placement locations 8 3. SPILL SCENARIOS MODEL RESULTS Trenching Rock placement SUMMARY OF RESULTS CONCLUSIONS REFERENCES 40 Document No.: 9TW-9TPE-EIA-PSE-REP EN-06

5 ABBREVIATION LIST ADCP Acoustic Doppler Current Profiler DHI Danish Hydraulic Institute EIA Environmental Impact Assessment ES Environmental Study NSP Nord Stream pipeline system NSP2 Nord Stream 2 pipeline system MIKE 3 three-dimensional modelling suite MIKE 3 HD hydrodynamic module of MIKE 3 MIKE 3 PT particle tracking module of MIKE 3 SGU Sveriges geologiska undersökning (Geological Survey of Sweden) Document No.: 9TW-9TPE-EIA-PSE-REP EN-06

6 1 1. INTRODUCTION The Environmental Study (ES) for the Nord Stream 2 pipeline (NSP2) requires forecasting of the sediment spill expected during seabed intervention works in order to evaluate the corresponding impact on the marine environment. This report documents the model input and the results of the simulations that have been selected as representative scenarios. The seabed intervention works used in the model scenarios is based on specifications from NSP2 with possible positions and volumes for seabed intervention works, /8/ /9/. The modelling of sediment spreading from seabed intervention work (trenching and rock placement) is based on a worst case scenario, therefore it is considered to be a conservative approximation, and the extent of impacts will most likely be much smaller in reality. The expected seabed intervention works is graphically presented in Figure 1-1, Figure 1-2 and Figure 1-3. The locations are listed in Table 2-3, Table 2-5 and Table 2-6. Figure 1-1: Map of Swedish waters with planned trenching locations.

7 2 Figure 1-2: Map of Swedish waters with planned rock placement locations.

8 3 Rock Placement Figure 1-3: Map of Swedish waters with planned spot gravel locations. The purpose of this report is to disseminate model results among contributors to the Swedish ES and the Espoo EIA. Consequently, it focuses on the presentation of results. Background information on the hydrographic basis and the fundamental assumptions and common methodology for Finland, Sweden and Denmark are only briefly summarised in this report. An indepth description is found in /2/. An overview of the input to the model simulations are given in Table 1-1. Table 1-1: Summary of input to model simulations Scenario Trenching Rock placement Locations Southeast of Hoburgs Bank and Norra Midsjöbanken East and northeast of Gotland and east of Hoburgs Bank Route NSP2 line B NSP2 line B Activity Post-lay trenching Rock placement Method Plough Fall-pipe Speed 300 m/hr 20,000 T/day Scope 72.4 km 125 locations (+79 spot gravel locations) Volume 6.2 m 3 /m (448,390 m 3 ) 518,479 m 3 Duration 10 days 49 days Spill 2% (6467 T) 5-16 kg/s <0.5% (1372T) Parameters Sediment Sediment kg/s Weather Normal, winter, summer Normal, winter, summer

9 4 This report contains a brief description of the seabed intervention works that form the basis for the scenarios the works include both post-lay trenching and rock placement. The modelling is carried out for one pipeline, and it is assumed that the impact from seabed intervention works for the other pipeline is similar or less to the pipeline that is modelled. Seabed interventions for line B is used for the modelling. A full description of the seabed intervention works (construction scenarios) is found in /3/. The interrelationship between this report and the related background documents is illustrated in Figure 1-4. Numerical modelling: Methodology and assumptions /2/ The fundamental assumptions and methodology common for Finland, Sweden and Denmark Numerical modelling: Overview of scenarios /3/ Full description of scenarios in Finland, Sweden and Denmark This Report -Brief summary of above reports -Results Figure 1-4: Interrelation between this report and background documents.

10 5 2. SEDIMENT CHARACTERISTICS This section presents an analysis of the sediment samples and the model input for the seabed intervention works planned in Swedish EEZ. The characterisation of sediment to be spilled in Sweden is based on sediment classification maps from the Geological Survey of Sweden (Sveriges geologiska undersökning SGU), /5/. The classes applied in this context are: 1. Mud, clay and gyttja; 2. Fine sand to pebbles; 3. Clay of the Baltic Ice Lake; 4. Glacial deposits; 5. Mixed sediments. Each sediment class is characterised on the basis of sediment distribution analyses of samples within each of the classified areas. For example, all grain size distributions within areas classified as gyttja, fine sand to pebbles are grouped in one class and a characteristic grain size distribution is estimated. The characteristic grain size distributions are shown on Figure 2-1. For full details on the metrology and the detailed estimation, please see /2/. Figure 2-1: Average values for SGU sediment types. Vertical lines are the mean values from Table 2-1. The grain size distributions are divided in six (6) different particle fractions, which will be used in the modelling: very fine sand ( mm), coarse silt ( mm), medium silt ( mm), fine silt ( mm), very fine silt ( mm) and clay (<0.004 mm). For each of the SGU sediment types the amount (percentage) of sediment within each fraction is determined on the basis of the curves shown in Figure 2-1. The sediment types are characterised by these percentages as e.g. type 1 mud, clay and gyttja contains 46% within the clay fraction and 7% within the fine sand fraction, while type 2 fine sand to pebbles contains 3% within the clay fraction and 16% within the fine sand fraction. The full description of the percentage of the particle fractions for each sediment type can be found in /2/. The coarser sediment fractions (coarser than mm) are not taken into consideration in this context because they will settle in proximity to the seabed intervention works and therefore will not influence the environment outside the immediate work area.

11 6 Table 2-1 shows the grain size ranges for each of the fractions used in the modelling. The representative logarithmic mean grain sizes are also shown in the table. Settling velocities are estimated for each fraction in /2/ on the basis of average water properties for the Baltic Proper. Settling velocities are also given in Table 2-1. Table 2-1: Grain size range Sediment spill class Lower grain size limit (mm) Upper grain size limit (mm) Mean (ln) grain size within range (mm) Settling velocity (m/s) Very fine sand Coarse silt Medium silt Fine silt Very fine silt Clay The water content and content of dry matter have been estimated in /2/. The results are given in Table 2-2. For full details, please see /2/. Table 2-2: Average water/dry content Sweden,/1/ Sediment type Dry content (%) Water content (%) Mud, clay and gyttja Fine sand to pebbles Clay of the Baltic Ice Lake Glacial deposits - - Mixed sediments - - 1) Estimated based on experience as water content in sample results was considered underestimated. 2.1 Trenching locations Figure 2-2 depicts the trenching sections and the corresponding sediment types. The numbers from 1 to 10 above the lines in the figure refers to trenching section 1-10 (TR1-TR10) referred to in Table 2-3. The numbers below the lines refer to the numbering of trenching sections received from NSP2 of which six sections are in Swedish waters. Each overall trenching section is split up to minor sections for use in the modelling on basis of the sediment types along the overall section. The trenching sections TR1 - TR5 used in the modelling is one continuous line but is this way split up into five different trenching sections based on the sediment types.

12 7 Figure 2-2: Numbering of trenching sections and sediment classification map. The sediment characteristics for the 10 trenching sections are described in Table 2-3. Table 2-3: Trenching sections and sediment classification. Trenching section Length (m) TR C3 SGU sediment type Clay of the Baltic Ice Lake Detailed description Clay of the Baltic Ice Lake, the Yoldia Sea and the Ancylus Lake TR S2 Fine sand to pebbles Coarse aleurite ( mm) TR G4 Glacial deposits (till) Glacial deposits (till) TR S2 Fine sand to pebbles Coarse aleurite ( mm) TR C3 TR S2 Clay of the Baltic Ice Lake Clay of the Baltic Ice Lake Clay of the Baltic Ice Lake, the Yoldia Sea and the Ancylus Lake Clay of the Baltic Ice Lake, the Yoldia Sea and the Ancylus Lake TR S2 Fine sand to pebbles Coarse aleurite ( mm) TR S2 Fine sand to pebbles Coarse aleurite ( mm) TR S2 Fine sand to pebbles Coarse aleurite ( mm) TR S2 Fine sand to pebbles Coarse aleurite ( mm) For each trenching section (source), the resulting spill rates for the six particle fractions are defined as per Table 2-4.

13 8 Table 2-4: Trenching calculated spill rates per sediment fraction in kg/s. Source ID contains sediment codes as given in Table 2-2. Source ID Very fine sand (kg/s) Coarse silt (kg/s) Medium silt (kg/s) Fine silt (kg/s) Very fine silt (kg/s) Clay (kg/s) Total fines (kg/s) TR TR TR TR TR TR TR TR TR TR The spill is assumed to be confined to a height of 5 m above the seabed based on considerations of the plough size used for trenching, /4/. Assuming a trenching speed of 300 m/h, trenching operations will cover a period of 10 days (240 hours). This does not include any time for relocation of the equipment, which is considered conservative. The trenching amount is assumed 6.2 m 3 /m. Spill rates are calculated on basis of trenching speed [m 3 /s], density of the specific sediment type [kg/m 3 ], the spill percent (2%), the dry matter content in the specific sediment type and the proportion of the fraction in the specific sediment type, /2/. 2.2 Rock placement locations Figure 2-3 depicts the rock placement locations and corresponding sediment types, and Figure 2-4 shows the spot gravel sections and corresponding sediment types. For the spot gravel sections it is assumed that the total volume will be divided into equal rock berms of 1250 m 3. This leads to 18 berms for the 22,852 m 3 for section 1, 35 berms for the 43,601 m 3 for section 2, 16 berms for the m 3 for section 3, 1 berm for sections 4-7 and 6 berms for the 7,218 m 3 for section 8. In Figure 2-4, the sections are hence shown in red while the berm number is shown in black.

14 9 Figure 2-3: Locations for rock placement and sediment classification map. Figure 2-4: Locations for spot gravel and sediment classification map. For each rock placement location (source) the distribution between the six sediment fractions are defined as per Table 2-5.

15 10 Table 2-5: Rock placement for seabed intervention works - calculated spill rates in kg/s and berm volumes in m 3 Type Berm number F1 F2 F3 F4 F5 F6 Volume berm (m 3 ) B B B B Pre-lay B B B B B B B B B B B B B B B B B B B B Post-lay, 2nd phase B B B B B B B B B B B B B B B B B B

16 11 Type Berm Number F1 F2 F3 F4 F5 F6 Volume berm (m 3 ) B B B B B B B B B B B B B B B B B Post-lay, 2nd phase B B B B B B B B B B B B B B B B B B B B B B

17 12 Type Berm number F1 F2 F3 F4 F5 F6 Volume berm (m 3 ) B B B B B B B B B B B B B Post-lay, 3rd phase B B B B B B B B B B B B B B B B B B B B Crossings B B B B B From generic scenario B

18 13 Table 2-6: Rock placement for spot gravel works calculated spill rates in kg/s and berm volumes in m 3. Volume Berm Spot gravel F1 F2 F3 F4 F5 F6 Berm number section (m 3 ) Berm Spot gravel F1 F2 F3 F4 F5 F6 Volume

19 14 number section Berm (m 3 ) Pipeline crossing Tie-in The spill is assumed to be confined to a height of 2 m above the seabed, /2/. Assuming a rock placement speed of t/d, rock placement operations will cover a period of 49 days (1161 hours). This does not include any time for relocation of the equipment, which is considered conservative.

20 15 Spill rates are calculated on the basis of guidelines in /7/ assuming that 30% of the rock volume contribute to the spilling, a velocity of the falling rock inside a tube of 1.44 m/s and 10% of the total energy will cause a resuspension of sediments.

21 16 3. SPILL SCENARIOS The environmental modelling is carried out using actual hindcast hydrographic scenarios. This means that the modelling is carried out for a real design period as opposed to an artificial situation. The challenge of this approach is defining a representative design period for this purpose. The representative design period should within a short period of time (approximately one month) reflect conditions that are typically seen and that characterise long-term data. The scenario periods are chosen to represent different current conditions (for transport modelling) and different stratification conditions. On the basis of current, salinity and temperature time series from the hydrodynamic model, scenario periods are selected to represent: Summer, typical (calm conditions / weak currents and high stratification); Normal conditions (average currents and stratification for an entire year); Winter, typical (rough conditions / strong currents and low stratification). The terms summer, normal and winter reflect the fact that relatively calm summer conditions result in reduced particle spreading over a small area close to the point where a substance is released, whereas relatively rough winter conditions cause transport further away from the point of release under larger dilution. When a particle (or a quantity of dissolved substance) is released, it is transported by the ambient water. The net transport (linear distance between the start and the end of the trajectory) is in the following chosen to be the measure for characterising the above-mentioned hydrographic scenario periods in relation to transport and spreading. A time series of monitoring data and model data for the locations shown in Figure 3-1 has been analysed for a three-year period starting in autumn Measured current velocities are acquired from acoustic Doppler current profiler (ADCP) measurements from the NSP monitoring program at locations P5 and P6. Time series of modelled current are extracted from the hydrodynamic model positions (P1 to P4) shown in Figure 3-1. Temperature and salinity data are extracted from positions P1 to P6. Figure 3-1: Positions of time series data from the MIKE 3 hydrodynamic model and ADCP measurements. The black line represents the position of NSP2.

22 17 On the basis of time series from the six positions shown on Figure 3-1, three scenario periods are chosen as described above to represent different hydrographic conditions with respect to particle transport and temperature/salinity stratification. The same scenario periods are used throughout the model domain, i.e. the same periods are used in the EIAs of all countries. On the basis of evaluations of accumulated frequency diagrams for particle transport distances and evaluations of isopleth plots for salinity and temperature stratifications, the following scenario periods are chosen: Normal conditions April 2010: Represents average current conditions with average particle transport capacity and average temperature and salinity stratification. Calm conditions (summer) June 2010: Represents calm current conditions with little particle transport capacity and relatively strong temperature and salinity stratification. Rough conditions (winter) November 2010: Represents relatively strong current conditions with high particle transport capacity and relatively low temperature and salinity stratification (but without ice coverage). Further details about the choice of periods can be found in the modelling basis report, /2/. The hydrographic forcing (current fields) is simulated by a calibrated MIKE 3 hydrodynamic (HD) model. For detailed information on the set-up and calibration of the hydrodynamic model, see /4/.

23 18 4. MODEL RESULTS This chapter presents the results of the modelling of the seabed intervention works. The results are presented as two-dimensional maps. The height of the sediment release is modelled in the simulations as 2 m above the seabed for rock placement and 5 m above the seabed for trenching. Due to the location of the release and because sediment is settling through the water column, the highest sediment concentrations are found near the seabed. Therefore all results related to suspended sediment are based on an average of the lower 10 m of the water column. The results for the concentrations of suspended sediments are shown in relation to different threshold concentrations. The thresholds of 5, 10 and 25 mg /l are used based on biological/ecotoxikological thresholds values. Considerations have been given to different organisms when choosing the thresholds. In literature however, fish is the receptor with the lowest thresholds for suspended sediment which has been used; 5mg / l have been found to affect cod eggs ability to flow (after 96 hours), 10 mg / l is a usual threshold value used for the avoidance behavior of fish and 25 mg / l is a common threshold used for impacts of clams and salmon. The maps show the following parameters: The maximum concentration of suspended sediment occurring under the entire simulation period. The maximum concentration is not exceeded at any time during the seabed intervention works. Duration of exceedance of 5, 10 and 25 mg/l. This is the accumulated period of time during which the concentration of suspended material exceeds 5, 10 and 25 mg/l during either trenching or rock placement. The duration is expressed in hours. Durations are not shown on maps for 25 mg/l, because the areas are small and not clearly visible on a map. The maximum duration of 5, 10 and 25 mg/l is shown in a table in the results summary. Sedimentation, which is expressed as g/m 2. The corresponding thickness depends on the density, which again is dependent on the consolidation of the material. Considering fluffy sediment with a dry matter content of 100 kg/m 3 means that a 1 mm thickness corresponds to a sedimentation of 100 g/m 2. A higher degree of consolidation (consequently higher density) corresponds to a thinner layer thickness for the same sedimentation, e.g. 100 g/m 2. The results for trenching are presented in Figure 4-1 to Figure 4-12 in section 4.1, while the results for rock placement are presented in Figure 4-13 to Figure 4-18 in section 4.2. The figures presenting the results are listed in Table 4-1. Table 4-1: Overview of modelling results Seabed intervention work Normal Summer Winter Trenching Rock placem ent Maximum concentration of suspended sediment (mg/l) Figure 4-1 Figure 4-2 Figure 4-3 Duration (hours) of exceeding threshold concentration 5 mg/l Figure 4-4 Figure 4-5 Figure 4-6 Duration (hours)of exceeding threshold concentration 10 mg/l Figure 4-7 Figure 4-8 Figure 4-9 Sedimentation (g/m 2 ) Figure 4-10 Figure 4-11 Figure 4-12 Maximum concentration of suspended sediment (mg/l) Figure 4-13 Figure 4-14 Figure 4-15 Duration (hours) of exceeding threshold concentration 5 mg/l N/A 1 N/A 1 N/A 1

24 19 Duration (hours) of exceeding threshold concentration 10 mg/l N/A 1 N/A 1 N/A 1 Sedimentation (g/m 2 ) Figure 4-16 Figure 4-17 Figure Concentrations are only exceeded in very small areas, which are not clearly visible when plotted on a map. None of the small areas are located within a protected area. Therefore the plots are omitted. 4.1 Trenching Figure 4-1: Maximum concentration of suspended sediment for trenching under normal hydrographic conditions. Figure 4-1 shows the highest concentrations observed during the trenching operations under normal conditions.

25 20 Figure 4-2: Maximum concentration of suspended sediment for trenching under typical summer conditions. Figure 4-2 shows the highest concentrations observed during the trenching operations under typical summer conditions.

26 21 Figure 4-3: Maximum concentration of suspended sediment for trenching under typical winter conditions. Figure 4-3 shows the highest concentrations observed during the trenching operations under typical winter conditions.

27 22 Figure 4-4: Duration of exceeding 5 mg/l for trenching under normal hydrographic conditions. Figure 4-4 shows the duration for which the concentration threshold of 5 mg/l is exceeded during the trenching operations under normal conditions.

28 23 Figure 4-5: Duration of exceeding 5 mg/l for trenching under typical summer conditions. Figure 4-5 shows the duration for which the concentration threshold of 5 mg/l is exceeded during the trenching operations under typical summer conditions.

29 24 Figure 4-6: Duration of exceeding 5 mg/l for trenching under typical winter conditions. Figure 4-6 shows the duration for which the concentration threshold of 5 mg/l is exceeded during the trenching operations under typical winter conditions.

30 25 Figure 4-7: Duration of exceeding 10 mg/l for trenching under normal hydrographic conditions. Figure 4-7 shows the duration for which the concentration threshold of 10 mg/l is exceeded during the trenching operations under normal conditions.

31 26 Figure 4-8: Duration of exceeding 10 mg/l for trenching under typical summer conditions. Figure 4-8 shows the duration for which the concentration threshold of 10 mg/l is exceeded during the trenching operations under typical summer conditions.

32 27 Figure 4-9: Duration of exceeding 10 mg/l for trenching under typical winter conditions. Figure 4-9 shows the duration for which the concentration threshold of 10 mg/l is exceeded during the trenching operations under typical winter conditions.

33 28 Figure 4-10: Sedimentation of released material due to trenching under normal conditions. Figure 4-10 shows sedimentation after the last time step of the simulation under normal conditions.

34 29 Figure 4-11: Sedimentation of released material due to trenching under typical summer conditions. Figure 4-11 shows sedimentation after the last time step of the simulation under typical summer conditions.

35 30 Figure 4-12: Sedimentation of released material due to trenching under typical winter conditions. Figure 4-12 shows sedimentation after the last time step of the simulation under typical winter conditions.

36 Rock placement Figure 4-13: Maximum concentration of suspended sediment for rock placement under normal hydrographic conditions. Figure 4-13 shows the highest concentrations observed during the rock placement operations under normal conditions in the northern area with rock placement operations shown with a red square in the overview map. This is the area with the largest impact from the rock placement operations, and concentrations are generally lower or equal in the areas longer towards south where rock placement is undertaken (shown with black squares).

37 32 Figure 4-14: Maximum concentration of suspended sediment for rock placement under typical summer conditions. Figure 4-14 shows the highest concentrations observed during the rock placement operations under typical summer conditions in the northern area with rock placement operations shown with a red square in the overview map. This is the area with the largest impact from the rock placement operations, and concentrations are generally lower or equal in the areas longer towards south where rock placement is undertaken (shown with black squares).

38 33 Figure 4-15: Maximum concentration of suspended sediment for rock placement under typical winter conditions. Figure 4-15 shows the highest concentrations observed during the rock placement operations under typical winter conditions in the northern area with rock placement operations shown with a red square in the overview map. This is the area with the largest impact from the rock placement operations, and concentrations are generally lower or equal in the areas longer towards south where rock placement is undertaken (shown with black squares).

39 34 Figure 4-16: Sedimentation of released material due to rock placement under normal conditions. Figure 4-16 shows sedimentation after the last time step of the simulation under normal conditions in the northern area with rock placement operations shown with a square in the overview map. This is the area with the largest impact from the rock placement operations, and sedimentation is generally lower or equal in the areas longer towards south where rock placement is also undertaken.

40 35 Figure 4-17: Sedimentation of released material due to rock placement under typical summer conditions. Figure 4-17 shows sedimentation after the last time step of the simulation under typical summer conditions in the northern area with rock placement operations shown with a square in the overview map. This is the area with the largest impact from the rock placement operations, and sedimentation is generally lower or equal in the areas longer towards south where rock placement is also undertaken.

41 36 Figure 4-18: Sedimentation of released material due to rock placement under typical winter conditions. Figure 4-18 shows sedimentation after the last time step of the simulation under typical winter conditions in the northern area with rock placement operations shown with a square in the overview map. This is the area with the largest impact from the rock placement operations, and sedimentation is generally lower or equal in the areas longer towards south where rock placement is also undertaken.

42 37 5. SUMMARY OF RESULTS This section presents a summary of the modelling results for the trenching and rock placement simulations. The summary contains: Areas where concentrations of 5 mg/l, 10 mg/l and 25 mg/l are exceeded. Maximum duration of exceedance of 5 mg/l, 10 mg/l and 25 mg/l. Areas where sedimentation of 10, 100, 200, 1000 and 1500 g/m 2 are exceeded. Maximum concentration (mg/l) at specific distances from the pipelines. Maximum sedimentation (g/m2) at specific distances from the pipelines. The values presented are overall maximum values, based on conservative volumes for seabed intervention works, covering all three hydrographic scenarios normal, summer and winter. This means that for each period the largest value of the three scenarios has been used. The corresponding tables for the individual hydrographic scenarios are presented in Appendix 1. Table 5-1: Size of areas where threshold concentrations are exceeded Seabed intervention works maximum of hydrographic scenarios Route section Suspended sediment Area with concentration > 5 mg/l > 10 mg/l > 25 mg/l km tonnes km 2 km 2 km 2 Trenching Rock placement 125 locations (+79 spot gravel locations) <0.02 Total SE The smallest grid size (modelling setup) have an area of km 2 Table 5-2: Maximum duration of exceeding threshold concentrations Seabed intervention works maximum of hydrographic scenarios Route section Suspended sediment Max duration with concentration > 5 mg/l > 10 mg/l > 25 mg/l km tonnes hours hours hours Trenching Rock placement 125 locations (+79 spot gravel locations) <0.5 The smallest grid size (modelling setup) have an area of km 2

43 38 Table 5-3: Size of areas where sedimentation values are exceeded Seabed intervention works maximum of hydrographic scenarios Route section Suspended sediment Area with sedimentation > > 10 > 100 > 200 g/m 2 g/m 2 g/m g/m 2 > 1500 g/m 2 km tonnes km 2 km 2 km 2 km 2 km 2 Trenching <0.02 <0.02 Rock placement 125 locations (+79 spot gravel locations) <0.02 Total SE <0.06 <0.04 The smallest grid size (modelling setup) have an area of km 2 Table 5-4: Maximum concentration in specific distances from pipelines Seabed intervention works maximum of hydrographic scenarios Route section Suspended sediment Max concentration in specific distances from pipelines 200 m 500 m 1000 m Km tonnes mg/l mg/l mg/l Trenching Rock placement 125 locations (+79 spot gravel locations) The smallest grid size (modelling setup) have an area of km 2 Table 5-5: Maximum sedimentation in specific distances from pipelines Seabed intervention works maximum of hydrographic scenarios Route section Suspended sediment Max sedimentation in specific distances from pipelines 200 m 500 m 1000 m Km tonnes g/m 2 g/m 2 g/m 2 Trenching Rock placement 125 locations (+79 spot gravel locations) The smallest grid size (modelling setup) have an area of km 2

44 39 6. CONCLUSIONS The trenching scenarios show areas with maximum concentrations of suspended sediment above 5 mg/l, 10 mg/l and also 25 mg/l, depending on the hydrographic conditions and based on conservative volumes for seabed intervention works. For the trenching scenarios for average and summer conditions, the areas of impact are quite close to the pipeline route. However, for the winter conditions the sediment spreads to a larger area away from the vicinity of the pipeline route. The extent of the area over which the sediment is spread has been calculated and summarised in Table 5-1 for the three critical threshold concentrations. From Table 5-1 it is obvious that the trenching works during the winter period will have the largest impact due to high concentrations and large spreading of the sediments. Sedimentation is limited to the area very close to the pipeline route. For the rock placement scenarios, the maximum concentration of suspended sediment in a distance of 200 m from the pipeline is 12 mg/l, see Table 5-4. As shown in Figure 4-13 to Figure 4-15 and in Table 5-1 concentrations above 10 mg/l are limited to a very small area and only found right on the pipeline route. Sedimentation is at a maximum 0.8 kg/m 2 at a distance of 200 m from the pipeline route after the end of the trenching scenarios. After the rock placement simulations sedimentation is not exceeding 1.1 kg/m 2 at any location. The corresponding thickness depends on the density, which again is dependent on the consolidation of the material. Considering fluffy sediment with a dry matter content of 100 kg/m 3 a 1 mm thickness corresponds to sedimentation of 100 g/m 2. A higher degree of consolidation (consequently higher density) corresponds to a thinner layer thickness for the same sedimentation, e.g. 100 g/m 2. Comparing the results to the modelling performed in connection with the NSP project, the areas where a concentration of 10 mg/l is exceeded is larger, especially for the winter scenario where the area is 134 km 2 against only 70 km 2 in NSP. However, the duration of exceedance of 10 mg/l is generally lower than for the NSP. The larger area is mainly caused by a more detailed approach in the NSP2 modelling, where sediment characteristics are described in larger detail and the current field is described in larger detail. This means that in the NSP2 modelling the fine sediment fractions are described in more detail and with a larger range of settling velocities. Furthermore, the more detailed current field will tend to describe the large currents better and thereby also increasing the re-suspension of already settled material in the modelling. All this may bring concentrations above 10 mg/l to larger distances than seen in the NSP modelling. When comparing to NSP measurements, very low concentrations were seen during the monitoring campaign. This should be seen as a consequence of the specific hydrographic conditions under which the works was carried out, whereas the larger concentrations in the modelling is a consequence of the conservative input data and due to the modelling aiming at describing some worst case hydrographic scenarios. Also the duration of large concentrations should be considered as the concentration of e.g. 10 mg/l is only exceeded for a very short time at each location which limits the effect and the possibility for caching the highest concentrations during monitoring.

45 40 7. REFERENCES /1/ Nord Stream, 2007, Seabed sediment and fauna investigation, Nord Stream Environmental Baseline Survey in the Swedish EEZ, Contractor: Geological Survey of Sweden. ENV_S_BL_SED_IN_2007 /2/ Nord Stream 2. Numerical Modelling: Methodology and assumptions. Ramboll, August Doc. no. W-PE-EIA-POF-MEM EN-02 /3/ Nord Stream 2. Numerical Modelling: Overview of Scenarios. Ramboll, September Doc. no. W-PE-EIA-POF-MEM EN-02 /4/ Nord Stream 2 Project in the Baltic, Hydrographic basis for spill assessment, Data from enhanced DHI hydrographic model, The Rock Manual. The use of rock in hydraulic engineering (2nd edition) /5/ Western and central Baltic sea compiled from: -Repecka, M. & Cato, I., 1999: "Bottom Sediment Map of the Central Baltic Sea". Geological Survey of Lithuania (LGT) Series of Marine Geological Maps No. 1 and Geological Survey of Sweden (SGU). Series of Geological Maps Ba No. 54. /6/ Curt Fredén (editor), 1994: "Berg och jord". Sveriges National atlas, SNA Förlag, Stockholm, 208 pp. /7/ CIRIA, CUR and CETMEF, 2007, The Rock Manual - The use of rock in hydraulic engineering, C683, CIRIA, London. /8/ Nord Stream 2. Input data for EIA 1, Sweden. Saipem, , Rev. 2. /9/ Nord Stream 2. Input data for initiation of EIA Doc. No. W-EN-OFP-POF- MEM-800-EIA001EN-01

46 41 APPENDIX 1 RESULT TABLES FOR NORMAL, SUMMER AND WINTER HYDROGRAPHY

47 42 Normal hydrography This section presents a summary of the modelling results for normal hydrography Seabed intervention works normal conditions Route section Suspended sediment Area with concentration > 5 mg/l > 10 mg/l > 25 mg/l km tonnes km 2 km 2 km 2 Trenching Rock placement 125 locations (+79 spot gravel locations) <0.02 Total SE The smallest grid size (modelling setup) have an area of km 2 Seabed intervention works normal conditions Route section Suspended sediment Max duration with concentration > 5 mg/l > 10 mg/l > 25 mg/l km tonnes hours hours hours Trenching Rock placement 125 locations (+79 spot gravel locations) The smallest grid size (modelling setup) have an area of km <0.5

48 43 Seabed intervention works normal conditions Route section Suspended sediment Area with sedimentation > > 10 > 100 > 200 g/m 2 g/m 2 g/m g/m 2 > 1500 g/m 2 km tonnes km 2 km 2 km 2 km 2 km 2 Trenching <0.02 <0.02 Rock placement 125 locations (+79 spot gravel locations) <0.02 Total SE <0.02 The smallest grid size (modelling setup) have an area of km 2 Seabed intervention works normal conditions Route section Suspended sediment Max concentration in specific distances from pipelines 200 m 500 m 1000 m Km tonnes mg/l mg/l mg/l Trenching Rock placement 125 locations (+79 spot gravel locations) The smallest grid size (modelling setup) have an area of km Seabed intervention works normal conditions Route section Suspended sediment Max sedimentation in specific distances from pipelines 200 m 500 m 1000 m Km tonnes g/m 2 g/m 2 g/m 2 Trenching Rock placement 125 locations (+79 spot gravel locations) The smallest grid size (modelling setup) have an area of km

49 44 Summer hydrography This section presents a summary of the modelling results for summer hydrography. Seabed intervention works summer conditions Route section Suspended sediment Area with concentration > 5 mg/l > 10 mg/l > 25 mg/l km tonnes km 2 km 2 km 2 Trenching Rock placement 125 locations (+79 spot gravel locations) <0.02 Total SE The smallest grid size (modelling setup) have an area of km 2 Seabed intervention works summer conditions Route section Suspended sediment Max duration with concentration > 5 mg/l > 10 mg/l > 25 mg/l km tonnes hours hours hours Trenching Rock placement 125 locations (+79 spot gravel locations) <0.5 The smallest grid size (modelling setup) have an area of km 2

50 45 Seabed intervention works summer conditions Route section Suspended sediment Area with sedimentation > > 10 > 100 > 200 g/m 2 g/m 2 g/m g/m 2 > 1500 g/m 2 km tonnes km 2 km 2 km 2 km 2 km 2 Trenching <0.02 <0.02 Rock placement 125 locations (+79 spot gravel locations) <0.02 <0.02 Total SE <0.02 <0.02 The smallest grid size (modelling setup) have an area of km 2 Seabed intervention works summer conditions Route section Suspended sediment Max concentration in specific distances from pipelines 200 m 500 m 1000 m Km tonnes mg/l mg/l mg/l Trenching Rock placement 125 locations (+79 spot gravel locations) The smallest grid size (modelling setup) have an area of km Seabed intervention works summer conditions Route section Suspended sediment Max sedimentation in specific distances from pipelines 200 m 500 m 1000 m Km tonnes g/m 2 g/m 2 g/m 2 Trenching Rock placement 125 locations (+79 spot gravel locations) The smallest grid size (modelling setup) have an area of km

51 46 Winter hydrography This section presents a summary of the modelling results for winter hydrography. Seabed intervention works winter conditions Route section Suspended sediment Area with concentration > 5 mg/l > 10 mg/l > 25 mg/l km tonnes km 2 km 2 km 2 Trenching Rock placement 125 locations (+79 spot gravel locations) <0.02 Total SE The smallest grid size (modelling setup) have an area of km 2 Seabed intervention works winter conditions Route section Suspended sediment Max duration with concentration > 5 mg/l > 10 mg/l > 25 mg/l km tonnes hours hours hours Trenching Rock placement 125 locations (+79 spot gravel locations) The smallest grid size (modelling setup) have an area of km 2

52 47 Seabed intervention works winter conditions Route section Suspended sediment Area with sedimentation > > 10 > 100 > 200 g/m 2 g/m 2 g/m g/m 2 > 1500 g/m 2 km tonnes km 2 km 2 km 2 km 2 km 2 Trenching <0.02 <0.02 Rock placement 125 locations (+79 spot gravel locations) <0.02 <0.02 Total SE <0.02 <0.02 The smallest grid size (modelling setup) have an area of km 2 Seabed intervention works winter conditions Route section Suspended sediment Max concentration in specific distances from pipelines 200 m 500 m 1000 m Km tonnes mg/l mg/l mg/l Trenching Rock placement 125 locations (+79 spot gravel locations) The smallest grid size (modelling setup) have an area of km Seabed intervention works winter conditions Route section Suspended sediment Max sedimentation in specific distances from pipelines 200 m 500 m 1000 m Km tonnes g/m 2 g/m 2 g/m 2 Trenching Rock placement 125 locations (+79 spot gravel locations) The smallest grid size (modelling setup) have an area of km

Regional management of underwater noise made possible: an achievement of the BIAS project

Regional management of underwater noise made possible: an achievement of the BIAS project Regional management of underwater noise made possible: an achievement of the BIAS project T. Folegot, D. Clorennec, Quiet-Oceans, Brest A. Nikolopoulos, F. Fyhr, Aquabiota Water Research, Stockholm M.

More information

Introductory remarks

Introductory remarks Introductory remarks This document is a draft of a permit for Gaz System to construct a natural gas pipeline on the Danish continental shelf in the Baltic Sea. It should be emphasised that it has not yet

More information

8.4.9 Advice May 2013 ECOREGION STOCK

8.4.9 Advice May 2013 ECOREGION STOCK 8.4.9 Advice May 2013 ECOREGION STOCK Baltic Sea Herring in Subdivision 30 (Bothnian Sea) Advice for 2014 ICES advises on the basis of the MSY approach that catches in 2014 should be no more than 138 345

More information

Baltic Marine Environment Protection Commission

Baltic Marine Environment Protection Commission Baltic Marine Environment Protection Commission Heads of Delegation Helsinki, Finland, 14-15 June 2018 HOD 54-2018 Document title Revised proposal for a regional monitoring sub-program of continuous noise

More information

AmyMarie Accardi-Dey (The Louis Berger Group, Inc.)

AmyMarie Accardi-Dey (The Louis Berger Group, Inc.) Correspondence Date: January 27, 2010 To: From: Re: Scott Thompson (The Louis Berger Group, Inc.) AmyMarie Accardi-Dey (The Louis Berger Group, Inc.) Details on Net Suspended Sediment Estimation by Plume-Width

More information

Seabed preparation on Edradour Glenlivet project campaigns

Seabed preparation on Edradour Glenlivet project campaigns PAU, FRANCE 5-7 APRIL 2016 Seabed preparation on Edradour Glenlivet project 2014-2015 campaigns Loic Delebecque, TOTAL E&P EDRADOUR GLENLIVET PROJECT Edradour and Glenlivet are gas condensate fields located

More information

GCM mapping Vildbjerg - HydroGeophysics Group - Aarhus University

GCM mapping Vildbjerg - HydroGeophysics Group - Aarhus University GCM mapping Vildbjerg - HydroGeophysics Group - Aarhus University GCM mapping Vildbjerg Report number 06-06-2017, June 2017 Indholdsfortegnelse 1. Project information... 2 2. DUALEM-421s... 3 2.1 Setup

More information

Three-dimensional investigation of buried structures with multi-transducer parametric sub-bottom profiler as part of hydrographical applications

Three-dimensional investigation of buried structures with multi-transducer parametric sub-bottom profiler as part of hydrographical applications Three-dimensional investigation of buried structures with multi-transducer parametric sub-bottom profiler as part Jens LOWAG, Germany, Dr. Jens WUNDERLICH, Germany, Peter HUEMBS, Germany Key words: parametric,

More information

Mound Study Project Cape Fear, North Carolina Pre-Deployment Calibration Of OBS and ADV Sensors June/July 2001 EHI Project No

Mound Study Project Cape Fear, North Carolina Pre-Deployment Calibration Of OBS and ADV Sensors June/July 2001 EHI Project No Mound Study Project Cape Fear, North Carolina Pre-Deployment Calibration Of OBS and ADV Sensors June/July 21 EHI Project No. 6.21 February 23 Final VIMS Report CHSD-23-5 Prepared for Evans-Hamilton, Inc

More information

ICES Special Request Advice Barents Sea and Norwegian Sea Ecoregions Published 10 March 2016 Version 2; 13 May 2016

ICES Special Request Advice Barents Sea and Norwegian Sea Ecoregions Published 10 March 2016 Version 2; 13 May 2016 ICES Special Request Advice Barents Sea and Norwegian Sea Ecoregions Published 10 March 2016 Version 2; 13 May 2016 3.4.1 * Norway/Russia request for evaluation of harvest control rules for Northeast Arctic

More information

Roberts Bank Terminal 2 Project Field Studies Information Sheet

Roberts Bank Terminal 2 Project Field Studies Information Sheet July 2012 Port Metro Vancouver is continuing field studies in July as part of ongoing environmental and technical work for the proposed Roberts Bank Terminal 2 Project. Roberts Bank Terminal 2 Project

More information

7. Consider the following common offset gather collected with GPR.

7. Consider the following common offset gather collected with GPR. Questions: GPR 1. Which of the following statements is incorrect when considering skin depth in GPR a. Skin depth is the distance at which the signal amplitude has decreased by a factor of 1/e b. Skin

More information

QUANTITY SURVEYS. Introduction

QUANTITY SURVEYS. Introduction QUANTITY SURVEYS Introduction In engineering surveying, we often consider a route (road, sewer pipeline, channel, etc.) from three distinct perspectives. The plan view of route location is the same as

More information

ICCP Retrofit Challenges for an Offshore Jacket Complex

ICCP Retrofit Challenges for an Offshore Jacket Complex Paper No. 6012 ICCP Retrofit Challenges for an Offshore Jacket Complex Christophe Baeté, CP Manager Elsyca n.v. Vaartdijk 3/603, 3018 Wijgmaal, Belgium christophe.baete@elsyca.com ABSTRACT An offshore

More information

Investigation programme for the baseline survey of the OWF WINDANKER

Investigation programme for the baseline survey of the OWF WINDANKER Investigation programme in accordance with the Standards of Environmental Impact Assessments (StUK 3) of BSH concerning the baseline surveys for the offshore wind farm: Windanker December 2012 Client:

More information

Boggabri Coal Mine. Environmental Noise Monitoring October Prepared for Boggabri Coal Operations Pty Ltd

Boggabri Coal Mine. Environmental Noise Monitoring October Prepared for Boggabri Coal Operations Pty Ltd Boggabri Coal Mine Environmental Noise Monitoring October 2017 Prepared for Boggabri Coal Operations Pty Ltd Page i Boggabri Coal Mine Environmental Noise Monitoring October 2017 Reference: Report date:

More information

IMO. Resolution A.977(24) Adopted on 1 December 2005 (Agenda item 9) SHIPS ROUTEING

IMO. Resolution A.977(24) Adopted on 1 December 2005 (Agenda item 9) SHIPS ROUTEING INTERNATIONAL MARITIME ORGANIZATION E IMO ASSEMBLY 24th session Agenda item 9 A 24/Res.977 27 January 2006 Original: ENGLISH Resolution A.977(24) Adopted on 1 December 2005 (Agenda item 9) SHIPS ROUTEING

More information

22 Status of the breeding population of Great Cormorants in Sweden in 2012

22 Status of the breeding population of Great Cormorants in Sweden in 2012 22 Status of the breeding population of Great Cormorants in Sweden in 212 Henri Engström 1 & Anders Wirdheim 2 1 Swedish Ornithological Society, (Uppsala University) Norbyvägen 18d, 752 36 Uppsala, Sweden.

More information

Noise monitoring during drilling operations Lower Stumble Well Site Balcombe, West Sussex

Noise monitoring during drilling operations Lower Stumble Well Site Balcombe, West Sussex Noise monitoring during drilling operations Lower Stumble Well Site Balcombe, West Sussex Report ref. PJ3159/13181 Date August 13 Issued to Cuadrilla Resources Limited Issued by Peter Jackson MSc MIOA

More information

Technical Note. Noise reducing properties of crash barriers. Performed for WillumTech. AV 1217/11 Project no.: A Page 1 of 19 incl.

Technical Note. Noise reducing properties of crash barriers. Performed for WillumTech. AV 1217/11 Project no.: A Page 1 of 19 incl. Technical Note Noise reducing properties of crash barriers Performed for WillumTech Project no.: A581500 Page 1 of 19 incl. 1 annex 6 October 2011 DELTA Venlighedsvej 4 2970 Hørsholm Denmark Tel. +45 72

More information

Defense and Maritime Solutions

Defense and Maritime Solutions Defense and Maritime Solutions Automatic Contact Detection in Side-Scan Sonar Data Rebecca T. Quintal Data Processing Center Manager John Shannon Byrne Software Manager Deborah M. Smith Lead Hydrographer

More information

Free-Spanning Pipelines in the Digital Age Nicholas Nielsen & Olivier Royet

Free-Spanning Pipelines in the Digital Age Nicholas Nielsen & Olivier Royet Free-Spanning Pipelines in the Digital Age Nicholas Nielsen & Olivier Royet 1 SAFER, SMARTER, GREENER 1 2 3 4 Context What are free spans? Current approach How do we estimate fatigue life? New science

More information

Ashton Coal. Environmental Noise Monitoring May Prepared for Ashton Coal Operations Pty Ltd

Ashton Coal. Environmental Noise Monitoring May Prepared for Ashton Coal Operations Pty Ltd Ashton Coal Environmental Noise Monitoring May 2018 Prepared for Ashton Coal Operations Pty Ltd Page i Ashton Coal Environmental Noise Monitoring May 2018 Reference: Report date: 5 June 2018 Prepared for

More information

Mirmorax Subsea Technologies -Oil in Water Measurements for subsea applications Eivind Gransæther CEO. Mirmorax AS

Mirmorax Subsea Technologies -Oil in Water Measurements for subsea applications Eivind Gransæther CEO. Mirmorax AS Mirmorax Subsea Technologies -Oil in Water Measurements for subsea applications Eivind Gransæther CEO p1 Mirmorax AS Short about Mirmorax Established 2009 to become the preferred and trusted supplier of

More information

ROUTEING OF SHIPS, SHIP REPORTING AND RELATED MATTERS. New traffic separation schemes and two-way routes in Norra Kvarken

ROUTEING OF SHIPS, SHIP REPORTING AND RELATED MATTERS. New traffic separation schemes and two-way routes in Norra Kvarken E SUB-COMMITTEE ON SAFETY OF NAVIGATION 57th session Agenda item 3 NAV 57/3/7 11 March 2011 Original: ENGLISH ROUTEING OF SHIPS, SHIP REPORTING AND RELATED MATTERS New traffic separation schemes and two-way

More information

Assessing Tidal Energy Resource

Assessing Tidal Energy Resource Assessing Tidal Energy Resource Frank Biskup, Bilbao Marine Energy Week, Bilbao 1 Tidal Farm 2 Tidal Site ADCP with 10 min average 3 Tidal Site ADCP with high resolution of 2 Hz 4 Tidal Site ADCP Measurement

More information

Assured Monitoring Group

Assured Monitoring Group Assured Monitoring Group YARRANLEA SOLAR FARM NOISE & VIBRATION IMPACT ASSESSMENT JANUARY 2017 I3 CONSULTING PTY LTD Project ID. 10734 R_1 DATE OF RELEASE: 15/02/2017 Table 1: Document approval Name Position

More information

NY BILD. PEBERHOLM and its surrounding waters

NY BILD. PEBERHOLM and its surrounding waters NY BILD PEBERHOLM and its surrounding waters Peberholm, around the time just after the opening of the Bridge. Photo: Søren Madsen Peberholm year 2014. Photo: Martin Kielland Peberholm The artificial island

More information

Roberts Bank Terminal 2 Project Field Studies Information Sheet

Roberts Bank Terminal 2 Project Field Studies Information Sheet January 2013 Port Metro Vancouver is continuing field studies in January as part of ongoing environmental and technical work for the proposed. The is a proposed new multi berth container terminal which

More information

SWAN LAKE INTEGRATED WATERSHED MANAGEMENT PLAN SURFACE WATER HYDROLOGY REPORT 1

SWAN LAKE INTEGRATED WATERSHED MANAGEMENT PLAN SURFACE WATER HYDROLOGY REPORT 1 SWAN LAKE INTEGRATED WATERSHED MANAGEMENT PLAN SURFACE WATER HYDROLOGY REPORT 1 1. General Description Figure 1 provides a map of the Swan Lake Watershed. The watershed is characterized by two major parallel

More information

Coverage Metric for Acoustic Receiver Evaluation and Track Generation

Coverage Metric for Acoustic Receiver Evaluation and Track Generation Coverage Metric for Acoustic Receiver Evaluation and Track Generation Steven M. Dennis Naval Research Laboratory Stennis Space Center, MS 39529, USA Abstract-Acoustic receiver track generation has been

More information

Boggabri Coal Mine. Environmental Noise Monitoring June Prepared for Boggabri Coal Operations Pty Ltd

Boggabri Coal Mine. Environmental Noise Monitoring June Prepared for Boggabri Coal Operations Pty Ltd Boggabri Coal Mine Environmental Noise Monitoring June 2017 Prepared for Boggabri Coal Operations Pty Ltd Page i Boggabri Coal Mine Environmental Noise Monitoring June 2017 Reference: Report date: 5 July

More information

Alexander Hughes. Management Survey. Volume 4

Alexander Hughes. Management Survey. Volume 4 Alexander Hughes Management Survey Volume 4 2014 Østergade 1, 2 nd 1100 Copenhagen K Denmark Tel : +45 70 22 43 70 E-mail : copenhagen@alexanderhughes.com www.alexanderhughes.com Alexander Hughes Denmark

More information

JOHANN CATTY CETIM, 52 Avenue Félix Louat, Senlis Cedex, France. What is the effect of operating conditions on the result of the testing?

JOHANN CATTY CETIM, 52 Avenue Félix Louat, Senlis Cedex, France. What is the effect of operating conditions on the result of the testing? ACOUSTIC EMISSION TESTING - DEFINING A NEW STANDARD OF ACOUSTIC EMISSION TESTING FOR PRESSURE VESSELS Part 2: Performance analysis of different configurations of real case testing and recommendations for

More information

DS-CD-01 Rev 3

DS-CD-01 Rev 3 Coalescers OVERVIEW There are numerous industrial applications requiring effective physical separation of two process liquids. HAT has developed a number of AlphaSEP Coalescers to handle a wide range of

More information

Developments in Electromagnetic Inspection Methods II

Developments in Electromagnetic Inspection Methods II 6th International Conference on NDE in Relation to Structural Integrity for Nuclear and Pressurized Components October 2007, Budapest, Hungary For more papers of this publication click: www.ndt.net/search/docs.php3?mainsource=70

More information

Annex I Content, format and structure of annual reports for exploration under contract for polymetallic nodules

Annex I Content, format and structure of annual reports for exploration under contract for polymetallic nodules Annex I Content, format and structure of annual reports for exploration under contract for polymetallic nodules I, Executive summary 1. The Contractor is requested to provide a summary of major achievements

More information

Publishing date: 23/07/2015 Document title: We appreciate your feedback. Share this document

Publishing date: 23/07/2015 Document title: We appreciate your feedback. Share this document Publishing date: 23/07/2015 Document title: We appreciate your feedback Please click on the icon to take a 5 online survey and provide your feedback about this document Share this document REPORT ON UNIT

More information

Integrated Marine Data and Information System

Integrated Marine Data and Information System imardis Integrated Marine Data and Information System David Mills Graham Worley, Thomas Prebble, Gwyn Roberts, Cathy Blakey http://www.imardis.org Introduction Lessons learnt in SEACAMS 1 Collaborative

More information

Questions and Answers

Questions and Answers EKS Technology Development Program EKR-DT Process Process Optimisation Program COSIA Presentation Questions and Answers May 30, 2017 This document addresses some of outstanding questions that are related

More information

International Journal of Research in Computer and Communication Technology, Vol 3, Issue 1, January- 2014

International Journal of Research in Computer and Communication Technology, Vol 3, Issue 1, January- 2014 A Study on channel modeling of underwater acoustic communication K. Saraswathi, Netravathi K A., Dr. S Ravishankar Asst Prof, Professor RV College of Engineering, Bangalore ksaraswathi@rvce.edu.in, netravathika@rvce.edu.in,

More information

FLOOD ESTIMATE FROM POSSIBLE DAM BREAK SCENARIO OF SUN KOSI LAND SLIDE DAM, NEPAL. O. P. GUPTA Director Central Water Commission

FLOOD ESTIMATE FROM POSSIBLE DAM BREAK SCENARIO OF SUN KOSI LAND SLIDE DAM, NEPAL. O. P. GUPTA Director Central Water Commission FLOOD ESTIMATE FROM POSSIBLE DAM BREAK SCENARIO OF SUN KOSI LAND SLIDE DAM, NEPAL by O. P. GUPTA Director Central Water Commission Introduction Landslide dams are natural phenomenon that poses a major

More information

BALD EAGLE NIGHT ROOST SURVEYS

BALD EAGLE NIGHT ROOST SURVEYS SETTLEMENT AGREEMENT ARTICLE 512 BALD EAGLE NIGHT ROOST SURVEYS SEASON ONE RESULTS: NOVEMBER 2009 FEBRUARY 2010 BAKER RIVER HYDROELECTRIC PROJECT FERC No. 2150 Puget Sound Energy Bellevue, Washington May

More information

INTEGRITY AND CONTINUITY ANALYSIS FROM GPS JULY TO SEPTEMBER 2016 QUARTERLY REPORT

INTEGRITY AND CONTINUITY ANALYSIS FROM GPS JULY TO SEPTEMBER 2016 QUARTERLY REPORT INTEGRITY AND CONTINUITY ANALYSIS FROM GPS JULY TO SEPTEMBER 2016 QUARTERLY REPORT Name Responsibility Date Signature Prepared by M Pattinson (NSL) 07/10/16 Checked by L Banfield (NSL) 07/10/16 Authorised

More information

The Normal Baseline. Dick Gent Law of the Sea Division UK Hydrographic Office

The Normal Baseline. Dick Gent Law of the Sea Division UK Hydrographic Office The Normal Baseline Dick Gent Law of the Sea Division UK Hydrographic Office 2 The normal baseline for measuring the breadth of the territorial sea is the low water line along the coast as marked on large

More information

Herring (Clupea harengus) in divisions 7.a South of N, 7.g h, and 7.j k (Irish Sea, Celtic Sea, and southwest of Ireland)

Herring (Clupea harengus) in divisions 7.a South of N, 7.g h, and 7.j k (Irish Sea, Celtic Sea, and southwest of Ireland) ICES Advice on fishing opportunities, catch, and effort Celtic Seas Ecoregion Published 30 June 2017 DOI: 10.17895/ices.pub.3132 Herring (Clupea harengus) in divisions 7.a South of 52 30 N, 7.g h, and

More information

Wintering Corn Buntings

Wintering Corn Buntings Wintering Corn Buntings Title Wintering Corn Bunting 1992/93 Description and Summary of Results The Corn Bunting Emberiza calandra is one of a number of farmland birds which showed a marked decline in

More information

Boggabri Coal Mine. Environmental Noise Monitoring August Prepared for Boggabri Coal Operations Pty Ltd

Boggabri Coal Mine. Environmental Noise Monitoring August Prepared for Boggabri Coal Operations Pty Ltd Boggabri Coal Mine Environmental Noise Monitoring August 2018 Prepared for Boggabri Coal Operations Pty Ltd Page i Boggabri Coal Mine Environmental Noise Monitoring August 2018 Reference: Report date:

More information

VICINITY MAP LOCATION MAP GRAPHIC SCALES

VICINITY MAP LOCATION MAP GRAPHIC SCALES VICINITY MAP LOCATION MAP GI-01 LEGEND TABLE OF CONTENTS CONSTRUCTION SEQUENCE NOTES GENERAL NOTES SEDIMENTATION & EROSION CONTROL ABBREVIATIONS GI-02 M P P P P M EXISTING HYDRAULIC PROFILE AND DEMOLITION

More information

Cruise Report R/V Oceania, AREX 2006

Cruise Report R/V Oceania, AREX 2006 Powstańców Warszawy 55, PL - 81-712 Sopot, P.O. Box 68 January 20, 2007 Cruise Report R/V Oceania, AREX 2006 Ship: R/V Oceania Cruise: AREX 2006 Dates: 08.06.2006 19.07.2006 Port Calls: Gdansk (Poland)

More information

Seabed and wind farm interaction. A Research Program. B. Mutlu Sumer DTU Mekanik

Seabed and wind farm interaction. A Research Program. B. Mutlu Sumer DTU Mekanik Seabed and wind farm interaction. A Research Program B. Mutlu Sumer DTU Mekanik Will tell you about a current research program on Interaction between seabed and offshore wind farms Start off with A small

More information

ICES CM 2003/R:08. Vida ŽILIUKIENĖ

ICES CM 2003/R:08. Vida ŽILIUKIENĖ ICES CM 3/R:8 Distribution and size structure of smelt (Osmerus eperlanus L.) larvae in the Lithuanian part of the Curonian Lagoon during their migration to the Baltic Sea Vida ŽILIUKIENĖ Institute of

More information

Harmonisation of the Vertical Reference Systems. of nautical charts around the Baltic Sea

Harmonisation of the Vertical Reference Systems. of nautical charts around the Baltic Sea Harmonisation of the Vertical Reference Systems of nautical charts around the Baltic Sea (29 May 2007) Introduction The BSHC 11 th Conference decided that the current status of vertical reference systems

More information

Pre-Construction, Construction, and Post- Construction Monitoring Report for Greenland Meadows for July October 2010

Pre-Construction, Construction, and Post- Construction Monitoring Report for Greenland Meadows for July October 2010 Pre-Construction, Construction, and Post- Construction Monitoring Report for Greenland Meadows for July 2007- October 200 Prepared by The University of New Hampshire Stormwater Center December 200 Pre-Construction,

More information

Liddell Coal Operations

Liddell Coal Operations Liddell Coal Operations Environmental Noise Monitoring February 2018 Prepared for Liddell Coal Operations Pty Ltd Page i Liddell Coal Operations Environmental Noise Monitoring February 2018 Reference:

More information

Baltic Marine Environment Protection Commission

Baltic Marine Environment Protection Commission Baltic Marine Environment Protection Commission Ad hoc Seal Expert Group Berlin, Germany, 2-4 December 2015 SEAL 9-2015, 5-1 Document title Development of a HELCOM database for seals Code 5-1 Category

More information

Development of an improved flood frequency curve applying Bulletin 17B guidelines

Development of an improved flood frequency curve applying Bulletin 17B guidelines 21st International Congress on Modelling and Simulation, Gold Coast, Australia, 29 Nov to 4 Dec 2015 www.mssanz.org.au/modsim2015 Development of an improved flood frequency curve applying Bulletin 17B

More information

clarify the roles of the Department and minerals industry in consultation; and

clarify the roles of the Department and minerals industry in consultation; and Procedures for Crown Consultation with Aboriginal Communities on Mineral Exploration Mineral Resources Division, Manitoba Science, Technology, Energy and Mines The Government of Manitoba recognizes it

More information

Southeast O ahu (SEO) Regional Sediment Management (RSM) Workshop #2 June 1, 2005 Ko olau Golf Course

Southeast O ahu (SEO) Regional Sediment Management (RSM) Workshop #2 June 1, 2005 Ko olau Golf Course Southeast O ahu (SEO) Regional Sediment Management (RSM) Workshop #2 June 1, 2005 Ko olau Golf Course 1 June 2005 Southeast O ahu RSM Workshop #2 1 Agenda Welcome and Introductions Mr. Sam Lemmo Summary

More information

Chapter 3¾Examination and Description of Soils SOIL SURVEY MANUAL 73. Soil Color

Chapter 3¾Examination and Description of Soils SOIL SURVEY MANUAL 73. Soil Color Chapter 3¾Examination and Description of Soils SOIL SURVEY MANUAL 73 Soil Color Elements of soil color descriptions are the color name, the Munsell notation, the water state, and the physical state: "brown

More information

Acoustic propagation affected by environmental parameters in coastal waters

Acoustic propagation affected by environmental parameters in coastal waters Indian Journal of Geo-Marine Sciences Vol. 43(1), January 2014, pp. 17-21 Acoustic propagation affected by environmental parameters in coastal waters Sanjana M C, G Latha, A Thirunavukkarasu & G Raguraman

More information

Propagation Modelling White Paper

Propagation Modelling White Paper Propagation Modelling White Paper Propagation Modelling White Paper Abstract: One of the key determinants of a radio link s received signal strength, whether wanted or interfering, is how the radio waves

More information

Outcome of HELCOM HOLAS II Workshop on integrated hazardous substances assessment (HOLAS II HZ WS )

Outcome of HELCOM HOLAS II Workshop on integrated hazardous substances assessment (HOLAS II HZ WS ) Baltic Marine Environment Protection Commission Project for the development of the second holistic assessment of the Baltic Sea HOLAS II Workshop on integrated hazardous substances assessment Helsinki,

More information

Diagnosis of Operating Mine Dewatering Wells Efficiency through Groundwater Modelling

Diagnosis of Operating Mine Dewatering Wells Efficiency through Groundwater Modelling Diagnosis of Operating Mine Dewatering Wells Efficiency through Groundwater Modelling Houcyne El Idrysy1, Lenar Sultanov2 SRK Consulting (UK) Ltd, Cardiff, United Kingdom, hidrysy@srk.co.uk SRK Consulting

More information

Emerging Subsea Networks

Emerging Subsea Networks FIBRE-TO-PLATFORM CONNECTIVITY, WORKING IN THE 500m ZONE Andrew Lloyd (Global Marine Systems Limited) Email: andrew.lloyd@globalmarinesystems.com Global Marine Systems Ltd, New Saxon House, 1 Winsford

More information

Estimating Fish Densities from Single Fish Echo Traces

Estimating Fish Densities from Single Fish Echo Traces The Open Ocean Engineering Journal, 2009, 2, 17-32 17 Estimating Fish Densities from Single Fish Echo Traces Open Access Magnar Aksland * University of Bergen, Department of Biology, P.O. Box 7800, N-5020

More information

GEOLOGICAL INVESTIGATIONS

GEOLOGICAL INVESTIGATIONS GEOLOGICAL INVESTIGATIONS Aggregate Investigation Greenwood Aggregates Company Limited Part Lots 30 to 32, Concession 4, E.H.S. Town of Mono County of Dufferin Box #122, 38 Alpine Drive, Moonstone, Ontario,

More information

Measurement and Modelling of Underwater Noise from Pile Driving

Measurement and Modelling of Underwater Noise from Pile Driving Proceedings of 20 th International Congress on Acoustics, ICA 2010 23-27 August 2010, Sydney, Australia Measurement and Modelling of Underwater Noise from Pile Driving Alec J Duncan, Robert D McCauley,

More information

Well Control Contingency Plan Guidance Note (version 2) 02 December 2015

Well Control Contingency Plan Guidance Note (version 2) 02 December 2015 Well Control Contingency Plan Guidance Note (version 2) 02 December 2015 Prepared by Maritime NZ Contents Introduction... 3 Purpose... 3 Definitions... 4 Contents of a Well Control Contingency Plan (WCCP)...

More information

Capelin (Mallotus villosus) in subareas 1 and 2 (Northeast Arctic), excluding Division 2.a west of 5 W (Barents Sea capelin)

Capelin (Mallotus villosus) in subareas 1 and 2 (Northeast Arctic), excluding Division 2.a west of 5 W (Barents Sea capelin) ICES Advice on fishing opportunities, catch, and effort Barents Sea and Norwegian Sea Ecoregions Published 12 October 2017 DOI: 10.17895/ices.pub.3272 Capelin (Mallotus villosus) in subareas 1 and 2 (Northeast

More information

Underwater noise survey during impact piling to construct the Burbo Bank Offshore Wind Farm.

Underwater noise survey during impact piling to construct the Burbo Bank Offshore Wind Farm. Project Title Project Number Investigators Company Report Number Underwater noise and offshore wind farms. COWRIE ACO-04-2 S J Parvin and J R Nedwell Subacoustech Ltd. 726R0103 Date 25 th October 6 Underwater

More information

How we build reality. Company Overview. Scanning in Explosive Environments

How we build reality. Company Overview. Scanning in Explosive Environments How we build reality Scanning in Explosive Environments Case Study Offshore Company Overview Z+F is one of the world leading manufacturers of phase based laser scanners. Our strengths lie in the powerful

More information

Policy Research Corporation

Policy Research Corporation Policy Research Corporation SOUND SOLUTIONS BASED ON SCIENTIFIC RESEARCH The role of Maritime Clusters to enhance the strength and development of maritime sectors Country report Denmark INTRODUCTION TO

More information

Moisture measurements with time domain reflectometer (TDR)

Moisture measurements with time domain reflectometer (TDR) 10th International Symposium on District Heating and Cooling September 3-5, 2006 Tuesday, 5 September 2006 Sektion 8 a Heat distribution optimisation of existing solutions Moisture measurements with time

More information

MSI SELF ASSESSMENT - Baltic Sea Sub-area (BALTICO) of Navarea I, Submitted by Sweden

MSI SELF ASSESSMENT - Baltic Sea Sub-area (BALTICO) of Navarea I, Submitted by Sweden IHO Commission on the Promulgation of Radio Navigational Warnings (CPRNW) International Hydrographic Bureau, Monaco 11 14 Sep 2007 CPRNW 9-3.2.1-I-subarea Origin: Sweden MSI SELF ASSESSMENT - Baltic Sea

More information

Feedback from the Swedish Orienteering Federation regarding the final version of the ISOM 201x

Feedback from the Swedish Orienteering Federation regarding the final version of the ISOM 201x 14 January 2016 Feedback from the Swedish Orienteering Federation regarding the final version of the ISOM 201x General comments If not commented, we agree to the proposed definitions and changes. Three

More information

Fiber length of pulp by projection. 1. Scope and summary

Fiber length of pulp by projection. 1. Scope and summary T 232 cm-01 SUGGESTED METHOD 1953 REVISED 1968 CLASSICAL METHOD 1985 REVISED 2001 2001 TAPPI The information and data contained in this document were prepared by a technical committee of the Association.

More information

Predicting the temperature and strength development within cemented paste backfill structures

Predicting the temperature and strength development within cemented paste backfill structures Paste 10 R.J. Jewell and A.B. Fourie (eds) 10 Australian Centre for Geomechanics, Perth, ISBN 978-0-9806154-0-1 https://papers.acg.uwa.edu.au/p/1063_11_fall/ Predicting the temperature and strength development

More information

INTEGRATED COVERAGE MEASUREMENT SAMPLE DESIGN FOR CENSUS 2000 DRESS REHEARSAL

INTEGRATED COVERAGE MEASUREMENT SAMPLE DESIGN FOR CENSUS 2000 DRESS REHEARSAL INTEGRATED COVERAGE MEASUREMENT SAMPLE DESIGN FOR CENSUS 2000 DRESS REHEARSAL David McGrath, Robert Sands, U.S. Bureau of the Census David McGrath, Room 2121, Bldg 2, Bureau of the Census, Washington,

More information

18th World Conference on Non-destructive Testing, April 2012, Durban, South Africa

18th World Conference on Non-destructive Testing, April 2012, Durban, South Africa 18th World Conference on Non-destructive Testing, 16-20 April 20, Durban, South Africa Guided Wave Testing for touch point corrosion David ALLEYNE Guided Ultrasonics Ltd, London, UK; Phone: +44 2082329102;

More information

GCM mapping Gedved - HydroGeophysics Group - Aarhus University

GCM mapping Gedved - HydroGeophysics Group - Aarhus University GCM mapping Gedved - HydroGeophysics Group - Aarhus University GCM mapping Gedved Report number 23-06-2017, June 2017 1. INDHOLDSFORTEGNELSE 1. Indholdsfortegnelse... 1 2. Project information... 2 3. DUALEM-421s...

More information

SKIN FRICTION OF PILES COATED WITH BITUMINOUS COATS Makarand G. Khare 1 and Shailesh R. Gandhi 2

SKIN FRICTION OF PILES COATED WITH BITUMINOUS COATS Makarand G. Khare 1 and Shailesh R. Gandhi 2 SKIN FRICTION OF PILES COATED WITH BITUMINOUS COATS Makarand G. Khare 1 and Shailesh R. Gandhi 2 1 Ph.D Student, Dept. of Civil Engineering, Indian Institute of Tech. Madras, Chennai, India-600036 Email:

More information

INTEGRITY AND CONTINUITY ANALYSIS FROM GPS JANUARY TO MARCH 2017 QUARTERLY REPORT

INTEGRITY AND CONTINUITY ANALYSIS FROM GPS JANUARY TO MARCH 2017 QUARTERLY REPORT INTEGRITY AND CONTINUITY ANALYSIS FROM GPS JANUARY TO MARCH 2017 QUARTERLY REPORT Name Responsibility Date Signature Prepared by M Pattinson (NSL) 11/04/17 Checked by L Banfield (NSL) 11/04/17 Authorised

More information

West Linn-Wilsonville School District Primary (Grades K-5) Science/Health Curriculum

West Linn-Wilsonville School District Primary (Grades K-5) Science/Health Curriculum Essential Questions Concepts providing focus for student learning How does it move and/or change? (physical science including chemistry) How is it similar to and different from me? (life science and health)

More information

OWA Floating LiDAR Roadmap Supplementary Guidance Note

OWA Floating LiDAR Roadmap Supplementary Guidance Note OWA Floating LiDAR Roadmap Supplementary Guidance Note List of abbreviations Abbreviation FLS IEA FL Recommended Practices KPI OEM OPDACA OSACA OWA OWA FL Roadmap Meaning Floating LiDAR System IEA Wind

More information

NLGA INTERPRETATIONS

NLGA INTERPRETATIONS PART NATIONAL LUMBER GRADES AUTHORITY (NLGA) INTERPRETATIONS 1.0 GENERAL NLGA INTERPRETATIONS Unless otherwise specifi ed the following NLGA Interpretations shall apply to all portions of the NLGA Grade

More information

Non-Technical Summary of the SEA Report Draft on the Spatial Offshore Grid Plan for the German Exclusive Economic Zone of the North Sea 2016/2017

Non-Technical Summary of the SEA Report Draft on the Spatial Offshore Grid Plan for the German Exclusive Economic Zone of the North Sea 2016/2017 Non-Technical Summary of the SEA Report Draft on the Spatial Offshore Grid Plan for the German Exclusive Economic Zone of the North Sea unofficial translation Hamburg, June 2017 Content 1 Subject and Purpose...

More information

ABSTRACT INTRODUCTION. Immediate Displacement of the Seabed During Subsea Rock Installation (SRI) 3

ABSTRACT INTRODUCTION. Immediate Displacement of the Seabed During Subsea Rock Installation (SRI) 3 Immediate Displacement of the Seabed During Subsea Rock Installation (SRI) 3 RENÉ VISSER AND JOOP VAN DER MEER IMMEDIATE DISPLACEMENT OF THE SEABED DURING SUBSEA ROCK INSTALLATION (SRI) ABSTRACT The integrity

More information

Using Norwegian competence from oil and gas subsea operations towards the development of ocean mining operations

Using Norwegian competence from oil and gas subsea operations towards the development of ocean mining operations Using Norwegian competence from oil and gas subsea operations towards the development of ocean mining operations Yoshinori Miura, Jens Laugesen, Øyvind Fjukmoen, Lucy Brooks, Karsten Hagenah, Tor Jensen

More information

BASELINE NOISE MONITORING SURVEY

BASELINE NOISE MONITORING SURVEY t m s environment ltd TMS Environment Ltd 53 Broomhill Drive Tallaght Dublin 24 Phone: +353-1-4626710 Fax: +353-1-4626714 Web: www.tmsenv.ie BASELINE NOISE MONITORING SURVEY UNIVERSITY COLLEGE DUBLIN Report

More information

Thermodynamic Modelling of Subsea Heat Exchangers

Thermodynamic Modelling of Subsea Heat Exchangers Thermodynamic Modelling of Subsea Heat Exchangers Kimberley Chieng Eric May, Zachary Aman School of Mechanical and Chemical Engineering Andrew Lee Steere CEED Client: Woodside Energy Limited Abstract The

More information

Technical Note: Analysis of Offshore Pipeline Allowable Free Span Length. Introduction

Technical Note: Analysis of Offshore Pipeline Allowable Free Span Length. Introduction Technical Note: Analysis of Offshore Pipeline Allowable Free Span ength Downloaded from ijce.iust.ac.ir at :3 IRST on Sunday January 3th 9 Abbas Yeganeh Bakhtiary, Abbas Ghaheri and Reza Valipour 3 Assitant

More information

Liddell Coal Operations

Liddell Coal Operations Liddell Coal Operations Environmental Noise Monitoring May 2018 Prepared for Liddell Coal Operations Pty Ltd Page i Liddell Coal Operations Environmental Noise Monitoring May 2018 Reference: Report date:

More information

INCIDENTS CLASSIFICATION SCALE METHODOLOGY

INCIDENTS CLASSIFICATION SCALE METHODOLOGY 8 May 2014 WORKING GROUP INCIDENT CLASSIFICATION UNDER SYSTEM OPERATIONS COMMITTEE Contents Revisions... 5 References and Related documents... 5 Change request... 5 1. Overview... 6 1.1 Objectives and

More information

DEFORMATION CAMERA

DEFORMATION CAMERA DEFORMATION CAMERA Automated optical deformation analysis for long-term monitoring of instabilities in rock and ice based on high-resolution images and sophisticated image processing methods. GEOPREVENT

More information

Shallow water limits to hydro-acoustic communication baud rate and bit energy efficiency

Shallow water limits to hydro-acoustic communication baud rate and bit energy efficiency Shallow water limits to hydro-acoustic communication baud rate and bit energy efficiency Nicholas Andronis L3 Oceania Fremantle, Curtin University, ABSTRACT Shallow water hydro-acoustic communication channels

More information

HIGH-FREQUENCY ACOUSTIC PROPAGATION IN THE PRESENCE OF OCEANOGRAPHIC VARIABILITY

HIGH-FREQUENCY ACOUSTIC PROPAGATION IN THE PRESENCE OF OCEANOGRAPHIC VARIABILITY HIGH-FREQUENCY ACOUSTIC PROPAGATION IN THE PRESENCE OF OCEANOGRAPHIC VARIABILITY M. BADIEY, K. WONG, AND L. LENAIN College of Marine Studies, University of Delaware Newark DE 19716, USA E-mail: Badiey@udel.edu

More information

Beyond the Code - Subsea Cable Stability

Beyond the Code - Subsea Cable Stability Beyond the Code - Subsea Cable Stability All-Energy Conference, Aberdeen 2012 Chas Spradbery Outline Company Overview Why this presentation could save you Code limitations What actually happens Going Beyond

More information

Research Activities Plan. Appendix K Magnetic Fields from Submarine Cables

Research Activities Plan. Appendix K Magnetic Fields from Submarine Cables VOWTAP Research Activities Plan Appendix K Magnetic Fields from Submarine Cables December 2013 Electrical Engineering and Computer Science Practice Virginia Offshore Wind Technology Advancement Project

More information

Irina SMIRNOVA, Alexandra RUSANOVA

Irina SMIRNOVA, Alexandra RUSANOVA Irina SMIRNOVA, Alexandra RUSANOVA Monitoring of Landscape Changes Due to Petroleum Fields Exploitation, Construction of Oil Pipelines and Oil Terminal in the Northern Part of the Timan-Pechorian Petroleum

More information