Work Package Status Report

Size: px
Start display at page:

Download "Work Package Status Report"

Transcription

1 Work Package Status Report Date: August 2018 Work Package: WP5 Elliptical cavities and cryomodules Author: Pierre Bosland, Roger Ruber, Daniele Sertore, Mike Ellis, Christine Darve 1. Accomplishments by CEA WP05 M-ECCTD Cryomodule: o Cryomodule assembly: The M-ECCTD assembly is complete and the cryomodule is now installed in the test stand. Up to now we could follow the list of operations without any issue. The instrumentation connections have been checked. The 4 doorknobs have been mounted using of the new tooling and the wave guides are now connected to the couplers. 3 of the 4 power couplers have been already commissioned at room temperature with the standard procedure. No outgassing occurred and the duration of the sequence for each coupler was very short, 4 hours (see fig below of cav3). 1

2 The insulating vacuum is now being pumped down. The effect of the different vacuum configuration of the cryomodule of the cavities position is checked as well the cavity frequency shifts. The cooling down of the cold mass is in preparation and will start as soon as the insulating vacuum is pumped.. H-ECCTD: o High beta cavity test at Uppsala University: The cavity package prepared by CEA has been tested successfully at UU during a short period in summer. General conclusions before the test report are: RF power conditioning at warm up to 1.1MW and RF pulse length of 2.3ms done. Cooling down to 2K done. Increase of the cavity field done without big issue, but the large uncertainty of the gradient value measurement doesn t allow a clear conclusion (19MV/m or 13MV/m). Few electron field emission appearing during gradient increase could be easily and quickly processed. The slow tuner behaves as expected (good linearity of 17.3kHz/screw turn, low hysteresis) Tests of the piezo stacks done. Tuning range is as expected. We are waiting for the test report for more details about Lorentz detuning compensation and mechanical modes of the cavity) o High beta prototype cavities: o 4 of the 5 cavities have been sent to ZANON for the final preparation for the tests in vertical cryostat. 2

3 o Cavities 1 and 2 have been delivered to CEA. Cavity 1 is installed in vertical cryostat ready for cooling down and test on W38. o Couplers: Series cryomodules: o The third coupler pair of the pre series has been prepared for the RF processing. The following table summarizes the status of the main procurements for the series production: Vacuum vessels Contract awarded to ACPP, manufacturing of the first unit in progress, delivery expected mid of June Power couplers Coupling boxes for coupler conditioning Thermal shieldings Spaceframe Cold Tuning Systems (mechanical part) Motors for cold tuning systems Cryogenic heat exchanger Magnetic shielding MLI Internal instrumentation Intercavity bellows, coldwarm transitions Cavity supporting systems (tie rods) Cryogenic circuits, diphasic tubes, tubes for rupture disks, coupler bells Contract awarded to PMB, the 6 couplers of the preseries are delivered. Contract awarded to SDMS, all units delivered. Contract awarded to SDMS, first unit delivered middle of March SAT OK. Contract awarded to SDMS, first unit delivered middle of March SAT OK. Contract awarded to YVON BOYER kick-off meeting done in September, manufacturing in progress. Pre series manufacturing in progress. Contract awarded to TSA (PHYTRON), 48 motors received Contract awarded to SDMS, two first units delivered. Contract awarded to MECA MAGNETIC, kick-off meeting done, fabrication in progress. Intermediate FAT with mockup assembly done. Contract awarded to SODITECH, kick off meeting done Contract awarded to SODITECH, kick-off meeting done, manufacturing files validated the 15 th of February, fabrication of the first unit in progress Contract awarded to SDMS, kick-off meeting done Contract awarded to SPG Cryogenic circuits awarded to CRYODIFFUSION Di-phasic tubes awarded to SDMS Ti bellows: offers received 3

4 Cryogenic valves CV01 and CV02 Level sensors Temperature sensors Safety valves Controlled safety valves Rupture disks RF cables RF feedthroughs Pressure transmitters Screws for clean room assembly Vacuum components Contract awarded to VELAN, kick off meeting done, fabrication in progress Contract awarded to CRYOFORUM, all the components received Contract awarded to CRYOFORUM, several batches already delivered Contract awarded to LESER Contract aw<arded to Velan Contract awarded to BS&S Contract awarded to HABIA Contract awarded to MDC Vacuum Call for tender in progress Several contracts awarded Almost all item ordered HV90 purge valves: contract awarded to VAT. Standard pumps and gauges awarded to Pfeiffer Vacuum pumping groups Contract awarded to Cryomodule assembly Contract awarded to B&S 1.1. Accomplishment by UU Hb cavity package test in HNOSS In August we did a 2nd run of the elliptical cavity package. - Cooldown of cryostat and cavity - RF re-conditioning at cold - Measurement Q0 and Lorenz force detuning - test of Polish electronics for cold tuner system 2. Accomplishment by LASA Medium-beta cavity WP05.2 (June to August) Present Status During these months, INFN team visit OTIC for the quality control of sheets foreseen for the 3 rd batch. The inspection was successful and finally we released the delivery of the 148 sheets to INFN. Sheets arrived on July 6 th at LASA and were delivered to DESY July 11 th. DESY completed the scanning of all sheets and only 13 sheets were sent for further analysis. Finally only 3 sheets have geometrical defects and no inclusions have been detected. For the debugging of the DESY VT infrastructures and for the qualification of all VT infrastructures, in accordance with ESS and CEA, the dressed cavity prototype P05 will be used after a retreatment cycle at EZ (cavity sent to EZ in July). Once ready, this cavity will be cold tested at LASA and after at DESY to cross check the two infrastructures. Afterwards, this cavity will be also tested at CEA. 4

5 After the fabrication of the first 3 Half Cells (namely IC_N128; PC_N015, EC_N069) of the series production at EZ, the mechanical and RF measurements (done with Co.Co.De semi-automatic apparatus developed by EZ) checks have been done and the LASA-DMS (Data Management System) based on ALFRESCO was debugged for the managing of the documents between EZ and INFN. The first Terminal Dumb Bell (TD) is produced (namely TD_ICN128_PCN015) using first two IC and PC, to cross check the mechanical and RF measurement behavior after the EB welding process. Since a larger shrinkage than the expected has been measured, further checks on this TD has been done to obtain all necessary info before launching the series production. After some optimization (relative to the EZ production strategy and fabrication tools, and also of the HCs overmetal lengths), the production of the HCs of three types of the first lot (necessary for the production of 6 cavities) was released. All measurements done by EZ have been exchanged between EZ and INFN by using the LASA-DMS system. The HCs for six cavities have been produced and the coupling of HCs to Dumb Bells have been provided to the company. During August, DBs for the first two cavities have been produced. As already reported last month, the construction of the third INFN MB LG prototype (MBLG003) is used to debug, as far as possible, the overall production procedure. During this months, DBs and EGs have been measured after the INFN trimming instruction. The cavity composition has been sent to Zanon in preparation of the cavity welding in September with the new tool that should improve the alignment of the cavity components. As part of the debug process, we have used the LASA-DMS system to import documents and validate them. At LASA, the modifications of our Vertical Insert to accept cavity in series configuration has been completed and the insert has been tested at cold. On the vertical test at DESY, in July INFN team together with DESY team performed the cold RF test of the INFN MBLG002, confirming results obtained at LASA. During the test, the CEA mockup was in the insert to debug the real behavior of the system with a configuration similar to the one that we will have for the series cavities tests. This visit was also used to better clarify the kind of data to be collected by DESY for the qualification test, the outgoing/incoming documents to be prepared, the managing of information exchange between INFN and DESY. After this visit several issues have been clarified, only minor details are still to be completed. In June the Kyocera PUs arrived at LASA. INFN performed the thermal cycling and all vacuum leak tests confirming the expected quality of feedthroughs. EZ checked the dimension of the Ti 2-phase line seamless tube received from CEA, after the cutting operation (July 6 th ). Measurements show thickness variation not negligible while the external diameter is constant and in tolerance. This info have been given to CEA and we had the confirmation that they can be used. Future Progress a) Prototypes (1) Large Grain (LG003) welding, treatments and tuning b) Series Cavities i) Niobium 3 rd batch, deliver to EZ after EDS at DESY. ii) Follow up cavity production start-up process at vendor premises. In particular, further analysis of the measurements of produced HCs and composition instruction for the DBs fabrication. Measurement of EG. Trimming instruction for DBs and EGs 5

6 3. Accomplishment by STFC High-beta cavity WP05.3 Project Management Efforts are ongoing both to increase the team size and to prepare the team organization structure for cavity manufacturing. The CDR charge for the cavities is agreed in principal with ESS, although given the proposed change to STFC drafting the final design drawings this may require revisiting. For STFC this will be a critical point for ESS to confirm the final design, correct drawing revisions, and to ensure that during prototype testing (i.e. CEA s 5 HB cavities and the P01 test at Uppsala) has not identified any issues requiring design change to the cavity. Infrastructure: Control racks for the UHV systems and for offline cryostat insert checks are installed, as well as cable connection panels. Cable installation is ongoing. Cables for cryostat sensors, controls, and vacuum are complete pending final check The first UHV slow pump / slow vent system has completed assembly and is pending leak check. RF rack is progressing with additional cryocooler (coaxial resonator) testing scheduled for October. It is still the STFC target that first tests of the cryostat to cool down, develop processes etc will start at the beginning of October, but this is at risk due to staff availability in September. STFC s current target is to be able to start RF operations on the P02 cavity from 1 st week of November. The first scheduled test is final LLRF validation. SRF cavity measurements are not expected until Jan Cavity & material procurements A formal Kick-off meeting was held with Research Instruments on 4 th Sept, attended by RI, STFC, CEA, and an ESS representative. A lot of progress was made on key issues such as the final diphase line length, helium inlet, manufacturing infrastructure review etc. A follow up meeting is proposed in late September or early October to close remaining issues and to review the quality control requirements in detail. There is some urgency to approve the Acceptance Level 1 mechanical design drawings. This was proposed by STFC to be part of a formal review with ESS, which must be arranged urgently. The most recent official drawing release from ESS/CEA for the HB cavities is Rev E, although the provisionally agreed latest version is actually Rev H. This should be closed formally urgently between ESS, CEA and STFC. RI s proposed schedule is still in accordance with the SRF scheduling meetings, however there is a high level of risk and uncertainty about being able to release manufacture on schedule due to the drawing review process. This schedule shows the first 2 undressed pre-series cavities to be ready for test at DESY in Feb/Mar 2019, and after this testing, then jacket integration at RI, they would be at STFC by ~May ready for final testing. The actual testing would not start until Sept/Oct 2019 after completion of the infrastructure commissioning and benchmarking at STFC. Eddy current scanning has been completed on all of the first three batches of discs shipped to DESY. Batch 4 micrographs were received in late August and are currently being reviewed by STFC. High level discussions have been held with DESY to re-confirm the possibility of testing the pre-series cavities at their facility in ~Feb 2019 and ~April This is not expected 6

7 to have any impact on the medium beta testing schedule providing the interfaces to the cavity are matching with the medium beta (e.g. mechanical frame, valve and antennae positions / angles etc). Slow pump slow vent system assembled ready for leak check in the clean room 4. General See the minutes of the weekly Vidyo interface meetings at: Weekly Fridays meeting action items - ESS/SRF Collaboration Bi-Weekly Fridays meeting - Activities Plan (restricted) Weekly Tuesday meeting action items - ESS/CEA Weekly Tuesdays - TS2 coordination meeting and TS2 CM meeting Weekly Thursdays - ESS Linac Group meeting notes August 7-8: CEA - M-ECCTD and Hb cavity 7

8 5. Issues By CEA: FAT of the modulator scheduled on week 38 delayed by some weeks due to some technical issues. By STFC: STFC commissioning is currently conducted with 1 cavity P02, which means a lot of testing of different parts of the Vertical Test system in series. This extends the schedule due to serial operation and puts a very high risk on the schedule in the event of any incident taking the cavity offline. STFC have been searching for additional cavities to support commissioning but so far have not been able to identify any high-gradient jacketed cavities suitable. We would therefore like to formally request ESS support in identifying ESS-type jacketed cavities which could be available from Q4/2018 or Q1/2019 to help accelerate and de-risk the STFC vertical test facility. This will fundamentally reduce the risks on cavity delivery to ESS/CEA for the High Beta Cryomodules. ESS has proposed / requested that STFC use its cavity supplier to complete the final design drawings. It is anticipated that both the cost and time to create the drawings at RI will be small; however, STFC or RI cannot accept final cavity design responsibility so will need a review and approval with ESS and CEA. This final review could be the proposed CDR, and must be scheduled as soon as possible after RI will have the drawings ready; arranging this formal process is now highly likely to impact delivery and production of cavities. Since the Technical Annex will be changed and the approval of drawings may be delayed having schedule impact, this will need suitable change control approval between ESS and STFC. The CDR charge provisionally agreed with ESS will require some more input from STFC than expected, including potential for final drawing reviews as above. The proposed schedule for CDR is after STFC expect to have the kick-off meeting with the cavity vendor. STFC now propose to use the following strategy: o 1) kick-off meeting using current data package o 2) manufacturer starts preparations for tooling, manufacturing etc o 3) vendor and STFC create final cavity drawings and distribute for approval o 4) ESS CDR: this MUST be held prior to STFC authorizing the cavity vendor to manufacture any cavity Half Cells, End groups or other parts Anticipated production schedule starts component manufacture in Sept/Oct 2018 o 5) After successful CDR, STFC will authorize start of production at the vendor If Cavity Acceptance Criteria are to be changed to include an X-ray radiation limit, this will require a change control request to be produced and to be agreed between STFC and ESS. 8

9 One of the cryogenic engineers assigned as a core team member has resigned and will leave in mid September. The process to recruit a replacement has started, as well as arranging short-term expert cryogenic support to minimize delays in the cryostat commissioning. 6. Current and near Future Variances in Project Plan By STFC The delayed installation and commissioning will now impact delivery dates of cavities; the technical annex milestones in version 1.7 are not achievable and should be re-baselined by change control after the cavity manufacturing kick-off meeting in September. However, STFC s best estimated schedule has been provided and included in the updated ESS s joint SRF schedule v This delivers cavities to ESS (/CEA) ahead of the scheduled High beta CM builds, currently with around 3 months free float. To date, the cavity tender bids & winning bid are both compatible with the schedule referenced above. However, it is likely that the cavity fabrication may be delayed if drawing approval cannot be completed formally urgently. STFC critical path currently includes infrastructure commissioning. Any additional ESS cavities could help accelerate this, for example, MP05 and HP01 which are currently in use by INFN (at DESY) and at Uppsala respectively. If these were available for use by STFC from Q until Q3 2019, the commissioning for STFC s infrastructure could be accelerated and de-risk our delivery schedule of cavities. Final deliveries of Niobium are expected slightly ahead of schedule. STFC is coordinating regularly with DESY to ensure as much as practical a continuous supply of Niobium for their eddy current scanning activity. No impact on the cavity production is currently foreseen. 9

DEVELOPMENTS AND PROGRESS WITH ESS ELLIPTICAL CRYOMODULES AT CEA-SACLAY AND IPN-ORSAY -

DEVELOPMENTS AND PROGRESS WITH ESS ELLIPTICAL CRYOMODULES AT CEA-SACLAY AND IPN-ORSAY - DEVELOPMENTS AND PROGRESS WITH ESS ELLIPTICAL CRYOMODULES AT CEA-SACLAY AND IPN-ORSAY - F. Peauger, C. Arcambal, F. Ardellier, S. Berry, P. Bosland, A. Bouygues, E. Cenni, JP. Charrier, G. Devanz, F. Eozénou,

More information

LARGE SCALE TESTING OF SRF CAVITIES AND MODULES

LARGE SCALE TESTING OF SRF CAVITIES AND MODULES LARGE SCALE TESTING OF SRF CAVITIES AND MODULES Jacek Swierblewski IFJ PAN Krakow IKC for the XFEL Introduction IFJ PAN 2 Institute of Nuclear Physics (IFJ) located in Kraków, Poland was founded in 1955

More information

Design of the 352MHz, beta 0.50, Double- Spoke Cavity for ESS

Design of the 352MHz, beta 0.50, Double- Spoke Cavity for ESS Design of the 352MHz, beta 0.50, Double- Spoke Cavity for ESS Patricia DUCHESNE, Guillaume OLRY Sylvain BRAULT, Sébastien BOUSSON, Patxi DUTHIL, Denis REYNET Institut de Physique Nucléaire d Orsay SRF

More information

Mechanical study of the «Saclay piezo tuner» PTS (Piezo Tuning System) P. Bosland, Bo Wu DAPNIA - CEA Saclay. Abstract

Mechanical study of the «Saclay piezo tuner» PTS (Piezo Tuning System) P. Bosland, Bo Wu DAPNIA - CEA Saclay. Abstract SRF Mechanical study of the «Saclay piezo tuner» PTS (Piezo Tuning System) P. Bosland, Bo Wu DAPNIA - CEA Saclay Abstract This report presents the piezo tuner developed at Saclay in the framework of CARE/SRF.

More information

ESS RF Development at Uppsala University. Roger Ruber for the FREIA team Uppsala University

ESS RF Development at Uppsala University. Roger Ruber for the FREIA team Uppsala University ESS RF Development at Uppsala University Roger Ruber for the FREIA team Uppsala University ESS-UU Collaboration 2009 ESS and UU start discussion on 704 MHz RF development proposal for ESS dedicated test

More information

PROGRESS IN THE ELLIPTICAL CAVITIES AND CRYOMODULE DEMONSTRATORS FOR THE ESS LINAC

PROGRESS IN THE ELLIPTICAL CAVITIES AND CRYOMODULE DEMONSTRATORS FOR THE ESS LINAC PROGRESS IN THE ELLIPTICAL CAVITIES AND CRYOMODULE DEMONSTRATORS FOR THE ESS LINAC F. Peauger, C. Arcambal, S. Berry, N. Berton, P. Bosland, E. Cenni, J.P. Charrier, G. Devanz, F. Eozenou, F. Gougnaud,

More information

Tuning systems for superconducting cavities at Saclay

Tuning systems for superconducting cavities at Saclay Tuning systems for superconducting cavities at Saclay 1 MACSE: 1990: tuner in LHe bath at 1.8K TTF: 1995 tuner at 1.8K in the insulating vacuum SOLEIL: 1999 tuner at 4 K in the insulating vacuum Super-3HC:

More information

HIGH POWER COUPLER FOR THE TESLA TEST FACILITY

HIGH POWER COUPLER FOR THE TESLA TEST FACILITY Abstract HIGH POWER COUPLER FOR THE TESLA TEST FACILITY W.-D. Moeller * for the TESLA Collaboration, Deutsches Elektronen-Synchrotron DESY, D-22603 Hamburg, Germany The TeV Energy Superconducting Linear

More information

3.9 GHz System (AH1) XFEL WP46

3.9 GHz System (AH1) XFEL WP46 3.9 GHz System (AH1) XFEL WP46 14th European XFEL Machine Advisory Committee Meeting 02 May 2016 Paolo Pierini, INFN & DESY Elmar Vogel, DESY + INFN/DESY contributors PPT version 1 26/04/2016 Outline Status

More information

Status of the European XFEL Accelerator Construction Project. Reinhard Brinkmann, DESY

Status of the European XFEL Accelerator Construction Project. Reinhard Brinkmann, DESY Status of the European XFEL Accelerator Construction Project Reinhard Brinkmann, DESY European XFEL Introduction Some specifications Photon energy 0.3-24 kev Pulse duration ~ 10-100 fs Pulse energy few

More information

Performance of Superconducting Cavities for the European XFEL. Detlef Reschke DESY for the EU-XFEL Accelerator Consortium

Performance of Superconducting Cavities for the European XFEL. Detlef Reschke DESY for the EU-XFEL Accelerator Consortium Performance of Superconducting Cavities for the European XFEL Detlef Reschke DESY for the EU-XFEL Accelerator Consortium Outline 2 European XFEL Linear Accelerator Cavity Production Vertical Acceptance

More information

Tests of the Spoke Cavity RF Source and Cryomodules in Uppsala

Tests of the Spoke Cavity RF Source and Cryomodules in Uppsala FREIA Report 2012/03 October 2012 DEPARTMENT OF PHYSICS AND ASTRONOMY UPPSALA UNIVERSITY Tests of the Spoke Cavity RF Source and Cryomodules in Uppsala ESS TDR Contribution R. Ruber, T. Ekelöf, R.A. Yogi.

More information

INFN- LASA MEDIUM BETA CAVITY PROTOTYPES FOR ESS LINAC

INFN- LASA MEDIUM BETA CAVITY PROTOTYPES FOR ESS LINAC Content from this work may be used under the terms of the CC BY 3. licence ( 217). Any distribution of this work must maintain attribution to the author(s), title of the work, publisher, and DOI. 18th

More information

SNS CRYOMODULE PERFORMANCE*

SNS CRYOMODULE PERFORMANCE* SNS CRYOMODULE PERFORMANCE* J. Preble*, I. E. Campisi, E. Daly, G. K. Davis, J. R. Delayen, M. Drury, C. Grenoble, J. Hogan, L. King, P. Kneisel, J. Mammosser, T. Powers, M. Stirbet, H. Wang, T. Whitlatch,

More information

DEVELOPMENT OF A BETA 0.12, 88 MHZ, QUARTER WAVE RESONATOR AND ITS CRYOMODULE FOR THE SPIRAL2 PROJECT

DEVELOPMENT OF A BETA 0.12, 88 MHZ, QUARTER WAVE RESONATOR AND ITS CRYOMODULE FOR THE SPIRAL2 PROJECT DEVELOPMENT OF A BETA 0.12, 88 MHZ, QUARTER WAVE RESONATOR AND ITS CRYOMODULE FOR THE SPIRAL2 PROJECT G. Olry, J-L. Biarrotte, S. Blivet, S. Bousson, C. Commeaux, C. Joly, T. Junquera, J. Lesrel, E. Roy,

More information

Superconducting 1.3 GHz Cavities for European XFEL

Superconducting 1.3 GHz Cavities for European XFEL Superconducting 1.3 GHz Cavities for European XFEL W. Singer, J. Iversen, A. Matheisen, X. Singer (DESY, Germany) P. Michelato (INFN, Italy) Presented by Waldemar Singer Main issues: preparation phase

More information

High Power Couplers for TTF - FEL

High Power Couplers for TTF - FEL High Power Couplers for TTF - FEL 1. Requirements for High Power Couplers on superconducting Cavities 2. Characteristics of pulsed couplers 3. Standing wave pattern in the coaxial coupler line 4. Advantages

More information

Superconducting RF cavities activities for the MAX project

Superconducting RF cavities activities for the MAX project 1 Superconducting RF cavities activities for the MAX project OECD-NEA TCADS-2 Workshop Nantes, 22 May 2013 Marouan El Yakoubi, CNRS / IPNO 2 Contents 352 MHz spoke Cryomodule design 700 MHz test area 700

More information

RF STATUS OF SUPERCONDUCTING MODULE DEVELOPMENT SUITABLE FOR CW OPERATION: ELBE CRYOSTATS

RF STATUS OF SUPERCONDUCTING MODULE DEVELOPMENT SUITABLE FOR CW OPERATION: ELBE CRYOSTATS RF STATUS OF SUPERCONDUCTING MODULE DEVELOPMENT SUITABLE FOR CW OPERATION: ELBE CRYOSTATS J. Teichert, A. Büchner, H. Büttig, F. Gabriel, P. Michel, K. Möller, U. Lehnert, Ch. Schneider, J. Stephan, A.

More information

Commissioning of the ALICE SRF Systems at Daresbury Laboratory Alan Wheelhouse, ASTeC, STFC Daresbury Laboratory ESLS RF 1 st 2 nd October 2008

Commissioning of the ALICE SRF Systems at Daresbury Laboratory Alan Wheelhouse, ASTeC, STFC Daresbury Laboratory ESLS RF 1 st 2 nd October 2008 Commissioning of the ALICE SRF Systems at Daresbury Laboratory Alan Wheelhouse, ASTeC, STFC Daresbury Laboratory ESLS RF 1 st 2 nd October 2008 Overview ALICE (Accelerators and Lasers In Combined Experiments)

More information

HIGH POWER PULSED TESTS OF A BETA=0.5 5-CELL 704 MHZ SUPERCONDUCTING CAVITY

HIGH POWER PULSED TESTS OF A BETA=0.5 5-CELL 704 MHZ SUPERCONDUCTING CAVITY HIGH POWER PULSED TESTS OF A BETA=0.5 5-CELL 704 MHZ SUPERCONDUCTING CAVITY G. Devanz, D. Braud, M. Desmons, Y. Gasser, E. Jacques, O. Piquet, J. Plouin, J.- P. Poupeau, D. Roudier, P. Sahuquet, CEA-Saclay,

More information

QUARTER WAVE COAXIAL LINE CAVITY FOR NEW DELHI LINAC BOOSTER*

QUARTER WAVE COAXIAL LINE CAVITY FOR NEW DELHI LINAC BOOSTER* QUARTER WAVE COAXIAL LINE CAVITY FOR NEW DELHI LINAC BOOSTER* P.N. Prakash and A.Roy Nuclear Science Centre, P.O.Box 10502, New Delhi 110 067, INDIA and K.W.Shepard Physics Division, Argonne National Laboratory,

More information

Frequency Tuning and RF Systems for the ATLAS Energy Upgrade. Gary P. Zinkann

Frequency Tuning and RF Systems for the ATLAS Energy Upgrade. Gary P. Zinkann Frequency Tuning and RF Systems for the ATLAS Energy Upgrade Outline Overview of the ATLAS Energy Upgrade Description of cavity Tuning method used during cavity construction Description and test results

More information

S. Ghosh On behalf of Linac, IFR, Cryogenics, RF and beam transport group members. Inter University Accelerator Centre New Delhi India

S. Ghosh On behalf of Linac, IFR, Cryogenics, RF and beam transport group members. Inter University Accelerator Centre New Delhi India S. Ghosh On behalf of Linac, IFR, Cryogenics, RF and beam transport group members Inter University Accelerator Centre New Delhi 110067 India Highlights of presentation 1. Introduction to Linear accelerator

More information

SPOKE CRYOMODULES CONCEPTUAL DESIGNS FOR ESS & MYRRHA

SPOKE CRYOMODULES CONCEPTUAL DESIGNS FOR ESS & MYRRHA SPOKE CRYOMODULES CONCEPTUAL DESIGNS FOR ESS & MYRRHA Hervé Saugnac- IPNO SLHIPP-2 - Catania- 3&4 May 2012 ESS 72 MeV Baseline of the Spoke linac: 10 cryomodules, each one containing 2 double Spoke β=0.5

More information

Project X Cavity RF and mechanical design. T. Khabiboulline, FNAL/TD/SRF

Project X Cavity RF and mechanical design. T. Khabiboulline, FNAL/TD/SRF Project X Cavity RF and mechanical design T. Khabiboulline, FNAL/TD/SRF TTC meeting on CW-SRF, 2013 Project X Cavity RF and mechanical design T 1 High ß Low ß 0.5 HWR SSR1 SSR2 0 1 10 100 1 10 3 1 10 4

More information

R.Bachimanchi, IPAC, May 2015, Richmond, VA

R.Bachimanchi, IPAC, May 2015, Richmond, VA 1 new module C100 Cryomodule Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint Fundamental frequency f 0 Accelerating gradient E acc 1497 MHz >

More information

Packaging of Cryogenic Components

Packaging of Cryogenic Components Packaging of Cryogenic Components William J. Schneider Senior Mechanical Engineer Emeritus November 19-23 2007 1 Packaging of Cryogenic Components Day one Introduction and Overview 2 What is important?

More information

THE CRYOGENIC SYSTEM OF TESLA

THE CRYOGENIC SYSTEM OF TESLA THE CRYOGENIC SYSTEM OF TESLA S. Wolff, DESY, Notkestr. 85, 22607 Hamburg, Germany for the TESLA collaboration Abstract TESLA, a 33 km long 500 GeV centre-of-mass energy superconducting linear collider

More information

Vibration studies of a superconducting accelerating

Vibration studies of a superconducting accelerating Vibration studies of a superconducting accelerating module at room temperature and at 4.5 K Ramila Amirikas, Alessandro Bertolini, Wilhelm Bialowons Vibration studies on a Type III cryomodule at room temperature

More information

C100 Cryomodule. Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint

C100 Cryomodule. Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint 1 new module C100 Cryomodule Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint Fundamental frequency f 0 Accelerating gradient E acc 1497 MHz >

More information

HIGH POWER INPUT COUPLERS FOR THE STF BASELINE CAVITY SYSTEM AT KEK

HIGH POWER INPUT COUPLERS FOR THE STF BASELINE CAVITY SYSTEM AT KEK HIGH POWER INPUT COUPLERS FOR THE STF BASELINE CAVITY SYSTEM AT KEK E. Kako #, H. Hayano, S. Noguchi, T. Shishido, K. Watanabe and Y. Yamamoto KEK, Tsukuba, Ibaraki, 305-0801, Japan Abstract An input coupler,

More information

To produce more powerful and high-efficiency particle accelerator, efforts have

To produce more powerful and high-efficiency particle accelerator, efforts have Measuring Unloaded Quality Factor of Superconducting RF Cryomodule Jian Cong Zeng Department of Physics and Astronomy, State University of New York at Geneseo, Geneseo, NY 14454 Elvin Harms, Jr. Accelerator

More information

3.9 GHz work at Fermilab

3.9 GHz work at Fermilab 3.9 GHz work at Fermilab + CKM 13-cell cavity Engineering and designing W.-D. Moeller Desy, MHF-sl Protocol of the meeting about 3 rd harmonic cavities during the TESLA collaboration meeting at DESY on

More information

Cavity development for TESLA

Cavity development for TESLA Cavity development for TESLA Lutz.Lilje@desy.de DESY -FDET- Cavity basics History: Limitations and solutions»material inclusions»weld defects»field emission»increased surface resistance at high field Performance

More information

FREIA Facility for Research Instrumentation and Accelerator Development Infrastructure and Control Architecture

FREIA Facility for Research Instrumentation and Accelerator Development Infrastructure and Control Architecture FREIA Facility for Research Instrumentation and Accelerator Development Infrastructure and Control Architecture Konrad Gajewski 10 September 2013, Uppsala Why FREIA? Several circumstances test stand for

More information

INSTRUMENTATION AND CONTROL SYSTEM FOR THE INTERNATIONAL ERL CRYOMODULE

INSTRUMENTATION AND CONTROL SYSTEM FOR THE INTERNATIONAL ERL CRYOMODULE INSTRUMENTATION AND CONTROL SYSTEM FOR THE INTERNATIONAL ERL CRYOMODULE S. M. Pattalwar, R. Bate, G. Cox, P.A. McIntosh and A. Oates, STFC, Daresbury Laboratory, Warrington, UK Abstract ALICE is a prototype

More information

Motivation: ERL based e linac for LHeC

Motivation: ERL based e linac for LHeC Erk Jensen, for the LHeC team and the RF group ERL 2013, BINP, Novosibirsk, 09 Sep 2013 09 Sep 2013 1 Motivation: ERL based e linac for LHeC ( O. Brünings presentation) NB.: This is a 09 Sep 2013 2 Some

More information

Experience with 3.9 GHz cavity HOM couplers

Experience with 3.9 GHz cavity HOM couplers Cornell University, October 11-13, 2010 Experience with 3.9 GHz cavity HOM couplers T. Khabiboulline, N. Solyak, FNAL. 3.9 GHz cavity general parameters Third harmonic cavity (3.9GHz) was proposed to compensate

More information

XFEL Cryo System. Project X Collaboration Meeting, FNAL September 8-9, 2010 Bernd Petersen DESY MKS (XFEL WP10 & WP13) 1 st stage. Possible extension

XFEL Cryo System. Project X Collaboration Meeting, FNAL September 8-9, 2010 Bernd Petersen DESY MKS (XFEL WP10 & WP13) 1 st stage. Possible extension XFEL Cryo System Possible extension 1 st stage Project X Collaboration Meeting, FNAL September 8-9, 2010 (XFEL WP10 & WP13) Outline 2 XFEL accelerator structure TESLA technology Basic cryogenic parameters

More information

ACHIEVEMENT OF ULTRA-HIGH QUALITY FACTOR IN PROTOTYPE CRYOMODULE FOR LCLS-II

ACHIEVEMENT OF ULTRA-HIGH QUALITY FACTOR IN PROTOTYPE CRYOMODULE FOR LCLS-II ACHIEVEMENT OF ULTRA-HIGH QUALITY FACTOR IN PROTOTYPE CRYOMODULE FOR LCLS-II G. Wu 1, A. Grassellino, E. Harms, N. Solyak, A. Romanenko, C. Ginsburg, R. Stanek Fermi National Accelerator Laboratory, Batavia,

More information

TESLA RF POWER COUPLERS DEVELOPMENT AT DESY.

TESLA RF POWER COUPLERS DEVELOPMENT AT DESY. TESLA RF POWER COUPLERS DEVELOPMENT AT DESY. Dwersteg B., Kostin D., Lalayan M., Martens C., Möller W.-D., DESY, D-22603 Hamburg, Germany. Abstract Different RF power couplers for the TESLA Test Facility

More information

Status of the ESS Accelerator Workpackage

Status of the ESS Accelerator Workpackage Status of the ESS Accelerator Workpackage Peter McIntosh STFC Daresbury Laboratory UK ESS Interactions and Opportunities Rutherford Appleton Laboratory 3 Dec 2014 The ESS Linac The European Spallation

More information

KEK ERL CRYOMODULE DEVELOPMENT

KEK ERL CRYOMODULE DEVELOPMENT KEK ERL CRYOMODULE DEVELOPMENT H. Sakai*, T. Furuya, E. Kako, S. Noguchi, M. Sato, S. Sakanaka, T. Shishido, T. Takahashi, K. Umemori, K. Watanabe and Y. Yamamoto KEK, 1-1, Oho, Tsukuba, Ibaraki, 305-0801,

More information

Progresses on China ADS Superconducting Cavities

Progresses on China ADS Superconducting Cavities Progresses on China ADS Superconducting Cavities Peng Sha IHEP, CAS 2013/06/12 1 Outline 1. Introduction 2. Spoke012 cavity 3. Spoke021 cavity 4. Spoke040 cavity 5. 650MHz β=0.82 5-cell cavity 6. High

More information

ASSEMBLY PREPARATIONS FOR THE INTERNATIONAL ERL CRYOMODULE AT DARESBURY LABORATORY

ASSEMBLY PREPARATIONS FOR THE INTERNATIONAL ERL CRYOMODULE AT DARESBURY LABORATORY ASSEMBLY PREPARATIONS FOR THE INTERNATIONAL ERL CRYOMODULE AT DARESBURY LABORATORY P. A. McIntosh #, R. Bate, C. D. Beard, M. A. Cordwell, D. M. Dykes, S. M. Pattalwar and J. Strachan, STFC Daresbury Laboratory,

More information

PROGRESS IN IFMIF HALF WAVE RESONATORS MANUFACTURING AND TEST PREPARATION

PROGRESS IN IFMIF HALF WAVE RESONATORS MANUFACTURING AND TEST PREPARATION PROGRESS IN IFMIF HALF WAVE RESONATORS MANUFACTURING AND TEST PREPARATION G. Devanz, N. Bazin, G. Disset, H. Dzitko, P. Hardy, H. Jenhani, J. Neyret, O. Piquet, J. Plouin, N. Selami, CEA-Saclay, France

More information

A New 2 K Superconducting Half-Wave Cavity Cryomodule for PIP-II

A New 2 K Superconducting Half-Wave Cavity Cryomodule for PIP-II A New 2 K Superconducting Half-Wave Cavity Cryomodule for PIP-II Zachary Conway On Behalf of the ANL Physics Division Linac Development Group June 29, 2015 Acknowledgements People Working at ANL: PHY:

More information

High Voltage Instrumentation Cables for the ITER Superconducting Magnet Systems

High Voltage Instrumentation Cables for the ITER Superconducting Magnet Systems High Voltage Instrumentation Cables for the ITER Superconducting Magnet Systems Summary for Call for Nominations 1. Background and scope ITER will be the world's largest experimental facility to demonstrate

More information

Current Status of cerl Injector Cryomodule

Current Status of cerl Injector Cryomodule Current Status of cerl Injector Cryomodule E. Kako, Y. Kondo, S. Noguchi, T. Shishido, K. Watanabe, Y. Yamamoto (KEK, Japan) 1 Outline Overview of Injector Cryomodule 2-cell Cavities HOM RF Feedthroughs

More information

PERFORMANCE OF THE TUNER MECHANISM FOR SSR1 RESONATORS DURING FULLY INTEGRETED TESTS AT FERMILAB

PERFORMANCE OF THE TUNER MECHANISM FOR SSR1 RESONATORS DURING FULLY INTEGRETED TESTS AT FERMILAB PERFORMANCE OF THE TUNER MECHANISM FOR SSR1 RESONATORS DURING FULLY INTEGRETED TESTS AT FERMILAB D. Passarelli, J.P. Holzbauer, L. Ristori, FNAL, Batavia, IL 651, USA Abstract In the framework of the Proton

More information

EXPERIMENTAL RESULT OF LORENTZ DETUNING IN STF PHASE-1 AT KEK-STF

EXPERIMENTAL RESULT OF LORENTZ DETUNING IN STF PHASE-1 AT KEK-STF EXPERIMENTAL RESULT OF LORENTZ DETUNING IN STF PHASE-1 AT KEK-STF Y. Yamamoto #, H. Hayano, E. Kako, T. Matsumoto, S. Michizono, T. Miura, S. Noguchi, M. Satoh, T. Shishidio, K. Watanabe, KEK, Tsukuba,

More information

ALICE SRF SYSTEM COMMISSIONING EXPERIENCE A. Wheelhouse ASTeC, STFC Daresbury Laboratory

ALICE SRF SYSTEM COMMISSIONING EXPERIENCE A. Wheelhouse ASTeC, STFC Daresbury Laboratory ALICE SRF SYSTEM COMMISSIONING EXPERIENCE A. Wheelhouse ASTeC, STFC Daresbury Laboratory ERL 09 8 th 12 th June 2009 ALICE Accelerators and Lasers In Combined Experiments Brief Description ALICE Superconducting

More information

Third Harmonic Superconducting passive cavities in ELETTRA and SLS

Third Harmonic Superconducting passive cavities in ELETTRA and SLS RF superconductivity application to synchrotron radiation light sources Third Harmonic Superconducting passive cavities in ELETTRA and SLS 2 cryomodules (one per machine) with 2 Nb/Cu cavities at 1.5 GHz

More information

MHz NCRF R&D Program and Plans. R. Rimmer, A. Ladran, D. Li LBNL

MHz NCRF R&D Program and Plans. R. Rimmer, A. Ladran, D. Li LBNL 201.25 MHz NCRF R&D Program and Plans R. Rimmer, A. Ladran, D. Li LBNL 201.25 MHz cavity design status RF parameters for MICE Components Proposed manufacturing plan Fabrication tests Foils and grids Forces

More information

Supporting Planning and Engineering Processes at XFEL Examples, Benefits and Experience

Supporting Planning and Engineering Processes at XFEL Examples, Benefits and Experience Supporting Planning and Engineering Processes at XFEL Examples, Benefits and Experience Lars Hagge, Benno List SLAC, 31.03.2014 Agenda > Introduction: Collaborative Engineering > Collaborative Design &

More information

JRA1 SRF partner meeting Zeuthen Jan. 22, Michelato, INFN Milano LASA

JRA1 SRF partner meeting Zeuthen Jan. 22, Michelato, INFN Milano LASA JRA1 SRF partner meeting Zeuthen Jan. 22, 2004 Paolo P. Michelato, INFN LASA INFN Milano LASA WP2 task and objectives WP2 (Improved Standard Cavity Fabrication, ISCF) aims at improving the present cavity

More information

The European Spallation Source. Dave McGinnis Chief Engineer ESS\Accelerator Division IVEC 2013

The European Spallation Source. Dave McGinnis Chief Engineer ESS\Accelerator Division IVEC 2013 The European Spallation Source Dave McGinnis Chief Engineer ESS\Accelerator Division IVEC 2013 Overview The European Spallation Source (ESS) will house the most powerful proton linac ever built. The average

More information

A few results [2,3] obtained with the individual cavities inside their horizontal cryostats are summarized in Table I and a typical Q o

A few results [2,3] obtained with the individual cavities inside their horizontal cryostats are summarized in Table I and a typical Q o Particle Accelerators, 1990, Vol. 29, pp. 47-52 Reprints available directly from the publisher Photocopying permitted by license only 1990 Gordon and Breach, Science Publishers, Inc. Printed in the United

More information

OVERVIEW OF REGIONAL INFRASTRUCTURES FOR SCRF DEVELOPMENT

OVERVIEW OF REGIONAL INFRASTRUCTURES FOR SCRF DEVELOPMENT OVERVIEW OF REGIONAL INFRASTRUCTURES FOR SCRF DEVELOPMENT Carlo Pagani, University of Milano and INFN Milano - LASA, Italy Abstract The perspective of building the International Linear Collider, ILC, as

More information

Cornell ERL s Main Linac Cavities

Cornell ERL s Main Linac Cavities Cornell ERL s Main Linac Cavities N. Valles for Cornell ERL Team 1 Overview RF Design Work Cavity Design Considerations Optimization Methods Results Other Design Considerations Coupler Kicks Stiffening

More information

SUPERCONDUCTING CAVITIES AND CRYOMODULES FOR PROTON AND DEUTERON LINACS

SUPERCONDUCTING CAVITIES AND CRYOMODULES FOR PROTON AND DEUTERON LINACS Proceedings of LINAC2014, Geneva, Switzerland THIOA04 SUPERCONDUCTING CAVITIES AND CRYOMODULES FOR PROTON AND DEUTERON LINACS G. Devanz, CEA-Irfu CEA-Saclay, Gif-sur-Yvette 91191, France Abstract We review

More information

Cryogenics for Large Accelerators

Cryogenics for Large Accelerators Cryogenics for Large Accelerators Dr. Sergiy Putselyk Deutsches Elektronen-Synchrotron (DESY) MKS Division Notkestrasse 85 22607 Hamburg (Germany) Phone: +49 40 89983492 Fax: +49 40 89982858 E-Mail: Sergiy.Putselyk@desy.de

More information

Liquid Helium Heat Load Within the Cornell Mark II Cryostat

Liquid Helium Heat Load Within the Cornell Mark II Cryostat SRF 990615-07 Liquid Helium Heat Load Within the Cornell Mark II Cryostat E. Chojnacki, S. Belomestnykh, and J. Sears Floyd R. Newman Laboratory of Nuclear Studies Cornell University, Ithaca, New York

More information

Recent Progress in the Superconducting RF Program at TRIUMF/ISAC

Recent Progress in the Superconducting RF Program at TRIUMF/ISAC Recent Progress in the Superconducting RF Program at TRIUMF/ISAC Abstract R.E. Laxdal, K. Fong, M. Laverty, A. Mitra, R. Poirier, I. Sekachev, V. Zvyagintsev, TRIUMF, Vancouver, BC, V6T2A3, Canada A heavy

More information

Overview of ERL Projects: SRF Issues and Challenges. Matthias Liepe Cornell University

Overview of ERL Projects: SRF Issues and Challenges. Matthias Liepe Cornell University Overview of ERL Projects: SRF Issues and Challenges Matthias Liepe Cornell University Overview of ERL projects: SRF issues and challenges Slide 1 Outline Introduction: SRF for ERLs What makes it special

More information

INSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM

INSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM INSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM FOR THE EUROPEAN XFEL Julien Branlard, for the LLRF team TALK OVERVIEW 2 Introduction Brief reminder about the XFEL LLRF system Commissioning goals

More information

SRF EXPERIENCE WITH THE CORNELL HIGH-CURRENT ERL INJECTOR PROTOTYPE

SRF EXPERIENCE WITH THE CORNELL HIGH-CURRENT ERL INJECTOR PROTOTYPE SRF EXPERIENCE WITH THE CORNELL HIGH-CURRENT ERL INJECTOR PROTOTYPE M. Liepe, S. Belomestnykh, E. Chojnacki, Z. Conway, V. Medjidzade, H. Padamsee, P. Quigley, J. Sears, V. Shemelin, V. Veshcherevich,

More information

Status and Plans for the 805 MHz Box Cavity MuCool RF Workshop III 07/07/09 Al Moretti

Status and Plans for the 805 MHz Box Cavity MuCool RF Workshop III 07/07/09 Al Moretti Status and Plans for the 805 MHz Box Cavity MuCool RF Workshop III 07/07/09 Al Moretti 7/6/2009 1 Outline : Description of the Box cavity Concept. Box Cavity Summary Plans. HFSS Models of orthogonal and

More information

REVIEW OF HIGH POWER CW COUPLERS FOR SC CAVITIES. S. Belomestnykh

REVIEW OF HIGH POWER CW COUPLERS FOR SC CAVITIES. S. Belomestnykh REVIEW OF HIGH POWER CW COUPLERS FOR SC CAVITIES S. Belomestnykh HPC workshop JLAB, 30 October 2002 Introduction Many aspects of the high-power coupler design, fabrication, preparation, conditioning, integration

More information

First High Power Test of the ESS Double Spoke Cavity

First High Power Test of the ESS Double Spoke Cavity Nov. 2017 DEPARTMENT OF PHYSICS AND ASTRONOMY UPPSALA UNIVERSITY First High Power Test of the ESS Double Spoke Cavity H. Li, R. Santiago Kern, M. Jobs, A. Bhattacharyya, V. Goryashko, L. Hermansson, K.

More information

RF power tests of LEP2 main couplers on a single cell superconducting cavity

RF power tests of LEP2 main couplers on a single cell superconducting cavity RF power tests of LEP2 main couplers on a single cell superconducting cavity H.P. Kindermann, M. Stirbet* CERN, CH-1211 Geneva 23, Switzerland Abstract To determine the power capability of the input couplers

More information

ESS RF Source and Spoke Cavity Test Plan

ESS RF Source and Spoke Cavity Test Plan FREIA Report 2015/01 26 February 2015 DEPARTMENT OF PHYSICS AND ASTRONOMY UPPSALA UNIVERSITY ESS RF Source and Spoke Cavity Test Plan R. Ruber (ed.), A. Bhattacharyya, D. Dancila, T. Ekelöf, J. Eriksson,

More information

Current Industrial SRF Capabilities and Future Plans

Current Industrial SRF Capabilities and Future Plans and Future Plans Capabilities in view of Design Engineering Manufacturing Preparation Testing Assembly Taking into operation Future Plans Participate in and contribute to development issues, provide prototypes

More information

OVERVIEW OF INPUT POWER COUPLER DEVELOPMENTS, PULSED AND CW*

OVERVIEW OF INPUT POWER COUPLER DEVELOPMENTS, PULSED AND CW* Presented at the 13th International Workshop on RF Superconductivity, Beijing, China, 2007 SRF 071120-04 OVERVIEW OF INPUT POWER COUPLER DEVELOPMENTS, PULSED AND CW* S. Belomestnykh #, CLASSE, Cornell

More information

5.5 SNS Superconducting Linac

5.5 SNS Superconducting Linac JP0150514 ICANS - XV 15 th Meeting of the International Collaboration on Advanced Neutron Sources November 6-9, 2000 Tsukuba, Japan Ronald M. Sundelin Jefferson Lab* 5.5 SNS Superconducting Linac 12000

More information

Status of berlinpro and BESSY II Installation of SSA. Helmholtz-Zentrum Berlin for materials and energy (HZB)

Status of berlinpro and BESSY II Installation of SSA. Helmholtz-Zentrum Berlin for materials and energy (HZB) Status of berlinpro and BESSY II Installation of SSA Wolfgang Anders, Helmholtz-Zentrum Berlin for materials and energy (HZB) 19th ESLS-RF Meeting 30.9.-1.10.2015 MaxLab outline BERLinPro Status building

More information

LOW BETA CAVITY DEVELOPMENT FOR AN ATLAS INTENSITY UPGRADE

LOW BETA CAVITY DEVELOPMENT FOR AN ATLAS INTENSITY UPGRADE LOW BETA CAVITY DEVELOPMENT FOR AN ATLAS INTENSITY UPGRADE M. P. Kelly, Z. A. Conway, S. M. Gerbick, M. Kedzie, T. C. Reid, R. C. Murphy, B. Mustapha, S.H. Kim, P. N. Ostroumov, Argonne National Laboratory,

More information

Couplers for Project X. S. Kazakov, T. Khabiboulline

Couplers for Project X. S. Kazakov, T. Khabiboulline Couplers for Project X S. Kazakov, T. Khabiboulline TTC meeting on CW-SRF, 2013 Requirements to Project X couplers Cavity SSR1 (325MHz): Cavity SSR2 (325MHz): Max. energy gain - 2.1 MV, Max. power, 1 ma

More information

CAGE CAVITY: A LOW COST, HIGH PERFORMANCE SRF ACCELERATING STRUCTURE*

CAGE CAVITY: A LOW COST, HIGH PERFORMANCE SRF ACCELERATING STRUCTURE* CAGE CAVITY: A LOW COST, HIGH PERFORMANCE SRF ACCELERATING STRUCTURE* J. Noonan, T.L. Smith, M. Virgo, G.J. Waldsmidt, Argonne National Laboratory J.W. Lewellen, Los Alamos National Laboratory Abstract

More information

RF System LSD Work. William Merz

RF System LSD Work. William Merz RF System LSD Work William Merz LSD Re-Baseline Review Jefferson Lab Thomas Jefferson National Accelerator Facility Page 1 Outline What I will talk about 12 GEV RF power system installation and commissioning

More information

Structures for RIA and FNAL Proton Driver

Structures for RIA and FNAL Proton Driver Structures for RIA and FNAL Proton Driver Speaker: Mike Kelly 12 th International Workshop on RF Superconductivity July 11-15, 2005 Argonne National Laboratory A Laboratory Operated by The University of

More information

Superconducting Cavity Fabrication for ILC in Japan

Superconducting Cavity Fabrication for ILC in Japan Superconducting Cavity Fabrication for ILC in Japan -Industrial Activities- Masanori MATSUOKA (Mitsubishi Heavy Industries, Ltd.) Norihiko OZAKI (Linear Collider Forum of of Japan) Tuesday, Augsut 16,

More information

Report of working group 5

Report of working group 5 Report of working group 5 Materials Cavity design Cavity Fabrication Preparatioin & Testing Power coupler HOM coupler Beam line absorber Tuner Fundamental R&D items Most important R&D items 500 GeV parameters

More information

Completion of the first SSR1 cavity for PXIE

Completion of the first SSR1 cavity for PXIE 2013 North American Particle Accelerator Conference Pasadena, CA Completion of the first SSR1 cavity for PXIE Design, Manufacturing and Qualification Leonardo Ristori on behalf of the Fermilab SRF Development

More information

PIP-II Superconducting RF Linac Status and Challenges" Leonardo Ristori! ICEC-ICMC Conference, New Delhi! 9 March 2016!!

PIP-II Superconducting RF Linac Status and Challenges Leonardo Ristori! ICEC-ICMC Conference, New Delhi! 9 March 2016!! PIP-II Superconducting RF Linac Status and Challenges" Leonardo Ristori! ICEC-ICMC Conference, New Delhi!! Outline" PIP-II Mission & Strategy! PIP-II SRF Linac Overview! Technical Risk & Mitigation! Indian

More information

Advance on High Power Couplers for SC Accelerators

Advance on High Power Couplers for SC Accelerators Advance on High Power Couplers for SC Accelerators Eiji Kako (KEK, Japan) IAS conference at Hong Kong for High Energy Physics, 2017, January 23th Eiji KAKO (KEK, Japan) IAS at Hong Kong, 2017 Jan. 23 1

More information

Plans for the ESS Linac. Steve Peggs, ESS for the ESS collaboration

Plans for the ESS Linac. Steve Peggs, ESS for the ESS collaboration Plans for the ESS Linac, ESS for the ESS collaboration 8 Work Packages Romuald Duperrier (30 years ago) Cristina Oyon Josu Eguia Work Packages in the Design Upgrade Mats Lindroos 1. Management Coordination

More information

CEBAF waveguide absorbers. R. Rimmer for JLab SRF Institute

CEBAF waveguide absorbers. R. Rimmer for JLab SRF Institute CEBAF waveguide absorbers R. Rimmer for JLab SRF Institute Outline Original CEBAF HOM absorbers Modified CEBAF loads for FEL New materials for replacement loads High power loads for next generation FELs

More information

SRF in Storage Rings. Michael Pekeler ACCEL Instruments GmbH Bergisch Gladbach Germany

SRF in Storage Rings. Michael Pekeler ACCEL Instruments GmbH Bergisch Gladbach Germany SRF in Storage Rings Michael Pekeler ACCEL Instruments GmbH 51429 Bergisch Gladbach Germany SRF in Storage Rings Michael Pekeler ACCEL Instruments GmbH 51429 Bergisch Gladbach Germany TESLA type cavity:

More information

two pairs of dipole steering windings that t inside the quadrupole yoke an RF beam position monitor (BPM) consisting of a pill box RF cavity,

two pairs of dipole steering windings that t inside the quadrupole yoke an RF beam position monitor (BPM) consisting of a pill box RF cavity, Chapter 6 Quadrupole Package The quadrupole package is shown in Fig. 6.1. It consists of a superferric quadrupole doublet powered in series enclosed in a stainless steel vessel and cooled by 4 K LHe; two

More information

The TESLA Linear Collider. Winfried Decking (DESY) for the TESLA Collaboration

The TESLA Linear Collider. Winfried Decking (DESY) for the TESLA Collaboration The TESLA Linear Collider Winfried Decking (DESY) for the TESLA Collaboration Outline Project Overview Highlights 2000/2001 Publication of the TDR Cavity R&D TTF Operation A0 and PITZ TESLA Beam Dynamics

More information

KEYWORDS: ATLAS heavy ion linac, cryomodule, superconducting rf cavity.

KEYWORDS: ATLAS heavy ion linac, cryomodule, superconducting rf cavity. DESIGN AND DEVELOPMENT OF A NEW SRF CAVITY CRYOMODULE FOR THE ATLAS INTENSITY UPGRADE M. Kedzie 1, Z. A. Conway 1, J. D. Fuerst 1, S. M. Gerbick 1, M. P. Kelly 1, J. Morgan 1, P. N. Ostroumov 1, M. O Toole

More information

Institut für Kernphysik, TU Darmstadt Darmstadt, 64289, Germany

Institut für Kernphysik, TU Darmstadt Darmstadt, 64289, Germany Published in AIP Conference Proceedings 1218, pp. 831-838 (2010) INJECTOR UPGRADE FOR THE SUPERCONDUCTING ELECTRON ACCELERATOR S-DALINAC T. Kuerzeder1, J. Conrad1, R. Eichhorn1, J.D. Fuerst3, B. Bravo

More information

A 3 GHz SRF reduced-β Cavity for the S-DALINAC

A 3 GHz SRF reduced-β Cavity for the S-DALINAC A 3 GHz SRF reduced-β Cavity for the S-DALINAC D. Bazyl*, W.F.O. Müller, H. De Gersem Gefördert durch die DFG im Rahmen des GRK 2128 20.11.2018 M.Sc. Dmitry Bazyl TU Darmstadt TEMF Upgrade of the Capture

More information

CHALLENGES IN ILC SCRF TECHNOLOGY *

CHALLENGES IN ILC SCRF TECHNOLOGY * CHALLENGES IN ILC SCRF TECHNOLOGY * Detlef Reschke #, DESY, D-22603 Hamburg, Germany Abstract With a baseline operating gradient of 31,5 MV/m at a Q-value of 10 10 the superconducting nine-cell cavities

More information

PI piezo Life Time Test Report. A. Bosotti, R. Paparella, F. Puricelli

PI piezo Life Time Test Report. A. Bosotti, R. Paparella, F. Puricelli PI piezo Life Time Test Report A. Bosotti, R. Paparella, F. Puricelli 1. Introduction...3 1.1. Vacuum...4 1.2. Temperature...4 1.3. Preload...4 1.4. Driving signal...4 2. General features and conceptual

More information

HIGH Q CAVITIES FOR THE CORNELL ERL MAIN LINAC

HIGH Q CAVITIES FOR THE CORNELL ERL MAIN LINAC THIOB02 HIGH Q CAVITIES FOR THE CORNELL ERL MAIN LINAC # G.R. Eichhorn, B. Bullock, B. Clasby, B. Elmore, F. Furuta, M. Ge, D. Gonnella, D. Hall, A.Ganshin, Y. He, V. Ho, G.H. Hoffstaetter, J. Kaufman,

More information

COMPARISON OF BUFFERED CHEMICAL POLISHED AND ELECTROPOLISHED 3.9 GHz CAVITIES*

COMPARISON OF BUFFERED CHEMICAL POLISHED AND ELECTROPOLISHED 3.9 GHz CAVITIES* COMPARISON OF BUFFERED CHEMICAL POLISHED AND ELECTROPOLISHED 3.9 GHz CAVITIES* H. Edwards #, C.A. Cooper, M. Ge, I.V. Gonin, E.R. Harms, T. N. Khabiboulline, N. Solyak Fermilab, Batavia IL, USA Abstract

More information