PRACTICAL CONSIDERATIONS FOR CONTROLLED SWITCHING OF POWER TRANSFORMERS

Size: px
Start display at page:

Download "PRACTICAL CONSIDERATIONS FOR CONTROLLED SWITCHING OF POWER TRANSFORMERS"

Transcription

1 Seminar / Workshop on Controlled Switching Possible Benefits for Transformers Applications PRACTICAL CONSIDERATIONS FOR CONTROLLED SWITCHING OF POWER TRANSFORMERS Esteban Portales Yvon Filion André Mercier St-Petersburg, Florida - May

2 Transformers Controlled Switching : Programme 1. Introduction 2. Transformer energization and resulting Temporary Overvoltages (TOVs) 3. Mitigation means 4. Reasons for using CSS on transformers 5. Examples of cases where CSS can advantageously be used: a) Integration of power plant b) System restoring c) Energization of transformer near sensible equipment d) Replacement or complete refurbishment of CB 6. Optimal closing strategy a) Importance of the residual flux b) Switching algorithm c) Simulations with Controlled Switching solution d) Means for measuring the residual flux 7. Means for measuring the residual flux 8. Conclusions 9. References St-Petersburg, Florida - May

3 1: Introduction Transformer energization produces an inrush current whose magnitude depends on the transformer characteristics, the point on wave closing time and residual flux. Inrush current has a rich harmonic content, among which 2 nd, 3 rd, 4 th harmonics are the most important. Inrush current harmonics may cause temporary overvoltages on the system due to resonance prevailing under some operating conditions. St-Petersburg, Florida - May

4 2: Transformer energization and resulting TOVs Because generated temporary-overvoltages on the system at transformer energization depend on: Network configuration Operating condition Transformer characteristics Circuit breaker characteristics Etc. Each case has to be studied closely (simulations performed, etc.) in order to select the right solution and to specify the right characteristics for associated equipments St-Petersburg, Florida - May

5 2: Transformer energization and resulting TOVs example - Network TOV produced at the energization of a kv transformer from 315 kv without controlled switching St-Petersburg, Florida - May

6 2: Transformer energization and resulting TOVs example - Inrush current produced at the energization of a kv transformer from 315 kv without controlled switching St-Petersburg, Florida - May

7 3: Mitigation means - Reasons for using them to reduce the overvoltages (TOV) resulting from the energization of large power transformers [1], [2], [3]. to reduce the mechanical and electrical stresses on XFOS in order to increase their remaining life [4], [5] St-Petersburg, Florida - May

8 3: Mitigation means list of possible solutions Use of pre-insertion resistors Use of controlled switching system (CSS) Generator voltage ramping restoration procedure; Energization of transformers under load on the sub-transmission side (if possible). Apply restrictions on the operating conditions (less flexibility for the operators, may be critical for system restoring scenarios) St-Petersburg, Florida - May

9 3: Mitigation means pre-insertion resistors - Inserer les resultats de simulation avec 8 et 14 ms St-Petersburg, Florida - May

10 4: Use of CSS with optimal closing strategy A. Importance of the residual flux B. Switching algorithm C. Simulations with Controlled Switching solution D. Means for measuring the residual flux St-Petersburg, Florida - May

11 4: a) Importance of the residual flux Optimal closing strategy for 3-phase transformers equipped with a secondary or tertiary delta winding was found to be first closing the phase having the highest residual flux, and then closing the two remaining phases simultaneously: For the first phase to close, the optimal closing time is determined by the residual flux relative to the instantaneous voltage; Closing time of the two other phases is optimal upon zero crossing of the voltage induced onto these phases. St-Petersburg, Florida - May

12 4: a) Importance of the residual flux Accurate knowledge of the residual flux (magnitude and polarity on each phase) of the transformers to be switched-in is a key parameter allowing to determine the best strategy for minimizing the inrush current and thus limit system overvoltages and transformer stresses. St-Petersburg, Florida - May

13 4: b) Switching Algorithm The first closing instant is set when the instantaneous voltage is equal to: v =V * 2 3 ( ) *sinα α = arccos ϕ * 3 * 2 * ω r V St-Petersburg, Florida - May

14 4: b) Switching Algorithm Graphical example of the algorithm application Phase B Phase A Phase C St-Petersburg, Florida - May

15 5. Practical cases where CSS can advantageously be used. 5.1 Integration of power plant Energizing at power plant S/S Energizing at integrating S/S 5.2 System restoring 5.3 Energization of transformer near equipment sensible to system disturbances St-Petersburg, Florida - May

16 5.1 Integration of power plant Power plant substation Integrating substation St-Petersburg, Florida - May

17 5.1.1 Energizing of transformer at power plant s/s Integrating substation Power plant substation St-Petersburg, Florida - May

18 5.1.1 Energizing of transformer at power plant s/s (Next Next) Temporary overvoltages (tov) were observed when energizing the step-up transformers located at the power plant substation (refer to fig. 1) Protection systems may operate under such voltage disturbances, possible damages for the equipment For the cases where important TOVs are observed, it is necessary to reduce overvoltages using controlled switching or pre-insertion resistors. St-Petersburg, Florida - May

19 Example of TOVs observed in the power plant s/s during energization of transformer at the Power plant S/S without any mitigation means Fig 1 - TOVs and inrush currents observed when energization takes place at power plant S/S St-Petersburg, Florida - May

20 4: c) Simulations with Controlled Switching solution Practical case 1: Energizing power transformers at SM -3 3 (with ( controlled switching) St-Petersburg, Florida - May

21 5.1.2 Energization at remote s/s (particular operating conditions when power plant is islanded on the radial sub-transmission system) St-Petersburg, Florida - May

22 5.1.2 Situation at the remote s/s Overvoltages due to transformer energization at remote s/s with the power plant islanded on the subtransmission system may lead to even higher overvoltages. (refer to fig. 2) solutions contemplated to mitigate overvoltages : Pre-insertion resistors on breakers; Controlled switching with some adaptions for this particular application; Generator voltage ramping restoration procedure; Energization of transformers under load on the subtransmission side. St-Petersburg, Florida - May

23 5.1.2 Energization at remote s/s (w/o any mitigation means) Fig 2 - TOVs and inrush currents observed whwn energization takes place at integrating S/S St-Petersburg, Florida - May

24 5.2 System restoring 1. Start generator groups Integrating S/S Power plant S/S Power plant S/S 2. Energize Xfo at integrating S/S 735 kv system St-Petersburg, Florida - May

25 5.2 System restoring - results Similar case as for energizing at remote S/S Can result in very important TOVs Can cause damage to equipment St-Petersburg, Florida - May

26 5.2) System restoring another scenario - St-Petersburg, Florida - May

27 5.2 System restoring example with 2 Groups - 1 Line St-Petersburg, Florida - May

28 5: System restoring - Simulations with Controlled Switching solution Practical case 2: Sw.-in at 315 kv: 2Groups-1Line with css St-Petersburg, Florida - May

29 5.3 Energization of transformer near equipment sensible to system disturbances Islanded network Energizing one of these xfo w/o mitigation mean may cause some commutation failure of HVDC converter St-Petersburg, Florida - May

30 6: Measuring the residual flux Theory Sensors Real case measurement St-Petersburg, Florida - May

31 6: measuring the residual flux: theory To achieve the magnetic flux Φ measurement without being intrusive, the value has to be derived from a more common (or easily accessible) signal: the voltage E at the transformer input.. 1 Φ = E + ϕ r N Measuring and integrating the voltage of each phase just before and during de-energization of the transformer in the steady state determines the residual flux, which is the end value of the integrated voltage. When an event occurs, a time window is set (just before and during de-energization of the transformer) and the integration of the voltage signal of each phase of the unloaded transformer is performed. With this method, only a small number of cycles is used for integration to prevent that even a small offset error in the voltage measurement lead to a large error in the results. St-Petersburg, Florida - May

32 6: Measuring M the residual flux: sensors For an accurate magnetic flux measurement, the system needs 3 main items: Transformer voltage measurement Measurement of the transformer input current and a software package St-Petersburg, Florida - May

33 6: Measuring M the residual flux: sensors Transformer voltage measurement St-Petersburg, Florida - May

34 6: Measuring M the residual flux: sensors Transformer voltage measurement St-Petersburg, Florida - May

35 6: Measuring M the residual flux: sensors Accurate measurement of the transformer input current ranging from the very low magnetizing current up to the high inrush current values St-Petersburg, Florida - May

36 6: Measuring M the residual flux: sensors Transformer input current St-Petersburg, Florida - May

37 6: Measuring M the residual flux: sensors Software package St-Petersburg, Florida - May

38 6: Measuring M the residual flux: real case For integrating the new Sainte-Marguerite-3 hydroelectric powerhouse (SM-3) in TransÉnergie s 315-kV grid, the following challenges were successfully overcome: Extensive EMTP simulation studies Development of voltage and current sensors Development and installation of 2 prototypes Preliminary tests St-Petersburg, Florida - May

39 6. Measuring the residual flux: real case Measured/calculated residual flux after switching-out the transformer St-Petersburg, Florida - May

40 6. Measuring M the residual flux: real case Measured current at the transformer energization St-Petersburg, Florida - May

41 6. Measuring the residual flux: real case Measured network voltage at the transformer energization St-Petersburg, Florida - May

42 7. Economical considerations List of points to be considered Cost analysis (PIR replacement vs CSS) Maintenance costs (frequent switching) Technical feasibility of CSS with existing CB characteristics (RDDS, time scattering,) Reliability issue and consequences for unavailability of the equipment St-Petersburg, Florida - May

43 8. Conclusions Energization of power transformer can result in severe TOVs on the system mainly depending on: The system conditions Transformer characteristics Instant of energizing on the point on wave in relation with the residual flux. System simulation studies are necessary to evaluate the risk of havingtovs following XFo energization For the cases with TOVs, mitigation means are needed to avoid dammages to equipment. St-Petersburg, Florida - May

44 8. Conclusions Laboratory tests and on-site tests confirmed the accuracy of residual flux measurement. An optimal closing strategy was validated for 3-phase transformers having a secondary or tertiary delta connected winding. Accurate residual flux measurement enables energization of unloaded transformers without generating inrush current or TOV on any phase. Controlled switching of transformers is feasible, reliable, cost-effective and less stressful for the transformer and the electrical network. St-Petersburg, Florida - May

45 1: References Hydro Québec Simulation studies Other references 1) CIGRE WG13.07, Controlled Switching of HVAC Circuit Breakers Guide for application, Part 1: ELECTRA, No 183, April 1999, pp Part 2: ELECTRA, No 185, August 1999, pp ) CIGRE WG 13.07, Controlled Switching of HVAC Circuit Breakers Planning, Specification and Testing of controlled switching systems, ELECTRA, No 197, August ) CIGRE 2002, report , «Analysis, simulation and testing of transformer insulation failures related to switching transients overvoltages» 4) IEEE, Transactions on power delivery, M. Steurer, K. Fröhlich, The impact of inrush currents on the mechanical stress of high voltage power transformer coils St-Petersburg, Florida - May

46 1: References????? «Worldwide many transformer insulation failures have been reported caused by switching operations, while those transformers had previously passed all the standard tests and complied to all quality requirements.» «The problem is generally associated to the high frequency overvoltages produced by the re-strikes and pre-strikes during the opening or closing of a switching device.» St-Petersburg, Florida - May

47 1: References «From failure experience on power transformers very often it was suspected that inrush currents, occurring when energizing unloaded transformers, where reason for damage.» «Although inrush currents normally are smaller the forces can have similar amplitudes as those at short circuit however with longer exposure time.» St-Petersburg, Florida - May

48 Seminar / Workshop on Controlled Switching Possible Benefits for Transformers Applications Thank you for your attention St-Petersburg, Florida - May

ANALITICAL ANALYSIS OF TRANSFORMER INRUSH CURRENT AND SOME NEW TECHNIQUES FOR ITS REDDUCTION

ANALITICAL ANALYSIS OF TRANSFORMER INRUSH CURRENT AND SOME NEW TECHNIQUES FOR ITS REDDUCTION ANALITICAL ANALYSIS OF TRANSFORMER INRUSH CURRENT AND SOME NEW TECHNIQUES FOR ITS REDDUCTION R.Rahnavard 1, 2 M.Valizadeh 1 A.A.B.Sharifian 2 S.H.Hosseini 1 rerahnavard@gmail.com mj_valizad@yahoo.com hosseini@tabrizu.ac.ir

More information

REDUCTION OF TRANSFORMER INRUSH CURRENT BY CONTROLLED SWITCHING METHOD. Trivandrum

REDUCTION OF TRANSFORMER INRUSH CURRENT BY CONTROLLED SWITCHING METHOD. Trivandrum International Journal of Scientific & Engineering Research, Volume 7, Issue 4, April-216 628 REDUCTION OF TRANSFORMER INRUSH CURRENT BY CONTROLLED SWITCHING METHOD Abhilash.G.R Smitha K.S Vocational Teacher

More information

Reducing the magnetizing inrush current by means of controlled energization and de-energization of large power transformers

Reducing the magnetizing inrush current by means of controlled energization and de-energization of large power transformers International Conference on Power System Transients IPST 23 in New Orleans, USA Reducing the magnetizing inrush current by means of controlled energization and de-energization of large power transformers

More information

Tab 2 Voltage Stresses Switching Transients

Tab 2 Voltage Stresses Switching Transients Tab 2 Voltage Stresses Switching Transients Distribution System Engineering Course Unit 10 2017 Industry, Inc. All rights reserved. Transient Overvoltages Decay with time, usually within one or two cycles

More information

ESTIMATION OF RESIDUAL FLUX FOR THE CONTROLLED SWITCHING OF TRANSFORMER

ESTIMATION OF RESIDUAL FLUX FOR THE CONTROLLED SWITCHING OF TRANSFORMER International Journal of Electrical Engineering & Technology (IJEET) Volume 8, Issue 5, Sep-Oct 2017, pp. 32 44, Article ID: IJEET_08_05_004 Available online at http://www.iaeme.com/ijeet/issues.asp?jtype=ijeet&vtype=8&itype=5

More information

Energization of a no-load transformer for power restoration purposes: Impact of the sensitivity to parameters.

Energization of a no-load transformer for power restoration purposes: Impact of the sensitivity to parameters. Energization of a no-load transformer for power restoration purposes: Impact of the sensitivity to parameters. Michel Rioual, Senior Member, IEEE Christophe Sicre EDF / R&D Division ALTRAN TECHNOLOGIES

More information

Identification of network models parameters for simulating transients

Identification of network models parameters for simulating transients Identification of network models parameters for simulating transients D. Cavallera, J-L. Coulomb, O. Chadebec, B. Caillault, F-X. Zgainski and A.Ayroulet Abstract In case of electrical black-out, one of

More information

Simulation and Analysis of Power System Transients using EMTP-RV

Simulation and Analysis of Power System Transients using EMTP-RV 5-Day course Montréal - CANADA October 1-5, 2012 Simulation and Analysis of Power System Transients using EMTP-RV This course is organized by POWERSYS. Place: DELTA MONTREAL http://www.deltahotels.com/en/hotels/quebec/delta-montreal/

More information

Abstract. 1 Introduction

Abstract. 1 Introduction Energy Production and Management in the 21st Century, Vol. 1 345 Investigation of the electrical strength of a contact gap of the high voltage live tank circuit breaker 126 kv class using an intelligent

More information

Switching and Fault Transient Analysis of 765 kv Transmission Systems

Switching and Fault Transient Analysis of 765 kv Transmission Systems Third International Conference on Power Systems, Kharagpur, INDIA December >Paper #< Switching and Transient Analysis of 6 kv Transmission Systems D Thukaram, SM IEEE, K Ravishankar, Rajendra Kumar A Department

More information

Demagnetization of Power Transformers Following a DC Resistance Testing

Demagnetization of Power Transformers Following a DC Resistance Testing Demagnetization of Power Transformers Following a DC Resistance Testing Dr.ing. Raka Levi DV Power, Sweden Abstract This paper discusses several methods for removal of remanent magnetism from power transformers.

More information

Transformer energisation after network blackout

Transformer energisation after network blackout Transformer energisation after network blackout Impact on network restoration and improvement of its process ABSTRACT According to ENTSO-E Network policy 5, responsibility for system restoration after

More information

A Study on Ferroresonance Mitigation Techniques for Power Transformer

A Study on Ferroresonance Mitigation Techniques for Power Transformer A Study on Ferroresonance Mitigation Techniques for Power Transformer S. I. Kim, B. C. Sung, S. N. Kim, Y. C. Choi, H. J. Kim Abstract--This paper presents a comprehensive study on the ferroresonance mitigation

More information

Methodology Utilized in Black-Start Studies on EHV Power Networks

Methodology Utilized in Black-Start Studies on EHV Power Networks Methodology Utilized in Black-Start Studies on EHV Power Networks C. Saldaña / G. Calzolari Av. Millán 4016 - Montevideo 11700 - Uruguay gracclau@adinet.com.uy Abstract - This article presents the methodology

More information

USING OVER-DAMPING METHOD TO SUPPRESS THE FERRO-RESONANCE OF POTENTIAL TRANSFORMER

USING OVER-DAMPING METHOD TO SUPPRESS THE FERRO-RESONANCE OF POTENTIAL TRANSFORMER USING OVER-DAMPING METHOD TO SUPPRESS THE FERRO-RESONANCE OF POTENTIAL TRANSFORMER Lai Tianjiang, Lai Tianyu, Lai Qingbo Dalian Electric Power Company, China jimata@mail.dlptt.ln.cn 1 Forward In power

More information

Design, Control and Application of Modular Multilevel Converters for HVDC Transmission Systems by Kamran Sharifabadi, Lennart Harnefors, Hans-Peter

Design, Control and Application of Modular Multilevel Converters for HVDC Transmission Systems by Kamran Sharifabadi, Lennart Harnefors, Hans-Peter 1 Design, Control and Application of Modular Multilevel Converters for HVDC Transmission Systems by Kamran Sharifabadi, Lennart Harnefors, Hans-Peter Nee, Staffan Norrga, Remus Teodorescu ISBN-10: 1118851560

More information

Pinhook 500kV Transformer Neutral CT Saturation

Pinhook 500kV Transformer Neutral CT Saturation Russell W. Patterson Tennessee Valley Authority Presented to the 9th Annual Fault and Disturbance Analysis Conference May 1-2, 26 Abstract This paper discusses the saturation of a 5kV neutral CT upon energization

More information

Weidong Zhang, May.9, 2016 Development of Pre-Insertion Resistor for an 800kV GIS Circuit Breaker. ABB Group May 11, 2016 Slide 1

Weidong Zhang, May.9, 2016 Development of Pre-Insertion Resistor for an 800kV GIS Circuit Breaker. ABB Group May 11, 2016 Slide 1 Weidong Zhang, May.9, 2016 Development of Pre-Insertion Resistor for an 800kV GIS Circuit Breaker Group Slide 1 Background & Objects EHV/UHV system: Widely application for long distance transmission from

More information

FACTORY AND FIELD VERIFICATION TESTS OF CONTROLLED SWITCHING SYSTEM

FACTORY AND FIELD VERIFICATION TESTS OF CONTROLLED SWITCHING SYSTEM FACTORY AND FIELD VERIFICATION TESTS OF CONTROLLED SWITCHING SYSTEM by H. Ito, H. Tsutada, H. Kohyama, H. Yamamoto Mitsubishi Electric Corp. H. Wilson, S. Billings Mitsubishi Electric Power Products, Inc.

More information

Ferroresonances during Black Starts - Criterion for Feasibility of Scenarios

Ferroresonances during Black Starts - Criterion for Feasibility of Scenarios Ferroresonances during Black Starts - Criterion for Feasibility of Scenarios Lubomir KOCIS EGU HV Laboratory, a.s. kocis@egu-vvn.cz Czech Republic Abstract --After large black-out events in the USA and

More information

TECHNICAL BULLETIN 004a Ferroresonance

TECHNICAL BULLETIN 004a Ferroresonance May 29, 2002 TECHNICAL BULLETIN 004a Ferroresonance Abstract - This paper describes the phenomenon of ferroresonance, the conditions under which it may appear in electric power systems, and some techniques

More information

Long lasting transients in power filter circuits

Long lasting transients in power filter circuits Computer Applications in Electrical Engineering Vol. 12 2014 Long lasting transients in power filter circuits Jurij Warecki, Michał Gajdzica AGH University of Science and Technology 30-059 Kraków, Al.

More information

In power system, transients have bad impact on its

In power system, transients have bad impact on its Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kv Grid Station, Qasimabad Hyderabad SUNNY KATYARA*, ASHFAQUE AHMED HASHMANI**, AND BHAWANI SHANKAR CHOWDHRY*** RECEIVED ON 1811.2014

More information

of the improved scheme is presented. Index Terms Inrush current, power quality, transformer.

of the improved scheme is presented. Index Terms Inrush current, power quality, transformer. 208 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 22, NO. 1, JANUARY 2007 A Sequential Phase Energization Method for Transformer Inrush Current Reduction Transient Performance and Practical Considerations

More information

A NOVEL METHOD FOR ENERGIZING TRANSFORMERS FOR REDUCING INRUSH CURRENTS

A NOVEL METHOD FOR ENERGIZING TRANSFORMERS FOR REDUCING INRUSH CURRENTS A OVEL METHOD FOR EERGIZIG TRASFORMERS FOR REDUCIG IRUSH CURRETS M.B.B. Sharifian, Farhad Shahnia, Ali Shasvand 3, Iraj hasanzadeh 4,3,4 Faculty of Electrical and Computer Engineering, University of Tabriz,

More information

Solving Customer Power Quality Problems Due to Voltage Magnification

Solving Customer Power Quality Problems Due to Voltage Magnification PE-384-PWRD-0-11-1997 Solving Customer Power Quality Problems Due to Voltage Magnification R. A. Adams, Senior Member S. W. Middlekauff, Member Duke Power Company Charlotte, NC 28201 USA E. H. Camm, Member

More information

A SPECIAL CASE OF FERRORESONANCE INVOLVING A SERIES COMPENSATED LINE

A SPECIAL CASE OF FERRORESONANCE INVOLVING A SERIES COMPENSATED LINE A SPECIAL CASE OF FERRORESONANCE INVOLVING A SERIES COMPENSATED LINE K. Gauthier, M. Alawie Abstract-- Ferroresonance is a complex nonlinear phenomenon that can greatly affect high voltage power transmission

More information

Great Northern Transmission Line: Behind the (Electrical) Design

Great Northern Transmission Line: Behind the (Electrical) Design Great Northern Transmission Line: Behind the (Electrical) Design November 8, 2017 Christian Winter, P.E. Minnesota Power Sivasis Panigrahi, P.E. POWER Engineers, Inc. What is the Great Northern Transmission

More information

Transient Recovery Voltage (TRV) and Rate of Rise of Recovery Voltage (RRRV) of Line Circuit Breakers in Over Compensated Transmission Lines

Transient Recovery Voltage (TRV) and Rate of Rise of Recovery Voltage (RRRV) of Line Circuit Breakers in Over Compensated Transmission Lines Transient Recovery Voltage (TRV) and Rate of Rise of Recovery Voltage (RRRV) of Line Circuit Breakers in Over Compensated Transmission Lines Presenter Mark McVey C4/B5.41 INTERNATIONAL COUNCIL ON LARGE

More information

Transmission Interconnection Requirements for Inverter-Based Generation

Transmission Interconnection Requirements for Inverter-Based Generation Transmission Requirements for Inverter-Based Generation June 25, 2018 Page 1 Overview: Every generator interconnecting to the transmission system must adhere to all applicable Federal and State jurisdictional

More information

P. Larivière, Hydro-Québec, D. Vinet, SNC-Lavalin Inc.

P. Larivière, Hydro-Québec, D. Vinet, SNC-Lavalin Inc. An evaluation of the short-circuit transient current on circuit breakers for the Hydro-Québec sub-transmission network in the presence of subsynchronous phenomenon of the 735 kv series compensated transmission

More information

POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS.

POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS. POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS. This document may be subject to changes. Contact ARTECHE to confirm the characteristics and availability of the products

More information

Insulation Co-ordination For HVDC Station

Insulation Co-ordination For HVDC Station Insulation Co-ordination For HVDC Station Insulation Co-ordination Definitions As per IEC 60071 Insulation Coordination is defined as selection of dielectric strength of equipment in relation to the operating

More information

A Process for Evaluating the Degree of Susceptibility of a fleet of Power Transformers to Effects of GIC

A Process for Evaluating the Degree of Susceptibility of a fleet of Power Transformers to Effects of GIC 1 A Process for Evaluating the Degree of Susceptibility of a fleet of Power Transformers to Effects of GIC Ramsis Girgis, Kiran Vedante, and Gary Burden ABB Power Transformers Abstract: There has been

More information

Evaluation of coupling between dc and ac transmission lines on the same right-of-way: Parametric analysis and mitigation methods

Evaluation of coupling between dc and ac transmission lines on the same right-of-way: Parametric analysis and mitigation methods Abstract: Evaluation of coupling between dc and ac transmission lines on the same right-of-way: Parametric analysis and mitigation methods Jingxuan (Joanne) Hu RBJ Engineering Corp. Winnipeg, MB, Canada

More information

Capacitive Voltage Substations Ferroresonance Prevention Using Power Electronic Devices

Capacitive Voltage Substations Ferroresonance Prevention Using Power Electronic Devices Capacitive Voltage Substations Ferroresonance Prevention Using Power Electronic Devices M. Sanaye-Pasand, R. Aghazadeh Applied Electromagnetics Research Excellence Center, Electrical & Computer Engineering

More information

AORC Technical meeting 2014

AORC Technical meeting 2014 http : //www.cigre.org B4-112 AORC Technical meeting 214 HVDC Circuit Breakers for HVDC Grid Applications K. Tahata, S. Ka, S. Tokoyoda, K. Kamei, K. Kikuchi, D. Yoshida, Y. Kono, R. Yamamoto, H. Ito Mitsubishi

More information

Problems connected with Commissioning of Power Transformers

Problems connected with Commissioning of Power Transformers Problems connected with Commissioning of Power Transformers ABSTRACT P Ramachandran ABB India Ltd, Vadodara, India While commissioning large Power Transformers, certain abnormal phenomena were noticed.

More information

ANEW, simple and low cost scheme to reduce transformer

ANEW, simple and low cost scheme to reduce transformer 950 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 20, NO. 2, APRIL 2005 A Sequential Phase Energization Technique for Transformer Inrush Current Reduction Part II: Theoretical Analysis and Design Guide Wilsun

More information

Real Time Implementation of Transmission Line Controlled Switching

Real Time Implementation of Transmission Line Controlled Switching 1 Real Time Implementation of Transmission Line Controlled Switching K. M. C. Dantas, W. L. A. Neves, D. Fernandes Jr., G. A. Cardoso, L. C. Fonseca Abstract A method for controlled switching of line circuit

More information

Phase Shifter Application Workshop. Siemens Energy, Inc.

Phase Shifter Application Workshop. Siemens Energy, Inc. Phase Shifter Application Workshop Siemens Energy, Inc. PJM Power Pool, March, 2015 siemens.com/energy Phase Shifter Application Workshop Phase Shifting Transformers Principles, Design Aspects and Operation

More information

ATC s Mackinac Back to Back. Summary

ATC s Mackinac Back to Back. Summary ATC s Mackinac Back to Back HVDC Project Update Michael B. Marz American Transmission Company Summary The Need For Flow Control at Mackinac Mackinac Flow Control Requirements Available Flow Control Technologies

More information

Effects of GIC on Power Transformers and Power Systems

Effects of GIC on Power Transformers and Power Systems Effects of GIC on Power Transformers and Power Systems Prepared by Dr. Ramsis Girgis and Kiran Vedante (USA) in the name of CIGRE SC A2 Background There has been some misconception in the electric power

More information

Methods to Enable Open-Loop Synchronization For Islanded Systems

Methods to Enable Open-Loop Synchronization For Islanded Systems Methods to Enable Open-Loop Synchronization For Islanded Systems by Yaxiang Zhou A thesis submitted in partial fulfillment of the requirements for the degree of Master of Science in Energy Systems Department

More information

HYBRID STATCOM SOLUTIONS IN RENEWABLE SYSTEMS

HYBRID STATCOM SOLUTIONS IN RENEWABLE SYSTEMS HYBRID STATCOM SOLUTIONS IN RENEWABLE SYSTEMS Enrique PÉREZ Santiago REMENTERIA Aitor LAKA Arteche Spain Arteche Spain Ingeteam Power Technology-Spain ep@arteche.es sr@arteche.es Aitor.Laka@ingeteam.com

More information

Preventing transformer saturation in static transfer switches A Real Time Flux Control Method

Preventing transformer saturation in static transfer switches A Real Time Flux Control Method W H I T E PA P E R Preventing transformer saturation in static transfer switches A Real Time Flux Control Method TM 2 SUPERSWITCH 4 WITH REAL TIME FLUX CONTROL TM Preventing transformer saturation in static

More information

Ferroresonance in MV Voltage Transformers: Pragmatic experimental approach towards investigation of risk and mitigating strategy

Ferroresonance in MV Voltage Transformers: Pragmatic experimental approach towards investigation of risk and mitigating strategy Ferroresonance in MV Voltage Transformers: Pragmatic experimental approach towards investigation of risk and mitigating strategy W. Piasecki, M. Stosur, T. Kuczek, M. Kuniewski, R. Javora Abstract-- Evaluation

More information

ANALYSIS OF VOLTAGE TRANSIENTS IN A MEDIUM VOLTAGE SYSTEM

ANALYSIS OF VOLTAGE TRANSIENTS IN A MEDIUM VOLTAGE SYSTEM ANALYSIS OF VOLTAGE TRANSIENTS IN A MEDIUM VOLTAGE SYSTEM Anna Tjäder Chalmers University of Technology anna.tjader@chalmers.se Math Bollen Luleå University of Technology math.bollen@stri.se ABSTRACT Power

More information

DISTRIBUTION SYSTEM VOLTAGE SAGS: INTERACTION WITH MOTOR AND DRIVE LOADS

DISTRIBUTION SYSTEM VOLTAGE SAGS: INTERACTION WITH MOTOR AND DRIVE LOADS DISTRIBUTION SYSTEM VOLTAGE SAGS: INTERACTION WITH MOTOR AND DRIVE LOADS Le Tang, Jeff Lamoree, Mark McGranaghan Members, IEEE Electrotek Concepts, Inc. Knoxville, Tennessee Abstract - Several papers have

More information

Although shunt capacitors

Although shunt capacitors INSIDE PQ The Trouble With Capacitors Part 1 Switching capacitors seems like a simple proposition, but it can lead to some very interesting problems By R. Fehr, P.E., Engineering Consultant Although shunt

More information

Relevant Factors to a Statistical Analysis of Overvoltages - Application to Three-Phase Reclosing of Compensated Transmission Lines

Relevant Factors to a Statistical Analysis of Overvoltages - Application to Three-Phase Reclosing of Compensated Transmission Lines Energy and Power Engineering, 2013, 5, 1165-1171 doi:10.4236/epe.2013.54b221 Published Online July 2013 (http://www.scirp.org/journal/epe) Relevant Factors to a Statistical Analysis of Overvoltages - Application

More information

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES Highgate Converter Overview Prepared by Joshua Burroughs & Jeff Carrara IEEE PES Highgate Converter Abstract Introduction to HVDC Background on Highgate Operation and Control schemes of Highgate 22 Why

More information

Keywords: Transformer, differential protection, fuzzy rules, inrush current. 1. Conventional Protection Scheme For Power Transformer

Keywords: Transformer, differential protection, fuzzy rules, inrush current. 1. Conventional Protection Scheme For Power Transformer Vol. 3 Issue 2, February-2014, pp: (69-75), Impact Factor: 1.252, Available online at: www.erpublications.com Modeling and Simulation of Modern Digital Differential Protection Scheme of Power Transformer

More information

Alternative Testing Techniques for Current Transformers. Dinesh Chhajer, PE Technical Support Group MEGGER

Alternative Testing Techniques for Current Transformers. Dinesh Chhajer, PE Technical Support Group MEGGER Alternative Testing Techniques for Current Transformers Dinesh Chhajer, PE Technical Support Group MEGGER Agenda Current Transformer Definition and Fundamentals Current Transformer Applications o Metering

More information

CIRCUIT BREAKERS TRANSIENT REDUCTION BY USING A DEDICATED CONTROLLED SWITCHING SYSTEM

CIRCUIT BREAKERS TRANSIENT REDUCTION BY USING A DEDICATED CONTROLLED SWITCHING SYSTEM CIRCUIT BREAKERS TRANSIENT REDUCTION BY USING A DEDICATED CONTROLLED SWITCHING SYSTEM Virginia Ivanov Maria Brojboiu Sergiu Ivanov University of Craiova Faculty of Electrical Engineering Faculty of Electrical

More information

LIMITS FOR TEMPORARY OVERVOLTAGES IN ENGLAND AND WALES NETWORK

LIMITS FOR TEMPORARY OVERVOLTAGES IN ENGLAND AND WALES NETWORK LIMITS FOR TEMPORARY OEROLTAGES IN ENGLAND AND WALES NETWORK This document is for internal and contract specific use only. Disclaimer NGG and NGET or their agents, servants or contractors do not accept

More information

Application for A Sub-harmonic Protection Relay. ERLPhase Power Technologies

Application for A Sub-harmonic Protection Relay. ERLPhase Power Technologies Application for A Sub-harmonic Protection Relay ERLPhase Power Technologies 1 Outline Introduction System Event at Xcel Energy Event Analysis Microprocessor based relay hardware architecture Sub harmonic

More information

Analysis of a 405 km transmission line with series compensation

Analysis of a 405 km transmission line with series compensation Analysis of a 405 km transmission line with series compensation by Dr. Rupert Gouws, North-West University This paper presents an investigative case study and energy efficiency analysis of the 405 km,

More information

NOVEL PROTECTION SYSTEMS FOR ARC FURNACE TRANSFORMERS

NOVEL PROTECTION SYSTEMS FOR ARC FURNACE TRANSFORMERS NOVEL PROTECTION SYSTEMS FOR ARC FURNACE TRANSFORMERS Ljubomir KOJOVIC Cooper Power Systems - U.S.A. Lkojovic@cooperpower.com INTRODUCTION In steel facilities that use Electric Arc Furnaces (EAFs) to manufacture

More information

Analyzing the Impact of Shunt Reactor Switching Operations Based on DFR Monitoring System

Analyzing the Impact of Shunt Reactor Switching Operations Based on DFR Monitoring System Analyzing the Impact of Shunt Reactor Switching Operations Based on DFR Monitoring System Lalit Ghatpande, SynchroGrid, College Station, Texas, 77840 Naveen Ganta, SynchroGrid, College Station, Texas,

More information

Delayed Current Zero Crossing Phenomena during Switching of Shunt-Compensated Lines

Delayed Current Zero Crossing Phenomena during Switching of Shunt-Compensated Lines Delayed Current Zero Crossing Phenomena during Switching of Shunt-Compensated Lines David K Olson Xcel Energy Minneapolis, MN Paul Nyombi Xcel Energy Minneapolis, MN Pratap G Mysore Pratap Consulting Services,

More information

Southern Company Interconnection Requirements for Inverter-Based Generation

Southern Company Interconnection Requirements for Inverter-Based Generation Southern Company Interconnection Requirements for Inverter-Based Generation September 19, 2016 Page 1 of 16 All inverter-based generation connected to Southern Companies transmission system (Point of Interconnection

More information

ATC s Mackinac Back-to-Back HVDC Project: Planning and Operation Considerations for Michigan s Eastern Upper and Northern Lower Peninsulas

ATC s Mackinac Back-to-Back HVDC Project: Planning and Operation Considerations for Michigan s Eastern Upper and Northern Lower Peninsulas 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2013 Grid of the Future Symposium ATC s Mackinac Back-to-Back HVDC Project: Planning and Operation Considerations for

More information

FERRORESONANCE SIMULATION STUDIES USING EMTP

FERRORESONANCE SIMULATION STUDIES USING EMTP FERRORESONANCE SIMULATION STUDIES USING EMTP Jaya Bharati, R. S. Gorayan Department of Electrical Engineering Institute of Technology, BHU Varanasi, India jbharatiele@gmail.com, rsgorayan.eee@itbhu.ac.in

More information

ENERGISING INRUSH CURRENT TRANSIENTS IN PARALLEL-CONNECTED TRANSFORMERS

ENERGISING INRUSH CURRENT TRANSIENTS IN PARALLEL-CONNECTED TRANSFORMERS ENERGISING INRUSH CURRENT TRANSIENTS IN PARALLEL-CONNECTED TRANSFORMERS Hana ABDULL HALIM B.T. PHUNG John FLETCHER University of New South Wales - AU University of New South Wales -AU University of New

More information

Ferroresonance Experience in UK: Simulations and Measurements

Ferroresonance Experience in UK: Simulations and Measurements Ferroresonance Experience in UK: Simulations and Measurements Zia Emin BSc MSc PhD AMIEE zia.emin@uk.ngrid.com Yu Kwong Tong PhD CEng MIEE kwong.tong@uk.ngrid.com National Grid Company Kelvin Avenue, Surrey

More information

A Special Ferro-resonance Phenomena on 3-phase 66kV VT-generation of 20Hz zero sequence continuous voltage

A Special Ferro-resonance Phenomena on 3-phase 66kV VT-generation of 20Hz zero sequence continuous voltage A Special Ferro-resonance Phenomena on 3-phase 66kV VT-generation of Hz zero sequence continuous voltage S. Nishiwaki, T. Nakamura, Y.Miyazaki Abstract When an one line grounding fault in a transmission

More information

Coil Products Beginnings 1960 State of the Art. Customer partnership around the globe. Continuous innovation since 1900

Coil Products Beginnings 1960 State of the Art. Customer partnership around the globe. Continuous innovation since 1900 Coil Products Coil Products Customer partnership around the globe More than 250,000 coil products delivered to more than 170 countries. More than 60 years of operational experience. 35,000 in Europe 13,000

More information

Excitation Systems THYRIPART. Compound-Excitation System for Synchronous Generators. Power Generation

Excitation Systems THYRIPART. Compound-Excitation System for Synchronous Generators. Power Generation Excitation Systems Compound-Excitation System for Synchronous Generators Power Generation Operating Characteristics Load dependent Short circuit supporting Low voltage gradient dv/dt Black start capability

More information

POWER SYSTEM TRANSIENTS Solution Techniques for Electromagetic Transients in Power Systems -.Jean Mahseredjian

POWER SYSTEM TRANSIENTS Solution Techniques for Electromagetic Transients in Power Systems -.Jean Mahseredjian SOLUTION TECHNIQUES FOR ELECTROMAGNETIC TRANSIENTS IN POWER SYSTEMS Jean École Polytechnique de Montréal, Montréal, Canada Keywords: Power system, control systems, linear systems, nonlinear power components,

More information

SINGLE-STAGE HIGH-POWER-FACTOR SELF-OSCILLATING ELECTRONIC BALLAST FOR FLUORESCENT LAMPS WITH SOFT START

SINGLE-STAGE HIGH-POWER-FACTOR SELF-OSCILLATING ELECTRONIC BALLAST FOR FLUORESCENT LAMPS WITH SOFT START SINGLE-STAGE HIGH-POWER-FACTOR SELF-OSCILLATING ELECTRONIC BALLAST FOR FLUORESCENT S WITH SOFT START Abstract: In this paper a new solution to implement and control a single-stage electronic ballast based

More information

A new control scheme for an HVDC transmission link with capacitorcommutated converters having the inverter operating with constant alternating voltage

A new control scheme for an HVDC transmission link with capacitorcommutated converters having the inverter operating with constant alternating voltage 21, rue d Artois, F-758 PARIS B4_16_212 CIGRE 212 http : //www.cigre.org A new control scheme for an HVDC transmission link with capacitorcommutated converters having the inverter operating with constant

More information

Control of Over-voltages on Hydro-Québec 735-kV Series-Compensated System During a Major Electro-mechanical Transient Disturbance.

Control of Over-voltages on Hydro-Québec 735-kV Series-Compensated System During a Major Electro-mechanical Transient Disturbance. Paper number: #014 Control of Over-voltages on Hydro-Québec 735-kV Series-Compensated System During a Major Electro-mechanical Transient Disturbance. Que Bui-Van Michel Rousseau Bui_Van.Que@hydro.qc.ca

More information

Validation of a Power Transformer Model for Ferroresonance with System Tests on a 400 kv Circuit

Validation of a Power Transformer Model for Ferroresonance with System Tests on a 400 kv Circuit Validation of a Power Transformer Model for Ferroresonance with System Tests on a 4 kv Circuit Charalambos Charalambous 1, Z.D. Wang 1, Jie Li 1, Mark Osborne 2 and Paul Jarman 2 Abstract-- National Grid

More information

2. Current interruption transients

2. Current interruption transients 1 2. Current interruption transients For circuit breakers or other switching facilities, transient voltages just after the current interruptions are of great concern with successful current breakings,

More information

POWER QUALITY A N D Y O U R B U S I N E S S THE CENTRE FOR ENERGY ADVANCEMENT THROUGH TECHNOLOGICAL I NNOVATION

POWER QUALITY A N D Y O U R B U S I N E S S THE CENTRE FOR ENERGY ADVANCEMENT THROUGH TECHNOLOGICAL I NNOVATION POWER QUALITY A N D Y O U R B U S I N E S S A SUMMARY OF THE POWER QUALITY REPORT PUBLISHED BY THE CENTRE FOR ENERGY ADVANCEMENT THROUGH TECHNOLOGICAL I NNOVATION H YDRO ONE NETWORKS INC SEPTEMBER 2014

More information

E N G I N E E R I N G M A N U A L

E N G I N E E R I N G M A N U A L 1 1 1.0 PURPOSE The purpose of this document is to define policy and provide engineering guidelines for the AP operating companies (Monongahela Power Company, The Potomac Edison Company, and West Penn

More information

How OSHA s New Transient Overvoltage Requirements Affect Work Practices. B.A. YEUNG, H. BRANCO Leidos Engineering, LLC USA

How OSHA s New Transient Overvoltage Requirements Affect Work Practices. B.A. YEUNG, H. BRANCO Leidos Engineering, LLC USA 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium How OSHA s New Transient Overvoltage Requirements Affect Work Practices B.A. YEUNG,

More information

DEPARTMENT OF EEE QUESTION BANK

DEPARTMENT OF EEE QUESTION BANK DEPARTMENT OF EEE QUESTION BANK (As Per AUT 2008 REGULATION) SUB CODE: EE1004 SUB NAME: POWER SYSTEM TRANSIENTS YEAR : IV SEM : VIII PREPARED BY J.S. MEGAVATHI AP/EEE UNIT-I SWITCHING TRANSIENTS 1.What

More information

ACS 1000 Transformer Failure Investigation. Nathan Schachter, Peng

ACS 1000 Transformer Failure Investigation. Nathan Schachter, Peng Investigation Nathan Schachter, Peng Objectives Learn what happened Explain why it happened Discuss solutions Suggest remedies so it does not happen again Prevention is the key to success 2 ACS 1000 VFD

More information

Modeling and electromagnetic transients study of two 1800MVA phase shifting transformers in the Italian transmission network

Modeling and electromagnetic transients study of two 1800MVA phase shifting transformers in the Italian transmission network Modeling and electromagnetic transients study of two 18MVA phase shifting transformers in the Italian transmission network Luigi Colla, Vincenzo Iuliani, Francesco Palone, Massimo Rebolini, Stefano Zunino

More information

The relationship between operating maintenance and lightning overvoltage in distribution networks based on PSCAD/EMTDC

The relationship between operating maintenance and lightning overvoltage in distribution networks based on PSCAD/EMTDC The relationship between operating maintenance and lightning overvoltage in distribution networks based on PSCAD/EMTDC Xiaojun Chena *, Wenjie Zhengb, Shu Huangc, Hui Chend Electric Power Research Institute

More information

Power Upgrading of Transmission Line by Injecting DC Power in to AC Line with the help of ZIG-ZAG Transformer

Power Upgrading of Transmission Line by Injecting DC Power in to AC Line with the help of ZIG-ZAG Transformer Power Upgrading of Transmission Line by Injecting DC Power in to AC Line with the help of ZIG-ZAG Transformer C.GOPI*, M.KISHOR** *(Department. of Electrical and Electronics Engineering, SVPCET, Puttur)

More information

Accurate Modeling of Core-Type Distribution Transformers for Electromagnetic Transient Studies

Accurate Modeling of Core-Type Distribution Transformers for Electromagnetic Transient Studies IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 17, NO. 4, OCTOBER 2002 969 Accurate Modeling of Core-Type Distribution Transformers for Electromagnetic Transient Studies Taku Noda, Member, IEEE, Hiroshi Nakamoto,

More information

RESEARCH ON CLASSIFICATION OF VOLTAGE SAG SOURCES BASED ON RECORDED EVENTS

RESEARCH ON CLASSIFICATION OF VOLTAGE SAG SOURCES BASED ON RECORDED EVENTS 24 th International Conference on Electricity Distribution Glasgow, 2-5 June 27 Paper 97 RESEARCH ON CLASSIFICATION OF VOLTAGE SAG SOURCES BASED ON RECORDED EVENTS Pengfei WEI Yonghai XU Yapen WU Chenyi

More information

Experimental Investigations and Calculations in 6-35 kv Networks with Various Neutral Conditions

Experimental Investigations and Calculations in 6-35 kv Networks with Various Neutral Conditions PQ20 June 16-18, 2010 Kuressaare Experimental Investigations and Calculations in 6-35 kv Networks with Various Neutral Conditions A. Shirkovets, A. Vasilyeva, A. Telegin LLC BOLID, Novosibirsk, Russia

More information

Generation Interconnection Requirements at Voltages 34.5 kv and Below

Generation Interconnection Requirements at Voltages 34.5 kv and Below Generation Interconnection Requirements at Voltages 34.5 kv and Below 2005 March GENERATION INTERCONNECTION REQUIREMENTS AT 34.5 KV AND BELOW PAGE 1 OF 36 TABLE OF CONTENTS 1. INTRODUCTION 5 1.1. Intent

More information

Validation of power plant transformers re-energization schemes in case of black-out by comparison between studies and field tests measurements

Validation of power plant transformers re-energization schemes in case of black-out by comparison between studies and field tests measurements Validation of power plant transformers re-energization schemes in case of black-out by comparison between studies and field tests measurements François-Xavier ZGAINSKI, Bruno CAILLAULT, Vincent-Louis RENOUARD

More information

VOLTAGE OSCILLATION TRANSIENTS CAUSED BY CAPACITOR BANKING ENERGIZING FOR POWER FACTOR CORRECTION IN THE POWER SYSTEM

VOLTAGE OSCILLATION TRANSIENTS CAUSED BY CAPACITOR BANKING ENERGIZING FOR POWER FACTOR CORRECTION IN THE POWER SYSTEM VOLTAGE OSCILLATION TRANSIENTS CAUSED BY CAPACITOR BANKING ENERGIZING FOR POWER FACTOR CORRECTION IN THE POWER SYSTEM Dolly Chouhan 1, Kasongo Hyacinthe Kapumpa 2, Ajay Chouhan 3 1 M. Tech. Scholar, 2

More information

Should we transform our lines to HVDC?

Should we transform our lines to HVDC? Should we transform our lines to HVDC? HVDC versushvac Gaurav Dabhi 1, Nishit Sanghvi 2, Pinkesh Patel 3 1 Electrical Eng., G.H. Patel college of Eng. & Tech., dabhi60@gmail.com 2 Electrical Eng., G.H.

More information

DC current interruption tests with HV mechanical DC circuit breaker

DC current interruption tests with HV mechanical DC circuit breaker http: //www.cigre.org CIGRÉ A3/B4-124 CIGRÉ Winnipeg 2017 Colloquium Study Committees A3, B4 & D1 Winnipeg, Canada September 30 October 6, 2017 DC current interruption tests with HV mechanical DC circuit

More information

PREVENTING FLASHOVER NEAR A SUBSTATION BY INSTALLING LINE SURGE ARRESTERS

PREVENTING FLASHOVER NEAR A SUBSTATION BY INSTALLING LINE SURGE ARRESTERS 29 th International Conference on Lightning Protection 23 rd 26 th June 2008 Uppsala, Sweden PREVENTING FLASHOVER NEAR A SUBSTATION BY INSTALLING LINE SURGE ARRESTERS Ivo Uglešić Viktor Milardić Božidar

More information

Power System Impacts of Geomagnetic Disturbances

Power System Impacts of Geomagnetic Disturbances 1 Power System Impacts of Geomagnetic Disturbances Thomas J. Overbye Fox Family Professor of Electrical l and Computer Engineering i University of Illinois at Urbana Champaign overbye@illinois.edu September

More information

STRAY FLUX AND ITS INFLUENCE ON PROTECTION RELAYS

STRAY FLUX AND ITS INFLUENCE ON PROTECTION RELAYS 1 STRAY FLUX AND ITS INFLUENCE ON PROTECTION RELAYS Z. GAJIĆ S. HOLST D. BONMANN D. BAARS ABB AB, SA Products ABB AB, SA Products ABB AG, Transformers ELEQ bv Sweden Sweden Germany Netherlands zoran.gajic@se.abb.com

More information

Modeling for the Calculation of Overvoltages Stressing the Electronic Equipment of High Voltage Substations due to Lightning

Modeling for the Calculation of Overvoltages Stressing the Electronic Equipment of High Voltage Substations due to Lightning Modeling for the Calculation of Overvoltages Stressing the Electronic Equipment of High Voltage Substations due to Lightning M. PSALIDAS, D. AGORIS, E. PYRGIOTI, C. KARAGIAΝNOPOULOS High Voltage Laboratory,

More information

Relay Protection of EHV Shunt Reactors Based on the Traveling Wave Principle

Relay Protection of EHV Shunt Reactors Based on the Traveling Wave Principle Relay Protection of EHV Shunt Reactors Based on the Traveling Wave Principle Jules Esztergalyos, Senior Member, IEEE Abstract--The measuring technique described in this paper is based on Electro Magnetic

More information

Sequence Networks p. 26 Sequence Network Connections and Voltages p. 27 Network Connections for Fault and General Unbalances p. 28 Sequence Network

Sequence Networks p. 26 Sequence Network Connections and Voltages p. 27 Network Connections for Fault and General Unbalances p. 28 Sequence Network Preface p. iii Introduction and General Philosophies p. 1 Introduction p. 1 Classification of Relays p. 1 Analog/Digital/Numerical p. 2 Protective Relaying Systems and Their Design p. 2 Design Criteria

More information

Modeling insulation in high-voltage substations

Modeling insulation in high-voltage substations 38 ABB REVIEW DESIGNED FOR SAFETY DESIGNED FOR SAFETY Modeling insulation in high-voltage substations The goal of insulation coordination is to determine the dielectric strength of transformers and other

More information

Z-SOURCE INVERTER BASED DVR FOR VOLTAGE SAG/SWELL MITIGATION

Z-SOURCE INVERTER BASED DVR FOR VOLTAGE SAG/SWELL MITIGATION Z-SOURCE INVERTER BASED DVR FOR VOLTAGE SAG/SWELL MITIGATION 1 Arsha.S.Chandran, 2 Priya Lenin 1 PG Scholar, 2 Assistant Professor 1 Electrical & Electronics Engineering 1 Mohandas College of Engineering

More information

New Intellectual Networks (Smart Grid) for Detecting Electrical Equipment Faults, Defects and Weaknesses

New Intellectual Networks (Smart Grid) for Detecting Electrical Equipment Faults, Defects and Weaknesses Smart Grid and Renewable Energy, 2012, 3, 159-164 http://dx.doi.org/10.4236/sgre.2012.33023 Published Online August 2012 (http://www.scirp.org/ournal/sgre) 159 New Intellectual Networks (Smart Grid) for

More information