Power and Instrument Transformer Failures Root Causes and Modern Methods Used to Mitigate Risk. IEEE-NCS,IAS/PES (March 2017)

Size: px
Start display at page:

Download "Power and Instrument Transformer Failures Root Causes and Modern Methods Used to Mitigate Risk. IEEE-NCS,IAS/PES (March 2017)"

Transcription

1 Power and Instrument Transformer Failures Root Causes and Modern Methods Used to Mitigate Risk Tamer Abdelazim, PhD, PEng Senior Member, IEEE Eaton Corporation 2611 Hopewell Pl NE Calgary, AB T1Y 3Z8 Scott Basinger, P.Eng. Senior Member, IEEE Eaton Corporation Street NW Edmonton, AB T5V 1E4 IEEE-NCS,IAS/PES (March 2017) Outline Introduction Power Transformer & VT Failure Underlying Concepts Baseline Testing Solution Design Solution Testing Conclusions 2

2 Introduction Over the past few years there have been a number of high profile failures of Power Transformers and Voltage Transformers in medium voltage (5-38kV) applications. These failures have become more frequent because of changes in equipment selection and design in associated power systems. For MV Power Transformers, failures have generally been associated with circuit breaker transient switching: Modern MV Breakers chop current on opening, and pre-strike current on closing. High di/dt interacts with the circuit system characteristic producing a transient voltage of high frequency and high voltage, sometimes exceeding the TRV / RRRV withstand of the breaker, and the BIL rating of the transformer. Dry-type or Low BIL more susceptable, but oil-filled not immune. Short cable or bus connection to transformer. 3 Introduction Most applications do not require mitigation (RC snubbers), but some design choices will make the issue more likely: higher DOE energy-efficient transformers, shorter distance between MV breaker and transformer, dry-type MV transformers with lower BIL designs, MV breaker Vacuum Interrupters designed with higher (>5A) current chop. Switching Transient Studies can help identify the risk before it becomes a problem. 4

3 Introduction For PTs/VTs (Potential Transformers / Voltage Transformers), switching transients can lead to failure as well, although based on our experience, this is the least common mode of failure. The mode of failure we`ve started to see as a more common mode of failure in the field is due to ferroresonance. IEEE Standard defines ferroresonance as A phenomenon usually characterized by overvoltages and very irregular wave shapes, and associated with the excitation of one or more saturable inductors in series with capacitance. In a ferroresonant circuit, the capacitance Xc can be the capacitance of the cable, overhead lines, or stray capacitance of transformer windings or bushings. Under normal circumstances Xc is smaller than XL. In a switching event, voltage can increase, driving the transformer core into saturation and XL is lowered. This `jolts` the transformer XL into a lower saturated value where XL = Xc and ferroresonance starts. 5 Introduction After the upstream breaker opens, there will be a DC trapped voltage on the open line. This trapped voltage can be high enough to saturate the PT and `ring` with a square waveform. This phenomenon is made worse on an under-loaded PT. Modern protective relays have very low burdens compared to electromechanical. The combination of the two design characteristics can lead to some fairly costly failures. Study is required to determine when, but failures observed in the field are typically associated with longer lines and low burdens on switchgear PTs. Can mitigate by several methods to burden the PTs such as loading resistors, saturable reactor (new approach), or a frequency relay tied to a resistor and a timer. 6

4 Transient Overvoltages: 3 Problems Transient Overvoltage (TOV and/or dv/dt) Condition (magnitude and frequency) on Power Transformers leading to Failures. Transient Recovery Voltage (TRV), Rate of Rise of Recovery Voltage (RRRV) important to proper Vacuum Circuit Breaker interruption. PT Ferroresonance due to saturation in VCB switching operations. 7 Introduction Forensic evidence and history of failures Underlying concepts Predicting performance with simulations Mitigating the transients with snubbers Custom designing the snubber Snubber performance measurements 8

5 Unique Case Forensic Evidence Four electricians simultaneously opened four 26kV VCBs simulate utility outage systems transferred to standby generation loud pop in Sub Rm B the relay for VCB feeding transformer TB3 signaled trip Minutes later, two electricians simultaneously closed two 26kV VCBs breakers to Sub Rm A transformer TA3 failed catastrophically 9 Transformer Failure #1 De-energization Examination of primary windings Flash and burn marks on b-phase at bottom & middle Bottom - Indicate a coil-to-coil flashover (high dv/dt) Middle cable used to make delta swung free (lack of support) Transformer passed BIL test at 150kV but failed at 162kV Both failed units: 40 feet of cable High efficiency design VCB switching 10

6 Transformer Failure #2 - Energization Examination of primary windings Coil-to-coil tap burn off Winding showed an upward twist Burn marks from the initial blast Transient on first turns of windings 11 History of Failures Forensic Review Circuit Transformer*** Case Facility Voltage Cable Feet Bil Type Arrester Failure Mode Vacuum Breaker Vendor Switching 1* Hydro Dam Dry No 1st turn A Close 2 Hospital Dry No 1st turn A Close 3 Railroad Liquid N/A middle A Open 4 Data Center Cast coil Yes 1st turn B Close/Open Cast coil Yes None B Close 5 Oil Field Dry No 1st turn C Close 6** Oil Drill Ship <30 75 Cast coil Yes 1st turn C Close Notes: * = 40-50yrs. old with new breaker. ** = 2 yrs. old. All others new. *** = All transformers unloaded or lightly loaded when switched. 12

7 Common Parameters Rules of Thumb to screen applications: Generally, short distance between circuit breaker and transformer about 200 feet or less Dry-type transformer oil filled and cast coil not immune and low BIL Inductive load being switched transformer, motor, etc. (light load or no load) Circuit breaker switching characteristics: chop (vacuum or SF6) or restrike (vacuum) 13 Underlying Concepts - Current Chop VCB opens, arc burns metal vapor Heat supplied by current As current goes to zero, metal vapor ceases Arc ceases or chops All breaker chop current low end 3 5A high end 21A Contact Material Average (A) Maximum (A) CU Ag 4 7 Cr 7 16 W Cr-Cu (75 wt %) Modern VI 3 5 Cr-Cu-Bi (5 wt %) 1 3 Cr-Cu-Sb (9 wt %) 4 11 Cu-Bi (0.15 wt %) Older VI 6 21 WC-Ag (50 wt %) W-Cu (30 wt %) 5 10 Co-AG-SE Cu-Bi-Pb 1 9 6A current chop 14

8 Reignition and Voltage Escalation Current chop plus system C and L imposes high frequency TRV on VCB contacts If TRV exceeds breaker rated TRV, then reignition occurs VCB closes and then opens high frequency current Multiple reignitions lead to voltage escalation 15 Switching inductive circuits Current cannot change instantaneously in an inductor (conservation of energy) Energy Equation ½ LI 2 = ½ CV 2 or V = I L/C Vtransient = Venergy + Vdc + Vosc Venergy is from the Energy Equation Vdc = DC Off-set due to system X/R Vosc = the Oscillatory Ring Wave 16

9 Predicting Performance EMTP Simulations For purposes of screening applications for damaging TOVs Source, breaker, cable and transformer modeled Breaker models for current chop and re-ignition U R UTIL X UTIL UT C1 L CABLE R CABLE C2 T1 L TRAN R TRAN N:1 T2 UN V UTIL C/2 C/2 CH CL R LRG SYSTEM SOURCE AT 13.8 KV VCB BKR CABLE 13.8KV TRANSFORMER 17 Matching model to measurements 3 x 2865KW Gens Vacuum Breaker Short Cable 30KV BIL 1185KVA 630A 1865KW motors V max of 4.96kV < 30kV BIL Oscillation of 20.2kHz 18

10 Transient Mitigation Surge Arrester Overvoltage protection (magnitude only) Surge Arrester + Surge Capacitor Overvoltage protection Slows down rate-of-rise Surge Arrester + RC Snubber Overvoltage protection Slows down rate-of-rise Reduces DC offset and provides damping 19 Breaker opening followed by reignition C TRV exceeds limit C R = 40ohm C = 0.5uF TRV within limit 20

11 A Borderline Case Tier III Data Center 2x 24.8kV lines 2 x 12.5MVA service 13.2kV ring bus 2 x 2250KW generators 6 x 3750KVA cast-coil transformers 90kV BIL VCBs on primary side ft. cables 123kV 969Hz R = 30ohm C = 0.25uF 38.6kV 215Hz 21 Switching a Highly Inductive Circuit UTILITY 4713MVA 3PH SC 9.26 X/R 138KV 1600A 13OHM 50/66/83MVA 135.3/26.4KV 7.5%Z 27KV SF-6 BREAKER 2000A ALUMINUM IPS BUS 53FEET 386kV 1217Hz Vacuum Breaker Short Bus 200KV BIL AUTO LTC 56MVA 27-10KV 3.3%Z VACUUM BREAKER 1200A HEAVY DUTY COPPER PIPE 28FEET LMF XFMR 50/56MVA 25/.53KV 2.5%Z LMF 20MW 56.4kV 200Hz R = 100ohm C = 0.25uF 22

12 Concerns for the Industry VCB retrofit for primary load break switch (LBS) Units subs with LBS and no secondary main Arc flash issues on sec main (no room to install secondary main breaker) Retrofit VCB in LBS box solves AF issue VCB for rectifier (or isolation) transformer DC drives for feed water pumps VCB on primary Short run of cable to transformer (often dry type) New unit sub with primary VCB Metal enclosed vacuum switchgear 7500KVA transformer for gen boilers to meet EPA requirement 5 feet of bus 23 Test without snubber & with snubber Energize without snubber Oscillation continues beyond ¼ cycle Energize with snubber Oscillation well damped Transient followed by high frequency ring Transient near normal crest 24

13 VT failures Circuit configuration A site with a total of 25 SWGRs at 24.9kV A simplified one line diagram Each SWGR has two line-end VTs, one bus VT, and one bus CPT. The UTS breakers are VCBs The UPM devices are manually operated fused padmounted switches Failed VTs during commissioning Performed a comprehensive transient study analyzing transient overvoltage and ferroresonance coupled with test measurements 25 Line-end VT failures Two line-end VTs at 24.9 kv in the switchgear failed on Nov. 18, 2013 which initiated our investigation 26

14 Line-end VT failures When the dielectric rating of the insulation is exceeded, adjacent windings short together, heat and pressure build-up, and the VT housing ruptures. Could take days to weeks before the external evidence occurs. 27 Bus VT failures During the investigation, the bus VT for the same gear failed on Dec. 28,

15 VT Failures Ferroresonance and transient overvoltage Switching transients associated with circuit breakers observed for many years Breaker opening/closing interacts with the circuit elements producing ferroresonance or a transient overvoltage VTs and CPTs applied in system designs not seen 10 years ago We have investigated nearly 150 VT and CPT failures in past 3 years alone Failures may take hours, days or weeks to be detected Across all voltages 5kV, 15kV, 25kV and 35kV Failures not unique to any one manufacturer Mitigating the ferroresonance with damping resistors (conventional solution) with saturable reactors (specialized, custom solution) Mitigating the transient overvoltage RC snubber in combination with surge arrester 29 Underlying Concepts - Ferroresonance phenomenon and the VT When the source of current is interrupted, the trapped dc charge on the cables (capacitance) discharges into the VT VT Nonlinear inductance Dc trapped charge 30

16 Underlying Concepts - Simplified diagram The primary system circuit can be further simplified by lumping the system capacitance into a single representative capacitor and representing the inductance of the transformer as multiple smaller inductors in series. The over voltage across the primary winding is not equally distributed, resulting in high stress voltage differences across some of the windings. If the voltage difference between winding is in excess of their dielectric/insulation limits. VT Nonlinear inductance Dc trapped charge High stress 31 Underlying Concepts VT excitation curve Referring to the excitation diagram, one can see that it takes very little overvoltage to drive significantly higher excitation current through the thin primary conductors. With a turns ratio of 208/1, for only a 50% increase in voltage (180 V), the primary excitation current alone is 0.06 A (i.e / 208) or the full load rating of the primary winding. Amperes volts % 475% 4700 % 32

17 Baseline Testing - Instrumentation Test equipment includes voltage dividers and a transient recording device Voltage Dividers (Capacitive and resistive elements, 10MHz frequency response, SF6 insulated) Three-Phase Power Quality Recorder (Transient voltage waveshape sampling) 200 nsec sample resolution 5 Mhz sampling 33 Baseline Testing - UTS breaker opening Recorded Volts/Amps/Hz Zoomed Detail: 02/25/ :50:36-02/25/ :50: Measurement Volts Squarewaves with 17Hz :50: :50: :50: :50: :50: :50: HH:MM:SS.mmm V Waveform Avg AG V Waveform Avg BG V Waveform Avg CG [kv ] Simulation Squarewaves with 17-25Hz [s ] ase3.pl4; v :S1C :S1C 03B 03C (file C x-v ar t) 03A v v :S1C 34

18 Baseline Testing - UTS breaker opening Recorded Volts/Amps/Hz Zoomed Detail: 02/25/ :30:05-02/25/ :30: Measurement Volts Squarewaves with 10Hz :30: :30: :30: HH:MM:SS.m m m V Waveform Avg AN V Waveform Avg BN V Waveform Avg CN Squarewaves with 10Hz 35 Baseline Testing - UPM switch closing Recorded Volts/Amps/Hz Zoomed Detail: 02/27/ :39:33-02/27/ :39:33 300kV Measurement Volts :39: :39: :39: :39: :39: HH:MM:SS.mmm V Waveform Avg AN V Waveform Avg BN V Waveform Avg CN Recorded Volts/Amps/Hz Zoomed Detail: 02/27/ :26:18-02/27/ :26:18 430kV Measurement Volts :26: :26: :26: :26: :26: :26: HH:MM:SS.mmm V Waveform Avg AN V Waveform Avg BN V Waveform Avg CN 36

19 Solution Design Saturable Reactor + RC Snubbers + Surge Arresters Saturable Reactor (1) RC Snubber + Surge Arrester (2) VT Ohm Noninductive 22 kvpeak KJoules μ F at 27 kv SA Solution Design - Saturable Reactor Circuit The reactor is sized such that as Vs increases, the reactor saturates just before the VT. It is designed to absorb the high excitation current and act as a switch to insert its internal resistance. In addition to matching the magnetic characteristics to the specific VT, the reactor s internal resistance is tuned to the system parameters for critical damping. Since the reactor saturates before the VT and inserts its resistance into the secondary circuit, the VT never goes into saturation. Our modeling optimized the saturation characteristic and the resistance value. The high secondary current is reflected back into the primary, but it is such a short duration that it does not overheat the primary windings. IP Ip Is Xs Rp Rs Xp Is Ie R VP Xm Rm Vp Vs 38

20 Solution Design Saturable Reactor Desired Solution - only apply increased loading on the VT when it experiences ferroresonance. The saturable reactor on the secondary side of the VT only conducts current when the voltage begins to increase above its saturation voltage but below that of the VT s saturation voltage. An off the shelf reactor was initial used for testing, but produced worse results since it saturated below the secondary operating voltage of the VT premature saturation. Since the reactor saturates before the VT and inserts its resistance into the secondary circuit, the VT never goes into saturation. 39 Solution Design RC Snubber 27kV typical snubber & arrester voltage transformer protection non-inductive ceramic resistor 100 ohms Typically 25 to 100 ohms surge capacitor 0.25 μf - Typically 0.15 μf to 0.35 μf 3-phase 24.9kV solidly ground Surge Arrester Resistor 100Ohm Noninductive 22kVpeak 17.5KJoules 0.25μF at 27kV SA VT Surge Cap 40

21 Solution Design Damping Resistor A conventional solution was developed using damping resistors of 250W per phase Easily available Provided damping in 1200ms Can affect VT accuracy Will consume high power during steady state Requires switching circuit to be active only during ferroresonance * (file CaseRp.pl4; x-var t) v:s1c03a v:s1c03b v:s1c03c VT Voltage VT Power (file CaseRp.pl4; x-var t) v:r - 41 Solution Design Saturable Reactor The special design using saturable reactors Custom design Requires extensive simulations Provided damping in 250ms No affect on VT accuracy Will consume very small power during steady state No additional switching circuits required to make it work * (file CaseLp.pl4; x-var t) v:s1c03a v:s1c03b v:s1c03c VT Voltage VT Power (file CaseLp.pl4; x-var t) v:rl - 42

22 Solution Testing - UTS breaker opening Recorded Volts/Amps/Hz Zoomed Detail: 09/03/ :05:55-09/03/ :05: Measurement Volts [kv] :05: :05: HH:MM:SS.mmm V Waveform Avg AG V Waveform Avg BG V Waveform Avg CG Only 250ms Simulation [s] 0.25 (file Case_H_DesignE-Final1.pl4; x-var t) v:s1c03b v:s1c03a v:s1c03c 1 1 = saturable reactor 2 = snubber & arrester 43 Solution Testing - UTS breaker opening 100 Recorded Volts/Amps/Hz Zoomed Detail: 09/03/ :05:55-09/03/ :05: Measurement Volts [V] 75 14:05: :05: :05: HH:MM:SS.mmm V Waveform Avg AG V Waveform Avg BG V Waveform Avg CG 1 Only 250ms Simulation [s] 0.35 (file Cell3_inductor_H_Design.pl4; x-var t) v:tx0001- v:tx0003- v:tx = saturable reactor 2 = snubber & arrester 44

23 Solution Testing - UPM switch closing Recorded Volts/Amps/Hz Zoomed Detail: 09/03/ :42:15-09/03/ :42:15 220V Measurement Volts 0-50 F F Magnitude and Frequency are 14:42: :42: :42: HH:MM:SS.mmm V Waveform Avg AG V Waveform Avg BG V Waveform Avg CG well damped 150 [V] 125V Simulation [ms] 30 (file NM-1-Close-PD.pl4; x-var t) v:tx0001- v:tx0003- v:tx = saturable reactor 2 = snubber & arrester 45 Conclusions Failures due to MV breaker switching transients is on the increase due to higher efficiency transformers, installations with shorter cable lengths (~200ft or less), or VI s with high current chops (>5A). These failures can be mitigated by `hardened` transient resistant transformer designs, or RC snubbers a study is needed to identify the risk. System characteristics and nature of the switching can cause VT ferroresonance Damping resistors or saturable reactors both are able to mitigate ferroresonance 46

Surge Protection for Ladle Melt Furnaces

Surge Protection for Ladle Melt Furnaces Surge Protection for Ladle Melt Furnaces T.J. Dionise 1, S.A. Johnston 2 1 Eaton Electrical Group 130 Commonwealth Drive, Warrendale, PA, USA 15086 Phone: (724) 779-5864 Email: thomasjdionise@eaton.com

More information

Tab 2 Voltage Stresses Switching Transients

Tab 2 Voltage Stresses Switching Transients Tab 2 Voltage Stresses Switching Transients Distribution System Engineering Course Unit 10 2017 Industry, Inc. All rights reserved. Transient Overvoltages Decay with time, usually within one or two cycles

More information

Are snubbers required with Eaton s Cooper Power series liquid-filled hardened transformers?

Are snubbers required with Eaton s Cooper Power series liquid-filled hardened transformers? White Paper WP202001 COOPER POWER Are snubbers required with Eaton s Cooper Power series liquid-filled hardened transformers? SERIES Publication/ presentation details David D. Shipp P. E. CEO & Principal

More information

Shunt Reactor Switching

Shunt Reactor Switching Shunt Reactor Switching Dielectric stresses produced by circuit-breakers to shunt reactors. Presentation made during the IEEE Transformers Committee meeting, Amsterdam, Netherlands, April 2001 Presented

More information

Adi Mulawarman, P.E Xcel Energy Minneapolis, MN. Pratap G. Mysore, P.E Pratap Consulting Services, LLC Plymouth, MN

Adi Mulawarman, P.E Xcel Energy Minneapolis, MN. Pratap G. Mysore, P.E Pratap Consulting Services, LLC Plymouth, MN Effectiveness of Surge Capacitors on Transformer Tertiary connected shunt reactors in preventing failures- Field measurements and comparison with Transient study results Pratap G. Mysore, P.E Pratap Consulting

More information

DIFFERENCE BETWEEN SWITCHING OF MOTORS & GENERATORS WITH VACUUM TECHNOLOGY

DIFFERENCE BETWEEN SWITCHING OF MOTORS & GENERATORS WITH VACUUM TECHNOLOGY DIFFERENCE BETWEEN SWITCHING OF MOTORS & GENERATORS WITH VACUUM TECHNOLOGY Dr. Karthik Reddy VENNA Hong URBANEK Nils ANGER Siemens AG Germany Siemens AG Germany Siemens AG Germany karthikreddy.venna@siemens.com

More information

Relay Protection of EHV Shunt Reactors Based on the Traveling Wave Principle

Relay Protection of EHV Shunt Reactors Based on the Traveling Wave Principle Relay Protection of EHV Shunt Reactors Based on the Traveling Wave Principle Jules Esztergalyos, Senior Member, IEEE Abstract--The measuring technique described in this paper is based on Electro Magnetic

More information

ENGINEERING DATA SUBMITTAL For the Interconnection of Generation System

ENGINEERING DATA SUBMITTAL For the Interconnection of Generation System WHO SHOULD FILE THIS SUBMITTAL: Anyone in the final stages of interconnecting a Generation System with Nodak Electric Cooperative, Inc. This submittal shall be completed and provided to Nodak Electric

More information

Effects of Phase-Shifting Transformers, and Synchronous Condensers on Breaker Transient Recovery Voltages

Effects of Phase-Shifting Transformers, and Synchronous Condensers on Breaker Transient Recovery Voltages Effects of Phase-Shifting Transformers, and Synchronous Condensers on Breaker Transient Recovery Voltages Waruna Chandrasena, Bruno Bisewski, and Jeff Carrara Abstract-- This paper describes several system

More information

2. Current interruption transients

2. Current interruption transients 1 2. Current interruption transients For circuit breakers or other switching facilities, transient voltages just after the current interruptions are of great concern with successful current breakings,

More information

Switching Induced Transients:

Switching Induced Transients: Switching Induced Transients: Transformer switching is the most commonly performed operation in any power delivery system and most of the times this operation can be performed without any undesirable consequences.

More information

Do Capacitor Switching Transients Still Cause Problems?

Do Capacitor Switching Transients Still Cause Problems? Do Capacitor Switching Transients Still Cause Problems? Mark McGranaghan We have been evaluating problems related to capacitor switching transients for many years. Capacitor banks have been used on distribution

More information

(2) New Standard IEEE P (3) Core : (4) Windings :

(2) New Standard IEEE P (3) Core : (4) Windings : (d) Electrical characteristics (such as short-circuit withstand, commutating reactance, more number of windings, etc); (e) Longer life expectancy; (f) Energy efficiency; (g) more demanding environment.

More information

PART 1 OWNER/APPLICANT INFORMATION

PART 1 OWNER/APPLICANT INFORMATION CALHOUN COUNTY ELECTRIC COOP. ASSN. Application for Operation of Customer-Owned Generation This application should be completed as soon as possible and returned to the Cooperative in order to begin processing

More information

Owner/Customer Name: Mailing Address: City: County: State: Zip Code: Phone Number: Representative: Address: Fax Number:

Owner/Customer Name: Mailing Address: City: County: State: Zip Code: Phone Number: Representative:  Address: Fax Number: Interconnection of a Customer-Owned Renewable Generation System of Greater than 100 KW and Less than or Equal to 1 MW to the LCEC Electric Grid Tier 3 Application and Compliance Form Instructions: Complete

More information

High voltage engineering

High voltage engineering High voltage engineering Overvoltages power frequency switching surges lightning surges Overvoltage protection earth wires spark gaps surge arresters Insulation coordination Overvoltages power frequency

More information

FERRORESONANCE SIMULATION STUDIES USING EMTP

FERRORESONANCE SIMULATION STUDIES USING EMTP FERRORESONANCE SIMULATION STUDIES USING EMTP Jaya Bharati, R. S. Gorayan Department of Electrical Engineering Institute of Technology, BHU Varanasi, India jbharatiele@gmail.com, rsgorayan.eee@itbhu.ac.in

More information

EASTERN ILLINI ELECTRIC COOPERATIVE Application for Operation of Member-Owned Generation

EASTERN ILLINI ELECTRIC COOPERATIVE Application for Operation of Member-Owned Generation EASTERN ILLINI ELECTRIC COOPERATIVE Application for Operation of Member-Owned Generation This application is to be completed and returned to the Cooperative member service representative in order to begin

More information

SOUTH CENTRAL INDIANA REMC Application for Operation of Member-Owned Small Power Generation Systems

SOUTH CENTRAL INDIANA REMC Application for Operation of Member-Owned Small Power Generation Systems SOUTH CENTRAL INDIANA REMC Application for Operation of Member-Owned Small Power Generation Systems This application should be completed as soon as possible and returned to the Cooperative in order to

More information

HIGH VOLTAGE ENGINEERING(FEEE6402) LECTURER-24

HIGH VOLTAGE ENGINEERING(FEEE6402) LECTURER-24 LECTURER-24 GENERATION OF HIGH ALTERNATING VOLTAGES When test voltage requirements are less than about 300kV, a single transformer can be used for test purposes. The impedance of the transformer should

More information

thepower to protect the power to protect i-gard LITERATURE Low and medium voltage

thepower to protect  the power to protect i-gard LITERATURE Low and medium voltage thepower to protect i-gard LITERATURE Low and medium voltage distribution systems Arc Flash Hazards and High Resistance Grounding Grounding of Standby and Emergency Power Systems Neutral Grounding Resistors

More information

State of North Dakota Engineering data submittal Page 1 For interconnection of distributed generation to Otter Tail Power Company

State of North Dakota Engineering data submittal Page 1 For interconnection of distributed generation to Otter Tail Power Company Engineering data submittal Page 1 WHO SHOULD FILE THIS SUBMITTAL : Anyone in the final stages of in terconnecting a Generation System with Otter Tail Power. This submittal shall be completed and provided

More information

HIGH VOLTAGE CIRCUIT BREAKERS

HIGH VOLTAGE CIRCUIT BREAKERS HIGH VOLTAGE CIRCUIT BREAKERS Design and Applications Second Edition, Revised and Expanded RUBEN D. GARZON Square D Co. Smyrna, Tennessee MARCEL Ш D E К К E R MARCEL DEKKER, INC. NEW YORK BASEL CONTENTS

More information

APPLICATION FOR INTERCONNECTION & OPERATIONS OF MEMBER-OWNED GENERATION

APPLICATION FOR INTERCONNECTION & OPERATIONS OF MEMBER-OWNED GENERATION APPLICATION FOR INTERCONNECTION & OPERATIONS OF MEMBER-OWNED GENERATION This application should be completed and returned to in order to begin processing the request for interconnecting as required by

More information

Comparison of switching surges and basic lightning impulse surges at transformer in MV cable grids

Comparison of switching surges and basic lightning impulse surges at transformer in MV cable grids Comparison of switching surges and basic lightning impulse surges at transformer in MV cable grids Tarik Abdulahović #, Torbjörn Thiringer # # Division of Electric Power Engineering, Department of Energy

More information

POWER SYSTEM TRANSIENTS - Switching Overvoltages in Power Systems - Juan A. Martinez-Velasco, Jacinto Martin-Arnedo

POWER SYSTEM TRANSIENTS - Switching Overvoltages in Power Systems - Juan A. Martinez-Velasco, Jacinto Martin-Arnedo SWITCHING OVERVOLTAGES IN POWER SYSTEMS Juan A. Martinez-Velasco Universitat Politècnica de Catalunya, Barcelona, Spain Jacinto Martin-Arnedo Estabanell Energía, Granollers, Spain Keywords: Switching overvoltages,

More information

Conventional Paper-II-2011 Part-1A

Conventional Paper-II-2011 Part-1A Conventional Paper-II-2011 Part-1A 1(a) (b) (c) (d) (e) (f) (g) (h) The purpose of providing dummy coils in the armature of a DC machine is to: (A) Increase voltage induced (B) Decrease the armature resistance

More information

ANALYSIS OF VOLTAGE TRANSIENTS IN A MEDIUM VOLTAGE SYSTEM

ANALYSIS OF VOLTAGE TRANSIENTS IN A MEDIUM VOLTAGE SYSTEM ANALYSIS OF VOLTAGE TRANSIENTS IN A MEDIUM VOLTAGE SYSTEM Anna Tjäder Chalmers University of Technology anna.tjader@chalmers.se Math Bollen Luleå University of Technology math.bollen@stri.se ABSTRACT Power

More information

TECHNICAL BULLETIN 004a Ferroresonance

TECHNICAL BULLETIN 004a Ferroresonance May 29, 2002 TECHNICAL BULLETIN 004a Ferroresonance Abstract - This paper describes the phenomenon of ferroresonance, the conditions under which it may appear in electric power systems, and some techniques

More information

APPENDIX B: Generation Interconnection Application Form

APPENDIX B: Generation Interconnection Application Form 2 APPENDIX B: Generation Interconnection Application Form WHO SHOULD FILE THIS APPLICATION: Anyone expressing interest to install generation which will interconnect with Xcel Energy (Local electric utility)

More information

Calculation of Transient Overvoltages by using EMTP software in a 2-Phase 132KV GIS

Calculation of Transient Overvoltages by using EMTP software in a 2-Phase 132KV GIS Calculation of Transient Overvoltages by using EMTP software in a 2-Phase 132KV GIS M. Kondalu, Dr. P.S. Subramanyam Electrical & Electronics Engineering, JNT University. Hyderabad. Joginpally B.R. Engineering

More information

Safety through proper system Grounding and Ground Fault Protection

Safety through proper system Grounding and Ground Fault Protection Safety through proper system Grounding and Ground Fault Protection November 4 th, 2015 Presenter: Mr. John Nelson, PE, FIEEE, NEI Electric Power Engineering, Inc. Event to start shortly Scheduled time:

More information

Evaluating the Response of Surge Arresters

Evaluating the Response of Surge Arresters 1 Jens Schoene Chandra Pallem Tom McDermott Reigh Walling Evaluating the Response of Surge Arresters to Temporary Overvoltages Panel Session of the IEEE Wind and Solar Collector Design Working Group 2014

More information

A Study on Ferroresonance Mitigation Techniques for Power Transformer

A Study on Ferroresonance Mitigation Techniques for Power Transformer A Study on Ferroresonance Mitigation Techniques for Power Transformer S. I. Kim, B. C. Sung, S. N. Kim, Y. C. Choi, H. J. Kim Abstract--This paper presents a comprehensive study on the ferroresonance mitigation

More information

RESONANT TRANSFORMER

RESONANT TRANSFORMER RESONANT TRANSFORMER Whenever the requirement of the test voltage is too much high, a single unit transformer can not produce such high voltage very economically, because for high voltage measurement,

More information

FGJTCFWP"KPUVKVWVG"QH"VGEJPQNQI[" FGRCTVOGPV"QH"GNGEVTKECN"GPIKPGGTKPI" VGG"246"JKIJ"XQNVCIG"GPIKPGGTKPI

FGJTCFWPKPUVKVWVGQHVGEJPQNQI[ FGRCTVOGPVQHGNGEVTKECNGPIKPGGTKPI VGG246JKIJXQNVCIGGPIKPGGTKPI FGJTFWP"KPUKWG"QH"GEJPQNQI[" FGRTOGP"QH"GNGETKEN"GPIKPGGTKPI" GG"46"JKIJ"XQNIG"GPIKPGGTKPI Resonant Transformers: The fig. (b) shows the equivalent circuit of a high voltage testing transformer (shown

More information

McGill Power Sales & Engineering, INC.

McGill Power Sales & Engineering, INC. 1 McGill Power Sales & Engineering, INC. Power Factor Correction Terry McGill President McGill Power Sales & Engineering Inc. 2007 Eaton Corporation. All rights reserved. Agenda What is power factor? What

More information

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY 9. INTRODUCTION Control Cabling The protection and control equipment in power plants and substations is influenced by various of environmental conditions. One of the most significant environmental factor

More information

Although shunt capacitors

Although shunt capacitors INSIDE PQ The Trouble With Capacitors Part 1 Switching capacitors seems like a simple proposition, but it can lead to some very interesting problems By R. Fehr, P.E., Engineering Consultant Although shunt

More information

KNOW MORE ABOUT THE TRANSFORMERS. Glossary Transformers

KNOW MORE ABOUT THE TRANSFORMERS. Glossary Transformers KNOW MORE ABOUT THE TRANSFORMERS Glossary Transformers Ambient temperature The existing temperature of the atmosphere surrounding a transformer installation. Ampere The practical unit of electric current.

More information

Delayed Current Zero Crossing Phenomena during Switching of Shunt-Compensated Lines

Delayed Current Zero Crossing Phenomena during Switching of Shunt-Compensated Lines Delayed Current Zero Crossing Phenomena during Switching of Shunt-Compensated Lines David K Olson Xcel Energy Minneapolis, MN Paul Nyombi Xcel Energy Minneapolis, MN Pratap G Mysore Pratap Consulting Services,

More information

UNIT 4 PRINCIPLES OF CIRCUIT BREAKERS SVCET

UNIT 4 PRINCIPLES OF CIRCUIT BREAKERS SVCET UNIT 4 PRINCIPLES OF CIRCUIT BREAKERS Introduction Where fuses are unsuitable or inadequate, protective relays and circuit breakers are used in combination to detect and isolate faults. Circuit breakers

More information

ACS 1000 Transformer Failure Investigation. Nathan Schachter, Peng

ACS 1000 Transformer Failure Investigation. Nathan Schachter, Peng Investigation Nathan Schachter, Peng Objectives Learn what happened Explain why it happened Discuss solutions Suggest remedies so it does not happen again Prevention is the key to success 2 ACS 1000 VFD

More information

5. Black box arc modelling

5. Black box arc modelling 1 5. Black box arc modelling Circuit-breaker s performance in power system is analysed by representing the circuit-breaker characteristics by a function of electrical parameters such as current/voltage,

More information

Utility System Lightning Protection

Utility System Lightning Protection Utility System Lightning Protection Many power quality problems stem from lightning. Not only can the high-voltage impulses damage load equipment, but the temporary fault that follows a lightning strike

More information

Effects of Transient Recovery Voltages on Circuit Breaker Ratings

Effects of Transient Recovery Voltages on Circuit Breaker Ratings Effects of Transient Recovery Voltages on Circuit Breaker Ratings Term Project: - EE22 - Power System Transients. Spring 28 Instructor: - Dr. Bruce Mork Team: - Himanshu Bahirat Muhammad Ali Praveen KK

More information

Ferroresonance Experience in UK: Simulations and Measurements

Ferroresonance Experience in UK: Simulations and Measurements Ferroresonance Experience in UK: Simulations and Measurements Zia Emin BSc MSc PhD AMIEE zia.emin@uk.ngrid.com Yu Kwong Tong PhD CEng MIEE kwong.tong@uk.ngrid.com National Grid Company Kelvin Avenue, Surrey

More information

GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW

GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW ELECTRIC UTILITY CONTACT INFORMATION Consumers Energy Interconnection Coordinator 1945

More information

Power Quality and Reliablity Centre

Power Quality and Reliablity Centre Technical Note No. 8 April 2005 Power Quality and Reliablity Centre TRANSIENT OVERVOLTAGES ON THE ELECTRICITY SUPPLY NETWORK CLASSIFICATION, CAUSES AND PROPAGATION This Technical Note presents an overview

More information

EE 1402 HIGH VOLTAGE ENGINEERING

EE 1402 HIGH VOLTAGE ENGINEERING EE 1402 HIGH VOLTAGE ENGINEERING Unit 5 TESTS OF INSULATORS Type Test To Check The Design Features Routine Test To Check The Quality Of The Individual Test Piece. High Voltage Tests Include (i) Power frequency

More information

SWF DV/DT Solutions Sinewave Filters. N52 W13670 NORTHPARK DR. MENOMONEE FALLS, WI P. (262) F. (262)

SWF DV/DT Solutions Sinewave Filters. N52 W13670 NORTHPARK DR. MENOMONEE FALLS, WI P. (262) F. (262) SWF DV/DT Solutions Sinewave Filters N52 W13670 NORTHPARK DR. MENOMONEE FALLS, WI 53051 P. (262) 754-3883 F. (262) 754-3993 www.apqpower.com Does your application use variable frequency drives for improved

More information

A TECHNICAL REVIEW ON CAPACITOR BANK SWITCHING WITH VACUUM CIRCUIT BREAKERS

A TECHNICAL REVIEW ON CAPACITOR BANK SWITCHING WITH VACUUM CIRCUIT BREAKERS A TECHNICAL REVIEW ON CAPACITOR BANK SWITCHING WITH VACUUM CIRCUIT BREAKERS Shashi Kumar 1, Brajesh Kumar Prajapati 2, Vikramjeet Singh 3 1, 2 Students, Electrical Engineering Department Greater Noida

More information

Effect of High Frequency Cable Attenuation on Lightning-Induced Overvoltages at Transformers

Effect of High Frequency Cable Attenuation on Lightning-Induced Overvoltages at Transformers Voltage (kv) Effect of High Frequency Cable Attenuation on Lightning-Induced Overvoltages at Transformers Li-Ming Zhou, Senior Member, IEEE and Steven Boggs, Fellow, IEEE Abstract: The high frequency attenuation

More information

Medium voltage circuit breaker technical guide

Medium voltage circuit breaker technical guide IEC 56-1987 - ANSI C37-06 1987 COMPARISON CONTENTS page 1 - Rated voltage 3 2 - Rated isolating level 3 3 - Rated voltage during normal running 4 4 - Allowable short time current 4 5 - Allowable current

More information

Insulation Co-ordination For HVDC Station

Insulation Co-ordination For HVDC Station Insulation Co-ordination For HVDC Station Insulation Co-ordination Definitions As per IEC 60071 Insulation Coordination is defined as selection of dielectric strength of equipment in relation to the operating

More information

In power system, transients have bad impact on its

In power system, transients have bad impact on its Analysis and Mitigation of Shunt Capacitor Bank Switching Transients on 132 kv Grid Station, Qasimabad Hyderabad SUNNY KATYARA*, ASHFAQUE AHMED HASHMANI**, AND BHAWANI SHANKAR CHOWDHRY*** RECEIVED ON 1811.2014

More information

GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 2 MW

GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 2 MW GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 2 MW Electric Utility Contact Information DTE Energy Interconnection Coordinator One Energy Plaza, SB

More information

Modeling Ferroresonance Phenomena on Voltage Transformer (VT)

Modeling Ferroresonance Phenomena on Voltage Transformer (VT) Modeling Ferroresonance Phenomena on Voltage Transformer (VT) Mohammad Tolou Askari Department of Electrical Faculty of Engineering Universiti Putra Malaysia 43400 UPM Serdang, Selangor, Malaysia Abstract

More information

GIS Disconnector Switching Operation VFTO Study

GIS Disconnector Switching Operation VFTO Study GIS Disconnector Switching Operation VFTO Study Mariusz Stosur, Marcin Szewczyk, Wojciech Piasecki, Marek Florkowski, Marek Fulczyk ABB Corporate Research Center in Krakow Starowislna 13A, 31-038 Krakow,

More information

Modelling of Sf6 Circuit Breaker Arc Quenching Phenomena In Pscad

Modelling of Sf6 Circuit Breaker Arc Quenching Phenomena In Pscad Day 2 - Session IV-A High Voltage 163 Modelling of Sf6 Circuit Breaker Arc Quenching Phenomena In Pscad B. Kondala Rao, Gopal Gajjar ABB Ltd., Maneja, Vadodara, India Introduction Circuit breakers play

More information

DC VACUUM CIRCUIT BREAKER

DC VACUUM CIRCUIT BREAKER DC VACUUM CIRCUIT BREAKER Lars LILJESTRAND Magnus BACKMAN Lars JONSSON ABB Sweden ABB Sweden ABB Sweden lars.liljestrand@se.abb.com magnus.backman@se.abb.com lars.e.jonsson@se.abb.com Marco RIVA ABB Italy

More information

APQline Active Harmonic Filters. N52 W13670 NORTHPARK DR. MENOMONEE FALLS, WI P. (262) F. (262)

APQline Active Harmonic Filters. N52 W13670 NORTHPARK DR. MENOMONEE FALLS, WI P. (262) F. (262) APQline Active Harmonic Filters N52 W13670 NORTHPARK DR. MENOMONEE FALLS, WI 53051 P. (262) 754-3883 F. (262) 754-3993 www.apqpower.com Power electronic equipment and AC-DC power conversion equipment contribute

More information

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: IDAHO POWER COMPANY Designated Contact Person: Jeremiah Creason Address: 1221 W. Idaho Street, Boise ID 83702 Telephone

More information

Ferroresonance Conditions Associated With a 13 kv Voltage Regulator During Back-feed Conditions

Ferroresonance Conditions Associated With a 13 kv Voltage Regulator During Back-feed Conditions Ferroresonance Conditions Associated With a Voltage Regulator During Back-feed Conditions D. Shoup, J. Paserba, A. Mannarino Abstract-- This paper describes ferroresonance conditions for a feeder circuit

More information

A Special Ferro-resonance Phenomena on 3-phase 66kV VT-generation of 20Hz zero sequence continuous voltage

A Special Ferro-resonance Phenomena on 3-phase 66kV VT-generation of 20Hz zero sequence continuous voltage A Special Ferro-resonance Phenomena on 3-phase 66kV VT-generation of Hz zero sequence continuous voltage S. Nishiwaki, T. Nakamura, Y.Miyazaki Abstract When an one line grounding fault in a transmission

More information

Progress Report on Failures of High Voltage Bushings with Draw Leads By Jim McBride and Larry Coffeen, JMX Services / NEETRAC 7/26/2010

Progress Report on Failures of High Voltage Bushings with Draw Leads By Jim McBride and Larry Coffeen, JMX Services / NEETRAC 7/26/2010 The Team: Jim McBride: IEEE Member Larry Coffeen: IEEE Senior Member President, JMX Services, Inc. Senior Research Engineer, NEETRAC BS EE Georgia Tech BS EE Georgia Tech Testing, DAQ, and Measurement

More information

Protection Basics Presented by John S. Levine, P.E. Levine Lectronics and Lectric, Inc GE Consumer & Industrial Multilin

Protection Basics Presented by John S. Levine, P.E. Levine Lectronics and Lectric, Inc GE Consumer & Industrial Multilin Protection Basics Presented by John S. Levine, P.E. Levine Lectronics and Lectric, Inc. 770 565-1556 John@L-3.com 1 Protection Fundamentals By John Levine 2 Introductions Tools Outline Enervista Launchpad

More information

PQ for Industrial Benchmarking with various methods to improve. Tushar Mogre.

PQ for Industrial Benchmarking with various methods to improve. Tushar Mogre. General PQ: Power Quality has multiple issues involved. Thus, need to have some benchmarking standards. Very little is spoken about the LT supply installation within an industry. There is need to understand

More information

Ferroresonance in MV Voltage Transformers: Pragmatic experimental approach towards investigation of risk and mitigating strategy

Ferroresonance in MV Voltage Transformers: Pragmatic experimental approach towards investigation of risk and mitigating strategy Ferroresonance in MV Voltage Transformers: Pragmatic experimental approach towards investigation of risk and mitigating strategy W. Piasecki, M. Stosur, T. Kuczek, M. Kuniewski, R. Javora Abstract-- Evaluation

More information

CONTENTS. 1. Introduction Generating Stations 9 40

CONTENTS. 1. Introduction Generating Stations 9 40 CONTENTS 1. Introduction 1 8 Importance of Electrical Energy Generation of Electrical Energy Sources of Energy Comparison of Energy Sources Units of Energy Relationship among Energy Units Efficiency Calorific

More information

Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017

Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017 Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017 NAME: LOCATION: 1. The primitive self-inductance per foot of length

More information

A Pyrotechnic Fault Current Limiter Model for Transient Calculations in Industrial Power Systems

A Pyrotechnic Fault Current Limiter Model for Transient Calculations in Industrial Power Systems A Pyrotechnic Fault Current Limiter Model for Transient Calculations in Industrial Power Systems T. C. Dias, B. D. Bonatto, J. M. C. Filho Abstract-- Isolated industrial power systems or with high selfgeneration,

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements Division 502 Technical Applicability 1(1) Section 502.1 applies to: Expedited Filing Draft August 22, 2017 the legal owner of an aggregated generating facility directly connected to the transmission system

More information

WHITE PAPER. Medium Voltage On-Site Generation Overview. BY MIKE KIRCHNER Technical Support Manager at Generac Power Systems

WHITE PAPER. Medium Voltage On-Site Generation Overview. BY MIKE KIRCHNER Technical Support Manager at Generac Power Systems WHITE PAPER Medium Voltage On-Site Generation Overview BY MIKE KIRCHNER Technical Support Manager at Generac Power Systems INTRODUCTION It seems that just about everyone is looking for more power. As our

More information

Numbering System for Protective Devices, Control and Indication Devices for Power Systems

Numbering System for Protective Devices, Control and Indication Devices for Power Systems Appendix C Numbering System for Protective Devices, Control and Indication Devices for Power Systems C.1 APPLICATION OF PROTECTIVE RELAYS, CONTROL AND ALARM DEVICES FOR POWER SYSTEM CIRCUITS The requirements

More information

The InterNational Electrical Testing Association Journal. BY STEVE TURNER, Beckwith Electric Company, Inc.

The InterNational Electrical Testing Association Journal. BY STEVE TURNER, Beckwith Electric Company, Inc. The InterNational Electrical Testing Association Journal FEATURE PROTECTION GUIDE 64S Theory, Application, and Commissioning of Generator 100 Percent Stator Ground Fault Protection Using Low Frequency

More information

R10. IV B.Tech I Semester Regular/Supplementary Examinations, Nov/Dec SWITCH GEAR AND PROTECTION. (Electrical and Electronics Engineering)

R10. IV B.Tech I Semester Regular/Supplementary Examinations, Nov/Dec SWITCH GEAR AND PROTECTION. (Electrical and Electronics Engineering) R10 Set No. 1 Code No: R41023 1. a) Explain how arc is initiated and sustained in a circuit breaker when the CB controls separates. b) The following data refers to a 3-phase, 50 Hz generator: emf between

More information

Primary Metering. What is Primary Metering?

Primary Metering. What is Primary Metering? NWEMS Primary Metering August 22, 2018 Bill Unbehaun, Tacoma Power Exchanging Expertise Since 1893 What is Primary Metering? Metering energy flow past a point at high voltage above 600v Both PTs and CTs

More information

Ferroresonance on Transformer 13-kV Ungrounded Tertiary at Arab

Ferroresonance on Transformer 13-kV Ungrounded Tertiary at Arab Ferroresonance on Transformer 13-k Ungrounded Tertiary at Arab Gary L. Kobet, P.E. Tennessee alley Authority In October 1997, at TA s Arab AL 161k Substation, a distributor built a 13k switchyard to load

More information

7. INSPECTION AND TEST PROCEDURES

7. INSPECTION AND TEST PROCEDURES 7.1 Switchgear and Switchboard Assemblies A. Visual and Mechanical Inspection 1. Compare equipment nameplate data with drawings and specifications. 2. Inspect physical and mechanical condition. 3. Inspect

More information

DEPARTMENT OF EEE QUESTION BANK

DEPARTMENT OF EEE QUESTION BANK DEPARTMENT OF EEE QUESTION BANK (As Per AUT 2008 REGULATION) SUB CODE: EE1004 SUB NAME: POWER SYSTEM TRANSIENTS YEAR : IV SEM : VIII PREPARED BY J.S. MEGAVATHI AP/EEE UNIT-I SWITCHING TRANSIENTS 1.What

More information

+ 24V 3.3K - 1.5M. figure 01

+ 24V 3.3K - 1.5M. figure 01 ELECTRICITY ASSESSMENT 35 questions Revised: 08 Jul 2013 1. Which of the wire sizes listed below results in the least voltage drop in a circuit carrying 10 amps: a. 16 AWG b. 14 AWG c. 18 AWG d. 250 kcmil

More information

ABB Automation, Inc. Substation Automation & Protection Division Coral Springs, FL Allentown, PA

ABB Automation, Inc. Substation Automation & Protection Division Coral Springs, FL Allentown, PA ABB Automation, Inc. Substation Automation & Protection Division Coral Springs, FL Allentown, PA Instruction Leaflet 41-348.1H Effective: November 1997 Supersedes I.L. I.L. 41-348.1G, Dated January 1985

More information

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY WN U-60 Attachment C to Schedule 152, Page 1 SCHEDULE 152 APPLICATION FOR INTERCONNECTING A GENERATING FACILITY TIER 2 OR TIER 3 This Application is considered complete when it provides all applicable

More information

of the improved scheme is presented. Index Terms Inrush current, power quality, transformer.

of the improved scheme is presented. Index Terms Inrush current, power quality, transformer. 208 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 22, NO. 1, JANUARY 2007 A Sequential Phase Energization Method for Transformer Inrush Current Reduction Transient Performance and Practical Considerations

More information

Transient Recovery Voltage (TRV) and Rate of Rise of Recovery Voltage (RRRV) of Line Circuit Breakers in Over Compensated Transmission Lines

Transient Recovery Voltage (TRV) and Rate of Rise of Recovery Voltage (RRRV) of Line Circuit Breakers in Over Compensated Transmission Lines Transient Recovery Voltage (TRV) and Rate of Rise of Recovery Voltage (RRRV) of Line Circuit Breakers in Over Compensated Transmission Lines Presenter Mark McVey C4/B5.41 INTERNATIONAL COUNCIL ON LARGE

More information

TABLE OF CONTENT

TABLE OF CONTENT Page : 1 of 34 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia TABLE OF CONTENT SCOPE 3 REFERENCES

More information

Section 11: Power Quality Considerations Bill Brown, P.E., Square D Engineering Services

Section 11: Power Quality Considerations Bill Brown, P.E., Square D Engineering Services Section 11: Power Quality Considerations Bill Brown, P.E., Square D Engineering Services Introduction The term power quality may take on any one of several definitions. The strict definition of power quality

More information

Vacuum Interrupters for Medium Voltage

Vacuum Interrupters for Medium Voltage for Medium Voltage Reliable, Maintenance-Free and Environmentally Friendly Today, vacuum as an arc extinguishing medium provides the most cost-effective solution for medium-voltage circuit-breakers. Siemens

More information

The study of ferroresonance effects in electric power equipment

The study of ferroresonance effects in electric power equipment O.A. Ezechukwu, J.O. Ikelionwu / Journal of Engineering and Applied Sciences 6 () 7-77 Journal of Engineering and Applied Sciences 6 () 7-77 JOURNAL OF ENGINEERING AND APPLIED SCIENCES The study of ferroresonance

More information

ETAP PowerStation. Electrical Transient Analyzer Program. ETAP PowerStation. Short Circuit Analysis. ANSI Standard 3-Phase Fault Currents

ETAP PowerStation. Electrical Transient Analyzer Program. ETAP PowerStation. Short Circuit Analysis. ANSI Standard 3-Phase Fault Currents Page: 1 Electrical Transient Analyzer Program Short Circuit Analysis ANSI Standard 3-Phase Fault Currents Number of Buses: Swing Generator Load Total 1 0 4 5 Number of Branches: XFMR2 XFMR3 Reactor Line/Cable

More information

Industrial Electrician Level 3

Industrial Electrician Level 3 Industrial Electrician Level 3 Industrial Electrician Unit: C1 Industrial Electrical Code I Level: Three Duration: 77 hours Theory: Practical: 77 hours 0 hours Overview: This unit is designed to provide

More information

AORC Technical meeting 2014

AORC Technical meeting 2014 http : //www.cigre.org B4-112 AORC Technical meeting 214 HVDC Circuit Breakers for HVDC Grid Applications K. Tahata, S. Ka, S. Tokoyoda, K. Kamei, K. Kikuchi, D. Yoshida, Y. Kono, R. Yamamoto, H. Ito Mitsubishi

More information

Economical Solutions to Meet Harmonic Distortion Limits[4]

Economical Solutions to Meet Harmonic Distortion Limits[4] Economical Solutions to Meet Harmonic Distortion Limits[4] Abstract: The widespread adoption of variable frequency drive technology is allowing electricity to be utilized more efficiently throughout most

More information

FERRORESONANCE - its Occurrence and Control in Electricity Distribution Networks

FERRORESONANCE - its Occurrence and Control in Electricity Distribution Networks FERRORESONANCE - its Occurrence and Control in Electricity Distribution Networks by Alex Baitch FIEAust, CPEng Manager Network Capability, Integral Energy This paper was presented to the Annual Conference

More information

Understanding and Extracting Valuable Information from Basic and Advanced Power Transformer Testing Techniques

Understanding and Extracting Valuable Information from Basic and Advanced Power Transformer Testing Techniques Understanding and Extracting Valuable Information from Basic and Advanced Power Transformer Testing Techniques Charles Sweetser, Services Manager, PRIM Engineering, Waltham, Mass. Topics of Discussion

More information

ARC FLASH HAZARD ANALYSIS AND MITIGATION

ARC FLASH HAZARD ANALYSIS AND MITIGATION ARC FLASH HAZARD ANALYSIS AND MITIGATION J.C. Das IEEE PRESS SERIES 0N POWER ENGINEERING Mohamed E. El-Hawary, Series Editor IEEE IEEE PRESS WILEY A JOHN WILEY & SONS, INC., PUBLICATION CONTENTS Foreword

More information

Modeling insulation in high-voltage substations

Modeling insulation in high-voltage substations 38 ABB REVIEW DESIGNED FOR SAFETY DESIGNED FOR SAFETY Modeling insulation in high-voltage substations The goal of insulation coordination is to determine the dielectric strength of transformers and other

More information

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number: Address:

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number:  Address: NORTH CAROLINA INTERCONNECTION REQUEST Utility: Designated Contact Person: Address: Telephone Number: Fax: E-Mail Address: An is considered complete when it provides all applicable and correct information

More information

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control Spring 2014 Instructor: Kai Sun 1 References Saadat s Chapters 12.6 ~12.7 Kundur s Sections

More information