CHIEF ENGINEER PROCEDURE MANAGEMENT OF OVERLAPPING DESIGN AGREEMENT

Similar documents
ENGINEERING DRAWINGS MANAGEMENT POLICY (IFC/AS BUILTS)

DESIGN PRACTICE NOTE DESIGN/REVIEW REQUIREMENTS FOR TRACTION BONDING PLAN

TYPE APPROVAL PROCEDURE

Earthing Requirements for HV Transmission Structures

Drawing Management Standard

For the purposes of this document, the Engineering Consultant shall be referred to as the Engineer.

Herts Valleys Clinical Commissioning Group. Review of NHS Herts Valleys CCG Constitution

ELECTRICAL NETWORKS SPECIFICATION TECHNICAL SPECIFICATION FOR A 230V/110V AND 400V/110V TRANSFORMER

1 SERVICE DESCRIPTION

MESP TECHNICAL SPECIFICATION FOR AN ESSENTIAL SERVICES SUPPLY STEP UP TRANSFORMER

DESIGN PRACTICE NOTE GENERAL OCS SPECIFICATION UPDATE

Statement on variation of 900 MHz and 1800 MHz Wireless Telegraphy Act licences

Signalling Documentation and Drawings

Electrical Procedure No E032. Procedure No: ELE 032

WP197 Capacity Market Metering Test

CHAPTER 14: TRAFFIC SIGNAL STANDARDS Introduction and Goals Administration Standards Standard Attachments 14.

MESP TECHNICAL SPECIFICATION FOR AN AUXILIARY OR ESSENTIAL SERVICES AND AUXILIARY TRANSFORMER FOR USE IN A RAILWAY SUBSTATION

Fiscal 2007 Environmental Technology Verification Pilot Program Implementation Guidelines

Section Meetings Section Material and Equipment. None Required

The Corporation of the City of Nelson Office of the Finance and Purchasing Manager Telephone : (250) Fax : (250)

TECHNICAL MEMORANDUM

Specification For. Asset Information Pr8701

SATELLITE NETWORK NOTIFICATION AND COORDINATION REGULATIONS 2007 BR 94/2007

Definition of Bulk Electric System Phase 2

Level 1 VRQ Qualifications in Photo Imaging (7512) Assessment pack

(Non-legislative acts) DECISIONS

Consultation on Amendments to Industry Canada s Antenna Tower Siting Procedures

***************************************************************************** DRAFT UFGS- 01 XX XX (FEB 2014)

2. As such, Proponents of Antenna Systems do not require permitting of any kind from the Town.

SECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

Road signs Specifications

Intimate Communications Hub Interface Specification Report to Secretary of State

AS/NZS :2014

Control Command & Signalling. Standards Brief Sept Professional Head [S&C] 11/11/2014

Working Drawing Manual

SECTION ADMINISTRATIVE REQUIREMENTS SECTION ADMINISTRATIVE REQUIREMENTS

DIVISION 1 GENERAL REQUIREMENTS SECTION SUBMITTAL PROCEDURES

UK Film Council Strategic Development Invitation to Tender. The Cultural Contribution of Film: Phase 2

Procedures for the management of satellite network filings

Governing Council. Inventions Policy. October 30, 2013

L1-CHE-SPE-273 SIGNALLING AND COMMUNICATIONS CABLE APPLICATION GUIDELINES

MINISTRY OF AGRICULTURE, LIVESTOCK & FISHERIES STATE DEPARTMENT OF FISHERIES AND BLUE ECONOMY

THE USE OF A SAFETY CASE APPROACH TO SUPPORT DECISION MAKING IN DESIGN

Estates Development & Projects

Weather and Environmental Services - QMS Manual

New approach for lighting Regulations

MEASURES TO INCREASE THE EFFICIENCY OF CIF COMMITTEES. CTF-SCF/TFC.11/7/Rev.1 January 27, 2014

VCE Systems Engineering: Administrative information for Schoolbased Assessment in 2019

Delivery of Developer Funded Infrastructure A New Model

Contents EUROPEAN UNION AGENCY FOR RAILWAYS. Accompanying Report Practical arrangements for safety certification ERA-REC-126/ACR V 1.

BG6 Design Framework for Building Services

CARRA PUBLICATION AND PRESENTATION GUIDELINES Version April 20, 2017

STANDARD SPECIFICATIONS SECTION SUBMITTAL PROCEDURES

SECTION ADMINISTRATIVE REQUIREMENTS

CONSULTANT ACCREDITATION SCHEME WATER SUPPLY

Art Display Policy SUBJECT: Policy No: Date: October 17, Revision Date: October Number of Pages: 7

Table of Contents...2. Copyright notice...3 Disclaimer Introduction... 4

DNVGL-CG-0214 Edition September 2016

SPECIFICATIONS FOR NEW UNDERGROUND RESIDENTIAL DISTRIBUTION SYSTEMS

Consultation on the licensing of spectrum in the 800 MHz and 900 MHz bands

RULES AND REGULATIONS. Title 58 - RECREATION PENNSYLVANIA GAMING CONTROL BOARD [58 PA. CODE CH. 525] Table Game Internal Controls

JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia

Radiocommunication Facility Review Protocol

NATS Swanwick. Interface Agreement. Owners: General Manager Swanwick. General Manager XXX

LICENCE. for WEB LINKS. Check if this document is current Find similar documents StandardsWatch (info and login) Visit our website

00-General Drawings. Doc. no.: NA-00-STS002

REPORT OF DIRECTOR OF CITY OPERATIONS AGENDA ITEM: 7 PORTFOLIO: TRANSPORT, PLANNING & SUSTAINABILITY (COUNCILLOR RAMESH PATEL)

Demand Side Response Methodology (DSR) for Use after a Gas Deficit Warning (GDW) Background. Draft Business Rules

(A Sample Letter of Agreement for manuscript preparation) (Sample) Letter of Agreement

SECTION CONTRACTOR SUBMITTALS. A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER.

Representation - Draft Modification Report UNC A 0636B 0636C 0636D Updating the parameters for the NTS Optional Commodity Charge

INTERNAL AUDIT DIVISION

An interpretation of NHS England s Primary Care Co-commissioning: Regional Roadshows questions and answers Rachel Lea, Beds & Herts LMC Ltd

2

Air Monitoring Directive Chapter 9: Reporting

PROFESSIONAL PHOTOGRAPHY SERVICES AND RELATED PRODUCTS 2019 LEGISLATIVE SESSION

DIVISION 1 - GENERAL REQUIREMENTS SECTION SUBMITTALS

Level 2 VRQ Qualifications in Photo Imaging (7512)

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules. 45-day Formal Comment Period with Initial Ballot June July 2014

The following draft Agreement supplements, but does not replace, the MOU by and between the Bureau of Land Management (BLM) and the California

Primary IVF Conditions for Registration For Assisted Reproductive Treatment Providers under the Assisted Reproductive Treatment Act 2008

Privacy Policy SOP-031

RESOLUTION MEPC.290(71) (adopted on 7 July 2017) THE EXPERIENCE-BUILDING PHASE ASSOCIATED WITH THE BWM CONVENTION

Herefordshire CCG Patient Choice and Resource Allocation Policy

REVISIONS LTR DESCRIPTION DATE (YR-MO-DA) APPROVED. A Drawing updated to reflect current requirements. gt R. Monnin

A. Action Submittals: Written and graphic information that requires Architect's responsive action.

PEDIGREE Publication Policy & Procedures

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules

PATENT AND LICENSING POLICY SUMMARY

Task on the evaluation of the plasma response to the ITER ELM stabilization coils in ITER H- mode operational scenarios. Technical Specifications

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules

AS/NZS 1200:2000 AS/NZS

THE GRID CODE OC7.5 INTEGRAL EQUIPMENT TESTS GUIDANCE NOTES

Patient Choice and Resource Allocation Policy. NHS South Warwickshire Clinical Commissioning Group (the CCG)

THE UNIVERSITY OF AUCKLAND INTELLECTUAL PROPERTY CREATED BY STAFF AND STUDENTS POLICY Organisation & Governance

2016 CDM Smith All Rights Reserved July 2016 SECTION PROJECT MEETINGS

Investigation i of potentially contaminated sites - Code of Practice. Richard Owen Ove Arup & Partners Limited

Measurement of Signalling Distances

Guidelines. Guidelines to Applicants Wireless Public Address System Licences. Document No: 05/17R1 Date: 10 May 2017

CITY OF RICHMOND SUBDIVISION PLAT AND PUBLIC INFRASTRUCTURE SUBMITTAL, REVIEW AND APPROVAL PROCEDURES

Transcription:

Approval Amendment Record Approval Date Version Description 30/05/2014 1 Initial issue under MTM. This procedure supersedes the Overlapping Design Agreement, Application and Transfer Log documents L2-SIG-PRO-007, L4-SIG-FOR-028 and L4-SIG- FOR-029. PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 1 of 15

Table of Contents 1. Purpose...3 2. Background...3 3. Abbreviations...3 4. Definitions...4 5. References & Legislation...4 6. Responsibilities...5 7. Considerations...5 8. Process...6 8.1 Start Up Meeting & Risk Assessment... 6 8.2 Approval to undertake Overlapping Design Process... 7 8.3 Modification Process... 7 8.4 Cancellation or Rescheduling of Projects... 8 9. Liabilities...8 10. Related Documents...8 11. Appendices...9 Appendix A - Flowchart of Overlapping Design Process... 10 Appendix B - Interim Maintenance Distribution Process... 11 Appendix C As-Built Submission Process... 12 Appendix D Sample Temporary Title Block Locations... 13 Appendix E Overlapping Design Agreement Application... 14 Appendix F Overlapping Design Agreement Design Transfer Log... 15 PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 2 of 15

1. Purpose The purpose of this document is to highlight the process and responsibilities for an overlapping design agreement where two or more contractors are required to produce designs under concurrent or compressed timescales. This agreement is applicable for all designs relating to MTM. 2. Background Within Rail projects there are often multiple contractors involved that may require the same engineering drawings. The Public Transport Victoria s Drawing Management System (DMS) is limited to the update from only one contractor at a time via a book in / book out process. The limitation of this process is that, if a second contractor wanted to work on the same design, the first contractor who is in control of the drawings would be required to book the drawings back into DMS (relinquishing their control of the drawings) to allow for the second contractor to modify the drawings. This can be both time consuming and costly. This procedure allows for two or more contractors to mark up drawings in a controlled manner and reduce the consequences of allowing only one contractor to update drawings. Also, when more than one contractor is involved in modifying the engineering designs in the same area of the network in parallel, there is no clear line of responsibility to ensure the design updates are all incorporated in a coordinated manner. Hence, this procedure will formalise and document the process that has been informally applied by a number of projects, which has often resulted in the loss of revision control, thus allowing the drawings to be updated in a controlled manner. 3. Abbreviations AIS DMS DOT IFC MTM PTV RDE RODE VRIOGS As In Service Drawing Management System Department of Transport Issued For Construction Metro Trains Melbourne Public Transport Victoria Responsible Design Engineer Responsible Overlapping Design Engineer Victorian Rail Industry Operators Group Standards PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 3 of 15

4. Definitions Drawing Controller CAD File MTM staff responsible for the control of drawings booked out from DMS and allocation to the Project Manager / Design Contractors Computer Aided Design File that is required to modify drawings. This can take on numerous file types depending on the design MTM Engineering MTM Engineering responsible for ensuring compliance of all designs to be booked back into DMS Primary Contractor Project Engineer Project Manager Responsible Design Engineer (RDE) Responsible Overlapping Design Engineer (RODE) Secondary Contractor Contractor who the drawings are booked out to. Often, this is the contractor whose works must proceed before the second contractor MTM staff who assists the Project Manager in the design / testing and commissioning aspects of the Project. A Project Engineer may be required as a conduit to communicate with the Contractor The lead responsible for the deliverables for a Project. Depending on the project, there may be two Project managers one for each Design Contractor. It must be the Project Manager(s) who initiate the Overlapping Design Agreement Representative of the Contractor as a direct contact relating to the designs. In order to avoid confusion and ambiguity -there shall only be a single Responsible Design Engineer for each Contractor concerned Person appointed by MTM for the purpose of coordination and facilitation of the Overlapping Design Agreement. Contractor that requires modifications to the designs but is booked out to the Primary Contractor 5. References & Legislation WPB-MPR-00-DES-009 Regional Rail Link: Overlapping Design Process VRIOGS 012.1 Standard for Signalling Design and Documentation Rev. B VRIOGS 007.2 Infrastructure Drafting Standards L1-NAM-PRO-003 Infrastructure As-Built Drawings Management AS 4292.1: 2006 Railway Safety Management VRIOGS Dispensation Request to DMS Rail Safety Act 2006 PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 4 of 15

6. Responsibilities Shown below is a breakdown of the responsibilities Drawing Controller (MTM) Drawing Management System (DMS) MTM & DMS Project Manager(s) (MTM) RODE (MTM) Engineering (MTM) Project Engineer / Responsible Design Engineer (MTM / Primary Contractor) Project Engineer / Responsible Design Engineer (MTM / Secondary Contractor) Contractor Primary Contractor Secondary Contractor Figure 1: Flowchart of Responsibilities 7. Considerations An overlapping Design allows for more than one contractor to modify engineering designs. The potential consequences for this are: integrity of data can be reduced, incorrect versions of the drawings being used, confusion of responsibilities and disputes / conflict of interest from the different contractors. Thus, the use of overlapping designs should be limited to cases where delivery of the projects is within a concurrent / compressed timeframe and / or there are large financial and safety repercussions. When considering an overlapping design agreement the following preferences should follow (with 1 being most preferred.) 1. Reschedule works to remove the requirement for an overlapping design. 2. Utilize the same contractor to perform the designs where overlapping is expected. 3. Undertake an overlapping design arrangement as per this procedure, subject to approval by MTM Engineering. PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 5 of 15

8. Process The following outlines the typical process when undertaking an Overlapping Design Agreement. 8.1 Start Up Meeting & Risk Assessment A start up meeting is required among the contractors involved and the respective MTM representatives to: Assess the feasibility and requirements for an overlapping design agreement Identify the need for the overlapping design agreement Identify the Roles and responsibilities including, but not limited to: o Drawing Controller o RODE (Who will be responsible for the coordination of the drawings between the two contractors) o Primary Contractor (The Contractor where the drawings are booked out to) Secondary Contractor (The Contractor who wants to mark up the drawings booked out to the Primary Contractor) o Agree on the timeframes and design milestones including: When will the Secondary Contractor be able to obtain the CAD files; When will the Secondary Contractor complete their changes and transfer the design back to the Primary Contractor; When will the designs be submitted to Engineering for review and As In Service (AIS) Ascertain the designs that will be affected Define who will undertake the overall re-cad ing of the AIS post commissioning (Normally this would be the Primary Contractor) Who will undertake the final certification of the re-cad ed plans (Normally the Primary Contractor) Overall Tester In Charge (TIC) if the Project commissioning dates are the same Meeting minutes should be taken and should record all the above points as a minimum A risk assessment is to be performed with all stakeholders involved in the project to discuss the risks associated with allowing more than one contractor to work on engineering designs. Note that the Overlapping Design Agreement is subject to agreement by all parties concerned and the Contractor in control of the drawing has the right to refuse undergoing the agreement if they had appropriate justifications. PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 6 of 15

8.2 Approval to undertake Overlapping Design Process Upon agreement by all affected Contractors at the start-up meeting and upon completion of a risk assessment, all related contractors must sign an agreement which highlights: the Contractors involved in the Overlapping Design Agreement the list of drawings required to be included in the Overlapping Design Agreement the list of drawings to be retained compliant the list of drawings to be made compliant Who will be applying for dispensation Who is the current Drawing Controller Who will be the RODE Who is the Project Manager(s) A sample template of an agreement is provided in Appendix E - Overlapping Design Agreement Application. The Project may opt to use their own form of agreement. A mark-up of the plans, highlighting each contractor s scope of works in a different color and the signed design agreement shall be submitted to DMS under Dispensation D1. 8.3 Modification Process The processes of modifying designs are outlined below 1 : 1. The Secondary Contractor requires a design drawing from the Primary Contractor and notifies the RODE. 2. The RODE obtains a copy of the CAD file from the Primary Contractor. The copy of the CAD file will have a temporary new revision box overlaid on the existing drawing, for the purpose of the Overlapping Design Agreement. 3. The RODE logs the movement of the design. The log should contain, as a minimum,: RDE / Project Engineer providing the CAD file RDE / Project Engineer receiving the CAD file Date Reason for Change Attached list of comments & issues from the Primary Contractor The template log: Overlapping Design Agreement: Design Transfer Log can be used. The RODE shall keep all versions of the CAD files as it transfers between each contractor. This provides the ability to fall back to previous versions of the drawings, if required. 4. The RODE issues the CAD file, received from the Primary Contractor, to the Secondary Contractor. Note the Primary Contractor and the RODE shall retain a copy of the original CAD file booked out from DMS. 1 Refer to Appendix A for a flowchart of the Overlapping Design process. PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 7 of 15

5. The Secondary Contractor works on the CAD file copy and keeps a log of any issues. All changes made by the Secondary Contractor should be identified by a separate color or any other agreed methodology. The Secondary Contractor shall ensure that their portion of the works is checked and independently reviewed (if required) prior to sending the designs back to the Primary Contractor. 6. Once the necessary works are complete the Secondary Contractor issues the CAD file copy to RODE, with the temporary revision box filled in. Examples of the temporary revision box can be seen in Appendix D Sample Temporary Title Block Locations. 7. The RODE logs the movement as per step 3. 8. The Primary Contractor receives the CAD file and performs any other mark ups required (with the applicable checking and independent review requirements satisfied). 9. In the event that the Commissioning works are within the same time frame only 1 Master Test Copy shall be produced (typically done by the Primary Contractor unless otherwise agreed). There should also only be a single Tester in Charge for the scope of works of the Primary and the Secondary Contractor. This must be agreed to prior to accepting the Overlapping Design Agreement. 10. In the event that the Commissioning dates are separate, each Contractor will be required to perform their own commissioning works independently (e.g. Production of Test copies, Construction Copies and Interim Maintenance copies). In this instance, the Tester in Charge may be different for each Contractor s commissioning activity. Refer to Appendix B Interim Maintenance Copies Distribution Process and Appendix C As-Built Submission Process. 11. It is the Primary Contractor s responsibility (unless otherwise agreed) to bring the drawings up to DMS Compliance or seek dispensation. 8.4 Cancellation or Rescheduling of Projects In the event that the project is cancelled or rescheduled, all drawings will be assessed by the RODE and their team with any required modifications to be carried out. 9. Liabilities Each contractor is liable for their own design. Any updates made by the Contactors on behalf of another Contractor under the Overlapping Design Agreement, does not import any liability from the Contractor requesting the change. The Overlapping Design Agreement will still require all Design Procedures to be followed for each Contractors portion of works. This includes certification, checking and independent review. 10. Related Documents Nil PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 8 of 15

11. Appendices Appendix A - Flowchart of Overlapping Design Process Appendix B - Interim Maintenance Distribution Process Appendix C - As-Built Submission Process Appendix D - Sample Temporary Title Block Locations Appendix E - Overlapping Design Agreement Application Appendix F - Overlapping Design Agreement Design Transfer Log PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 9 of 15

Appendix A - Flowchart of Overlapping Design Process PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 10 of 15

Appendix B - Interim Maintenance Distribution Process PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 11 of 15

Appendix C As-Built Submission Process PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 12 of 15

Appendix D Sample Temporary Title Block Locations OR PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 13 of 15

Appendix E Overlapping Design Agreement Application OVERLAPPING DESIGN APPLICATION The following parties agree to facilitate for Overlapping Designs. Overlapping Designs are defined as designs that require multiple contractors to modify for the same project. Reason for the Overlapping Design Agreement : The Drawing Controller who will book out the Engineering Designs shall be: Name Email Phone Number Signature Drawing Controller: Organisation: The Responsible Overlapping Design Engineer (RODE) shall be: Responsible Overlapping Design Engineer Organisation: Name Email Phone Number Signature The RODE will be required to coordinate and track all movements related to the affected Engineering Designs between differing contractors. It is the RODE's responsibility to ensure that integrity of the designs are preserved. The Primary Contractor that will provide have the Engineering Designs booked to shall be: Responsible Design Engineer Name Email Phone Number Signature Organisation The Primary Contractor must provide the final designs incorporating all related Contractors design modifications and comments. It is the Primary Contractors responsibility to return the plans to DMS compliance The Secondary Contractor(s) shall be: Name Email Phone Number Signature Responsible Design Engineer Organisation (1) Responsible Design Engineer Organisation (2) (Delete if not required) Responsible Design Engineer Organisation (3) (Delete if not required) The Secondary Contractor will not have the designs booked under their name, yet require modifications to the designs for the same project. The Following Engineering Designs will be undertaken via an Overlapping Design methodology Title File Name Drawing Number Revision Location PTV DMS Dispensation Number (if any) : Attached to this application shall be the Start Up meeting minutes and Risk Register PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 14 of 15

Appendix F Overlapping Design Agreement Design Transfer Log OVERLAPPING DESIGN DESIGN TRANSFER LOG # Vault New / Existing File Name Drawing Number Title Drawing Revision Location Name Drawing Controller Primary Contractor Secondary Contractor Date of Request Date of Transfer From Transfer To Reason for Design Change Designs Received Name Company Name Company # Overlapping Design Agreement Design Transfer Log to be maintained by RODE for record and keeping track of the status of drawings PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 15 of 15