CITY OF RICHMOND SUBDIVISION PLAT AND PUBLIC INFRASTRUCTURE SUBMITTAL, REVIEW AND APPROVAL PROCEDURES
|
|
- Moses Lester
- 5 years ago
- Views:
Transcription
1 SUBDIVISION PLAT AND PUBLIC INFRASTRUCTURE SUBMITTAL, REVIEW AND APPROVAL PROCEDURES CITY OF RICHMOND 112 JACKSON STREET RICHMOND, TEXAS PHONE: FAX: CITY OF RICHMOND PUBLIC WORKS 600 MORTON STREET RICHMOND, TEXAS PHONE: FAX: KELLY R. KALUZA & ASSOCIATES, INC. CITY ENGINEERS 3014 AVENUE I ROSENBERG, TEXAS PHONE: FAX: February 11, 2011 Page 1 of 11
2 SUBDIVISION PLAT AND PUBLIC INFRASTRUCTURE SUBMITTAL, REVIEW AND APPROVAL PROCEDURES ATTACHMENTS Subdivision Plat 1. Subdivision Plat Submittal and Review Procedure (1 page) 2. Application - Subdivision Plat Review (1 page) 3. Plat Fee Calculation Form (1 page) Public Infrastructure 1. Public Infrastructure Construction Plan & Approval Procedure (3 pages) 2. Application - Public Infrastructure (1 page) 3. Infrastructure Plan Review Calculation Form (1 page) 4. City Inspection Fee Calculation Form (1 page) February 11, 2011 Page 2 of 11
3 SUBDIVISION PLAT SUBMITTAL AND REVIEW PROCEDURE A. Plat Submittal shall include: 1. Application Form (completed by applicant) 2. Applicable Fees including Fee Computation Form 3. Seven (7) copies of the Plat (preliminary or final) 4. Three (3) copies of the one line utility and drainage plans 5. Three (3) copies of the Title Report, Tax Certificates and other information for Final Plat submittals 6. To facilitate timely completion of the submittal, all information and fees will be submitted at Permit Office at least 21 calendar days in advance of the City Commission Meeting B. Submittal Distribution (By City): 1. The City Secretary will retain five (5) copies of the plat submittal. 2. One (1) copy of the one line utility and drainage plans and plat to the Director of Public Works. 3. One (1) copy of the entire submittal will be sent to the City Engineer. C. Review and Approval of Plats: 1. City Engineer will review the submittal and determine whether the information is complete. 2. City Engineer will review the Plat submittal and provide comments and a recommendation to the City Manager regarding approval of the plat (preliminary and final). 3. The City Manager will place the Plat on the next available City Commission Meeting for action. 4. Once the Commission has taken action, the Applicant will resolve any outstanding comments with the City Engineer. 5. After comments are resolved; mylar originals of the Plat will be submitted to the City Engineer for a final review and submitted to the City for signature. Two (2) paper copies of the mylar originals shall be submitted with the Final Plat submitted for signature. 6. The Plat, with City signatures, will be returned to the Applicant for additional approvals (ETJ) and/or recordation at the office of the Fort Bend County Clerk. February 11, 2011 Page 3 of 11
4 APPLICATION SUBDIVISION PLAT REVIEW Application For G Preliminary Plat G Final Plat G Replat or Amended Subdivision Name: Engineer/ Phone: Surveyor: Fax: Contact Person: Address: City: State: Zip: Address: Owner: Phone: Fax: Address: City: State: Zip: Address: Location of Property (Address if Applicable): Survey Name: Abstract No. Acreage: Is this a replat of an existing recorded subdivision? G Yes G No If yes, give name and date when the existing subdivision was filed for record: Existing Subdivision Name: Date Filed: Slide No. Number of lots within original subdivision: Proposed lots: Was this subdivision restricted by deed restrictions to single family? G Yes G No I am authorized to make application for a subdivision on behalf of the Owner of this property. Agent Signature The above person is my representative, authorized to make application for a subdivision on my behalf and I am the owner of this property for which this application is made. Owner Signature For Office Use Only: Date Received By Check No. Amount $ February 11, 2011 Page 4 of 11
5 PLAT FEE CALCULATION FORM Subdivision Name: Submittal Type Number/Acres Total Conceptual Land Plan $ = Residential Plat (Preliminary & Final) $ = Number of Lots X $ 2.00 = Reserve Acreage X $ = Commercial Plat (Preliminary) $ = Reserve Acreage X $ = Commercial Plat (Final) $ = Reserve Acreage X $ = Multi-Family (Preliminary & Final) $ = Reserve Acreage X $ 2.00 = Amendment or Partial Replat $ = Variance Request $ = Total Amount Due = $ For Office Use Only: Date: Received By: Check No.: Amount $ February 11, 2011 Page 5 of 11
6 112 JACKSON STREET RICHMOND, TEXAS PHONE: FAX: PUBLIC INFRASTRUCTURE CONSTRUCTION PLAN REVIEW & APPROVAL A. Initial Submittal (Submit at Permit Office) 1. All plan review fees shall be paid at the time of submittal. 2. Submit three (3) copies of the application form and fee calculation form with fees and supporting documents. 3. Submittal Distribution (By City) a. Distribute two (2) sets of construction drawings to the Director of Public Works (DPW) or designee. b. One (1) copy of entire submittal (including plans, calculations, etc. to City Engineer). 4. DPW will route Public Works comments to City Engineer within approximately two weeks. 5. City Engineer will complete the review of the Project submittal, after receipt of DPW comments. 6. City Engineer will create a comment memorandum addressed to Project Engineer and copied to DPW. 7. Project Engineer will address all comments and resubmit to City Hall. B. Project Review Re-submittal (Submit at Permit Office, if required) 1. Submit two (2) complete sets of construction drawings, calculations, supplemental information, fee calculation form and applicable fees. 2. Project Engineer will attach a letter identifying all review comments and responses of specific action performed by the Project Engineer addressing all comments. 3. Submittal Distribution (By City) a. One (1) copy to the City Engineer. b. One (1) set to DPW. 4. Include the previous submittal correspondence and red line mark-ups (if returned) with the re-submittal. 5. City Engineer will clear all items from the comment list or require additional submittal by Project Engineer (repeat process as necessary to clear all comments). February 11, 2011 Page 6 of 11
7 PUBLIC INFRASTRUCTURE CONSTRUCTION PLAN REVIEW & APPROVAL (CONT D) C. Final Approval and Signatures of Construction Plans 1. City Engineer will provide final review of the plans and comments. When the plans are complete, the City Engineer will request submittal of original mylar drawings for signature. 2. Project Engineer will submit the construction plans originals and project specifications to City Engineer. 3. City Engineer will sign the drawing sets and forward the mylars to the City Manager for signatures. (Project Engineer will provide a signature block for the City Engineer and City Manager on the Cover Sheet of the plan set.) 4. City Manager will sign the originals and return the plans to Project Engineer. 5. As required, Project Engineer will obtain approvals and signature from other agencies with jurisdiction over the Project. 6. Project Engineer will provide two (2) copies of approved construction plans to DPW and one (1) copy of approved construction plans to City Engineer. 7. Project Engineer will provide a CD containing pdf files of the approved construction drawings and other pertinent information to the City Engineer. 8. Two (2) copies of the approved plans shall be provided prior to or coincidental with the preconstruction meeting for the Project. D. Construction Phase 1. Preconstruction Meeting a. Submit inspection fee with completed fee calculation form to the Permit Office. All fees including inspection fees shall be paid at the time the preconstruction meeting is scheduled. b. All preconstruction meetings will be held at the City of Richmond, Public Works Department (600 Morton Street) or at other location designated by the DPW. c. Project Engineer shall contact DPW or his designated representative to schedule a preconstruction meeting. d. DPW will coordinate the scheduling of a preconstruction meeting with the City Staff and the City Engineer. e. DPW will notify the Project Engineer of the approved meeting time and location. f. Project Engineer will confirm the meeting with all parties including a fax or notifying all parties as to the scheduled preconstruction meeting. February 11, 2011 Page 7 of 11
8 PUBLIC INFRASTRUCTURE CONSTRUCTION PLAN REVIEW & APPROVAL (CONT D) 2. Construction a. Contractor shall notify DPW or his designated representative and the City Engineer at least 48 hours prior to beginning construction. b. Project Engineer shall be responsible for coordination with DPW for all inspections. (Call DPW at ) c. Project Engineer shall be responsible for coordination of independent testing during construction. d. All test results shall be sent to DPW and the City Engineer. Test results shall be provided in a pdf formatted electronic file. Project Engineer shall identify and discuss deficient tests with the City Engineer and make recommendations as to remedy for such deficiencies. e. Prior to final acceptance of the Project, Project Engineer shall coordinate a final inspection with DPW, City Engineer and other agencies having jurisdiction over the Project. f. Project Engineer shall issue a final approved punch list with copies to DPW and City Engineer. The punch list shall be approved by the City Engineer prior to distribution. g. Once the Project is completed, i.e. the final punch list items have been addressed, the Project Engineer shall provide the DPW and City Engineer with certification that the Project has been completed in substantial compliance with the approved Construction Plans. h. Concurrent with the certification in Item D.2.g. above, Project Engineer shall provide a copy of the plans to the DPW and shall two (2) compact discs containing pdf formatted electronic files of the full set of the Records Drawings, all testing results and all other pertinent Project information to the City Engineer. 3. One Year Warranty Inspection a. Project Engineer shall be responsible for coordination of a oneyear inspection for the Project. b. Project Engineer shall notify DPW and City Engineer at 11-months after the beginning of the warranty period of the intent to schedule the one-year inspection. c. DPW will schedule a time for the inspection. d. Project Engineer shall coordinate with all Agencies with jurisdiction so each agency is represented at the one-year inspection. February 11, 2011 Page 8 of 11
9 APPLICATION PUBLIC INFRASTRUCTURE Application For G First Submittal G Second Submittal G Additional Resubmittal Project Name: Acreage: Engineer: Phone: Contact Person: Fax: Address: City: State: Zip: Address: Owner: Address: Phone: Fax: City: State: Zip: Address: Location of Property (Address if Applicable): Survey Name: Abstract No. I am authorized to make application for a subdivision on behalf of the Owner of this property. Print Name: Agent Signature Date For Office Use Only: Date: Received By: Check No.: Amount $ February 11, 2011 Page 9 of 11
10 PERMIT AND BUILDING PERMIT INFRASTRUCTURE PLAN REVIEW FEE CALCULATION FORM Name of Project: Initial Submittal G Acreage G Acres $ = G Acres $ = G Acres $ = G 100 Acres or More $ = First Resubmittal G Additional Resubmittal G Grading Plan G G Acres $ = G Acres $ = G Acres $ = G 100 Acres or More $ = G Acres $ = G Acres $ = G Acres $ = _ G 100 Acres or More $ = G Acres $ = G Acres $ = G 5 Acres or More $ = Total Amount Due = $ For Office Use Only: Check No. Receipt No. February 11, 2011 Page 10 of 11
11 CITY INSPECTION FEE CALCULATION FORM Name of Project: a) Construction Cost $10,000 or less Fee = Construction Cost x 0.01 $ x 0.01 = $ b) Construction Cost greater than $10,000 and less than $50,000 Fee = (Construction Cost x ) + $ ($ x ) + $ = $ c) Construction Cost $50,000 or greater Fee = (Construction Cost x 0.005) + $ ($ x 0.005) + $ = $ Total Amount Due = $ Check No. For Office Use Only: Receipt No. February 11, 2011 Page 11 of 11
SUBDIVISION PLAT APPLICATION
SUBDIVISION PLAT APPLICATION ONLY COMPLETE SUBMISSIONS WILL BE PROCESSED CITY OF PORT ST. LUCIE P&Z File No. PLANNING & ZONING DEPARTMENT Fee (Nonrefundable)$ (772)871-5212 FAX: (772)871-5124 Receipt #.......................................
More informationAPPLICATION FOR ZONING AND LAND DEVELOPMENT
APPLICATION FOR ZONING AND LAND DEVELOPMENT To be completed by Town staff: Application date: Application/Fee Received: Fee Paid: TYPE OF APPLICATION (CHECK ALL THAT APPLY) ZONING DEVELOPMENT PLANS Zoning
More informationDOUGLAS COUNTY SUBDIVISION RESOLUTION Table of Contents 10/29/91 TABLE OF CONTENTS
ARTICLE 1 TABLE OF CONTENTS ADMINISTRATIVE PROVISIONS Page 101 Short Title... 1-1 102 Purpose... 1-1 103 Control Over Platting... 1-2 104 Authority... 1-3 105 Jurisdiction... 1-3 106 Interpretation...
More informationMINOR DEVELOPMENT PERMIT SUBMITTAL REQUIREMENTS
9500 Civic Center Drive Thornton, CO 80229 CITY DEVELOPMENT DEPARTMENT 303-538-7295 developmentsubmittals@cityofthornton.net MINOR DEVELOPMENT PERMIT SUBMITTAL REQUIREMENTS Applications must contain the
More informationPRELIMINARY PLAT / CONSTRUCTION PLAN APPLICATION SUBMITTAL PACKAGE REQUIREMENTS
Development Services Department, 3363 West Park Place, Pensacola, Fl 32505 (850) 595-3475 PRELIMINARY PLAT / CONSTRUCTION PLAN APPLICATION SUBMITTAL PACKAGE REQUIREMENTS All Preliminary Plat / Construction
More informationSANITARY SEWER SYSTEM ADMINISTRATIVE STANDARDS A.1 SANITARY SEWER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS
SANITARY SEWER SYSTEM ADMINISTRATIVE STANDARDS A.1 SANITARY SEWER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS All plans for sanitary sewer main extensions, improvements and modifications
More informationDevelopment Application
Storey County Planning Department 26 South B Street, P.O. Box 176, Virginia City, NV 89440 Phone: 775-847-1144 Fax: 775-847-0949 planning@storeycounty.org Development Application Submit this completed
More informationUNPLATTED SUBDIVISION APPLICATION PACKAGE SUBMITTAL REQUIREMENTS
Development Services Department, 3363 West Park Place, Pensacola, Fl 32505 (850) 595-3475 UNPLATTED SUBDIVISION APPLICATION PACKAGE SUBMITTAL REQUIREMENTS All Unplatted Subdivision Application Submittal
More informationPLANNING AND DEVELOPMENT
OVERVIEW Effective January 1, 1992 all applications for multi-family residential and all non-residential building permits require site plan approval before permit issuance. All new developments and existing
More informationDEVELOPMENT REVIEW COMMENTS LAND DISTURBANCE PERMIT (LDP) CLEARING CLEARING & GRUBBING GRADING. Date Reviewed by. Project Name
GWINNETT COUNTY Department of Planning and Development One Justice Square 446 West Crogan Street Suite 150 1 st Floor Lawrenceville, GA 30046 Phone: 678.518.6000 Fax: 678.518.6240 www.gwinnettcounty.com
More informationHillside & Foothills Development Application
Hillside & Foothills Development Application This box for office use only File #: Cross Referenced File(s): Fee: Zone(s): Are Pre-Application materials attached? Yes No This application is a request to
More informationPRELIMINARY PLAT / CONSTRUCTION PLAN APPLICATION SUBMITTAL PACKAGE REQUIREMENTS
Development Services Department, 3363 West Park Place, Pensacola, Fl 32505 (850) 595-3475 www.myescambia.com PRELIMINARY PLAT / CONSTRUCTION PLAN APPLICATION SUBMITTAL PACKAGE REQUIREMENTS All Preliminary
More informationProcedure to Petition for Plat Review and Site Plan Review
Economic Development Department (734) 676-7104 or (734) 676-7109 Procedure to Petition for Plat Review and Site Plan Review All site plans shall be submitted to the Economic Development Department to be
More informationAPPLICATION FOR SITE PREPARATION PERMIT
Engineering Division 550 Landa Street New Braunfels, Texas 78130 (830) 221-4020 1. Subdivision/Plat Name: Location Description/ Nearest Intersection: Acreage: APPLICATION FOR SITE PREPARATION PERMIT No.
More informationAPPLICATION FOR SITE PLAN REVIEW
APPLICATION FOR SITE PLAN REVIEW ONLY COMPLETE SUBMISSIONS WILL BE PROCESSED CITY OF PORT ST. LUCIE P&Z File No. PLANNING & ZONING DEPARTMENT Fees (Nonrefundable) $ Arch.: $ (772) 871-5212 FAX: (772) 871-5124
More informationCHAPTER 11 PRELIMINARY SITE PLAN APPROVAL PROCESS
CHAPTER 11 PRELIMINARY SITE PLAN APPROVAL PROCESS 11.01.00 Preliminary Site Plan Approval 11.01.01 Intent and Purpose 11.01.02 Review 11.01.03 Application 11.01.04 Development Site to be Unified 11.01.05
More informationTOWN OF AMHERST PLANNING DEPARTMENT MINOR SITE PLAN AND MINOR ADJUSTMENT REVIEW AND APPROVAL PROCEDURE
TOWN OF AMHERST PLANNING DEPARTMENT MINOR SITE PLAN AND MINOR ADJUSTMENT REVIEW AND APPROVAL PROCEDURE This application package includes the following: Application Procedures Application Form & Checklist
More informationCITY OF EL MIRAGE DEVELOPMENT APPLICATION PROCESS
DEVELOPMENT APPLICATION PROCESS Development Applications are reviewed by the El Mirage Technical Advisory Committee (TAC) to ensure Building, Engineering and Zoning compliance before scheduling public
More informationCITY OF EL MIRAGE DEVELOPMENT APPLICATION PROCESS
DEVELOPMENT APPLICATION PROCESS I. Technical Advisory Committee (TAC) 1. Submit TAC Review Application (See Page 3 for TAC Review Application Requirements) 2. Review of TAC Review Application by Technical
More informationCONSTRUCTION PLAN APPLICATION SUBMITTAL PACKAGE REQUIREMENTS
Development Services Department, 3363 West Park Place, Pensacola, Fl 32505 (850) 595-3475 CONSTRUCTION PLAN APPLICATION SUBMITTAL PACKAGE REQUIREMENTS All Construction Plan Submittal Packages shall contain
More informationINTENT An Administrative Site Plan is required for the following situations, excluding single-family detached development:
SECTION 13-400 ADMINISTRATIVE SITE PLAN 13-401 INTENT An Administrative Site Plan is required for the following situations, excluding single-family detached development: A. All development on vacant land
More informationSITE PLAN Application Packet (Required For All Non-Residential Development Projects)
SITE PLAN Application Packet (Required For All Non-Residential Development Projects) Community Development Department 90 North Main Street, Tooele, UT 84074 (435) 843-2130 Fax (435) 843-2139 Dear Applicant,
More informationRESIDENTIAL DEMOLITION PERMIT APPLICANT CHECKLIST
RESIDENTIAL DEMOLITION PERMIT APPLICANT CHECKLIST The purpose of this form is to inform applicants of: 1) the requirements for building permits and stormwater permits for residential demolition projects;
More informationA. Action Submittals: Written and graphic information that requires Engineer's responsive action.
SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification
More informationSECTION 2 GENERAL REQUIREMENTS
SECTION 2 GENERAL REQUIREMENTS 2-1 ENGINEER REQUIRED: All plans and specifications for Improvements which are to be accepted for maintenance by the County and private, on-site drainage and grading shall
More informationCharlotte-Mecklenburg Planning Department Review Fees
Charlotte-Mecklenburg Planning Department Review Fees (Rezoning / Subdivision / Zoning Administration) (July 1, 2010 June 30, 2011) FEES EFFECTIVE JULY 1, 2010 REZONING APPLICATION, CONDITIONAL ZONING
More informationAPPLICATION FOR CERTIFICATE OF APPROPRIATENESS IN THE HISTORIC DESIGN REVIEW DISTRICT
209 South Main Street Marysville, Ohio 43040 Phone: (937) 645-7350 Fax: (937) 645-7351 www.marysvilleohio.org APPLICATION FOR CERTIFICATE OF APPROPRIATENESS IN THE HISTORIC DESIGN REVIEW DISTRICT *** IMPORTANT
More informationMinor Site Plan Review Process
Minor Site Plan Review Process Pre-Application Conference Community Meeting (optional) Submit Application Determination of Completeness Staff Report (optional) Technical Review Committee Decision Notice
More informationSite Plan/Building Permit Review
Part 6 Site Plan/Building Permit Review 1.6.01 When Site Plan Review Applies 1.6.02 Optional Pre- Application Site Plan/Building Permit Review (hereafter referred to as Site Plan Review) shall be required
More informationC I T Y O F M c K I N N E Y PLANNING
C I T Y O F M c K I N N E Y PLANNING 221 N. TENNESSEE STR EE T, McKI NNEY, TEXA S 75069 CONTENTS Approval Process Flowchart FAQs Letter of Intent Requirements Façade Plan Submittal Checklist Non-Residential
More informationWorking Drawing Manual
Working Drawing Manual 2012 Table of Contents Section 1 Working Drawing Types... 1 1.1 General... 1 Section 2 Processing Steps... 1 2.1 Project Manager... 1 2.2 Engineering Document Unit... 2 2.3 Contractor...
More informationWILTON MANORS, Island City 2020 WILTON DRIVE, WILTON MANORS, FLORIDA 33305
WILTON MANORS, Island City 2020 WILTON DRIVE, WILTON MANORS, FLORIDA 33305 COMMUNITY DEVELOPMENT SERVICES (954) 390-2180 FAX: (954) 567-6069 This package includes: General Submittal Procedures Submittal
More informationAPPLICATION FOR PLANNED UNIT DEVELOPMENT (PUD) DEVELOPMENT PLAN
209 S. Main Street Marysville, Ohio 43040 Phone: (937) 645-7350 Fax: (937) 645-7351 www.marysvilleohio.org APPLICATION FOR PLANNED UNIT DEVELOPMENT (PUD) DEVELOPMENT PLAN *** IMPORTANT INFORMATION ~ Please
More informationDOCUMENT MINIMUM CONSTRUCTION DRAWING REQUIREMENTS FOR PRELIMINARY REVIEW/APPROVAL 1.2. GALVESTON COUNTY CONSOLIDATED DRAINAGE DISTRICT (GCCDD)
DOCUMENT 01105 FOR PRELIMINARY REVIEW/APPROVAL PART I: SUBMITTAL 1.1 CITY OF FRIENDSWOOD (COF) A. Submit four (4) copies of drawings. B. Submit by 5:00 PM a minimum of fourteen calendar days (14 cd) prior
More informationMISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration
SECTION 01 340 - SHOP DRAWINGS, PRODUCT DATA AND SAMPLES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationSECTION SUBMITTAL PROCEDURES
SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification
More informationResidential Room Additions
Residential Room Additions The purpose of this information sheet is to provide information regarding building code and permit processing requirements for RESIDENTIAL ROOM ADDITION(S) in the City of Poway.
More informationSECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS
SECTION 01 33 00 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification
More informationFREMONT COUNTY. APPLICATION FOR ZONE CHANGE #2 USE DESIGNATION PLAN (Requires Subsequent Approval of ZC #2 Final Designation Plan) 1.
FREMONT COUNTY APPLICATION FOR ZONE CHANGE #2 USE DESIGNATION PLAN (Requires Subsequent Approval of ZC #2 Final Designation Plan) 1. Project Name: 2. Applicant: Address: City: State: Zip Code: Telephone
More informationElectronic Document Review (EDR)
Electronic Document Review (EDR) Submittal Requirements Table of Contents Introduction... 3 Electronic Document Review Submittals:... 4 Plans... 4 Plat... 4 Forms... 4 Correspondence... 5 Plan Revisions...
More informationDIVISION 1 GENERAL REQUIREMENTS SECTION SUBMITTAL PROCEDURES
DIVISION 1 GENERAL REQUIREMENTS SECTION 01 33 00 PART 1 - GENERAL 1.1 SUMMARY A. This section includes administrative and procedural requirements for submittals required for performance of the work, including
More informationPROCEDURE FOR PROCESSING WORKING DRAWINGS
PROCEDURE FOR PROCESSING WORKING DRAWINGS MAY 2005 Procedure for Processing Working Drawings GENERAL: The procedure for the review and processing of working drawings provide for two primary types of drawings,
More informationCloud Based Plan Review Process (Applicant)
1 Cloud Based Plan Review Process (Applicant) Organize Documentation Process Overview Upload Documents To Mercer Island FTP Site No Initial Submittal? Yes Intake Screening Approved? CST will inform you
More informationConceptual, Preliminary and Final Site Plan Review in Holladay City
Conceptual, Preliminary and Final Site Plan Review in Holladay City The City of Holladay incorporated in December, 1999 and adopted its own zoning ordinance in May, 2000. All land use decisions are made
More informationLOWNDES COUNTY ENGINEERING PLAN REVIEW CHECKLIST. Design Professional: Phone: Developer: Phone: 2 nd Submittal (No Fee)
MEMORANDUM MICHAEL B. FLETCHER, P.E. COUNTY ENGINEER 327 N. Ashley Street Valdosta, GA 31601 Telephone: (229) 671-2424 Fax: (229) 245-5299 mfletcher@lowndescounty.com LOWNDES COUNTY ENGINEERING PLAN REVIEW
More informationOAK RUN BUILDING PERMIT
OAK RUN BUILDING PERMIT (DOCK APPLICATION) ALL PERMIT APPLICATIONS MUST BE SUBMITTED AT THE POA OFFICE A MINIMUM OF 48 HOURS BEFORE THE SCHEDULED MEETING. ALL INFORMATION MUST BE SUPPLIED AND HAVE PROPER
More informationDESIGN REVIEW BOARD APPLICATION EXTERIOR PLAN / LANDSCAPE PLAN
209 S. Main Street Marysville, Ohio 43040 Phone: (937) 645-7350 Fax: (937) 645-7351 www.marysvilleohio.org DESIGN REVIEW BOARD APPLICATION EXTERIOR PLAN / LANDSCAPE PLAN *** IMPORTANT INFORMATION Please
More informationDESIGN REVIEW PROCESS AND APPLICATION
DESIGN REVIEW PROCESS AND APPLICATION Design review is the first step in the process of any construction project requiring permits. The Community Redevelopment Agency (CRA) Board is responsible for ensuring
More informationTown of Apex, North Carolina
POND DRAINAGE PLAN APPLICATION Town of Apex, North Carolina POND DRAINAGE PLAN APPLICATION: Applications are due by 12:00 pm on the first business day of each month. Please see the Minor Site Plan Schedule
More informationA. Action Submittals: Written and graphic information that requires Architect's responsive action.
SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification
More informationIMPORTANT ADDITIONAL CONTRACTOR INFORMATION FROM THE OKLAHOMA TAX COMMISSION
IMPORTANT ADDITIONAL CONTRACTOR INFORMATION FROM THE OKLAHOMA TAX COMMISSION This Page Intentionally Left Blank Date Received Receipt Number Approved Date Date: Zoning: Intended Use of Structure: Home
More informationFRENCHTOWN CHARTER TOWNSHIP PLANNING COMMISSION OFFICE (734) EXT. 4 FAX (734)
FRENCHTOWN CHARTER TOWNSHIP PLANNING COMMISSION OFFICE (734) 242-5900 EXT. 4 FAX (734) 242-1634 PARCEL I.D.# DATE APPLICANT ADDRESS CITY STATE ZIP CODE TELEPHONE ( ) FAX ( ) OWNER ADDRESS CITY STATE ZIP
More informationWorking Drawing Procedure
Working Drawing Procedure June 2007 Prepared by Structural Engineering & Construction Services 1.0 Working Drawing Procedure 1.1 General There are two primary types of working drawings, those requiring
More informationDEVELOPMENT SERVICES SITE PLAN SUBMITTAL 2.2.3
DEVELOPMENT SERVICES SITE PLAN SUBMITTAL 2.2.3 Unified Development Code (UDC) Article 2, Applications, Procedures and Criteria provides the steps for applying the Unified Development Code standards to
More informationAnswer: Qualification statement should be provided with the bid.
Little Diversified Architectural Consulting, Inc. 5815 Westpark Drive Charlotte, North Carolina 28217 Phone: 704-525-6350 Fax: 704-561-8700 Lincoln County Probation Renovation 208 N. Government Street
More informationEast Central College
SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification
More informationDOWNTOWN DEVELOPMENT REVIEW BOARD APPLICATION
This application, including the Conceptual Review Presentation, must be completed and submitted to the Downtown Development Review Board (DDRB) Staff twenty (20) business days prior to the upcoming DDRB
More informationSECTION A. RFI: Request from Contractor seeking interpretation, information, or clarification of the Contract Documents.
SECTION 01 3000 PART 1 GENERAL 1.1 SECTION INCLUDES A. Electronic document submittal service. B. Preconstruction meeting. C. Submittals for review, information, and project closeout. D. Submittal procedures.
More informationSECTION CONTRACTOR SUBMITTALS. A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER.
SECTION 01300 - PART 1 - GENERAL 1.1 GENERAL A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER. B. Unless otherwise noted, within 14 days after the date of commencement as stated in
More informationTCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II
SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification
More informationWhite Lake Township Building Dept Highland Rd. (248) White Lake, MI Fax (248)
White Lake Township Building Dept. 7525 Highland Rd. (248) 698-3300 SUBMITTAL REQUIREMENTS FOR SINGLE FAMILY HOMES, ADDITIONS, GARAGES AND RENOVATIONS --NEW-- Package for new residences must include $
More informationCity of Hamilton INFORMATION FOR CONDITIONAL USE PERMIT
City of Hamilton INFORMATION FOR CONDITIONAL USE PERMIT There is a $200.00 non-refundable fee for each request. Requests must be completed and submitted to the Public Works Department, City of Hamilton,
More informationPromontory Architectural Review Committee
Promontory Architectural Review Committee Design Review Application Purpose The Design Review Process and Application have been established to insure that a proposed project is compatible with historical,
More informationUCCS University Hall Fire Sprinkler System Upgrade March 1, 2011 RTA SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL
SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification
More informationCHAPTER 2 SUBMITTAL AND REVIEW PROCEDURES TABLE OF CONTENTS
CHAPTER 2 SUBMITTAL AND REVIEW PROCEDURES TABLE OF CONTENTS Section Title Page 2.1 General... 2-1 2.1.1 General Submittal Criteria and Procedures...2-1 2.1.2 Authorization/Certification...2-1 A. Designer
More informationSECTION SUBMITTAL PROCEDURES
SECTION 01330 SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide submittals in accordance with the General Conditions as modified by the Supplementary Conditions,
More informationSECTION ADMINISTRATIVE REQUIREMENTS SECTION ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL 1.01 SECTION INCLUDES A. Project Coordination. B. Preconstruction meeting. C. Progress meetings. D. Preinstallation conferences. E. Requests for information (RFI). F. Coordination drawings.
More informationUNION COUNTY VOCATIONAL-TECHNICAL SCHOOLS West Hall Addition Project Raritan Road, Scotch Plains, NJ
SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 General
More informationSECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
SECTION 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES PART 1 GENERAL 1.1 DESCRIPTION A. This specification defines the general requirements and procedures for submittals. A submittal is information
More informationSECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.
SECTION 013300 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting
More informationSITE PLAN REVIEW GUIDELINES Rev. 2016
SITE PLAN REVIEW GUIDELINES Rev. 2016 The Site Plan Review process mandates that all information required in the Zoning Resolution and on the checklist be submitted and/or indicated on the site plan before
More informationLARAMIE COUNTY PLANNING & DEVELOPMENT OFFICE 3966 Archer Pkwy Cheyenne, WY Phone (307) Fax (307)
3966 Archer Pkwy Cheyenne, WY 82009 planning@laramiecounty.com Phone (307) 633-4303 Fax (307) 633-4616 SITE PLAN REVIEW PROCESS 1. Pre-Application Meeting: The applicant shall meet with a Laramie County
More informationTown of Rotterdam Office of the Planning Commission
Town of Rotterdam Office of the Planning Commission SITE PLAN/SPECIAL USE PERMIT APPLICATION AND PROCEDURES Site Plan: Application $150 Final Site Plan $150 Application Fees Special Use Permit (IF REQUIRED):
More informationElectronic Plans Management Training. Upload Drawings
Electronic Plans Management Training Upload Drawings Upload Drawings The Electronic Plan Management system (EPM) is an online tool designed to allow architects, engineers, and designers the ability to
More informationSUMMIT COUNTY PLANNING AND ENGINEERING DEPARTMENT
SUMMIT COUNTY PLANNING AND ENGINEERING DEPARTMENT SINGLE-FAMILY SITE PLAN INFORMATION PACKET GENERAL INFORMATION This information packet explains how your application for a single-family site plan will
More informationMinor Site Plan Application and Checklist Land Disturbing Activities
Minor Site Plan Application and Checklist Land Disturbing Activities INSTRUCTIONS: Please provide the requested information below. The Development Services Department reviews each site plan submittal based
More informationJEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia
BULLETIN NO. 6 TO THE PLANS AND SPECIFICATIONS FOR JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia EwingCole Architects.Engineers.Interior Designers.Planners
More informationDEPARTMENT OF COMMUNITY DEVELOPMENT SITE PLAN INFORMATION
DEPARTMENT OF COMMUNITY DEVELOPMENT SITE PLAN INFORMATION 220 Clay Street Cedar Falls, Iowa 50613 General Information: Applications for developing a commercial, multi-family, or residential (in an overlay
More informationSPECIFICATIONS FOR NEW UNDERGROUND RESIDENTIAL DISTRIBUTION SYSTEMS
Page: 4-1 4.0 URD Process and Documentation Requirements 4.1 Process Steps The process of developing underground distribution facilities in a residential area consists of 10 major steps, which are summarized
More informationLETTER OF TRANSMITTAL
1730 VARSITY DRIVE, SUITE 500, RALEIGH, NC 27606 TEL (919) 233-8091 FAX (919) 233-8031 LETTER OF TRANSMITTAL ADDRESS: ATTENTION: 80-A East Street Pittsboro, NC 27312-0130 Lynn Richardson Chatham County
More informationSECTION III SUBMITTALS AND APPROVALS
SECTION III SUBMITTALS AND APPROVALS In order to expedite the approval process of new water distribution system and sanitary sewer collection system extensions, the Hilton Head No. 1 Public Service District
More informationChecklist for Tentative Subdivision Map
Checklist for Tentative Subdivision Map All submittal information shall be provided to the Community Development Department. All submittal information shall be presented along with the Uniform Application,
More informationMULTIPLE-FAMILY DESIGN REVIEW SUBMITTAL CHECKLIST
MULTIPLE-FAMILY DESIGN REVIEW SUBMITTAL CHECKLIST This application lists the content and format of the submittal requirements to initiate the Design Review process. An incomplete application will not be
More informationSection Meetings Section Material and Equipment. None Required
January 2000 Page 1 of 8 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED WORK PART 2 PRODUCTS The General Conditions of the Contract, General Requirements and Supplemental
More informationEXECUTIVE SUMMARY of DESIGN REVIEW
EXECUTIVE SUMMARY of DESIGN REVIEW 1 - REVISIONING PROMONTORY From its inception, Promontory has focused on creating a premier community which blends the natural beauty of its mountain setting with excellence
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017
SECTION 01 3300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification
More informationSUBMITTAL REQUIREMENTS RCV D REJECT PENDING
1 of 5 SUBMITTAL REQUIREMENTS RCV D REJECT PENDING 1. General Information. 1.1 Applicant s name, address and contact numbers. 1.2 Project name, type, address and legal description of the property. 1.3
More informationPLANNED SIGN PROGRAM SUBMITTAL REQUIREMENTS
PLANNED SIGN PROGRAM SUBMITTAL REQUIREMENTS City of Greenwood Village Community Development Department 6060 S. Quebec Street Greenwood Village, CO 80111-4591 (303) 486-5783; FAX (303) 773-1238 SUBMITTAL
More information2016 CDM Smith All Rights Reserved July 2016 SECTION PROJECT MEETINGS
PART 1 GENERAL 1.01 REQUIREMENTS INCLUDED SECTION 01 20 00 PROJECT MEETINGS A. Construction Manager shall schedule and administer pre-construction meeting, periodic progress meetings, and specially called
More informationArchitectural Design Process
Architectural Design Process Custom Residential A. Schematic Design Phase Pre-Design Meeting Site Analysis Site Survey Conceptual Design & Project Scope Design Program Guideline Project Team Formation
More informationStreet Acceptance Guidelines
Street Acceptance Guidelines Fairfax County Guidelines Flowcharts and Examples October 1, 2009 Table of Contents: Procedural Guidelines Overall Procedure... 2 Contact Information... 2 Initial Street Acceptance
More informationCity of Colleyville Community Development Department. Site/Landscape Plan Application Packet
City of Colleyville Community Development Department Site/Landscape Plan Application Packet 1 Development Application Fees City of Colleyville 100 Main Street Colleyville TX 76034 817.503.1050 Zoning Zoning
More informationCity Development Department 9500 Civic Center Drive Thornton, Colorado FAX
City Hall City Development Department 9500 Civic Center Drive 303-538-7295 Thornton, Colorado 80229-4326 FAX 303-538-7373 www.cityofthornton.net Zach Lauterbach Evergreen Devco, Incorporated 2390 East
More informationCITY OF DES MOINES, IA PERMIT AND DEVELOPMENT CENTER 602 Robert D Ray Drive Des Moines, IA Phone:
CITY OF DES MOINES, IA PERMIT AND DEVELOPMENT CENTER 602 Robert D Ray Drive Des Moines, IA 50311 Phone: 515-283-4200 Minor Site Plan list This checklist should be used as a guide in the preparation of
More informationArticle 4 PROCEDURES for PLOT PLAN and SITE PLAN REVIEW
Article 4 PROCEDURES for PLOT PLAN and SITE PLAN REVIEW Section 4.01 Purpose It is the intent of this Article to specify standards, application and data requirements, and the review process which shall
More informationSITE PLAN APPLICATION
SITE PLAN APPLICATION SECTION 1. APPLICANT/OWNER INFORMATION Please Print or Type Applicant/Developer: City: State: Zip: Telephone: Fax: E-mail: Applicant s Status: (Check One) Owner Tenant Prospective
More informationTown of Holly Springs Sign Installation Packet
Town of Holly Springs Sign Installation Packet Department of Planning & Zoning 128 S. Main Street P.O. Box 8 Holly Springs, NC 27540 (919) 557-3908 HSPlanning@hollyspringsnc.us GENERAL INFORMATION: If
More informationA. This section specifies procedural requirements for Shop Drawings, product data, samples, and other miscellaneous Work-related submittals.
SECTION 01300 PART 1 GENERAL 1.1 SECTION INCLUDES A. Description of Requirements B. Submittal Procedures C. Specific Submittal Requirements D. Action on Submittals E. Repetitive Review 1.2 DESCRIPTION
More information9 LAND SURVEYING. 9.1 General. 9.2 Administrative Requirements Standards Meetings Survey Data Provided to the Design-Builder
9 LAND SURVEYING 9.1 General The Design-Builder shall conduct all Work necessary to meet the requirements associated with land surveying, including Project and supplemental horizontal and vertical control