Robert W. Cummings - NERC Director of System Analysis and Reliability Initiatives William Herbsleb - Chairman of Frequency Response Standard Drafting

Similar documents
Frequency Response Initiative Industry Advisory Generator Governor Frequency Response

Harmonizing the Changing Resource Mix Keeping the Grid Together

NARUC. Summer Committee Meetings. Staff Subcommittees on Electricity & Electric Reliability

Demonstration of PFR Improvement September ERCOT Operations Planning

Minutes Frequency Response Initiative Meeting

Forward Looking Frequency Trends Technical Brief ERS Framework 1 Measures 1, 2, and 4: Forward Looking Frequency Analysis

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications

Table of Contents Error! Bookmark not defined.

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications

Lessons Learned in Model Validation for NERC Compliance

Frequency Response Initiative Report

generation greater than 75 MVA (gross aggregate nameplate rating) Generation in the ERCOT Interconnection with the following characteristics:

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

Frequency Response Standard Background Document November, 2012

Informational Filing, Frequency Response Annual Analysis Docket No. RM

2015 Frequency Response Annual Analysis

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number: Address:

BAL Standard Project Frequency Response and Frequency Bias Setting Industry Webinar

2018 Frequency Response Annual Analysis

Final ballot January BOT adoption February 2015

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY

11/4/2013. NERC RS Meeting October 28, 2013 Sullivan s Island, SC. Troy Blalock SERC NERC RS Representative

Frequency Response Characteristic Survey Training Document

Using Synchrophasors for Frequency Response Analysis in the Western Interconnection. Bonneville Power Administration -- WECC JSIS Chair

Lessons Learned in Model Validation for NERC Compliance

Table of Contents. NERC 2016 Frequency Response Annual Analysis September 2016 ii

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC

Procedure for ERO Support of Frequency Response and Frequency Bias Setting Standard. Event Selection Process

Keeping it up to Speed Off-Nominal Frequency Operations. CETAC 2018 San Ramon

Frequency Response Standard Whitepaper

How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements

Informational Filing, Frequency Response Annual Analysis Docket No. RM

Wind Power Plants and future Power System Frequency Stability

EE 742 Power System Components. Y. Baghzouz ECE Department UNLV

1200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report

Lecture 15 EMS Application II Automatic Generation Contol. Davood Babazadeh

Grid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event

Informational Filing Regarding 2017 Frequency Response Annual Analysis Report Docket No. RM

NERC Training Document Understand and Calculate Frequency Response

IEEE sion/1547revision_index.html

Standard MOD Verification of Models and Data for Generator Excitation Control System or Plant Volt/Var Control Functions

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

EH2741 Communication and Control in Electric Power Systems Lecture 2

Loss of Solar Resources during Transmission Disturbances due to Inverter Settings II

Indication of Dynamic Model Validation Process

Industry Webinar. Reactive Power Planning. NERC System Analysis and Modeling Subcommittee (SAMS) March 2017

Interconnection-Wide Oscillation Analysis: Baselining Oscillation Modes in the North American Power System Objective Purpose

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

AORC Technical meeting 2014

Step-Response Tests of a Unit at Atatürk Hydro Power Plant and Investigation of the Simple Representation of Unit Control System

Standard MOD Verification of Models and Data for Generator Excitation Control Sys tem or Plant Volt/Var Control Functions

Endorsed Assignments from ERS Framework

Owner/Customer Name: Mailing Address: City: County: State: Zip Code: Phone Number: Representative: Address: Fax Number:

IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces

BPS-Connected Inverter-Based Resource Performance

System Protection and Control Subcommittee

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting

Attachment B to Primary Frequency Response Reference Document Sustained Primary Frequency Response Methodology for BAL-001-TRE-1

Inverter-Based Resource Disturbance Analysis

IEEE Major Revision of Interconnection Standard

Low Frequency Demand Disconnection Summary

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

Recently, the SS38 Working Group on Inter-Area Dynamic Analysis completed two study reports on behalf of the UFLS Regional Standard Drafting Team.

Market mechanisms for frequency control

Wide-Area Measurements to Improve System Models and System Operation

Bulk Electric System Definition Reference Document

NPCC Regional Reliability Reference Directory # 12. Underfrequency Load Shedding Program Requirements

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

NERC Protection Coordination Webinar Series June 23, Phil Tatro

Power Plant and Transmission System Protection Coordination

Sarma (NDR) Nuthalapati, PhD

EASTERN ILLINI ELECTRIC COOPERATIVE Application for Operation of Member-Owned Generation

Power Plant and Transmission System Protection Coordination Fundamentals

TEAMS Competition 2014

Synchrophasor Technology PMU Use Case Examples

System Protection and Control Subcommittee

AUTOMATIC VOLTAGE REGULATOR AND AUTOMATIC LOAD FREQUENCY CONTROL IN TWO-AREA POWER SYSTEM

IEEE Std Bulk System Opportunities from New Distributed Energy Resource Interconnection and Interoperability Standards

Fault Ride Through Principles. and. Grid Code Proposed Changes

900 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report

Standard BAL b Automatic Generation Control

VOLTAGE STABILITY OF THE NORDIC TEST SYSTEM

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/

1

Standard BAL b Automatic Generation Control

Unit Auxiliary Transformer (UAT) Relay Loadability Report

PID GOVERNOR FOR BLACK START

A Real-Time Regulator, Turbine and Alternator Test Bench for Ensuring Generators Under Test Contribute to Whole System Stability

Reliability Considerations for PPMV. Ryan Quint, NERC Dmitry Kosterev, BPA NASPI-NERC PPMV Tools Workshop October 2016

Transmission Interconnection Requirements for Inverter-Based Generation

Standard Development Timeline

Operational Modeling and Model Inputs

Standard BAL b3 Automatic GenerationBalancing Authority Control DRAFT

Frequency response White paper

Post-Event Analysis of a Compound Event in the ERCOT System Using Synchrophasor Data

Implementation of Revised IEEE Standard 1547

Minnesota Power Systems Conference 2015 Improving System Protection Reliability and Security

Transcription:

Generator Governor and Information Settings Webinar Robert W. Cummings - NERC Director of System Analysis and Reliability Initiatives William Herbsleb - Chairman of Frequency Response Standard Drafting Team Sydney Niemeyer - Control Systems Specialist NRG Energy September 30, 2010

Survey Instructions 2 All generators rated 20 MVA or higher, or plants that aggregate to a total of 75 MVA or greater net rating at point of interconnection (i.e., wind farms, PV farms, etc.), Statement of Compliance Registry Criteria, Rev. 5.0. Jointly-owned units reported by the operating entity. Combined-cycle plants combustion turbines and heatrecovery (steam turbine) units to be reported separately. Wind farms report on a point-of-interconnection of interconnection basis. If operable in more than one interconnection, complete the survey for operation in each of the interconnections.

Frequency Response Concerns 3 Frequency Response is declining in Eastern Interconnection Various factors are influencing When is frequency response too low? Pi Primary Control lfrequency Response is being withdrawn Primary inertial generation being supplanted by non-inertial resources wind, solar, electronically coupled resources What is their response to frequency excursions? What is their susceptibility to tripping during frequency excursions? Load characteristics are changing Unknown frequency response characteristics Current modeling is insufficient to analyze the phenomenon

Eastern Interconnection Mean Primary Frequency Response Trend 4

Eastern Interconnection Mean Primary Frequency Response Projected 5

Classic Frequency Excursion Recovery Frequency (Hz) 60.050 Excursion Recovery 6 60.025 Recovery Completed, T V 60.000 59.975975 59.950 59.925 A = 60.000 59.900900 59.875 59.850 59.825 59.800 C = 59.812 B = 59.874 59.775 59.750-30 0 30 60 90 120 150 180 210 240 270 300 330 360 390 420 Time (Seconds)

Frequency Performance Page 7 Arresting Period Rebound Period Recovery Period

Typical Frequency Traces Following oo gau Unit Trip 8

Frequency Response Basics (Using a 1400 MW generation loss event as an example) Page 9 2000 1800 1600 NERC Frequency Response = A Pre Event Frequency Generation Loss (MW) Frequency Point A -Frequency Point B 60.10 60.05 60.00 Go overnor/loa ad Response e (MW) 1400 1200 1000 800 600 400 200 C Frequency Nadir: Generation and Load Response equals the generation loss Slope of the dark green line illustrates the System Inertia (Generation and Load). The slope is ΔP/(D+2H) B Settling Frequency: Primary Response is almost all deployed Governor Response Load Response Frequency 59.95 59.90 59.85 59.80 59.75 59.70 59.65 Frequ uency (Hz) 0 59.60 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 Time (Seconds)

Inertial Response Variability 10 High Inertia Light Inertia

Frequency Response Basics 11 Whys and Wherefores (things to examine) Deadband currently typical setting is at ±36 mhz ERCOT greatly improved frequency response by reducing deadband to ± 16.6 mhz Sliding pressure controls MW setpoints limited time of response Blocked governor response Once-through boilers Gas Turbine inverse response

12 ERCOT Experience p

Governor response is proportional at the deadband reaching 5% at 3 Hz deviation Governor response Steps to the 5% droop curve at the dead-band 13 Frequency Grid Frequency Deviation Frequency Response Hz Hz MW Droop % Frequency Grid Frequency Deviation Frequency Response Hz Hz MW Droop % -0.04000 59.96000 4.69287 8.52357% -0.03900 59.96100 4.49175 8.68258% -0.03800 59.96200 4.29064 8.85650% -0.03700 59.96300 4.08952 9.04752% -0.03600 59.96400 3.88840 9.25830% -0.03500 59.96500 3.68728 9.49208% -0.03400 59.96600 3.48617 9.75283% -0.03300 59.96700 3.28505 10.04551% -0.03200 59.96800 3.08393 10.37636% -0.03100 59.96900 2.88281 10.75338% -0.03000 59.97000 2.68170 11.18694% -0.02900 59.97100 2.48058 11.69081% -0.02800 59.97200 2.27946 12.28359% -0.02700 02700 59.9730097300 2.07835 12.99110% -0.02600 59.97400 1.87723 13.85020% -0.02500 59.97500 1.67611 14.91548% -0.02400 59.97600 1.47499 16.27125% -0.02300 59.97700 1.27388 18.05512% -0.02200 59.97800 1.07276 20.50786% -0.02100 02100 59.9790097900 0.87164 24.09245% -0.02000 59.98000 0.67052 29.82737% -0.01900 59.98100 0.46941 40.47654% -0.01800 59.98200 0.26829 67.09147% -0.01700 59.98300 0.06717 100.00000% -0.01600 59.98400 0.00000 100.00000% Dead-band -0.04000 59.96000 8.00000 5.00000% -0.03900 59.96100 7.80000 5.00000% -0.03800 59.96200 7.60000 5.00000% -0.03700 59.96300 7.40000 5.00000% -0.03600 59.96400 7.20000 5.00000% -0.03500 59.96500 0.00000 100.00000% -0.03400 59.96600 0.00000 100.00000% -0.03300 59.96700 0.00000 100.00000% -0.03200 59.96800 0.00000 100.00000% -0.03100 59.96900 0.00000 100.00000% -0.03000 59.97000 0.00000 100.00000% -0.02900 59.97100 0.00000 100.00000% -0.02800 59.97200 0.00000 100.00000% -0.02700 02700 59.9730097300 0.0000000000 100.00000% 00000% -0.02600 59.97400 0.00000 100.00000% -0.02500 59.97500 0.00000 100.00000% -0.02400 59.97600 0.00000 100.00000% -0.02300 59.97700 0.00000 100.00000% -0.02200 59.97800 0.00000 100.00000% -0.02100 02100 59.9790097900 0.0000000000 100.00000% 00000% -0.02000 59.98000 0.00000 100.00000% -0.01900 59.98100 0.00000 100.00000% -0.01800 59.98200 0.00000 100.00000% -0.01700 59.98300 0.00000 100.00000% -0.01600 59.98400 0.00000 100.00000% Dead-band 0.01666 Hz Dead-Band 0.036 Hz Dead-Band BAL-001-TRE-1 Implementation Common Industry Implementation 600 MW Steam Turbine 5% Droop Setting

Close up look at +/-0.0166 Hz Dead Band with No Step Implementation 600 MW Generator Capability (MW) 600.000 Frequency Response Deadband Setting 0.0166 Hz 14 150.00 100.00 50.00 Change MW 0.00 No Step response at dead-band. -50.00-100.00-150.00 59.50 59.55 59.60 59.65 59.70 59.75 59.80 59.85 59.90 59.95 60.00 60.05 60.10 60.15 60.20 60.25 60.30 60.35 60.40 60.45 60.50 Hz Droop Setting 5.00%

Close up look at +/-0.036 Hz Dead Band with Step Implementation 600 MW Generator Capability (MW) 600.000 Frequency Response Deadband Setting 0.036 Hz 15 150.00 100.00 50.00 MW Change 0.00-50.00 Step response at dead-band. -100.00-150.00 00 59.50 59.55 59.60 59.65 59.70 59.75 59.80 59.85 59.90 59.95 60.00 60.05 60.10 60.15 60.20 60.25 60.30 60.35 60.40 60.45 60.50 Hz Droop Setting 5.00%

35000 30000 25000 20000 15000 10000 5000 0 ERCOT Frequency Profile Comparison January through haugust of each hyear 16 60.08 60.09 60.1 60.07 60.06 59.94 59.95 59.96 59.97 59.98 59.99 60 60.01 60.02 60.03 60.04 60.05 59.93 2010 2008 59 59.92 59 59.91 59 59.9 One Minute Occ urances

120000 100000 January thru August 2008 0.036 db vs. 2010 0.016 db MW Minute Movement of a 600 MW Unit @ 5% Droop 368360.3 2010 MW Response of 0.0166 db 23.89% Decrease in MW movement with lower deadband. 484006.00 2008 MW Response of 0.036036 db 17 80000 MW 60000 40000 20000 0 59.9 59.91 59.92 59.93 59.94 59.95 59.96 59.97 59.98 59.99 60 60.01 60.02 60.03 60.04 60.05 60.06 60.07 60.08 60.09 60.1 2008 MW Response of 0.036 db 2010 MW Response of 0.0166 db Same 600 MW unit - MW movement due to frequency each year.

18 8 Frequency q y Response p Initiative

FRI Objectives 19 Coordinate all NERC standards development and performance analysis activities related to frequency response and control Identify specific frequency-related reliability factors Identify root causes of changes in frequency response Identify practices and methods to address root causes Consider impacts of integration of new generation technologies (such as wind, solar, and significant nuclear expansion)

FRI Objectives 20 Develop metrics and benchmarks to improve frequency response performance tracking Share lessons learned with the industry via outreach, alerts, and webinars Determine if performance-based frequency response standards are warranted

Near-Term Tasks 21 Develop a clear set of terminology for use by NERC and the industry Nearing completion Issue a Recommendation (ROP 810) and survey to collect data and information for analysis Analyze current and historical Primary and Secondary Control Response performance what factors influence that performance Develop automated t method for determining i frequency deviation events to be used for BAs to measure Primary Control Response Evaluating CERTS FMA Tool Develop appropriate metrics for tracking frequency performance on each interconnection to monitor trends and performance Develop sustainable methods for automatically collecting, trending, and analyzing various elements of frequency response and control for frequency deviation events

Mid-Term Tasks Improve transient dynamic models of Primary Control Response for generators and other devices Explore and analyze what are appropriate frequency response and control performance requirements to maintain system reliability Determine appropriate minimum Bias settings for use in AGC systems as part of an overall Frequency Response and Control strategy 22

Longer-Term Tasks 1 to 2 Years Develop and implement mid-term dynamic models of Primary Control Response of generators and other devices Research required Analyze current Inertial Response performance and determine what factors influence performance Examine Primary Control Frequency Response characteristics of electronically-coupled resources and smart grid loads Develop load and generator models (research required) to properly analyze influence on system behavior in transient, post-transient, and mid-term stability Explore how displacement of inertial generation with electronically-coupled resources might influence Inertial Response 23

Reporting & Ongoing Activities 24 Ongoing Activities Communications / Educational Outreach Technical Reference Documents Webinars / Workshops Metrics & Calculations Ongoing determination of frequency events for analysis Quarterly determination of response performance Reporting on FRI Progress Oct. 18, 2010 Report to FERC Dec. 31, 2010 Report to Board February 2011 February 2011 Report to Board and FERC 2011 & 2012 Quarterly Reports to Board

25 5 Question & Answer

Survey Instructions 26 1. Unit name and number. 2. Balancing Authority (BA) in which the generator is operated (pull-down). a. If operable in more than one, please note all applicable BAs. b. If operable in more than one interconnection, complete the survey for operation in each of the interconnections.

Survey Instructions 27 3. Unit seasonal Net MW ratings normally reported to NERC for resource adequacy analyses: a. Summer Net MW rating b. Winter Net MW rating 4. Prime mover (steam turbine, combustion turbine, wind turbine, etc. pull-down) 5. Fuel type (coal, oil, nuclear, etc. pull-down)

Survey Instructions 28 6. Unit inertia constant (H) as modeled in dynamics analyses the combined kinetic energy of the generator and prime-mover in watt-seconds at rated speed divided by the VA (Volt-Ampere) base. 7. What are the annual run hours for the unit (data for each of the last 3 years)? 8. What is the continuous MW rating (Pmax) of the unit?

Survey Instructions 29 9. What percent of time does the unit run at Pmax or valves wide-open? a. 0 to 30 % b. 31 % to 60 % c. 61 % to 100 % 10. Equipped with a Governor? (Y/N) If not, no further answers are necessary.

Survey Instructions 30 11. If yes, is the governor operational? (Y/N with a comment box) If not, please explain. a. Is the governor normally in operation? (Y/N with a comment box) (even if not normally operated, the data on the governor is still needed) b. What is the normal governor mode of operation? (pull-down) c. Is the governor response sustainable for more than one minute if conditions remain outside of the deadband? (Y/N)

Survey Instructions 31 11. (continued) d. Are there any regulatory restrictions regarding the operation of the governor? This should cover nuclear regulation, environmental e restrictions s (water temperature, emissions), water flow, etc. e. Does the governor respond beyond the high/low operating limit (boiler blocks)? (Y/N) f. Is the governor response limited by the rate of change? (Y/N) g. Are there any other unit-level or plant-level control schemes that t would override or limit it governor performance? If yes, please explain.

Survey Instructions 32 12.Governor Type? Electronic (analog electro-hydraulic); DEH (digital electro hydraulic); Mechanical; Other please specify 13.Governor manufacturer and model? a. If mixed vendor equipment is installed, please explain.

Survey Instructions 33 14.Governor Deadband setting? a. Deadband in(+/-) mhz i. If in mhz is the deadband centered around a frequency reference (60 Hz or current frequency)? b. Deadband in (+/-) RPM i. For RPM specify number of machine poles ii. If in RPM, is the RPM reference nominal or current RPM? c. What is the basis for this setting? d. Once activated, what are the conditions for which the governor action is reset?

Survey Instructions 34 15.What is the percentage (%) droop setting on the governor? a. What is the basis for the droop setting? 16.Does the unit Frequency Response step into the droop curve or is it linear from the deadband?

Survey Instructions 35 17.Prime mover control mode What is the normally used Turbine Control mode(s)? If more than one is prevalently used, select a primary and explain. Turbine manual Pre-select Thermally-limited Turbine ub following oo Boiler following Part-load MW set point Coordinated control o Other (please explain)

Survey Instructions 36 18.Do market rules restrict or override governor speed controls? (Y/N) If yes, please explain.

Survey Instructions For steam generator controls or central station controls: 19.Does the boiler control or combined cycle central station control have a frequency input? (Y/N) If yes, answer the following questions: a. Deadband in(+/-) mhz i. If in mhz is the deadband centered around a frequency reference (60 Hz or current frequency)? 37 b. Deadband in (+/-) RPM i. For RPM specify number of machine poles ii. If in RPM, is the RPM reference nominal or current RPM? c. What is the basis for this setting?

Survey Instructions 38 20.Does the control s Frequency Response step into the droop curve or is it linear from the deadband? 21.What is the steam turbine control mode? (boiler following, turbine following, coordinated control) 22.Do the unit or plant controls over-ride governor speed control or are the control parameters supportive? (Y/N)

Survey Instructions 39 23.Does the boiler operate under variable/sliding pressure? (Y/N) a. What is the control/governor valve position percentage (%) during variable pressure operation? 24.Do unit or plant economic controls over-ride governor speed control? (Y/N)

Eastern Interconnection 40 0706 UTC 306 Atlantic ti Standard d 406 Atlantic Daylight 206 Eastern Standard 306 Eastern Daylight 106 Central Standard 206 Central Daylight 2406 Mountain Standard 106 Mountain Daylight 2306 Pacific Standard d 2406 Pacific Daylight

8-16-1010 Braidwood Trip 41

Event Performance Data Questions 42 Interconnection Date Time Time Zone Eastern 8/16/2010 1:06:15 CST Western 8/12/2010 14:44:03 CST Texas 8/20/2010 14:25:29 CST Québec 12/10/2009 15:09:31 EST

Survey Instructions 43 25.Was the unit on-line during the event? (Y/N) 26.Pre-event generation (MW) Enter the MW output of the generator at the time just before the event began. 27.Post-event generation (MW) Enter the MW output of the generator after the event that was reflects the response by the governor to the frequency deviation. 28.Time to achieve post-event response (seconds) Enter the time (in seconds) it took to achieve the MW response in question 27.