Anticipated schedule, Page 2. Change the Contract Term from 635 Days to be 1,127 Days.

Similar documents
Software Services, Section 16748, Add as an attachment to this section Attachment A enclosed with this addendum.

ADDENDUM NO. 1 TO THE CONTRACT DOCUMENTS AND SPECIFICATIONS DATED JULY 2017 FLORIDA GOVERNMENTAL UTILITY AUTHORITY PROJECT NO.

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

ADDENDUM NO. 3 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO COM.00030

A. This section specifies procedural requirements for Shop Drawings, product data, samples, and other miscellaneous Work-related submittals.

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

SECTION SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS

SECTION CONTRACTOR SUBMITTALS. A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER.

December 31, 2015 A. THE BID OPENING DATE IS UNCHANGED. B. Questions, Additions, and Deletions

ADDENDUM NO. 2 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO COM.00030

UNIFIED FACILITIES GUIDE SPECIFICATIONS

ADDENDUM NO. 02 July 31, 2012

WTP FILTERS REHABILITATION (FILTERS 1, 2, 3, & 7) CITY OF CARTERSVILLE

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

WATER MAIN ALONG ENTRANCE TO ENCINO PS / HWY 281 TO ENCINO TANK Solicitation Number: CO Job No.:

SECTION ADMINISTRATIVE REQUIREMENTS SECTION ADMINISTRATIVE REQUIREMENTS

SECTION CLOSEOUT SUBMITTALS SECTION CLOSEOUT SUBMITTALS

JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia

CITY OF TOMBALL. Section FIRE HYDRANTS 1.01 SECTION INCLUDES. A. Fire hydrants. B. Adjustment of fire hydrants and gate valves.

SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS

Section Meetings Section Material and Equipment. None Required

November 16, 2017 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA. Y CH / Addendum #6 SHERRY DRIVE BRIDGE REPLACEMENT

PORT OF ST. HELENS SCAPPOOSE INDUSTRIAL AIRPARK PARALLEL TAXIWAY B RELOCATON AIP PROJECT ADDENDUM NO. 1

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

FAST TRACK WORKSHOP OBJECTIVES

Heat Exchanger Construction Checklist

SECTION III SUBMITTALS AND APPROVALS

DIVISION 1 GENERAL REQUIREMENTS SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES

[Note to PSC: Include these sections in the Contract Documents, even though some are not included in the U of I Facilities Standards]

State College of Florida, Manatee-Sarasota

9. Pay for the power consumed until the project has been accepted as substantially complete.

DIVISION 1 - GENERAL REQUIREMENTS SECTION SUBMITTALS

Taylor County July 2011 SECTION SHOP DRAWINGS, WORKING DRAWINGS AND SAMPLES

2016 CDM Smith All Rights Reserved July 2016 SECTION PROJECT MEETINGS

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SUBMITTAL LIST Note: See tab below for Samples and Instructions. Attach to end of Specification Section when complete.

A. Action Submittals: Written and graphic information that requires Engineer's responsive action.

Anne Arundel County Dept. of Inspections and Permits Water Sewer Plan Checklist

East Central College

***************************************************************************** DRAFT UFGS- 01 XX XX (FEB 2014)

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

SECTION SCHEDULE OF VALUES PART 1 - GENERAL 1.1 THE REQUIREMENT A. This Section defines the process whereby the Schedule of Values (Lump Sum

ADDENDUM TO RFQ/P DOCUMENTS PROJECT # ADDENDUM: #01

VIRGINIA RAILWAY EXPRESS AMENDMENT OF SOLICITATION INVITATION FOR BIDS (IFB) ADDENDUM No. 3. Issued: February 23, 2016

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

ADDENDUM NO. 01 July 20, 2012

UCCS University Hall Fire Sprinkler System Upgrade March 1, 2011 RTA SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL

2. What are the estimated volumes for the Residuum Harvesting See response to Question 1

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

Section XV - PER, Design, and Construction Submittal Requirements

SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2011 PROPOSITION A BOND PROGRAM Miraloma ES & Sunnyside ES Green Schoolyard ADDENDUM NO. 1

A. Action Submittals: Written and graphic information that requires Architect's responsive action.

Bid No. B14-02 Building 100 HVAC Improvements

Chapter 1 General Design Information

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION

CLARIFICATIONS 1. See attached meeting minutes from the Pre-Bid meeting on June 14, 2017.

Facility Services Subgroup Preface for Divisions 21` through 28

SECTION SUBMITTAL PROCEDURES

SECTION PROJECT MANAGEMENT AND COORDINATION

ADDENDUM NOTICE INTERIOR RENOVATIONS AT THE BATHURST CLARK RESOURCE LIBRARY, 900 CLARK AVENUE WEST, VAUGHAN, ON

Working Drawing Manual

SECTION SUBMITTALS

LETTER OF TRANSMITTAL

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration

MPA Project No. M545-C2 Project Title: New Berth 10 Project - Phase II Location: Conley Terminal, South Boston, Massachusetts

ADDENDUM #1. April 29, 2009

List of Figures. List of Forms

1.01 NOTICE TO BIDDERS

SAN ANTONIO WATER SYSTEM PURCHASING DEPARTMENT FORMAL INVITATION FOR BIDS ANNUAL CONTRACT FOR WELL MAINTENANCE SERVICES ADDENDUM NO.

Renewable Water Resources Greenville, South Carolina. CONTRACT DOCUMENTS Reedy River Basin Sewer Tunnel ADDENDUM IV - CONTRACT REVISIONS.

SPECIFICATIONS FOR NEW UNDERGROUND RESIDENTIAL DISTRIBUTION SYSTEMS

MSU Barnard Hall 105 Cleanroom Installation PPA # Page 1

ADDENDUM THREE SPECIFICATIONS. Vincennes University Renovations of the Curtis G. Shake Learning Resources Center

CHABOT-LAS POSITAS COMMUNITY COLLEGE DISTRICT CHABOT COLLEGE CAMPUS MASTER SIGN PROGRAM, PHASE 2 BID NO

June 10, 2014 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA

CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT

CITY AND COUNTY OF SAN FRANCISCO PUBLIC UTILITIES COMMISSION WASTEWATER ENTERPRISE

SUBMITTAL PROCEDURES

Answer: Qualification statement should be provided with the bid.

FAB GSE Remodel ITB Solicitation #1538 Invitation to Bid (ITB) for General Contracting Services. ADDENDUM #4 December 5, 2014

STANDARD SPECIFICATIONS SECTION SUBMITTAL PROCEDURES

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

SECTION METAL FABRICATIONS

Update: July 20, 2012

Procurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202

ADDENDUM NO. 4 November 15, Page 1

CITY OF NAPERVILLE DEVELOPMENT SERVICES TEAM ELEVATOR INSTALLATION/MODERNIZATION/REPAIR

EMMEGI ARCHITECTURAL FENCING MASTER SPECIFICATION SECTION METAL FENCING, GATES & RAILING SYSTEM PART 1 GENERAL

NEVADA DEPARTMENT OF TRANSPORTATION Addendum 3 to RFP July 28, 2017

00-General Drawings. Doc. no.: NA-00-STS002

ADDENDA ADDENDUM NO. 1 DATE: MARCH 1, 2016

Proposal PROJECT MANUAL P R O P E R T Y M A N A G E M E N T F A L L O N C O U N T Y. Baker, MT P.O. Box 846

Scope of Services. Project management tasks are estimated based upon anticipated project duration of 52 weeks.

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PRESSURE GAUGES, Section 15130

SECTION SUBMITTAL PROCEDURES

Efficient Tactics of Project Management

SECTION SHORT CIRCUIT, COMPONENT PROTECTION, FLASH HAZARD AND SELECTIVE COORDINATION STUDY

ADDENDUM #2 September 12, 2018

Transcription:

This addendum is hereby made part of the Request for Bid for the above-named project and shall be taken into consideration by all firms preparing a submittal on this project. Acknowledge receipt of this addendum must be notated on Appendix A for this solicitation. CHANGES TO THE REQUEST FOR BIDS Anticipated schedule, Page 2. Change the Contract Term from 635 Days to be 1,127 Days. Scope of Work, Page 11, Project Schedule. In the table under Task Duration / Milestone Date change the Substantial Completion date from July 1, 2020 to be October 1, 2021 and change the Final Completion date from October 1, 2020 to be November 1, 2021. CHANGES TO THE CONSTRUCTION AGREEMENT EXHIBIT A, page 13, Key Dates, replace Substantial Completion to 1,096 days. EXHIBIT A, page 13, Key Dates, replace Final Completion to 1,127 days. CHANGES TO THE SPECIFICATONS Submittals, Section 01330, page 01330-5, Paragraph 1.08, REPLACE Paragraph 1.08.A. with Except for submittals for record, information or similar purposes, where action and return is required or requested, ENGINEER will review each submittal, mark to indicate action taken, and return within three weeks, or fifteen business days of receipt. Summary of Work, Section 01110, page 01110-3, Subsection 1.04.A.5.b. Add the following sentence to the end of this paragraph, Contractor shall assume all service water supply valves also leak. Summary of Work, Section 01110, page 01110-4, Subsection 1.04.A.11.a. Replace with Contractor can use the existing plant bridge crane. Contract shall bring their own certified operator to operate the bridge crane. Working hours shall be restricted to 7:00am to 5:00pm. Painting, Section 09900, page 09900-6, Subsection 2.03.D, add as additional subsections the following: 4. Potable Submerged and Intermittently Submerged Metal, Epoxy Coated: Apply 2 coats of an epoxy-polyamide or epoxy-polyamine system as approved by the NSF for potable water service conforming to AWWA D102 inside System No. 1. Painting, Section 09900, page 09900-8, Subsection 3.03.C., 3. After this paragraph insert the following new paragraph: Page 1 of 8

4. Submerged ferrous metals shall have all welds ground smooth to remove spatter, recesses, pinholes, and protrusions. Metal shall be degreased in accordance with SSPC-SP1 and abrasive blast cleaned in accordance with SSPC-SP10, "Near White Abrasive Blast Cleaning." Process Valves, Section 15110, page 15110-3, Subsection 2.01.A.3 Cone Valves. Delete line item C. Pratt Valve. Process Valves, Section 15110, page 15110-3, Subsection 2.01. Add the following paragraph after 5., c. B. Electric motor operators for all valves on the project shall be from the same manufacturer. CHANGES TO THE DRAWINGS Sheet D-500, Valve Schedule. In the Mark column replace G-100 & 102 with G-100 & 101. Sheet D-500, Valve Schedule. For the valve V-8 line item, in the Quantity column change 2 to be 1. Sheet D-500. Add the following new note to this sheet: 3. ALL CONE VALVES THAT ARE NOT REPLACED WITH NEW OR REFURBISHED VALVES SHALL HAVE THE EXISTING OIL HYDRAULIC ACTUATOR APPURTENANCES REMOVED AND THE VALVE STORED AT A LOCATION ONSITE AS DETERMINED BY GLWA OPERATIONS STAFF. Sheet D-503. Add the following new note to this sheet: 7. CONTRACTOR SHALL CONFIRM DESIGN OF NEW STOP PLATES AND PROVIDE PE STAMPED SHOP DRAWING SUBMITTALS. Sheet M-101, Demolition Plan. For valves V-22 and V-23 add hatching to indicate demolition of the hydraulic piping and cylinders similar to the other cone valves shown on this sheet.. Sheet M-101. Add the following note to this sheet: NOTE: 1. THIS SHEET DEPICTS DEMOLITION OF THE OIL HYDRAULIC SYSTEM AND CONE VALVE CYLINDERS. SEE VALVE SCHEDULE ON SHEET D-500 FOR A LISTING OF WHICH CONE VALVES ARE DEMOLISHED AND WHICH ARE REFURBISHED. Sheet M-104, Generator Location Partial Plan, Notes. Change Note 4 from WITH DTE; PAYMENT FOR WORK WILL BE COVERED IN THE UTILITY ALLOWANCE. to read WITH DTE; Page 2 of 8

PAYMENT FOR WORK WILL BE IN ACCORDANCE WITH THE CASH ALLOWANCE FOR NEW GAS SERVICE. Sheet E-002, Trenching Detail. In the note referring to the marking tape replace 6 WIDE YELLOW with 6 WIDE RED. RESPONSE TO QUESTIONS Rotor Electric Company email dated 6/8/2018 Question 1: We have found a discrepancy in the Contract Documents. Specification Section 16231-7 states that the minimum Generator size is to be 350 KW. Contract Drawing E-601 shows the Generator sized at 150 KW. Please confirm the size of the Generator. The Generator is to be sized at a minimum 150 KW. Contract documents for this requirement have been amended herein. Clark Construction Company email dated 6/11/2018 Question 1: Sheet D-002, There are two (2) New Gate Valves called off as G-100 & G101, on Sheet D-500 these valves are called off as G-100 & G-102, Please clarify which numbers are correct. Under CHANGES TO DRAWINGS, see change for drawing D-500 included in this Question 2: Sheet M-101, Shows V-20, 21, 22,23, & 24 as remaining in place. Sheet D-500 shows V- 20, 21, & 22 as New and V-23 & 24 as refurbished, Please Clarify Question 3: Question 4: Under CHANGES TO DRAWINGS, see change for drawing M-101 included in this Sheet E-101, Trenching Detail calls for YELLOW polyethylene Marking Tape, This tape is normally RED, Please clarify which color to use. Under CHANGES TO DRAWINGS, see change for drawing E-002 included in this Sheet M-104, Note 4 refers to a utility allowance to be used for additional gas line work. The RFB has a Cash Allowance of $15,000 for New Gas Service, are these the same? Please Clarify. Under CHANGES TO DRAWINGS, See change for drawing M-104 included in this Page 3 of 8

Question 5: Question 6: Appendix F of the RFB show a Cash Allowance for Permits, Please Clarify which Permits are required. Refer to Construction Agreement, 4.6 and Section 01210 for description of permits. Contractor is responsibly to obtain. Removal and lowering of equipment into the lower level of the pipe gallery will require the use of the existing 30-ton bridge crane. Please indicate whether Plant Operations will allow the contractor to use of the crane and whether a GLWA operator will be available to operate the crane as needed. Refer to Section 01110, page 4. Question 7: I would like to request another site visit of this project. Please let me know if this is possible. Refer to Addendum No. 2. Weiss Construction Co. LLC email dated 6/11/2018 Question 1: Given the current bid due date s close proximity to the July 4th holiday, we respectfully request that the bid due date be extended a few days to allow for the necessary coordination for an accurate bid to take place. Refer to Addendum No. 2. Question 2: Question 3: We respectfully request a second site walkthrough be scheduled. See response to Clark Construction Question 7 included in this Please confirm this project has an anticipated Notice to Proceed of October/November 2018 as mentioned in the pre-bid conference. This is correct; the anticipated Notice to Proceed is in October 2018. Question 4: Question 5: Given the complexity of the construction sequencing, work restrictions, and coordination with other contracts, it will not be feasible to submit an accurate schedule in accordance with Appendix G of the RFB. Please confirm the submission of a plausible construction schedule will be satisfactory at the time of bid. Please also confirm that the contractor will not be held accountable for deviations from the dates shown in the bid schedule. Contractor shall submit a schedule that best anticipates the constraints as provided in the contract documents. Any assumptions or restrictions shall be noted on the schedule. Given the complexity of the construction sequencing, work restrictions, coordination with other contracts, and lead times for equipment and refurbishment, the targeted completion Page 4 of 8

dates of July 1, 2020 (Substantial) and October 1, 2020 (Final) do not appear to be feasible. We respectfully request the contract duration be extended ten months to include an additional Non-Peak season to allow the contract work to be completed based on the assumption of an October/November 2018 NTP. This would result in a targeted Substantial Completion date of May 1, 2021 and a targeted Final Completion date of July 1, 2021. Question 6: Question 7: Question 8: Question 9: Under CHANGES TO CONSTRUCTION AGREEMENT, See changes to duration included in this Please note Specification Section 01110 Paragraph 1.04.A.5.a.1.a, please clarify if GLWA plant staff is able to exercise the inlet isolation butterfly valves associated with HL Pumps 4 & 5 to determine if they are operable prior to the bid submission date. If not, please provide an alternate isolation plan to allow this work to be performed. GLWA plant staff has been able to exercise the inlet isolation butterfly valves at these locations. Please note Specification Section 01110 Paragraph 1.04.A.11.a, please clarify if a certified operator of the contractor is able to operate the bridge crane, or if we must use GLWA personnel. If GLWA personnel must be utilized, please confirm they will be available for all working hours that require crane use including extended hours as required to meet scheduling restrictions. Under CHANGES TO SPECIFICATIONS, see changes for Summary of Work included in this Please note Drawing D-503, please clarify if the existing design of the G-3 stop logs is adequate for the new stop logs, and if any specific manufacturers must be utilized for fabrication. Please also clarify if Tetra Tech will be performing the final structural approval of the new stop logs, or if the contractor is required to carry a PE stamp for the final shop drawings. Under CHANGES TO SPECIFICATIONS, see changes for Summary of Work included in this Please note Specification Section 01110 Paragraph 1.06.D.3, states work shall progress every day at a steady pace until completed. Please define this statement. The contractor assumes this mean a standard 5-day, 40-hr work week. Contractor shall review schedule and proceed accordingly to maintain project schedule at all times. Contractor would require written approval for work outside of normal business hours and shall coordinate such approvals with GLWA staff. Days where contractor does not work shall be documented during construction for purposes of tracking schedule progress and time delays. Standard work weeks are five days and for forty hours. Contractor shall note that taking equipment out of service shall not be Page 5 of 8

permitted unless work is actively progressing. Any long-term equipment shutoffs shall be coordinated and approved by the Owner, Engineer, and GLWASC as needed. Question 10: Question 11: Question 12: Question 13: Question 14: Question 15: Please note Specification Section 01110 Paragraph 1.06.D.4, please confirm GLWA plant staff will be responsible for installing the stop plates on the pump suction wells including the newly fabricated stop plates. Please also clarify if the contractor may assist with this installation to ensure the potential for leaking is minimized GLWA plant staff will install stop plates on the pump suction wells. Contractor will be present during initial installation to verify stop plates have been delivered in proper working order and without deviation from requested design requirements. Please note Drawings D-002 & D-500, the valve schedule on drawing D-500 references (2) gate valves G-100 & 102, however drawing D-002 shows (2) gate valves G-100 & G- 101. Please confirm these reference the same valves, and that there are only (2) gate valves associated with this project. See response to Clark Construction Question No. 1 included in this Please note Drawing D-503 Note 2, the reference drawings mentioned do not appear to be included within the released bid documents. Please issue these reference drawings. Contract W-143 and CON-133 are available upon request for review at the Water Resource Recovery Facility, 4th floor document control center from Mr. Jason Williams. His number is (313) 297-0230. Please note Specification Section 01110, there are several mentions of service water supply valves that need to be closed as part of the construction sequencing. Please provide the condition of these valves and if they are expected to leak. If they are expected to leak, please provide further direction on how to handle this water. Under CHANGES TO SPECIFICATIONS, see changes for Summary of Work included in this Please note Drawing D-503 Note 3, please confirm approved epoxy coating system manufacturers are the same as specified in Specification Section 09900 or if a specific system is required. Under CHANGES TO SPECIFICATIONS, see changes for Painting included in this Can GLWA please provide the flow rates or operating pressures for the 42 BFV s, in order to accurately size the EMO? In addition, should the EMOs be used for Open close or throttling service. Page 6 of 8

Question 16: Question 17: Question 18: As noted on Specification page 15110-3, butterfly valves shall be designed for AWWA C504, 150 psi working pressure and be Class 150B with the B referring to 16 f/s velocity. See Valve Schedule on D-500, Valve Schedule, Remarks column for the service which the 42 valves is Open-Shut. Please note Specification Section 01500 Paragraph 3.03.D, please confirm that a temporary field office for the engineer is required to be provided by the contractor for this project. Contractor shall provide a temporary trailer field office during the duration of the project. The temporary field office shall have an office for the Engineer. Please note Specification Section 01330 Paragraph 1.08, please clarify what the expected review duration will be for submittals and shop drawings. Engineer s expected review duration for each submittal is three weeks, or fifteen business days. Please note Specification Section 01330 Paragraph 1.10 & 1.11, please clarify if the progress and record photographs must be taken by a professional photographer, and if so, please clarify the expected number of photographs to be submitted. Contractor shall provide photographs with clear and visible features. A professional photographer is not required. Contractor shall submit photographs to capture all pertinent information of the required subject. The number of photos necessary to capture each item will vary. PCI Vetrix LLC email dated 6/12/2018 Question 1: Question 2: On the I&C drawings (I-xxx), there are references to "ECP" but there is no description of what this system or device is. Please clarify. ECP is the Electrical Control Panel as shown and labeled on E-603. Will the new gate actuators be controlled via a position setpoint, or full Open/Close? The I/O shown coming off of the actuators on I-101 through 104 shows both types - Z* for analogs, X* for digitals. The control scheme for each actuator is detailed out in Specification 16748. Question 3: Please provide a description of the I/O tags shown coming off of the actuators. Discharge Valves: signals to Ovation Panel - analog position feedback, analog position control, digital auto/man selection, digital open/close; signals to ECP - Valve 40% open NO, Valve 40% open NC, Valve 95% closed Header Valves: signals to Ovation Panel - Valve full open, Valve full closed. Page 7 of 8

Question 4: Question 5: Question 6: Question 7: The specifications (16748) reference PLC programming - are there any new PLC's being provided in this project? No. The Contractor is updating the existing controller programming to provide the control scheme called for in the specification. Spec section 16748-1.02-I calls for a 3-year warranty that includes software updates. What type of updates are inferred? Normal patches and fixes, or revision level updates/upgrades? As clearly stated in the specification service shall include software package updates and phone/personal support for software package issues. 16748-2.01-D calls for an additional 160 hours of software support time after the SAT is completed. Please clarify the requirement and expectations for this time. 160 hours of programmer time to perform whatever tasks the Owner requests. 16748-2.01-E calls for "minimum of 40 parameters" for each stormwater pump. Are the pumps included in this project? If the parameters called for in the specification do not exist, will the equipment be added by GLWA? The physical pumps are not part of this project, however, the updating of the HMI screens is part of this project. The HMI screens shall be updated as called for in the specification. Page 8 of 8