Inverter-Based Resource Disturbance Analysis

Similar documents
1200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report

Loss of Solar Resources during Transmission Disturbances due to Inverter Settings II

900 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report

BPS-Connected Inverter-Based Resource Performance

1,200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report

Implementation of Revised IEEE Standard 1547

Response of Grid Interconnected Solar PV inverters to Transmission System Faults

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC

INTERIM ARRANGEMENTS FOR GRID TIED DISTRIBUTED ENERGY RESOURCES. Technical Requirements for Grid-Tied DERs

Transmission Interconnection Requirements for Inverter-Based Generation

E N G I N E E R I N G M A N U A L

Final ballot January BOT adoption February 2015

Grid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

Technical Requirements for Connecting Small Scale PV (sspv) Systems to Low Voltage Distribution Networks

Possible Future Modifications to IEEE 1547

Renewable Interconnection Standard & Experimental Tests. Yahia Baghzouz UNLV Las Vegas, NV, USA

DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation

IEEE sion/1547revision_index.html

Setting and Verification of Generation Protection to Meet NERC Reliability Standards

Inverter Source Requirement Document of ISO New England (ISO-NE)

Generation and Load Interconnection Standard

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

Wind Power Facility Technical Requirements CHANGE HISTORY

Harmonizing the Changing Resource Mix Keeping the Grid Together

DER Ride-Through Performance Categories and Trip Settings Presentation at PJM Ride-Through Workshop, Philadelphia, PA, October 1-2, 2018

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

Revised IEEE 1547 Standard for Interconnecting Distributed Energy Resources with Electric Power Systems- National Grid Solar Program

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

Protective Relaying for DER

Ameren Illinois Company d/b/a Ameren Illinois Smart Inverter Specifications

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/

Generation and Load Interconnection Standard

IEEE Std Bulk System Opportunities from New Distributed Energy Resource Interconnection and Interoperability Standards

BED INTERCONNECTION TECHNICAL REQUIREMENTS

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF GENERATION FACILITIES NOT SUBJECT TO FERC JURISDICTION

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event

Jonathan (Xiangmin) Gao - GE Grid Solutions Douglas Rust - Dandsco LLC Presented by: Tom Ernst GE Grid Solutions

Southern Company Interconnection Requirements for Inverter-Based Generation

IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces

PRC Disturbance Monitoring and Reporting Requirements

Industry Webinar. Reactive Power Planning. NERC System Analysis and Modeling Subcommittee (SAMS) March 2017

IEEE Major Revision of Interconnection Standard

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications

Table of Contents. Introduction... 1

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications

Impact of High PV Penetration on Grid Operation. Yahia Baghzouz Professor of Electrical engineering University of Nevada Las Vegas

NPCC Regional Reliability Reference Directory # 12. Underfrequency Load Shedding Program Requirements

1

IEEE sion/1547revision_index.html

Phase-phase/phase-neutral: 24/13.8 kv star, 13.8 kv delta, 12/6.9 kv star.

Synchrophasor Technology PMU Use Case Examples

FNN comments on NC HVDC submitted to ENTSO E

Fuel cell power system connection. Dynamics and Control of Distributed Power Systems. DC storage. DC/DC boost converter (1)

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

Technical information SUNNY TRIPOWER CORE1-US

HARDWARE BASED CHARACTERISATION OF LV INVERTER FAULT RESPONSE

Generation Interconnection Requirements at Voltages 34.5 kv and Below

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

Sarma (NDR) Nuthalapati, PhD

The Connecticut Light and Power Company

GUIDE FOR GENERATOR INTERCONNECTION THE WIRES OWNER DISTRIBUTION SYSTEM

Technical information SUNNY BOY 3.0-US / 3.8-US / 5.0-US / 6.0-US / 7.0-US / 7.7-US

POWER QUALITY A N D Y O U R B U S I N E S S THE CENTRE FOR ENERGY ADVANCEMENT THROUGH TECHNOLOGICAL I NNOVATION

Technical information Grid Support Utility Interactive Inverters for Sunny Central-US and Sunny Central Storage-US

each time the Frequency is above 51Hz. Continuous operation is required

Power Quality Basics. Presented by. Scott Peele PE

SolidGround TM grid stability and harmonics mitigation system Geomagnetic Storm Induced Current (GIC) and Electromagnetic Pulse (EMP) protection

Intermittent Renewable Resources (Wind and PV) Distribution Connection Code (DCC) At Medium Voltage (MV)

Power Plant and Transmission System Protection Coordination

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF LARGE GENERATION FACILITIES. Document 9020

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

Highgate Converter Overview. Prepared by Joshua Burroughs & Jeff Carrara IEEE PES

POWER QUALITY IMPACTS AND MITIGATION OF DISTRIBUTED SOLAR POWER

Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES

TECHNICAL GUIDELINE FOR THE INTERCONNECTION OF DISTRIBUTED ENERGY RESOURCES TO EPCOR DISTRIBUTION AND TRANSMISSION INC. S DISTRIBUTION SYSTEM

Parameters related to frequency stability

Introduce system protection relays like underfrequency relays, rate of change of frequency relays, reverse - power flow

Recently, the SS38 Working Group on Inter-Area Dynamic Analysis completed two study reports on behalf of the UFLS Regional Standard Drafting Team.

Implementation Plan Project Modifications to PRC Reliability Standard PRC-025-2

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number: Address:

System Protection and Control Subcommittee

EH2741 Communication and Control in Electric Power Systems Lecture 2

Anti-Islanding Protection of Distributed Generation Resources Using Negative Sequence Component of Voltage

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY

TechSurveillance. Revision of IEEE Standard New Disturbance Response Requirements. Business & Technology Strategies.

A Tutorial on the Application and Setting of Collector Feeder Overcurrent Relays at Wind Electric Plants

Utility Interconnection and System Protection

Power Quality enhancement of a distribution line with DSTATCOM

Performance of Distributed Energy Resources During and After System Disturbance Voltage and Frequency Ride-Through Requirements

Testing Advanced Photovoltaic Inverters Conforming to IEEE Standard 1547 Amendment 1

PQ Monitoring Standards

An Introduction to Completing a NERC PRC-019 Study for Traditional and Distributed Generation Sources

Improvement of Islanding Detector Using Interharmonics Current Injection Method and Its Applications

Grid Converters for Photovoltaic

Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES

Experiences in Integrating PV and Other DG to the Power System

2012 Grid of the Future Symposium. Impacts of the Decentralized Photovoltaic Energy Resources on the Grid

Transcription:

Inverter-Based Resource Disturbance Analysis Key Findings and Recommendations Informational Webinar February 15, 2018

August 16, 2016 Blue Cut Fire Disturbance Key Findings and Recommendations 2

Western Interconnection Frequency 3

500 kv Fault Trace Phase A amps Phase B amps Phase C amps Residual amps 4

Solar Resource Loss 5

Data Gathering 26 different solar developments All utility scale Majority connected at 500kV or 230kV 10 different inverter manufacturers Reported causes of trips Under frequency Under voltage Over voltage DC overcurrent 1 loss of synchronism 6

Not an Isolated Event 7 # Date/Time 1 2 3 4 5 6 7 8 9 10 11 08/16/2016 11:45 08/16/2016 14:04 08/16/2016 15:13 08/16/2016 15:19 09/06/2016 13:17 09/12/2016 17:40 11/12/2016 10:00 02/06/2017 12:13 02/06/2017 12:31 02/06/2017 13:03 05/10/2017 10:13 Fault Location 500 kv line 500 kv line 500 kv line 500 kv line 220 kv line 500 kv line 500 kv CB 500 kv line 500 kv line 500 kv line Fault Type Line to Line (AB) Line to Ground (AG) Line to Ground (AG) Line to Ground (AG) Line to Ground (AG) Line to Ground (BG) Line to Ground (CG) Line to Ground (BG) Line to Ground (BG) Line to Ground (BG) Clearing Time (cycles) Lost Generation (MW) Geographic Impact 2.49 1,178 Widespread 2.93 234 500 kv line unknown unknown 579 Somewhat Localized 3.45 311 Widespread 3.05 30 Localized 2.5 490 Localized 3.04 62 Localized 2.05 231 Widespread 2.97 319 Widespread 3.01 38 Localized 3.00 543 Widespread Somewhat Localized

Key Finding #1 Largest block of solar PV loss (~700 MW) due to underfrequency tripping Inverter sensed a near instantaneous frequency of <57 Hz and tripped instantaneously 8

What Was the Frequency? 9

Phase Jump 10

PRC-024-2 Frequency Ride-Through Curve 11

Issues 12

Key Finding #1 Isolated to one inverter manufacturer Manufacturer quickly devised solution following event Added time delay to inverter frequency tripping Allows inverter to ride through transient/distorted waveform period without tripping. 13

Key Finding #2: Undervoltage Tripping 2 nd largest block of inverter loss (~450 MW) was attributed to low voltage 14

PRC-024-2 Voltage Ride-Through Curve 15

Key Finding #2 Inverters have three modes of operation Operating (injecting active current into the system) Momentary Cessation (momentarily cease to inject current during voltages outside continuous operating range -.9 to 1.0 per unit) Trip (cease to inject current, disconnect from grid, wait ~ five minutes and return to service if grid voltage and frequency are within bounds) 16

Key Finding #2 The inverters did not Trip, they went into Momentary Cessation Majority of installed inverters set to momentarily cease current injection for voltages of V <.9 p.u. or V > 1.1 p.u. In inverter language, Momentary Cessation does not equal trip 17

Actions in response to Blue Cut Fire Frequency tripping Manufacturer is adding tripping delay Simulations to identify momentary cessation risk ~7200 MW potential Specify maximum delay and ramp rate for Restore Output 18

Key Findings and Recommendations NERC Alert/Recommendation to Industry was issued 6/20/2017 Work with inverter manufacturer to ensure no erroneous frequency tripping If momentary cessation is used, restore output in no more than 5 seconds 19

Alert responses 20

Alert responses 21

Key Findings and Recommendations Further study needed for risk associated with momentary cessation (IRPTF) Clarify that outside the PRC-024 frequency and voltage ridethrough curves are may trip, not must trip Review PRC-024 to determine if any changes are needed 22

October 9, 2017 Canyon 2 Fire Disturbance Key Findings and Recommendations 23

Map of Affected Area 24

Two Fault Events Smoke-induced L-L fault events caused by Canyon 2 Fire Both fault cleared normally Fault Event 1: 220 kv L-L Fault < 3 cycle clearing Fault Event 2: 500 kv L-L Fault < 3 cycle clearing 25

Frequency Response from 500 kv Fault Event #2 26

Aggregate SCE Solar PV Performance SCADA Data ~15 minutes -74-682 -1011 Event 1: 682 0 = 682 MW Event 2: 1011 74 = 937 MW 27

Solar PV Outputs Northeastern Northern Eastern 28

Solar PV Outputs 29

Key Findings 1. No erroneous frequency tripping 2. Continued use of momentary cessation 3. Ramp rate interactions with return from momentary cessation 4. Interpretation of PRC-024-2 voltage ride-through curve 5. Instantaneous voltage tripping and measurement filtering 6. Phase lock loop synchronization issues 7. DC reverse current tripping 8. Transient interactions and ride-through considerations 30

Key Findings #1 No erroneous frequency tripping Alert recommended GOPs and GOs ensure inverter controls do not erroneously trip on instantaneous frequency measurements By October 9, 2017 event, 97% of inverter manufacturer s BPSconnected fleet had been updated Mitigating actions by inverter manufacturer and GOs appear to have worked 31

Key Findings #2 Continued use of momentary cessation Majority of existing inverters use momentary cessation Most use a low voltage threshold of ~0.9 pu Recovery of current following momentary cessation varies, relatively slow for grid dynamics Blue Cut Fire recommendation interim solution NERC IRPTF studies new recommendation Stability studies show potential BPS wide-area stability issues 32

Clarification and Recommendation for Momentary Cessation t fault 33

Clarification and Recommendation for Momentary Cessation t fault + 0.5 sec 34

Clarification and Recommendation for Momentary Cessation t fault + 1.0 sec 35

Clarification and Recommendation for Momentary Cessation t fault + 1.5 sec 36

Clarification and Recommendation for Momentary Cessation t fault + 2.0 sec 37

Clarification and Recommendation for Momentary Cessation t fault + 2.8 sec 38

Momentary Cessation Recommendation Moving Forward Generator Owners should coordinate with their inverter manufacturer(s) to eliminate momentary cessation (MC) to the greatest extent possible. For inverters where MC cannot be eliminated (e.g., use another form of ride-through mode), MC settings should be changed by: Reducing the MC low voltage threshold to the lowest value possible. Reducing the recovery delay to the smallest value possible (e.g., on the order of 1-3 electrical cycles). Increasing the active power ramp rate to at least 100% per second (e.g., return to pre-disturbance active current injection within 1 second). Setting reactive current priority upon recovery (if applicable) should eliminate the use of MC on all inverters that are capable of continuous current injection during abnormal voltages. 39

Key Findings #3 Ramp rate interactions with return from momentary cessation 40

Key Findings #4 Interpretation of PRC-024-2 voltage ride-through curve 41

Key Findings #4 Clarification 1 Interpretation of PRC-024-2 voltage ride-through curve May Trip Zone NOT a Must Trip Zone 42

Key Findings #4 Clarification 2 Interpretation of PRC-024-2 voltage ride-through curve This curve is a minimum requirement. This curves should NOT be a design criteria. Protection should be set based on equipment limitations. Equipment should be designed as robust as possible. 43

Key Findings #4 Clarification 3 Interpretation of PRC-024-2 voltage ride-through curve Requirement R2: Each Generator Owner that has generator voltage protective relaying1 activated to trip its applicable generating unit(s) shall set its protective relaying such that the generator voltage protective relaying does not trip the applicable generating unit(s) as a result of a voltage excursion (at the point of interconnection 3 ) caused by an event on the transmission system external to the generating plant that remains within the no trip zone of PRC-024 Attachment 2. Footnote 3: For the purposes of this standard, point of interconnection means the transmission (high voltage) side of the generator step-up or collector transformer. 44

Key Findings #5 Instantaneous voltage tripping and measurement filtering 45

Key Findings #5 Instantaneous voltage tripping and measurement filtering 46

Key Findings #5 IRPTF Recommended HVRT Instantaneous voltage tripping and measurement filtering 47

Key Findings #6 Phase lock loop synchronization issues Grid voltage phase jumps occur (e.g., during faults) Inverter PLLs should be robust to withstand BPS phase jumps Should not result in inverter tripping or momentary cessation Advanced controls should enable PLL ride-through rather than tripping 48

Key Findings #7 DC reverse current tripping Anti-parallel diodes dissipate energy, mitigate voltage spikes Can conduct if forward biased (AC voltage > DC voltage) UL 1741 requires testing and detection, no specified trip settings DC reverse current detection protects panels, not inverter Very sensitive settings for one plant 49

Key Findings #8 Transient interactions and ride-through considerations Interactions between momentary cessation, in-plant shunt capacitors, transient voltages, harmonics, etc., that are not sufficient understood Requires detailed electromagnetic transient (EMT) studies needed 50

Next Steps and Future Work Disturbance Report to be published in February 2018 NERC Alert to be published in likely March 2018 Mitigation of momentary cessation Voltage protective control functions PRC-024-2 curve interpretation Transient overvoltage settings IRPTF will be publishing a Reliability Guideline on Inverter-Based Resources Performance in Q3 or Q4 2018 51

Relevant Links Blue Cut Fire Disturbance Report: http://www.nerc.com/pa/rrm/ea/pages/1200-mw-fault-induced-solar- Photovoltaic-Resource-Interruption-Disturbance-Report.aspx EA Page (for future Disturbance Report): http://www.nerc.com/pa/rrm/ea/pages/default.aspx NERC Alerts Page: http://www.nerc.com/pa/rrm/bpsa/pages/alerts.aspx IRPTF Page: http://www.nerc.com/comm/pc/pages/inverter-based-resource- Performance-Task-Force.aspx 52

Rich Bauer Associate Director Reliability Risk Management-Event Analysis Office (404) 446-9738 Cell (404) 357-9843 rich.bauer@nerc.net Ryan Quint Senior Manager, Advanced Analytics and Modeling Office (202) 400-3015 Cell (202) 809-3079 ryan.quint@nerc.net 53