Controllable Generation UCAP determination. Eligibility WG September 12, 2017

Similar documents
Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting

Procedure for ERO Support of Frequency Response and Frequency Bias Setting Standard. Event Selection Process

Geoff Brown & Associates Ltd

Transmission Facilities Rating Methodology for Florida

System Operating Limit Definition and Exceedance Clarification

generation greater than 75 MVA (gross aggregate nameplate rating) Generation in the ERCOT Interconnection with the following characteristics:

FACILITY RATINGS METHOD TABLE OF CONTENTS

Agricultural Data Verification Protocol for the Chesapeake Bay Program Partnership

Unit Auxiliary Transformer Overcurrent Relay Loadability During a Transmission Depressed Voltage Condition

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

Transmission Facilities Rating Methodology

Statistical Pulse Measurements using USB Power Sensors

DUKE ENERGY CAROLINAS TRANSMISSION SYSTEM PLANNING GUIDELINES. Transmission Planning

PJM Regulation Study Update

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

Comfort and Load Control: It s Getting Hot in Here But is the Utility to Blame?

POWER POTENTIAL: DISTRIBUTED ENERGY RESOURCES (DER) TECHNICAL SPECIFICATIONS GUIDANCE FOR PROVISION OF REACTIVE AND ACTIVE POWER SERVICES

NORMES DE FIABILITÉ DE LA NERC (VERSION ANGLAISE)

Wireless Transmissions:

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules. 45-day Formal Comment Period with Initial Ballot June July 2014

ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES Revision 0

Voltage and Reactive Procedures CMP-VAR-01

SYNCHROPHASOR TECHNOLOGY GLOSSARY Revision Date: April 24, 2011

Engineering Recommendation M30 Issue Standard Electricity Network Operator Electricity Smart Meter Configurations

Transmission Availability Data System Phase II Final Report

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules

Central Hudson Gas & Electric Corporation. Transmission Planning Guidelines

GridLiance Reliability Criteria

Unit Auxiliary Transformer (UAT) Relay Loadability Report

Bulk Electric System Definition Reference Document

ESB National Grid Transmission Planning Criteria

Utility Systems Technologies, Inc. Sag Fighter. Deep Voltage Sag Protection:

TRANSMISSION FACILITIES...7

Planning Criteria. Revision 1.4 MAINTAINED BY: Transmission Working Group System Protection and Control Working Group Supply Adequacy Working Group

TTC Study for: the PEGS-Ambrosia Lake 230 kv Line and the PEGS-Bluewater 115 kv Line

Capacity Market Prequalification

Final ballot January BOT adoption February 2015

MidAmerican Energy Company Reliability Planning Criteria for 100 kv and Above

Table 1 - Assignment of BA Obligations... 8

Module 7-4 N-Area Reliability Program (NARP)

Load-Frequency Control Service in a Deregulated Environment

Transmission Availability Data System 2008 Automatic Outage Metrics and Data Report Region: RFC

Evaluation of Algorithm Performance /06 Gas Year Scaling Factor and Weather Correction Factor

Reliability Guideline Integrating Reporting ACE with the NERC Reliability Standards

VI.D AIR DISCONNECT SWITCHES

System Ratings, Limits and Real-Time Monitoring. Presented to: Operating Committee April 21, 2016

Standard MOD Area Interchange Methodology

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

Air Monitoring Directive Chapter 9: Reporting

General Specifications

Recently, the SS38 Working Group on Inter-Area Dynamic Analysis completed two study reports on behalf of the UFLS Regional Standard Drafting Team.

Cymbaluk Noise Complaints

WATER MAIN ALONG ENTRANCE TO ENCINO PS / HWY 281 TO ENCINO TANK Solicitation Number: CO Job No.:

AHRI Standard Standard for Performance Rating of Modulating Positive Displacement Refrigerant Compressors

60V, 50mA, Ultra-Low Quiescent Current, Linear Regulator

Calculating and Using Reporting ACE in a Tie Line Bias Control Program

ROCHESTER PUBLIC UTILITIES FACILITY RATINGS METHODOLOGY FOR TRANSMISSION, SUBSTATION, & GENERATION EQUIPMENT

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number: Address:

NPCC Regional Reliability Reference Directory # 12. Underfrequency Load Shedding Program Requirements

Alberta Reliability Standard Frequency Response and Frequency Bias Setting BAL-003-AB-1.1

Bulk Electric System Definition Reference Document

OPTIONS [MATH FUNCTION] [TOTALIZER] [FLOW CORRECTION]

1

COURSE NOTES Testing Compliance to Energy Efficiency Standards

Frequency Response Characteristic Survey Training Document

Lab/Project Error Control Coding using LDPC Codes and HARQ

Line Impedance Estimation Using SCADA Data

Available Transfer Capability (ATC) EE 521 Analysis of Power Systems Chen-Ching Liu Washington State University

A New Approach for Transformer Bushing Monitoring. Emilio Morales Technical Application Specialist Qualitrol

DIGITAL THERMOMETER VIEW RECORDERS Digital Thermometer FEATURES

Category: ELECTRICITY Requirement: EL-ENG Page: 1 of 13. Document(s): S-E-01, S-E-04 Issue Date: Effective Date:

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System

ST662AB ST662AC. DC-DC converter from 5 V to 12 V, 0.03 A for Flash memory programming supply. Features. Description

Appendix D Fault Levels

General report format, ref. Article 12 of the Birds Directive, for the report

Proposed Language in BAL-003-1/Comments New Standard or Other Action R1. Each Balancing Authority shall This. Attachment A.

The LIPAedge program has established the following rules for its operation:

Tampa Electric Company Facility Rating Methodology Approved 11/20/2018

15.2 Rate Schedule 2 - Payments for Supplying Voltage Support Service

Area Control Error (ACE) Equation Special Cases

ATTACHMENT Y STUDY REPORT

Standard Development Timeline

Office for Nuclear Regulation

NARUC. Summer Committee Meetings. Staff Subcommittees on Electricity & Electric Reliability

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event

8th Floor, 125 London Wall, London EC2Y 5AS Tel: +44 (0) Fax: +44 (0)

Loss of Solar Resources during Transmission Disturbances due to Inverter Settings II

MSI Design Examples. Designing a circuit that adds three 4-bit numbers

Transmission Availability Data System Automatic Outage Metrics and Data. Region: RFC 2009 Report

Parasitically Powered Digital Input

Bulk Electric System Definition Reference Document

The Engineering Problem. Calculating GIC Flow through the EHV System

Consultation on Proposed National Rollout of Electricity and Gas Smart Metering

Distributed generation on 11kV voltage constrained feeders

G1 Capacity Market Metering

PRC Disturbance Monitoring and Reporting Requirements

Transcription:

Controllable Generation UCAP determination Eligibility WG September 12, 2017

Purpose and objective The objectives of this presentation include: Recap the installed capacity (ICAP) and unforced capacity (UCAP) definitions Understand the data requirements for UCAP Compare GADs and AESO data Request feedback from workgroup 1

Recall from July 4 th meeting UCAP Calculation for a Thermal Resource Example: Gas Combined Cycle with a nameplate capacity of 500 MW Seasonal Net Dependable (ICAP) accounts for the impact of ambient weather conditions (Summer) on unit performance Unforced Capacity (UCAP) is the ICAP value of the unit reduced by its recent actual forced outage rate during system demand periods (EFORd) Generator will able to offer 396 UCAP MW into the capacity auction Nameplate capacity rating = 500 MW Nameplate capacity modified for seasonal ambient limitations (ICAP). Example: If ambient temprature reduction is 10 % of the nameplate capacity. Ex. ICAP = 500 MW * 90% = 450 MW UCAP= ICAP * (1-EFORd) Forced outage rate = 12% UCAP = ICAP * (1- forced outage rate) Ex. If UCAP = 450 MW * (1-0.12) = 396 MW Public 2

UCAP calculation and data requirements UCAP= ICAP x (1- EFORd) where Equivalent Demand Forced Outage Rate (EFORd) is a measure of probability that a generating unit will not be available due to forced outages or forced derates when there is a demand on the unit to generate* The EFORd calculation relies on reliability data that comes from the Generation Availability Data System (GADS). GADs data are collected by NERC and provide information about the performance and outages / derates of generating units** The UCAP calculation may have different data requirements for uncontrollable and controllable generation AESO does not have GADS data *PJM Capacity Market/ PJM Manual 18/PJM Capacity Market Operations http://www.pjm.com/~/media/documents/manuals/m18.ashx **http://www.nerc.com/pa/rapa/gads/pages/default.aspx 3

UCAP Calculation: ETS data deficiencies Information needed for calculating UCAP based on EFORd Duration of Forced outages, Planned Outages, Forced Derates and Planned Derates Service Hours (The period of time that the unit was generating electricity) Reserve Shutdown ( the period that the unit was available, but not dispatched) Number of Actual Starts and Attempted Unit Starts Do we have this information? NO Yes Yes NO Comments ETS gives the option to the participants to leave out the event type in their submissions within a 7 day period before the event. In the case that they do not submit this field, it would be automatically populated using a logic that does not allow participants to clearly distinguish between forced and planned events. Therefore the event field would not be useful in determining the type of the outages and derates. This could be extracted from the metered volumes. When the unit is available (AC 0) but generation is zero. The data are not available. Based on the data currently available, calculation of UCAP based on EFORd methodology will be time consuming and complex. This methodology needs information similar to what GADs provide. However, this method could be used in the future if the GADS data become available. 4

Conceptual differences between AC and UCAP Maximum Capability = 200 MW PJM Ambient temp and humidity adjustment Alberta Ambient temp and humidity adjustment Maximum Capability = 200 MW ICAP = 170 MW 30 MW Forced outages/derates 30 MW 30 MW Forced outages/derates 30 MW PJM based UCAP for thermal generator = 140 MW Planned Outages/derates Planned Outages/derates ACf: is 140MWs UCAP is ICAP adjusted for performance through GADS data In other jurisdictions This example is for illustrative purposes only 40 MW + Available 100 MW 40 MW Available Capacity (AC in ETS) 100 MW AC = 100 MW AESO AC data does not separate between ambient, forced or planned outages. AC accounts for all lost generation UCAP: ICAP after capacity reduction due to forced outages and derates AESO ACf: ICAP after capacity reduction due to implied forced outages and implied derates AESO AC: ICAP after capacity reduction due to forced outages and derates and planned outages 5

Questions for the workgroup discussion Which option should be used for the interim UCAP calculation? A NERC mandate for 20MW and greater generators: do Alberta generators follow this requirement and have GADS data? Is the quality robust enough for use for UCAP Calculation? Are categorization practices comparable for all generation owners? Approach for generators less than 20MWs? If In the event ETS data is used, should AESO prioritize classifying outages earlier for the purpose of calculating more accurate UCAP on time for delivery during the transition period? Should the AESO investigate GADS further? Use GADS, AC or ACf for UCAP calculations? What demand hours should be used? 6

Thank you

Appendix B AC and AC f Overview Option 1: Use Available Capability as UCAP For existing resources this option uses historically submitted AC Variable resource may use capacity factors New resources and technologies may use class averages either from historical available capabilities or from sources outside the AESO for units with no historical data Seasons and demand hours will need to be defined Option 2: Use Available Capability that only includes forced outages/derates but excludes planned outages (AC F ) For existing resources this option uses historical AC submissions AC f may be calculated using a derate factor that only takes into account hours with forced outages and derates Forced outages are any outages/derates submitted within 7 days. Any submissions before 7 days are assumed to be planned Variable resource may use capacity factors New resources and technologies may use class averages either from historical available capabilities or from sources outside the AESO for units with no historical data Seasons and demand hours will need to be defined 8

Appendix B AC and AC f Advantages Option 1: Use Available Capability as UCAP Simple to understand and implement Availability of historical data Provides a conservative estimate of a plant s true capability as it includes planned and forced outages. Historical performance can be measured Option 2: Use Available Capability that only includes forced outages/derates but excludes planned outages (AC F ) This approach is closer in nature to way UCAP is calculated in North American capacity markets using GADs data Transition to GADS may be smoother as the difference in UCAP and ACF volumes may be lower Rules and compliance procedures in place to evaluate quality of AC submissions 9

Appendix B AC and AC f Disadvantages Option 1: Use Available Capability as UCAP Determining true availability of a unit will require additional work as some units may show full AC but not be dispatchable i.e. Long lead time, Mothball, peaking units, etc. AC data and rules were designed to meet the needs of an energy-only market and were not intended to fulfill the requirements of the UCAP calculation Option 2: Use Available Capability that only includes forced outages/derates but excludes planned outages (AC F ) More complex to implement as it requires parsing the data into planned and forced outages, which requires assumptions AC F will still be based on AC submissions, which were designed to meet the needs of an energy-only market and were not intended to fulfill the requirements of the UCAP calculation Methodology requires defining an approach to account for the impact of ambient weather conditions Method is still under investigation. AESO needs to further examine AC submission data to assess feasibility 10

Appendix B AC and AC f Example This example is only for illustrative purpose It intends to show the expected differences in magnitude between AC and AC f It uses a dummy generator with a maximum capability equal to 452 MW The same data set was used to calculate the AC and AC f values For the purpose of this example, the summer season comprised months from May to October and the winter season covered the months from November to April The actual months and HEs to be used in the UCAP methodology are yet to be decided 11

Appendix B AC and AC f Terminology Forced Outage Hours - FOH Sum of all hours experienced during Forced Outages. Forced outages are any outages submitted within 7 days. Equivalent Forced Derated Hours EFDH Forced derates are any derates submitted within 7 days. Each individual Forced Derating is transformed into equivalent full outage hour(s). This is calculated by multiplying the actual duration of the derating (hours) by the size of the reduction (MW) and dividing by the Maximum Capacity (MC). These equivalent hour(s) are then summed. (Derating Hours x Size of Reduction*)/ MC NOTE: Includes Forced Deratings during Reserve Shutdowns (RS). Service Hours SH Sum of all Unit Service Hours Equivalent Forced Derated Hours During Reserve Shutdowns EFDHRS Each individual Forced Derating or the portion of any Forced derating which occurred during a Reserve Shutdown (RS) is transformed into equivalent full outage hour(s). This is calculated by multiplying the actual duration of the derating (hours) by the size of the reduction (MW) and dividing by the Maximum Capacity (MC). These equivalent hour(s) are then summed. (Derating Hours x Size of Reduction*)/ MC 12

Appendix B AC and AC f Example Option 1: Use Available Capability as UCAP Option 2: Use Available Capability that only includes forced outages/derates but excludes planned outages (AC F ) AB1 Avg AC Median AC Max AC Min AC Summer 416 452 452 0 Winter 414 452 452 0 AC f = MC (1 Derate Factor) Derate Factor = FOH + EFDH FOH + SH + EFDHRS 100% AB1 Derate Factor AC f Summer 2.67% 440 Winter 4.25% 433 13