Low Frequency Demand Disconnection Summary

Similar documents
Loss of Mains Protection

ESB National Grid Transmission Planning Criteria

J Project Methods. V (%) Network with high generation and low load. Network with low generation and high load

Power Quality Summary

Geoff Brown & Associates Ltd

Network Monitoring and Visibility Summary

Table of Contents. Introduction... 1

Company Directive STANDARD TECHNIQUE: SD1E/2. Technical Requirements for Customer Export Limiting Schemes

EDS FAULT LEVELS

Frequency response White paper

each time the Frequency is above 51Hz. Continuous operation is required

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

EE 742 Power System Components. Y. Baghzouz ECE Department UNLV

EH2741 Communication and Control in Electric Power Systems Lecture 2

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

Company Directive POLICY DOCUMENT: SD4/7. Relating to 11kV and 6.6kV System Design

Islanding and Detection of Distributed Generation Islanding using Negative Sequence Component of Current

RfG Implementation Fault Ride Through

Appendix D Fault Levels

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event

E N G I N E E R I N G M A N U A L

DUKE ENERGY CAROLINAS TRANSMISSION SYSTEM PLANNING GUIDELINES. Transmission Planning

Single Line Diagram of Substations

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

ROCHESTER PUBLIC UTILITIES FACILITY RATINGS METHODOLOGY FOR TRANSMISSION, SUBSTATION, & GENERATION EQUIPMENT

Wind and Solar (PV) Sub harmonic Interactions with Power Systems

Unit 2. Single Line Diagram of Substations

Technical Requirements for Connecting Small Scale PV (sspv) Systems to Low Voltage Distribution Networks

Notes 1: Introduction to Distribution Systems

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

Considerations and Recommendations for the Harmonisation of Under Frequency Loadshedding Schemes in Multi Zone Meshed Grids

INTERIM ARRANGEMENTS FOR GRID TIED DISTRIBUTED ENERGY RESOURCES. Technical Requirements for Grid-Tied DERs

Fuel cell power system connection. Dynamics and Control of Distributed Power Systems. DC storage. DC/DC boost converter (1)

SYNCHROPHASOR TECHNOLOGY GLOSSARY Revision Date: April 24, 2011

MidAmerican Energy Company 69 kv Facility Ratings Methodology

SYNCHRONISING AND VOLTAGE SELECTION

Southern Company Interconnection Requirements for Inverter-Based Generation

SolidGround TM grid stability and harmonics mitigation system Geomagnetic Storm Induced Current (GIC) and Electromagnetic Pulse (EMP) protection

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

Harmonizing the Changing Resource Mix Keeping the Grid Together

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/

Fault Ride Through Principles. and. Grid Code Proposed Changes

ABB AG - EPDS. I S -limiter The worldʼs fastest limiting and switching device

MidAmerican Energy Company 100 kv and Above Facility Ratings Methodology

MidAmerican Energy Company Reliability Planning Criteria for 100 kv and Above

Wind Power Facility Technical Requirements CHANGE HISTORY

G59 and G83 Protection Requirements

TTC Study for: the PEGS-Ambrosia Lake 230 kv Line and the PEGS-Bluewater 115 kv Line

SDG&E Transmission Synchrophasor Project Update

Optimal sizing of battery energy storage system in microgrid system considering load shedding scheme

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

SCIENCE & TECHNOLOGY

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number: Address:

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting

Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing Methods

How to maximize reliability using an alternative distribution system for critical loads

Transmission Lines and Feeders Protection Pilot wire differential relays (Device 87L) Distance protection

Line Protection Roy Moxley Siemens USA

Robert W. Cummings - NERC Director of System Analysis and Reliability Initiatives William Herbsleb - Chairman of Frequency Response Standard Drafting

2012 Grid of the Future Symposium. Impacts of the Decentralized Photovoltaic Energy Resources on the Grid

Embedded Generation Connection Application Form

WSAT Online Tool for Assessment of Secure Level of Wind Generation on the System

The Value of Frequency Keeping and Governor Response to New Zealand

Central Hudson Gas & Electric Corporation. Transmission Planning Guidelines

Endorsed Assignments from ERS Framework

Industrial and Commercial Demand Response for outage management and as an alternative to network reinforcement

SHORT CIRCUIT ANALYSIS OF 220/132 KV SUBSTATION BY USING ETAP

Level 6 Graduate Diploma in Engineering Electrical Energy Systems

Network Equilibrium Balancing Act Conference Thursday 8th September 2016

A. df/dt Measurement principle by relays

Modelling Parameters. Affect on DER Impact Study Results

Appendix S: PROTECTION ALTERNATIVES FOR VARIOUS GENERATOR CONFIGURATIONS

The Connecticut Light and Power Company

Target Mchunu and Themba Khoza Eskom Transmission Division, System Operator Grid Code Management

Introduce system protection relays like underfrequency relays, rate of change of frequency relays, reverse - power flow

Voltage Relays. Ensuring Reliable Protection for Electrical Systems against Voltage Faults. ISO 9001:2008 Certified.

Low Frequency Local mode Oscillations in NER Grid, Validation using Model based analysis and Mitigation

WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS

MODELLING AND ANALYSIS OF THE ENHANCED TAPP SCHEME FOR DISTRIBUTION NETWORKS

ADVANCED VECTOR SHIFT ALGORITHM FOR ISLANDING DETECTION

Accurate Synchrophasor Estimation to Support the Islanding Maneuver of Active Distribution Networks

Hamdy Faramawy Senior Application Specialist ABB Sweden

POWER QUALITY IMPACTS AND MITIGATION OF DISTRIBUTED SOLAR POWER

The Role of Effective Parameters in Automatic Load-Shedding Regarding Deficit of Active Power in a Power System

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY

Implementation of Revised IEEE Standard 1547

Embedded Generation Connection Application Form

Response of Grid Interconnected Solar PV inverters to Transmission System Faults

Bus Protection Fundamentals

Transmission System Phase Backup Protection

Transmission Interconnection Requirements for Inverter-Based Generation

Protecting Feeders With Distributed Resource Scott Elling HDR Inc HDR, all rights reserved.

Prepared By Pierre Archambault, PEng Power Survey International Inc Trans Canada Hwy. St-Laurent, QC H4S 1S4 CANADA

DRAFT. City of Lethbridge Electric ENGINEERING STANDARDS GUIDELINE FOR GENERATOR INTERCONNECTION THE CITY OF LETHBRIDGE ELECTRIC DISTRIBUTION SYSTEM

GUIDE FOR GENERATOR INTERCONNECTION THE WIRES OWNER DISTRIBUTION SYSTEM

CAISO Restricted - Do Not Distribute Outside of RC Project LOI and NDA Entities Page 1 of 24

STANDARDS/MANUALS/ GUIDELINES FOR SMALL HYDRO DEVELOPMENT

SYSTEM MONITORING FAULT RECORDING

Transcription:

Low Frequency Demand Disconnection Summary This article assesses the suitability of current low frequency protection on the network as more distributed generation is connected to WPD s network. DSOF June 2018

Note: a glossary and diagram key can be found in the DSOF introduction document on our website Background Low Frequency Demand Disconnection (LFDD) schemes are designed to limit the fall in frequency for extreme events beyond those defined as secured events in the SQSS [1] and Operating Code OC6 (Demand Control) of the Grid Code [2]. Frequency plays a very important role in power transmission and distribution in relation to the balance between the demand and generation requirements of the network. The maintenance of system frequency within set levels is required to maintain stability and prevent a full system collapse. Under normal operating conditions National Grid as the System Operator (GBSO) is obligated to maintain the system frequency between 49.8 and 50.2 Hz. If the network generation is higher than the demand the frequency rises, however conversely if generation is lower than the demand the frequency reduces. As the generation at any instant is unlikely to equal the demand the frequency constantly varies. The variation in frequency is normally small and has little impact on customers. Any variation in frequency must be controlled to enable certain items of equipment (e.g. clocks) to operate correctly. The GBSO continuously monitors the frequency and dispatches the appropriate generator output. Should the total dispatch of generation available be insufficient to meet the demands due to a fault or loss of generation or an unexpected increase in demand, the frequency will fall. Under exceptional circumstances (e.g. loss of a large generator) the frequency should not deviate outside the range 49.5 to 50.5Hz for more than 60 seconds. In order to achieve this, the GBSO contracts frequency response to secure the power system for a number of events. There may be certain circumstances where the contracted frequency response may not be sufficient to maintain the system frequency between the statutory limits where the total loss of generation exceeds the amount secured for and a deficit of generation arises.. In order to reduce the generation deficit (or excess in demand) to maintain stability, Distribution Network Operators (DNOs) have low frequency relays to disconnect demand. This procedure is called LFDD and is described in Operating Code OC6 (Demand Control) of the Grid Code. Network Impact DNO Obligations To comply with the requirements of the Grid Code, Western Power Distribution as a DNO is obligated to install LFDD schemes. The schemes are designed to automatically disconnect at least 60% of the total DNO demand on a stage by stage basis at the time of the forecasted National Electricity Transmission System peak Demand. Implementation The demand subject to automatic low frequency disconnection is divided into 9 predetermined discrete MW blocks which are disconnected at defined low frequency levels. Each block of demand is distributed across each license area, so far as reasonably practical, so that the demand at different Grid Supply Point (GSP) sites is reduced evenly, as shown in Table 1. 2

Table 1: Low Frequency Demand Disconnection settings for each frequency disconnection block [2] Frequency (Hz) % of Demand Disconnection 48.8 5 48.75 5 48.7 10 48.6 7.5 48.5 7.5 48.4 7.5 48.2 7.5 48.0 5 47.8 5 Total % Demand 60 LFDD schemes are fitted at 132kV substations and are designed to trip the lower voltage side of the incoming 132kV transformers or some or all of the outgoing feeders. The operating time of an LFDD scheme is as far as reasonably practicable be less than 200mS. Growth of Distributed Generation The growth of distributed generation connected on DNO networks at voltage levels below where the LFDD relays are installed is likely to impact on the effectiveness of the scheme. If the level of distributed generation output is high when the relay is triggered, the amount of demand disconnected may be lower than expected. Conversely if the level of distributed generation output is low the amount of demand disconnected may be higher than expected. Decreasing System Inertia In addition levels of system inertia are decreasing (e.g. due to the closure of large power stations) along with net transmission system demand. This reduces the effectiveness of LFDD schemes as changes in frequency will be faster and larger. Should the frequency fall at a high rate, more than one LFDD stage could operate resulting in too much demand being disconnected. Detailed Assessment The following examples consider the impact of an LFDD scheme on a 132/33kV substation with a significant level of distributed generation connected (35.8MVA at 33kV & 28.2MVA at 11kV and below). The LFDD relays are connected to the 33kV circuit breaker on each 132/33kV transformer. The total installed capacity of Wind generation is around 16MVA and Solar PV 36.3 MVA. Winter with Minimal Generation A typical winter demand and load profile on a day with minimal distributed generation is shown in Figure 1 for a 132kV substation. The underlying network demand is deflated by any distributed generation connected at 11kV and below.

Figure 1: Typical Winter demand and load profile (minimal 33kV distributed generation) In the above graph the underlying network demand requirement and load-flow through the 132/33kV transformers is similar with only a small offset when the 33kV connected generation is exporting. At 12:00hrs the network demand is 29.5MVA of which 26.7MVA is fed via the 132/33kV transformers plus 2.8MVA from the distributed 33kV connected generation. If LFDD was required at this instant it would remove 26.7MVA of demand plus 2.8MVA of generation. Winter with Significant Generation A typical winter demand and load profile on a day with significant distributed generation is distorted as shown in Figure 2. The underlying network demand is deflated by any distributed generation connected at 11kV and below. Figure 2: Typical Winter demand and load profile (significant 33kV distributed generation) In the above graph the 33kV distributed generation output peaks during daylight hours causing reverse power-flow through the 132/33kV transformers for a 5.5 hour period (between 10:30 and 16:00 hrs). Should the LFDD relays be required to operate at 18:00 hrs, the load disconnected will consist of 19.21MVA of net demand as seen flowing through the 132/33kV transformers (the demand being deflated by generation at 11kV and below) along with 18.88MVA of 33kV distributed generation. In the 4

event of LFDD relays being required to operate at 12:00hrs, the net load disconnected as seen at the 132/33kV transformers is 21MVA which is effectively generation rather than demand. Summer with Significant Generation When a typical summer s day is considered the demand and load profile is further distorted as shown in Figure 3. Figure 3: Typical Summer demand and load profile (significant 33kV distributed generation) The level of distributed generation causes reverse power-flow through the 132/33kV transformers for a 10 hour period (between 08:30 & 18:30hrs). Should the LFDD relays be required to operate at 14:30hrs, the load disconnected will consist of 0.5MVA of net generation as seen flowing through the 132/33kV transformers (the demand being deflated by generation at 11kV and below) along with 29.7MVA of 33kV distributed generation. Impact on Operability The above scenarios show when there is an excess of generation over demand an LFDD scheme will disconnect generation rather than demand which will contribute to a further deficit in generation rather than a demand reduction. In summary, whilst LFDD schemes will still function and address shortages in generation, the presence of distributed generation reduces their effectiveness and predictability for the GBSO. The reduction in the effectiveness of LFDD schemes may impact on the DNO by disconnecting a higher number of customers to achieve the required disconnection of demand. Short Term Mitigation and Solutions A short term solution is to assess on a seasonal basis the likelihood of 132/33kV substations being net exporters of generation rather than importers of demand and impacting on the effectiveness of LFDD schemes. If necessary the selected substations for each selected block of load could be modified to reduce the risk of creating a further deficit of generation.

Long Term Solutions Move LFDD Relays to a Lower Voltage Level A longer term solution could be to connect the LFDD schemes at a lower voltage level closer to the demand (e.g. at 33/11kV substations). This will potentially improve the effectiveness of the LFDD scheme as it will not be disconnecting any 33kV connected generation and reduce amount of any deficit in generation. Figure 4 below shows the current location of LFDD relays on the 33kV transformer circuit breakers at 132/33kV bulk supply points (BSPs) and the proposed re-location of the relays to the 11kV transformer circuit breakers at 33/11kV (Primary) substations. Current Practice Proposed Practice Figure 4: Illustrative example of moving LFDD relays locations Monitor Direction of Power-flow A further refinement to an LFDD scheme could be to automatically monitor the direction of active powerflow and block operation when there is an export of power (when the local distributed generation output exceeds network demand). Bibliography [1] The SQSS Review Panel, National Electricity Transmission System Security and Quality of Supply Standard, Version 2.3, 8th February 2017. [2] National Grid Electricity Transmission plc, The Grid Code, Issue 5, Revision 21, 21 March 2017. 6