Equipment Description Quantity as per drawings Actual quantity

Similar documents
ECP COMPACT AND MICRO SUBSTATION COMMISSIONING PROCEDURE

ECP DISTRIBUTION TRANSFORMER COMMISSIONING PROCEDURE

ECP HV INSULATION TESTING

Section 3. Test Procedures

ECP HV INSULATION TESTING

ET 40 - Electrician Theory Examination Marking Schedule

EI HIGH VOLTAGE INSULATION TESTING POLICY

Reference Number PCP 02 (RIC Standard: EP SP)

FAQ ON EARTHING STANDARDS 16/08/2018

Isolation Fault Troubleshooting - Application Note

Field Instruction. Induced voltages can occur in overhead lines, underground cables, or in switchyards.

EAS Electrical Appliance Serviceperson Answer Schedule

NOTE: This paper relates to a closed book exam & therefore candidates should attempt this exam paper with no study-notes or text books.

Collection of standards in electronic format (PDF) 1. Copyright

Field Instruction Switching Activities. Purpose. Scope. Objective. Safety

IMP/010/011 Code of Practice for Earthing LV Networks and HV Distribution Substations

2394 EXAM PAPER. 1. State THREE circumstances that would require a periodic inspection and test to be carried out on an installation

Best Practice Reducing The Risk of Arc Flash Cross Over

ELECTRICIAN S THEORY EXAMINATION 20 November 2010 QUESTION AND ANSWER BOOKLET

Click to edit Master title style. Click to edit Master title style. Northern Powergrid Asset Recording Guidance

Module Title: Electrical Installation II Laboratory Sheet:

EDS LV SUPPLIES TO MOBILE PHONE BASE STATIONS MOUNTED ON TRANSMISSION TOWERS

SERVICING & METERING SERVICING AND METERING SECTION 5 SEC5:

Industrial and Commercial Power Systems Topic 7 EARTHING

The Variable Threshold Neutral Isolator (VTNI)

Portable Appliance Testers. OmegaPAT MI 2140 BetaPAT MI 2141 User Manual Ver Code No

C&G Level 3 Award in the Periodic Inspection, Testing and Certification of Electrical Installations

ER 87 Electrician Regulations Answer Schedule. Question 1 Marks Reference Marking notes. (1 mark) ESR 27(2) (2 marks) ESR 74A(1AA)

M.I. Cable High Resistance Fault Locator

Earthing, HV Switching and Associated Operational Equipment. Approval: Chief Operating Officer

SUBJECT HEADING: Switching Programmes ISSUE: 18

ECP GROUND-MOUNTED SWITCHGEAR WITH PROTECTION RELAYS COMMISSIONING PROCEDURE

returned to your distributor for attention. 14. Do not operate the function switch while the instrument is connected to a circuit.

G81 PART 1 FRAMEWORK APPENDIX

FINAL - ER 70 Electrician Regulations Answer Schedule. Question 1 Marks Reference Marking notes

ECP HV METERING EQUIPMENT COMMISSIONING PROCEDURE

NPS/002/016 Technical Specification for 33 kv Cable Joints and Terminations

Model UT20B: OPERATING MANUAL Table of Contents (1)

Rutherford Electrical Engineering Services. DPI CONFERENCE Sydney 2008 High Voltage, Data and Communications, Electronics, CCTV

ECP GROUND-MOUNTED SWITCHGEAR COMMISSIONING PROCEDURE

HAWK5000 Operators Manual

SDCS-03 DISTRIBUTION NETWORK GROUNDING CONSTRUCTION STANDARD (PART-I) UNDERGROUND NETWORK GROUNDING. Rev. 01

DMRC ELECTRICAL STANDARDS & DESIGN WING (DESDW)

EDS LV WAVEFORM MAINS CABLE RATINGS

EASQ ELECTRICAL APPLIANCE SERVICEPERSON (QUALIFIED) MARKING SCHEDULE. SECTION 1 Marks Reference Marking notes Qu 1 A 10 MΩ (2 marks)

Company Directive STANDARD TECHNIQUE: SD5F. Relating to connecting multiple small low voltage connections with limited network analysis

2/15/2015. Current will always try to return to its source. In order for there to be current, there must be a complete circuit

Guideline for Creating Disconnection Points and Establishing a Not Electrically Connected Area

Underground Distribution Construction Manual

PHASE ROTATION METER. Operating and Instruction Manual. a n d A C C E S S O R I E S

Les Hampson Cert Ed FSCTE, Chairman CAI Technical Committee

ELECTRICIAN S THEORY EXAMINATION 17 November 2012 QUESTION AND ANSWER BOOKLET

TN, TT & IT Earthing Arrangements

Wisconsin Contractors Institute Continuing Education

INTELLIMETER REGISTER

Multi-Function Installation Tester MEGGER CM500. User Guide MEGGER

MEGGER CM300 MK II, CM400 MK II & CM500

Cable fault location in power cables. Systematics for cable testing, diagnosis and cable fault location

VCE VET INTEGRATED TECHNOLOGIES

Licensed Electricians Practical Assessment (LEP)

Installation Manual DOC R1 Date: 05/27/99. Plug-in Meter Installation Manual

Licensed Electricians Practical Assessment (LEP)

MAVOWATT 4 Multifunction Power Meter

7 o/c4 - To meet the requirements of BS 7671, all fault current protective devices without back-up protection on the supply side must be capable of:

GETTING STARTED GUIDE NI AI, ±60 V, 24 Bit, 1 ks/s/ch Simultaneous

Busbars and lines are important elements

Underground Distribution Construction Manual

Field Measurement of Transmission Cable Dissipation Factor

Testing Manual for Electrical Equipment

BME 3511 Bioelectronics I - Laboratory Exercise #2. Series Resistive Circuits

Company Directive STANDARD TECHNIQUE: TP14C. Distribution Business Provided Metering Facilities

SM6. installation instructions. internal arc 16kA. 1s. addition to the standard cell user s instructions

6. Internal lightning protection

TECHNICAL DESCRIPTION TD-77A/3 170 KV COMPACT GAS INSULATED INTEGRATED SUBSTATION MODULES

Residual Current Operated Circuit-Breakers (RCCBs)

RADIODETECTION Application Note

MINISTRY OF ELECTRICITY

ET 61 - Electrician Theory Examination Marking Schedule

Pathfinder. Instruction Manual for: PF620 Circuit Tracer Kit

CONTINUING EDUC ATION

NEW FIXED WIRING COLOURS. A practical guide

Benefits of SFRA - Case Studies

The frequency inverter continues to carry hazardous voltages for up to 5 minutes after it was switched off.

V P N. Voltage transducer DVM 4200 = 4200 V

Education & Training

Earthing Guidance Notes

CX-A6 Amplifier Installation & User Guide V9.0

ModieLoad. Static capacitive load unit 9.8A 240vac single phase. CAUTION: Ensure only Phase to Neutral connection CAT IV 300V

VCE VET ENGINEERING STUDIES CERTIFICATE II

Model : OPERATING MANUAL Table of Contents (1)

Specialists in HV and MV test and diagnostics. Testing in Substations

ENCORE 300 SERIES INSTALLATION AND OPERATING INSTRUCTIONS

The SENSE and SIGNAL inputs are very high impedance and are unaffected by the (~384ohm) series resistance of the xx61p barriers.

Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017

PREMIER INSTALLATION AND OPERATING INSTRUCTIONS

BVM Systems Limited. PQSensor MkIII Installation & Commissioning Manual - 1 -

SINGLE PHASE BUCK & BOOST TRANSFORMERS INSTRUCTION MANUAL

User instructions for CMS EE HV Distribution Crates [DEG 547] (including the associated control, input and output cards)

POWER TRACE TM TASCO, INC.

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance

Transcription:

NOTE: SAFETY: Tests must be carried out after the installation, alteration or repair and before putting back to service. At all times maintain suitable clearance to all other electrical equipment and verify planned escape routes and fire risks. In preparation for the tests, wherever possible, de-energise and disconnect the LV cables from the equipment and make the area safe. DATE: Project No.: Name of Officer: Location of Equipment: Equipment Description Quantity as per drawings Actual quantity Working ends Uni-pillars Mini-pillars 1. LOCATION OF THE PILLARS (lot number and road name) A: F: B: G: C: H: D: I; E: J: 2. CABLE WITHOUT PILLARS (SINGLE RUN) use column X Size of conductor (mm²) Length of cable (approximately) (m) 3. VISUAL INSTALLATION AND SAFETY CHECKS X 1 Confirm that the cable is de-energised (with approved testing device). 2 Check that the pillars finished ground level is satisfactory. N/A 3 Check that all the cables and pillars are correctly installed and that there is no sign of damage. 4 Check that there are no loose connections or unconnected cables in the pillars. N/A Document Management CS# 2734124 Page 1 of 6

5 6 7 Ensure that the customer connections, streetlights, and unmetered supplies are disconnected. X Check that the phase and neutral conductor arrangement inside the pillars is correct. Check that the neutral screens are all solidly and separately bolted to the neutral bar/block. Check that all the cables are correctly connected in accordance with the design drawings and protected against mechanical damage. 8 Check that the labelling is correct as per the standard. 9 Normally open points (NOP) on Uni-pillars: Cables are identified by labels that show their first points of isolation from that source. Check the labelling to identify the correct circuit in all pillars. Ensure that red reflective labels are placed on the outside of the unipillars. NOP 1 NOP 2 NOP 3 N/A N/A 10 Check that no cables are exposed and backfill if required. 11 Check that the final positions of the top and bottom busbars of the universal pillars are correctly aligned to accept fuses or links. 12 Disconnect the neutral of the cable under test from the MEN and N-E connections. Document Management CS# 2734124 Page 2 of 6

4. CONTINUITY AND PHASING TEST This test verifies the continuity of the circuit. Connect the four-lead resistor box at the beginning of the cable. Example: At the transformer's low voltage connection point, between phases and neutral, carry out the test using a 500 V insulation resistance tester at the pillars. Correct resistance values should be measured between R-N, W-N, and B-N, respectively. A value of more than 10 MΩ should be measured between N-E. Ensure all the MEN link and N-E connections at the uni-pillars, mini-pillars and low voltage connection points are disconnected for this test.) Resistor box values (MΩ) Red phase White phase Blue phase Red phase to neutral MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ White phase to neutral MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ Blue phase to neutral MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ Document Management CS# 2734124 Page 3 of 6

5. INSULATION RESISTANCE TEST (DISCONNECT THE RESISTOR BOX IN PREPARATION FOR INSULATION RESISTANCE TEST) Note: If an NOP is in the circuit, relocate the resistor box. This test is to be carried out using a 1 kv (never use 5 kv insulation testers for this test) between phase to phase, phase to neutral, and neutral to earth for 1 minute. Values greater than 10 MΩ for new cables and 1 MΩ for existing cables are acceptable. Ensure that all persons are clear of the circuit before testing. Red phase to white phase MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ White phase to blue phase MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ Blue phase to red phase MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ Red phase to neutral MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ White phase to neutral MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ Blue phase to neutral MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ 6. SHEATH INTEGRITY TEST: NEUTRAL TO EARTH TEST AT 1 KV This test confirms the integrity of the cable sheath. Damaged or punctured sheaths allow moisture to enter the cable. Use a 1 kv insulation resistance tester for 1 minute with all the neutral connections disconnected within the circuit of the cable being tested. If the sheath integrity is <10 MΩ for new cables or <1 MΩ for existing cables, report unsatisfactory results to the appropriate authorities for further testing or repair; otherwise proceed. X Neutral to earth MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ MΩ 7. REINSTATEMENT OF ALL MEN LINKS AND N EARTH CONNECTORS AND INSULATION RESISTANCE TEST BETWEEN PHASES AND NEUTRAL Confirm cables have been discharged after testing. All connections reinstated as per section 4 above Yes No Note: A final insulation resistance test must be performed between all phases and neutral/earth on all low voltage circuits before energising for the first time. If energisation occurs more than two weeks after this commissioning test, conduct a final insulation resistance test to ensure the cable is safe to energise. Yes Document Management CS# 2734124 Page 4 of 6

8. HANDOVER OF RESPONSIBILITY FOR THE COMPLETION OF SECTIONS 1 TO 7 I hereby certify that sections 1 to 7 have been completed with satisfactory results and transfer responsibility to the commissioning officer. Testing Officer/Cable Jointer/CPM: Pay Number: Signature: Date: DD/MM/YY Time: HH:MM 9. ENERGISATION Ensure that all persons and equipment are clear of the circuit and all pillars and units are secured. Check that the LV fuses are correct (if applicable). Conduct a service connection test on all installations where the service connections have been disturbed. 10. RECORD VOLTAGES AT LV CONNECTION POINTS Phase out at the feeder pillars and LV connection points, because cross-phasing is likely to occur at these points. Phase-to-same-phase tests, acceptable results 0~10 V: Red phase to red phase White phase to white phase Blue phase to blue phase Phase-to-other-phase tests, acceptable results 400~440 V: Red phase to white phase V V V V V V V V V V White phase to blue phase V V V V V V V V V V Blue phase to red phase V V V V V V V V V V Document Management CS# 2734124 Page 5 of 6

Phase-to-neutral tests, acceptable results 225~254 V: Red phase to neutral V V V V V V V V V V White phase to neutral V V V V V V V V V V Blue phase to neutral V V V V V V V V V V Check correct phase-rotation at all LV connection points. 11. OPERATIONAL HANDOVER The commissioning officer must ensure that all checks are completed and the test results comply with the minimum standards. I hereby certify that all sections have been completed with satisfactory results and transfer responsibility to the network operating authority. This equipment is ready to be SAFELY energised. Commissioning Officer: Pay Number: Signature: Date: DD/MM/YY Time: HH:MM 1. Ensure the work area is left tidy with no hazards to the public. 2. Hand over responsibility to the operating authority 3. Return this sheet to the project/working file as a record of commissioning and as a document required for the Handover Certificate. IMPORTANT: PLEASE ATTACH AS-BUILT DRAWINGS AND DATASHEETS TO THIS SHEET AND SEND TO RELEVANT ASSET MANAGER Document Management CS# 2734124 Page 6 of 6