Keystone Pipeline Phases 1 & 2 Acoustic Monitoring Report for Canadian Pump Stations

Size: px
Start display at page:

Download "Keystone Pipeline Phases 1 & 2 Acoustic Monitoring Report for Canadian Pump Stations"

Transcription

1 Revision 0 Keystone Project Document # RE-03 [ ] ATCO Project # TransCanada Pipeline Ltd. Keystone Pipeline Project Keystone Pipeline Phases 1 & 2 Acoustic Monitoring Report for Canadian Pump Stations

2 EXECUTIVE SUMMARY ATCO Structures & Logistics (ATCO) has completed noise monitoring for 23 pump stations of the Keystone Pipeline in Canada currently owned and operated by TransCanada Pipeline Ltd. (TCPL). The Canadian portion of Keystone Pipeline extends from Hardisty, Alberta through Saskatchewan to a point near Haskett, Manitoba before crossing the Canadian border entering the United States. ATCO personnel visited all 23 Canadian pump stations to conduct environmental noise monitoring at the corresponding critical receptor location. The operating condition of the pump stations during the noise monitoring has been obtained from the Keystone Pipeline Control Center. Published meteorological data was collected from the nearby weather stations. The collected sound level data was analyzed and the sound level results were compared with the noise criteria to determine compliance. The noise level limits of each pump station are established from a regulatory perspective utilizing Alberta ERCB Noise Directive 038 in both Alberta and Saskatchewan, and Manitoba s Guideline for Sound Pollution in Manitoba. The noise monitoring indicates that the Canadian pump stations of Keystone Pipeline comply with the noise criteria. The table below summarizes the result of nighttime noise monitoring, which represents the worst case scenario for each pump station as the noise level limit of nighttime period is 10 db lower than that of daytime period. Pump Station Pump Station Measurement Calculated L eq of Max. Noise Level # Name Result L eq, dba Load Operation, dba Limits, dba Compliance PS05 Hardisty Yes PS06 Lakesend Yes PS07 Monitor Yes PS08 Oyen Yes PS09 Bindloss Yes PS10 Liebenthal Yes PS11 Cabri Yes PS12 Stewart Valley Yes PS13 Herbert Yes PS14 Chaplin Yes PS15 Caron 31* 36* 40 Yes PS16 Belle Plaine 33* 36* 40 Yes PS17 Regina Yes PS18 Kendal Yes PS19 Grenfell Yes PS20 Whitewood 35** 38** 40 Yes PS21 Moosomin Yes PS22 Crandall Yes PS23 Rapid City Yes PS24 Wellwood Yes ATCO Project # Page i

3 Pump Station Pump Station Measurement Calculated L eq of Max. Noise Level # Name Result L eq, dba Load Operation, dba Limits, dba Compliance PS25 Portage La Prairie Yes PS26 Carman Yes PS27 Haskett *** Yes * These sound levels are calculated noise impact contribution from the pump station only, as no valid data was identified from the noise monitoring due to significant background noise contamination. ** These sound levels are based on the daytime noise monitoring results as Whitewood pump station was switched into a bypass mode at nighttime. ***The maximum acceptable level at Haskett pump station is reduced from 50 dba to 45 dba as a 5 db penalty is applied due to the presence of a tonal component. ATCO Project # Page ii

4 TABLE OF CONTENTS EXECUTIVE SUMMARY...i 1. INTRODUCTION Background Site Description Noise Criteria NOISE MONITORING PROTOCOL Instrumentation Test Procedure Site Operating Condition Meteorological Condition DATA ANALYSIS AND RESULTS PS05 Hardisty Pump Station PS06 Lakesend Pump Station PS07 Monitor Pump Station PS08 Oyen Pump Station PS09 Bindloss Pump Station PS10 Liebenthal Pump Station PS11 Cabri Pump Station PS12 Stewart Valley Pump Station PS13 Herbert Pump Station PS14 Chaplin Pump Station PS15 Caron Pump Station PS16 Belle Plaine Pump Station PS17 Regina Pump Station PS18 Kendal Pump Station PS19 Grenfell Pump Station PS20 Whitewood Pump Station PS21 Moosomin Pump Station ATCO Project # Page iii

5 3.18 PS22 Crandall Pump Station PS23 Rapid City Pump Station PS24 Wellwood Pump Station PS25 Portage La Prairie Pump Station PS26 Carman Pump Station PS27 Haskett Pump Station CONCLUSIONS DISCLAIMER Appendix A GLOSSARY Appendix B ERCB DIRECTIVE KEY POINTS Appendix C ERCB DIRECTIVE PERMISSIBLE SOUND LEVEL DETERMINATION Appendix D MANITOBA GUIDELINES FOR SOUND POLLUTION KEY POINTS Appendix E NSTRUMENTATION CALIBRATION RECORDS ATCO Project # Page iv

6 1. INTRODUCTION 1.1 Background The Keystone Pipeline transports crude oil through Alberta, Saskatchewan and Manitoba to the United States. The Canadian portion extends from Hardisty, Alberta to Haskett, Manitoba near the Canadian/US border. Figure 1 shows the pipeline route map. Figure 1: Keystone Pipeline Route Map Keystone Pipeline Project has retained ATCO Structures & Logistics (ATCO) to conduct noise monitoring for the 23 pump stations in Canada. 1.2 Site Description There are a total of 23 pump stations in Canada. The surrounding area of each pump station is primarily used for agriculture. Aerial maps are presented in Section 3, together with the noise monitoring results. Table 1 below lists the name and location of each Canadian pump station. ATCO Project # Page 1

7 Pump Station # Table 1: Keystone Pipeline Canadian Pump Stations Pump Station Name Pump Station GPS Coordinates County / MD / RM / Special Areas PS05 Hardisty Flagstaff PS06 Lakesend Provost PS07 Monitor Special Area #4 PS08 Oyen Special Area #3 PS09 Bindloss Special Area #2 PS10 Liebenthal Happyland PS11 Cabri Miry Creek PS12 Stewart Valley Riverside PS13 Herbert Excelsior PS14 Chaplin Chaplin PS15 Caron Caron PS16 Belle Plaine Pense PS17 Regina Edenwold PS18 Kendal Francis PS19 Grenfell Chester PS20 Whitewood Silverwood PS21 Moosomin Moosomin PS22 Crandall Hamiota PS23 Rapid City Saskatchewan PS24 Wellwood North Cypress PS25 Portage La Prairie Portage La Prairie PS26 Carman R.M. of Dufferin PS27 Haskett R.M. of Stanley Province Alberta Saskatchewan Manitoba A previous noise impact study at the pipeline planning stage identified the most impacted receptor by the pump station noise as critical noise receptor. These critical noise receptors are selected to be the noise monitoring locations, except that of Monitor, Oyen, Bindloss and Carman pump stations. For these four pump stations, the sound measurement equipment was set up at a nearby location, representative of the critical receptor, due to accessibility and security reasons. At Monitor, Oyen and Bindloss pump station, the noise monitoring location was selected for the security of sound measurement equipment. At Carman pump station, the landowner of the critical noise receptor didn t permit ATCO personnel to conduct noise monitoring on the property, therefore a nearby location was selected. The noise monitoring location for each pump station is presented in Table 2. ATCO Project # Page 2

8 Pump Station # Table 2: Critical Receptor Location of Canadian Pump Stations Pump Station Name Acoustic Monitoring Locations GPS Coordinates Distance between Monitoring Location and Pump Station Distance between Critical Receptor Location and Pump Station PS05 Hardisty , ,500 m W 1,500 m W PS06 Lakesend , ,500 m SE 1,500 m SE PS07 Monitor , ,300 m SW 1,500 m SW PS08 Oyen , ,000 m W 1,500 m W PS09 Bindloss , ,250 m NW 1,500 m NW PS10 Liebenthal , m WNW 550 m WNW PS11 Cabri , ,500 m N 1,500 m N PS12 Stewart Valley , ,400 m NW 1,400 m NW PS13 Herbert , m SW 600 m SW PS14 Chaplin , m S 1050 m S PS15 Caron , m NW 1000 n NW PS16 Belle Plaine , m NE 1300 m NE PS17 Regina , m W 1800 m W PS18 Kendal , m NNW 850 m NNW PS19 Grenfell , m SE 1350 m SE PS20 Whitewood , m S 300 m S PS21 Moosomin , m SW 600 m SW PS22 Crandall , m SE 670 m SE PS23 Rapid City , m N 920 m N PS24 Wellwood , m S 610 m S PS25 Portage La Prairie , m N 310 m N PS26 Carman , ,300 m SSE 1,000 m SSE PS27 Haskett , m SE 350 m SE 1.3 Noise Criteria The noise level limits of each pump station are established from a regulatory perspective utilizing Alberta ERCB Noise Directive 038 in both Alberta and Saskatchewan, and Manitoba s Guideline for Sound Pollution in Manitoba. Environmental noise from energy industry facilities in Alberta is regulated by the ERCB, as described in Directive 038 (2007). Currently Saskatchewan does not have regulations that govern noise levels associated with industrial activities. Keystone Project applied Alberta Directive 038 to the pump stations in Saskatchewan in the pipeline planning stage; the noise monitoring will follow such practice. ATCO Project # Page 3

9 Directive 038 has adopted the A weighted energy equivalent sound levels (L eq ) as the sound pressure level criterion for a receptor location. The PSLs of the noise receptors in Alberta and Saskatchewan are derived from information on the receptor location regarding the area population density, proximity to heavily traveled transportation routes including motor vehicle routes, rail lines and aircraft flyways and other specified adjustments. Directive 038 includes a low frequency noise (LFN) analysis. A low frequency noise complaint condition may exist when: the isolated (i.e., nonfacility noise, such as wind noise, has been removed) timeweighted average dbc dba value for the measured day or night time period is equal to or greater than 20 db, and a clear tonal component exists at a frequency below 250 Hz. Key points of the Directive are listed in Appendix B. A typical PSL determination matrix is presented in Appendix C, showing the adjustments and calculation of the PSL at residences nearby a pump station. In Manitoba, Guidelines for Sound Pollution published by the Manitoba Department of Environment outlines separate noise level limits for residential areas, commercial areas and industrial areas. The maximum acceptable sound levels for a residential area are 60 dba and 50 dba during daytime (07:00 to 22:00) and nighttime (22:00 to 07:00) hours respectively. The maximum acceptable levels are to be reduced by 5 dba if the sound source under assessment contains predominant discrete tones or impulsive character. Definitions of tonal and impulsive character are provided in the guideline. Key points of the guideline are listed in Appendix D. The noise level limit for the critical receptor of each Canadian pump station is presented in Table 3 below. ATCO Project # Page 4

10 Pump Station # Table 3: Noise Level Limits of Canadian Pump Stations Pump Station Name Province Critical Receptor Noise Level Limit Location Daytime Nighttime PS 05 Hardisty AB 1,500 m W PS 06 Lakesend AB 1,500 m SE PS 07 Monitor AB 1,500 m SW PS 08 Oyen AB 1,500 m W PS 09 Bindloss AB 1,500 m NW PS 10 Liebenthal SK 550 m WNW PS 11 Cabri SK 1,500 m N PS 12 Stewart Valley SK 1,400 m NW PS 13 Herbert SK 600 m SW PS 14 Chaplin SK 1050 m S PS 15 Caron SK 1000 n NW PS 16 Belle Plaine SK 1300 m NE PS 17 Regina SK 1800 m W PS 18 Kendal SK 850 m NNW PS 19 Grenfell SK 1350 m SE PS 20 Whitewood SK 300 m S PS 21 Moosomin SK 600 m SW PS 22 Crandall MB 670 m SE PS 23 Rapid City MB 920 m N PS 24 Wellwood MB 610 m S PS 25 Portage La Prairie MB 310 m N PS 26 Carman MB 1,000 m SSE PS 27 Haskett MB 350 m SE 60 45* *The maximum acceptable level at Haskett pump station is reduced from 50 dba to 45 dba as a 5 db penalty is applied due to the presence of a tonal component. ATCO Project # Page 5

11 2. NOISE MONITORING PROTOCOL 2.1 Instrumentation The noise monitoring was conducted utilizing six Type 1 sound level meters, Bruel & Kjaer Type 2250 or Table 4 presents the instrumentation setup. Table 4: Sound Level Meter Instrumentation Setup Instrumentation Sound Level Meter Bruel & Kjaer 2250/2270 Bandwidth 1/3 Octave Range db Broad band Slow, A weighted & C weighted Spectral measurement Slow, Linear SLM Serial Number Microphone Serial Number Calibration Level 94.0 db The sound level meters logged continuously in one minute intervals. The one minute interval was chosen in order to isolate sound contamination by individual noise events, such as airplane flyover and traffic noise. The sound level meter was set to slow response, and spectral L eq levels in one third octave bands were measured and recorded. L n statistical exceedance levels were also recorded. Digital audio recording was conducted throughout the whole noise monitoring period. The measurements were made with the sound level meter set on both the A weighting and C weighting scales. The A weighting scale simulates the response of the human ear to environmental sounds whereas the C weighting scale is more sensitive to sounds at low frequencies than the A weighted sound level, and is sometimes used to assess the lowfrequency content of complex sound environments. The sound level meters have current laboratory certification. These current laboratory certificates are presented in Appendix E. 2.2 Test Procedure Measurements were taken in accordance with Alberta ERCB Directive 038 and American National Standards Institute (ANSI) standard ANSI S12.9 R 1993, Quantities and Procedures for Description and Measurement of Environmental Sound. ATCO Project # Page 6

12 The sound level meter was set up 15 m from the nearest or most impacted dwelling unit in the direction of the pump station and 15 m away from any reflective façade. The microphone was placed at a height between 1.5 m and 2 m above ground. An outdoor type windscreen was placed on the microphone during monitoring in order to reduce the effects of windinduced noise. The sound level meter was field calibrated immediately before and after the measurement series and after any change in equipment conditions such as a battery replacement. Sound levels were measured during daytime and nighttime periods with the pump stations in a representative load condition. 2.3 Site Operating Condition Each Canadian pump station includes one to five motor/pump units. The number of units installed at each station is presented in Table 5. Table 5: Number of Units in Each Pump Station Pump Station # Pump Station Name Total Number of Units Installed Power Rating of Each Unit, hp PS05 Hardisty 6 (including one spare unit) 5000 PS06 Lakesend PS07 Monitor PS08 Oyen PS09 Bindloss PS10 Liebenthal PS11 Cabri PS12 Stewart Valley PS13 Herbert PS14 Chaplin PS15 Caron PS16 Belle Plaine PS17 Regina PS18 Kendal PS19 Grenfell PS20 Whitewood PS21 Moosomin PS22 Crandall PS23 Rapid City PS24 Wellwood PS25 Portage La Prairie PS26 Carman PS27 Haskett ATCO Project # Page 7

13 The designed nominal oil flow is 591 kbpd (3,915 m 3 /hr). During the noise monitoring period, the actual oil flow was between 2,400 m 3 /hr and 3,500 m 3 /hr. At these pump stations, there was usually one to three pumps in operation to achieve this flow rate. The detailed load log of each pump station is presented together with the sound level results in Section Meteorological Condition The published meteorological data was collected throughout the survey from the weather station in the nearest town/city where such data is available. Temperature, wind speed, wind direction, and relative humidity are presented in Section 3. Sound level measurements taken during periods of unfavorable weather conditions were excluded during data analysis. According to the ANSI Standards, no sound level measurement should be made when the average wind velocity exceeds 5 m/s (18 km/hr). ATCO Project # Page 8

14 3. DATA ANALYSIS AND RESULTS At each Canadian pump station, at least one long term noise measurement was conducted at the critical noise receptor location. Each set of long term noise monitoring data is divided into daytime periods (7:00 am to 10:00 pm) and nighttime periods (10:00 pm to 7:00 am) to account for the different noise level limits for the two periods in the applicable noise criteria. The obviously contaminated sound data was excluded based on digital audio recording and published weather data. The main noise measurement contamination factors include: 1) exceedance of maximum wind speed; 2) precipitation; 3) natural sounds, typically at dawn or dusk, such as birdsongs, dog barks, frog sound etc.; 4) abnormal noise events, including aircraft flyovers and vehicular traffic. After the data exclusion, valid data was compared with the applicable noise criteria to determine noise compliance. Most of the pump stations were monitored during their partial load operation. When the pump station is in partial load operating condition, not all the available motor/pump units are operating, however each motor/pump unit in operation is running at full speed. Corrections have been applied to take into account the total number of pumps to predict the maximum noise level at the critical receptor location. The estimated noise level of maximum load operation is calculated with one of the following approaches: 1) if the valid data indicates the pump station was the dominant noise source, a correction was added to take into account the difference between maximum number of pumps and the number of pumps monitored; 2) if the sound data indicates there was continuous dominant background noise contamination and was only pronounced at certain frequency bands where the pump station s contribution is minor, e.g. high frequency noise contamination by birdsongs, these bands were adjusted to portray a more typical spectrum. Then a correction is added to take into account the difference between maximum number of pumps and the number of pumps monitored; 3) if the sound data indicates there was continuous dominant background noise contamination across the octave band spectrum, e.g. highway traffic noise or noise from other industrial facilities, the contributing noise level from the pump station at the critical receptor location is projected by noise propagation calculation. The sound power level of the pump station is calculated from site spot measurements; then an acoustic model is built to calculate the noise impact from the pump station only. A correction is then added to take into account the difference between maximum number of pumps and the number of pumps monitored. The results of the noise monitoring are presented below for each individual pump station. ATCO Project # Page 9

15 3.1 PS05 Hardisty Pump Station An aerial map in Figure 2 shows the pump station location, the acoustic monitoring location, the critical receptor location and other area features. N Keystone Hardisty Pump Station M & R 1 km M Measurement Location; R Critical Receptor Location. Figure 2: Aerial Map PS05 Hardisty Pump Station The recorded data of the equivalent sound level (L eq ) of each 1 minute logging period at the monitoring location of the Hardisty pump station from 8:37 p.m. April 27 to 2:53 p.m. April 28, 2011 is presented in Figure 3. The obviously contaminated data by natural sounds, tree noise, local traffic noise, aircraft flyover, intrusive highway noise or human activities nearby the sound level meter have been excluded. Also excluded is data in the periods when the pump station was turned off or the weather condition was unfavorable. The published weather data and the pump station load log are shown in Table 6 and Table 7. ATCO Project # Page 10

16 Excluded Period Daytime Period Nighttime Period db :00:00 PM 12:00:00 AM 02:00:00 AM 04:00:00 AM 06:00:00 AM 08:00:00 AM 10:00:00 AM 12:00:00 PM 02:00:00 PM LAeq Figure 3: Time History Logged Sound Data PS05 Hardisty Pump Station Table 6: Published Weather Data PS05 Hardisty Pump Station Date Temperature, Relative Wind Speed, Condition (MM/DD/YY MDT) C Humidity, % km/h Wind Direction :00 Cloudy WSW :00 Cloudy WSW :00 Cloudy WSW :00 Showers NNW :00 Showers NE :00 Cloudy WSW :00 Cloudy WSW :00 Cloudy SW :00 Cloudy WSW :00 Cloudy SSW :00 Cloudy SW :00 Cloudy SW :00 Clear WSW :00 Clear W :00 Clear WNW :00 Clear WNW :00 Clear NW :00 Cloudy SSW :00 Cloudy NNE :00 Cloudy WNW ATCO Project # Page 11

17 Table 7: Facility Load Log PS05 Hardisty Pump Station Date Actual Oil (MM/DD/YY MDT) Flow (m 3 /h) Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Unit : On Off On Off Off Off : On Off On Off Off Off : On Off On Off Off Off : On Off On Off Off Off : On Off On Off Off Off : On Off On Off Off Off : On Off On Off Off Off : On Off On Off Off Off : On Off On Off Off Off : On Off On Off Off Off : On Off On Off Off Off : Off Off On Off Off Off : Off Off On Off Off Off : Off Off On Off Off Off : Off Off On Off Off Off : Off Off On Off Off Off : Off Off On Off Off Off : Off Off On Off Off Off : Off Off On Off Off Off : Off Off On Off Off Off One of the six units is a spare unit. There was 4 hours and 49 minutes of valid data during the nighttime period after isolation analysis. No valid data was recorded during the daytime monitoring period due to steady highway traffic. The detailed data analysis results are shown in Table 8. The dbc dba value is only 13 db, and thus a LFN issue, as defined by Section of Directive 038, was not present. Therefore no tonal analysis was performed. Table 8: Noise Monitoring Result PS05 Hardisty Pump Station Period L eq, dba L eq, dbc dbc dba Tonal Component Frequency, Hz LFN Penalty, db Noise Level plus LFN Penalty, dba Apr. 27/28, 2011 Daytime N.A. 0 Apr , 2011 Nighttime N.A The measurement result, the estimated noise level of maximum load operation and the determination of compliance are presented in Table 9. ATCO Project # Page 12

18 Table 9: Noise Monitoring Result PS05 Hardisty Pump Station Period Measurement Result Calculated L eq of Max. Load Noise Level L eq (2 Units), dba Operation (5 Units), dba Limits, dba Compliance Apr. 27/28, 2011 Daytime 50 Apr , 2011 Nighttime Yes The results indicate that the Hardisty pump station is in compliance with the PSL set by Alberta ERCB Noise Directive. ATCO Project # Page 13

19 3.2 PS06 Lakesend Pump Station An aerial map in Figure 4 shows the pump station location, the acoustic monitoring location, the critical receptor location and other area features. N Keystone Lakesend Pump Station 1 km M & R M Measurement Location; R Critical Receptor Location. Figure 4: Aerial Map PS06 Lakesend Pump Station The recorded data of the equivalent sound level (L eq ) of each 1 minute logging period at the monitoring location of the Lakesend pump station from 9:54 p.m. April 27 to 10:45 a.m. April 28, 2011 is presented in Figure 5. The obviously contaminated data by natural sounds, tree noise, local traffic noise, aircraft flyover, intrusive highway noise or human activities nearby the sound level meter have been excluded. Also excluded is data in the periods when the pump station was turned off or the weather condition was unfavorable. The published weather data and the pump station load log are shown in Table 10 and Table 11. ATCO Project # Page 14

20 Excluded Period Daytime Period Nighttime Period db :00:00 PM 12:00:00 AM 02:00:00 AM 04:00:00 AM 06:00:00 AM 08:00:00 AM 10:00:00 AM LAeq Figure 5: Time History Logged Sound Data PS06 Lakesend Pump Station Table 10: Published Weather Data PS06 Lakesend Pump Station Date Temperature, Relative Wind Speed, Condition (MM/DD/YY MDT) C Humidity, % km/h Wind Direction :00 Cloudy WSW :00 Cloudy WSW :00 Showers NNW :00 Showers NE :00 Cloudy WSW :00 Cloudy WSW :00 Cloudy SW :00 Cloudy WSW :00 Cloudy SSW :00 Cloudy SW :00 Cloudy SW :00 Clear WSW :00 Clear W :00 Clear WNW ATCO Project # Page 15

21 Table 11: Facility Load Log PS06 Lakesend Pump Station Date Actual Oil (MM/DD/YY MDT) Flow (m 3 /h) Unit 1 Unit 2 Unit 3 Unit 4 Unit : Off On Off Off Off : Off On Off Off Off : Off On Off Off Off : Off On Off Off Off : Off On Off Off Off : Off On Off Off Off : Off On Off Off Off : Off On Off Off Off : Off On Off Off Off : Off On Off Off Off : Off On Off Off Off : Off On Off Off Off : Off On Off Off Off : Off On Off Off Off There was 3 hours and 5 minutes valid data during the daytime monitoring period and 8 hours and 6 minutes during the nighttime period after isolation analysis. The detailed data analysis results are shown in Table 12. The highest dbc dba value is only 14 db, and thus a LFN issue, as defined by Section of Directive 038, was not present. Therefore no tonal analysis was performed. Table 12: Noise Monitoring Result PS06 Lakesend Pump Station Period L eq, dba L eq, dbc dbc dba Tonal Component Frequency, Hz LFN Penalty, db Noise Level plus LFN Penalty, dba Apr. 27/28, 2011 Daytime N.A Apr , 2011 Nighttime N.A The measurement result, the estimated noise level of maximum load operation and the determination of compliance are presented in Table 13. Table 13: Noise Monitoring Result PS06 Lakesend Pump Station Period Measurement Result Calculated L eq of Max. Load Noise Level L eq (1 Unit), dba Operation (5 Units), dba Limits, dba Compliance Apr. 27/28, 2011 Daytime Yes Apr , 2011 Nighttime Yes The results indicate that the Lakesend pump station is in compliance with the PSL set by Alberta ERCB Noise Directive. ATCO Project # Page 16

22 3.3 PS07 Monitor Pump Station An aerial map in Figure 6 shows the pump station location, the acoustic monitoring location, the critical receptor location and other area features. N Keystone Monitor Pump Station M R 1 km M Measurement Location; R Critical Receptor Location. Figure 6: Aerial Map PS07 Monitor Pump Station The recorded data of the equivalent sound level (L eq ) of each 1 minute logging period at the monitoring location of the Monitor pump station from 7:04 p.m. May 6 to 11:30 a.m. May 7, 2011 is presented in Figure 7. The obviously contaminated data by natural sounds, tree noise, local traffic noise, aircraft flyover, intrusive highway noise or human activities nearby the sound level meter have been excluded. Also excluded is data in the periods when the pump station was turned off or the weather condition was unfavorable. The published weather data and the pump station load log are shown in Table 14 and Table 15. ATCO Project # Page 17

23 Excluded Period Daytime Period Nighttime Period db :00:00 PM 10:00:00 PM 12:00:00 AM 02:00:00 AM 04:00:00 AM 06:00:00 AM 08:00:00 AM 10:00:00 AM LAeq Figure 7: Time History Logged Sound Data PS07 Monitor Pump Station Table 14: Published Weather Data PS07 Monitor Pump Station Date Temperature, Relative Wind Speed, Condition (MM/DD/YY MDT) C Humidity, % km/h Wind Direction 05/06/11 19:00 Clear NNW 05/06/11 20:00 Clear NNW 05/06/11 21:00 Clear NNW 05/06/11 22:00 Clear ENE 05/06/11 23:00 Clear ESE 05/06/11 00:00 Clear SSE 05/07/11 01:00 Clear ESE 05/07/11 02:00 Clear ESE 05/07/11 03:00 Clear SSE 05/07/11 04:00 Clear SE 05/07/11 05:00 Clear ENE 05/07/11 06:00 Cloudy WNW 05/07/11 07:00 Cloudy NNE 05/07/11 08:00 Cloudy NE 05/07/11 09:00 Cloudy NE 05/07/11 10:00 Cloudy ENE 05/07/11 11:00 Cloudy NE ATCO Project # Page 18

24 Table 15: Facility Load Log PS07 Monitor Pump Station Date Actual Oil (MM/DD/YY MDT) Flow (m 3 /h) Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 05/06/11 19:00 0 Off Off Off Off Off 05/06/11 20: On Off Off On Off 05/06/11 21: On Off On On Off 05/06/11 22: On Off On On Off 05/06/11 23: Off Off On On Off 05/06/11 00: Off Off On Off Off 05/07/11 01: Off Off On On Off 05/07/11 02: Off Off On On Off 05/07/11 03: Off Off On On Off 05/07/11 04: Off Off On On Off 05/07/11 05: Off Off On On Off 05/07/11 06:00 0 Off Off Off Off Off 05/07/11 07:00 0 Off Off Off Off Off 05/07/11 08:00 0 Off Off Off Off Off 05/07/11 09:00 0 Off Off Off Off Off 05/07/11 10:00 0 Off Off Off Off Off 05/07/11 11:00 0 Off Off Off Off Off There was 1 hours and 58 minutes valid data during the daytime monitoring period and 6 hours and 53 minutes during the nighttime period after isolation analysis. The detailed data analysis results are shown in Table 16. The highest dbc dba value is only 16 db, and thus a LFN issue, as defined by Section of Directive 038, was not present. Therefore no tonal analysis was performed. Table 16: Noise Monitoring Result PS07 Monitor Pump Station Period L eq, dba L eq, dbc dbc dba Tonal Component Frequency, Hz LFN Penalty, db Noise Level plus LFN Penalty, dba May 6/7, 2011 Daytime N.A May 6 7, 2011 Nighttime N.A The measurement result, the estimated noise level of maximum load operation and the determination of compliance are presented in Table 17. Table 17: Noise Monitoring Result PS07 Monitor Pump Station Period Measurement Result Calculated L eq of Max. Load Noise Level L eq (2 Units), dba Operation (5 Units), dba Limits, dba Compliance May 6/7, 2011 Daytime Yes May 6 7, 2011 Nighttime Yes The results indicate that the Monitor pump station is in compliance with the PSL set by Alberta ERCB Noise Directive. ATCO Project # Page 19

25 3.4 PS08 Oyen Pump Station An aerial map in Figure 8 shows the pump station location, the acoustic monitoring location, the critical receptor location and other area features. N Keystone Oyen Pump Station R M 1 km M Measurement Location; R Critical Receptor Location. Figure 8: Aerial Map PS08 Oyen Pump Station The recorded data of the equivalent sound level (L eq ) of each 1 minute logging period at the monitoring location of the Oyen pump station from 2:35 p.m. May 17 to 10:14 a.m. May 18, 2010 is presented in Figure 9. The obviously contaminated data by natural sounds, tree noise, local traffic noise, aircraft flyover, intrusive highway noise or human activities nearby the sound level meter have been excluded. Also excluded is data in the periods when the pump station was turned off or the weather condition was unfavorable. The published weather data and the pump station load log are shown in Table 18 and Table 19. ATCO Project # Page 20

26 Excluded Period Daytime Period Nighttime Period db :00:00 PM 08:00:00 PM 12:00:00 AM 04:00:00 AM 08:00:00 AM LAeq C AM AM LA 48 3 db LAS 58 6 db LAS db Figure 9: Time History Logged Sound Data PS08 Oyen Pump Station Table 18: Published Weather Data PS08 Oyen Pump Station Date Temperature, Relative Wind Speed, Condition (MM/DD/YY MDT) C Humidity, % km/h Wind Direction 05/17/11 14:00 N/A S 05/17/11 15:00 N/A S 05/17/11 16:00 N/A SSE 05/17/11 17:00 N/A SSE 05/17/11 18:00 N/A SSE 05/17/11 19:00 N/A SSW 05/17/11 20:00 N/A SSE 05/17/11 21:00 N/A SSW 05/17/11 22:00 N/A SSE 05/17/11 23:00 N/A ESE 05/18/11 00:00 N/A SE 05/18/11 01:00 N/A SE 05/18/11 02:00 N/A SE 05/18/11 03:00 N/A SE 05/18/11 04:00 N/A SSE 05/18/11 05:00 N/A SSE 05/18/11 06:00 N/A SSE 05/18/11 07:00 N/A SSE 05/18/11 08:00 N/A SSE 05/18/11 09:00 N/A SE 05/18/11 10:00 N/A SSE ATCO Project # Page 21

27 Table 19: Facility Load Log PS08 Oyen Pump Station Date Actual Oil (MM/DD/YY MDT) Flow (m 3 /h) Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 05/17/11 14: On Off Off Off Off 05/17/11 15: On Off Off Off Off 05/17/11 16: On Off Off Off Off 05/17/11 17: On Off Off Off Off 05/17/11 18: On Off Off Off Off 05/17/11 19: On Off Off Off Off 05/17/11 20: On On Off Off Off 05/17/11 21: On On On Off Off 05/17/11 22: On On On Off Off 05/17/11 23: On On On Off Off 05/18/11 00: On On On Off Off 05/18/11 01: On On On Off Off 05/18/11 02: On On On Off Off 05/18/11 03:00 0 Off Off Off Off Off 05/18/11 04:00 0 Off Off Off Off Off 05/18/11 05: On On Off Off Off 05/18/11 06: On On Off Off Off 05/18/11 07: On On Off Off Off 05/18/11 08: On On Off Off Off 05/18/11 09: On On Off Off Off 05/18/11 10: On On Off Off Off There was 1 hours and 57 minutes valid data during the daytime monitoring period and 3 hours and 19 minutes during the nighttime period after isolation analysis. Nighttime data at the measurement location 1 km from the pump station was heavily contaminated by frogs which were constant and dominant in the 2.5 khz and 3.15 khz 1/3 octave bands, which is illustrated in Figure 10 below. The results with contamination are presented in Table 20. Table 20: Noise Monitoring Result PS08 Oyen Pump Station (Measurement Location at 1 km Measured Results) Period L eq, dba L eq, dbc dbc dba Tonal Component Frequency, Hz LFN Penalty, db Noise Level plus LFN Penalty, dba May 17/18, 2011 Daytime N.A May 17 18, 2011 Nighttime N.A ATCO Project # Page 22

28 60 50 Sound Pressure Level (db) Frequency (Hz) Figure 10: Averaged Nighttime 1/3 Octave Band Spectrum after Isolation (with Contamination) PS08 Oyen Pump Station These two bands were adjusted to portray a more typical spectrum without any contamination. The 1/3 octave band spectrum and results are shown in Figure 11 and Table 21 below. Table 21: Noise Monitoring Result PS08 Oyen Pump Station (Measurement Location at 1 km Adjusted Levels) Period L eq, dba L eq, dbc dbc dba Tonal Component Frequency, Hz LFN Penalty, db Noise Level plus LFN Penalty, dba PSL, dba May 18, 2011 Daytime N.A May 17 18, 2011 Nighttime N.A ATCO Project # Page 23

29 Sound Pressure Level (db) Frequency (Hz) Figure 11: Adjusted Averaged Nighttime 1/3 Octave Band Spectrum after Isolation (without Contamination) PS08 Oyen Pump Station As the critical noise boundary for the facility is 1.5 km from the pump station, further calculations were performed to predict what the levels will be at 1.5 km based on the measured results. The final data analysis results are shown in Table 22. The highest dbc dba value is only 19 db, and thus a LFN issue, as defined by Section of Directive 038, was not present. Therefore no tonal analysis was performed. Table 22: Noise Monitoring Result PS08 Oyen Pump Station Period L eq, dba L eq, dbc dbc dba Tonal Component Frequency, Hz LFN Penalty, db Noise Level plus LFN Penalty, dba May 17/18, 2011 Daytime N.A May 17 18, 2011 Nighttime N.A The measurement result, the estimated noise level of maximum load operation and the determination of compliance are presented in Table 23. ATCO Project # Page 24

30 Table 23: Noise Monitoring Result PS08 Oyen Pump Station Measurement Result Calculated L Period eq of Max. Load Noise Level Compliance L eq (2 Units), dba Operation (5 Units), dba Limits, dba May 17/18, 2011 Daytime Yes Measurement Result Calculated L Period eq of Max. Load Noise Level Compliance L eq (3 Units), dba Operation (5 Units), dba Limits, dba May 17 18, 2011 Nighttime Yes The results indicate that the Oyen pump station is in compliance with the PSL set by Alberta ERCB Noise Directive. ATCO Project # Page 25

31 3.5 PS09 Bindloss Pump Station An aerial map in Figure 12 shows the pump station location, the acoustic monitoring location, the critical receptor location and other area features. N R M Keystone Bindloss Pump Station 1 km M Measurement Location; R Critical Receptor Location. Figure 12: Aerial Map PS09 Bindloss Pump Station The recorded data of the equivalent sound level (L eq ) of each 1 minute logging period at the monitoring location of the Bindloss pump station from 5:22 p.m. May 5 to 3:01 p.m. May 6, 2010 is presented in Figure 13. The obviously contaminated data by natural sounds, tree noise, local traffic noise, aircraft flyover, intrusive highway noise or human activities nearby the sound level meter have been excluded. Also excluded is data in the periods when the pump station was turned off or the weather condition was unfavorable. The published weather data and the pump station load log are shown in Table 24 and Table 25. ATCO Project # Page 26

32 Excluded Period Daytime Period Nighttime Period db :00:00 PM 10:00:00 PM 02:00:00 AM 06:00:00 AM 10:00:00 AM 02:00:00 PM LAeq Figure 13: Time History Logged Sound Data PS09 Bindloss Pump Station ATCO Project # Page 27

33 Table 24: Published Weather Data PS09 Bindloss Pump Station Date Temperature, Relative Wind Speed, Condition (MM/DD/YY MDT) C Humidity, % km/h Wind Direction 05/05/11 17:00 Mostly Clear WSW 05/05/11 18:00 Mostly Clear NW 05/05/11 19:00 Mostly Clear NNW 05/05/11 20:00 Mostly Clear NNE 05/05/11 21:00 Mostly Clear NNE 05/05/11 22:00 Mostly Clear NNW 05/05/11 23:00 Mostly Clear NNW 05/06/11 00:00 Mostly Clear N 05/06/11 01:00 Mostly Clear NNW 05/06/11 02:00 Mostly Clear NW 05/06/11 03:00 Mostly Clear NW 05/06/11 04:00 Mostly Clear NW 05/06/11 05:00 Mostly Clear NW 05/06/11 06:00 Mostly Clear NNW 05/06/11 07:00 Mostly Clear NW 05/06/11 08:00 Mostly Clear NNW 05/06/11 09:00 Mostly Clear NW 05/06/11 10:00 Mostly Clear NNW 05/06/11 11:00 Mostly Clear NNW 05/06/11 12:00 Mostly Clear NNW 05/06/11 13:00 Mostly Clear NNW 05/06/11 14:00 Mostly Clear NNW 05/06/11 15:00 Mostly Clear NNW ATCO Project # Page 28

34 Table 25: Facility Load Log PS09 Bindloss Pump Station Date Actual Oil (MM/DD/YY MDT) Flow (m 3 /h) Unit 1 Unit 2 Unit 3 Unit 4 05/05/11 17: On Off Off On 05/05/11 18: On Off Off On 05/05/11 19: On Off Off On 05/05/11 20: On Off Off On 05/05/11 21: On Off Off On 05/05/11 22: On On Off On 05/05/11 23: On On Off On 05/06/11 00: On On Off On 05/06/11 01: On On Off On 05/06/11 02: On On Off On 05/06/11 03: On On Off On 05/06/11 04: On On Off On 05/06/11 05: On On Off On 05/06/11 06: On On Off On 05/06/11 07: On On Off On 05/06/11 08: On On Off On 05/06/11 09: On On Off On 05/06/11 10: On On Off On 05/06/11 11: On Off Off On 05/06/11 12: On Off Off On 05/06/11 13: On Off Off On 05/06/11 14: On Off Off On 05/06/11 15: On Off Off On There was 1 hours and 57 minutes valid data during the daytime monitoring period and 4 hours and 27 minutes during the nighttime period after isolation analysis. The detailed data analysis results are shown in Table 26. The highest dbc dba value is only 19 db, and thus a LFN issue, as defined by Section of Directive 038, was not present. Therefore no tonal analysis was performed. Table 26: Noise Monitoring Result PS09 Bindloss Pump Station Period L eq, dba L eq, dbc dbc dba Tonal Component Frequency, Hz LFN Penalty, db Noise Level plus LFN Penalty, dba May 5/6, 2011 Daytime N.A May 5 6, 2011 Nighttime N.A The measurement result, the estimated noise level of maximum load operation and the determination of compliance are presented in Table 27. ATCO Project # Page 29

35 Table 27: Noise Monitoring Result PS09 Bindloss Pump Station Measurement Result Calculated L Period eq of Max. Load Noise Level Compliance L eq (2 Units), dba Operation (4 Units), dba Limits, dba May 5/6, 2011 Daytime Yes Measurement Result Calculated L Period eq of Max. Load Noise Level Compliance L eq (3 Units), dba Operation (4 Units), dba Limits, dba May 5 6, 2011 Nighttime Yes The results indicate that the Bindloss pump station is in compliance with the PSL set by Alberta ERCB Noise Directive. ATCO Project # Page 30

36 3.6 PS10 Liebenthal Pump Station An aerial map in Figure 14 shows the pump station location, the acoustic monitoring location, the critical receptor location and other area features. N M & R Keystone Liebenthal Pump Station 1 km M Measurement Location; R Critical Receptor Location. Figure 14: Aerial Map PS10 Liebenthal Pump Station The recorded data of the equivalent sound level (L eq ) of each 1 minute logging period at the monitoring location of the Liebenthal pump station from 3:20 p.m. May 5 to 11:06 a.m. May 6, 2011 is presented in Figure 15. The obviously contaminated data by natural sounds, tree noise, local traffic noise, aircraft flyover, intrusive highway noise or human activities nearby the sound level meter have been excluded. Also excluded is data in the periods when the pump station was turned off or the weather condition was unfavorable. The published weather data and the pump station load log are shown in Table 28 and Table 29. ATCO Project # Page 31

37 Excluded Period Daytime Period Nighttime Period db :00:00 PM 08:00:00 PM 12:00:00 AM 04:00:00 AM 08:00:00 AM LAeq Figure 15: Time History Logged Sound Data PS10 Liebenthal Pump Station Table 28: Published Weather Data PS10 Liebenthal Pump Station Date Temperature, Relative Wind Speed, Condition (MM/DD/YY CST) C Humidity, % km/h Wind Direction 05/05/11 15:00 Cloudy SW 05/05/11 16:00 Cloudy SSW 05/05/11 17:00 Cloudy WSW 05/05/11 18:00 Cloudy SW 05/05/11 19:00 Cloudy SW 05/05/11 20:00 Cloudy N 05/05/11 21:00 Cloudy NNW 05/05/11 22:00 Cloudy NW 05/05/11 23:00 Cloudy NNW 05/06/11 00:00 Mostly Cloudy /06/11 01:00 Mostly Cloudy WNW 05/06/11 02:00 Mostly Cloudy WNW 05/06/11 03:00 Mostly Cloudy WNW 05/06/11 04:00 Mostly Cloudy WNW 05/06/11 05:00 Mostly Cloudy NW 05/06/11 06:00 Mostly Cloudy NW 05/06/11 07:00 Fog NW 05/06/11 08:00 Fog NW 05/06/11 09:00 Mostly Cloudy NW 05/06/11 10:00 Mainly Clear NW 05/06/11 11:00 Mainly Clear NNW ATCO Project # Page 32

38 Table 29: Facility Load Log PS10 Liebenthal Pump Station Date Actual Oil (MM/DD/YY CST) Flow (m 3 /h) Unit 1 Unit 2 Unit 3 05/05/11 15: On On Off 05/05/11 16: On On Off 05/05/11 17: On On Off 05/05/11 18: On On Off 05/05/11 19: On On Off 05/05/11 20: On On Off 05/05/11 21: On Off Off 05/05/11 22: On Off Off 05/05/11 23: On Off Off 05/06/11 00: On Off Off 05/06/11 01: On Off Off 05/06/11 02: On Off Off 05/06/11 03: On Off Off 05/06/11 04: On Off Off 05/06/11 05: On Off Off 05/06/11 06: On Off Off 05/06/11 07: On Off Off 05/06/11 08: On Off Off 05/06/11 09: On Off Off 05/06/11 10: On Off Off 05/06/11 11: On Off Off There was 4 hours and 59 minutes valid data during the nighttime period after isolation analysis. No valid data was recorded during the daytime monitoring period due to unfavorable weather conditions. Nighttime data was heavily contaminated by frogs which were constant and dominant in the 2.5 khz and 3.15 khz 1/3 octave bands, which is illustrated in Figure 16 below. The results with contamination are presented in Table 30. Table 30: Noise Monitoring Result PS10 Liebenthal Pump Station (Measured Results) Period L eq, dba L eq, dbc dbc dba Tonal Component Frequency, Hz LFN Penalty, db Noise Level plus LFN Penalty, dba PSL, dba May 5/6, 2011 Daytime N.A May 5 6, 2011 Nighttime N.A ATCO Project # Page 33

39 80 70 Sound Pressure Level (db) Frequency (Hz) Figure 16: Averaged Nighttime 1/3 Octave Band Spectrum after Isolation (with Contamination) PS10 Liebenthal Pump Station These two bands were adjusted to portray a more typical spectrum without any contamination. The 1/3 octave band spectrum and results are shown in Figure 17 and Table 31 below. Table 31: Noise Monitoring Result PS10 Liebenthal Pump Station (Adjusted Levels) Period L eq, dba L eq, dbc dbc dba Tonal Component Frequency, Hz LFN Penalty, db Noise Level plus LFN Penalty, dba PSL, dba May 5/6, 2011 Daytime N.A May 5 6, 2011 Nighttime N.A ATCO Project # Page 34

40 80 70 Sound Pressure Level (db) Frequency (Hz) Figure 17: Adjusted Averaged Nighttime 1/3 Octave Band Spectrum after Isolation (without Contamination) PS10 Liebenthal Pump Station The final data analysis results are shown in Table 32. The highest dbc dba value is only 16 db, and thus a LFN issue, as defined by Section of Directive 038, was not present. Therefore no tonal analysis was performed. Table 32: Noise Monitoring Result PS10 Liebenthal Pump Station Period L eq, dba L eq, dbc dbc dba Tonal Component Frequency, Hz LFN Penalty, db Noise Level plus LFN Penalty, dba May 5/6, 2011 Daytime N.A. 0 May 5 6, 2011 Nighttime N.A The measurement result, the estimated noise level of maximum load operation and the determination of compliance are presented in Table 33. ATCO Project # Page 35

41 Table 33: Noise Monitoring Result PS10 Liebenthal Pump Station Period Measurement Result Calculated L eq of Max. Load Noise Level L eq (1 Unit), dba Operation (3 Units), dba Limits, dba Compliance May 5/6, 2011 Daytime 50 May 5 6, 2011 Nighttime Yes The results indicate that the Liebenthal pump station is in compliance with the PSL set by Alberta ERCB Noise Directive. ATCO Project # Page 36

42 3.7 PS11 Cabri Pump Station An aerial map in Figure 18 shows the pump station location, the acoustic monitoring location, the critical receptor location and other area features. The Cabri pump station is colocated with a TCPL gas compressor facility. During the noise monitoring period, the gas compressor facility was not in operation. Therefore, the sound data collected for the pump station was not contaminated by the gas compressor facility. N M & R Keystone Cabri Pump Station 1 km M Measurement Location; R Critical Receptor Location. Figure 18: Aerial Map PS11 Cabri Pump Station The recorded data of the equivalent sound level (L eq ) of each 1 minute logging period at the monitoring location of the Cabri pump station from 5:47 p.m. May 4 to 1:11 p.m. May 5, 2011 is presented in Figure 19. The obviously contaminated data by natural sounds, tree noise, local traffic noise, aircraft flyover, intrusive highway noise or human activities nearby the sound level meter have been excluded. Also excluded is data in the periods when the Pump station was turned off or the weather condition was unfavorable. The published weather data and the Pump station load log are shown in Table 34 and Table 35. ATCO Project # Page 37

43 Excluded Period Daytime Period Nighttime Period db :00:00 PM 10:00:00 PM 02:00:00 AM 06:00:00 AM 10:00:00 AM LAeq Figure 19: Time History Logged Sound Data PS11 Cabri Pump Station Table 34: Published Weather Data PS11 Cabri Pump Station Date Temperature, Relative Wind Speed, Condition (MM/DD/YY CST) C Humidity, % km/h Wind Direction 05/04/11 17:00 N/A NW 05/04/11 18:00 N/A NW 05/04/11 19:00 N/A WNW 05/04/11 20:00 N/A WNW 05/04/11 21:00 N/A WSW 05/04/11 22:00 N/A WSW 05/04/11 23:00 N/A SW 05/05/11 00:00 N/A SW 05/05/11 01:00 N/A SW 05/05/11 02:00 N/A SW 05/05/11 03:00 N/A SW 05/05/11 04:00 N/A SW 05/05/11 05:00 N/A SW 05/05/11 06:00 N/A SW 05/05/11 07:00 N/A SW 05/05/11 08:00 N/A SW 05/05/11 09:00 N/A WSW 05/05/11 10:00 N/A SW 05/05/11 11:00 N/A SW 05/05/1112:00 N/A SW 05/05/11 13:00 N/A SW ATCO Project # Page 38

44 Table 35: Facility Load Log PS11 Cabri Pump Station Date Actual Oil (MM/DD/YY CST) Flow (m 3 /h) Unit 1 Unit 2 Unit 3 05/04/11 17: Off On Off 05/04/11 18: Off On Off 05/04/11 19: Off On Off 05/04/11 20: On Off Off 05/04/11 21: On Off Off 05/04/11 22: On Off Off 05/04/11 23: On Off Off 05/05/11 00: On Off Off 05/05/11 01: On Off Off 05/05/11 02: On Off Off 05/05/11 03: On Off Off 05/05/11 04: On Off Off 05/05/11 05: On Off Off 05/05/11 06: On Off Off 05/05/11 07: On Off Off 05/05/11 08: On Off Off 05/05/11 09: On Off Off 05/05/11 10: On Off Off 05/05/11 11: On Off Off 05/05/11 12: On Off Off 05/05/11 13: On Off Off There was 4 hours and 8 minutes of valid data during the nighttime period after isolation analysis. No valid data was recorded during the daytime monitoring period due to unfavorable weather conditions. The detailed data analysis results are shown in Table 36. The highest dbc dba value is only 16 db, and thus a LFN issue, as defined by Section of Directive 038, was not present. Therefore no tonal analysis was performed. Table 36: Noise Monitoring Result PS11 Cabri Pump Station Period L eq, dba L eq, dbc dbc dba Tonal Component Frequency, Hz LFN Penalty, db Noise Level plus LFN Penalty, dba May 4/5, 2011 Daytime N.A. 0 May 4 5, 2011 Nighttime N.A The measurement result, the estimated noise level of maximum load operation and the determination of compliance are presented in Table 37. ATCO Project # Page 39

45 Table 37: Noise Monitoring Result PS11 Cabri Pump Station Period Measurement Result Calculated L eq of Max. Load Noise Level L eq (1 Unit), dba Operation (3 Units), dba Limits, dba Compliance May 4/5, 2011 Daytime 50 May 4 5, 2011 Nighttime Yes The results indicate that the Cabri Pump station is in compliance with the PSL set by Alberta ERCB Noise Directive. ATCO Project # Page 40

46 3.8 PS12 Stewart Valley Pump Station An aerial map in Figure 20 shows the pump station location, the acoustic monitoring location, the critical receptor location and other area features. N M & R Keystone Stewart Valley Pump Station 1 km M Measurement Location; R Critical Receptor Location. Figure 20: Aerial Map PS12 Stewart Valley Pump Station The recorded data of the equivalent sound level (L eq ) of each 1 minute logging period at the monitoring location of the Stewart Valley pump station from 7:06 p.m. May 4 to 9:37 a.m. May 5, 2010 is presented in Figure 21. The obviously contaminated data by natural sounds, tree noise, local traffic noise, aircraft flyover, intrusive highway noise or human activities nearby the sound level meter have been excluded. Also excluded is data in the periods when the pump station was turned off or the weather condition was unfavorable. The published weather data and the pump station load log are shown in Table 38 and Table 39. ATCO Project # Page 41

47 Excluded Period Daytime Period Nighttime Period db :00:00 PM 10:00:00 PM 12:00:00 AM 02:00:00 AM 04:00:00 AM 06:00:00 AM 08:00:00 AM LAeq C PM PM LA 42 1 db LAS 49 4 db LAS db Figure 21: Time History Logged Sound Data PS12 Stewart Valley Pump Station Table 38: Published Weather Data PS12 Stewart Valley Pump Station Date Temperature, Relative Wind Speed, Condition (MM/DD/YY CST) C Humidity, % km/h Wind Direction 05/04/11 19:00 N/A WNW 05/04/11 20:00 N/A WNW 05/04/11 21:00 N/A WSW 05/04/11 22:00 N/A WSW 05/04/11 23:00 N/A SW 05/05/11 00:00 N/A SW 05/05/11 01:00 N/A SW 05/05/11 02:00 N/A SW 05/05/11 03:00 N/A SW 05/05/11 04:00 N/A SW 05/05/11 05:00 N/A SW 05/05/11 06:00 N/A SW 05/05/11 07:00 N/A SW 05/05/11 08:00 N/A SW 05/05/11 09:00 N/A WSW ATCO Project # Page 42

48 Table 39: Facility Load Log PS12 Stewart Valley Pump Station Date Actual Oil (MM/DD/YY CST) Flow (m 3 /h) Unit 1 Unit 2 05/04/11 19: On On 05/04/11 20: On Off 05/04/11 21: On Off 05/04/11 22: On On 05/04/11 23: On On 05/05/11 00: On On 05/05/11 01: On On 05/05/11 02: On On 05/05/11 03: On On 05/05/11 04: On On 05/05/11 05: On On 05/05/11 06: On On 05/05/11 07: On On 05/05/11 08: On On 05/05/11 09: On On There was 3 hours and 19 minutes valid data during the nighttime period and no valid data during the daytime monitoring period after isolation analysis. The detailed data analysis results are shown in Table 40. The highest dbc dba value is only 14 db, and thus a LFN issue, as defined by Section of Directive 038, was not present. Therefore no tonal analysis was performed. Table 40: Noise Monitoring Result PS12 Stewart Valley Pump Station Period L eq, dba L eq, dbc dbc dba Tonal Component Frequency, Hz LFN Penalty, db Noise Level plus LFN Penalty, dba May 4/5, 2011 Daytime N.A. 0 May 4 5, 2011 Nighttime N.A The measurement result, the estimated noise level of maximum load operation and the determination of compliance are presented in Table 41. Table 41: Noise Monitoring Result PS12 Stewart Valley Pump Station Period Measurement Result L eq of Max. Load Operation Noise Level L eq (2 Units), dba (2 Units), dba Limits, dba Compliance May 4/5, 2011 Daytime 50 May 4 5, 2011 Nighttime Yes The results indicate that the Stewart Valley pump station is in compliance with the PSL set by Alberta ERCB Noise Directive. ATCO Project # Page 43

49 3.9 PS13 Herbert Pump Station An aerial map in Figure 22 shows the pump station location, the acoustic monitoring location, the critical receptor location and other area features. The Herbert pump station is co located with a TCPL gas compressor facility. During the noise monitoring period, the gas compressor facility was not in operation. Therefore, the sound data collected for the pump station was not contaminated by the gas compressor facility. N Keystone Herbert Pump Station M & R 1 km M Measurement Location; R Critical Receptor Location. Figure 22: Aerial Map PS13 Herbert Pump Station The recorded data of the equivalent sound level (L eq ) of each 1 minute logging period at the monitoring location of the Herbert pump station from 3:50 pm May 4, 2011 to 1:28 pm May 5, 2011 is presented in Figure 23. The obviously contaminated data by natural sounds, tree noise, local traffic noise, aircraft flyover, intrusive highway noise or human activities nearby the sound level meter have been excluded. Also excluded is data in the periods when the pump station was turned off or the weather condition was unfavorable. The published weather data and the pump station load log are shown in Table 42 and Table 43. ATCO Project # Page 44

50 Excluded Period Daytime Period Nighttime Period db :00:00 PM 10:00:00 PM 02:00:00 AM 06:00:00 AM 10:00:00 AM LAeq Figure 23: Time History Logged Sound Data PS13 Herbert Pump Station ATCO Project # Page 45

51 Table 42: Published Weather Data PS13 Herbert Pump Station Date Temperature, Relative Wind Speed, Condition (MM/DD/YY CST) C Humidity, % km/h Wind Direction 05/04/11 15:00 Mostly Cloudy NW 05/04/11 16:00 Partly Cloudy NNW 05/04/11 17:00 Light Rain NW 05/04/11 18:00 Partly Cloudy NW 05/04/11 19:00 Partly Cloudy NW 05/04/11 20:00 Partly Cloudy WNW 05/04/11 21:00 Partly Cloudy NW 05/04/11 22:00 Partly Cloudy WNW 05/04/11 23:00 Scattered Clouds WNW 05/05/11 00:00 Clear SW 05/05/11 01:00 Clear SW 05/05/11 02:00 Scattered Clouds SW 05/05/11 03:00 Scattered Clouds SW 05/05/11 04:00 Scattered Clouds SW 05/05/11 05:00 Clear SW 05/05/11 06:00 Clear SW 05/05/11 07:00 Clear SW 05/05/11 08:00 Clear SW 05/05/11 09:00 Clear WSW 05/05/11 10:00 Clear SW 05/05/11 11:00 Clear SW 05/05/11 12:00 Partly Cloudy SW 05/05/11 13:00 Partly Cloudy SW ATCO Project # Page 46

52 Table 43: Facility Load Log PS13 Herbert Pump Station Date Actual Oil (MM/DD/YY CST) Flow (m 3 /h) Unit 1 Unit 2 05/04/11 15: Off On 05/04/11 16: Off On 05/04/11 17: Off On 05/04/11 18: Off On 05/04/11 19: Off On 05/04/11 20: On Off 05/04/11 21: On Off 05/04/11 22: On Off 05/04/11 23: On Off 05/05/11 00: On Off 05/05/11 01: On Off 05/05/11 02: On Off 05/05/11 03: On Off 05/05/11 04: On Off 05/05/11 05: On Off 05/05/11 06: On Off 05/05/11 07: On Off 05/05/11 08: On Off 05/05/11 09: On Off 05/05/11 10: On Off 05/05/11 11: Off On 05/05/11 12: Off On 05/05/11 13: Off On There was 1 hr and 32 min valid data during the nighttime period after isolation analysis. No valid data was recorded during the daytime monitoring period due to unfavorable weather conditions and contamination. The detailed data analysis results are shown in Table 44. The highest dbc dba value is only 16 db, and thus a LFN issue, as defined by Section of Directive 038, was not present. Therefore no tonal analysis was performed. Table 44: Noise Monitoring Result PS13 Herbert Pump Station Period L eq, dba L eq, dbc dbc dba Tonal Component Frequency, Hz LFN Penalty, db Noise Level plus LFN Penalty, dba May 4/5, 2011 Daytime N.A. May 4 5, 2011 Nighttime N.A ATCO Project # Page 47

53 The measurement result, the estimated noise level of maximum load operation and the determination of compliance are presented in Table 45. Table 45: Noise Monitoring Result PS13 Herbert Pump Station Period Measurement Result Calculated L eq of Max. Load Noise Level L eq (1 Unit), dba Operation (2 Units), dba Limits, dba Compliance May 4/5, 2011 Daytime 50 May 4 5, 2011 Nighttime Yes The results indicate that the Herbert pump station is in compliance with the PSL set by Alberta ERCB Noise Directive. ATCO Project # Page 48

54 3.10 PS14 Chaplin Pump Station An aerial map in Figure 24 shows the pump station location, the acoustic monitoring location, the critical receptor location and other area features. N Keystone Chaplin Pump Station M & R 1 km M Measurement Location; R Critical Receptor Location. Figure 24: Aerial Map PS14 Chaplin Pump Station The recorded data of the equivalent sound level (L eq ) of each 1 minute logging period at the monitoring location of the Chaplin pump station from 2:00 pm May 4, 2011 to 10:40 am May 5, 2011 is presented in Figure 25. The obviously contaminated data by natural sounds, tree noise, local traffic noise, aircraft flyover, intrusive highway noise or human activities nearby the sound level meter have been excluded. Also excluded is data in the periods when the pump station was turned off or the weather condition was unfavorable. The published weather data and the pump station load log are shown in Table 46 and Table 47. ATCO Project # Page 49

55 Excluded Period Daytime Period Nighttime Period db :00:00 PM 10:00:00 PM 02:00:00 AM 06:00:00 AM 10:00:00 AM LAeq Figure 25: Time History Logged Sound Data PS14 Chaplin Pump Station Table 46: Published Weather Data PS14 Chaplin Pump Station Date Temperature, Relative Wind Speed, Condition (MM/DD/YY CST) C Humidity, % km/h Wind Direction 05/04/11 14:00 Partly Cloudy WNW 05/04/11 15:00 Mostly Cloudy NW 05/04/11 16:00 Partly Cloudy NNW 05/04/11 17:00 Light Rain NW 05/04/11 18:00 Partly Cloudy NW 05/04/11 19:00 Partly Cloudy NW 05/04/11 20:00 Partly Cloudy WNW 05/04/11 21:00 Partly Cloudy NW 05/04/11 22:00 Partly Cloudy WNW 05/04/11 23:00 Scattered Clouds WNW 05/05/11 00:00 Clear SW 05/05/11 01:00 Clear SW 05/05/11 02:00 Scattered Clouds SW 05/05/11 03:00 Scattered Clouds SW 05/05/11 04:00 Scattered Clouds SW 05/05/11 05:00 Clear SW 05/05/11 06:00 Clear SW 05/05/11 07:00 Clear SW 05/05/11 08:00 Clear SW 05/05/11 09:00 Clear WSW 05/05/11 10:00 Clear SW ATCO Project # Page 50

56 Table 47: Facility Load Log PS14 Chaplin Pump Station Date Actual Oil (MM/DD/YY CST) Flow (m 3 /h) Unit 1 Unit 2 05/04/11 14: Off On 05/04/11 15: Off On 05/04/11 16: Off On 05/04/11 17: Off On 05/04/11 18: Off On 05/04/11 19: Off On 05/04/11 20: On On 05/04/11 21: On On 05/04/11 22: On On 05/04/11 23: On On 05/05/11 00: On On 05/05/11 01: On On 05/05/11 02: On On 05/05/11 03: On On 05/05/11 04: On On 05/05/11 05: On On 05/05/11 06: On On 05/05/11 07: On On 05/05/11 08: On On 05/05/11 09: On On 05/05/11 10: On On There was 32 min daytime valid data and 4 hr and 27 min nighttime valid data after isolation analysis. The detailed data analysis results are shown Table 48. The highest dbc dba value is only 16 db, and thus a LFN issue, as defined by Section of Directive 038, was not present. Therefore no tonal analysis was performed. Table 48: Noise Monitoring Result PS14 Chaplin Pump Station Period L eq, dba L eq, dbc dbc dba Tonal Component Frequency, Hz LFN Penalty, db Noise Level plus LFN Penalty, dba May 4/5, 2011 Daytime N.A May 4 5, 2011 Nighttime N.A The measurement result, the estimated noise level of maximum load operation and the determination of compliance are presented in Table 49. ATCO Project # Page 51

57 Table 49: Noise Monitoring Result PS14 Chaplin Pump Station Period Measurement Result L eq of Max. Load Operation Noise Level L eq (2 Units), dba (2 Units), dba Limits, dba Compliance May 4/5, 2011 Daytime Yes May 4 5, 2011 Nighttime Yes The results indicate that the Chaplin pump station is in compliance with the PSL set by Alberta ERCB Noise Directive. ATCO Project # Page 52

58 3.11 PS15 Caron Pump Station An aerial map in Figure 26 shows the pump station location, the acoustic monitoring location, the critical receptor location and other area features. The Caron pump station is colocated with a TCPL gas compressor facility. During the noise monitoring period, the gas compressor facility was not in operation. Therefore, the sound data collected for the pump station was not contaminated by the gas compressor facility. M & R Keystone Caron Pump Station 1 km M Measurement Location; R Critical Receptor Location. Figure 26: Aerial Map PS15 Caron Pump Station The recorded data of the equivalent sound level (L eq ) of each 1 minute logging period at the monitoring location of the Caron pump station from 12:00 pm May 5, 2011 to 12:50 pm May 6, 2011 is presented in Figure 27. The published weather data and the pump station load log are shown in Table 50 and Table 51. ATCO Project # Page 53

59 Excluded Period Daytime Period Nighttime Period db :00:00 PM 06:00:00 PM 10:00:00 PM 02:00:00 AM 06:00:00 AM 10:00:00 AM LAeq Figure 27: Time History Logged Sound Data PS15 Caron Pump Station ATCO Project # Page 54

60 Date (MM/DD/YY CST) Table 50: Published Weather Data PS15 Caron Pump Station Condition Temperature, C Relative Humidity, % Wind Speed, km/h Wind Direction 05/05/11 12:00 Overcast WSW 05/05/11 13:00 Mostly Cloudy SW 05/05/11 14:00 Mostly Cloudy SW 05/05/11 15:00 Mostly Cloudy SW 05/05/11 16:00 Overcast SW 05/05/11 17:00 Overcast SW 05/05/11 18:00 Overcast SW 05/05/11 19:00 Mostly Cloudy SW 05/05/11 20:00 Mostly Cloudy SSW 05/05/11 21:00 Mostly Cloudy SSE 05/05/11 22:00 Mostly Cloudy S 05/05/11 23:00 Mostly Cloudy SSW 05/06/11 00:00 Mostly Cloudy SSW 05/06/11 01:00 Mostly Cloudy SW 05/06/11 02:00 Mostly Cloudy SW 05/06/11 03:00 Mostly Cloudy W 05/06/11 04:00 Mostly Cloudy WNW 05/06/11 05:00 Mostly Cloudy WNW 05/06/11 06:00 Mostly Cloudy WNW 05/06/11 07:00 Mostly Cloudy WNW 05/06/11 08:00 Mostly Cloudy WNW 05/06/11 09:00 Mostly Cloudy NW 05/06/11 10:00 Mostly Cloudy WNW 05/06/11 11:00 Mostly Cloudy NW 05/06/11 12:00 Mostly Cloudy NW ATCO Project # Page 55

61 Table 51: Facility Load Log PS15 Caron Pump Station Date Actual Oil (MM/DD/YY CST) Flow (m 3 /h) Unit 1 Unit 2 Unit 3 05/05/11 12: Off On Off 05/05/11 13: Off On Off 05/05/11 14: Off On Off 05/05/11 15: Off On Off 05/05/11 16: Off On Off 05/05/11 17: Off On Off 05/05/11 18: Off On Off 05/05/11 19: Off On Off 05/05/11 20: Off On Off 05/05/11 21: Off On Off 05/05/11 22: Off On Off 05/05/11 23: Off On Off 05/06/11 00: Off On Off 05/06/11 01: Off On Off 05/06/11 02: Off On Off 05/06/11 03: Off On Off 05/06/11 04: Off On Off 05/06/11 05: Off On Off 05/06/11 06: Off On Off 05/06/11 07: Off On Off 05/06/11 08: Off On Off 05/06/11 09: Off On Off 05/06/11 10: Off On Off 05/06/11 11: Off On Off 05/06/11 12: Off On Off All the collected sound data was heavily contaminated by continuous traffic noise from TransCanada Highway, natural sounds and gusts. Therefore no valid data was identified. ATCO personnel conducted another long term monitoring at the pump station fence line. However, due to the same heavy contamination, no valid data was found. The noise impact from the Caron pump station at the critical noise receptor can therefore only be determined by noise propagation calculation. Several spot measurements were taken around the pump station. The total sound power level of the pump station was calculated based on these sound data. Then the noise impact from the Caron pump station is projected by an acoustic model, which is presented in Table 52. ATCO Project # Page 56

62 Table 52: Estimated Noise Impact from PS15 Caron Pump Station Period Estimated L eq of 1 Unit Operation (Survey Condition), dba Estimated L eq of 1 Unit Operation (Survey Condition), dbc dbc dba (1 Unit) Estimated Max L eq of 3 Units in Operation, dba Estimated Max L eq of 3 Units in Operation, dbc dbc dba (3 Units) PSL, dba Compliance Daytime Yes Nighttime Yes The results indicate that the Caron pump station is in compliance with the noise limit levels set by the Alberta ERCB Noise Directive. ATCO Project # Page 57

63 3.12 PS16 Belle Plaine Pump Station An aerial map in Figure 28 shows the pump station location, the acoustic monitoring location, the critical receptor location and other area features. N M & R Keystone Belle Plaine Pump Station Potash Facility 1 km M Measurement Location; R Critical Receptor Location. Figure 28: Aerial Map PS16 Belle Plaine Pump Station The recorded data of the equivalent sound level (L eq ) of each 1 minute logging period at the monitoring location of the Belle Plaine pump station from 8:50 pm May 19, 2011 to 3:55 pm May 20, 2011 is presented in Figure 29. The published weather data and the pump station load log are shown in Table 53 and Table 54. ATCO Project # Page 58

64 Excluded Period Daytime Period Nighttime Period db :00:00 PM 02:00:00 AM 06:00:00 AM 10:00:00 AM 02:00:00 PM LAeq Figure 29: Time History Logged Sound Data PS16 Belle Plaine Pump Station Date (MM/DD/YY CST) Table 53: Published Weather Data PS16 Belle Plaine Pump Station Condition Temperature, C Relative Humidity, % Wind Speed, km/h Wind Direction 05/19/11 21:00 Mostly Cloudy ENE 05/19/11 22:00 Mostly Cloudy ENE 05/19/11 23:00 Mostly Cloudy ENE 05/20/11 00:00 Mostly Cloudy E 5/20/ :00 Mostly Cloudy NNE 5/20/ :00 Mostly Cloudy NNW 5/20/ :00 Mostly Cloudy NW 5/20/ :00 Overcast E 5/20/ :00 Overcast E 5/20/ :00 Overcast ESE 5/20/ :00 Overcast ENE 5/20/ :00 Overcast ESE 5/20/ :00 Mostly Cloudy NE 5/20/ :00 Mostly Cloudy NE 5/20/ :00 Mostly Cloudy ENE 5/20/ :00 Mostly Cloudy ENE 5/20/ :00 Mostly Cloudy NE 5/20/ :00 Mostly Cloudy ENE 5/20/ :00 Mostly Cloudy NE ATCO Project # Page 59

65 Table 54: Facility Load Log PS16 Belle Plaine Pump Station Date Actual Oil (MM/DD/YY CST) Flow (m 3 /h) Unit 1 Unit 2 05/19/11 21: On Off 05/19/11 22: On Off 05/19/11 23: On Off 05/20/11 00: On Off 05/20/11 01: On Off 05/20/11 02: On Off 05/20/11 03: On Off 05/20/11 04: On Off 05/20/11 05: On Off 05/20/11 06: On Off 05/20/11 07: On Off 05/20/11 08: On Off 05/20/11 09: On Off 05/20/11 10: On Off 05/20/11 11: On Off 05/20/11 12: On On 05/20/11 13: On On 05/20/11 14: On On 05/20/11 15: On On All the collected sound data was heavily contaminated by the continuous noise from the nearby Potash facility and natural sounds. Therefore no valid data was identified. The noise impact from the Belle Plaine pump station at the critical noise receptor can therefore only be determined by noise propagation calculation. Several spot measurements were taken around the pump station. The total sound power level of the pump station was calculated based on these sound data. Then the noise impact from the Belle Plaine pump station is projected by an acoustic model, which is presented in Table 55. Table 55: Estimated Noise Impact from PS16 Belle Plaine Pump Station Period Estimated L eq of 1 Unit Operation (Survey Condition), dba Estimated L eq of 1 Unit Operation (Survey Condition), dbc dbc dba (1 Unit) Estimated Max L eq of 2 Units in Operation, dba Estimated Max L eq of 2 Units in Operation, dbc dbc dba (2 Units) PSL, dba Compliance Daytime Yes Nighttime Yes The results indicate that the Belle Plaine pump station is in compliance with the noise limit levels set by the Alberta ERCB Noise Directive. ATCO Project # Page 60

66 3.13 PS17 Regina Pump Station An aerial map in Figure 30 shows the pump station location, the acoustic monitoring location, the critical receptor location and other area features. The Regina pump station is co located with a TCPL gas compressor facility. During the noise monitoring period, the gas compressor facility was not in operation. Therefore, the sound data collected for the pump station was not contaminated by the gas compressor facility. N M & R Keystone Regina Pump Station 1 km M Measurement Location; R Critical Receptor Location. Figure 30: Aerial Map PS17 Regina Pump Station The recorded data of the equivalent sound level (L eq ) of each 1 minute logging period at the monitoring location of the Regina pump station from 10:43 pm May 20, 2011 to 9:35 am May 21, 2011 Figure 31. The obviously contaminated data by natural sounds, tree noise, local traffic noise, aircraft flyover, intrusive highway noise or human activities nearby the sound level meter have been excluded. Also excluded is data in the periods when the pump station was turned off or the weather condition was unfavorable. The published weather data and the pump station load log are shown in Table 56 and Table 57. ATCO Project # Page 61

67 Excluded Period Daytime Period Nighttime Period db :00:00 AM 02:00:00 AM 04:00:00 AM 06:00:00 AM 08:00:00 AM LAeq Date (MM/DD/YY CST) Figure 31: Time History Logged Sound Data PS17 Regina Pump Station Table 56: Published Weather Data PS17 Regina Pump Station Condition Temperature, C Relative Humidity, % Wind Speed, km/h Wind Direction 05/20/11 22:00 Overcast 14 N/A 13 E 05/20/11 23:00 Overcast ESE 05/21/11 00:00 Light Rain Showers E 05/21/11 01:00 Light Rain Showers NNE 05/21/11 02:00 Light Rain Showers NNE 05/21/11 03:00 Light Rain Showers NNE 05/21/11 04:00 Overcast NNE 05/21/11 05:00 Overcast NE 05/21/11 06:00 Overcast NE 05/21/11 07:00 Light Rain NNE 05/21/11 08:00 Light Rain Showers NE 05/05/11 09:00 Light Rain Showers NE 05/20/11 22:00 Overcast 14 N/A 13 E ATCO Project # Page 62

68 Table 57: Facility Load Log PS17 Regina Pump Station Date Actual Oil (MM/DD/YY CST) Flow (m 3 /h) Unit 1 Unit 2 Unit 3 05/20/11 22: On Off Off 05/20/11 23: On On Off 05/21/11 00: On On Off 05/21/11 01: On On Off 05/21/11 02: On On Off 05/21/11 03: On On Off 05/21/11 04: On On Off 05/21/11 05: On Off Off 05/21/11 06: On On Off 05/21/11 07: On On Off 05/21/11 08: On Off Off 05/21/11 09: On Off Off There was 3 hr 57 min nighttime valid data after isolation analysis. The results are presented in Table 58. Table 58: Noise Monitoring Result PS17 Regina Pump Station (Measured Results) Period L eq, dba L eq, dbc dbc dba Tonal Component Frequency, Hz LFN Penalty, db Noise Level plus LFN Penalty, dba PSL, dba May 21, 2011 Daytime N.A. 50 May 20 21, 2011 Nighttime N.A However, the valid data still contains continuous contamination from frogs and birdsongs in the background. Such contamination is dominant at 2,500 Hz and 3,150 Hz bands. Contamination exclusion was performed at these two bands, as shown Figure 32 below. ATCO Project # Page 63

69 Figure 32: Averaged Nighttime 1/3 Octave Band Spectra before and after Exclusion PS17 Regina Pump Station The results after removing the contamination at 2,500 Hz and 3,150 Hz bands are presented in Table 59. The dbc dba value is only 15 db, and thus a LFN issue, as defined by Section of Directive 038, was not present. Therefore no tonal analysis was performed. Table 59: Noise Monitoring Result PS17 Regina Pump Station (Adjusted Levels) Period L eq, dba L eq, dbc dbc dba Tonal Component Frequency, Hz LFN Penalty, db Noise Level plus LFN Penalty, dba May 21, 2011 Daytime N.A. May 20 21, 2011 Nighttime N.A The adjusted sound levels, the estimated noise level of maximum load operation and the determination of compliance are presented in Table 60. Table 60: Noise Monitoring Result PS17 Regina Pump Station Period Measurement Result Calculated L eq of Max. Load Noise Level L eq (2 Units), dba Operation (3 Units), dba Limits, dba Compliance May 21, 2011 Daytime 50 May 20 21, 2011 Nighttime Yes The results indicate that the Regina pump station is in compliance with the PSL set by Alberta ERCB Noise Directive. ATCO Project # Page 64

70 3.14 PS18 Kendal Pump Station An aerial map in Figure 33 shows the pump station location, the acoustic monitoring location, the critical receptor location and other area features. N M & R Keystone Kendal Pump Station 1 km M Measurement Location; R Critical Receptor Location. Figure 33: Aerial Map PS18 Kendal Pump Station The recorded data of the equivalent sound level (L eq ) of each 1 minute logging period at the monitoring location of the Kendal pump station from 5:00 pm May 17, 2011 to 9:00 am May 18, 2011 is presented in Figure 34. The obviously contaminated data by natural sounds, tree noise, local traffic noise, aircraft flyover, intrusive highway noise or human activities nearby the sound level meter have been excluded. Also excluded is data in the periods when the pump station was turned off or the weather condition was unfavorable. The published weather data and the pump station load log are shown in Table 61 and Table 62. ATCO Project # Page 65

71 Excluded Period Daytime Period Nighttime Period db :00:00 PM 08:00:00 PM 10:00:00 PM 12:00:00 AM 02:00:00 AM 04:00:00 AM 06:00:00 AM 08:00:00 AM LAeq Figure 34: Time History Logged Sound Data PS18 Kendal Pump Station Date (MM/DD/YY CST) Table 61: Published Weather Data PS18 Kendal Pump Station Condition Temperature, C Relative Humidity, % Wind Speed, km/h Wind Direction 5/17/ :00 Clear SE 5/17/ :00 Clear SE 5/17/ :00 Clear SE 5/17/ :00 Clear SE 5/17/ :00 5/17/ :00 Clear SE 5/17/ :00 Clear E 5/18/ :00 Clear SE 5/18/ :00 Clear SE 5/18/ :00 Clear E 5/18/ :00 Clear E 5/18/ :00 5/18/ :00 Clear SE 5/18/ :00 5/18/ :00 Clear NE 5/18/ :00 Clear E ATCO Project # Page 66

72 Table 62: Facility Load Log PS18 Kendal Pump Station Date Actual Oil (MM/DD/YY CST) Flow (m 3 /h) Unit 1 Unit 2 Unit 3 05/17/11 17: On On Off 05/17/11 18: On On Off 05/17/11 19: On On Off 05/17/11 20: On On Off 05/17/11 21: On On Off 05/17/11 22: On On Off 05/17/11 23: On On Off 05/18/11 00: On On Off 05/18/11 01: On On Off 05/18/11 02: On On Off 05/18/11 03: On On Off 05/18/11 04: On On Off 05/18/11 05: On On Off 05/18/11 06: On On Off 05/18/11 07: On On Off 05/18/11 08: On On Off There was 3 hr 08 min daytime valid data and 5 hr and 14 min nighttime valid data after isolation analysis. The detailed data analysis results are shown in Table 63. The highest dbc dba value is only 14 db, and thus a LFN issue, as defined by Section of Directive 038, was not present. Therefore no tonal analysis was performed. Table 63: Noise Monitoring Result PS18 Kendal Pump Station Period L eq, dba L eq, dbc dbc dba Tonal Component Frequency, Hz LFN Penalty, db Noise Level plus LFN Penalty, dba May 17/18, 2011 Daytime N.A May 17 18, 2011 Nighttime N.A The measurement result, the estimated noise level of maximum load operation and the determination of compliance are presented in Table 64. Table 64: Noise Monitoring Result PS18 Kendal Pump Station Period Measurement Result Calculated L eq of Max. Load Noise Level L eq (2 Units), dba Operation (3 Units), dba Limits, dba Compliance May 17/18, 2011 Daytime Yes May 17 18, 2011 Nighttime Yes The results indicate that the Kendal pump station is in compliance with the PSL set by Alberta ERCB Noise Directive. ATCO Project # Page 67

73 3.15 PS19 Grenfell Pump Station An aerial map in Figure 35 shows the pump station location, the acoustic monitoring location, the critical receptor location and other area features. The Grenfell pump station is co located with a TCPL gas compressor facility. During the noise monitoring period, one gas compressor unit enclosed by an acoustic building was in operation; however it was inaudible in the compressor station. Therefore, the sound data collected for the pump station was not contaminated by the gas compressor facility. N Keystone Grenfell Pump Station 1 km M & R M Measurement Location; R Critical Receptor Location. Figure 35: Aerial Map PS19 Grenfell Pump Station The recorded data of the equivalent sound level (L eq ) of each 1 minute logging period at the monitoring location of the Grenfell pump station from 2:00 pm May 18, 2011 to 11:50 am May 19, 2011 is presented in Figure 36. The obviously contaminated data by natural sounds, tree noise, local traffic noise, aircraft flyover, intrusive highway noise or human activities nearby the sound level meter have been excluded. Also excluded is data in the periods when the pump station was turned off or the weather condition was unfavorable. The published weather data and the pump station load log are shown in Table 65 and Table 66. ATCO Project # Page 68

74 Excluded Period Daytime Period Nighttime Period db LAeq 06:00:00 PM 10:00:00 PM 02:00:00 AM 06:00:00 AM 10:00:00 AM Figure 36: Time History Logged Sound Data PS19 Grenfell Pump Station ATCO Project # Page 69

75 Date (MM/DD/YY CST) Table 65: Published Weather Data PS19 Grenfell Pump Station Condition Temperature, C Relative Humidity, % Wind Speed, km/h Wind Direction 5/18/ :00 Mainly Clear SE 5/18/ :00 Mainly Clear SE 5/18/ :00 Mainly Clear SE 5/18/ :00 Mainly Clear SE 5/18/ :00 Mostly Cloudy ESE 5/18/ :00 Mostly Cloudy ESE 5/18/ :00 Mostly Cloudy ESE 5/18/ :00 Mainly Clear E 5/18/ :00 Mostly Cloudy ESE 5/18/ :00 Mostly Cloudy ESE 5/19/ :00 Mostly Cloudy ESE 5/19/ :00 Mostly Cloudy ESE 5/19/ :00 Mostly Cloudy E 5/19/ :00 Mostly Cloudy E 5/19/ :00 Mostly Cloudy E 5/19/ :00 Mostly Cloudy NNE 5/19/ :00 Mostly Cloudy E 5/19/ :00 Mostly Cloudy ESE 5/19/ :00 Mostly Cloudy ESE 5/19/ :00 Mostly Cloudy SE 5/19/ :00 Mostly Cloudy ESE 5/19/ :00 Mostly Cloudy E ATCO Project # Page 70

76 Table 66: Facility Load Log PS19 Grenfell Pump Station Date Actual Oil (MM/DD/YY CST) Flow (m 3 /h) Unit 1 Unit 2 05/18/11 14: Off On 05/18/11 15: Off On 05/18/11 16: Off On 05/18/11 17: Off On 05/18/11 18:00 0 Off Off 05/18/11 19:00 0 Off Off 05/18/11 20: Off Off 05/18/11 21: On Off 05/18/11 22: On Off 05/18/11 23: On Off 05/19/11 00: On Off 05/19/11 01: On Off 05/19/11 02: On Off 05/19/11 03: On Off 05/19/11 04: On Off 05/19/11 05: On Off 05/19/11 06: On Off 05/19/11 07: On Off 05/19/11 08: On Off 05/19/11 09:00 0 Off Off 05/19/11 10:00 0 Off Off 05/19/11 11:00 0 Off Off There was 58 min daytime valid data and 5 hr and 44 min nighttime valid data after isolation analysis. The detailed data analysis results are shown in Table 67. The highest dbc dba value is only 17 db, and thus a LFN issue, as defined by Section of Directive 038, was not present. Therefore no tonal analysis was performed. Table 67: Noise Monitoring Result PS19 Grenfell Pump Station Period L eq, dba L eq, dbc dbc dba Tonal Component Frequency, Hz LFN Penalty, db Noise Level plus LFN Penalty, dba May 18/19, 2011 Daytime N.A May 18 19, 2011 Nighttime N.A The measurement result, the estimated noise level of maximum load operation and the determination of compliance are presented in Table 68. ATCO Project # Page 71

77 Table 68: Noise Monitoring Result PS19 Grenfell Pump Station Period Measurement Result L eq of Max. Load Operation Noise Level L eq (1 Unit), dba (2 Units), dba Limits, dba Compliance May 18/19, 2011 Daytime Yes May 18 19, 2011 Nighttime Yes The results indicate that the Grenfell pump station is in compliance with the PSL set by Alberta ERCB Noise Directive. ATCO Project # Page 72

78 3.16 PS20 Whitewood Pump Station An aerial map in Figure 37 shows the pump station location, the acoustic monitoring location, the critical receptor location and other area features. N Keystone Whitewood Pump Station M & R 1 km M Measurement Location; R Critical Receptor Location. Figure 37: Aerial Map PS20 Whitewood Pump Station The recorded data of the equivalent sound level (L eq ) of each 1 minute logging period at the monitoring location of the Whitewood pump station from 1:30 pm May 19, 2011 to 11:00 am May 20, 2011 is presented in Figure 38. The obviously contaminated data by natural sounds, tree noise, local traffic noise, aircraft flyover, intrusive highway noise or human activities nearby the sound level meter have been excluded. Also excluded is data in the periods when the pump station was turned off or the weather condition was unfavorable. The published weather data and the pump station load log are shown in Table 69 and Table 70. ATCO Project # Page 73

79 Excluded Period Daytime Period Nighttime Period db :00:00 PM 06:00:00 PM 10:00:00 PM 02:00:00 AM 06:00:00 AM 10:00:00 AM LAeq Figure 38: Time History Logged Sound Data PS20 Whitewood Pump Station ATCO Project # Page 74

80 Date (MM/DD/YY CST) Table 69: Published Weather Data PS20 Whitewood Pump Station Condition Temperature, C Relative Humidity, % Wind Speed, km/h Wind Direction 05/19/11 13:00 N/A N/A N/A N/A N/A 05/19/11 14:00 N/A N/A N/A N/A N/A 05/19/11 15:00 Clear ESE 05/19/11 16:00 Partly Cloudy ESE 05/19/11 17:00 Clear E 05/19/11 18:00 Clear ESE 05/19/11 19:00 Clear E 05/19/11 20:00 Clear E 05/19/11 21:00 Clear ENE 05/19/11 22:00 Clear E 05/19/11 23:00 Clear E 05/20/11 00:00 Clear ENE 05/20/11 01:00 Clear ENE 05/20/11 02:00 Partly Cloudy ENE 05/20/11 03:00 Clear ENE 05/20/11 04:00 Clear NE 05/20/11 05:00 Partly Cloudy NE 05/20/11 06:00 Clear ENE 05/20/11 07:00 Clear ENE 05/20/11 08:00 Clear ENE 05/20/11 09:00 Clear ENE 05/20/11 10:00 Clear ENE ATCO Project # Page 75

81 Table 70: Facility Load Log PS20 Whitewood Pump Station Date Actual Oil (MM/DD/YY CST) Flow (m 3 /h) Unit 1 Unit 2 05/19/11 13:00 0 Off Off 05/19/11 14:00 0 Off Off 05/19/11 15:00 0 Off Off 05/19/11 16: On Off 05/19/11 17: On Off 05/19/11 18: On Off 05/19/11 19: On Off 05/19/11 20: On Off 05/19/11 21: On Off 05/19/11 22: On Off 05/19/11 23: On Off 05/20/11 00: Off Off 05/20/11 01: Off Off 05/20/11 02: Off Off 05/20/11 03: Off Off 05/20/11 04: Off Off 05/20/11 05: Off Off 05/20/11 06: Off Off 05/20/11 07: Off Off 05/20/11 08: Off Off 05/20/11 09: Off Off 05/20/11 10: Off Off There was 3 hr 29 min daytime and 1 hr and 02 min nighttime valid data after isolation analysis. The results are presented in Table 71. Table 71: Noise Monitoring Result PS20 Whitewood Pump Station (Measured Results) Period L eq, dba L eq, dbc dbc dba Tonal Component Frequency, Hz LFN Penalty, db Noise Level plus LFN Penalty, dba PSL, dba May 19/20, 2011 Daytime N.A May 19 20, 2011 Nighttime N.A However, the valid data still contains continuous contamination from frogs and birdsongs in the background. Such contamination is dominant at 2,500 Hz and 3,150 Hz bands. Contamination exclusion was performed at these two bands, as shown in Figure 39 and Figure 40 below. ATCO Project # Page 76

82 Figure 39: Averaged Daytime 1/3 Octave Band Spectra before and after Exclusion PS20 Whitewood Pump Station Figure 40: Averaged Nighttime 1/3 Octave Band Spectra before and after Exclusion PS20 Whitewood Pump Station ATCO Project # Page 77

83 The results after removing the contamination at 2,500 Hz and 3,150 Hz bands are presented in Table 72. The highest dbc dba value is only 19 db, and thus a LFN issue, as defined by Section of Directive 038, was not present. Therefore no tonal analysis was performed. Table 72: Noise Monitoring Result PS20 Whitewood Pump Station (Adjusted Levels) Period L eq, dba L eq, dbc dbc dba Tonal Component Frequency, Hz LFN Penalty, db Noise Level plus LFN Penalty, dba May 19/20, 2011 Daytime N.A May 19 20, 2011 Nighttime N.A During the nighttime measurement period, there was one pump/motor unit in operation from 10:00 pm to 11:05 pm before the pump station was switched into a bypass mode operation for the rest of the nighttime period. In the bypass mode, crude oil was passing through the pump station while no pump/motor was in operation; therefore, no noise was emitted from the pump station. A pressure control valve (PCV) was involved in the process of switching the pump station into the bypass mode between 10:00 pm and 11:05 pm when the pump/motor unit was still in operation. The nighttime L eq of 39 dba collected in this period includes the noise contribution from both the pump/motor unit and the PCV. As this is a short period/transient operating condition, the L eq of 39 dba is not representative of the expected operating conditions. Nighttime sound level of normal operating condition at the critical noise receptor is expected to be similar to the daytime sound level collected. The data analysis result, the estimated noise level of maximum load operation and the determination of compliance are presented in Table 73. Table 73: Noise Monitoring Result PS20 Whitewood Pump Station (Normal Operating Condition) Period Measurement Result Calculated L eq of Max. Load Noise Level L eq (1 Unit), dba Operation (2 Units), dba Limits, dba Compliance May 19/20, 2011 Daytime Yes Nighttime Yes The results indicate that the Whitewood pump station is in compliance with the PSL set by Alberta ERCB Noise Directive. ATCO Project # Page 78

84 3.17 PS21 Moosomin Pump Station An aerial map in Figure 41 shows the pump station location, the acoustic monitoring location, the critical receptor location and other area features. The Moosomin pump station is co located with a TCPL gas compressor facility. During the noise monitoring period, the gas compressor facility was not in operation. Therefore, the sound data collected for the pump station was not contaminated by the gas compressor facility. N Keystone Moosomin Pump Station M & R 1 km M Measurement Location; R Critical Receptor Location. Figure 41: Aerial Map PS21 Moosomin Pump Station The recorded data of the equivalent sound level (L eq ) of each 1 minute logging period at the monitoring location of the Grenfell pump station from 4:21 pm May 18, 2011 to 2:50 pm May 19, 2011 is presented in Figure 42. The obviously contaminated data by natural sounds, tree noise, local traffic noise, aircraft flyover, intrusive highway noise or human activities nearby the sound level meter have been excluded. Also excluded is data in the periods when the pump station was turned off or the weather condition was unfavorable. The published weather data and the pump station load log are shown in Table 74 and Table 75. ATCO Project # Page 79

BASELINE NOISE MONITORING SURVEY

BASELINE NOISE MONITORING SURVEY t m s environment ltd TMS Environment Ltd 53 Broomhill Drive Tallaght Dublin 24 Phone: +353-1-4626710 Fax: +353-1-4626714 Web: www.tmsenv.ie BASELINE NOISE MONITORING SURVEY UNIVERSITY COLLEGE DUBLIN Report

More information

TECHNICAL REPORT 2016 IEL ENVIRONMENTAL NOISE SURVEY OF THE DAIRYGOLD CASTLEFARM FACILITY, MITCHELSTOWN, CO. CORK.

TECHNICAL REPORT 2016 IEL ENVIRONMENTAL NOISE SURVEY OF THE DAIRYGOLD CASTLEFARM FACILITY, MITCHELSTOWN, CO. CORK. TECHNICAL REPORT 16 IEL ENVIRONMENTAL NOISE SURVEY OF THE DAIRYGOLD CASTLEFARM FACILITY, MITCHELSTOWN, CO. CORK. FOR Gabriel Kelly Group Environmental Manager Dairygold Food ingredients Castlefarm Mitchelstown

More information

Appendix 8. Draft Post Construction Noise Monitoring Protocol

Appendix 8. Draft Post Construction Noise Monitoring Protocol Appendix 8 Draft Post Construction Noise Monitoring Protocol DRAFT CPV Valley Energy Center Prepared for: CPV Valley, LLC 50 Braintree Hill Office Park, Suite 300 Braintree, Massachusetts 02184 Prepared

More information

Black. LWECS Site Permit. Stearns County. Permit Section:

Black. LWECS Site Permit. Stearns County. Permit Section: PERMIT COMPLIANCE FILING Permittee: Permit Type: Project Location: Docket No: Permit Section: Date of Submission : Black Oak Wind,, LLC LWECS Site Permit Stearns County IP6853/WS-10-1240 and IP6866/WS-11-831

More information

Noise and Ground-Borne Vibration Monitoring

Noise and Ground-Borne Vibration Monitoring 69 Noise and Vibration Study Noise and Ground-Borne Vibration Monitoring Labrador City, Newfoundland Nov, 07 Iron Ore Company of Canada TABLE OF CONTENTS 1.0 INTRODUCTION... 2 1.1 Study Objectives... 2

More information

REPORT PERIOD: JANUARY 01 MARCH

REPORT PERIOD: JANUARY 01 MARCH QUARTERLY NOISE MONITORING REPORT FOR EAST GALWAY LANDFILL REPORT PERIOD: JANUARY 01 MARCH 31 2018 IE LICENCE REF. NO. W0178-02 APRIL 2018 QUARTERLY NOISE MONITORING REPORT FOR EAST GALWAY LANDFILL REPORT

More information

Pfizer Ireland Pharmaceuticals

Pfizer Ireland Pharmaceuticals Allegro Acoustics Limited, Unit 2A Riverside, Tallaght Business Park, Tallaght, Dublin 24 Tel/Fax: +33 () 1 4148 Pfizer Ireland Pharmaceuticals Pfizer Grange Castle, Grange Castle Business Park, Clondalkin,

More information

CENTRAL WASTE MANAGEMENT FACILITY, INAGH, CO. CLARE. ENVIRONMENTAL NOISE MONITORING MAY 2017.

CENTRAL WASTE MANAGEMENT FACILITY, INAGH, CO. CLARE. ENVIRONMENTAL NOISE MONITORING MAY 2017. CENTRAL WASTE MANAGEMENT FACILITY, INAGH, CO. CLARE. ENVIRONMENTAL NOISE MONITORING MAY 2017. Prepared for: CLARE COUNTY COUNCIL ÁRAS CONTAE AN CHLÁIR NEW ROAD ENNIS CO. CLARE 3156 May 16 th, 2017 EPA

More information

W For inspection purposes only. This report shall not be reproduced except in full, without the approval of BnM Environmental.

W For inspection purposes only. This report shall not be reproduced except in full, without the approval of BnM Environmental. ANNUAL MONITORING OF ENVIRONMENTAL NOISE AT THE BORD NA MóNA KILBERRY COMPOST FACILITY IN COMPLIANCE WITH IED LICENCE, NO. W0198-01 For the Attention of: Site Work & Report Prepared by: Anua File Ref:

More information

Offaly County Council

Offaly County Council Derryclure Landfill Facility, Derryclure, Co. Offaly Annual Monitoring Report Waste Licence Reg. No. W0029-04 Report Date: th October 15 Fitz Scientific Unit 35A, Boyne Business Park, Drogheda, Co. Louth

More information

NOISE IMPACT ASSESSMENT 2016

NOISE IMPACT ASSESSMENT 2016 Panther Environmental Solutions Ltd, Unit 4, Innovation Centre, Institute of Technology, Green Road, Carlow, Ireland. Mobile: 087-8519284 Telephone /Fax: 059-9134222 Email: info@pantherwms.com Website:

More information

Noise monitoring during drilling operations Lower Stumble Well Site Balcombe, West Sussex

Noise monitoring during drilling operations Lower Stumble Well Site Balcombe, West Sussex Noise monitoring during drilling operations Lower Stumble Well Site Balcombe, West Sussex Report ref. PJ3159/13181 Date August 13 Issued to Cuadrilla Resources Limited Issued by Peter Jackson MSc MIOA

More information

Liddell Coal Operations

Liddell Coal Operations Liddell Coal Operations Environmental Noise Monitoring February 2018 Prepared for Liddell Coal Operations Pty Ltd Page i Liddell Coal Operations Environmental Noise Monitoring February 2018 Reference:

More information

Quarterly Noise Monitoring Report Austar Coal Mine Middle Road, Paxton NSW January 2007

Quarterly Noise Monitoring Report Austar Coal Mine Middle Road, Paxton NSW January 2007 REPORT 30-1664R1R0 Quarterly Noise Monitoring Report Austar Coal Mine Middle Road, Paxton NSW January 2007 PREPARED FOR P.O Box 806 Cessnock NSW 2325 14 MAY 2007 Quarterly Noise Monitoring Report Austar

More information

Roche Ireland Limited

Roche Ireland Limited Limited Clarecastle, Co. Clare Monitoring Report Industrial Emissions Licence Number P0012-05 Report Date: 1 st February 17 Fitz Scientific Unit 35A, Boyne Business Park, Drogheda, Co. Louth Report No.

More information

McGill Environmental Ltd.

McGill Environmental Ltd. McGill Environmental Ltd. Coom, Glenville, Co. Cork Environmental Noise Survey Report Date: 7 th October 2016 For inspection purposes only. KD Environmental Ltd. 1 Swiftbrook Glen, Virginia, Co. Cavan

More information

Ashton Coal. Environmental Noise Monitoring May Prepared for Ashton Coal Operations Pty Ltd

Ashton Coal. Environmental Noise Monitoring May Prepared for Ashton Coal Operations Pty Ltd Ashton Coal Environmental Noise Monitoring May 2018 Prepared for Ashton Coal Operations Pty Ltd Page i Ashton Coal Environmental Noise Monitoring May 2018 Reference: Report date: 5 June 2018 Prepared for

More information

Liddell Coal Operations

Liddell Coal Operations Liddell Coal Operations Environmental Noise Monitoring May 2018 Prepared for Liddell Coal Operations Pty Ltd Page i Liddell Coal Operations Environmental Noise Monitoring May 2018 Reference: Report date:

More information

Roche Ireland Limited

Roche Ireland Limited Roche Ireland Limited Clarecastle, Co. Clare Environmental Noise Monitoring Report Industrial Emissions Licence Number P0012-05 Report Date: 6 th October 17 Fitz Scientific Unit 35A, Boyne Business Park,

More information

Cymbaluk Noise Complaints

Cymbaluk Noise Complaints Decision 20259-D01-2015 Cymbaluk Noise Complaints December 22, 2015 Alberta Utilities Commission Decision 20259-D01-2015 Cymbaluk Noise Complaints Proceeding 20259 Application 20259-A001 December 22, 2015

More information

Pre-Construction Sound Study. Velco Jay Substation DRAFT. January 2011 D A T A AN AL Y S IS S OL U T I ON S

Pre-Construction Sound Study. Velco Jay Substation DRAFT. January 2011 D A T A AN AL Y S IS S OL U T I ON S Pre-Construction Sound Study Substation DRAFT January 2011 D A T A AN AL Y S IS S OL U T I ON S TABLE OF CONTENTS 1.0 INTRODUCTION...1 2.0 SOUND LEVEL MONITORING...1 3.0 SOUND MODELING...4 3.1 Modeling

More information

Xtratherm Limited Kells Road, Navan, Co Meath

Xtratherm Limited Kells Road, Navan, Co Meath Air I Noise I Water I Soil I Environmental Consultancy www.axisenv.ie Unit 5 Caherdavin Business Centre Ennis Road Limerick Kells Road, Navan, Co Meath Annual Environmental Noise Survey 2017 IPPC Licence

More information

The following is the summary of Keane Acoustics community mechanical noise study for the City of St. Petersburg.

The following is the summary of Keane Acoustics community mechanical noise study for the City of St. Petersburg. August 11, 2017 David Goodwin Director Planning & Economic Development Department City of St. Petersburg Re: City of St. Petersburg Dear Mr. Goodwin, The following is the summary of Keane Acoustics community

More information

Rehab Glassco. Unit 4, Osberstown Industrial Park, Caragh Road, Naas, Co. Kildare. For inspection purposes only.

Rehab Glassco. Unit 4, Osberstown Industrial Park, Caragh Road, Naas, Co. Kildare. For inspection purposes only. Air I Noise I Water I Soil I Environmental Consultancy www.axisenv.ie Unit 5 Caherdavin Business Centre, Ennis Road, Limerick Unit 4, Osberstown Industrial Park, Caragh Road, Naas, Co. Kildare Environmental

More information

Liddell Coal Operations

Liddell Coal Operations Liddell Coal Operations Environmental Noise Monitoring April 2016 Prepared for Liddell Coal Operations Pty Ltd Page i Liddell Coal Operations Environmental Noise Monitoring April 2016 Reference: Report

More information

Attended Noise Monitoring Program

Attended Noise Monitoring Program 16 May 2018 Ref: 171356/7853 Muswellbrook Coal Company PO Box 123 Muswellbrook NSW 2333 RE: MAY 2018 NOISE MONITORING RESULTS MUSWELLBROOK COAL MINE This letter report presents the results of noise compliance

More information

Protocol for Ambient Level Noise Monitoring

Protocol for Ambient Level Noise Monitoring July 2015 Protocol for Ambient Level Noise Monitoring L pressure =10.log [10 (Lp/10) - 10 (LpBackground/10) ] L pressure = 10.log [10 (Lp/10) - 10 (LpBackground/10) ] CENTRAL POLLUTION CONTROL BOARD P

More information

Attended Noise Monitoring Program

Attended Noise Monitoring Program 1 November 2018 Ref: 171356/8121 Muswellbrook Coal Company PO Box 123 Muswellbrook NSW 2333 RE: OCTOBER 2018 NOISE MONITORING RESULTS MUSWELLBROOK COAL MINE This letter report presents the results of noise

More information

Muswellbrook Coal Company

Muswellbrook Coal Company Muswellbrook Coal Company Environmental ise Monitoring May 2015 Prepared for Muswellbrook Coal Page i Muswellbrook Coal Company Environmental ise Monitoring May 2015 Reference: Report date: 18 June 2015

More information

Glassco Recycling. Unit 4, Osberstown Industrial Park, Caragh Road, Naas, Co. Kildare. For inspection purposes only.

Glassco Recycling. Unit 4, Osberstown Industrial Park, Caragh Road, Naas, Co. Kildare. For inspection purposes only. Air I Noise I Water I Soil I Environmental Consultancy www.axisenv.ie Unit 5 Caherdavin Business Centre, Ennis Road, Limerick. info@axisenv.ie 00353 61 324587 Unit 4, Osberstown Industrial Park, Caragh

More information

ENVIRONMENTAL NOISE MONITORING QUARTER 1, Northparkes Mines PO Box 995 Parkes NSW 2870

ENVIRONMENTAL NOISE MONITORING QUARTER 1, Northparkes Mines PO Box 995 Parkes NSW 2870 ENVIRONMENTAL NOISE MONITORING QUARTER 1, 2018 s PO Box 995 Parkes NSW 2870 Job No: J38252 Report issued: 25 June 2018 ESP ENVIRONMENTAL & SAFETY PROFESSIONALS A division of Enviro-Net Australia Pty. Ltd.

More information

Assured Monitoring Group

Assured Monitoring Group Assured Monitoring Group YARRANLEA SOLAR FARM NOISE & VIBRATION IMPACT ASSESSMENT JANUARY 2017 I3 CONSULTING PTY LTD Project ID. 10734 R_1 DATE OF RELEASE: 15/02/2017 Table 1: Document approval Name Position

More information

Attended Noise Monitoring - Quarter Ending September 2013

Attended Noise Monitoring - Quarter Ending September 2013 Unity Mining Level 10, 350 Collins St Melbourne VIC 3000 Version: Page 2 PREPARED BY: ABN 29 001 584 612 Units 7-8, 26-28 Napier Close Deakin ACT 2600 Australia (PO Box 9344 Deakin ACT 2600 Australia)

More information

University of York Heslington East Campus Details of Noise Modelling and Noise Survey. Report ref AAc/ /R01

University of York Heslington East Campus Details of Noise Modelling and Noise Survey. Report ref AAc/ /R01 Heslington East Campus Details of Noise Modelling and Noise Survey Report ref Heslington East Campus Details of Noise Modelling and Noise Survey January 2008 Arup Acoustics Admiral House, Rose Wharf, 78

More information

MALONE O REGAN. Annual Noise Survey Powerstown Landfill Industrial Emission Licence No. W March 2016

MALONE O REGAN. Annual Noise Survey Powerstown Landfill Industrial Emission Licence No. W March 2016 MALONE O REGAN March 2016 Powerstown Landfill Industrial Emission Licence No. W0025-04 Annual Noise Survey 2015 2B Richview Office Park, Clonskeagh, Dublin 14. Tel: +353 01 2602655 Fax: +353 01 2602660

More information

Boggabri Coal Mine. Environmental Noise Monitoring October Prepared for Boggabri Coal Operations Pty Ltd

Boggabri Coal Mine. Environmental Noise Monitoring October Prepared for Boggabri Coal Operations Pty Ltd Boggabri Coal Mine Environmental Noise Monitoring October 2017 Prepared for Boggabri Coal Operations Pty Ltd Page i Boggabri Coal Mine Environmental Noise Monitoring October 2017 Reference: Report date:

More information

Muswellbrook Coal Company

Muswellbrook Coal Company Muswellbrook Coal Company Environmental Noise Monitoring November 2015 Prepared for Muswellbrook Coal Page i Muswellbrook Coal Company Environmental Noise Monitoring November 2015 Reference: Report date:

More information

WesPac Pittsburg Energy Infrastructure Project. Noise Assessment Report

WesPac Pittsburg Energy Infrastructure Project. Noise Assessment Report WesPac Pittsburg Energy Infrastructure Project Noise Assessment Report Prepared for WesPac Energy Pittsburg LLC And Oiltanking North America LLC Prepared by TRC 1200 Wall Street West, 2 nd Floor Lyndhurst,

More information

Fundamentals of Environmental Noise Monitoring CENAC

Fundamentals of Environmental Noise Monitoring CENAC Fundamentals of Environmental Noise Monitoring CENAC Dr. Colin Novak Akoustik Engineering Limited April 03, 2013 Akoustik Engineering Limited Akoustik Engineering Limited is the sales and technical representative

More information

Rev2-18.Feb Safety Reliability Integrity Training Asset Support Design Support Troubleshooting

Rev2-18.Feb Safety Reliability Integrity Training Asset Support Design Support Troubleshooting KEYSBROOK ENVIRONMENTAL NOISE COMPLIANCE REPORTING Q1 2016 MZI RESOURCES LTD 1370900-5-100-Rev2-18.Feb.2016 www.svt.com.au Perth Brisbane Kuala Lumpur Bangkok Noise Vibration Corrosion Safety Reliability

More information

ARTHUR KILL 3. US Army Corps of Engineers NEW YORK DISTRICT NOISE MONITORING REPORT EASTERN SHORE (WEEK OF NOVEMBER 25, 2013 DECEMBER 01, 2013)

ARTHUR KILL 3. US Army Corps of Engineers NEW YORK DISTRICT NOISE MONITORING REPORT EASTERN SHORE (WEEK OF NOVEMBER 25, 2013 DECEMBER 01, 2013) ARTHUR KILL 3 US Army Corps of Engineers NEW YORK DISTRICT NOISE MONITORING REPORT EASTERN SHORE (WEEK OF NOVEMBER 25, 2013 DECEMBER 01, 2013) SITE NAK-1 DUARTE MARTI SCHOOL, FIRST STREET, ELIZABETH, NEW

More information

Boggabri Coal Mine. Environmental Noise Monitoring August Prepared for Boggabri Coal Operations Pty Ltd

Boggabri Coal Mine. Environmental Noise Monitoring August Prepared for Boggabri Coal Operations Pty Ltd Boggabri Coal Mine Environmental Noise Monitoring August 2018 Prepared for Boggabri Coal Operations Pty Ltd Page i Boggabri Coal Mine Environmental Noise Monitoring August 2018 Reference: Report date:

More information

91 Street Earth Berm Removal in Edmonton, Alberta

91 Street Earth Berm Removal in Edmonton, Alberta aci Acoustical Consultants Inc. 5031-210 Street Edmonton, Alberta, Canada T6M 0A8 Phone: (780) 414-6373 www.aciacoustical.com Environmental Noise Monitoring For The 91 Street Earth Berm Removal in Edmonton,

More information

Black Butte Copper Project Mine Operating Permit Application (Revision 3)

Black Butte Copper Project Mine Operating Permit Application (Revision 3) Mine Operating Permit Application (Revision 3) APPENDIX J: Tintina Montana, Inc. July 17 MEMORANDUM DATE: October 7, 13 TO: FROM: RE: Allan Kirk / Geomin Resources Bob Jacko / Tintina Resources Sean Connolly

More information

Electricity Supply to Africa and Developing Economies. Challenges and opportunities. Planning for the future in uncertain times

Electricity Supply to Africa and Developing Economies. Challenges and opportunities. Planning for the future in uncertain times Electricity Supply to Africa and Developing Economies. Challenges and opportunities. Planning for the future in uncertain times 765 kv Substation Acoustic Noise Impact Study by Predictive Software and

More information

Southwest Anthony Henday Drive At Wedgewood Heights Residential Neighborhood in Edmonton, AB

Southwest Anthony Henday Drive At Wedgewood Heights Residential Neighborhood in Edmonton, AB aci Acoustical Consultants Inc. 5031-210 Street Edmonton, Alberta, Canada T6M 0A8 Phone: (780) 414-6373 www.aciacoustical.com Environmental Noise Study For Southwest Anthony Henday Drive At Wedgewood Heights

More information

Environmental Noise Assessment Cambourne to Cambridge options

Environmental Noise Assessment Cambourne to Cambridge options Environmental Noise Assessment Cambourne to Cambridge options CLIENT: Cambridgeshire County Council Major Infrastructure Delivery Box No SH1311 Shire Hall Cambridge CB3 0AP CONTACT: Tim Watkins REPORTED

More information

Review of Baseline Noise Monitoring results and Establishment of Noise Criteria

Review of Baseline Noise Monitoring results and Establishment of Noise Criteria Appendix G Review of Baseline Noise Monitoring results and Establishment of Noise Criteria Environmental Management Plan G May 2014 Colton Coal Mine Aldershot, Queensland Review of Baseline Noise Monitoring

More information

Environment Protection Authority (EPA), Industrial Noise Policy (INP) 2000;

Environment Protection Authority (EPA), Industrial Noise Policy (INP) 2000; 15 December 2017 Suite 6, Level 1, 146 Hunter Street Newcastle NSW 2300 PO Box 506 Pere Riini Quarry Manager Hanson Construction Materials Pty Ltd Level 5, 75 George Street Parramatta, NSW 2150 Newcastle,

More information

Standard Guide for Measurement of Outdoor A-Weighted Sound Levels 1

Standard Guide for Measurement of Outdoor A-Weighted Sound Levels 1 Designation: E 1014 84 (Reapproved 1995) e1 AMERICAN SOCIETY FOR TESTING AND MATERIALS 100 Barr Harbor Dr., West Conshohocken, PA 19428 Reprinted from the Annual Book of ASTM Standards. Copyright ASTM

More information

Public Hearing on Revisions to Lincoln County Zoning Ordinance

Public Hearing on Revisions to Lincoln County Zoning Ordinance November 21, 2016 William G. Beck Bill.Beck@woodsfuller.com Extension 601 Lincoln County Commission 104 N. Main Street Canton, SD 57013 Lincoln County State s Attorney s Office 104 N. Main Street, Suite

More information

Boggabri Coal Mine. Environmental Noise Monitoring June Prepared for Boggabri Coal Operations Pty Ltd

Boggabri Coal Mine. Environmental Noise Monitoring June Prepared for Boggabri Coal Operations Pty Ltd Boggabri Coal Mine Environmental Noise Monitoring June 2017 Prepared for Boggabri Coal Operations Pty Ltd Page i Boggabri Coal Mine Environmental Noise Monitoring June 2017 Reference: Report date: 5 July

More information

R e p o r t th A u g u s t

R e p o r t th A u g u s t N o ise Mon it o r ing R e p o r t L e g a c y W a y T u n n e l M o n i t o r i n g P o s t C o m m is s i o n ing T es ts V e n ti la t ion S t a c ks Jun e 20 1 6 R e p o r t 3557 4 th A u g u s t 2

More information

Bloomfield Colliery. Quarterly Noise Monitoring. and Compliance Assessment September Report Number Q R2.

Bloomfield Colliery. Quarterly Noise Monitoring. and Compliance Assessment September Report Number Q R2. Bloomfield Colliery Quarterly Noise Monitoring and Compliance Assessment September 2015 Report Number Q59 630.01053-R2 15 October 2015 Bloomfield Collieries Four Mile Creek Road Ashtonfield NSW 2323 Version:

More information

Acoustics Technical Note

Acoustics Technical Note Acoustics Technical Note To Ian Roach From Alf Maneylaws Copies to File Date 30/3/11 Subject D123356: Devonport EfW: Analysis of measurement data to support adopted approach to BS4142 assessment. Introduction

More information

Soltec (Ireland) Limited Mullingar Business Park, Mullingar, Co Westmeath. Annual Noise Report

Soltec (Ireland) Limited Mullingar Business Park, Mullingar, Co Westmeath. Annual Noise Report Mullingar Business Park, Mullingar, Co Westmeath. Annual Noise Report 2013 Licence Number: W0115-01 Report Date: 09 th July 2013 Report Number: 3220-13-03 Version 0 AXIS environmental services 40 Coolraine

More information

July 8, Mr. Bryan Tripp Canadian Hydro Developers, Inc. 34 Harvard Road Guelph, ON N1G 4V8

July 8, Mr. Bryan Tripp Canadian Hydro Developers, Inc. 34 Harvard Road Guelph, ON N1G 4V8 July 8, 2009 Mr. Bryan Tripp Canadian Hydro Developers, Inc. 34 Harvard Road Guelph, ON N1G 4V8 Re: Spring 2009 Acoustic Audit and Intermediate Verification Measurements Amaranth Transformer Station, Melancthon

More information

Swan DH Noise Impact Assessment Report

Swan DH Noise Impact Assessment Report Swan 4-64 6-1 3DH Noise Impact Assessment Report April 9, 2018 Prepared for: ConocoPhillips 34501 East Quincy Avenue Watkins, Colorado 80137 Prepared by: Behrens and Associates, Inc. 13806 Inglewood Avenue

More information

January 15, File: A. Urban Systems Ltd Homer Street Vancouver, BC V6B 2W9. Attention: Tim Stevens. Dear Tim:

January 15, File: A. Urban Systems Ltd Homer Street Vancouver, BC V6B 2W9. Attention: Tim Stevens. Dear Tim: January 15, 2016 File: 0890-15A Urban Systems Ltd. 1090 Homer Street Vancouver, BC V6B 2W9 Attention: Tim Stevens Dear Tim: Re: Highway 1 - Admirals McKenzie Interchange Project Baseline Noise Monitoring

More information

ACOUSTIC BARRIER FOR TRANSFORMER NOISE. Ruisen Ming. SVT Engineering Consultants, Leederville, WA 6007, Australia

ACOUSTIC BARRIER FOR TRANSFORMER NOISE. Ruisen Ming. SVT Engineering Consultants, Leederville, WA 6007, Australia ICSV14 Cairns Australia 9-12 July, 2007 ACOUSTIC BARRIER FOR TRANSFORMER NOISE Ruisen Ming SVT Engineering Consultants, Leederville, WA 6007, Australia Roy.Ming@svt.com.au Abstract In this paper, an acoustic

More information

Wambo Coal Mine and Rail Spur

Wambo Coal Mine and Rail Spur Wambo Coal Mine and Rail Spur Environmental Noise Monitoring August 2017 Prepared for Wambo Coal Pty Limited Page i Wambo Coal Mine and Rail Spur Environmental Noise Monitoring August 2017 Reference: Report

More information

January 7, Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C

January 7, Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C Gas Pipeline-Transco 2800 Post Oak Boulevard (77056) P.O. Box 1396 Houston, Texas 77251-1396 713/215-2000 January 7, 2009 Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street,

More information

Project Survey Report Plotting of Noise Isopleth Maps of Robinson Lake Natural Gas Plant

Project Survey Report Plotting of Noise Isopleth Maps of Robinson Lake Natural Gas Plant HAGEMEYER NORTH AMERICA - Technical Services. 6825 West Sam Houston Parkway North, Houston, Texas 77041 OFFICE 713.896.0193 FAX 713.896.6006 WWW.HAGEMEYERNA.COM April 2 nd, 2013 Mr. Justin Clock Health

More information

Pipeline Blowdown Noise Levels

Pipeline Blowdown Noise Levels Pipeline Blowdown Noise Levels James Boland 1, Henrik Malker 2, Benjamin Hinze 3 1 SLR Consulting, Acoustics and Vibration, Brisbane, Australia 2 Atkins Global, Acoustics, London, United Kingdom 3 SLR

More information

Northeast Stoney Trail in Calgary, AB

Northeast Stoney Trail in Calgary, AB aci Acoustical Consultants Inc. 5031-2 Street Edmonton, Alberta, Canada T6M 0A8 Phone: (780) 414-6373, Fax: (780) 414-6376 www.aciacoustical.com Environmental Noise Monitoring For Northeast Stoney Trail

More information

Cullen Valley Mine. Environmental Noise Monitoring Quarter 2, Prepared for Castlereagh Coal

Cullen Valley Mine. Environmental Noise Monitoring Quarter 2, Prepared for Castlereagh Coal Cullen Valley Mine Environmental Noise Monitoring Quarter 2, 2018 Prepared for Castlereagh Coal Page i Cullen Valley Mine Environmental Noise Monitoring Quarter 2, 2018 Reference: Report date: 28 June

More information

Environment Protection Authority (EPA), Industrial Noise Policy (INP) 2000;

Environment Protection Authority (EPA), Industrial Noise Policy (INP) 2000; 10 October 2017 Suite 6, Level 1,, 146 Hunter Street Newcastle NSW 2300 PO Box 506 Pere Riini Quarry Manager Hanson Construction Materials Pty Ltd Level 5, 75 George Street Parramatta, NSW 2150 Newcastle,

More information

THE CASE FOR SPECTRAL BASELINE NOISE MONITORING FOR ENVIRONMENTAL NOISE ASSESSMENT.

THE CASE FOR SPECTRAL BASELINE NOISE MONITORING FOR ENVIRONMENTAL NOISE ASSESSMENT. ICSV14 Cairns Australia 9-12 July, 2007 THE CASE FOR SPECTRAL BASELINE NOISE MONITORING FOR ENVIRONMENTAL NOISE ASSESSMENT Michael Caley 1 and John Savery 2 1 Senior Consultant, Savery & Associates Pty

More information

OneSteel Recycling Hexham Quarterly Noise Monitoring Report Q2 2017

OneSteel Recycling Hexham Quarterly Noise Monitoring Report Q2 2017 OneSteel Recycling Pty Ltd 14-Jul-2017 60493017 OneSteel Recycling Hexham Quarterly Noise Monitoring Report Q2 2017 NATA ACCREDITATION No. 2778 (14391) Accredited for compliance with ISO/IEC 17025 Testing

More information

Assessing the accuracy of directional real-time noise monitoring systems

Assessing the accuracy of directional real-time noise monitoring systems Proceedings of ACOUSTICS 2016 9-11 November 2016, Brisbane, Australia Assessing the accuracy of directional real-time noise monitoring systems Jesse Tribby 1 1 Global Acoustics Pty Ltd, Thornton, NSW,

More information

ARTHUR KILL 3. US Army Corps of Engineers NEW YORK DISTRICT NOISE MONITORING REPORT EASTERN SHORE (WEEK OF JUNE 30, 2014 JULY 06, 2014)

ARTHUR KILL 3. US Army Corps of Engineers NEW YORK DISTRICT NOISE MONITORING REPORT EASTERN SHORE (WEEK OF JUNE 30, 2014 JULY 06, 2014) ARTHUR KILL 3 US Army Corps of NEW YORK DISTRICT NOISE MONITORING REPORT EASTERN SHORE (WEEK OF JUNE 30, 2014 JULY 06, 2014) SITE NAK-1 DUARTE MARTI SCHOOL, FIRST STREET, ELIZABETH, NEW JERSEY SITE # NAK-3

More information

Appendix L Noise Technical Report. Rehabilitation and Restoration of the Longfellow Bridge

Appendix L Noise Technical Report. Rehabilitation and Restoration of the Longfellow Bridge Appendix L Noise Technical Report Rehabilitation and Restoration of the Longfellow Bridge Noise Technical Report Rehabilitation and Restoration of the Longfellow Bridge Boston, MA May, 2011* Prepared by

More information

ARTHUR KILL 3. US Army Corps of Engineers NEW YORK DISTRICT NOISE MONITORING REPORT EASTERN SHORE (WEEK OF JANUARY 27, 2014 FEBRUARY 2, 2014)

ARTHUR KILL 3. US Army Corps of Engineers NEW YORK DISTRICT NOISE MONITORING REPORT EASTERN SHORE (WEEK OF JANUARY 27, 2014 FEBRUARY 2, 2014) ARTHUR KILL 3 US Army Corps of NEW YORK DISTRICT NOISE MONITORING REPORT EASTERN SHORE (WEEK OF JANUARY 27, 2014 FEBRUARY 2, 2014) SITE NAK-1 DUARTE MARTI SCHOOL, FIRST STREET, ELIZABETH, NEW JERSEY SITE

More information

Lion s Gate Secondary Wastewater Treatment Plant Pile Driving North Vancouver, BC. Final Report Rev 1

Lion s Gate Secondary Wastewater Treatment Plant Pile Driving North Vancouver, BC. Final Report Rev 1 Lion s Gate Secondary Wastewater Treatment Plant Pile Driving North Vancouver, BC Final Report Rev 1 Noise Impact Assessment RWDI # 1502274 SUBMITTED TO Paul Dufault Project Manager Metro Vancouver 4330

More information

TigerShark UAS Level Flyover Noise Measurements

TigerShark UAS Level Flyover Noise Measurements TigerShark UAS Level Flyover Noise Measurements Final 18 July 216 Adrian Sescu, Calvin Walker, Ratan Jha Mississippi State University Prepared for: Federal Aviation Administration Office of Environment

More information

Technical Note. Noise reducing properties of crash barriers. Performed for WillumTech. AV 1217/11 Project no.: A Page 1 of 19 incl.

Technical Note. Noise reducing properties of crash barriers. Performed for WillumTech. AV 1217/11 Project no.: A Page 1 of 19 incl. Technical Note Noise reducing properties of crash barriers Performed for WillumTech Project no.: A581500 Page 1 of 19 incl. 1 annex 6 October 2011 DELTA Venlighedsvej 4 2970 Hørsholm Denmark Tel. +45 72

More information

Compliance Noise Survey & Assessment

Compliance Noise Survey & Assessment John Trotter Compliance Noise Survey & Assessment Duralie Coal October 2009 Issued October 2009 Vipac Engineers & Scientists Ltd Hunter Valley / Newcastle, NSW REPORT NO: 29N-09-0002-TRP-470219-0 PREPARED

More information

Wambo Coal Mine and Rail Spur

Wambo Coal Mine and Rail Spur Wambo Coal Mine and Rail Spur Environmental Noise Monitoring September 2017 Prepared for Wambo Coal Pty Limited Page i Wambo Coal Mine and Rail Spur Environmental Noise Monitoring September 2017 Reference:

More information

Background Noise Survey Report SANTA ISABEL WIND FARM PROJECT

Background Noise Survey Report SANTA ISABEL WIND FARM PROJECT Background Noise Survey Report SANTA ISABEL WIND FARM PROJECT OCTOBER 2010 Prepared for: Prepared By: TABLE OF CONTENTS 1 INTRODUCTION... 3 2 METHODOLOGY... 5 2.1 Study Area and Noise Receptors... 5 2.2

More information

Noise Monitoring Report For. Schloetter (Ireland) Ltd. Naas Enterprise Park, Naas, Co. Kildare

Noise Monitoring Report For. Schloetter (Ireland) Ltd. Naas Enterprise Park, Naas, Co. Kildare Bray (Co. Wicklow) 01 276 1428 Lisburn (Co. Antrim) 028 9262 6733 Birmingham (U.K.) 0121 673 1804 Blackrock (Co.Cork) 021 4536155 Noise Monitoring Report 2017 For Schloetter (Ireland) Ltd. Naas Enterprise

More information

CALGA SAND QUARRY ATTENDED COMPLIANCE NOISE MONITORING 12 APRIL 2017 REPORT NO E VERSION A APRIL 2017 PREPARED FOR

CALGA SAND QUARRY ATTENDED COMPLIANCE NOISE MONITORING 12 APRIL 2017 REPORT NO E VERSION A APRIL 2017 PREPARED FOR ATTENDED COMPLIANCE NOISE MONITORING 12 APRIL 2017 REPORT NO. 01127-E VERSION A APRIL 2017 PREPARED FOR HANSON CONSTRUCTION MATERIALS PTY LTD LOT 151 PEATS RIDGE ROAD CALGA NSW 2250 DOCUMENT CONTROL Version

More information

79 First Avenue Mob: FIVE DOCK NSW 2046 VENTILATED ACOUSTIC ENCLOSURE NOISE EMISSION ASSESSMENT ACOUSTIC SERVICES & ADVICE

79 First Avenue Mob: FIVE DOCK NSW 2046 VENTILATED ACOUSTIC ENCLOSURE NOISE EMISSION ASSESSMENT ACOUSTIC SERVICES & ADVICE Head Office Postal Address T 02 9908 1270 Suite 9 PO Box 270 F 02 9908 1271 38-46 Albany St Neutral Bay 2089 E info@acousticdynamics.com.au St Leonards 2065 ABN: 36 105 797 715 W www.acousticdynamics.com.au

More information

November 12, Mr. Bryan Tripp Canadian Hydro Developers, Inc. 34 Harvard Road Guelph, ON N1G 4V8

November 12, Mr. Bryan Tripp Canadian Hydro Developers, Inc. 34 Harvard Road Guelph, ON N1G 4V8 November 12, 2009 Mr. Bryan Tripp Canadian Hydro Developers, Inc. 34 Harvard Road Guelph, ON N1G 4V8 Re: Summer 2009 Acoustic Audit and Intermediate Verification Measurements Amaranth Transformer Station,

More information

REPORT OF NOISE MONITORING OF TUTUR1C SID TRIAL AT EDINBURGH AIRPORT AUGUST TO NOVEMBER 2015 SITE 2: UPHALL

REPORT OF NOISE MONITORING OF TUTUR1C SID TRIAL AT EDINBURGH AIRPORT AUGUST TO NOVEMBER 2015 SITE 2: UPHALL Date: 09 March 2016 REPORT OF NOISE MONITORING OF TUTUR1C SID TRIAL AT EDINBURGH AIRPORT AUGUST TO NOVEMBER 2015 SITE 2: UPHALL Client: Edinburgh Limited Report Author:... Dr R. Peters Principal Consultant

More information

ARTHUR KILL 3. US Army Corps of Engineers NEW YORK DISTRICT NOISE MONITORING REPORT EASTERN SHORE (WEEK OF APRIL 29, 2013 MAY 05, 2013)

ARTHUR KILL 3. US Army Corps of Engineers NEW YORK DISTRICT NOISE MONITORING REPORT EASTERN SHORE (WEEK OF APRIL 29, 2013 MAY 05, 2013) ARTHUR KILL 3 US Army Corps of Engineers NEW YORK DISTRICT NOISE MONITORING REPORT EASTERN SHORE (WEEK OF APRIL 29, 2013 MAY 05, 2013) SITE NAK-1 DUARTE MARTI SCHOOL, FRONT STREET, ELIZABETH, NEW JERSEY

More information

Bloomfield Colliery. Quarterly Noise Monitoring and Compliance Assessment. September Report Number

Bloomfield Colliery. Quarterly Noise Monitoring and Compliance Assessment. September Report Number Report Number 630.01053 20 December 2016 Bloomfield Collieries Four Mile Creek Road Ashtonfield NSW 2323 Version: v1.0 Report Number 630.01053 20 December 2016 v1.0 Page 2 PREPARED BY: ABN 29 001 584 612

More information

Appendix D: Preliminary Noise Evaluation

Appendix D: Preliminary Noise Evaluation Appendix D: Preliminary Noise Evaluation Acoustics The study of sound and its properties is known as acoustics. By considering basic physical properties of sound and the acoustic environment, the potential

More information

ISO INTERNATIONAL STANDARD

ISO INTERNATIONAL STANDARD INTERNATIONAL STANDARD ISO 1996-2 Second edition 2007-03-15 Acoustics Description, measurement and assessment of environmental noise Part 2: Determination of environmental noise levels Acoustique Description,

More information

Annual Noise Monitoring Report

Annual Noise Monitoring Report Noise monitoring program Annual report sum mary 2 0 1 7 Annual Noise Monitoring Report The Vancouver Fraser Port Authority has a noise m onitoring program in place to better understand the source and intensity

More information

ABERDEEN HARBOUR EXPANSION PROJECT November Volume 3: Technical Appendices

ABERDEEN HARBOUR EXPANSION PROJECT November Volume 3: Technical Appendices ABERDEEN HARBOUR EXPANSION PROJECT November 2015 Volume 3: Technical Appendices Appendix 20-B BASELINE NOISE SURVEY 20-B BASELINE NOISE SURVEY Noise Sensitive Receptors A desk-based study and site walkover

More information

Mackas Sand Pty Ltd ENVIRONMENTAL NOISE MONITORING JULY 2013

Mackas Sand Pty Ltd ENVIRONMENTAL NOISE MONITORING JULY 2013 Mackas Sand Pty Ltd ENVIRONMENTAL NOISE MONITORING JULY 2013 September 2013 Mackas Sand Pty Ltd ENVIRONMENTAL NOISE MONITORING JULY 2013 September 2013 Prepared by on behalf of Mackas Sand Pty Ltd Project

More information

HIIUMAA OFFSHORE WINDFARM, ESTONIA LOW FREQUENCY NOISE AND INFRASOUND SURVEY

HIIUMAA OFFSHORE WINDFARM, ESTONIA LOW FREQUENCY NOISE AND INFRASOUND SURVEY Intended for Nelja Energia AS Document type Report Date 15/11/2016 Reference 1510023010 Madalsagedusliku ning infraheli uuringu tõlge asub KMH aruande ptk-s 5.11.2 Infraheli ja madalsageduslik müra HIIUMAA

More information

WITHIN GENERATOR APPLICATIONS

WITHIN GENERATOR APPLICATIONS POWER SYSTEMS TOPICS 9 Measuring and Understanding Sound WITHIN GENERATOR APPLICATIONS INTRODUCTION When selecting a generator, there are many factors to consider so as not to negatively impact the existing

More information

SUMMARY REPORT OF NOISE MONITORING AT MEATH GREEN OCTOBER 2010 TO SEPTEMBER 2011

SUMMARY REPORT OF NOISE MONITORING AT MEATH GREEN OCTOBER 2010 TO SEPTEMBER 2011 Date: 9 June 2012 Ref: SUMMARY REPORT OF NOISE MONITORING AT MEATH GREEN OCTOBER 2010 TO SEPTEMBER 2011 Client: Gatwick Airport Limited Report Author :... Dr R. Peters Principal Consultant Approved by

More information

The following is the summary of Keane Acoustics acoustical study for the City of St. Petersburg.

The following is the summary of Keane Acoustics acoustical study for the City of St. Petersburg. November 23, 2017 David Goodwin Director Planning & Economic Development Department City of St. Petersburg Re: City of St. Petersburg Dear Mr. Goodwin, The following is the summary of Keane Acoustics acoustical

More information

Bickerdike Allen Partners

Bickerdike Allen Partners 25 CHURCH ROAD, SE19 ENTERTAINMENT NOISE ASSESSMENT Report to Kayode Falebita Kingsway International Christian Centre 3 Hancock Road Bromley-By-Bow London E3 3DA A9540/R01-A-HT 26/07/2012 CONTENTS Page

More information

ITV CORONATION STREET PRODUCTION FACILITY, TRAFFORD WHARF ROAD ASSESSMENT OF POTENTIAL NOISE & VIBRATION IMPACT OF PROPOSED METROLINK LINE

ITV CORONATION STREET PRODUCTION FACILITY, TRAFFORD WHARF ROAD ASSESSMENT OF POTENTIAL NOISE & VIBRATION IMPACT OF PROPOSED METROLINK LINE ITV CORONATION STREET PRODUCTION FACILITY, TRAFFORD WHARF ROAD ASSESSMENT OF POTENTIAL NOISE & VIBRATION IMPACT OF PROPOSED METROLINK LINE On behalf of: ITV plc Report No. 22396.01v1 October 2014 ITV CORONATION

More information

M Sport Evaluation Centre ( MEC ) Dovenby Hall Estate

M Sport Evaluation Centre ( MEC ) Dovenby Hall Estate M Sport Evaluation Centre ( MEC ) Dovenby Hall Estate Noise Management Plan Date November 2014 Issue No 1 TABLE OF CONTENTS 1. Introduction/Purpose 2. Responsibility and Authority 3. Noise Monitoring 4.

More information

Noise Assessment for Planning Purposes - as per TAN11

Noise Assessment for Planning Purposes - as per TAN11 Noise Assessment for Planning Purposes - as per TAN11 Report No: 1703035R01A Report Status: Final Report (Amended) Dated: 23 October 2017 Purchase order No: n/a Prepared for: Garep Demirci 73 Spencer David

More information

Portable Noise Monitoring Report March 5 - April 24, 2016 The Museum of Vancouver. Vancouver Airport Authority

Portable Noise Monitoring Report March 5 - April 24, 2016 The Museum of Vancouver. Vancouver Airport Authority Portable Noise Monitoring Report March 5 - April 24, 2016 The Museum of Vancouver Vancouver Airport Authority September 27, 2016 Table of Contents INTRODUCTION... 2 OBJECTIVES... 2 VANCOUVER: AIRCRAFT

More information