Signalling Works Testing

Size: px
Start display at page:

Download "Signalling Works Testing"

Transcription

1 Railway Group Standard Issue Two Date September 1995 Signalling Works Testing Synopsis This standard defines the requirements for the through testing of new or altered signalling installations before they are placed into service. Signatures removed from electronic version Submitted by Philip Wiltshire Nominated Responsible Manager Approved by Robin Nelson Chairman, Train Control & Communications Subject Committee Authorised by Ken Burrage Controller, Safety Standards This document is the property of Railtrack. It shall not be reproduced in whole or in part without the written permission of the Controller, Safety Standards, Published by Safety & Standards Directorate Railtrack Hudson House, York Copyright 1995 Railtrack

2

3 This page is intentionally blank.

4

5 Signalling Works Testing Railway Group Standard Issue Two Date September1995 Page A1 of 8 Contents Section Description Page Part A Issue Record Responsibilities and Distribution Implementation Disclaimer Supply A3 A3 A3 A3 A3 Part B 1 Purpose B1 2 Scope B1 3 Definitions B1 4 Objective of Testing B1 5 Testing Management B1 6 Staffing B5 7 Documentation and Certification B6 Part C Testing Procedures 1 General C1 2 Definitions C1 3 General Procedures C1 4 Cables C3 5 Equipment Rooms and location Cases C4 6 Track Circuits C6 7 Point Operation and Detection C8 8 Signals C11 9 Automatic Warning System C12 10 Panels (Operational, Emergency and Maintenance) C13 11 Mechanical Signal Boxes and Ground Frames C14 12 Telecommunications Equipment for Signalling C16 13 Power Supplies C16 14 Supplementary Systems C17 15 Level Crossings C18 16 Block Systems C19 17 Functional Testing of System - Through Testing C25 18 Functional Testing of System - Testing to Control Tables C26 19 Functional Testing of System - Principles Test C42 20 Functional Testing of System - Aspect Sequence Test C43 21 Functional Testing of System - Test Trains C45 22 Post commissioning Work C45 23 General C47 R A I L T R A C K A1

6 Railway Group Issue Two Date September 1995 Page A2 of 8 Withdrawn Document Signalling Works Testing Section Description Page Part D Testing of SSI and IEEC 1 Introduction D1 2 Methodology D2 3 SSI Workstation Test D3 4 SSI TFM Equipment Tests D6 5 SSI Data Link Transmission Systems D7 6 SSI Central Interlocking Site Test D8 7 Testing SSI within an IECC Scheme D11 8 Changes and Amendments to SSI or IECC Systems D12 A2

7 Signalling Works Testing Railway Group Standard Issue Two Date September1995 Page A3 of 8 Issue record Part A This standard will be updated when necessary by distribution of a complete replacement Part. Amended or additional parts of revised pages will be marked by a vertical black line in the adjacent margin. This standard supersedes GS/WT0001 and GS/WT0002. Part Issue Date Comments Part A TwoOne SeptemberFebruary 1995 Original document. Part B One February 1995 Original document. Part C One February 1995 Original document. Part D One February 1995 Original document. Responsibilities and distribution Implementation Health and Safety Responsibilities Supply Controlled copies of this standard shall be complied with by all personnel who are responsible for the testing of new or altered signalling installations. The provisions of this Railway Group Standard are mandatory, and shall be implemented not later than 1st July In authorising this Standard, Railtrack PLC makes no warranties, express or implied, that compliance with all or any Railway Group Standards is sufficient on its own to ensure safe systems of work or operation. Each user is reminded of its own responsibilities to ensure health and safety at work and its individual duties under health and safety legislation. Controlled and uncontrolled copies of this standard may be obtained from The Catalogue Secretary, Railtrack Safety & Standards Directorate, Floor 2, Fitzroy House, 355 Euston Road, London, NW1 3AG. Telephone: or (BT) Facsimile: or (BT) R A I L T R A C K A3

8 Railway Group Issue Two Date September 1995 Withdrawn Document Signalling Works Testing Page A4 of 8 Index Description Part Section/ Paragraph Activity block, Wiring Diagrams App E Alterations, Tests to be carried out for, (Modifications) to Circuitry on New Installations not yet Commissioned, Testing of System Components - Equipment Rooms and Location Cases C 5.5 Apparatus Operating Currents and Voltages App F5 Aspect Sequence Test, Functional Testing of System C 20 Audio Frequency track Circuits (TI21/U/SF15/Z), Interfacing of App F1 Audio Frequency Track Circuits with Axle Counters (TI21/U/SF15/Z), Use of App F1 Automatic Warning System C 9 Electro Inductors, currents and voltages App F2 Axle Counters C 14.5 B Block Systems, Double Line, Testing of System Components C 16.1 Block Token System, Single Line, Testing of System Components C 16. C Cable Core Insulation, Information App F4 Cable, Testing of System Components C 4 Certificates, Testing B 67.3 Master Test Certificate App B1 Test Certificate - Relay Room/Equipment Room/Location Case App B2 Test Certificate - Points App B4 Test Certificate - Signals App B3 Check Marks, Method and Identification of Any Other Test App C78 Contact Analysis App C67 Control Tables App C45 Equipment Inspection App C56 On Track Equipment Tests App C78 Panel Fascia Details App C78 Solid State Interlocking App C78 Wiring Diagrams (one drawing method) App C2 Wiring Diagrams (two drawing method) App C3 Checklists B 76.5 Commissioning Plan B 54.4 Communication Protocol C 23.1 Competency of Staff B 65.1 Conductor Resistance for Cables App F4 A A4

9 Signalling Works Testing Railway Group Standard Issue Two Date September1995 Page A5 of 8 Description Part Section/ Paragraph C (continued) Continuity and Circuit Tests, and Diagram Wire Count C Control Table Test C 18 Correlation C 3.2 Currents and Voltages, Apparatus Operating App F5 Deferred Test Logs B 7.6 Definitions of Test Procedures C 2 Design Details - Presentation, Production of App C1 D Documentation and Certification B 7 Checklists B 7.5 Commissioning Plan B 5.4 Design Details B 7.1 Record of Testing B 7.2 Testing Plan B 5.3 Testing Strategy B 5.2 Management of Certification B 7.6 Minor Modifications Required as a Result of Testing B Test Certificates B 7.3 Test Logs B 7.4 Tester Identification B 7.2 Earth Tests C 3.1 Equipment Rooms and Location Cases C 5 Inspection C 5.1 Wire Count and Continuity Tests C 5.2 Commissioning Tests C 5.3 Test for Alterations to Existing Working Installations C 5.4 Tests to be Carried Out for Alterations (Modifications) to Circuitry on New Installations Not Yet Commissioned C 5.5 F FDM Remote Control Systems C 14.2 Final Wire and Termination Check C 3.6 E R A I L T R A C K A5

10 Railway Group Issue Two Date September 1995 Withdrawn Document Signalling Works Testing Page A6 of 8 Description Part Section/ Paragraph Ground Frames, Mechanical Signal Boxes C 11 Hot Axlebox Detectors C 14.7 IECC Scheme, Testing SSI within an, D 7 Inspection C 3.3 Installation, Design, Manufacture, and Use of Test Rigs App H Insulation App F4 Intermixing of Audio Frequency Jointless Track Circuits (TI21/U/SF15/Z) App F1.2 Key Token Instruments C 16.2 Level Crossings, Testing of System Components C 15 Location Cases and Equipment Rooms C 5 Logs, Test B 76.4 App D Maintenance of Test Desks App H Maintenance Records C Management, Testing B 54 Mechanical Interlocking C 11.4 Mechanical Signal Boxes and Ground Frames C 11 Metric Cables, Conductor Resistance for App F3 Observance of Rules C 23.9 Override, Remote Control System C Panels (Operational, Emergency and Maintenance) C 10 Permutation Chart for Point Correspondence Tests App G Plan, Commissioning B 54.4 Plan, Testing B 54.3 Point Correspondence Tests, Permutation Chart for App G Point Operation and Detection C 7 Measurements App F3 G H I J K L M O P A6

11 Signalling Works Testing Railway Group Standard Issue Two Date September1995 Page A7 of 8 Description Part Section/ Paragraph P (continued) Post Commissioning Work C 22 Power Supplies, Testing of System Components C 13 Principles test, Functional Testing of System C 19 Processor Controlled Interlockings C 14.4 Production of Design details - Presentation App C1 Recoveries C Records of Testing C 76.2 Q R Redundant Wiring C 23.8 Reed Track Circuits App F1 Rigs, Test - Design, Manufacture, Installation and Use App H Rules, Observance of C 23.9 Security of Equipment C Signal Beam Alignment App F2 Signal Lamp Voltages App F2 Signals C 8 Single Line Block Token System C 16.2 SSI and IECC, Testing of D - SSI Central Interlocking Site Test D 6 SSI Data Link Transmission Systems D 5 SSI Workstation Test D 3 SSI, Testing, within an IECC Scheme D 7 SSI TFM Equipment Exercise Test D 4 SSI Test Equipment C 23.3 Staff, Competence of B 65.1 Strap and Function Test C 3.8 Strategy, Testing, Testing Management B 54 Supplementary Systems C 14 Axle Counters C 14.5 CCTV Monitoring Systems C 14.6 FDM Remote Control Systems C 14.2 Hot Axlebox Detectors C 14.7 Processor Controlled Interlockings C 14.4 TDM Remote Control Systems C 14.1 Train Describers C 14.3 S R A I L T R A C K A7

12 Railway Group Issue Two Date September 1995 Withdrawn Document Signalling Works Testing Page A8 of 8 Description Part Section/ Paragraph TDM Remote Control Systems C 14.1 Telecommunications Equipment for Signalling C 12 Telecomms, Testing of System Components C 12 Telephones, Level Crossing, Testing of System Components C 12.2 Telephones, Lineside Signal, Testing of System Components C 12.1 Temporary Test Wiring C 23.4 Test Certificates App B T Test Desk Wiring C 23.5 Test Instruments C 23.7 Test Log B 76.4 App D Test Rigs, Design, Manufacture, Installation, and Use of App H Test Trains, Functional Testing of System C 21 Tester in Charge B 54.1 Testing of SSI and IECC D - Testing of System Components C - Testing Plan. B 45.3 Testing Procedures C -3 Testing Straps C 23.2 Testing Strategy B 54.2 Through Testing, Functional Testing of System C 17 Track Circuits C 6 TI21 App F1 Aster Type U App F1 Train Describers C 14.3 Treadles App F Voltages and Currents, Apparatus Operating App F4 Wire Count C 3 Wiring Diagram Activity Block App E Wiring, Stage, Coloured C 23.6 Working Installations, Test for Alterations to Existing C 5.4 U V W X, Y, Z A8

13 Railway Group Standard Signalling Works Testing Date February 1995 Part B Page B1 of 38 1 Purpose 2 Scope 3 Definitions 4 Objective of Testing 5 Testing Management This standard sets out the mandatory procedures necessary to ensure that new signalling installations and alterations to existing installations are independently tested in a manner which assures their safe operation and compliance with design before they are placed into service. The standard applies to all new signalling installations and to all alterations to existing installations where there is any change to the design. The standard for testing alterations where there is no change to the design is published as Railway Group Standard GK/RT0231 Signalling Maintenance Testing. The Appendices for this standard are arranged sequentially within the particular Part of the standard to which they are most relevant. Infrastructure Controller The organisation having control of the railway infrastructure. Maintenance Engineer The engineer contractually responsible to the Infrastructure Controller for the maintenance of the signalling system. The objective of testing is to ensure that the installation is in accordance with the design details supplied and that it performs to the system specifications and infrastructure controller s requirements. The installation must conform to statutory requirements and Railway Group standards. The assurance of the quality and completeness of the installation work is a separate activity for which testing staff must have evidence. However it is the responsibility of all staff to be vigilant for any shortcoming which might compromise the safety of the system and immediately advise their superior if they become aware of such a shortcoming. 5.1 Tester in Charge A person competent in accordance with Railway Group Standard GK/RT0101 Competence Standards for S&T Staff shall be nominated as being in overall charge of testing for each scheme. That person, designated Tester in Charge, shall be responsible for the organisation and satisfactory completion of the testing The Tester in Charge is responsible for the production and implementation of the testing plan, and any associated commissioning plans. The Tester in Charge may delegate the execution of these tasks to competent persons, but remains personally responsible for their completion The Tester in Charge shall ensure that each person involved is given adequate notice of, and is fully conversant with, their role in implementing the testing plan The Tester in Charge shall ensure that all testers involved in the work are fully briefed and are provided with written notes detailing what is to be done in each phase of the work. R A I L T R A C K B1

14 Railway Group Date February 1995 Withdrawn Document Signalling Works Testing Page B2 of Testing Strategy Each scheme shall have a Testing Strategy, written at the project specification stage, and forming part of the Project Specification For minor schemes this Testing Strategy may incorporate the Testing Plan A Testing Strategy is a written statement of the proposed testing methodology prepared on the basis of the specification, proposed layout and anticipated testing content of the scheme. It shall determine the extent of testing necessary, the resources required, the appropriate timescales and any preparatory testing required to confirm the feasibility of the proposed strategy. It must take account of the proposed commissioning strategy, including stageworks and possession arrangements. It shall include an assessment of the risks involved The Testing Strategy shall be approved by the engineer with overall responsibility for the project to ensure that it is compatible with the proposals for Signalling Design and Installation, and the work of the other infrastructure disciplines The Testing Strategy shall be kept up to date during project development and must identify the resources necessary for scheme implementation Following the authorisation of the scheme the Testing Strategy is the basis from which the Testing Plans and Commissioning Plans, including stagework, are to be developed The Testing Strategy shall consider the elements shown in Appendix A1 and include those which are appropriate to the project. 5.3 Testing Plan Each phase of the project shall be supported by a written Testing Plan. The Testing Plan must detail each testing activity to be undertaken. The Testing Plan shall state who is Tester in Charge and who is in overall charge of the scheme. The Testing Plan shall name the leading testers and clearly define the responsibilities and authorities of each. The Testing Plan shall be prepared sufficiently far in advance as to enable arrangements to be made for the safe working of trains The Testing Plan shall identify the resources necessary to implement the Testing Strategy. Responsibility for the procurement of sufficient competent testing staff and other necessary resources rests with the Tester in Charge The Tester in Charge may delegate the preparation of sections of the Testing Plan to competent persons The Testing Plan shall specify a satisfactory method of recording and certificating tests. The method and identification of check marks on plans, diagrams and control tables shall be defined before the work commences in accordance with examples contained in Appendix C. The diagrams must be signed in accordance with Appendix E. B2

15 Railway Group Standard Signalling Works Testing Date February 1995 Page B3 of The Testing Plan shall be independently checked by a competent person. The master copy shall bear the signatures of both the preparer and independent checker, one of whom must be the Tester in Charge. Controlled copies of the checked Testing Plan and any subsequent amendments, excluding any Check Lists and Test Certificates, shall be issued to named addressees only. The master copy shall be retained by the Tester in Charge The checked Testing Plan shall be issued sufficiently far in advance of any testing activity to ensure that all staff concerned are able to familiarise themselves with their testing roles and responsibilities before commencing work. This does not apply to the testing of off site prewiring. When it is necessary to undertake testing while the design for other parts of the project is incomplete, an interim Testing Plan must be issued Amendments to the Testing Plan are at the discretion of the Tester in Charge (or competent person delegated by the Tester in Charge). If the amendment alters the requirements of the Testing Strategy, the engineer with overall responsibility for the project shall be advised of the amendment. Amendments shall be recorded and must, where possible, be independently checked The Testing Plan may incorporate the Commissioning Plan; however, in many schemes it is impractical to separate out all the parts of the Testing Plan to be completed in particular commissioning periods without making numerous amendments to the Testing Plan. To overcome this a separate Commissioning Plan shall be written in these cases, which details the work necessary for those commissioning periods The Testing Plan shall consider the elements shown in Appendix A2, and include those which are relevant to the project. 5.4 Commissioning Plan The Commissioning Plan shall be prepared as soon as the split of work between preparatory testing and testing to be completed during the commissioning period is decided. It shall be prepared sufficiently far in advance of the proposed commissioning date to enable arrangements to be made for the safe working of trains during the commissioning period The Commissioning Plan shall be prepared jointly by the Tester in Charge and the engineer responsible for the installation work (or their delegated representatives) and include all the activities to be co ordinated The Commissioning Plan shall be independently checked by a competent person. The master copy shall bear the signatures of both the preparer and independent checker, one of whom must be the Tester in Charge. Controlled copies of the checked Commissioning Plan and any subsequent amendments, excluding any Checklists and Commissioning Certificates, shall be issued to named addressees only. The master copy shall be retained by the Tester in Charge The checked Commissioning Plan shall be issued sufficiently far in advance of any testing activities to which it relates to ensure that all staff concerned can familiarise themselves with their testing roles and responsibilities. R A I L T R A C K B3

16 Railway Group Date February 1995 Page B4 of 38 Withdrawn Document Signalling Works Testing 6 Staffing The Commissioning Plan shall consider the elements shown in Appendix A2 and include those which are relevant. 5.5 General The format of these strategies and plans will depend on the scale and nature of the work, but they shall, as a minimum clearly indicate the extent of the testing necessary and the allocation of testing responsibilities to all persons involved The Tester in Charge shall carry out checks to satisfy himself that the testing is being carried out in accordance with the standards, and with the testing and/or commissioning plans. 5.6 Co ordination with Railway Operations Before testing commences at sites containing signalling equipment which is in use, the engineer responsible for the maintenance of the equipment shall be informed of the extent and programme of work At the commencement of each period of work at sites containing signalling equipment which is in use the tester shall inform the signalman of the intended work, its likely duration and the means of contacting the testing staff Before any period of work during which it is intended to carry out testing on equipment which forms part of, or is connected to, a signalling system which is in use: arrangements shall be made to ensure the safety of the railway in accordance with the Rule Book When the site is to be left unattended, details of any alterations to working equipment shall be left available for reference by maintenance staff and the engineer responsible for the maintenance shall be informed of the arrangements made Testing activities shall be arranged so that they do not prevent maintenance staff gaining access to working equipment. 6.1 Competence Testing staff shall have documented proof of competence in accordance with Railway Group Standard GK/RT0101 Competence Standards for S&T Staff Testing staff shall have been authorised by or on behalf of the infrastructure controller to undertake the testing work The Tester in Charge shall be satisfied that all staff on testing duties are competent and authorised to carry out the roles to which they are allocated in the Testing Plan. 6.2 Independence Independence of testing must be achieved. Staff who have participated by direct preparation, direct advice or direct control of that particular design or installation, shall not assume any testing responsibilities for such work. Such staff may, however, undertake testing responsibilities for any other part of the project in which they have had no direct involvement Staff who have had a direct involvement with the design and cannot therefore demonstrate the necessary independence may only act in an assisting role. B4

17 Railway Group Standard Signalling Works Testing Date February 1995 Page B5 of 38 7 Documentation and Certification Care must be exercised, when deploying staff to work in an assisting role to ensure that, if such staff are to assist other staff over whom they normally exercise managerial responsibility, they are not placed in a situation where the independence of the testing might be compromised. 7.1 Design Details A complete set of approved plans and independently checked diagrams must be provided for the exclusive use of testing staff The copy of the Design details provided for the use of testing staff shall normally be printed on Pink paper The production, issue, format and version control of all plans, diagrams and data shall be in accordance with procedures specified in Railway Group Standard GK/RT0201 Signalling Design Production Where it is necessary to carry out the changeover of equipment in a series of specific phases during a particular stage of the work, the test copies for that stage shall clearly indicate the work to be done in each phase, in accordance with the Signalling Design Standards. The Tester in Charge shall agree the method of presentation with the designer. The method of depicting the various phases shall be set out in the Test Plan Where the installation is to be returned to service between stages of the work, separate test copies shall be issued for each stage A closure list showing the totality of the design details issued shall be sent to the Tester in Charge Once diagrams have been issued to testing staff any required modifications shall only be produced as an approved modification in accordance with procedures specified in Railway Group Standard GK/RT0201 Signalling Design Production. Before issuing such diagrams or modification sheets the Design Office shall advise the Tester in Charge and obtain a Test Log number for each modification Minor modifications to design which are found to be required during commissioning may be undertaken by on site competent staff not involved in the testing of that part of the installation. Before installing such modifications there shall be an independent design check by a competent person whose independence has not been compromised by involvement in the design, installation or testing for that part of the work. Modifications prepared in this manner shall be forwarded, as soon as possible, to the relevant design office for approval and inclusion in the final records. Note: A list of plans, diagrams and other details that may be required are shown in Appendix A3. R A I L T R A C K B5

18 Railway Group Issue Two Date February 1995 Withdrawn Document Signalling Works Testing Page B6 rev of Record of Testing The testing copy of the design details shall be the primary auditable record of testing achievement Each tester shall record their name, signature and the test date in an Activity Box (Appendix E) in the colour to be used to record the tests Each tester shall use a colour for their work that does not appear on the test copies when testing starts Individual tests shall be recorded on the test copies using check marks specified in the testing plan (Section B5.3.4) All test values shall be recorded on the maintenance record card/sheet as specified by the infrastructure controller, during or on completion of the work. 7.3 Certification of Testing Certificates of test and conformity shall be produced covering all equipment Certificates shall be produced on distinctively coloured paper (normally Pink) Test Certificates shall be prepared prior to the commencement of testing, their format being dependent upon the nature of the testing involved The Tester in Charge shall: (1) Produce a Master Certificate. (2) Be responsible for the production, issue and control of all certification. (3) Be responsible for documenting any non compliances with standards found during testing and any deferred Test Logs Management of certification is specified in Section B.7.6. (A suggested format for certification is shown in Appendix B.) The Master Certificate shall be signed by the Tester in Charge. 7.4 Test Logs Test Logs shall be produced for any queries, disagreements or deficiencies For every Testing Plan a formal Test Log Index, which may be subdivided, shall be prepared The Tester in Charge shall be responsible for the index and specify in the Testing/Commissioning Plan where the index(es) shall be located Each Test Log shall have a unique identity number in a continuous sequence taken from the index(es) Any deferred Test Logs shall be dealt with in accordance with Section B The Test Logs shall be made up in triplicate. The top copy Green, the middle copy Yellow and the bottom copy Pink. B6rev

19 Railway Group Standard Signalling Works Testing Date February 1995 Page B7 of The Tester shall initially fill in the Test Log detailing the problem as they see it. The problem shall be clearly identified and, where necessary, shall guide the person from whom the response is expected as to where the problem lies. Where the necessity to guide becomes too involved, or if a circuit design query is of a complex nature, the testing of a resulting modification may need to be carried out by a tester independent of the initial testing which highlighted the problem Generally, each item shall be entered on a separate Test Log. Items of a common nature may only be included on one Test Log, with the agreement of the Tester in Charge After a Test Log is filled in, the Green and Yellow copies shall be passed forward to the relevant designer/installation group and the Pink copy filed with the index. The relevant group shall enter a response, complete with Mod Number if appropriate, and retain the Yellow copy for their records. The Green top copy shall be returned, complete with any Mod Sheets to the Tester in Charge All resulting modifications shall be subject to a retest. Such retesting must include all parts of the installation which could have been affected by the alteration. If the action is satisfactorily retested, then the Green copy shall be signed by the Tester and replace the Pink copy with the Green Copy and the Index endorsed to show that Test Log item completed. If the action does not satisfy the Test Log item, the Green copy shall be endorsed as such by the Tester and the index endorsed to show that a new Test Log has been generated to progress the problem. Note: A flow chart of the Test Log cycle and a suggested format of the index and Test Log sheets are shown in Appendix D. 7.5 Check Lists Check lists are an aid to testing and may be used as necessary to: (1) Summarise physical progress. (2) Collate certification progress. (3) Aid the Tester. (4) Record Mod state of equipment. 7.6 Management of Certification Before the installation is handed over to the infrastructure controller to be placed into service the Tester in Charge is responsible for: a) The collection and inspection of all Test Logs to ensure that they comply with one of the following categories: Completed to the satisfaction of a suitably competent tester. Not completed, with outstanding items considered to be undesirable but not inherently unsafe. R A I L T R A C K B7

20 Railway Group Issue Two Date February 1995 Withdrawn Document Signalling Works Testing Page B8 rev of 38 Such Test Logs may be deferred for later rectification when the Tester in Charge and the infrastructure controller or his nominated representative agree that the Test Log item is not inherently unsafe; and are satisfied that there is an action plan which includes: the method of rectification, the completion date and a monitoring and progress review strategy. Completed to the infrastructure controller s requirements; but endorsed to the effect that in the tester s professional engineering judgement concerns remain over the interpretation and application of signalling standards to the installation under test. The Tester in Charge shall ensure that the infrastructure controller is aware of the details of endorsed Test Logs, and that the infrastructure controller formally accepts the responsibility. b) The collection and collation of all plans, diagrams and certification, and for ensuring that all such documents have been received and are properly annotated. Where it is not practicable to return completed documentation to the Tester in Charge prior to the handover, the Tester in Charge must be positively notified, in writing where possible (fax acceptable) by the tester responsible for the activities documented. The completed documentation must be returned to the Tester in Charge within 72 hours of such notification When all Test Logs and documentation have been collected and dealt with as required in Section B7.6.1 the Tester in Charge shall certify that the testing is complete, using the Master Test Certificate. The installation may then be signed into use by the infrastructure controller or, where the infrastructure controller has delegated the responsibility, by the Tester in Charge All test results shall be entered on the forms or other maintenance records, specified by the infrastructure controller, during or on completion of the work and be handed over for maintenance use The set of plans and diagrams used for testing shall be returned to the originating design office for all Test Logs modifications and layout changes to be correlated into the final records On completion of the record update, the set of plans and diagrams used for testing and the completed testing certification shall be returned to the infrastructure controller or his designated engineer. The location to which these plans were sent must be recorded on the relevant correspondence file. A copy of the Master Test Certificate must also be kept on the same file All testing copies of the plans and diagrams and all certification sheets and top copies of the Test Logs must be retained by or on behalf of the infrastructure controller. B8rev

21 Railway Group Standard Signalling Works Testing Date February 1995 Page B9 of 38 Appendix A1 - Testing Strategy 1. The Design Concept. 2. Target Date. 3. Correlation of Records. 4. Installation Strategy. 5. An Outline Testing Programme. 6. The Physical Boundaries of the Total Testing Activities. 7. The Possession Pattern/Requirement/Consequential effect on the Rules of the Route. 8. Stagework. 9. Proposed method of Changeover. 10. Source of competent testing resources. 11. Reactions with other Projects. 12. Novel or specialist Equipment. 13. Training Requirements. 14. Safety. 15. Risk Assessment. 16. Communications. 17. Transport. 18. Accommodation. R A I L T R A C K B9

22 Railway Group Issue Two Date February 1995 Page B10 of 38 Withdrawn Document Signalling Works Testing Appendix A2 -Testing Plans and Commissioning Plans 1. Place/Control Centre. 2. A Description of the Work. 3. Version Number and Date. 4. Distribution List. 5. Name and Signature of the Preparer. 6. Name and Signature of the Independent Checker. 7. Correspondence Reference Number. 8. The Master Test Certificate. 9. Location of Test Log Index. 10. The Signalling Plan Number and Amendment Issue. 11. A Closure List of all Design Details. 12. A Manageable detailed dated Testing Programme. 13. Work to be carried out by other departments. 14. The source and duties of competent testing resources. 15. Names and Responsibilities of the Principal Managers and Testers. 16. A complete listing and designation of responsibility of all staff involved with the testing activities (including skill level). 17. Training Requirements/Specialist Skills. 18. Shift and Shift Change Arrangements. 19. Reporting Instructions. 20. The Method of Changeover. 21. The Method for the recovery/protection of Wiring and other equipment. 22. Details of Disconnection/Closure of Signal Boxes. 23. Stagework Details. 24. Occupation/Possession Details. 25. Method of Train Working during Commissioning. 26. Special Safety Considerations. 27. Risk Assessment. 28. Test Equipment/Straps. 29. Test Wiring Requirements. 30. Accommodation. 31. Messing Facilities. 32. Control Centre Staffing. 33. Communications Systems and Emergency Numbers. 34. Telephone Directory. 35. Detailed Programme of Work. 36. Staff Briefings. 37. Location Area/Track Plan and Maps. 38. Transport. B10

23 Railway Group Standard Signalling Works Testing Date February 1995 Appendix A3 - Design Details Page B11 of 38 1 Final project/operating specification. 2 Approved signalling scheme plan(s). 3 Table of signalled routes. 4 Control tables (2 copies). 5 Location area plan(s). 6 Cable route plan(s). 7 Level crossing site plan(s). 8 Bonding plan(s). 9 Mechanical interlocking tables. 10 Mechanical locking chart. 11 Nameplate/pullplate chart/lever painting chart. 12 Cable schematic plans. 13 Cable core plans. 14 Power cable plans. 15 Location/signalbox/relay room/circuit diagrams. 16 Through circuit diagrams. 17 Control panel/console/signalbox diagram/vdu map layouts. 18 Signal sighting forms. 19 SSI data lists. 20 SSI data difference lists. 21 SSI identities. 22 Aspect sequence charts. 23 TFM allocation list. 24 IECC fast files. 25 Data Link Network Plan. 26 Central Interlocking Status Record (CISR). 27 Clean copy of updated contact analysis, if requested. R A I L T R A C K B11

24 Railway Group Issue Two Date February 1995 Withdrawn Document Signalling Works Testing Page B12 of 38 PLACE/CONTROL CENTRE: SCHEME/PROJECT: Appendix B - Suggested format for Test Certification B.1 Master Test Certificate (COMPANY NAME) MASTER TEST CERTIFICATE PLAN NO: REFERENCE No: MASTER TEST CERTIFICATE No: CUSTOMER: PREPARED BY: SIGNED: DATE: IND CHECK BY: DESIGN CLOSURE LIST INSTALLATION NAME SIGNED: SIGNATURE DATE: DATE TESTING CABLES SIGNALS POINTS TRACK CIRCUITS LOCATIONS RELAY ROOMS CONTROL LEVEL CROSSINGS ASPECT PRINCIPLES TEST LOG ACTIONS: DEFERRED ENDORSEMENTS I hereby certify that all equipment and systems relative to the signalling referred to and described above has been tested against Railway Group Standards, design details and customer specifications and found to be correct in all respects subject to the endorsement noted above. TESTER IN CHARGE Name: (CAPITALS) SIGNATURE: DATE: TIME: B12

25 Railway Group Standard Signalling Works Testing Date February 1995 B.2 - Signal Test Certificate Page B13 of 38 (COMPANY NAME) SIGNAL TEST CERTIFICATE PLACE/CONTROL CENTRE: SCHEME/PROJECT: MASTER TC No: SIGNAL No: LOCATION No: RECORD DETAILS OF ALL TESTS ON TEST COPY Structure erected in conformity of sighting form, structure gauge and Scheme Plan NAME SIGNATURE DATE Installation conforms to Installation Handbook Signal handed over to Testing Manager Installation Testing Inspection (equipment conforms to diagrams) Wire count and continuity Functionally tested Ready for Commissioning Final Sighting and Alignment R A I L T R A C K B13

26 Railway Group Issue Two Date February 1995 Withdrawn Document Signalling Works Testing Page B14 of 38 B.3 - Points Test Certificate (COMPANY NAME) PLACE/CONTROL CENTRE: SCHEME/PROJECT: POINTS TEST CERTIFICATE MASTER TC No: POINTS No: LOCATION No: RECORD DETAILS OF ALL TESTS ON TEST COPY DIAGRAMS Drive equipment installed and set up in conformity to Scheme plan and mechanical drawings NAME SIGNATURE DATE Installation conforms to Installation Handbook Points handed over to Testing Manager Installation Testing Inspection (equipment conforms to diagrams) Wire count and continuity Functionally tested Ready for Commissioning Final Test B14

27 Railway Group Standard Signalling Works Testing Date February 1995 B.4 - Location Test Certificate (COMPANY NAME) LOCATION TEST CERTIFICATE PLACE/CONTROL CENTRE: SCHEME/PROJECT: Page B15 of 38 MASTER TC No: REFERENCE No: LOCATION No: RECORD DETAILS OF ALL TESTS ON TEST COPY DIAGRAMS Installation conforms to Installation Handbook NAME SIGNATURE DATE Location handed over to Testing Manager Installation Testing Inspection (equipment conforms to diagrams) Wire count and continuity Functionally tested Through tested External equipment tested Ready for Commissioning R A I L T R A C K B15

28 Railway Group Issue Two Date February 1995 Page B16 of 38 Withdrawn Document Signalling Works Testing Appendix C1 - Presentation C1.1 Information For alterations to existing installations a two colour code system is to be used as follows: Green to identify existing wires / equipment to be recovered. Red to identify new wires / equipment to be installed. (See App Figure 2 for colour convention.) Where alterations involve large scale recoveries or modifications to existing circuits, consideration should be given to the production of two copies of each drawing, showing the alterations as follows: First copy - showing existing wires/equipment to be removed (green). Second copy - showing new wires/equipment to be installed (red). (See App Figure 2 for colour convention.) Where recoveries are such that a complete drawing becomes redundant, then the drawing must bear a cross, coloured green, through the sheet (ie, it is not necessary to colour each individual redundant circuit). Where an existing circuit is transferred from one drawing to another then both drawings must bear a suitably coloured note to that effect quoting the relevant drawing numbers. When a new drawing is required to be produced for an existing installation and the drawing depicts all new work to be installed, the drawing must bear the following: ALL NEW WORK coloured red. Where it is required to signify that a book of drawings depicts all new work, it will only be necessary for the index sheet to be endorsed as follows: ALL NEW WORK coloured red. When stageworks are involved, a separate set of drawings must be produced for each stage, irrespective of the timescale between stages. Each stage must be clearly identified on each drawing or book of drawings. Design details produced for testing purposes must be printed on pink paper, or alternatively, be identified by a coloured patch (see Appendix C2). Each new drawing or master print of the design details must bear the producer s printed and signed initials in the signature panel. Where the design details are to be carried out on existing drawings, then each drawing affected, together with subsequent duplicate copies, must be stamped with the relevant signature panel which must contain the producer s printed and signed initials. Note: The source of this Appendix is GK/RT0201, Signalling Design Production. B16

29 Railway Group Standard Signalling Works Testing Date February 1995 Page B17 of 38 1 A B C B A1 A2 A1 A2 A1 A2 R1 R2 CONTACT OF NEW RELAY USED IN EXISTING CIRCUIT 2 A1 A A2 A1 B A2 A1 C A2 SPARE CONTACT OF EXISTING RELAY USED IN EXISTING CIRCUIT 3 A1 A A2 A1 B A2 A1 C A2 CONTACT OF EXISTING RELAY REMOVED FROM EXISTING CIRCUIT RELAY REMAINS - CONTACT SPARE 4 A1 B A2 R1 B R2 CONTACT OF EXISTING RELAY REMOVED FROM EXISTING CIRCUIT RELAY ALSO REMOVED 5 A1 B A2 CONTACT OF EXISTING RELAY REMOVED FROM EXISTING CIRCUIT A1 B A2 AND RE-USED IN EXISTING CIRCUIT OR A1 D A2 A1 B A2 A1 E A2 RE-USED IN NEW CIRCUIT 6 A1 B C B C A2 R1 R2 RELAY NOMENCLATURE CHANGE 7 B C1 A1 A2 C2 B B1 B2 R1 B R2 RELAY CONFIGURATION CHANGE EXISTING CONNECTORS RE-USED EXISTING CONTACT CHANGED NEW CONNECTORS REQUIRED EXISTING CONNECTOR RE-USED - B1 NEW CONNECTOR REQUIRED - B2 App Figure 1 Colour Conventions for Alterations to Existing Circuits (New and Old Shown on Same Drawing) R A I L T R A C K B17

30 Railway Group Issue Two Date February 1995 Page B18 of 38 Withdrawn Document Signalling Works Testing DRAWING 1 (OLD) DRAWING 2 (OLD) 1 CONTACT OF NEW RELAY USED IN EXISTING CIRCUIT A C A B C B A1 A2 A1 A2 A1 A2 A1 A2 A1 A2 R1 R2 2 SPARE CONTACT OF EXISTING RELAY USED IN EXISTING CIRCUIT A C A B C A1 A2 A1 A2 A1 A2 A1 A2 A1 A2 3 CONTACT OF EXISTING RELAY REMOVED FROM EXISTING CIRCUIT RELAY REMAINS - CONTACT SPARE A B C A C A1 A2 A1 A2 A1 A2 A1 A2 A1 A2 4 CONTACT OF EXISTING RELAY REMOVED FROM EXISTING CIRCUIT RELAY ALSO REMOVED A B C A C A1 A2 A1 A2 A1 A2 A1 A2 A1 A2 R1 B R2 5a CONTACT OF EXISTING RELAY REMOVED FROM EXISTING CIRCUIT AND RE-USED IN EXISTING CIRCUIT A B C A C A1 D1 A2 A1 A2 A1 A2 A1 A2 A1 A2 D E D B E D2 D1 D2 D1 D2 A1 A2 D1 D2 5b CONTACT OF EXISTING RELAY REMOVED FROM EXISTING CIRCUIT AND RE-USED IN NEW CIRCUIT A B C A C A1 A2 A1 A2 A1 A2 A1 A2 A1 A2 F B E A1 A2 A1 A2 A3 A3 6 RELAY NOMENCLATURE CHANGE C C B B WAS C A1 A2 R1 R2 A1 A2 R1 R2 7 RELAY CONFIGURATION CHANGE B B B B C1 C2 R1 R2 A1 A2 R1 R2 B B B1 B2 B1 B2 B18 App Figure 2 Colour Conventions for Alterations to Existing Circuits (Two drawing Situation)

31 Railway Group Standard Signalling Works Testing Date February 1995 Page B19 of 38 Appendix C2 - Method and Identification of Check Marks (one drawing situation) It is essential that staff involved in the testing process understand the check marks used on the drawings as the testing proceeds. This Appendix outlines the standard check marks to be used during testing. It is impossible to be totally comprehensive. If a test is undertaken for which no check mark is detailed, then the tester will invent one. When a novel mark is used, its meaning shall be explained in the Testing Plan and/or on the diagram used for testing. If the symbol is to be used commonly throughout a scheme, it may be drawn and explained upon the diagram cover or upon a specially issued explanation sheet to be issued to all affected testers, with a copy attached to the diagrams. This Appendix contains samples of the Wiring Diagrams (showing new and old wiring on the same diagram) which are applicable to Signalling Works Testing. R A I L T R A C K B19

32 Railway Group Issue Two Date February 1995 Page B20 of 38 Withdrawn Document Signalling Works Testing Note: Only the testing check marks to be demonstrated are shown in colour (blue). OLD WIRES TO BE REMOVED/INSULATED REM INS INS CORE COUNT t1 t2 t3 t Note: REM or INS is not written on the drawing until the wire count of the old has been proven & the old wire positively identified & labelled. ON REMOVAL/INSULATION 4c 50/0.25 mm Note: Wire count symbol indicates the correct number & labelling of the cores. (if any) The tick against the core number denotes correct core at the appropriate end. CIRCUIT FUNCTION/STRAP & FUNCTION REM INS INS STRAP & FUNCTION 2 FUNCTION RELAY FUNCTIONED NEW CONTINUITY TEST CIRCUIT FUNCTION 2 FUNCTION 1 FUNCTION RELAY FUNCTIONED 1 FUNCTION WIRE COUNT CIRCUIT FUNCTIONED TO LINKS WIRE TO GO ON NEW Note: O and TGO are interchangeable. WIRE COUNT ON CONNECTION Note: For complicated mesh circuits the practice of multi-ticking may be too cumbersome. The test plan must show what action is to be taken. CIRCUIT THROUGH TESTED TT TT TT TT App Figure 3 New and Old Shown on Same Drawing B20

33 PRE COMMISSIONING TEST f1 COMMISSIONING TEST f1 REM INS POST COMMISSIONING TEST f1 2A 2A 2A A1 A-1 A-1 A2 A-2 D1 D2 A-2 A1 A2 D1 D2 A1 A-1 A2 A-2 D1 D2 REM REM A1 A1 D B D B A2 INS A2 INS C INS A1 A2 A3 A4 A1 A2 C INS INS TEMP INS A3 A4 TEMP INS REM REM REM A1 TEMP INS F D3 D4 TEMP INS F A2 D3 D4 D3 D4 D TEMP INS REM E B1 B2 B1 B2 REM F REM A3 A4 C1 C2 REM D1 D2 REM REM RWKR 2 E A3 A4 RWKR 2 RWKR 1 RWKR 1 RWKR 1 C1 C2 RWKR 1 B1 B2 B1 B2 E A3 A4 B1 B2 RWKR 1 RWKR 1 C1 C2 B1 B2 F D1 D2 D1 D2 REM REM R1 R1 TKZR X TKZR Y TKZR X R2 R2 R1 R2 TKZR Y R1 R2 TKZR X R1 R2 TKZR Y R1 R2 t1 t2 t1 t2 t1 t2 Withdrawn Document Railway Group Standard Signalling Works Testing Date February 1995 Page B21 of 38 Note: Only the testing check marks to be demonstrated are shown in colour (blue). N5 j N5 j 1 1 N5 j N5 j N5 j N5 j C D A1 A2 A3 A4 INS TEMP C D D F B5 j B5 j B5 j R A I L T R A C K B21

34 Railway Group Issue Two Date February 1995 Page B22 of 38 Withdrawn Document Signalling Works Testing App Figure 4 New and Old Shown on Same Drawing B22

35 Railway Group Standard Signalling Works Testing Date February 1995 Page B23 of 38 Appendix C3 - Method and Identification of Check Marks (two drawing situation) This Appendix contains samples of the Wiring Diagrams (showing the two drawing situation), which are applicable to Signalling Works Testing. Note: For each case shown below only the applicable check marks are demonstrated in blue. OLD WIRE TO BE REMOVED/INSULATED REM ON REMOVAL/INSULATION REM INS Note: REM or INS is not written on the drawing until the wire count of the old has been proven & the old wire positively identified & labelled. INS IN S INS CORE COUNT t1 t2 t3 t c 50/0.25 mm Note: Wire count symbol indicates the correct number and labelling of the cores. (if any) The tick against the core number denotes correct core at the appropriate end. CIRCUIT FUNCTION/STRAP & FUNCTION STRAP & FUNCTION 2 FUNCTION RELAY FUNCTIONED NEW CONTINUITY TEST CIRCUIT FUNCTION 2 FUNCTION 1 FUNCTION RELAY FUNCTIONED WIRE COUNT TGO NEW WIRE TO GO ON 1 FUNCTION CIRCUIT FUNCTIONED TO LINKS Note: O and TGO are interchangeable. WIRE COUNT ON CONNECTION Note: For complicated mesh circuits the practice of multi-ticking may be too cumbersome. The test plan must show what action is to be taken. CIRCUIT THROUGH TESTED TGO TT TT TT TT R A I L T R A C K B23

36 Railway Group Issue Two Date February 1995 Page B24 of 38 Withdrawn Document Signalling Works Testing App Figure 5 Two Drawing Situation B24

37 NEW PRE COMMISSIONING TEST f1 COMMISSIONING TEST f1 1 1 A-1 R1 R2 A-1 A-2 R1 R2 A-2 D R1 R2 D R1 R2 F D3 D4 F D3 D4 E A3 A4 NWKR 2 B1 B2 E A3 A4 NWKR 2 RWKR 1 C1 C2 NWKR 1 B1 B2 RWKR 1 C1 C2 NWKR 1 B1 B2 B1 B2 TKZR X R1 R2 TKZR Y R1 R2 TKZR X R1 R2 TKZR Y R1 R t1 t2 t1 t2 Withdrawn Document Railway Group Standard Signalling Works Testing Date February 1995 Page B25 of 38 Note: Only the testing check marks to be demonstrated are shown in colour (blue). N5 j N5 j N5 j N5 j R1 R2 R1 R2 B5 j B5 j R A I L T R A C K B25

38 Railway Group Issue Two Date February 1995 Page B26 of 38 Withdrawn Document Signalling Works Testing App Figure 6 Two drawing Situation B26

39 OLD PRE COMMISSIONING TEST f1 COMMISSIONING TEST f1 REM POST COMMISSIONING TEST f A R1 R2 A R1 R2 A R1 R2 B REM R1 R2 A3 A4 REM INS INS REM R1 R1 B B R2 INS R2 INS A3 INS A3 INS C TEMP INS C C A4 TEMP INS A4 TEMP INS REM REM REM D TEMP INS R1 R2 D R1 R2 TEMP INS D R1 R2 TEMP INS A4 REM A3 A4 C1 C2 REM D1 D2 REM REM A3 E NWKR 2 B1 B2 B1 B2 E NWKR 2 B1 B2 E A3 A4 NWKR 2 B1 B2 RWKR 1 C1 C2 NWKR 1 RWKR 1 NWKR 1 B1 B2 RWKR 1 C1 C2 NWKR 1 B1 B2 REM D1 D2 REM REM D1 F F F D2 REM TKZR X R1 R2 TKZR Y R1 R2 TKZR X R1 R2 TKZR Y R1 R2 TKZR X R1 R2 TKZR Y R1 R t1 t2 t1 t2 t1 t2 Withdrawn Document Railway Group Standard Signalling Works Testing Date February 1995 Page B27 of 38 Note: Only the testing check marks to be demonstrated are shown in colour (blue). N5 j N5 j N5 j N5 j N5 j N5 j B5 j B5 j B5 j R A I L T R A C K B27

40 Railway Group Issue Two Date February 1995 Page B28 of 38 Withdrawn Document Signalling Works Testing App Figure 7 Two drawing Situation B28

41 Railway Group Standard Signalling Works Testing Date February 1995 Page B29 of 38 Appendix C4 - Control Tables This Appendix contains samples of the Control Tables which are applicable to Signalling Works Testing. TRACKS CLEAR TRACKS OCC. POINTS SET AND DETECTED SIGNALS ALIGHT REPLACED BY TRACKS SPECIAL CONTROLS SIGNAL CONTROLS REQUIRE AB. AC. AD. end locked NORMAL N or R end locked REVERSE occ. occ. X AA1. AA AA AB UDL 1 COMBINED POINT CONTROLS ROUTE LOCKING RELEASED BY SWINGING OVERLAP REQUIRES POINTS CALLED REQUIRES TRACKS CLEAR SET BY ROUTES REQUIRES ROUTES & ROUTE LOCKING NORMAL TRACKS CLEAR OR TRACKS OCC NO. SECS TRACKS CLEAR POINTS SET OR FREE OR ROUTE & ROUTE LOCKING NORMAL N - R CO 239A. 239B 345 1D CM. CO 345 1D CE CM CO 243A 243B 245 A 245 B CO 34(9)A CM CY R - N CO 34 (S)D. 245A CY CM 36 (S)D. 245B CY CM 243A. 243B. 243A. 245A. 245B. 243B. 34(5)A. = Where more than one function is tested (eg, 451 locked normal & detected normal) Note: Controls not shown on the tables, but usually tested at this stage should be written on, but ticked through when tested. R A I L T R A C K B29

Absolute Block. Uncontrolled When Printed Document to be part superseded by GKRT0055 Iss 1 and GKRT0077 Iss 1 (published on 07/09/2013)

Absolute Block. Uncontrolled When Printed Document to be part superseded by GKRT0055 Iss 1 and GKRT0077 Iss 1 (published on 07/09/2013) Signatures removed from electronic version Submitted by... Richard Genner Nominated Responsible Manager Approved by... Philip Wiltshire Chairman, Train Control & Communications Subject Committee Approved

More information

Signalling Maintenance Testing

Signalling Maintenance Testing Date Feb 1997 Signalling Maintenance Testing Signatures removed from electronic version Synopsis This standard defines the testing requirements for previously working and commissioned signalling systems

More information

Code of Practice : Preferred Value Testing Data

Code of Practice : Preferred Value Testing Data Code of Practice Issue One Date Dec 1997 Code of Practice : Preferred Value Testing Data Synopsis This Code of Practice gives preferred values for testing data for signalling works in support of GK/RT0221.

More information

Lineside Signs. Withdrawn Document Uncontrolled When Printed. Railway Group Standard. Issue Three Date July 1996

Lineside Signs. Withdrawn Document Uncontrolled When Printed. Railway Group Standard. Issue Three Date July 1996 Railway Group Standard Date July 1996 Lineside Signs Signatures removed from electronic version Submitted by Philip Wiltshire Nominated Responsible Manager Approved by Synopsis This standard defines signs

More information

Signalling Documentation and Drawings

Signalling Documentation and Drawings Discipline: Engineering (Signalling) Category: Standard Signalling Documentation and Drawings SCP 06 Applicability New South Wales CRIA (NSW CRN) Primary Source RIC Standard SC 00 23 00 00 SP Version 3.0

More information

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

ENGINEERING DRAWINGS MANAGEMENT POLICY (IFC/AS BUILTS)

ENGINEERING DRAWINGS MANAGEMENT POLICY (IFC/AS BUILTS) Approval Amendment Record Approval Date Version Description 15/10/2015 1 This policy takes precedence over L1-NAM-PRO-003 Infrastructure As Built Drawing Management due to business restructures. New Content

More information

CHIEF ENGINEER PROCEDURE MANAGEMENT OF OVERLAPPING DESIGN AGREEMENT

CHIEF ENGINEER PROCEDURE MANAGEMENT OF OVERLAPPING DESIGN AGREEMENT Approval Amendment Record Approval Date Version Description 30/05/2014 1 Initial issue under MTM. This procedure supersedes the Overlapping Design Agreement, Application and Transfer Log documents L2-SIG-PRO-007,

More information

Requirements for GSM-R Voice Radio System

Requirements for GSM-R Voice Radio System Requirements for GSM-R Voice Radio System Signatures removed from electronic version Synopsis This document mandates requirements for the use of GSM-R systems, where these are available, to support operational

More information

Train Detection Handbook

Train Detection Handbook Page 1 of 14 Issue and revision record Section/ Issue Date Comments document 1 August 1994 New Document 2 June 1996 Renamed, formerly Track Circuit See CONTENTS for details of other documents. Train Detection

More information

BR930 Series Pin Code Allocations and Contact Arrangements

BR930 Series Pin Code Allocations and Contact Arrangements BR930 Series Pin Code Allocations and Contact Arrangements Synopsis This Guidence Note provides details of pin code allocations and contact arrangements f BR930 series equipment. Submitted by Nick Howland

More information

GK/GN0609. Guidance on Identification of Signalling and Related Equipment. Issue One June 2011 Rail Industry Guidance Note for GK/RT0009.

GK/GN0609. Guidance on Identification of Signalling and Related Equipment. Issue One June 2011 Rail Industry Guidance Note for GK/RT0009. GN Published by Block 2 Angel Square 1 Torrens Street London EC1V 1NY Copyright 2011 Rail Safety and Standards Board Limited GK/GN0609 Issue One June 2011 Rail Industry Guidance Note for GK/RT0009 Issue

More information

Provision of Telephones at Level Crossings

Provision of Telephones at Level Crossings Provision of Telephones at Level Crossings Submitted by Synopsis This standard describes the requirements for the provision of telephone facilities at level crossings.... Jon Melmoth Nominated Responsible

More information

Electrical Procedure No E032. Procedure No: ELE 032

Electrical Procedure No E032. Procedure No: ELE 032 Procedure No: ELE 032 Procedure Title: Date of Procedure: Responsible Person(s) Safety Isolation of Low Voltage Networks and Systems for work to be carried out by third parties. i.e. Non University personnel.

More information

GE/GN8648. Guidance on Positioning of Lineside Telephones. Rail Industry Guidance Note for GE/RT8048

GE/GN8648. Guidance on Positioning of Lineside Telephones. Rail Industry Guidance Note for GE/RT8048 GN This document contains one or more pages which contain colour. Published by: Block 2 Angel Square 1 Torrens Street London EC1V 1NY Copyright 2013 Rail Safety and Standards Board Limited GE/GN8648 Issue

More information

JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia

JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia BULLETIN NO. 6 TO THE PLANS AND SPECIFICATIONS FOR JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia EwingCole Architects.Engineers.Interior Designers.Planners

More information

Fiscal 2007 Environmental Technology Verification Pilot Program Implementation Guidelines

Fiscal 2007 Environmental Technology Verification Pilot Program Implementation Guidelines Fifth Edition Fiscal 2007 Environmental Technology Verification Pilot Program Implementation Guidelines April 2007 Ministry of the Environment, Japan First Edition: June 2003 Second Edition: May 2004 Third

More information

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES SECTION 01330 SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide submittals in accordance with the General Conditions as modified by the Supplementary Conditions,

More information

SATELLITE NETWORK NOTIFICATION AND COORDINATION REGULATIONS 2007 BR 94/2007

SATELLITE NETWORK NOTIFICATION AND COORDINATION REGULATIONS 2007 BR 94/2007 BR 94/2007 TELECOMMUNICATIONS ACT 1986 1986 : 35 SATELLITE NETWORK NOTIFICATION AND COORDINATION ARRANGEMENT OF REGULATIONS 1 Citation 2 Interpretation 3 Purpose 4 Requirement for licence 5 Submission

More information

SUBJECT HEADING: Switching Programmes ISSUE: 18

SUBJECT HEADING: Switching Programmes ISSUE: 18 SUBJECT: Switchgear/Switching PROCEDURE: S04 SUBJECT HEADING: Switching Programmes ISSUE: 18 DATE: Apr 2017 1. INTRODUCTION 1.1 A written programme of switching operations shall be prepared. This programme

More information

A. Action Submittals: Written and graphic information that requires Architect's responsive action.

A. Action Submittals: Written and graphic information that requires Architect's responsive action. SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

Train Radio Systems for Voice and Related Messaging Communications

Train Radio Systems for Voice and Related Messaging Communications Uncontrolled When Printed Railway Group Standard Train Radio Systems for Voice and Related Messaging Communications Synopsis This document mandates the minimum requirements for radio systems that provide

More information

.2 Accompany all submissions with a transmittal letter, in duplicate, containing:.4 Specification Section number for each submittal

.2 Accompany all submissions with a transmittal letter, in duplicate, containing:.4 Specification Section number for each submittal City of Winnipeg Brady Road Landfill Site Section 01300 New Entrance and Scale Facility Page 1 of 4 SUBMITTALS 1. SHOP DRAWINGS 1.1 General.1 Arrange for the preparation of clearly identified Shop Drawings

More information

Guideline for Creating Disconnection Points and Establishing a Not Electrically Connected Area

Guideline for Creating Disconnection Points and Establishing a Not Electrically Connected Area Guideline for Creating Disconnection Points and Establishing a Not Document Number: Authorised by: Issue Date: 29 June 2012 Previous Document: 12 February 2010 Principal Authors: J Dohmen Powerlink D Brown

More information

Revision 24 of Issue 3 of the Grid Code has been approved by the Authority for implementation on 19 th November 2007.

Revision 24 of Issue 3 of the Grid Code has been approved by the Authority for implementation on 19 th November 2007. Our Ref: Your Ref: Date: November 2007 To: All Recipients of the Serviced Grid Code Regulatory Frameworks Electricity Codes National Grid Electricity Transmission plc National Grid House Warwick Technology

More information

Section Meetings Section Material and Equipment. None Required

Section Meetings Section Material and Equipment. None Required January 2000 Page 1 of 8 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED WORK PART 2 PRODUCTS The General Conditions of the Contract, General Requirements and Supplemental

More information

(Non-legislative acts) DECISIONS

(Non-legislative acts) DECISIONS 4.12.2010 Official Journal of the European Union L 319/1 II (Non-legislative acts) DECISIONS COMMISSION DECISION of 9 November 2010 on modules for the procedures for assessment of conformity, suitability

More information

SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS SECTION 01 33 00 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

A. Action Submittals: Written and graphic information that requires Engineer's responsive action.

A. Action Submittals: Written and graphic information that requires Engineer's responsive action. SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

GK/GN0653. Guidance on Control of Unwanted Voltages on Telecommunications. Equipment at Stations. Rail Industry Guidance Note for GK/RT0053

GK/GN0653. Guidance on Control of Unwanted Voltages on Telecommunications. Equipment at Stations. Rail Industry Guidance Note for GK/RT0053 GN Published by: Block 2 Angel Square 1 Torrens Street London EC1V 1NY Copyright 2011 Rail Safety and Standards Board Limited GK/GN0653 Telecommunications Equipment at Stations Issue One: December 2011

More information

DESIGN PRACTICE NOTE DESIGN/REVIEW REQUIREMENTS FOR TRACTION BONDING PLAN

DESIGN PRACTICE NOTE DESIGN/REVIEW REQUIREMENTS FOR TRACTION BONDING PLAN Approval Amendment Record Approval Date Version Description 01/04/2014 1 Initial Issue under MTM PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 1 of 7 Table of Contents

More information

Control Command & Signalling. Standards Brief Sept Professional Head [S&C] 11/11/2014

Control Command & Signalling. Standards Brief Sept Professional Head [S&C] 11/11/2014 Control Command & Signalling Standards Brief Sept 2014 Professional Head [S&C] 11/11/2014 1 General This presentation gives headline details of the September 2014 Signalling Standards Brief It contains

More information

East Central College

East Central College SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

EDS LV SUPPLIES TO MOBILE PHONE BASE STATIONS MOUNTED ON TRANSMISSION TOWERS

EDS LV SUPPLIES TO MOBILE PHONE BASE STATIONS MOUNTED ON TRANSMISSION TOWERS ENGINEERING DESIGN STANDARD EDS 08-2109 LV SUPPLIES TO MOBILE PHONE BASE STATIONS MOUNTED ON TRANSMISSION TOWERS Network(s): Summary: EPN, LPN, SPN This standard provides guidance on the installation of

More information

25kV A.C. Electrified Lines - Traction Bonding

25kV A.C. Electrified Lines - Traction Bonding Date:MAR 94 25kV A.C. Electrified Lines - Traction Page 1 of 6 Part A Synopsis This is issued by the to define the Boards requirements for continuity bonding on railway systems. This will ensure a continuous

More information

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES SECTION 013300 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply

More information

SECTION ADMINISTRATIVE REQUIREMENTS SECTION ADMINISTRATIVE REQUIREMENTS

SECTION ADMINISTRATIVE REQUIREMENTS SECTION ADMINISTRATIVE REQUIREMENTS PART 1 GENERAL 1.01 SECTION INCLUDES A. Project Coordination. B. Preconstruction meeting. C. Progress meetings. D. Preinstallation conferences. E. Requests for information (RFI). F. Coordination drawings.

More information

Brad Luke. Director Peddle Thorp Auckland

Brad Luke. Director Peddle Thorp Auckland Brad Luke Director Peddle Thorp Auckland Site Observation and Practical Completion Preparation PEDDLE THORP Introduction Architects Agreement for Services. Observation Work Plans. Auckland Council Quality

More information

Guidance Note: Signalling Control Centres

Guidance Note: Signalling Control Centres Guidance Note: Signalling Control Centres Synopsis This document provides guidance on meeting the requirements of Railway Group Standard GK/RT0025. Signatures removed from electronic version Submitted

More information

TYPE APPROVAL PROCEDURE

TYPE APPROVAL PROCEDURE Approval Amendment Record Approval Date Version Description 15/06/2012 1 Initial issue under MTM. Replaces Connex documents cml- 8.13-PR-002 & cml-8.21-po-168 30/11/2012 2 Document revised and updated

More information

UCCS University Hall Fire Sprinkler System Upgrade March 1, 2011 RTA SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL

UCCS University Hall Fire Sprinkler System Upgrade March 1, 2011 RTA SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration SECTION 01 340 - SHOP DRAWINGS, PRODUCT DATA AND SAMPLES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 3300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

Intimate Communications Hub Interface Specification Report to Secretary of State

Intimate Communications Hub Interface Specification Report to Secretary of State Intimate Communications Hub Interface Specification Report to Secretary of State DCC V1.0 28/02/14 Page 1 of 14 Executive Summary 1. DCC is required in accordance with the terms of its Licence to produce,

More information

INTERNATIONAL TELECOMMUNICATION UNION DATA COMMUNICATION NETWORK: INTERFACES

INTERNATIONAL TELECOMMUNICATION UNION DATA COMMUNICATION NETWORK: INTERFACES INTERNATIONAL TELECOMMUNICATION UNION CCITT X.21 THE INTERNATIONAL (09/92) TELEGRAPH AND TELEPHONE CONSULTATIVE COMMITTEE DATA COMMUNICATION NETWORK: INTERFACES INTERFACE BETWEEN DATA TERMINAL EQUIPMENT

More information

Guide on the General and Administrative Aspects of the Voluntary System of Modular Evaluation of Measuring instruments

Guide on the General and Administrative Aspects of the Voluntary System of Modular Evaluation of Measuring instruments WELMEC 8.8, 2017 Guide on the General and Administrative Aspects of the Voluntary System of Modular Evaluation of Measuring instruments For information: The amendments in this guide (red) are available

More information

Air Monitoring Directive Chapter 9: Reporting

Air Monitoring Directive Chapter 9: Reporting Air Monitoring Directive Chapter 9: Reporting Version Dec 16, 2016 Amends the original Air Monitoring Directive published June, 1989 Title: Air Monitoring Directive Chapter 9: Reporting Number: Program

More information

VCE Product Design and Technology: Administrative information for Schoolbased Assessment in 2018

VCE Product Design and Technology: Administrative information for Schoolbased Assessment in 2018 VCE Product Design and Technology: Administrative information for Schoolbased Assessment in 2018 Units 3 and 4 School-assessed Task The School-assessed Task contributes 50 per cent to the study score and

More information

THIRD SCHEDULE Form of Application For A Revised Disability Access Certificate Article 20E(2)

THIRD SCHEDULE Form of Application For A Revised Disability Access Certificate Article 20E(2) THIRD SCHEDULE Form of Application For A Revised Disability Access Certificate Article 20E(2) Building Control Acts 1990 and 2007 Application for a Revised Disability Access Certificate Building Control

More information

SYNCHRONISING AND VOLTAGE SELECTION

SYNCHRONISING AND VOLTAGE SELECTION SYNCHRONISING AND VOLTAGE SELECTION This document is for Relevant Electrical Standards document only. Disclaimer NGG and NGET or their agents, servants or contractors do not accept any liability for any

More information

A. This section specifies procedural requirements for Shop Drawings, product data, samples, and other miscellaneous Work-related submittals.

A. This section specifies procedural requirements for Shop Drawings, product data, samples, and other miscellaneous Work-related submittals. SECTION 01300 PART 1 GENERAL 1.1 SECTION INCLUDES A. Description of Requirements B. Submittal Procedures C. Specific Submittal Requirements D. Action on Submittals E. Repetitive Review 1.2 DESCRIPTION

More information

SEI Certification Program Manual

SEI Certification Program Manual Safety Equipment Institute SEI Certification Program Manual Section 29: Industrial Protective Clothing and Equipment Program 0 of 6 SEI Certification Program Manual Section 29: Industrial Protective Clothing

More information

GENERAL DESCRIPTION OF THE CMC SERVICES

GENERAL DESCRIPTION OF THE CMC SERVICES STANDARD FOR CERTIFICATION No.1.1 GENERAL DESCRIPTION OF THE CMC SERVICES MAY 2007 FOREWORD (DNV) is an autonomous and independent foundation with the objectives of safeguarding life, property and the

More information

UNION COUNTY VOCATIONAL-TECHNICAL SCHOOLS West Hall Addition Project Raritan Road, Scotch Plains, NJ

UNION COUNTY VOCATIONAL-TECHNICAL SCHOOLS West Hall Addition Project Raritan Road, Scotch Plains, NJ SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 General

More information

Herts Valleys Clinical Commissioning Group. Review of NHS Herts Valleys CCG Constitution

Herts Valleys Clinical Commissioning Group. Review of NHS Herts Valleys CCG Constitution Herts Valleys Clinical Commissioning Group Review of NHS Herts Valleys CCG s constitution Agenda Item: 14 REPORT TO: HVCCG Board DATE of MEETING: 30 January 2014 SUBJECT: Review of NHS Herts Valleys CCG

More information

Level 1 VRQ Qualifications in Photo Imaging (7512) Assessment pack

Level 1 VRQ Qualifications in Photo Imaging (7512) Assessment pack Level 1 VRQ Qualifications in Photo Imaging (7512) Assessment pack www.cityandguilds.com May 2012 Version 1.1 About City & Guilds City & Guilds is the UK s leading provider of vocational qualifications,

More information

MINISTRY OF HEALTH STAGE PROBITY REPORT. 26 July 2016

MINISTRY OF HEALTH STAGE PROBITY REPORT. 26 July 2016 MINISTRY OF HEALTH Request For Solution Outline (RFSO) Social Bonds Pilot Scheme STAGE PROBITY REPORT 26 July 2016 TressCox Lawyers Level 16, MLC Centre, 19 Martin Place, Sydney NSW 2000 Postal Address:

More information

Title Operating Work - Low Voltage Distribution System. Reference Number POP 06 - (RIC Standard: EP SI)

Title Operating Work - Low Voltage Distribution System. Reference Number POP 06 - (RIC Standard: EP SI) Discipline Engineering Standard - NSW Category Electrical Title Operating Work - Low Voltage Distribution System Reference Number POP 06 - (RIC Standard: EP 95 30 00 03 SI) Document Control Status Date

More information

PROCEDURE FOR INSPECTION OF ELECTRICAL INSTALLATIONS ABOVE 250KVA

PROCEDURE FOR INSPECTION OF ELECTRICAL INSTALLATIONS ABOVE 250KVA PROCEDURE FOR INSPECTION OF ELECTRICAL INSTALLATIONS ABOVE 250KVA Generally inspection of electrical installations is carried out under Regulation-30 (Periodical inspection & testing) & Regulation-43 (Approval

More information

-and- (the Artist ) maquette means the drawing or model, prepared by the Artist, of the proposed Art Work;

-and- (the Artist ) maquette means the drawing or model, prepared by the Artist, of the proposed Art Work; THIS AGREEMENT made in triplicate this th day of, 200 BETWEEN: CITY OF OTTAWA (the City -and- (the Artist WHEREAS the Council of the former City of Ottawa, an old municipality as defined in the City of

More information

PRACTICE NOTE NO: 13 Version 1 Amended March 2001 Page 1 of 6 PRECAST CONCRETE ELEMENT DESIGN RESPONSIBILITIES AND CONTRACTUAL ARRANGEMENTS

PRACTICE NOTE NO: 13 Version 1 Amended March 2001 Page 1 of 6 PRECAST CONCRETE ELEMENT DESIGN RESPONSIBILITIES AND CONTRACTUAL ARRANGEMENTS PRACTICE NOTE NO: 13 Version 1 Amended March 2001 Page 1 of 6 Scope This Practice Note is intended to identify responsibilities and contractual arrangements for precast elements used in buildings. Such

More information

THE GRID CODE OC7.5 INTEGRAL EQUIPMENT TESTS GUIDANCE NOTES

THE GRID CODE OC7.5 INTEGRAL EQUIPMENT TESTS GUIDANCE NOTES THE GRID CODE OC7.5 INTEGRAL EQUIPMENT TESTS GUIDANCE NOTES Issue 9: May 2013 National Grid National Grid Registered Office National Grid Electricity Transmission plc Registered Office: 1-3 Strand London

More information

Status Date Prepared Reviewed Endorsed Approved

Status Date Prepared Reviewed Endorsed Approved Discipline Engineering Standard NSW Category Signalling Title Reference Number SDS 17 (RIC Standard: SC 00 13 01 17 SP) Document Control Status Date Prepared Reviewed Endorsed Approved Mar 05 Standards

More information

THE GRID CODE OC7.5 INTEGRAL EQUIPMENT TESTS

THE GRID CODE OC7.5 INTEGRAL EQUIPMENT TESTS THE GRID CODE OC7.5 INTEGRAL EQUIPMENT TESTS GUIDANCE NOTES Issue 11: February 2018 National Grid Registered Office National Grid Electricity Transmission plc Registered Office: 1-3 Strand London WC2N

More information

Estates Development & Projects

Estates Development & Projects Estates Development & Projects Production Guidelines for the Building Fabric Manual (incorporating Health & Safety File) Guidance for the Technical Author REVISION 10.2 Issue Date 09/2017 Contents Part

More information

Drawing Management Standard

Drawing Management Standard Record Number: R0000393979 Version Number: 1.0 Date: December 2015 Authorisations Action Name and title Date Prepared by TasNetworks 23/12/2015 Reviewed by David King With input from Rick Stevens, Jeshua

More information

Incentive Guidelines. Aid for Research and Development Projects (Tax Credit)

Incentive Guidelines. Aid for Research and Development Projects (Tax Credit) Incentive Guidelines Aid for Research and Development Projects (Tax Credit) Issue Date: 8 th June 2017 Version: 1 http://support.maltaenterprise.com 2 Contents 1. Introduction 2 Definitions 3. Incentive

More information

LICENCE. for WEB LINKS. Check if this document is current Find similar documents StandardsWatch (info and login) Visit our website

LICENCE. for WEB LINKS. Check if this document is current Find similar documents StandardsWatch (info and login) Visit our website LICENCE for Licensee: Date: Conditions of use: Click here for full conditions of Licence WEB LINKS Check if this document is current Find similar documents StandardsWatch (info and login) Visit our website

More information

Australian Standard. Precast reinforced concrete box culverts. Part 1: Small culverts (not exceeding 1200 mm width and 900 mm depth) AS 1597.

Australian Standard. Precast reinforced concrete box culverts. Part 1: Small culverts (not exceeding 1200 mm width and 900 mm depth) AS 1597. AS 1597.1 1974 Australian Standard Precast reinforced concrete box culverts Part 1: Small culverts (not exceeding 1200 mm width and 900 mm depth) The following industrial and governmental organizations

More information

DNVGL-CP-0338 Edition October 2015

DNVGL-CP-0338 Edition October 2015 CLASS PROGRAMME DNVGL-CP-0338 Edition October 2015 The electronic pdf version of this document, available free of charge from http://www.dnvgl.com, is the officially binding version. FOREWORD DNV GL class

More information

SECTION - II BID DATA SHEET

SECTION - II BID DATA SHEET SECTION - II BID DATA SHEET Kenya Power and Lighting Company II - 1 Contract: A36 SECTION -II BID DATA SHEET The following bid-specific data for the plant and equipment to be procured shall amend and/or

More information

1 SERVICE DESCRIPTION

1 SERVICE DESCRIPTION DNV GL management system ICP Product Certification ICP 4-6-3-5-CR Document number: ICP 4-6-3-5-CR Valid for: All in DNV GL Revision: 2 Date: 2017-05-05 Resp. unit/author: Torgny Segerstedt Reviewed by:

More information

Australian Standard. Switchgear assemblies and ancillary equipment for alternating voltages above 1 kv AS

Australian Standard. Switchgear assemblies and ancillary equipment for alternating voltages above 1 kv AS AS 2067 1984 Australian Standard Switchgear assemblies and ancillary equipment for alternating voltages above 1 kv [Title allocated by Defence Cataloguing Authority: SWITCHGEAR ASSEMBLIES, ELECTRICAL AND

More information

Greenlining and Bluelining of Ergon Energy Substation Drawings

Greenlining and Bluelining of Ergon Energy Substation Drawings Greenlining and Bluelining of Ergon Energy Table of Contents Purpose and Scope... 1 Responsibilities... 1 Definitions, Abbreviations and Acronyms... 1 References... 1 General... 1 Requirements... 3 Testing

More information

VCE Systems Engineering: Administrative information for Schoolbased Assessment in 2019

VCE Systems Engineering: Administrative information for Schoolbased Assessment in 2019 VCE Systems Engineering: Administrative information for Schoolbased Assessment in 2019 Units 3 and 4 School-assessed Task The School-assessed Task contributes 50 per cent to the study score and is commenced

More information

AS Australian Standard STEEL WIRE FOR TENDONS IN PRESTRESSED CONCRETE. This is a free 5 page sample. Access the full version online.

AS Australian Standard STEEL WIRE FOR TENDONS IN PRESTRESSED CONCRETE. This is a free 5 page sample. Access the full version online. AS 1310 1987 Australian Standard STEEL WIRE FOR TENDONS IN PRESTRESSED CONCRETE This Australian Standard was prepared by Committee BD/23, Structural Steel. It was approved on behalf of the Council of the

More information

VCE Media: Administration information for School-based Assessment in 2018

VCE Media: Administration information for School-based Assessment in 2018 VCE Media: Administration information for School-based Assessment in 2018 Units 3 and 4 School-assessed Task The School-assessed Task contributes 40 per cent to the study score and is commenced in Unit

More information

GUIDELINES FOR THE APPLICATION FOR PUBLIC RADIOCOMMUNICATIONS SERVICE (PRS) LICENCES

GUIDELINES FOR THE APPLICATION FOR PUBLIC RADIOCOMMUNICATIONS SERVICE (PRS) LICENCES GN-35/2012 GUIDELINES FOR THE APPLICATION FOR PUBLIC RADIOCOMMUNICATIONS SERVICE (PRS) LICENCES Office of the Communications Authority Hong Kong August 2012 CONTENTS SECTION 1 The regulatory framework

More information

Type Approval JANUARY The electronic pdf version of this document found through is the officially binding version

Type Approval JANUARY The electronic pdf version of this document found through  is the officially binding version STANDARD FOR CERTIFICATION No. 1.2 Type Approval JANUARY 2013 The electronic pdf version of this document found through http://www.dnv.com is the officially binding version The content of this service

More information

Standards Australia LICENCE

Standards Australia LICENCE Standards Australia LICENCE Title: Licensee: Date: Conditions of use (Click here for full conditions of Licence) Check if current WEB SEARCH Find similar documents StandardsWatch (Info and Login) Visit

More information

SECTION SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS

SECTION SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS SECTION 01300 SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections,

More information

Engineering Drawing System

Engineering Drawing System LPR 7320.1 Effective Date: February 2, 2010 Expiration Date: February 2, 2015 Langley Research Center Engineering Drawing System National Aeronautics and Space Administration Responsible Office: Systems

More information

Superseded by a more recent version INTERNATIONAL TELECOMMUNICATION UNION

Superseded by a more recent version INTERNATIONAL TELECOMMUNICATION UNION INTERNATIONAL TELECOMMUNICATION UNION ITU-T V.24 TELECOMMUNICATION STANDARDIZATION SECTOR OF ITU (10/96) SERIES V: DATA COMMUNICATION OVER THE TELEPHONE NETWORK Interfaces and voiceband modems List of

More information

Adoption of pipe systems by a GT management of UIP activities

Adoption of pipe systems by a GT management of UIP activities IGEM/TD/101 Edition 3 Communication 1802 Adoption of pipe systems by a GT management of UIP activities Founded 1863 Royal Charter 1929 Patron: Her Majesty the Queen IGEM/TD/101 Edition 3 Communication

More information

SECTION CONTRACTOR SUBMITTALS. A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER.

SECTION CONTRACTOR SUBMITTALS. A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER. SECTION 01300 - PART 1 - GENERAL 1.1 GENERAL A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER. B. Unless otherwise noted, within 14 days after the date of commencement as stated in

More information

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance National Grid UK Electricity Transmission plc NATIONAL SAFETY INSTRUCTION and Guidance NSI 26 RAILWAY CONNECTION CIRCUITS Copyright National Grid plc 2016, all rights reserved. No part of this publication

More information

Competency Standard for Registration as a Professional Engineer

Competency Standard for Registration as a Professional Engineer ENGINEERING COUNCIL OF SOUTH AFRICA Standards and Procedures System Competency Standard for Registration as a Professional Engineer Status: Approved by Council Document : R-02-PE Rev-1.3 24 November 2012

More information

Chapter 1 General Design Information

Chapter 1 General Design Information Chapter 1 General Information Introduction The primary aim in both designing and checking is to produce a structure that will safely carry the anticipated loads. The design team, consisting of the designers,

More information

Signalling Layout and Signal Aspect Sequence Requirements

Signalling Layout and Signal Aspect Sequence Requirements Signalling Layout and Signal Aspect Sequence Requirements Synopsis This document sets out requirements for the lineside signalling system to be compatible with train operations and guidance on their application.

More information

DIVISION 1 - GENERAL REQUIREMENTS SECTION SUBMITTALS

DIVISION 1 - GENERAL REQUIREMENTS SECTION SUBMITTALS DIVISION 1 - GENERAL REQUIREMENTS SECTION 01300 - SUBMITTALS PART 1 - GENERAL 1.1 STIPULATIONS A. The section "Special Requirements" forms a part of this section by this reference thereto and shall have

More information

00-General Drawings. Doc. no.: NA-00-STS002

00-General Drawings. Doc. no.: NA-00-STS002 Gæðaskjal (GSK) GSK-1773 Date of issue: 24.11.2016 Revision no.:2.0 Responsible: Einar Friðgeir Björnsson Editor: Rafn Magnús Jónsson 00-General Drawings Doc. no.: NA-00-STS002 This standard technical

More information

TECHNOLOGY QUALIFICATION MANAGEMENT

TECHNOLOGY QUALIFICATION MANAGEMENT OFFSHORE SERVICE SPECIFICATION DNV-OSS-401 TECHNOLOGY QUALIFICATION MANAGEMENT OCTOBER 2010 FOREWORD (DNV) is an autonomous and independent foundation with the objectives of safeguarding life, property

More information

SPECIFICATIONS FOR NEW UNDERGROUND RESIDENTIAL DISTRIBUTION SYSTEMS

SPECIFICATIONS FOR NEW UNDERGROUND RESIDENTIAL DISTRIBUTION SYSTEMS Page: 4-1 4.0 URD Process and Documentation Requirements 4.1 Process Steps The process of developing underground distribution facilities in a residential area consists of 10 major steps, which are summarized

More information

RELEVANT ELECTRICAL STANDARDS

RELEVANT ELECTRICAL STANDARDS RELEVANT ELECTRICAL STANDARDS Issue 2 October 2014 Issue 2 September 2014 National Grid 2014 2014 Copyright owned by National Grid Electricity Transmission plc, all rights reserved. No part of this publication

More information

Continuous On-line Measurement of Water Content in Petroleum (Crude Oil and Condensate)

Continuous On-line Measurement of Water Content in Petroleum (Crude Oil and Condensate) API Manual of Petroleum Measurement Standards TR 2570 EI Hydrocarbon Management HM 56 Continuous On-line Measurement of Water Content in Petroleum (Crude Oil and Condensate) First Edition, October 2010

More information

SECTION A. RFI: Request from Contractor seeking interpretation, information, or clarification of the Contract Documents.

SECTION A. RFI: Request from Contractor seeking interpretation, information, or clarification of the Contract Documents. SECTION 01 3000 PART 1 GENERAL 1.1 SECTION INCLUDES A. Electronic document submittal service. B. Preconstruction meeting. C. Submittals for review, information, and project closeout. D. Submittal procedures.

More information

Co-ordination of the Group of Notified Bodies for the Construction Products Directive 89/106/EEC. GNB-CPD Conference on CPR

Co-ordination of the Group of Notified Bodies for the Construction Products Directive 89/106/EEC. GNB-CPD Conference on CPR GNB-CPD All Co-ordination of the Group of Notified Bodies for the Construction Products Directive 89/106/EEC NB-CPD/All-13/112 Issued: 13 June 2013 Answers to GNB- CPD questions GNB-CPD Conference on CPR

More information

IGEM/TD/101 Edition 2 Communication 1740 Adoption of pipe systems by a GT management of UIP activities

IGEM/TD/101 Edition 2 Communication 1740 Adoption of pipe systems by a GT management of UIP activities Communication 1740 Adoption of pipe systems by a GT management of UIP activities Founded 1863 Royal Charter 1929 Patron: Her Majesty the Queen Communication 1740 Adoption of pipe systems by a GT management

More information

Engineering Drawing System

Engineering Drawing System LPR 7320.1 Effective Date: July 18, 2004 Expiration Date: July 18, 2008 Langley Research Center Engineering Drawing System National Aeronautics and Space Administration Responsible Office: Systems Engineering

More information