LOSS ESTIMATION FOR THREE 33/11kV TRANSFORMERS AT SCOTTISH & SOUTHERN ENERGY POWER DISTRIBUTION

Size: px
Start display at page:

Download "LOSS ESTIMATION FOR THREE 33/11kV TRANSFORMERS AT SCOTTISH & SOUTHERN ENERGY POWER DISTRIBUTION"

Transcription

1 LOSS ESTIMATION FOR THREE 33/11kV TRANSFORMERS AT SCOTTISH & SOUTHERN ENERGY POWER DISTRIBUTION by SIMON RYDER Addressee: MACIEJ FILA (SCOTTISH& SOUTHERN ENERGY POWER DISTRIBUTION) Registered in England & Wales Registered Office, 5 New Street Square, London EC4A 3TW

2 JOB INFORMATION REPORT REFERENCE CUSTOMER SITE JOB DESCRIPTION TEST ENGINEERS TEST DATE REPORT PREPARED BY DATE REPORT AUTHORISED BY DATE 9635/SSEPD ISSUE 3 Scottish & Southern Energy Power Distribution Causeway, Frome, and Ferndown 33kV substations Loss estimation for three 33/11kV transformers Stefan DRAGOSTINOV, Simon RYDER (01/02/2016 and 03/02/2016), and Steve WARD (12/02/2016) 01/02/2016 Causeway 03/02/2016 Frome 12/02/2016 Ferndown Simon RYDER 18/02/2016 (ISSUE 1); 07/03/2016 (ISSUE 2); 14/03/2016 (ISSUE 3) Stefan DRAGOSTINOV (ISSUE 1) John LAPWORTH (ISSUE 2) Richard HEYWOOD (ISSUE 3) 23/02/2016 (ISSUE 1); 10/03/2016 (ISSUE 2); 15/03/2016 (ISSUE 3) /SSEPD

3 TABLE OF CONTENTS JOB INFORMATION... 2 INTRODUCTION... 4 CONCLUSIONS... 4 LOSS ESTIMATION METHODS... 4 RESULTS... 7 TABLES... 9 FIGURES CIRCULATION /SSEPD

4 INTRODUCTION Following initial discussions at Scottish & Southern Energy Power Distribution (SSEPD) offices in Reading on 09/11/2015, Doble PowerTest were asked to make a trial of a proposed method for loss estimation on three 33/11kV transformers at SSEPD primary sub-stations. The measurements were made between 01/02/2016 and 12/01/2016. This report presents an explanation of the proposed method and results of the trials. It was revised and corrected following closing discussions at SSEPD offices in Reading on 04/03/2016. CONCLUSIONS Based on the proposed method, Doble PowerTest estimate the following losses for the three transformers included in the trial: Causeway 33/11kV transformer 3 (Brush serial no /1, built 2007) Load loss on tap 9 (12MVA base, 75 C reference temperature) 79.8kW No-load loss at rated excitation 6.0kW Frome C1MT (Brush serial no /1, built 2008) Load loss on tap 9 (15MVA base, 75 C reference temperature) 88.1kW No-load loss at rated excitation 7.2kW Ferndown C1MT (Tironi serial no. E6601, built 1998) Load loss on tap 9 (12MVA base, 75 C reference temperature) 47.6kW No-load loss at rated excitation 8.2kW LOSS ESTIMATION METHODS Origins of Transformer Losses Transformer losses can be divided into no-load losses, which are present whenever the transformer is energised, and load losses, which vary as the square of the load current. No-load losses are essentially caused by magnetisation of the transformer core. Load losses have a variety of causes, of which losses owing to the winding resistance make up the largest part (approximately 80% on modern designs). Other causes of load losses include currents induced by the leakage flux in the windings and also in the core, frame, and tank. Transformer Losses over the Years In general, losses in medium and large power transformers used in the transmission and distribution networks have reduced over the years. There has been increased pressure on users to specify transformers with lower losses. Alternatively, there has been increased pressure on users to specify high loss capitalisation values for total cost of ownership calculations. To produce transformers with lower losses, manufacturers have worked to improve design and construction. Additionally, manufacturers have worked with suppliers to develop new materials /SSEPD

5 Major improvements in design, construction, and materials include: No-load loss: Improved core steel Improved slitting and cutting of core steel Elimination of through bolts Use of so-called step-lap joints between limbs and yokes Reduced flux density Reduced internal clearances (and hence reduced mass) Load loss Use of continuously transposed conductors Single point earthing Use of flux shields Use of flux shunts Reduced internal clearances (and hence reduced mass) Compared with designs produced 50 years ago, contemporary designs typically have 30-50% of the noload losses and 40-70% of the load losses. Most of these changes have taken place gradually. One important exception is the reduction in no-load losses caused by use of reduced flux densities, which was the result of a change in specifications from As was mentioned above, no-load losses are essentially caused by magnetisation of the transformer core, and are thus strongly dependent on the properties of the core material. Early transformers had hot-rolled steel cores, the properties of which deteriorate with use. No-load losses in such transformers are likely to increase in service. Hot-rolled steel has been replaced by cold-rolled steel in modern designs, the properties of which do not deteriorate with use. Cold-rolled steel was first patented by Norman GOSS in 1935, and is highly likely to be used in any designs manufactured after the patent expired in (It may also be used in some earlier designs). As was also mentioned above, load losses have a variety of causes, of which losses owing to the winding resistance make up the largest part. Substantially all transformers have windings manufactured from copper, the properties of which do not deteriorate with use. It follows that load losses in such transformers will not substantially increase in service. Measurement of Losses At manufacturer s works, no-load losses are measured in the test laboratory by exciting the transformer using a powerful variable voltage supply (usually a rotary convertor, but static convertors are also used). Voltage and current are measured using highly accurate instrument transformers class 0.1 or better. Losses are then measured using a highly accurate power analyser /SSEPD

6 At manufacturer s works, load losses are usually measured in the test laboratory by short-circuiting one winding and supplying the other, using a powerful variable voltage supply. Voltage and current are measured using highly accurate instrument transformers class 0.1 or better. Losses are then measured using a highly accurate power analyser. Accurate determination of the load losses is particularly challenging owing to the low power factor of the transformer in the measurement configuration. Estimating Losses in the Field In the field, it would be very difficult to duplicate the methods for measuring transformer losses at the test laboratories in manufacturer s works. For smaller transformers, it might be possible to transport the transformer to a suitable test laboratory for measurement. For larger transformers, this would also be very difficult. To overcome difficulties in measuring losses on transformers in the field, Doble PowerTest propose to make measurements of some parameters using portable test equipment and then estimate the losses from these results. These estimates can be refined based on available design data, e.g. masses recorded on the nameplate or in the operating/maintenance manual. Measurements required are as follows: Winding resistance Impedance (mainly to confirm values marked on the nameplate) Load loss estimated using the following methodology: Winding resistance losses are calculated directly from measured winding resistance and currents, based on nameplate values of rated power. Losses induced in the windings by the leakage flux (so-called winding eddy current losses) are estimated from the winding resistance losses using a dimensionless multiplication factor based on medium power transformer designs reviewed by Doble PowerTest over the last 5-10 years. Analysis of 33 different designs by 10 different manufacturers suggest that this multiplication factor is in the range 0.030pu to 0.133pu with an average value of 0.086pu. Losses induced in other parts of the transformer by the leakage flux (so-called other eddy current losses or stray losses) are estimated from the reactive power absorption of the transformer using a multiplication factor. The reactive power absorption is calculated from the impedance. As for winding eddy current losses, the multiplication factor is based on medium power transformer designs reviewed by Doble PowerTest over the last 5-10 years. Analysis of 33 different designs by 10 different manufacturers suggest that this multiplication factor is in the range 0.67kW/Mvar to 4.96kW/Mvar with an average value of 2.72kW/Mvar. Load loss estimates are thus made using the following formula: = % 100 where k1 is the dimensionless multiplication factor for winding eddy current losses and k2 is the multiplication factor for other eddy current losses /SSEPD

7 No-load loss estimates are based on the core mass. If no value for the core mass is available, this is assumed to be 60% of the core and winding assembly mass (sometimes also referred to as the untanking mass). This is multiplied by specific losses from manufacturer s data. For the first issue of this report, rated excitation was assumed to be 1.7T. This was found to be incorrect, following a review of results and a subsequent review of specifications. For the second issue of this report, rated excitation is now assumed to be 1.55T. Rated losses of available core lamination grades are in the range 0.75W/kg to 1.45W/kg at 1.7T. Alternatively, rated losses of available core lamination grades are in the range 0.50W/kg to 1.05W/kg at 1.55T. Lower values are used for more modern designs, to reflect changes in design practices and improvements in core lamination grades. This is also multiplied by a dimensionless multiplication factor often known as the building factor, to reflect additional losses caused by slitting and cutting the laminations; stacking the laminations; and especially partial saturation of laminations at the joints between the limbs and yokes. For modern designs with step-lap joints and without through bolts, the building factor is typically 1.1pu. For older designs the building factor may be as high as 1.5pu. No-load loss estimates are thus made using the following formula: = where ps is the specific loss and k3 is the dimensionless multiplication or building factor for no-load losses. RESULTS Causeway 33/11kV Transformer 3 Causeway 33/11kV transformer 3 is a 12/24MVA continuous emergency rated transformer built by Brush in 2007, serial no /1. Figure 1 shows a general view of Causeway 33/11kV transformer 3. Figure 2 shows a close-up view of the nameplate. Calibration data for the test equipment used is listed in Table 1. Results of winding resistance results are listed in Table 2 (HV) and Table 3 (LV). Selected results are also shown in graphical form in Figure 3. Ambient temperature at the time of the measurements was 13 C. Results of impedance measurements are listed in Table 4. Based on the measurement results, Doble PowerTest estimate that load losses for Causeway 33/11kV transformer 3 on tap 9 at 12MVA are 79.8kW at 75 C reference temperature. Load losses on other tap positions and also minimum and maximum expected values of load losses are listed in Table 5. Measured load losses from works test on tap 9 at 12MVA are 84.3kW at 75 C reference temperature. Measured no-load losses on other tap positions are listed in Table 6. Based on the untanking mass recorded on the nameplate and their experience with transformers manufactured around the same time, Doble PowerTest estimate that no-load losses for Causeway 33/11kV transformer 3 are 6.0kW at rated excitation. Minimum and maximum expected values of noload losses are listed in Table 7. Measured no-load losses are 5.7kW at rated excitation /SSEPD

8 Frome C1MT Frome C1MT is a 15/30MVA continuous emergency rated transformer built by Brush in 2008, serial no /1. Figure 4 shows a general view of Frome C1MT. Figure 5 shows a close-up view of the nameplate. Calibration data for the test equipment used is listed in Table 1. Results of winding resistance results are listed in Table 8 (HV) and Table 9 (LV). Selected results are also shown in graphical form in Figure 6. Ambient temperature at the time of the measurements was 7 C. Results of impedance measurements are listed in Table 10. Based on the measurement results, Doble PowerTest estimate that load losses for Frome C1MT on tap 9 at 15MVA are 88.1kW at 75 C reference temperature. Load losses on other tap positions and also minimum and maximum expected values of load losses are listed in Table 11. Measured load losses from works test on tap 9 at 15MVA are 92.6kW at 75 C reference temperature. Measured no-load losses on other tap positions are listed in Table 12. Based on the untanking mass recorded on the nameplate and their experience with transformers manufactured around the same time, Doble PowerTest estimate that no-load losses for Frome C1MT are 7.2kW at rated excitation. Minimum and maximum expected values of no-load losses are listed in Table 13. Measured no-load losses are 7.1kW at rated excitation. Ferndown C1MT Ferndown C1MT is a 12/24MVA continuous emergency rated transformer built by Tironi in 1998, serial no. E6601. Figure 7 shows a general view of Frome C1MT. The nameplate was illegible. Information on the untanking mass etc. was obtained from a drawing in the operation and maintenance manual. Calibration data for the test equipment used is listed in Table 1. Results of winding resistance results are listed in Table 14 (HV) and Table 15 (LV). Selected results are also shown in graphical form in Figure 8. Ambient temperature at the time of the measurements was 6 C. Results of impedance measurements are listed in Table 16. Based on the measurement results, Doble PowerTest estimate that load losses for Ferndown C1MT on tap 9 at 12MVA are 47.6kW at 75 C reference temperature. Load losses on other tap positions and also minimum and maximum expected values of load losses are listed in Table 17. Measured load losses from works test on tap 9 at 15MVA are 43.9kW at 75 C reference temperature. Measured no-load losses on other tap positions are listed in Table 18. Based on the untanking mass recorded on the nameplate drawing and their experience with transformers manufactured around the same time, Doble PowerTest estimate that no-load losses for Ferndown C1MT are 8.2kW at rated excitation. Minimum and maximum expected values of load losses are listed in Table 19. Measured no-load losses are 8.6kW at rated excitation /SSEPD

9 TABLES Table 1 Calibration Data for Measurement Equipment Test Equipment Serial No. Calibration Due Winding Resistance DV Power RMO60T DOB /10/2017 Impedance Doble M4000 DOB /08/2018 Table 2 Causeway 33/11kV transformer 3, HV winding resistance (mohm) Tap A-B A-C B-C Table 3 Causeway 33/11kV transformer 3, LV winding resistance (mohm) Tap a-n b-n c-n Table 4 Causeway 33/11kV transformer 3, impedance Tap Impedance (%, 12MVA base) Table 5 Causeway 33/11kV transformer 3, Load losses (kw at 12MVA, 75 C reference temperature) Tap Minimum Expected Maximum /SSEPD

10 Table 6 Causeway 33/11kV transformer 3, Load losses (kw at 12MVA, 75 C reference temperature) Tap Works Test Table 7 Causeway 33/11kV transformer 3, No-load losses (kw at rated excitation) Flux Density Minimum Expected Maximum Original Estimate (B MAX = 1.7T) Revised Estimate (B MAX = 1.55T) Table 8 Frome C1MT, HV winding resistance (mohm) Tap A-N B-N C-N Table 9 Frome C1MT, LV winding resistance (mohm) Tap a-n b-n c-n /SSEPD

11 Table 10 Frome C1MT, impedance Tap Impedance (%, 15MVA base) Table 11 Frome C1MT, Load losses (kw at 15MVA, 75 C reference temperature) Tap Minimum Expected Maximum Table 12 Frome C1MT, Load losses (kw at 15MVA, 75 C reference temperature) Tap Works Test Table 13 Frome C1MT, No-load losses (kw at rated excitation) Flux Density Minimum Expected Maximum Original Estimate (B MAX = 1.7T) Revised Estimate (B MAX = 1.55T) Table 14 Ferndown C1MT, HV winding resistance (mohm) Tap A-N B-N C-N /SSEPD

12 Table 15 Ferndown C1MT, LV winding resistance (mohm) Tap a-n b-n c-n Table 16 Ferndown C1MT, impedance Tap Impedance (%, 12MVA base) Table 17 Ferndown C1MT, Load losses (kw at 12MVA, 75 C reference temperature) Tap Minimum Expected Maximum Table 18 Ferndown C1MT, Load losses (kw at 12MVA, 75 C reference temperature) Tap Works Test Table 19 Ferndown C1MT, No-load losses (kw at rated excitation) Flux Density Minimum Expected Maximum Original Estimate (B MAX = 1.7T) Revised Estimate (B MAX = 1.55T) /SSEPD

13 FIGURES Figure 1 Causeway 33/11kV transformer 3, general view Figure 2 Causeway 33/11kV transformer 3, nameplate /SSEPD

14 Figure Winding Resistance Results for Causeway 33/11kV Transformer A-B A-C B-C Figure 4 Frome C1MT, general view /SSEPD

15 Figure 5 Frome C1MT, nameplate Figure Winding Resistance Results for Frome C1MT A-N B-N C-N /SSEPD

16 Figure 7 Ferndown C1MT, general view Figure Winding Resistance Results for Ferndown C1MT A-N B-N C-N /SSEPD

17 CIRCULATION Doble PowerTest UK Stefan Dragostinov Richard Heywood (File) Scottish and Southern Energy Power Distribution Maciej Fila Sarah Rigby Alistair Steele Copyright Doble PowerTest All rights reserved. No part of this publication may be produced, stored in a retrieval system, or transmitted in any form by any means, electronic, mechanical, photocopying, recording or otherwise, without the prior written permission of Doble. Indemnity This document may not be distributed or used outside the client for whom it is prepared, except with written authorisation from Doble. Doble disclaims all liability for any loss, damage, injury or other consequence whatsoever arising from any unauthorised use howsoever caused, including any such resulting from error, omission or negligence in its application /SSEPD

Transformer Technology Seminar What to consider at Design Reviews

Transformer Technology Seminar What to consider at Design Reviews Pomona CA, May 24-25, 2016 Transformer Technology Seminar Siemens AG Transformers siemens.com/answers Why to perform Design Review Meetings? To ensure both parties having the same understanding of the

More information

TRANSFORMER TECHNOLOGY GPT

TRANSFORMER TECHNOLOGY GPT Core-Form TRANSFORMER TECHNOLOGY GlobalPT Corporation performs research and engineering developments and co-ordination of works of technical partners in the field of technological progress and commercial

More information

APPENDIX 4 TYPICAL LAYOUT, VALUES AND CONSTANTS

APPENDIX 4 TYPICAL LAYOUT, VALUES AND CONSTANTS 109 APPENDIX 4 TYPICAL LAYOUT, VALUES AND CONSTANTS TYPICAL LAYOUT The purpose of a transformer is to transfer energy from the input to the output through the magnetic field. The layout of a partial typical

More information

MGM Transformer. Vacuum Pressure Impregnated (VPI) Dry-Type Substation Transformer Specification Guide

MGM Transformer. Vacuum Pressure Impregnated (VPI) Dry-Type Substation Transformer Specification Guide MGM Transformer Vacuum Pressure Impregnated (VPI) Dry-Type Substation Transformer Specification Guide MGM Transformer Company 5701 Smithway Street Commerce, CA 90040 www.mgmtransformer.com Phone: 323.726.0888

More information

Electrical Design Process

Electrical Design Process Electrical Design Process Jason Varnell Lead Design Engineer Jason.Varnell@spx.com SPX Transformer Solutions, Inc. September 26, 2018 Agenda 1. Bid Design Process Parameters Affecting Bid Design 2. Final

More information

Outcomes from this session

Outcomes from this session Outcomes from this session At the end of this session you should be able to Understand what is meant by the term losses. Iron Losses There are three types of iron losses Eddy current losses Hysteresis

More information

UNIVERSITY OF TECHNOLOGY By: Fadhil A. Hasan ELECTRICAL MACHINES

UNIVERSITY OF TECHNOLOGY By: Fadhil A. Hasan ELECTRICAL MACHINES UNIVERSITY OF TECHNOLOGY DEPARTMENT OF ELECTRICAL ENGINEERING Year: Second 2016-2017 By: Fadhil A. Hasan ELECTRICAL MACHINES І Module-II: AC Transformers o Single phase transformers o Three-phase transformers

More information

MAHARASHTRA STATE BOARD OF TECHNICAL EDUCATION

MAHARASHTRA STATE BOARD OF TECHNICAL EDUCATION Important Instructions to examiners: 1) The answers should be examined by key words and not as word-to-word as given in the model answer scheme. 2) The model answer and the answer written by candidate

More information

POWER TRANSFORMER SPECIFICATION, DESIGN, QUALITY CONTROL AND TESTING 18 MARCH 2009

POWER TRANSFORMER SPECIFICATION, DESIGN, QUALITY CONTROL AND TESTING 18 MARCH 2009 POWER TRANSFORMER SPECIFICATION, DESIGN, QUALITY CONTROL AND TESTING 18 MARCH 2009 Nkosinathi Buthelezi Senior Consultant: Power Transformers and Reactors Presentation Content Standardization of Power

More information

Regional Technical Seminar TAP CHANGERS

Regional Technical Seminar TAP CHANGERS Regional Technical Seminar TAP CHANGERS SPX Transformer Solutions, Inc. September 4, 2018 De-Energized and Load Tap Changers Jason Varnell Lead Design Engineer jason.varnell@spx.com SPX Transformer Solutions,

More information

Transformer Factory Testing

Transformer Factory Testing Transformer Factory Testing John J. Foschia Test Engineer John.Foschia@spx.com September 2018 Reasons for Testing Compliance with user specifications Assessment of quality and reliability Verification

More information

Basic Principles and Operation of Transformer

Basic Principles and Operation of Transformer Basic Principles and Operation of Transformer CONSTRUCTIONAL ASPECTS Cores In order to enhance core s magnetic properties, it is constructed from an iron and silicon mixture (alloy). The magnetic core

More information

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System Company Directive STANDARD TECHNIQUE: SD7F/2 Determination of Short Circuit Duty for Switchgear on the WPD Distribution System Policy Summary This document provides guidance on calculation of fault levels

More information

INVESTIGATION OF ENERGY LOSS IN A TRANSMISSION SUBSTATION USING ONITSHA 330/132KV AS A CASE STUDY F.O. Enemuoh, T.L. Alumona and C.H.

INVESTIGATION OF ENERGY LOSS IN A TRANSMISSION SUBSTATION USING ONITSHA 330/132KV AS A CASE STUDY F.O. Enemuoh, T.L. Alumona and C.H. INVESTIGATION OF ENERGY LOSS IN A TRANSMISSION SUBSTATION USING ONITSHA 330/132KV AS A CASE STUDY F.O. Enemuoh, T.L. Alumona and C.H. Aliche 1,2 nnamdi azikiwe university, awka, anambra state, nigeria.

More information

Particulate Control O&M Training. APC/PCUG Conference July 12-16, 2009 The Woodlands, TX

Particulate Control O&M Training. APC/PCUG Conference July 12-16, 2009 The Woodlands, TX Particulate Control O&M Training APC/PCUG Conference July 12-16, 2009 The Woodlands, TX WPCA Particulate Training Seminar July 11, 2009 ESP Power Supply Choices Slide No 1 Precipitator Power Supplies Conventional

More information

A Glance into the Future of Transformers and Beyond

A Glance into the Future of Transformers and Beyond A Glance into the Future of Transformers and Beyond Pat Bodger and Wade Enright Department of Electrical and Computer Engineering University of Canterbury, Christchurch Abstract: An overview of the research

More information

Calculating and compensating for power transformer and cable (or line) losses - standard methods

Calculating and compensating for power transformer and cable (or line) losses - standard methods Guidance Calculating and compensating for power transformer and cable (or line) losses - standard methods Foreword This guidance sets out basic standard methods for calculating electrical loss compensation

More information

Effects of Harmonic Distortion I

Effects of Harmonic Distortion I Effects of Harmonic Distortion I Harmonic currents produced by nonlinear loads are injected back into the supply systems. These currents can interact adversely with a wide range of power system equipment,

More information

SPECIFICATION FOR STEP UP TRANSFORMER 0.415/11Kv and (630KVA & 1000KVA)

SPECIFICATION FOR STEP UP TRANSFORMER 0.415/11Kv and (630KVA & 1000KVA) SPECIFICATION FOR STEP UP TRANSFORMER 0.415/11Kv and (630KVA & 1000KVA) 0.415/33kV DESIGN AND CONSTRUCTION General 1. The transformer shall be three phase, oil immersed type, air cooled, core type, outdoor

More information

Title Substation Auxiliary Transformer from Rectifier Transformer Secondary. Reference Number PDS 01 (RIC Standard: EP SP)

Title Substation Auxiliary Transformer from Rectifier Transformer Secondary. Reference Number PDS 01 (RIC Standard: EP SP) Discipline Engineering Standard NSW Category Electrical Title Substation Auxiliary Transformer from Rectifier Transformer Secondary Reference Number PDS 01 (RIC Standard: EP 05 00 00 01 SP) Document Control

More information

GE Ventilated Dry-Type Transformers. Secondary Substation Transformers - 5 and 15kV Class

GE Ventilated Dry-Type Transformers. Secondary Substation Transformers - 5 and 15kV Class GE Ventilated Dry-Type Transformers Secondary Substation Transformers - 5 and 15kV Class GE ventilated dry-type transformers are designed for indoor or outdoor applications in schools, hospitals, industrial

More information

Trade of Electrician. The Transformer

Trade of Electrician. The Transformer Trade of Electrician Standards Based Apprenticeship The Transformer Phase 2 Module No. 2.1 Unit No. 2.1.10 COURSE NOTES Created by Gerry Ryan - Galway TC Revision 1 April 2000 by Gerry Ryan - Galway TC

More information

DIRECT CURRENT COMPENSATION FIELD EXPERIENCE UNDER SERVICE CONDITIONS

DIRECT CURRENT COMPENSATION FIELD EXPERIENCE UNDER SERVICE CONDITIONS Journal of Energy VOLUME 63 2014 journal homepage: http://journalofenergy.com/ Helfried Passath Siemens AG Österreich Transformers Weiz helfried.passath@siemens.com Peter Hamberger Siemens AG Österreich

More information

Introduction : Design detailed: DC Machines Calculation of Armature main Dimensions and flux for pole. Design of Armature Winding & Core.

Introduction : Design detailed: DC Machines Calculation of Armature main Dimensions and flux for pole. Design of Armature Winding & Core. Introduction : Design detailed: DC Machines Calculation of Armature main Dimensions and flux for pole. Design of Armature Winding & Core. Design of Shunt Field & Series Field Windings. Design detailed:

More information

Validation of a Power Transformer Model for Ferroresonance with System Tests on a 400 kv Circuit

Validation of a Power Transformer Model for Ferroresonance with System Tests on a 400 kv Circuit Validation of a Power Transformer Model for Ferroresonance with System Tests on a 4 kv Circuit Charalambos Charalambous 1, Z.D. Wang 1, Jie Li 1, Mark Osborne 2 and Paul Jarman 2 Abstract-- National Grid

More information

Problems connected with Commissioning of Power Transformers

Problems connected with Commissioning of Power Transformers Problems connected with Commissioning of Power Transformers ABSTRACT P Ramachandran ABB India Ltd, Vadodara, India While commissioning large Power Transformers, certain abnormal phenomena were noticed.

More information

Electrical Protection System Design and Operation

Electrical Protection System Design and Operation ELEC9713 Industrial and Commercial Power Systems Electrical Protection System Design and Operation 1. Function of Electrical Protection Systems The three primary aims of overcurrent electrical protection

More information

PES & IAS NY Chapter And NY LMAG June 23 rd, 2015

PES & IAS NY Chapter And NY LMAG June 23 rd, 2015 PES & IAS NY Chapter And NY LMAG June 23 rd, 2015 High Temperature Insulation Systems and their use in Mobile Transformers Myron B. Bell, PE mbell@deltastar.com Delta Star, Inc. June 23 rd 2015 Introduction

More information

3. What is hysteresis loss? Also mention a method to minimize the loss. (N-11, N-12)

3. What is hysteresis loss? Also mention a method to minimize the loss. (N-11, N-12) DHANALAKSHMI COLLEGE OF ENGINEERING, CHENNAI DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING EE 6401 ELECTRICAL MACHINES I UNIT I : MAGNETIC CIRCUITS AND MAGNETIC MATERIALS Part A (2 Marks) 1. List

More information

Loss prophet. Predicting stray losses in power transformers and optimization of tank shielding using FEM

Loss prophet. Predicting stray losses in power transformers and optimization of tank shielding using FEM Loss prophet Predicting stray losses in power transformers and optimization of tank shielding using FEM JANUSZ DUC, BERTRAND POULIN, MIGUEL AGUIRRE, PEDRO GUTIERREZ Optimization of tank shielding is a

More information

(2) New Standard IEEE P (3) Core : (4) Windings :

(2) New Standard IEEE P (3) Core : (4) Windings : (d) Electrical characteristics (such as short-circuit withstand, commutating reactance, more number of windings, etc); (e) Longer life expectancy; (f) Energy efficiency; (g) more demanding environment.

More information

TRANSFORMERS PART A. 2. What is the turns ratio and transformer ratio of transformer? Turns ratio = N2/ N1 Transformer = E2/E1 = I1/ I2 =K

TRANSFORMERS PART A. 2. What is the turns ratio and transformer ratio of transformer? Turns ratio = N2/ N1 Transformer = E2/E1 = I1/ I2 =K UNIT II TRANSFORMERS PART A 1. Define a transformer? A transformer is a static device which changes the alternating voltage from one level to another. 2. What is the turns ratio and transformer ratio of

More information

MAHARASHTRA STATE BOARD OF TECHNICAL EDUCATION

MAHARASHTRA STATE BOARD OF TECHNICAL EDUCATION Important Instructions to examiners: 1) The answers should be examined by key words and not as word-to-word as given in the model answer scheme. 2) The model answer and the answer written by candidate

More information

Silent Transformers to Help Consolidated Edison Meet New York City s Ultrastrict Noise Ordinances

Silent Transformers to Help Consolidated Edison Meet New York City s Ultrastrict Noise Ordinances BY DR. RAMSIS GIRGIS, ABB INC. The Sound of Silence: Silent Transformers to Help Consolidated Edison Meet New York City s Ultrastrict Noise Ordinances S ilence is a source of great strength. Although these

More information

HOW TO SAFE GUARD THE TRANSFORMER..???

HOW TO SAFE GUARD THE TRANSFORMER..??? CPRI HOW TO SAFE GUARD THE TRANSFORMER..??? CPRI Efficient and Effective network planning, Design and Forecasting Highly Reliable and Stable Protection system and co-ordination Measures to mitigate various

More information

Effects of GIC on Power Transformers and Power Systems

Effects of GIC on Power Transformers and Power Systems Effects of GIC on Power Transformers and Power Systems Prepared by Dr. Ramsis Girgis and Kiran Vedante (USA) in the name of CIGRE SC A2 Background There has been some misconception in the electric power

More information

G. KOBET, I. GRANT, G. GOZA Tennessee Valley Authority USA. R. GIRGIS, M. ESPINDOLA ABB Corporation USA SUMMARY

G. KOBET, I. GRANT, G. GOZA Tennessee Valley Authority USA. R. GIRGIS, M. ESPINDOLA ABB Corporation USA SUMMARY 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium Assessment of the Impact of GMD on the TVA 500 kv Grid & Power Transformers Part II:

More information

Walchand Institute of Technology. Basic Electrical and Electronics Engineering. Transformer

Walchand Institute of Technology. Basic Electrical and Electronics Engineering. Transformer Walchand Institute of Technology Basic Electrical and Electronics Engineering Transformer 1. What is transformer? explain working principle of transformer. Electrical power transformer is a static device

More information

148 Electric Machines

148 Electric Machines 148 Electric Machines 3.1 The emf per turn for a single-phase 2200/220- V, 50-Hz transformer is approximately 12 V. Calculate (a) the number of primary and secondary turns, and (b) the net cross-sectional

More information

Group F : Sl. No. - 1) 33/0.403 KV, 100 KVA Station Transformer GUARANTEED & OTHER TECHNICAL PARTICULARS. Table : A

Group F : Sl. No. - 1) 33/0.403 KV, 100 KVA Station Transformer GUARANTEED & OTHER TECHNICAL PARTICULARS. Table : A Group F : No. - 1) 33/0.403 KV, 100 KVA Station Transformer GUARANTEED & OTHER TECHNICAL PARTICULARS Table : A No. Description 1. Make & Manufacturer 2. Place of Manufacturer 3. Voltage Ratio 4. Rating

More information

CHAPTER 8 Effect of HT Distribution Feeder Voltage on Distribution Transformer Losses

CHAPTER 8 Effect of HT Distribution Feeder Voltage on Distribution Transformer Losses CHAPTER 8 Effect of HT Distribution Feeder Voltage on Distribution Transformer Losses 8.1 Introduction The present level of Transmission and Distribution (T & D) losses in Indian power system is estimated

More information

The Advantages and Application of Three Winding Transformers

The Advantages and Application of Three Winding Transformers The Advantages and Application of Three Winding Transformers MSc, CEng, FIEE, FIMechE, FIPENZ Principal, Sinclair Knight Merz Abstract Although seldom used in Australia and New Zealand, three winding transformers

More information

CHAPTER 3 REVIEW OF POWER TRANSFORMER PROTECTION SCHEMES

CHAPTER 3 REVIEW OF POWER TRANSFORMER PROTECTION SCHEMES CHAPTER 3 REVIEW OF POWER TRANSFORMER PROTECTION SCHEMES 3.1. Introduction Power Transformer is the nerve centre of any power distribution system. The capacity of power transformers is generally decided

More information

MODERN POWER TRANSFORMER PRACTICE BIBLIOGRAPHY

MODERN POWER TRANSFORMER PRACTICE BIBLIOGRAPHY 354 BIBLIOGRAPHY MODERN POWER TRANSFORMER PRACTICE Bolton, D. J., Electrical Engineering Economics, Chapman and Hall, London, 2nd edn (1936) Brownsey, C. M., 'The Problem of Noise with Particular Reference

More information

Transformer & Induction M/C

Transformer & Induction M/C UNIT- 2 SINGLE-PHASE TRANSFORMERS 1. Draw equivalent circuit of a single phase transformer referring the primary side quantities to secondary and explain? (July/Aug - 2012) (Dec 2012) (June/July 2014)

More information

HTS PARTIAL CORE TRANSFORMER- FAULT CURRENT LIMITER

HTS PARTIAL CORE TRANSFORMER- FAULT CURRENT LIMITER EEA CONFERENCE & EXHIBITION 2013, 19-21 JUNE, AUCKLAND HTS PARTIAL CORE TRANSFORMER- FAULT CURRENT LIMITER JIT KUMAR SHAM*, UNIVERSITY OF CANTERBURY, CHRISTCHURCH, NEW ZEALAND PROF. PAT BODGER, UNIVERSITY

More information

S C Strength of Winding Exits and Leads : A critical area for Failure Prevention in Power Transformers

S C Strength of Winding Exits and Leads : A critical area for Failure Prevention in Power Transformers S C Strength of Winding Exits and Leads : A critical area for Failure Prevention in Power Transformers by MANAN PANDYA SIEMENS LTD. manan.pandya@siemens.com 1 Introduction Short circuit withstand capability

More information

Stray Losses in Transformer Clamping Plate

Stray Losses in Transformer Clamping Plate 325 1 Stray Losses in Transformer Clamping Plate Zarko Janic, Zvonimir Valkovic and Zeljko Stih Abstract Stray losses in transformer clamping plate can be a considerable part of the overall stray loss

More information

Collection of standards in electronic format (PDF) 1. Copyright

Collection of standards in electronic format (PDF) 1. Copyright Collection of standards in electronic format (PDF) 1. Copyright This standard is available to staff members of companies that have subscribed to the complete collection of SANS standards in accordance

More information

Hours / 100 Marks Seat No.

Hours / 100 Marks Seat No. 17415 15162 3 Hours / 100 Seat No. Instructions (1) All Questions are Compulsory. (2) Answer each next main Question on a new page. (3) Illustrate your answers with neat sketches wherever necessary. (4)

More information

GOVERNMENT COLLEGE OF ENGINEERING, BARGUR

GOVERNMENT COLLEGE OF ENGINEERING, BARGUR 1. Which of the following is the major consideration to evolve a good design? (a) Cost (b) Durability (c) Compliance with performance criteria as laid down in specifications (d) All of the above 2 impose

More information

Liquid-Filled Transformers

Liquid-Filled Transformers Liquid-Filled Transformers Custom Transformers at Standard Prices NIAGARA TRANSFORMER CORP. Induction Furnace Transformer Cycloconverter Rectifier Duty Transformer Arc Furnace Transformer Full Range of

More information

EEE3441 Electrical Machines Department of Electrical Engineering. Lecture. Basic Operating Principles of Transformers

EEE3441 Electrical Machines Department of Electrical Engineering. Lecture. Basic Operating Principles of Transformers Department of Electrical Engineering Lecture Basic Operating Principles of Transformers In this Lecture Basic operating principles of following transformers are introduced Single-phase Transformers Three-phase

More information

SOUTHERN ELECTRICITY SUPPLY COMPANY OF ODISHA LIMITED (SOUTHCO UTILITY)

SOUTHERN ELECTRICITY SUPPLY COMPANY OF ODISHA LIMITED (SOUTHCO UTILITY) E -Tender Notice No. Annexure - VII SOUTHCO/DEPOSIT/3.15 & 5 MVA Power Transformer /02/2015 16 Dt. 02.03.2016 NAME OF THE WORK PROCUREMENT OF33/11 KV, 3.15 MVA & 5 MVA Power Transformer SUPPLIER INFORMATION

More information

Code No: R Set No. 1

Code No: R Set No. 1 Code No: R05310204 Set No. 1 III B.Tech I Semester Regular Examinations, November 2007 ELECTRICAL MACHINES-III (Electrical & Electronic Engineering) Time: 3 hours Max Marks: 80 Answer any FIVE Questions

More information

The power transformer

The power transformer ELEC0014 - Introduction to power and energy systems The power transformer Thierry Van Cutsem t.vancutsem@ulg.ac.be www.montefiore.ulg.ac.be/~vct November 2017 1 / 35 Power transformers are used: to transmit

More information

PROBLEMS on Transformers

PROBLEMS on Transformers PROBLEMS on Transformers (A) Simple Problems 1. A single-phase, 250-kVA, 11-kV/415-V, 50-Hz transformer has 80 turns on the secondary. Calculate (a) the approximate values of the primary and secondary

More information

K Factor Power Transformers

K Factor Power Transformers Ashley-Edison AsiaElectricTransformers (UK) K Factor Power Transformers DTKF series Low Voltage Dry Type K Factor Power Transformers AET-DTKF-2004-01: Page 1 Asia Electric Transformers, Entrepreneur Business

More information

Insulation Level and Test Technology of. 1000kV Power Transformer

Insulation Level and Test Technology of. 1000kV Power Transformer Insulation Level and Test Technology of 1000kV Power Transformer Li Guangfan, Wang Xiaoning, Li Peng et al HIMALAYAL - SHANGHAI - CHINA Abstract: The insulation coordination for the first 1000kV UHVAC

More information

Single & Three Phase Transformers SAMPLE. Learner Workbook. Version 1. Training and Education Support Industry Skills Unit Meadowbank

Single & Three Phase Transformers SAMPLE. Learner Workbook. Version 1. Training and Education Support Industry Skills Unit Meadowbank Single & Three Phase Transformers Learner Workbook Version 1 Training and Education Support Industry Skills Unit Meadowbank Product Code: 5634 Table of Contents Introduction... 5 Section 1. Transformer

More information

Single-Phase Transformation Review

Single-Phase Transformation Review Single-Phase Transformation Review S T U D E N T M A N U A L March 2, 2005 2 STUDENT TRAINING MANUAL Prerequisites: None Objectives: Given the Construction Standards manual and a formula sheet, you will

More information

Transformer Protection

Transformer Protection Transformer Protection Nature of transformer faults TXs, being static, totally enclosed and oil immersed develop faults only rarely but consequences large. Three main classes of faults. 1) Faults in Auxiliary

More information

Picture perfect. Electromagnetic simulations of transformers

Picture perfect. Electromagnetic simulations of transformers 38 ABB review 3 13 Picture perfect Electromagnetic simulations of transformers Daniel Szary, Janusz Duc, Bertrand Poulin, Dietrich Bonmann, Göran Eriksson, Thorsten Steinmetz, Abdolhamid Shoory Power transformers

More information

Reduction stray loss on transformer tank wall with optimized widthwise electromagnetic shunts

Reduction stray loss on transformer tank wall with optimized widthwise electromagnetic shunts Reduction stray loss on transformer tank wall with optimized widthwise electromagnetic shunts Atabak Najafi 1, Okan Ozgonenel, Unal Kurt 3 1 Electrical and Electronic Engineering, Ondokuz Mayis University,

More information

Transformer Thermal Impact Assessment White Paper TPL Transmission System Planned Performance for Geomagnetic Disturbance Events

Transformer Thermal Impact Assessment White Paper TPL Transmission System Planned Performance for Geomagnetic Disturbance Events Transformer Thermal Impact Assessment White Paper TPL-007-2 Transmission System Planned Performance for Geomagnetic Disturbance Events Background Proposed TPL 007 2 includes requirements for entities to

More information

EI HIGH VOLTAGE INSULATION TESTING POLICY

EI HIGH VOLTAGE INSULATION TESTING POLICY Network(s): Summary: ENGINEERING INSTRUCTION EI 09-0001 HIGH VOLTAGE INSULATION TESTING POLICY EPN, LPN, SPN This engineering instruction details the policy for the on-site insulation testing of new and

More information

Evaluating Transformer Heating due to Geomagnetic Disturbances

Evaluating Transformer Heating due to Geomagnetic Disturbances Evaluating Transformer Heating due to Geomagnetic Disturbances Presented by: Brian Penny, American Transmission Company 53 rd Annual Minnesota Power Systems Conference November 7, 2017 atcllc.com Presentation

More information

nical catalogue Tech

nical catalogue Tech Technical catalogue About Etra 33 has been acting as transformer manufacturer over more than 75 years. Specializing in the manufacturing of power transformers rating up to 500 MVA and 420 kv the company

More information

Power Transformers Basics

Power Transformers Basics Power Transformers Basics Transformer Basic Objective Introduce Basic Transformer Theory as it Relates to Diagnostics Provide a Better Understanding of the Diagnostic Test Environment Identify Important

More information

Power transformers. Shunt reactors Proven history for future success

Power transformers. Shunt reactors Proven history for future success Power transformers Shunt reactors Proven history for future success Shunt reactors an investment for today and for the future 2 Shunt reactors Improving power quality and reducing transmission costs Shunt

More information

Transformer Thermal Impact Assessment White Paper Project (Geomagnetic Disturbance Mitigation)

Transformer Thermal Impact Assessment White Paper Project (Geomagnetic Disturbance Mitigation) Transformer Thermal Impact Assessment White Paper Project 2013-03 (Geomagnetic Disturbance Mitigation) TPL-007-1 Transmission System Planned Performance for Geomagnetic Disturbance Events Background On

More information

A Thyristor Controlled Three Winding Transformer as a Static Var Compensator

A Thyristor Controlled Three Winding Transformer as a Static Var Compensator Abstract: A Thyristor Controlled Three Winding Transformer as a Static Var Compensator Vijay Bendre, Prof. Pat Bodger, Dr. Alan Wood. Department of Electrical and Computer Engineering, The University of

More information

APPLICATION NOTE - 018

APPLICATION NOTE - 018 APPLICATION NOTE - 018 Power Transformers Background Power Transformers are used within an AC power distribution systems to increase or decrease the operating voltage to achieve the optimum transmission

More information

PRELIMINARIES. Generators and loads are connected together through transmission lines transporting electric power from one place to another.

PRELIMINARIES. Generators and loads are connected together through transmission lines transporting electric power from one place to another. TRANSMISSION LINES PRELIMINARIES Generators and loads are connected together through transmission lines transporting electric power from one place to another. Transmission line must, therefore, take power

More information

No. of Printed Pages : 5 ADVANCED LEVEL CERTIFICATE COURSE IN ELECTRICAL ENGINEERING / DIPLOMA IN ELECTRICAL ENGINEERING / ACELVI / DELVI

No. of Printed Pages : 5 ADVANCED LEVEL CERTIFICATE COURSE IN ELECTRICAL ENGINEERING / DIPLOMA IN ELECTRICAL ENGINEERING / ACELVI / DELVI No. of Printed Pages : 5 BIEE-027 ADVANCED LEVEL CERTIFICATE COURSE IN ELECTRICAL ENGINEERING / DIPLOMA IN ELECTRICAL ENGINEERING / ACELVI / DELVI 00969 Term-End Examination June, 2012 BIEE-027 : ELECTRICAL

More information

HV AC TESTING OF SUPER-LONG CABLES

HV AC TESTING OF SUPER-LONG CABLES HV AC TESTING OF SUPER-LONG CABLES Stefan SCHIERIG, (Germany), schierig@highvolt.de Peter COORS, (Germany), coors@highvolt.de Wolfgang HAUSCHILD, IEC, CIGRE, (Germany), hauschild@highvolt.de ABSTRACT The

More information

Generator Users Group Annual Conference Core testing, low and high flux, tap. Mladen Sasic, IRIS Power

Generator Users Group Annual Conference Core testing, low and high flux, tap. Mladen Sasic, IRIS Power Generator Users Group Annual Conference 2015 Core testing, low and high flux, tap Mladen Sasic, IRIS Power Stator Cores Cores provide low reluctance paths for working magnetic fluxes Support stator winding,

More information

CHAPTER 2 ELECTROMAGNETIC FORCE AND DEFORMATION

CHAPTER 2 ELECTROMAGNETIC FORCE AND DEFORMATION 18 CHAPTER 2 ELECTROMAGNETIC FORCE AND DEFORMATION 2.1 INTRODUCTION Transformers are subjected to a variety of electrical, mechanical and thermal stresses during normal life time and they fail when these

More information

Ferroresonance Experience in UK: Simulations and Measurements

Ferroresonance Experience in UK: Simulations and Measurements Ferroresonance Experience in UK: Simulations and Measurements Zia Emin BSc MSc PhD AMIEE zia.emin@uk.ngrid.com Yu Kwong Tong PhD CEng MIEE kwong.tong@uk.ngrid.com National Grid Company Kelvin Avenue, Surrey

More information

ECP HV INSULATION TESTING

ECP HV INSULATION TESTING Document Number: ECP 11-0006 Network(s): Summary: All ENGINEERING COMMISSIONING PROCEDURE ECP 11-0006 HV INSULATION TESTING This standard details the policy for the on-site insulation testing of new and

More information

Magnetization System of Magnetically Controlled Shunt Reactors

Magnetization System of Magnetically Controlled Shunt Reactors Magnetization System of Magnetically Controlled Shunt Reactors Leonid Kontorovych, Technical Director of ZTR PJSC, PH.D. in Engineering Sciences; Igor Shyrokov, head of the department of reactors control

More information

BVM Systems Limited. PQSensor MkIII Installation & Commissioning Manual - 1 -

BVM Systems Limited. PQSensor MkIII Installation & Commissioning Manual - 1 - BVM Systems BVM Systems Limited PQSensor MkIII Installation & Commissioning Manual Patents: 1295133, 6,919,717 BVM Systems LImited 21 Springvale Road Gilford Craigavon BT63 6EB United Kingdom Email: -

More information

Specialists in HV and MV test and diagnostics. Testing in Substations

Specialists in HV and MV test and diagnostics. Testing in Substations Specialists in HV and MV test and diagnostics Testing in Substations Testing in Substations Testing in Substations At 4fores we specialize in the diagnosis and measurement of all types of existing technologies

More information

Phase Shifter Application Workshop. Siemens Energy, Inc.

Phase Shifter Application Workshop. Siemens Energy, Inc. Phase Shifter Application Workshop Siemens Energy, Inc. PJM Power Pool, March, 2015 siemens.com/energy Phase Shifter Application Workshop Phase Shifting Transformers Principles, Design Aspects and Operation

More information

Shunt Reactors. Global Top Energy, Machinery & Plant Solution Provider

Shunt Reactors. Global Top Energy, Machinery & Plant Solution Provider Shunt Reactors Global Top Energy, Machinery & Plant Solution Provider Our Business Brief introduction of Hyosung Power & Industrial Systems PG While Hyosung is an established name for world-class electrical

More information

Effective Magnetic Shielding in Electric Arc Furnace Transformers Using Interphase Wall Shunts

Effective Magnetic Shielding in Electric Arc Furnace Transformers Using Interphase Wall Shunts Effective Magnetic Shielding in Electric Arc Furnace Transformers Using Interphase Wall Shunts Masood Moghaddami 1, Arif I. Sarwat 1 1 Department of Electrical and Computer Engineering, Florida International

More information

ISSN: X Impact factor: (Volume 3, Issue 6) Available online at Modeling and Analysis of Transformer

ISSN: X Impact factor: (Volume 3, Issue 6) Available online at   Modeling and Analysis of Transformer ISSN: 2454-132X Impact factor: 4.295 (Volume 3, Issue 6) Available online at www.ijariit.com Modeling and Analysis of Transformer Divyapradeepa.T Department of Electrical and Electronics, Rajalakshmi Engineering

More information

Keywords: Overvoltage Suppression, Shunt Reactor, Loss Reduction, Regulate Voltage Level, Reactive Power Balance.

Keywords: Overvoltage Suppression, Shunt Reactor, Loss Reduction, Regulate Voltage Level, Reactive Power Balance. www.semargroup.org, www.ijsetr.com ISSN 2319-8885 Vol.03,Issue.11 June-2014, Pages:2481-2486 Design of 25 MVA Shunt Reactor for 230 kv Transmission Line HSU MON AUNG 1, DR. MIN MIN OO 2 1 Dept of Electrical

More information

Transformer Thermal Impact Assessment White Paper (Draft) Project (Geomagnetic Disturbance Mitigation)

Transformer Thermal Impact Assessment White Paper (Draft) Project (Geomagnetic Disturbance Mitigation) Transformer Thermal Impact Assessment White Paper (Draft) Project 2013-03 (Geomagnetic Disturbance Mitigation) TPL-007-1 Transmission System Planned Performance during Geomagnetic Disturbances Background

More information

KNOW MORE ABOUT THE TRANSFORMERS. Glossary Transformers

KNOW MORE ABOUT THE TRANSFORMERS. Glossary Transformers KNOW MORE ABOUT THE TRANSFORMERS Glossary Transformers Ambient temperature The existing temperature of the atmosphere surrounding a transformer installation. Ampere The practical unit of electric current.

More information

TMC Transformers TMC

TMC Transformers TMC TMC Product & Technology Presentation Cast Resin Transformer (CRT) History Cast resin transformers first appeared in Germany during the 1960s. This new style of dry type transformer was developed with

More information

1. THREE-PHASE TRANSFORMER. SHORT CIRCUIT TEST

1. THREE-PHASE TRANSFORMER. SHORT CIRCUIT TEST 1. THREE-PHASE TRANSFORMER. SHORT CIRCUIT TEST 1.1 INTRODUCTION. DESCRIPTION OF THE EXPERIMENT The short-circuit test consists of measuring the input quantities of the transformer when its secondary winding

More information

Transformers. gpmacademics.weebly.com

Transformers. gpmacademics.weebly.com TRANSFORMERS Syllabus: Principles of operation, Constructional Details, Losses and efficiency, Regulation of Transformer, Testing: OC & SC test. TRANSFORMER: It is a static device which transfers electric

More information

ELECTRICAL ENGINEERING ESE TOPIC WISE OBJECTIVE SOLVED PAPER-II

ELECTRICAL ENGINEERING ESE TOPIC WISE OBJECTIVE SOLVED PAPER-II ELECTRICAL ENGINEERING ESE TOPIC WISE OBJECTIVE SOLVED PAPER-II From (1992 2017) Office : F-126, (Lower Basement), Katwaria Sarai, New Delhi-110016 Phone : 011-26522064 Mobile : 8130909220, 9711853908

More information

DISTRIBUTION TRANSFORMERS

DISTRIBUTION TRANSFORMERS The University of New South Wales School of Electrical Engineering and Telecommunications Industrial and Commercial Power Systems Topic 4 DISTRIBUTION TRANSFORMERS A transformer is a static device that

More information

Alternative Testing Techniques for Current Transformers. Dinesh Chhajer, PE Technical Support Group MEGGER

Alternative Testing Techniques for Current Transformers. Dinesh Chhajer, PE Technical Support Group MEGGER Alternative Testing Techniques for Current Transformers Dinesh Chhajer, PE Technical Support Group MEGGER Agenda Current Transformer Definition and Fundamentals Current Transformer Applications o Metering

More information

Reduction in Load (Copper) loss Due to Overhauling of Power Transformer or OLTC

Reduction in Load (Copper) loss Due to Overhauling of Power Transformer or OLTC Reduction in Load (Copper) loss Due to Overhauling of Power Transformer or OLTC by Neeraj Khare BSES RAJDHANI POWER LTD. Neeraj.khare@relianceada.com, Khareneeraj974@gmail.com, BSES Rajdhani Power Limited

More information

Transformer Winding Design. The Design and Performance of Circular Disc, Helical and Layer Windings for Power Transformer Applications

Transformer Winding Design. The Design and Performance of Circular Disc, Helical and Layer Windings for Power Transformer Applications The Design and Performance of Circular Disc, Helical and Layer Windings for Power Transformer Applications Minnesota Power Systems Conference November 3 5, 2009 Earl Brown Heritage Center University of

More information

Notes 1: Introduction to Distribution Systems

Notes 1: Introduction to Distribution Systems Notes 1: Introduction to Distribution Systems 1.0 Introduction Power systems are comprised of 3 basic electrical subsystems. Generation subsystem Transmission subsystem Distribution subsystem The subtransmission

More information