The Legal Frame for the Use of Offshore Wind Energy in Germany

Size: px
Start display at page:

Download "The Legal Frame for the Use of Offshore Wind Energy in Germany"

Transcription

1 The Legal Frame for the Use of Offshore Wind Energy in Germany Which kind of legal frame is needed in the Baltic States? 3 rd seminar on EIA for offshore wind farms vis-à-vis Natura2000 and other land uses Riga, Lettland 15./16. April 2009 RA in Dr. Ursula Prall

2 I. The status of offshore wind farms in Germany 1. Situation and history of the development Objective in MW electric power to be installed by 2030, using a step by step-approach: : preparation phase : at least 500 MW : to MW : to MW Things went differently legal framework was not ready to cope with project developers activity: Relevant ordinance supplied only the essential requirements for occasional structures project developing was free from constrictions situation speaks for itself BSH started developing a high standard of concretising and closing gaps in legislation designed for single, not hundreds of structures environmental standards were developed in cooperation with authorities competent for nature protection; sensitive areas were identified and research on the effects on the maritime environment started methods for risk analyses were developed and harmonised.

3 I. The status of offshore wind farms in Germany (North Sea/BSH) 3

4 I. The status of offshore wind farms in Germany (Baltic Sea/BSH) 4

5 I. The status of offshore wind farms in Germany 2. Why are there not yet any offshore wind farms built in Germany? Conditions Unlike other European countries, offshore wind farms are planned in distances of often more than 100km from the shore, in water depths of 20 to 40m. These conditions are more demanding than in UK or Denmark. Scarcity of components Because of these difficult conditions, installation and operation is more cost intensive which means that 5MW turbines shall be used. Such turbines are still in the prototype status, and most other components are scarce as well (situation improves only now). Insufficient incentive Until the beginning of 2009, the incentive was too low; installation and operation would not have been profitable. This has been substantially improved. No licensed grid connections Only were few offshore wind farms have a licensed grid connection (which is not yet built). 5

6 I. The status of offshore wind farms in Germany 3. Conclusions The use of offshore wind energy in Germany is not yet a story of success. But there is reason to hope that this will change in the very near future, and preparation has certainly been thorough. The length of the preparation process shows how much more is to be done than was reckoned with in the earlier stages. It makes sense to consider these experiences. Not all experiences, conclusions and achievements are applicable everywhere else. They cannot be transferred to another situation without examination of their applicability. 6

7 II. Why should an offshore wind farm be built? 1. Expensive projects binding EU targets Expensive projects 80 turbines with an electric power of 5MW cost more than 1 billion Euros. This does not include grid connection. Using a new technology in a rough environment with difficult operation and maintenance conditions is risky. Binding EU targets on the use of RES by 2020 Latvia: 40% (2005: 32.6%) Estonia: 25% (2005: 18%) Lithunia: 23% (2005: 15%) Consequence: It is necessary to make the use of RES happen. 7

8 II. Why should an offshore wind farm be built? 2. Options for action Feed-in tariffs: fixed, above-market price for each generated kwh incentive for potential operators obligation for transmission/distribution system operator Quota system: obligation of using a fixed quantity of RES obligation for either system operator, consumer, or producer to transmit, use or produce a minimum quantity of RES electricity price is subject to the market No harmonised promotion system on EU level 8

9 II. Why should an offshore wind farm be built? 3. How is it done in Germany? a) Feed-in tariffs (1) Erneuerbare Energien-Gesetz (EEG; Renewable Energy Sources Act) EEG entered into force in 1990 and was very substantially amended every four years (last version entered into force on Januar 1 st 2009), adjusting, inter alia, the objective and feed-in tariffs. Objectives provide for sustainable development of energy supply reduce economic costs of energy supply by internalising external costs promote the development of relevant technologies spare fossil energy resources 30% of all electriciy shall be RES based by 2020 and shall continue to increase afterwards (EEG 2004: 12.5% until 2010 and 20% in 2020) Instruments guaranteed grid acces and guaranteed transmission; obligation of grid extension guaranteed above-market price for twenty years price differs from source to source, in accordance with technological status. difference to market price can be passed on to consumers 9

10 II. Why should an offshore wind farm be built? 3. How is it done in Germany? a) Feed-in tariffs (2) Feed-in tariffs for offshore wind energy 15 Ct/kWh for the first twelve years if an offshore wind turbine starts operating before 2016 ( incentive for accelerating realisation) 13 Ct/kWh for the first twelve years if a turbine starts operating in 2016 or later 3.5 Ct/kWh for another eight years ( high tariff in the beginning is more important than a middling one over a longer period) 15 or 13 Ct/kWh for an additional 1.7 months for each additional meter of water depth starting at 20m 13 or 15 Ct/kW for an additional 0.5 month for each additional mile of distance from the shore, starting at 12 nm ( no incentive, but compensation for difficult conditions and extra costs for installation and operation & maintenance) no fixed, above-market price for wind farms situated in a Natura2000-area ( negative incentive) if a wind farm starts operating in 2015 or later, a degression of 5% of the relevant tariff applies ( incentive for acceleration, but also aligning costs to developments) 10

11 II. Why should an offshore wind farm be built? 3. How is it done in Germany? b) Grid connection to be supplied by TSO Until end of 2006 grid connection was the responsibility of each wind farm project developer/operator additional investment of 25% - 40%, depending on distance more environmental impact by numerous sea cables less cost-efficiency Since end of 2006 responsibility of transmission system operators costs can be passed on to consumer bundling of cables: less environmental impact and more cost-efficiency (2009) problematic move ( VI.) 11

12 II. Why should an offshore wind farm be built? 4. Conclusions feed-in tariffs are a highly successful instrument for promoting the use of RES, by establishing a reliable incentive. The system has been copied in many other countries; it is widely held to be the best instrument. quota systems might make sense if it is necessary to initialise the use of RES. As an incentive, it is not as reliable as a feed-in tariff. studies show that electricity prices tend to rise more if a quota system is used. political question, not a legal one. 12

13 III. Where should an offshore wind farm be built? 1. Conflicting interests Other interests navigation marine environment/nature conservation fishery air traffic military landscape/tourism existing structures (cables; pipelines) sand and gravel excavation EU legal frame Habitat Directive 1992/43/EEC Bird Directive 1979/409/EEC EIA Directive 1985/337/EEC SEA Directive 2001/42/EC (all as amended) 13

14 III. Where should an offshore wind farm be built? 2. Options for action Decision in each single case location is choice of the applicant, the competent authority has to decide in each single case without any additional guidance as to the suitability of the location Identification of no-go-areas finding areas that should by all means be kept free of structures, such as Natura2000-areas or areas with dense traffic Identification of "go-areas" finding areas that are particularly suitable because of little potential for conflicts Comprehensive spatial planning prepare comprehensive spatial planning and balancing all interests 14

15 III. Where should an offshore wind farm be built? 3. How is it done in Germany? (1) no formal provisions traffic routes were known but not formalised sensitive areas were half-known but not affirmed and not formally protected structures and excavation areas were known locations were intensively discussed between applicant and BSH and projects were limited to 80 WTG, so gross errors were mostly avoided September 2005: Nature conservation areas areas that should be part of Natura2000 were notified to Brussels, covering some 30% of the German EEZ ( applicability of Art. 6 Habitat Dir.) negative incentive (no fixed tariff) started working guidance as to where not to plan an offshore wind farm was in place December 2005: Areas particularly suitable for offshore wind farms three areas particularly suitable were identified (little traffic, no major environmental conflicts less investigations necessary guidance as to where to plan an offshore wind farm with less expenditure 15

16 III. Where should an offshore wind farm be built? 3. How is it done in Germany? (2) 2005/2008: Spatial planning In 2005, BSH started working on a comprehensive spatial planning for the German EEZ (12nm-zone: responsibility of Länder), draft was announced three (!) years later priority areas for traffic were to be established priority areas for offshore wind farms were to be established, outside such areas an offshore wind farm would not be permissible. room for approximately MW hardly any room for new projects reflected the planning situation in 2005, not in 2008 effective steerage of land use in respect to offshore wind farms - but offshore wind farm industry pointed out that it would effectively cut off the development which aims at MW 2009: fundamental changes to the draft, i.e. priority areas for offshore wind farms but the possibility of having projects licensed outside these areas remains 16

17 Spatial planning in the North Sea (draft by BSH) 17

18 Spatial Planning in the Baltic Sea (draft by BSH) 18

19 III. Where should an offshore wind farm be built? 4. Conclusions Best: Have spatial planning in place before projects are developed, in order to effectively steer the use of space. Everybody would profit if the different interests are considered early, fairly and thoroughly Each country must decide whether this is "worthwhile" or whether another option might suffice, which would depend on quality and quantity of conflicting uses. Second best: Have areas identified with little potential for conflict, i.e. not forcing, but inducing project developers to use those areas Third best (minimum): Identify no-go areas in respect to nature conservation and traffic Worst: Force the competent authority to make its decisions with an instrument designed for a few cases, with no possibility of denying a project because it does not fit into an overall structure of land use. 19

20 IV. Under what circumstances should an offshore wind farm be licensed? 1. Defining scope and requirements of licensing Striking a balance When defining licensing requirements, many issues need to be considered: the need to use RES the applicants rights and interests many different interests that need to be protected. It is necessary to find requirements that strike a balance between all these aspects. EU legal frame Habitat Directive 1992/43/EEC Bird Directive 1979/409/EEC EIA Directive 1985/337/EEC (all as amended) 20

21 IV. Under what circumstances should an offshore wind farm be licensed? 2. Options for action General considerations Should the approval be discretionary or non-discretionary? Should the regimes in EEZ and 12nm-zone differ (UNCLOS needs to be taken into account in the EEZ)? what should be the scope of the permit, which elements of the project should be covered? only the wind farm? also grid connection? onshore part of cable? Licensing requirements Should all potentially conflicting interests be protected? Or should only some be protected and others left out of the decision making process? Should the technical details be already part of the licensing process or should these matters be left to the execution stage? 21

22 IV. Under what circumstances should an offshore wind farm be licensed? 3. How is it done in Germany? a) General considerations Non-discretionary administrative act If none of the reasons for refusing the project are fulfilled, the project has to be licensed. Differentiation between EEZ and 12nm-zone different competent authority slightly different procedures slightly different requirements Scope of permit/eez one permit for wind farm, transformer station, inner park cable connection one permit for cable/eez-part another permit for cable/12nm-zone part again another permit for land many different authorities involved (matter of federalism) Scope of permit/12nm-zone Although typically split into several steps, the permit would cover everything 22

23 IV. Under what circumstances should an offshore wind farm be licensed? 3. How is it done in Germany? b) Licensing requirements (EEZ) - Overview Overview of requirements A wind farm has to be approved, provided that it does not impair the safety and efficiency of navigation, it is not detrimental to the marine environment, if it does not impair other public interests (added in 2008), if it does not contradict spatial planning (added in 2008), and if such effects cannot be either prevented or compensated by collateral clauses. BSH Standards concretising requirements harmonisation of methods for risk analyses Standard Environmental Investigation Concept Standard Design of Offshore Wind Farms Standard Geological Site Investigation planned: Standard on safety/emergency management; health & safety 23

24 IV. Under what circumstances should an offshore wind farm be licensed? 3. How is it done in Germany? b) Licensing requirements (EEZ) - safety of navigation (1) No more "freedom of navigation" Offshore wind farms are obstacles to navigation. UNCLOS forbids artificial structures at a location where they would intervene with the use of important, internationally recognised shipping routes outside such shipping routes, no such provision exists. wind farms need to be placed were they cause the least negative impact on navigation. Efficiency of navigation relevant mostly in respect to economic aspects (detours cause more fuel consumption also, more attention might have to be paid by the officers if all superfluous impediments are avoided, a negative impact has to be put up with. 24

25 IV. Under what circumstances should an offshore wind farm be licensed? 3. How is it done in Germany? b) Licensing requirements (EEZ) - safety of navigation (2) Threat to safety of navigation: Collisions It is crucial that collisions between a vessel and an offshore wind farm are avoided, since it might lead to casualities (ferries involved?), contamination of the environment (hazardous substances, such as oil or chemicals involved?) great damage to turbine and vessel. Safety measures marking of turbines, radar/ais "collision friendly foundations" surveillance of the area positioning of safety vessels with significant towing capacity inside a wind farm (in one case only) 25

26 IV. Under what circumstances should an offshore wind farm be licensed? 3. How is it done in Germany? b) Licensing requirements (EEZ) - safety of navigation (3) Defining an acceptable risk (abstract general rule) Which probability of a collision is acceptable? decision considering legal and political aspects must be made by the competent authority (or on a higher level) obviously, it is not up to a project developer, because most protected interests are not at his disposition Germany: one collision in hundred years is an acceptable risk Risk analysis (each individual case ) What probability of a collision exists at that particular location? analysis of the traffic situation probabilistic risk assessment, covering different scenarios Additional measures Risk mitigation measures consent of Waterways and Shipping Directorates safety zones (in accordance with UNCLOS) 26

27 IV. Under what circumstances should an offshore wind farm be licensed? 3. How is it done in Germany? b) Licensing requirements (EEZ) - marine environment Purpose of an EIA Collect facts on the environment of the proposed project and evaluate the probable effects and consequences on the environment: which species are affected? what kind of habitat? which other interests (landscape, climate, people, etc.; Art. 3 EIA Dir.) cumulative effects how slight/middling/severe are any effects? No decision-making guidance by EIA Directive EIA Dir. does not give any guidance as to how to decide, but all aspects need to be considered third parties are involved, so all aspects/pros and cons should be on the table ways of optimising the project can be identified Strict limits to decision making by Habitat Directive and Bird Directive Art. 6 and 12 Habitat Directive, Art. 4, 5, 9 Bird Directive ECJ juristdiction 27

28 IV. Under what circumstances should an offshore wind farm be licensed? 3. How is it done in Germany? b) Licensing requirements (EEZ) - other public interests landscape important to people living near the coast and in respect to tourism. Experiences show that communities can be reconciled mitigation measures and information about the project are important very much a matter of attitude Military use It is usually difficult to say whether the issue is concerned because of confidentiality. Early discussions with the relevant bodies might help. Fishing industry Increasing concern because a lot of space might be used - compensations? Existing structures It is no technical problem to cross other cables/pipelines, but fairly expensive. 28

29 IV. Under what circumstances should an offshore wind farm be licensed? 3. How is it done in Germany? b) Licensing requirements (EEZ) - technical aspects Geotechnical investigations Partly before, partly after licensing geophysical and geotechnical site investigations have to be carried out: geophysical site investigation (SSS) (100%) before licensing geotechnical site investigation (bore holes) for 10% of all locations before licensing rest of geotechnical site investigation after licensing and before construction (relevant for manufacturing foundations; each one has to be specific) BSH Standard; investigations to be certified by an independent expert Details of construction Partly before, partly after licensing the detailed technical features of each foundation, turbine and the transformer station must be decided: all materials and details must be suitable for offshore conditions all installation methods must be suitable for offshore conditions installation logistics must be planned to perfection BSH Standard; all materials, details and logistics need to be certified by an independent expert 29

30 IV. Under what circumstances should an offshore wind farm be licensed? 3. How is it done in Germany? b) Licensing requirements (EEZ) - collateral clauses "Cradle to grave" Numerous collateral clauses cover installation, operation and decommissioning of an offshore wind farm, ensuring that the requirements of licensing are continuously met. They concern, inter alia: safety during the construction phase state of the art geotechnical study state of the art methods in the construction prior to start of construction presentation of a safety concept covering emergencies installation of lights, radar, AIS use of environmentally friendly materials and non-glare paint foundation design minimising collision impact noise reduction during construction and operation environmental monitoring during operation limitation of the permit for 25 years (possibility of prolongation if requirements are still met) decommissioning it was substantially underestimated how demanding these conditions would be! 30

31 IV. Under what circumstances should an offshore wind farm be licensed? 4. Conclusions General considerations It makes more sense to differentiate between onshore and offshore wind farms than to differentiate between windfarms situated within the territory of a state and those situated within the EEZ. a license should preferably cover all elements, i.e. wind farm and grid connection. It reduces the risk of delay, and everybody knows what one is dealing with from the beginning. Licensing requirements Navigation: Whilst some detriments to efficiency must be put up with, safety may not suffer. Environment: EU legal frame must be observed, which should cover all necessary aspects Other public interests: A balance between the use of offshore wind energy and other interests must be reached. Existing uses might have to suffer some restrictions, in the interest of climate protection. Anxieties about "sunset pollution" might be met with less lights, less height. Whether these interests need to be preconditions for licensing depends on their relevance in each single country. 31

32 IV. Under what circumstances should an offshore wind farm be licensed? 4. Conclusions Licensing requirements (cont.) All BSH Standards have been extremely helpful. After a critical look in respect to applicability and extent, they should provide a very good guidelines for others as well. Collateral clauses are a crucial part of each permission and should cover all aspects, making sure that the licensing requirements are constantly met. Existing permissions might be a guideline. Technical details should be dealt with at a later stage, not as a precondition for licensing. Otherwise, money might be spent on a project which might not be licensed. 32

33 V. Competent authorities and proceedings 1. Establishing formalities Competent authority For each administrative act, a competent authority must be assigned: "formal" competence but also competence in the sense of expertise/necessary knowledge to make an informed decision Proceedings which steps are to be taken? which documents etc. need to be submitted, and at what stage? who is to be involved? EU legal frame EIA Directive 85/337/EEC prescribes certain steps that need to be observed. 33

34 V. Competent authorities and proceedings 2. Options for action Competent authority one for those projects within the EEZ, another one for projects within the 12nmzone? Or one for all offshore wind farms? Proceedings (integrating provisions by EIA Directive) EIA can be integrated in the proceedings or it could be an extra procedure. The following elements must be covered (Art. 5 and 6 EIA Directive): other concerned authorities must be involved public shall be informed of the project and certain information must be made available public must be given early and effective opportunity of participation reasonable time frames shall be provided for this participation other Member States may have to be included. There are no specific forms prescribed for the participation of these groups and bodies. 34

35 V. Competent authorities and proceedings 3. How is it done in Germany? (1) Competent authority Competent authority for projects within the EEZ is the Federal Maritime and Hydrographic Agency (Bundesamt für Seeschifffahrt und Hydrographie - BSH) competent authority for projects within the 12nm-zone are appointed by Länder Proceedings Both the "before licensing stage" as well as the "execution stage" shall be presented, because many of the important details happen after licensing. Before licensing upon receival, BSH checks completeness (basic information: location, probable environment, size, time frame of realisation,...) first round of participation is initiated: other authorities are informed and asked for comments after evaluation of these first comments, more - also private - stakeholders are involved in a second participation round and are given an opportunity to comment 35

36 V. Competent authorities and proceedings 3. How is it done in Germany? (2) Before licensing (cont.) first public discussion (application conference/scoping): the project is presented and conflicting interests and uses are discussed. As a consequence, the scope of investigation is prescribed. objective: defining the scope of investigation by identifying potential conflicts. phase of investigation (environmental impact study, risk analysis, basic technical designs). third round of participation: all resulting documents are passed on to the public and other authorities/bodies for inspection and comment. second public discussion of these documents objective: identification of actual conflicts and - if possible - finding solutions review of all points and - if all requirements are met - granting of approval (parallel: granting of approval by Waterways and Shipping Directorates, if safety standards are met). time frame: between two and five years (two if everyone is really fast and a lot of work was done in advance) 36

37 V. Competent authorities and proceedings 3. How is it done in Germany? (3) Execution of a permit A lot of questions are unsolved at the point of licensing, because the requirements (in Germany) only say that the wind farm as a whole does not constitute a danger to the protected subjects. Many technical details concerning constructional safety are still open: geotechnical investigations need to be carried out for each location even the last screw needs to be certified for offshore use installation logistics need to be thought through. environmental monitoring concept noise reduction methods emergency management concept operation and maintenance concept... realisation process is very demanding and should not be underestimated. But: the nearer to the shore and the shallower the water, the easier experience should help a lot 37

38 V. Competent authorities and proceedings 4. Conclusions Competent authority Considering how complex a matter it is, it might make sense to appoint one authority which would deal with all applications. Otherwise, expertise would need to be built up in more places than necessary. Proceedings EU legal frame needs to be observed (EIA Directive) The proceedings might seem to be very long winded, but they constitute an excellent method of discussing problems and finding solutions/compromises. The more people/stakeholders involved, the better the chance of agreement and support. The decision should not be rushed (it should certainly not be artificially prolonged, though). 38

39 VI. Where would the electricity go? 1. "No life without arteries" offshore onshore planning and licensing difficult routes (sensitive areas, crossing of streets, rivers, train lines etc.) should be avoided, if at all possible contracts with land owners need to be concluded onshore transmission/distribution grid sufficient capacity to transmit the electricity to where it is in demand? need for extension of power lines or nodes, new transformer stations? will some grid capacity be available in the future, because another power plant might be shut down, etc.? 39

40 VI. Where would the electricity go? 2. Options for action offshore onshore who shall build the grid connection - TSO, wind farm operator, state? who shall pay - operator or consumer/tax payer? onshore transmission/distribution grid if more capacity is needed, is the legal frame work in place or are adjustments necessary? when would the capacity be needed - when should planning and building of new powerlines be underway? should it be underground cables or power lines above ground? 40

41 VI. Where would the electricity go? 3. How is it done in Germany? a) Grid connection offshore onshore Responsibility The TSOs are responsible for connecting all wind farms that start being built until the end of 2015 to the onshore transmission grid the connection must be in place at the same time the wind farm is ready to start operation Costs of grid connection costs can be passed on to the electricity consumers Advantages more cost efficient because of bundling less environmental impact because of bundling incentive for project developers since they do not need to invest acceleration of project realisation because of limited responsibility Disadvantage one sometimes gets the impression that TSOs simply don't care about their legal responsibility. 41

42 VI. Where would the electricity go? 3. How is it done in Germany? b) Capacity of the onshore (transmission) grid Problem In Germany, wind electricity is mostly generated in the north but needed in the south or the middle. Its use/percentage is constantly increasing The grid needs to be restructured, in order to cope with decentralised electricity generation. Identification of extra capacity needed From , a comprehensive technical study was done. Conclusion: 850 km of high voltage power lines (in specified locations) are needed for integrating wind power (on- and offshore) until Another technical study is under way, examining another time horizon Legislation on accelerating the building of power lines under way Overhead power lines are very contentious, which is why - at the moment - some legislation is under way to speed up licensing and realisation. It is discussed to install more underground cables, but there is little chance that more than very few stretches will be built as cables; it is argued that cables are too expensive. 42

43 VI. Where would the electricity go? 4. Conclusions Offshore onshore It must be made sure that the grid connection is ready at the same time the wind farm is ready to operate. If someone else than the wind farm operator is responsible for grid connection, it must be ascertained that he is willing to do his job, that there is absolutely no loop-hole and that it is done in time. Capacity of onshore grid If there are doubts about the capacity of the onshore grid, early action should be taken to investigate the matter and - if necessary - amend the situation. Grid connection/grid capacity is vital! 43

44 VII. What else is needed? Components Where to the turbines, foundations and transformer stations come from? where the jack-up platforms and other installation equipment (vessels for cable laying)? Infrastructure Can the turbines etc. be stored at the quay side? onshore grid connection? Operation and maintenance are operation and maintenance concepts in place? Emergency management What shall be done if a vessel comes dangerously close to a wind farm is out of control? Who is in command? Is some sort of surveillance of the area already in place - what needs to be added? What is to be done if a collision occurs - what strategies? 44

Federal Maritime and Hydrographic Agency Bundesamt für Seeschiffahrt und Hydrographie Seminar on EIA, May 2013, Riga Anika Beiersdorf, BSH

Federal Maritime and Hydrographic Agency Bundesamt für Seeschiffahrt und Hydrographie Seminar on EIA, May 2013, Riga Anika Beiersdorf, BSH Legal Framework for Construction and EIA for Offshore Windfarms in Germany Federal Maritime and Hydrographic Agency Bundesamt für Seeschiffahrt und Hydrographie Seminar on EIA, 21. - 22. May 2013, Riga

More information

Draft of the Spatial Offshore Grid Plan for the German Exclusive Economic Zone of the Baltic Sea 2016/2017. unofficial translation

Draft of the Spatial Offshore Grid Plan for the German Exclusive Economic Zone of the Baltic Sea 2016/2017. unofficial translation Draft of the Spatial Offshore Grid Plan for the German Exclusive Economic Zone of the Baltic Sea 2016/2017 unofficial translation Hamburg, June 2017 Content 1 THE SPATIAL OFFSHORE GRID PLAN... 1 1.1 Legal

More information

Dutch offshore wind energy policy an overview. Mark Stuurman Policy advisor

Dutch offshore wind energy policy an overview. Mark Stuurman Policy advisor Dutch offshore wind energy policy an overview Mark Stuurman Policy advisor Overview Quick introduction Dutch Approach Site selection Roadmap Seabed Lease Tender system Future Challenges and latest developments

More information

Maasvlakte CCS Project - ROAD

Maasvlakte CCS Project - ROAD Maasvlakte CCS Project - ROAD European CCS Demonstration Project Network Meeting Rotterdam, May 10, 2011 Hans Schoenmakers Project Director ROAD Permits for a CCS project Power Plant Capture Plant Transport

More information

Draft of the Spatial Offshore Grid Plan for the German Exclusive Economic Zone of the North Sea 2016/2017. unofficial translation

Draft of the Spatial Offshore Grid Plan for the German Exclusive Economic Zone of the North Sea 2016/2017. unofficial translation Draft of the Spatial Offshore Grid Plan for the German Exclusive Economic Zone of the North Sea 2016/2017 unofficial translation Hamburg, June 2017 Content 1 THE SPATIAL OFFSHORE GRID PLAN... 1 1.1 Legal

More information

Offshore Wind Energy in Germany: System Benefits and Cost Reduction Potentials

Offshore Wind Energy in Germany: System Benefits and Cost Reduction Potentials Offshore Wind Energy in Germany: System Benefits and Cost Reduction Potentials Presentation of study results from prognos/fichtner and Fraunhofer-IWES Andreas WAGNER Stiftung OFFSHORE-WINDENERGIE German

More information

Accelerating the Deployment of Offshore Renewable Energy Technologies. IEA Implementing Agreement on Renewable Energy Technology Deployment

Accelerating the Deployment of Offshore Renewable Energy Technologies. IEA Implementing Agreement on Renewable Energy Technology Deployment Accelerating the Deployment of Offshore Renewable Energy Technologies IEA Implementing Agreement on Renewable Energy Technology Deployment Background RETD The mission of RETD is to accelerate the large-scale

More information

AN OVERVIEW OF THE STATE OF MARINE SPATIAL PLANNING IN THE MEDITERRANEAN COUNTRIES MALTA REPORT

AN OVERVIEW OF THE STATE OF MARINE SPATIAL PLANNING IN THE MEDITERRANEAN COUNTRIES MALTA REPORT AN OVERVIEW OF THE STATE OF MARINE SPATIAL PLANNING IN THE MEDITERRANEAN COUNTRIES MALTA REPORT Malta Environment & Planning Authority May 2007 AN OVERVIEW OF THE STATE OF MARINE SPATIAL PLANNING IN THE

More information

Introductory remarks

Introductory remarks Introductory remarks This document is a draft of a permit for Gaz System to construct a natural gas pipeline on the Danish continental shelf in the Baltic Sea. It should be emphasised that it has not yet

More information

HSE and Quality. Sisimiut, 10th December FING: Arctic Region Oil & Gas Seminar in Training and Education

HSE and Quality. Sisimiut, 10th December FING: Arctic Region Oil & Gas Seminar in Training and Education HSE and Quality Sisimiut, 10th December 2013 FING: Arctic Region Oil & Gas Seminar in Training and Education 1 Arctic Issues Above ground challenges FING: Arctic Region Oil & Gas Seminar in Training and

More information

The offshore wind puzzle getting the pieces right

The offshore wind puzzle getting the pieces right ENERGY The offshore wind puzzle getting the pieces right FOWIND workshop Paul Reynolds 09/09/14 1 SAFER, SMARTER, GREENER World s largest dedicated renewable energy consultancy 2 Content & Key messages

More information

PORT OF POOLE DEVELOPING FOR THE FUTURE

PORT OF POOLE DEVELOPING FOR THE FUTURE PORT OF POOLE DEVELOPING FOR THE FUTURE Nick Clarke & Kim Moore INTRODUCTION Masterplan the benefits EIA & SEA (Strategic Environmental ) Changes in Marine Licensing. PORT DEVELOPMENT PROCESS Development

More information

Route Planning & Cable Route Surveys

Route Planning & Cable Route Surveys Route Planning & Cable Route Surveys Graham Evans Director EGS Survey Group www.egssurvey.com Concept to Reality Key Phases Development of Business Model Definition of Key Project Milestones Project Concept

More information

Blue growth. Stijn Billiet. DG Maritime Affairs and Fisheries

Blue growth. Stijn Billiet. DG Maritime Affairs and Fisheries Blue growth Stijn Billiet DG Maritime Affairs and Fisheries Overview The EU's blue economy is already significant 550 billion EUR Gross Value Added (4% of the EU economy), 5 million jobs EU is global market

More information

Founding Manifesto Friends of Floating Offshore Wind 18 May 2016

Founding Manifesto Friends of Floating Offshore Wind 18 May 2016 Founding Manifesto Friends of Floating Offshore Wind 18 May 2016 Members: Pilot Offshore Renewables Hexicon RES Offshore IDEOL Floating Power Plant Glosten PelaStar Principle Power Inc. Atkins ACS Cobra

More information

The potential for windpower in the Baltic Sea

The potential for windpower in the Baltic Sea 4th September 2013 Stanisław Paszkowski/Michał Gronert DNV An Independent Foundation 300 offices 100 countries 10,500 employees 2 Offshore Wind - Combining DNV competences + = 25+ years of hands-on experience

More information

SUBMARINE CABLES, RESOURCE USE, AND ENVIRONMENTAL PROTECTION. Ambassador Satya Nandan

SUBMARINE CABLES, RESOURCE USE, AND ENVIRONMENTAL PROTECTION. Ambassador Satya Nandan SUBMARINE CABLES, RESOURCE USE, AND ENVIRONMENTAL PROTECTION Ambassador Satya Nandan CIL Workshop on Submarine Cables and Law of the Sea Singapore 14-15 December 2009 www.telegeography.com LOSC Framework

More information

(EC) ), 11(8) 347/ /2009, (EC)

(EC) ), 11(8) 347/ /2009, (EC) ENTSOs consistent and interlinked electricity and gas model in accordance with Article 11(8) of Regulation (EU) No 347/2013 of the European Parliament and of the Council of 17 April 2013 21 December 2016

More information

Offshore Wind Risks - Issues and Mitigations

Offshore Wind Risks - Issues and Mitigations DNV Offshore Wind Soren Karkov DNV an independent foundation Our Purpose To safeguard life, property and the environment Our Vision Global impact for a safe and sustainable future 2 More than 145 Years

More information

VDMA Response to the Public Consultation Towards a 7 th EU Environmental Action Programme

VDMA Response to the Public Consultation Towards a 7 th EU Environmental Action Programme European Office VDMA Response to the Public Consultation Towards a 7 th EU Environmental Action Programme Registration number in the register of representative bodies: 976536291-45 May 2012 1. Introduction

More information

Arctic Shipping Navigating the Legal Landscape for marine infrastructure and Off-Shore Development

Arctic Shipping Navigating the Legal Landscape for marine infrastructure and Off-Shore Development Arctic Shipping Navigating the Legal Landscape for marine infrastructure and Off-Shore Development Peter G. Pamel Partner Connecticut Maritime Association SHIPPING 2012 Hilton Stamford March 21 st, 2012

More information

Minutes of the 1 st Thematic Working Group Environment and Society of the Baltic InteGrid project

Minutes of the 1 st Thematic Working Group Environment and Society of the Baltic InteGrid project Minutes of the 1 st Thematic Working Group Environment and Society of the Baltic InteGrid project February 28 th, 2017, Warsaw, Poland Venue: Marriott Hotel, Al. Jerozolimskie 65/79, 00-697 Warsaw Host:

More information

German Market andprojects revisited

German Market andprojects revisited German Market andprojects revisited Andreas Wagner, Managing Director German Offshore Wind Energy Foundation Lars Engelmann German Association for Marine Technology (GMT) e.v. London, 6 June 2017 Offshore

More information

East Anglia TWO and East Anglia ONE North. Summary and Approach to Site Selection

East Anglia TWO and East Anglia ONE North. Summary and Approach to Site Selection East Anglia TWO and East Anglia ONE North Summary and Approach to Site Selection 1 Introduction ScottishPower Renewables (SPR) has recently concluded work in order to inform our onshore site selection

More information

Offshore Renewables Institute

Offshore Renewables Institute Offshore Renewables Institute Introducing the Offshore Renewables Institute (ORI) About Us We bring together experts and expertise from across a broad university partnership: the University of Dundee;

More information

National Grid s commitments when undertaking works in the UK. Our stakeholder, community and amenity policy

National Grid s commitments when undertaking works in the UK. Our stakeholder, community and amenity policy National Grid s commitments when undertaking works in the UK Our stakeholder, community and amenity policy Introduction This document describes the ten commitments we have made to the way we carry out

More information

Certified quality for offshore wind farms. We certify offshore projects independently, proficiently, and reliably.

Certified quality for offshore wind farms. We certify offshore projects independently, proficiently, and reliably. Certified quality for offshore wind farms We certify offshore projects independently, proficiently, and reliably. From the design phase through to dismantling all from one source Hanseatic Power Cert GmbH

More information

Policy Research Corporation

Policy Research Corporation Policy Research Corporation SOUND SOLUTIONS BASED ON SCIENTIFIC RESEARCH The role of Maritime Clusters to enhance the strength and development of maritime sectors Country report Denmark INTRODUCTION TO

More information

(5) The measures provided for in this Regulation are in accordance with the opinion of the Committee for the European Maritime and Fisheries Fund,

(5) The measures provided for in this Regulation are in accordance with the opinion of the Committee for the European Maritime and Fisheries Fund, 21.11.2014 EN L 334/39 COMMISSION IMPLEMENTING REGULATION (EU) No 1243/2014 of 20 November 2014 laying down rules pursuant to Regulation (EU) No 508/2014 of the European Parliament and of the Council on

More information

PROPOSALS FOR AQUIND INTERCONNECTOR

PROPOSALS FOR AQUIND INTERCONNECTOR PROPOSALS FOR AQUIND INTERCONNECTOR Introduction AQUIND Limited is the developer of AQUIND Interconnector, a new underground and subsea electric power transmission link that will connect the UK and French

More information

Goal: Effective Decision Making

Goal: Effective Decision Making Goal: Effective Decision Making Objective 1. Enhance inter-agency coordination Focus on aspects of governmental decision-making (NEPA and other existing siting/regulatory programs) related to marine energy

More information

Marine biological diversity of areas beyond national jurisdiction. Legal and policy framework

Marine biological diversity of areas beyond national jurisdiction. Legal and policy framework Marine biological diversity of areas beyond national jurisdiction Legal and policy framework 1. The United Nations Convention on the Law of the Sea (UNCLOS) provides the legal framework within which all

More information

The objective of the group would be to coordinate the range of the main implementary actions, the methods and schedule of their implementation.

The objective of the group would be to coordinate the range of the main implementary actions, the methods and schedule of their implementation. The objective of the group would be to coordinate the range of the main implementary actions, the methods and schedule of their implementation. 1 Introduction The discussion on the justness of the development

More information

Offshore Grid Development in the North Seas ENTSO-E views

Offshore Grid Development in the North Seas ENTSO-E views Offshore Grid Development in the North Seas ENTSO-E views European Network of Transmission System Operators for Electricity Offshore Grid Development in the North Seas Country The connection and integration

More information

Non-Technical Summary of the SEA Report Draft on the Spatial Offshore Grid Plan for the German Exclusive Economic Zone of the North Sea 2016/2017

Non-Technical Summary of the SEA Report Draft on the Spatial Offshore Grid Plan for the German Exclusive Economic Zone of the North Sea 2016/2017 Non-Technical Summary of the SEA Report Draft on the Spatial Offshore Grid Plan for the German Exclusive Economic Zone of the North Sea unofficial translation Hamburg, June 2017 Content 1 Subject and Purpose...

More information

NURTURING OFFSHORE WIND MARKETS GOOD PRACTICES FOR INTERNATIONAL STANDARDISATION

NURTURING OFFSHORE WIND MARKETS GOOD PRACTICES FOR INTERNATIONAL STANDARDISATION NURTURING OFFSHORE WIND MARKETS GOOD PRACTICES FOR INTERNATIONAL STANDARDISATION Summary for POLICY MAKERS SUMMARY FOR POLICY MAKERS The fast pace of offshore wind development has resulted in remarkable

More information

Written Comment: Sydney Basin and Orpheus Graben Areas

Written Comment: Sydney Basin and Orpheus Graben Areas December 23, 2015 Written Comment: Sydney Basin and Orpheus Graben Areas Based on the draft Strategic Environmental Assessment 202 Brownlow Ave. Suite A305, Cambridge 1 Dartmouth, NS B3B 1T5 (902) 425-4774

More information

Proposal for a COUNCIL DECISION

Proposal for a COUNCIL DECISION EUROPEAN COMMISSION Brussels, 23.5.2017 COM(2017) 273 final 2017/0110 (NLE) Proposal for a COUNCIL DECISION on the position to be adopted, on behalf of the European Union, in the European Committee for

More information

DNVGL-CG-0214 Edition September 2016

DNVGL-CG-0214 Edition September 2016 CLASS GUIDELINE DNVGL-CG-0214 Edition September 2016 The content of this service document is the subject of intellectual property rights reserved by ("DNV GL"). The user accepts that it is prohibited by

More information

Emerging Subsea Networks

Emerging Subsea Networks FIBRE-TO-PLATFORM CONNECTIVITY, WORKING IN THE 500m ZONE Andrew Lloyd (Global Marine Systems Limited) Email: andrew.lloyd@globalmarinesystems.com Global Marine Systems Ltd, New Saxon House, 1 Winsford

More information

Building the marine Natura 2000 network towards effective management

Building the marine Natura 2000 network towards effective management International Symposium on Marine Nature Restoration in Northern Europe Restoration of Reefs Copenhagen, 11/03/2013 Building the marine Natura 2000 network towards effective management Fotios Papoulias

More information

The EU and Norway: addressing Arctic and maritime challenges

The EU and Norway: addressing Arctic and maritime challenges SPEECH/11/673 Maria Damanaki European Commissioner for Maritime Affairs and Fisheries The EU and Norway: addressing Arctic and maritime challenges Seminar High North Oslo, 17 October 2011 Ladies and Gentlemen,

More information

INVESTMENTS FOR SMART AND SUSTAINABLE SOLUTIONS FOR COMPETITIVE BLUE GROWTH IN THE BALTIC SEA REGION. Warnemünde, 28 th of September 2016

INVESTMENTS FOR SMART AND SUSTAINABLE SOLUTIONS FOR COMPETITIVE BLUE GROWTH IN THE BALTIC SEA REGION. Warnemünde, 28 th of September 2016 INVESTMENTS FOR SMART AND SUSTAINABLE SOLUTIONS FOR COMPETITIVE BLUE GROWTH IN THE BALTIC SEA REGION Warnemünde, 28 th of September 2016 Conference of Peripheral and Maritime Regions CPMR Baltic Sea Commission

More information

RESOLUTION MSC.278(85) (adopted on 1 December 2008) ADOPTION OF THE NEW MANDATORY SHIP REPORTING SYSTEM "OFF THE COAST OF PORTUGAL - COPREP"

RESOLUTION MSC.278(85) (adopted on 1 December 2008) ADOPTION OF THE NEW MANDATORY SHIP REPORTING SYSTEM OFF THE COAST OF PORTUGAL - COPREP MSC 85/26/Add.1 RESOLUTION MSC.278(85) SYSTEM OFF THE COAST OF PORTUGAL COPREP THE MARITIME SAFETY COMMITTEE, RECALLING Article 28 of the Convention on the International Maritime Organization concerning

More information

CHAPTER TWENTY COOPERATION. The objective of this Chapter is to facilitate the establishment of close cooperation aimed, inter alia, at:

CHAPTER TWENTY COOPERATION. The objective of this Chapter is to facilitate the establishment of close cooperation aimed, inter alia, at: CHAPTER TWENTY COOPERATION ARTICLE 20.1: OBJECTIVE The objective of this Chapter is to facilitate the establishment of close cooperation aimed, inter alia, at: strengthening the capacities of the Parties

More information

Co-ordination of the Group of Notified Bodies for the Construction Products Directive 89/106/EEC. GNB-CPD Conference on CPR

Co-ordination of the Group of Notified Bodies for the Construction Products Directive 89/106/EEC. GNB-CPD Conference on CPR GNB-CPD All Co-ordination of the Group of Notified Bodies for the Construction Products Directive 89/106/EEC NB-CPD/All-13/112 Issued: 13 June 2013 Answers to GNB- CPD questions GNB-CPD Conference on CPR

More information

Tidal Energy. Transmission & Distribution Network. Wind Energy. Offshore Substation. Onshore Substation. Tidal Stream Energy.

Tidal Energy. Transmission & Distribution Network. Wind Energy. Offshore Substation. Onshore Substation. Tidal Stream Energy. Offshore Renewables Tidal Energy Transmission & Distribution Network Offshore Substation Wind Energy Onshore Substation Tidal Stream Energy Consumer Atkins in Offshore Renewables The offshore wind journey

More information

Publishing date: 23/07/2015 Document title: We appreciate your feedback. Share this document

Publishing date: 23/07/2015 Document title: We appreciate your feedback. Share this document Publishing date: 23/07/2015 Document title: We appreciate your feedback Please click on the icon to take a 5 online survey and provide your feedback about this document Share this document REPORT ON UNIT

More information

Outcome of the joint HELCOM-BIAS workshop on underwater noise

Outcome of the joint HELCOM-BIAS workshop on underwater noise Outcome of the joint HELCOM-BIAS workshop on underwater noise HELCOM Secretariat, Helsinki, Finland, 26 November 2014 Introduction The 2013 HELCOM Copenhagen Ministerial Meeting agreed that the level of

More information

PROPOSALS FOR AQUIND INTERCONNECTOR

PROPOSALS FOR AQUIND INTERCONNECTOR PROPOSALS FOR AQUIND INTERCONNECTOR Get in touch To find out more about AQUIND Interconnector, please visit our consultation website at https://aquindconsultation.co.uk If you have any questions, you can

More information

Overview: where do we stand? What is built, what is planned? Bergen, 27 June 2013 Theresa Schneider

Overview: where do we stand? What is built, what is planned? Bergen, 27 June 2013 Theresa Schneider Overview: where do we stand? What is built, what is planned? Bergen, 27 June 2013 Theresa Schneider Agenda Current situation: where do we stand and what is planned? Planning: strategic and combined? Agenda

More information

Optimizing wind farms

Optimizing wind farms Optimizing wind farms We are Uniper We are a leading international energy company with operations in more than 40 countries and around 13,000 employees. We combine a balanced portfolio of modern assets

More information

Welcome! to the Pan Baltic SCOPE Opening Conference!

Welcome! to the Pan Baltic SCOPE Opening Conference! Welcome! to the Pan Baltic SCOPE Opening Conference! #panbalticscope Photo: Pernillan 2 FELIX LEINEMANN EUROPEAN COMMISSION THE DIRECTORATE GENERAL FOR MARITIME AFFAIRS AND FISHERIES HEAD OF UNIT 3 HELEN

More information

LAW ON TECHNOLOGY TRANSFER 1998

LAW ON TECHNOLOGY TRANSFER 1998 LAW ON TECHNOLOGY TRANSFER 1998 LAW ON TECHNOLOGY TRANSFER May 7, 1998 Ulaanbaatar city CHAPTER ONE COMMON PROVISIONS Article 1. Purpose of the law The purpose of this law is to regulate relationships

More information

European Charter for Access to Research Infrastructures - DRAFT

European Charter for Access to Research Infrastructures - DRAFT 13 May 2014 European Charter for Access to Research Infrastructures PREAMBLE - DRAFT Research Infrastructures are at the heart of the knowledge triangle of research, education and innovation and therefore

More information

Annex III - 3. Memorandum of Understanding on the development of the Pan-European Transport Corridor VII (The Danube) (DRAFT)

Annex III - 3. Memorandum of Understanding on the development of the Pan-European Transport Corridor VII (The Danube) (DRAFT) Annex III - 3 Memorandum of Understanding on the development of the Pan-European Transport Corridor VII (The Danube) (DRAFT) Desiring to promote international transport of goods and passengers through

More information

RECOGNIZING also that other factors such as habitat loss, pollution and incidental catch are seriously impacting sea turtle populations;

RECOGNIZING also that other factors such as habitat loss, pollution and incidental catch are seriously impacting sea turtle populations; Conf. 9.20 (Rev.) * Guidelines for evaluating marine turtle ranching proposals submitted pursuant to Resolution Conf..6 (Rev. CoP5) RECOGNIZING that, as a general rule, use of sea turtles has not been

More information

Wind Energy Technology Roadmap

Wind Energy Technology Roadmap Wind Energy Technology Roadmap Making Wind the most competitive energy source Nicolas Fichaux, TPWind Secretariat 1 TPWind involvement in SET-Plan process SRA / MDS Programme Report / Communication Hearings

More information

Offshore Renewable Energy Conversion platforms - Coordination Action

Offshore Renewable Energy Conversion platforms - Coordination Action Offshore Renewable Energy Conversion platforms - Coordination Action a European coordination action on the combined offshore wind and ocean energy resources, technologies and markets Jochen Bard Project

More information

COUNTRIES SURVEY QUESTIONNAIRE

COUNTRIES SURVEY QUESTIONNAIRE COUNTRIES SURVEY QUESTIONNAIRE The scope of part A of this questionnaire is to give an opportunity to the respondents to provide overall (generic) details on their experience in the safety investigation

More information

Coastal Virginia Offshore Wind partnership with Orsted. February 2018 Update

Coastal Virginia Offshore Wind partnership with Orsted. February 2018 Update Coastal Virginia Offshore Wind partnership with Orsted February 2018 Update 1 Coastal Virginia Offshore Wind Project: Lease Update Research and Commercial Lease Areas Phase 1 CVOW Lease Area (2,135 acres)

More information

The Marine Plan for the Isle of Man. Dr Peter McEvoy Marine Spatial Planning Project Officer Isle of Man Government

The Marine Plan for the Isle of Man. Dr Peter McEvoy Marine Spatial Planning Project Officer Isle of Man Government The Marine Plan for the Isle of Man Dr Peter McEvoy Marine Spatial Planning Project Officer Isle of Man Government Irish Sea Maritime Forum, 2 nd Annual Conference, Glasgow 21 st May 2013 Aims of the project

More information

NATIONAL POLICY ON OILED BIRDS AND OILED SPECIES AT RISK

NATIONAL POLICY ON OILED BIRDS AND OILED SPECIES AT RISK NATIONAL POLICY ON OILED BIRDS AND OILED SPECIES AT RISK January 2000 Environment Canada Canadian Wildlife Service Environnement Canada Service canadien de la faune Canada National Policy on Oiled Birds

More information

Goals, progress and difficulties with regard to the development of German nuclear standards on the example of KTA 2000

Goals, progress and difficulties with regard to the development of German nuclear standards on the example of KTA 2000 Goals, progress and difficulties with regard to the development of German nuclear standards on the example of KTA 2000 Dr. M. Mertins Gesellschaft für Anlagen- und Reaktorsicherheit (GRS) mbh ABSTRACT:

More information

Comments on the paper by Andres, Guasch, Lopez Azumendi (2009)

Comments on the paper by Andres, Guasch, Lopez Azumendi (2009) Comments on the paper by Andres, Guasch, Lopez Azumendi (2009) Regulation and performance of power sector Carl Bernadac AFD Paris Technical Department / Infrastructure and Environment Agence Française

More information

Night-time obstruction lighting for offshore (and onshore) wind farms and birds: demands from different interest groups

Night-time obstruction lighting for offshore (and onshore) wind farms and birds: demands from different interest groups Night-time obstruction lighting for offshore (and onshore) wind farms and birds: demands from different interest groups Development of concepts for the marking of offshore wind farms Sub-project: Ecological

More information

Offshore Renewable. Energy Conversion platforms Coordination. Action

Offshore Renewable. Energy Conversion platforms Coordination. Action Offshore Renewable Energy Conversion platforms Coordination Action Jochen Bard Head of Marine Energy Systems Fraunhofer Institute for Wind Energy and Energy System Technology, Germany. www.iwes.fraunhofer.de

More information

Power Lines and Bird Mortality in Europe

Power Lines and Bird Mortality in Europe Power Lines and Bird Mortality in Europe - International and European legal background - Markus Nipkow NABU BirdLife Germany H. Löffler ELSIC Current Situation High and large-scale bird mortality from

More information

Project BONUS ESABALT

Project BONUS ESABALT Project BONUS ESABALT Economic and Non-Economic Feasibility Analysis dr Paweł Banaś Maritime University of Szczecin Content Assumptions 1. Analysis of navigational systems and devices 2. Expected ESABALT

More information

UNIVERSAL SERVICE PRINCIPLES IN E-COMMUNICATIONS

UNIVERSAL SERVICE PRINCIPLES IN E-COMMUNICATIONS UNIVERSAL SERVICE PRINCIPLES IN E-COMMUNICATIONS BEUC paper EC register for interest representatives: identification number 9505781573-45 100% broadband coverage by 2013 ICT services have become central

More information

NER300 Offshore Wind Park Nordsee One. Tobias Griesshaber Shareholder representative of Innogy SE on behalf of project Nordsee One GmbH

NER300 Offshore Wind Park Nordsee One. Tobias Griesshaber Shareholder representative of Innogy SE on behalf of project Nordsee One GmbH NER300 Offshore Wind Park Nordsee One Tobias Griesshaber Shareholder representative of Innogy SE on behalf of project Nordsee One GmbH Brussels, 15 December 2017 1 Agenda General project overview & timeline

More information

Lexis PSL Competition Practice Note

Lexis PSL Competition Practice Note Lexis PSL Competition Practice Note Research and development Produced in partnership with K&L Gates LLP Research and Development (R&D ) are under which two or more parties agree to jointly execute research

More information

Ladies and Gentlemen. Thank you for the invitation!

Ladies and Gentlemen. Thank you for the invitation! Speech at the Baltic Ports Conference Role of ports in EU Transport Policy the level playing field for all ports Henrik Hololei, Director General, Mobility and Transport, European Commission Ladies and

More information

(The Fishing Municipalities Strömstad-Tanum-Sotenäs-Lysekil-Tjörn-Göteborg-Ökerö Västra Götaland Region)

(The Fishing Municipalities Strömstad-Tanum-Sotenäs-Lysekil-Tjörn-Göteborg-Ökerö Västra Götaland Region) 1(5) (The Fishing Municipalities Strömstad-Tanum-Sotenäs-Lysekil-Tjörn-Göteborg-Ökerö Västra Götaland Region) Consultation on reform of Common Fisheries Policy The Fishing Municipalities The Fishing Municipalities,

More information

Demand inspired research in offshore wind energy systems

Demand inspired research in offshore wind energy systems Demand inspired research in offshore wind energy systems Jos Beurskens We@Sea / ECN www.we-at at-sea.org / www.ecn.nl This presentation We@Sea programme and experiences Update R&D top priorities based

More information

Consultation on International Ocean Governance

Consultation on International Ocean Governance Consultation on International Ocean Governance 1 Context Oceans are a key source of nutritious food, medicine, minerals and renewable energy. They are also home to a rich, fragile, and largely unknown

More information

Environmental and non-technical impacts of lean principles applied to offshore wind farms

Environmental and non-technical impacts of lean principles applied to offshore wind farms Environmental and non-technical impacts of lean principles applied to offshore wind farms 28 th September 2016 Mihaela DRAGAN Environment & Planning Analyst, WindEurope Project supported within the Ocean

More information

TNO division Defense, Security and Safety. Report numbers TNO

TNO division Defense, Security and Safety. Report numbers TNO Organisation Report name TNO division Defense, Security and Safety Final report WE@SEA project ROBIN Lite bird radar development aimed at maritime bird migration monitoring Report numbers WE@SEA 2005-022

More information

ENERGY TECHNOLOGY ROADMAPS SYNTHESIS: OCEAN ENERGY. 1. Overview, Discussion. 2. International Energy Agency, Ocean Energy Systems

ENERGY TECHNOLOGY ROADMAPS SYNTHESIS: OCEAN ENERGY. 1. Overview, Discussion. 2. International Energy Agency, Ocean Energy Systems ENERGY TECHNOLOGY ROADMAPS SYNTHESIS: OCEAN ENERGY 1. Overview, Discussion 2. International Energy Agency, Ocean Energy Systems 3. DTI Arup Technology Roadmap, Wave Energy 4. World Energy Council, Survey

More information

Fact Sheet IP specificities in research for the benefit of SMEs

Fact Sheet IP specificities in research for the benefit of SMEs European IPR Helpdesk Fact Sheet IP specificities in research for the benefit of SMEs June 2015 1 Introduction... 1 1. Actions for the benefit of SMEs... 2 1.1 Research for SMEs... 2 1.2 Research for SME-Associations...

More information

Policy Research Corporation

Policy Research Corporation Policy Research Corporation SOUND SOLUTIONS BASED ON SCIENTIFIC RESEARCH The role of Maritime Clusters to enhance the strength and development of maritime sectors Country report Poland INTRODUCTION TO

More information

OCEAN ECONOMY: SA - Norway PRESENTATION

OCEAN ECONOMY: SA - Norway PRESENTATION OCEAN ECONOMY: SA - Norway PRESENTATION PRESENTATION OUTLINE 1) Introduction: Ocean Economy 2) Introduction: Ocean Economy Focus Areas 3) Ocean Economy recommendations 4) Ocean Economy Focus Area Progress

More information

Prepared by Daniel Piec Natura International Polska

Prepared by Daniel Piec Natura International Polska Report from Study Visit in Romania on 14 to 18 September 2016 under the task F.5, part of the LIFE project Protection of rare zone birds within selected Natura 2000 areas in Lublin Province Prepared by

More information

Final Prospectus and Terms of Reference for an Independent Review of the New England Fishery Management Council 2/27/18

Final Prospectus and Terms of Reference for an Independent Review of the New England Fishery Management Council 2/27/18 Final Prospectus and Terms of Reference for an Independent Review of the New England Fishery Management Council 2/27/18 The New England Fishery Management Council (NEFMC, Council) has initiated an independent

More information

To Undertake a Rapid Assessment of Fisheries and Aquaculture Information Management System (FIMS) in Kenya

To Undertake a Rapid Assessment of Fisheries and Aquaculture Information Management System (FIMS) in Kenya Republic of Kenya MINISTRY OF AGRICULTURE, LIVESTOCK & FISHERIES STATE DEPARTMENT OF FISHERIES AND BLUE ECONOMY KENYA MARINE FISHERIES AND SOCIO-ECONOMIC DEVELOPMENT PROJECT (KEMFSED) TERMS OF REFERENCE

More information

Well Control Contingency Plan Guidance Note (version 2) 02 December 2015

Well Control Contingency Plan Guidance Note (version 2) 02 December 2015 Well Control Contingency Plan Guidance Note (version 2) 02 December 2015 Prepared by Maritime NZ Contents Introduction... 3 Purpose... 3 Definitions... 4 Contents of a Well Control Contingency Plan (WCCP)...

More information

The Norwegian Context PTIL/PSA 1

The Norwegian Context PTIL/PSA 1 The Norwegian Context 1 Some fast facts about Norway s petroleum industry Oil and gas is Norway s largest industry today Net cash flow from the petroleum industry is 26% of GNP (2012) 40 years of operations

More information

The actors in the research system are led by the following principles:

The actors in the research system are led by the following principles: Innovation by Co-operation Measures for Effective Utilisation of the Research Potential in the Academic and Private Sectors Position Paper by Bundesverband der Deutschen Industrie Bundesvereinigung der

More information

NCRIS Capability 5.7: Population Health and Clinical Data Linkage

NCRIS Capability 5.7: Population Health and Clinical Data Linkage NCRIS Capability 5.7: Population Health and Clinical Data Linkage National Collaborative Research Infrastructure Strategy Issues Paper July 2007 Issues Paper Version 1: Population Health and Clinical Data

More information

3. Existing uncertainties

3. Existing uncertainties Fig. 1. Cumulative and annual offshore wind installations [1]. sector, some uncertainties have not been identified yet; these will be discussed in the paper with the aim of achieving an adequate and sustainable

More information

Latin-American non-state actor dialogue on Article 6 of the Paris Agreement

Latin-American non-state actor dialogue on Article 6 of the Paris Agreement Latin-American non-state actor dialogue on Article 6 of the Paris Agreement Summary Report Organized by: Regional Collaboration Centre (RCC), Bogota 14 July 2016 Supported by: Background The Latin-American

More information

Onshore & Offshore Engineering and Management of Subsea Cables and Pipelines

Onshore & Offshore Engineering and Management of Subsea Cables and Pipelines Established in 1997, Primo Marine is an independent specialist with a wealth of experience in subsea cable engineering, from landfalls to subsea marine infrastructures. With an extensive track record,

More information

BONUS EEIG- (Article 185, ex.169) the Joint Baltic Sea Research and Development Programme

BONUS EEIG- (Article 185, ex.169) the Joint Baltic Sea Research and Development Programme BONUS EEIG- (Article 185, ex.169) the Joint Baltic Sea Research and Development Programme MedSpring workshop, Beirut, 11/12.07.2013 Dr. Ulrich Wolf, PtJ-MGS National BONUS Contact Point for Germany 8 EU

More information

Given FELA s specific expertise, FELA s submissions are largely focussed on policy and law issues related to inshore fisheries.

Given FELA s specific expertise, FELA s submissions are largely focussed on policy and law issues related to inshore fisheries. Environmental Law Association Association 22 Dhanji Street Samabula, Suva Phone: (679) 330 0122 Fax: (679) 330 0122 Website: www.fela.org.fj FELA SUBMISSION TO THE NATIONAL FISHERIES POLICY FELA The primary

More information

Orkney Electricity Network Reinforcement Stakeholder Consultation Response. August 2014

Orkney Electricity Network Reinforcement Stakeholder Consultation Response. August 2014 Orkney Electricity Network Reinforcement August 2014 Introduction In February 2014 Scottish and Southern Energy Power Distribution 1 (SSEPD) undertook a stakeholder consultation Connecting Orkney: Electricity

More information

The Energy Sector of the Blue Economy Kristian Petrick eco-union

The Energy Sector of the Blue Economy Kristian Petrick eco-union The Energy Sector of the Blue Economy Kristian Petrick eco-union Workshop, Marseille, 31 May 2017 Med Trends Report 2015 Getting an idea of the importance of the sectors (today vs. 2030 globally) 2 Energy

More information

DERIVATIVES UNDER THE EU ABS REGULATION: THE CONTINUITY CONCEPT

DERIVATIVES UNDER THE EU ABS REGULATION: THE CONTINUITY CONCEPT DERIVATIVES UNDER THE EU ABS REGULATION: THE CONTINUITY CONCEPT SUBMISSION Prepared by the ICC Task Force on Access and Benefit Sharing Summary and highlights Executive Summary Introduction The current

More information

RECOMMENDATIONS LDAC CONFERENCE ON EXTERNAL DIMENSION OF THE CFP LAS PALMAS DE GRAN CANARIA, September 2015

RECOMMENDATIONS LDAC CONFERENCE ON EXTERNAL DIMENSION OF THE CFP LAS PALMAS DE GRAN CANARIA, September 2015 RECOMMENDATIONS LDAC CONFERENCE ON EXTERNAL DIMENSION OF THE CFP LAS PALMAS DE GRAN CANARIA, 16-17 September 2015 GENERAL STATEMENTS 1. We recognise the progress made with the latest reforms to the exterior

More information

Baltic Sea Conference

Baltic Sea Conference Baltic Sea Conference 26/03/2015 Speech by Karmenu Vella - Commissioner for Environment, Maritime Affairs and Fisheries at the Baltic Sea Conference Kiel, Germany, 26 March 2015 Dear Minister, Dear Ms

More information

Rampion Offshore Wind Farm Meet The Buyer Event

Rampion Offshore Wind Farm Meet The Buyer Event Rampion Offshore Wind Farm Meet The Buyer Event 26 February 2014, Amex Stadium, Brighton Vaughan Weighill, Project Manager Presentation Overview 1. Introduction 2. Project Overview 3. Current Status 4.

More information