Phase I Preliminary Design Report - FINAL

Size: px
Start display at page:

Download "Phase I Preliminary Design Report - FINAL"

Transcription

1 Phase I Preliminary Design Report - FINAL Riser Lifecycle Monitoring System for Integrity Management Contract November 18, 2014 Judith Guzzo, Principle Investigator, and Team: Uttara Dani, Brandon Good, Jeff Lemonds, Shaopeng Liu, John Carbone, Mike Volk GE Global Research One Research Circle Niskayuna, NY

2 Table of Contents Table of Contents...2 Executive Summary...3 Task 5- Overall RLMS System Design using TRL 5 & 6 Subsystems...4 Subtask 5.1 Voice of the Customer (VOC) Effort...4 Summary of Approach...4 Preliminary VOC Results...5 Initial Framework of Cost/Benefit Analysis...8 Subtask 5.2 Preliminary System Design and Risk Analysis for Key Subsystems Summary of Preliminary System Design for RLMS Summary of Failure Modes and Effects Analysis for RLMS Subsytems Subtask RFID Subsystem for Asset Identification for RLMS Initial Design Criteria for RFID in RLMS System Technical Approach Failure Modes and Effects Analysis Next Steps Subtask Subsea Sensing & Acoustic Telemetry Subsystem for RLMS Initial Design Criteria for Subsea Platform Technical Approach & Results Failure Modes and Effects Analysis Next Steps Subtask Vibration & Fatigue Analysis Methodology for RLMS Initial Design Criteria for Vibration and Lifing Analysis Technical Approach and Results Failure Modes and Effects Analysis Next Steps Subtask Software Management Subsystem for RLMS Initial Design Criteria Technical Approach & Results Failure Modes and Effects Analysis Next Steps

3 Executive Summary The objective of this two-phase project is to develop an integrated, reliable, and commercially viable solution for a real-time, telemetry-based marine Riser Lifecycle Management System (RLMS). RLMS is an integrated system of hardware and software tools comprised of sensors located on select riser joints, wireless subsea communication between the vessel and select instrumented risers, and software for data collection, processing, riser fatigue analysis, visualization and alerts for enhanced operational decision-making for contractors and operators. The initial focus is on drilling risers but this technology could translate to production risers. Summarized herein are initial Phase I results which focus on the RLMS technical solution design, development, and risk retirement. Initial end-user requirements for an integrated structural riser monitoring system design were obtained using Voice of the Customer (VOC). This information was collected from drilling contractors, an offshore classification society, and riser offshore engineering manufacturer subject matter experts. Using Six Sigma methodology, this VOC was then translated into preliminary system user requirements for a RLMS System, and functional design specifications for select subsystems using a Quality Function Deployment (QFD) tool. An initial framework for a cost-benefit analysis (CBA) is presented to evaluate all relevant costs and benefits of the RLMS solutions, with the goal to quantitatively assess whether oil and gas users, public and private enterprises, and government agencies would experience a net benefit from the proposed RLMS solution (note, the formal CBA will be completed in Phase II). For each RLMS subsystem, the initial design criteria based upon the VOC is presented. This is followed by the preliminary system design, technical approach, initial test results, failure modes risk analysis (FMEA) results and next steps. The key RLMS subsystems are RFID, subsea sensors, acoustic communication, vibration and fatigue analysis, topside software and architecture. Operational considerations such as RLMS system installation and maintenance are considered as well. 3

4 Task 5- Overall RLMS System Design using TRL 5 & 6 Subsystems Subtask 5.1 Voice of the Customer (VOC) Effort Summary of Approach For the preliminary Riser Lifecycle Monitoring System (RLMS) design, the team identified key stakeholders for Voice of the Customer (VOC) input into a structural riser monitoring system for deepwater marine drilling. Initial VOC was obtained from drilling contractors, an offshore classification society, and riser offshore engineering manufacturer subject matter experts. Benefits and innovation of this system include: 1. Modular and open subsea platform approach - for ease of installation, near real time data backhaul with acoustic telemetry and open sensor Input and Output for commercial-off-the-shelf (COTS) sensor integration. This system will produce highquality, time-synchronized measurements of riser response to environmental and operational excitation at several discrete subsea sensor data logger installation points along the riser length 2. Economical sensor node placement to reduce impact on riser running operations and address criteria in Cost-Benefit Analysis. 3. Intelligent Decisioning System for Continuous Calculation of Fatigue Damage and Key Performance Indicators - for enhanced visibility during drilling operations, to identify highly fatigued riser joints and optimize riser configuration post extreme events. Display real-time frequency and time measurements. Display fatigue damage rate and cumulative damage estimates at any elevation and angle around the riser circumference, along with intermediate results (excited modes, modal contribution to vibration, etc.) at specified intervals (e.g. hourly). 4. Performance-based Inspection Track the accumulated fatigue damage on a perjoint basis, to aid in joint rotation and optimize inspection schedule & estimate remaining useful life (re: condition- based monitoring). The above features and benefits enable realization of a Fleet Wide Lifecycle Management System as a tool to enhance safety, optimize drilling operations and future equipment design and provide information to the industry (OEM s, contractors, operators, regulatory) for data-driven inspection and maintenance of riser equipment. In Phase I of the program, the framework for a cost-benefit analysis (CBA) is being developed by Dr. Michael Volk, in conjunction with the GE team and WPG/Project Champion, to evaluate all relevant costs and benefits of the RLMS solution. The final analysis will be performed in Phase II (Task Business Model Analysis and Cost vs. Benefit Assessment). 4

5 Using Six Sigma methodology 1, the VOC was then translated into preliminary system user requirements for RLMS, and functional design specifications for the Subsea Sensor Platform using a Quality Function Deployment (QFD) tool. This tool is a quantitative mechanism to translate customer needs into prioritized technical requirements and facilitates communications of Customer-to-Quality needs and design (CTQs) between the key stakeholders (e.g. customer, business and technical team) and reduces risk of program delays. This iterative process will be used to refine and validate the Riser Lifecycle Monitoring System (RLMS) user requirements and product functional design specifications during the remainder of the program (Phase I and II) with additional stakeholders and SME s. From this VOC, an initial framework for a cost-benefit analysis of the proposed preliminary solution design has been developed. Objectives of the VOC are to obtain an understanding of the following: Current challenges during drilling operations Expected value & benefits Actions that can be taken based on a near real time monitoring system System installation & maintenance needs (e.g. operationalization requirements) Expectations for system requirements/functionality Economics/Return on Investment (ROI) Preliminary VOC Results A prioritized summary of customer needs from the VOC includes: 1. Enhance Operations & Reliability Provide high availability to drill Keep riser in service (e.g. how much longer can risers stay in service compared to expected design life?) Facilitate planning of riser configuration Increase operational window and monitoring of safety margins 2. Impact Inspection and Maintenance (I&M) schedules Condition based maintenance of deployed and stored equipment Performance based Inspection: o Accurately measure, record and evaluate riser utilization and inspection criteria (Table 1) 5

6 Table 1: Summary Inspection Criteria and Riser Utilization Criteria Impacted by Riser Monitoring System 3. Easily retrofit and install on existing risers Minimal impact on operations 4. Real time loads & tension near wellhead Risk aversion strategy (e.g. reduce uncertainty in variation in tensioners/ ability to accurately monitor & calculate tension in the riser at key points) Maintain integrity of well head 5. Cost effective Translate benefits to ROI 6. Rugged, reliable & accurate system Environmental deployment (e.g. at 10,000 ft), operational handling & storage conditions 7. Intuitive User Interface (UI) with actionable information Visibility of real time critical information to operator Present results of analysis of relevant data to rig crew in real-time in a comprehensive way, and such that the rig crew can optimize the rig and riser operation, compare with operating limits, and take necessary action to avoid exceeding the specified operating limits These prioritized customer expectations are summarized below in Table 1, and are used to construct the first House of Quality (House 1) which translates Customer Needs into RLMS System Requirements (Figure 1). 6

7 Table 2: Summary of Initial Customer Expectations for Riser Monitoring System 5= high importance 3= medium importance 1= low importance House 1 System CTQs (Xs or HOWs) Customer Expectations (Ys or WHATs) Importance Real-time advisory Information for riser operations Ability to retrofit and install on existing installatio 5 H H M M M 135 Enhance operations reliabilty (e.g. Impact oper 5 H H H 135 Impact inspection & maintenance schedules wit 5 H M M M M 105 Rugged, reliable and accurate system 5 H H H H 180 Cost effective 3 M H 36 Simple, intuitive, easy-to-understand user exper 3 H 27 Total Online stress and fatigue level estimation Easy, tetherless installation Mimimal impact on existing operations, processes Rugged construction of system Sufficient system operation life Reduce uncertainty in variation of riser tensioner, well head loads, etc. Low cost ownership Actionable info with varing information levels depending on user roles Total Figure 1: Translation of Customer Needs into Initial System Design Requirements for Riser Monitoring System 7

8 A Pareto diagram of prioritized system requirements for a RLMS System (Figure 2) highlights attributes key to a successful system design that will be accepted by the industry (e.g. easy, tetherless installation that does not interfere with existing riser operations). This process will continue to be refined and validated by industry SME s throughout the program. Figure 2: Pareto of Prioritized System Requirements for Riser Monitoring System Initial Framework of Cost/Benefit Analysis As part of Phase II (Task Business Model Analysis and Cost vs. Benefit Assessment) of the program, the GE team, in conjunction with Dr. Michael Volk, will conduct a rigorous cost-benefit analysis (CBA) to evaluate all relevant costs and benefits of the RLMS solution. The goal is to quantitatively assess whether oil and gas users, public and private enterprises, and government agencies would experience a net benefit from the proposed RLMS solution. The methodology entails the systematic estimation of all benefits and all costs of a contemplated course of action in comparison with alternative courses of action. Note the framework for the CBA is being developed in Phase I, including the criteria information drilling users will see (Figure 1), and the formal CBA will be performed in Phase II. CBA considers both gains and losses to all members of the community, including offshore oil and gas users, public and private enterprises, and government agencies, who are affected by the project. This analysis will not concentrate solely on the financial implications of a project but other tangible and intangible externalities that must be assessed. The analysis for this project will include a forecast of the costs and benefits of each option (i.e. without project and with-project, e.g. incorporating GE s RLMS for Integrity Management) to convince end users to implement the operational improvements. In developing a CBA model for this project, the following key elements will be included: 8

9 Scenario A: Benchmark or base case or without-project scenario which represents the current level of service Scenario B: Case with Riser Lifecycle Monitoring System implemented for drilling contractor and/or operator Planning period/horizon Identification and estimation of costs over the planning period including operating expenditure (opex), capital expenditure (capex), social and environmental costs for the RLMS Solution Provider (RLMSP). Table 3 highlights example of the tangible and intangible costs that will be used: Table 3: Examples of Tangible and Intangible Costs in Framework for CBA Tangible Costs (monetary) Price of equipment (CAPEX) Start-up fees (Development costs) Licenses Shipping, handling and transportation costs Operating expenses (OPEX) Field trials Testing Maintenance Staffing costs (wages, training, etc.) Real estate (rental offices, etc.) Insurance and taxes Utilities Intangible Costs (non-monetary) Cost of time spent on project Imperfect processes Cost of energy spent on project Cost of adjusting an established routine Cost of any lost business during project implementation Risk factor value for safety and customer loyalty Market saturation or penetration from uncertainties Influence on one s reputation Identification and estimation of the benefits for a Riser Lifecycle Monitoring System, to customers and society as a whole over the planning period (expressed in terms of monetary benefits, cost savings or both). Potential project benefits would include:. Income produced (increased sales) Money saved (expense reduction/decreased cost of service) reduced service and maintenance cost Time and effort saved (productivity savings) Repeat customer business Referrals, customer satisfaction, happier employees, a safer workplace Operate in increasingly deeper and harsher environments Reduced likelihood of event occurrence, enhance safety Risk and sensitivity analysis to integrate risk and uncertainty into the framework. An initial framework for this analysis is under development as part of Phase I to ensure the team gathers critical information (e.g. hardware, software, labor costs, and potential benefits) relevant to the analysis. 9

10 Subtask 5.2 Preliminary System Design and Risk Analysis for Key Subsystems Summary of Preliminary System Design for RLMS Based on initial VOC and identification of initial System Design Requirements (Figure 1), the following enabling technical design elements for the RLMS solution are required: 1. Radio-Frequency Identification (RFID) to automate marine riser identification and to enable topside riser analytics, riser pedigree, and Condition Based Maintenance (CBM) 2. Subsea Sensing and Communication for marine riser monitoring and near real time tetherless data transmission, and to enable CBM 3. Vibration and Fatigue Analysis for topside surface alerts during drilling operations and for estimated riser life prediction 4. Topside Software for data acquisition, RLMS analytics and intuitive user interface Figure 3 summarizes these design elements, highlighting functionality of the Subsea Sensing and Acoustic Platform and the underwater and surface analytics. Detailed design elements, risk assessment and next steps in Phase I for each subsystem are described in subsequent sections of this report. Figure 3: System Design for RLMS based on VOC 10

11 The QFD process was used to translate output from House 1 (Figure 1) into Subsystem Product Design specifications. By example, this is shown for the Subsea Sensing and Acoustic Platform (Figure 4). House 2 System CTQs (Xs or HOWs) Product Fuctionality Importance Wireless/acoustic communication from subsea to surface Battery powered Report extreme events, high tension/stress occurrences along the riser Measure acceleration and angle at selected locations on the riser Easy, tetherless installation 5 H H M L 110 Mimimal impact on existing operations, process 5 H H H H M 195 Online stress and fatigue level estimation 5 H H H H H M L 245 Real-time advisory Information for riser operatio 5 H H H H H M M L 260 Reduce uncertainty in variation of riser tensione 5 H H H 135 Rugged construction of system 5 H 45 Sufficient system operation life 5 H H L 95 Actionable info with varing information levels de 3 H H 54 Low cost ownership 3 M M H 45 Total Monitor/estimate the actual tension at riser tensioner Measure/estimate loads at critical locations, e.g., wellhead, slick joint, flex joint, etc. Rugged system packaging that is resistant to tough handling: "roughneck", and withstand ru Low overall/equivalent system supply current Simple attachment mechanism, e.g., magnetic installation, or ROV deployable Interface to external existing sensors on the riser Platform generic HW/SW design, not customized, suitable for various riser types Reconfigurable SW user interface SW platform that allows customized SW development Energy harvesting Total Figure 4: Translate System Requirements for Riser Monitoring System to Functional Design Specifications for Subsea Sensing and Acoustic Platform 11

12 House 2 Pareto Wireless/acoustic communication from Battery powered Report extreme events, high Measure acceleration and angle at Monitor/estimate the actual tension at Measure/estimate loads at critical Rugged system packaging that is resistant Low overall/equivalent system supply Simple attachment mechanism, e.g., Interface to external existing sensors on Platform generic HW/SW design, not Reconfigurable SW user interface SW platform that allows customized SW Energy harvesting Figure 5: Pareto of Functional System Requirements for Subsea Sensor Platform A Pareto diagram (Figure 5) of the prioritized Functional System Requirements for the Subsea Platform highlights functionality key to a successful RLMS system design that will be accepted by the industry. Again, this process will continue to be refined and validated by industry SME s throughout the program. Summary of Failure Modes and Effects Analysis for RLMS Subsytems A Failure Modes and Effects Analysis (FMEA), or risk analysis, was performed by the team for the following six key categories: (1) RFID, (2) Subsea sensor package, (3) Subsea acoustic communication, (4) vibration and lifing analytics, (5) Topside data acquisition and software and (6) System installation and maintenance. The team rated each risk by severity, probability and detectability, with the following definitions for each: Sev = Severity of consequences if failure mode activates 1: minor performance loss 2: results in partial system malfunction 3: renders product unfit for service OR could cause injury OR dissatisfies customer Prob= Probability of occurrence of failure mode 1: very low probability 2: occasional occurrence 3: very likely to occur Detect = Detectability of activation of failure mode 1: defect is obvious or detection process can be automate 2: detection requires manual inspection 3: defect is not detectable OR difficult or expensive to detect RPN = Severity x Probability, with note of Detectability-rating 12

13 From the 66 risks identified (Figure 6), 3 emerged as high Probability and high Severity (red), and 14 risks emerged as medium or high Probability and medium or high Severity (orange). Risk mitigation plans were assigned to each potential failure mode. Probability Severity L M H H M L Figure 6: Output Summary from FMEA on RLMS Table 4 provides the details for the 17 High and Medium-High Priority Risks. These are the focus for Phase I and Phase II of the program. Detailed discussion for key subsystems is discussed in subsequent sections of this document. Table 4: Summary of High and Medium-High Priority Risks for RLMS HIGH PRIORTY (3 Risks) System Installation & Maintenance Risk / Failure Mode Sev Prob Detect RPN Batteries run out during drilling campaign Acoustic Communication buoyancy module blocks acoustic link Acoustic Communication Transducer beam pattern not appropriate Acoustic Communication excessive acoustic noise from working enviroment MED HIGH PRIORTY (14 risks) Vibration & Lifing Analytics Data screening not accurate Vibration & Lifing Analytics Vibration & Lifing Analytics Ocean currents only measured to a certain depth Unavailability of real time ocean current/velocity measurements Vibration & Lifing Analytics Complex components (BOP, LMRP) not modeled or fidelity is too low TopSide Data Acquisition System and Software No data in Historian TopSide Data Acquisition System and Software Bad data in Historian System Installation & Maintenance HW system leaking saltwater System Installation & Maintenance broken cabling Acoustic Communication Transducer beam pattern not appropriate Acoustic Communication No certification to perform field testing Subsea Sensor Package not enough sensor sampling data for analytics Subsea Sensor Package sensors installed to insensitive location Subsea Sensor Package can't reliably detect events of interest by customer (e.g. real time tension near wellhead) RFID modification of riser for tag (e.g. drill holes)

14 Since System Installation & Maintenance is not one of the five technical areas discussed in this document, the FMEA is shown below (Table 4). The FMEA is an iterative process which will be updated and refined through the life of the program by the WPG and project champion. Table 5: FMEA Results for System Installation & Maintenance Saftey Risk / Failure Mode Sev Prob Detect Issue? RPN Risk Mitigation Plan Create procedure for power loss & replacement. Batteries run out during drilling campaign Develop/Optimize the battery model HW system leaking saltwater Robust sensor node packaging design and testing Broken cabling SOP with customer & HW certification Sensor package interferes with riser depoyment Sensor packaging design with O&G Chief engineer Batteries run out after 1 drilling campaign Create procedure to evaluate power state (e.g. visual, etc) & process for device or battery replacement Hardware disconnects SOP for HW setup and training plan for HW I&M Don't meet regulatory requirments/certification for field trial Review cert. requirements with customer & DNV Modem function unreliable or impared without firmware updates Create procedure for firmware updates Dead subsea modem SOP for predeployment testing of modems Subtask RFID Subsystem for Asset Identification for RLMS RFID technology will be utilized to identify each riser section for the drill string and to enable topside riser alerts and analytics (condition-based maintenance). RFID is an enabler to automate processes such as riser string reading and configuration, and enable the analytics and riser pedigree/utilization. Complete hardware and software solutions are not readily available on the market today for this application (e.g. stationary readers for automated reading during string deployment). Some development work thus far has been done by riser or drill pipe manufacturers, and they are selling the technology as part of their commercial riser systems. solutions. Since RFID technology is relatively mature and has lower technical risk compared to other RLMS sub-systems (e.g. vibration and fatigue analytics), the objective for this RLMS subsystem is to evaluate existing ruggedized RFID hardware for riser identification and incorporate the tag data into the overall RLMS being developed. Initial Design Criteria for RFID in RLMS System The following are initial design criteria to address customer CTQ s identified in Table 1: 1. RFID Reader will be handheld and dockable 2. RFID Reader battery life will last for an entire drilling campaign (3-6 months) 3. RFID Reader will be ruggedized and water resistant

15 4. RFID Tags will attach to the riser without requiring modifications 5. RFID Tags will withstand 5,200 PSI and F 6. RFID Tags will be passive (no battery) 7. RFID Tags will read from 2ft away 8. RFID Tag placement will not interfere with riser operations 9. Riser sections will be scanned during staging before going to the spider Technical Approach The RFID system will consist of a handheld reader and RFID tags attached to each riser section. The tags will be attached to each riser before the riser string assembly process is started. Each tag will be associated with the riser s unique ID and stored in the backend system. At the beginning of the riser string assembly process, the handheld will start a new riser string build list. The rig worker will use the handheld to scan each riser section as it is being selected to add to the riser string. The handheld will add the scanned tag to the riser string build list. At the end of the riser assembly process, the handheld will have a complete build list of the riser sections and the order they are connected. The handheld will be docked and the riser string build list will be uploaded to the onsite workstation. This file will be utilized by the vibration & fatigue analysis software. After an extensive analysis of RFID Commercial-off-the-Shelf (COTS) technology based on the above design criteria, three systems have been down selected for purchase and lab testing (Table 6). Each system is from a different RFID frequency family (125 khz, MHz, 915 MHz) and will be tested and validated against the design criteria. Using a tradeoff matrix for quantitative assessment, the highest performing system will be implemented in the final solution. Table 6: Summary of Three RFID Systems for Lab Testing Failure Modes and Effects Analysis Table 7 shows the results of the FMEA performed for the RFID subsystem. A majority of the Failure/Risks are low severity/probability and do not require mitigation plans. Riser modification for tag installation emerged as the highest risk item. A majority of the RFID riser management solutions on the market require modification of the riser for installation. 15

16 This program and pilot will mitigate this risk be selecting an RFID system that can be attached without structural modification to the riser. Table 7: FMEA Results for RFID Subsystem Next Steps Risk / Failure Mode Sev Prob Detect Three RFID systems have been purchased and will be evaluated in our lab. 1. Develop lab test plan and conduct lab testing; down-select top RFID subsystem based on design criteria: a. System performance b. mechanism to attach tags to riser section 2. Write handheld application to collect tag IDs and build riser string list., This application will have a simple User Interface for the rig crew user. 3. Develop Docking Solution and Test Upload Process 4. Develop SOP for RFID system operation 5. Plan for field trial testing and vendor validation (Phase II) Subtask Subsea Sensing & Acoustic Telemetry Subsystem for RLMS Initial Design Criteria for Subsea Platform Saftey Issue? RPN Risk Mitigation Plan riser modification for tag (e.g. drill holes) Pick RFID technology that doesn't require modification HH battery dies Have extra charged batteries on hand HH User Operation error Simple User Interface-- SOP's HH reads too many tags Chose tag technology/size to limit read distance electrostatic discharge from HH Y 3 Get Ruggedized ATEX Reader tag interferes with riser operation Get VOC for tag placement Drillstring out of sequence Notify user that wrong section has been selected riser failure due to tag placement Avoid modifying the riser to attach tag equipment damaged by dropped HH Y 3 Tether HH to User HH will not read tag Move closer to the tag lost riser string build file system testing & validation; SOP for operator dock HH fails system testing & validation; SOP for operator HH freezes - data lost system testing & validation; SOP for operator HH breaks / drop HH into water system testing & validation; SOP for operator tag installed on wrong riser SOP for operator tag stops reading system testing & validation; SOP for operator tag falls off riser system testing & validation; SOP for operator The primary customer expectations (Table 1) in the preliminary QFD design (Figure 1) drive the system CTQs and define the initial design criteria for the Subsea Platform: 16

17 Integrated Acoustic telemetry, allowing real-time or near real-time condition monitoring and alerts A modular platform, integrating commercial off-the-shelf (COTS) motion sensors (accelerometer + gyro), interfaces for additional sensor data acquisition, processing capability for customized edge computation and analytics, wireless communication, storage for data backup when wireless not present, battery, and marinized pressure vessel/casing Plug-and-go and battery powered, eliminating the requirement of auxiliary cabling, and minimally impacting existing operations Open OS environment on the processor, allowing customized software application development for interfacing with additional sensors, performing signal processing, and edge analytics. These features differentiate the proposed Subsea Platform from existing products. Note that the detailed specifications will depend on the overall design of the entire RLMS system, considering both the Subsea Platform and the vibration and fatigue analysis, with the goal of optimizing the system battery life and analysis performance. Technical Approach & Results The Subsea Platform uses a modular design approach, aiming to provide a plug-and-go system for easy installation and minimal impact on existing operations. The platform consists of the following seven components, as seen in the system architecture (Fig. 7), where COTS components are leveraged as much as possible for optimized cost: Acoustic Modem and Transducer. The subsea platform will integrate an acoustic modem with transducer attached enabling underwater wireless communication to the topside of a drilling vessel. The subsea platform leverages the acoustics for data transmission from the subsea platform to the topside data center, as well as for platform management and control when needed. Micro-Modem 2, a small-footprint, low-power acoustic modem developed by the Acoustic Communications Group at the Woods Hole Oceanographic Institution (WHOI), is being evaluated for integration in the Subsea Platform. A COTS acoustic transducer was selected from those on the market by considering the specific beam pattern design in the actual ocean environment. Battery. A rechargeable Li-ion battery will be used to power the subsea platform and eliminate the use of auxiliary cabling. A detailed and scalable battery model is being developed to estimate and optimize the Subsea Platform battery life. Various aspects of the RLMS system specifications have been factored into the model, such as the sensor data sampling interval, sampling duration, and sampling rate, as well as the selection of the acoustic transmission power level, transmission rate, etc. Depending on the choice of the above system specifications and the intended battery life, the battery model will output the estimated battery size/capacity, and vice versa. 17

18 Potential risks of overheating in the subsea platform are minimal, primarily due to 1) the colder subsea environment becomes a natural heat sink, and 2) the electronics in the subsea platform, which are mostly COTS components, have been used in many subsea deepwater applications by the vendor, Woods Hole Oceanographic Institution. As such, WHOI have not observed issues related with heat generation. Sensors and Sensor Interfaces. Each subsea platform will consist of two motion sensors: one triaxial accelerometer and one triaxial gyroscope (angular rate sensor). Together with the vibration and fatigue algorithms (Subtask 5.2.3), it is expected that loads and stresses at different sections of the risers and related fatigue levels will be calculated using the motion sensor data. Both the accelerometer and gyroscope are COTS components with high sensitivity for the low vibration conditions of drilling risers. The Subsea Platform will also have additional sensor interfaces such as serial/rs232 connections, I2C/SPI digital interfaces, analog-todigital conversion I/O, etc., that are open to end users to connect existing field sensors to provide real-time visibility for topside control. Microprocessor. A single board computer will serve as the edge intelligence of the subsea platform, and will control the acquisition of the sensor data, perform signal processing and/or algorithms on the collected data as needed, manage the acoustic communication protocol, data backup/storage, and power management. The open Operating System (OS) on the microprocessor will provide spaces for users to develop customized software applications, e.g., user specific analysis on the sensor data. The microprocessor will also host flash memory allowing secondary data backup and storage in case of situations when the acoustic link is down. Figure 7: Subsea Platform System Architecture 18

19 System Functionality Testing & Preliminary Results A laboratory test setup has been prepared for the Subsea Platform system functionality testing. The block diagram is shown in Figure 8. To streamline lab testing, one subsea acoustic modem and one surface modem have been assembled in a benchtop modem box, between which Bayonet Neill Concelman (BNC) connectors are used to simulate a perfect acoustic channel. Real acoustic environments will be simulated by adding artificial noise into the BNC cable. A processor is connected to the subsea modem through serial connection, and an accelerometer and gyroscope are connected to the processor via the I2C interface. A laptop containing the acoustic communication protocol is connected to the surface modem via serial port. The laptop also hosts the user interface for topside data collection and display. Figure 9 shows the actual lab test setup, where (a) shows the test setup connection, (b) and (c) show the inside components of the setup. Additional laboratory experiments will test the communication protocol and sensor data collection accuracy. Figure 8: System functionality test setup block diagram 19

20 (a) (b) (c) Figure 9: Subsea Platform Laboratory Test Setup Failure Modes and Effects Analysis A FMEA has been performed to capture the potential failure modes and risks of the Subsea Platform. The FMEA was divided into two sections: the acoustic communication and the sensing platform. Table 8 shows the FMEA results for the sensing platform, and Table 9 shows results for acoustic communication, respectively. 20

21 Table 8. FMEA Results for Subsea Sensing Platform Risk / Failure Mode Sev Prob Detect RPN Risk Mitigation Plan Not enough sensor sampling data for Perform simulation together with the vibration team to analytics determine the analysis accuracy vs. the data sample size Perform simulation together with the vibration team to Sensors installed to insensitive location determine the analysis accuracy vs. the sensor location Can't reliably detect events of interest by Connect with customers to determine the event of customer interests Perform system integration testing at BTC to test the Sensor not attached to enclosure perfectly (as one rigid body) sensor installation mechanism and collected signal integrity Sensor falls off (inside packaging) Perform system integration testing at BTC to test the sensor installation mechanism and collected signal integrity Sensor fails due to damage Perform system integration testing at BTC to test the sensor installation mechanism and collected signal integrity Subsea processor fails / reboots Processor stress testing Sampling interval too long to capture Connect with customers/industry experts/ocean current instantaneous extreme event profiles to identify the proper event monitoring interval Perform simulation together with the vibration team to Sensors are inaccurate (not enough sensitivity) determine the analysis accuracy vs. the sensor resolution/sensitivity Perform simulation together with the vibration team to Vibration exceeds sensor range determine maximum possible acceleration Table 9. FMEA Results for Acoustic Communication Acoustic Buoyancy module blocks acoustic link Field testing with buoyancy module on riser joints Transducer beam pattern not appropriate Field testing with buoyancy module on riser joints Excessive acoustic noise from working Increase tx power & determine regulatory enviroment requirements (e.g. FCC) for maximum data Acoustic transuder interference by (or to) other systems Engagment with GE O&G and drilling contractors No certification to perform field testing Discuss with customer DNV and/or API to get clarity Corrupted data due to acoustic transmission from interference/noice Increase tx power & determine regulatory requirements (e.g. FCC) for maximum data transmission power Risk mitigation for failure modes with RPN values 6 will be the focus of efforts during the remainder of Phase I and in Phase II of the program. Laboratory tests and results on the subsea sensor module platform will be presented in the final Phase 1 report. Next Steps The next steps in the development of the Subsea Platform are: Rig testing will include attaching the subsea platform to a full scale riser joint to: 1) test the sensor signal integrity under controlled axial tension and bending loads, and 2) evaluate installation mechanism of the subsea platform. 21

22 Enhance the software functionality and capability, and define strategy and architecture for customized app development Build the transfer function for modeling the platform battery life with respect to the various system parameters Working with Woods Hole Oceanographic Institute (WHOI) to leverage their experience in underwater acoustic communication systems and vessel marinization (e.g. 12,000ft depths), define system marinization approach for a customized, pressurized enclosure for field testing Define strategy & plan for system installation on riser deployment operations Subtask Vibration & Fatigue Analysis Methodology for RLMS Initial Design Criteria for Vibration and Lifing Analysis The Riser Lifecycle Monitoring System (RLMS) will include state-of-the-art methodology for predicting fatigue damage based on data from real-time sensor measurements. Fatigue damage rate estimates will be updated frequently in order to adequately capture events that produce above-average fatigue damage. Figure 10 highlights a block diagram for RLMS inputs, key analysis process steps, and example operational alerts and recommendations, all at the individual riser joint level. For example, the system will display high-level plots to the rig operator showing how fatigue damage is actually accumulating during a drilling campaign relative to what is expected based on design specifications and known average ocean current levels in the drilling region. In addition to this enhanced visibility into the drilling operations, the system will make recommendations to the rig operator on how to optimize the riser configuration when fatigue damage estimates in some riser components reach high levels or after extreme events. Figure 10: Workflow for Riser Health Analytics with Example User Interface Outputs Several factors contribute to fatigue damage in deepwater risers, all of which are difficult to quantify with existing data. The primary factor responsible for fatigue damage is VIV vortex-induced vibration from ocean currents. Much uncertainty exists in the factors 22

23 responsible for VIV which makes fatigue damage prediction quite difficult. Deep water currents vary considerably in magnitude, direction and duration. In addition, high toptensions frequently need to be applied to the riser, yet precise quantification of the stresses produced by the cable tension is difficult. Load-sharing between the main pipe and auxiliary lines can cause mismatches in tension that magnify bending stresses at joints. High hoop stresses exist due to mud weight in the riser which can vary over time -- this affects the hydrodynamic response which is predicted by empirical models that have precision issues. Uncertainty also exists in many of the riser system inputs used in design. The ability to estimate fatigue damage rates from real-time sensor measurements, root mean square (rms) acceleration (ft/sec 2 ), can do much to alleviate concerns regarding the aforementioned uncertainties and to provide damage predictions that can be used with confidence when making decisions regarding inspection and maintenance actions. The RLMS system will provide continuous updates on key parameters related to the health of the riser string. These data will assist the rig operator with decision-making processes that affect drilling operations. The top-level parameters that will be continuously updated include: Maximum fatigue damage level in the riser assembly Average and maximum fatigue damage rates during the past day, week and month Planned and recommended time to the next inspection Remaining useful life based on accumulating fatigue predictions vs. design specs Estimated time-history of the axial force on the wellhead The continuous availability of such data will offer the rig operator an enhanced view of the effects of the current drilling operations on riser life metrics and will assist on decisionmaking processes related to performance-based inspection and maintenance. Several of these processes and related scenarios are discussed here, with many more arising in practice. Of primary importance is the identification of critical riser joints those which are aging faster than expected from a fatigue standpoint. These joints will be identified and highlighted in visual displays (Figure 11) and can be flagged for scrutiny during upcoming maintenance cycles. The system will display a plot of the highest level of fatigue damage rate, compared to expected design life, in the riser assembly and will recommend revisions to the next inspection date if the fatigue damage history warrants such action. 23

24 Figure 11: Identification and Display of Critical Riser Components at any Point in a Drilling Campaign The monitoring system will also provide continuous updates on how the fatigue damage history is affecting the next planned inspection interval and the remaining useful life. Structural integrity risks increase if inspections are performed too late, when fatigue damage levels are high. Conversely, the operator might decide to postpone or skip an inspection should the fatigue damage be observed to be accumulating much slower than anticipated. Figure 12 shows a point in time following a series of several drilling campaigns when the accumulated fatigue damage has reached a high enough level to prompt the system to recommend that an inspection be performed right away, even though the original plan did not call for an inspection for two more years. In addition to this alert, the system also identifies that if fatigue damage rates continue at the high recent levels, the remaining useful life will be reduced by six years. The system identifies five specific riser joints that have sustained high damage, and recommends that they either be repaired or replaced. Alternatively, when the riser string is reassembled at the next drilling field, those five joints can be swapped with riser joints that have sustained lower damage levels. In that case, even if ocean current levels remain high, the higher fatigue levels will occur in younger riser joints, thereby enabling the drilling contractor to restore much of the remaining useful life to the rest of the string that would otherwise have been lost. 24

25 Figure 12: Recommendation to Perform a Repair to Five Specific Riser Joints Following High Fatigue Damage Accumulations Conversely, if this riser string is moved to a new field in which the ocean currents are less intense than anticipated, the system may recommend that the next planned inspection interval be postponed or delayed. Figure 13 shows a scenario in which fatigue damage has accumulated more slowly than was anticipated, possibly allowing the planned inspection at 20 years of service to be skipped, with the next planned inspection to be performed at 25 years. In addition, the remaining useful life is shown to have increased considerably (assuming that average ocean current intensities remain the same). 25

26 Figure 13: Recommendation to Postpone an Inspection Based on Low Fatigue Damage Accumulation Rates A high-level view of the architecture of the RLMS system is shown in Figure 14. The use of the system is simple and effective, involving essentially just five steps (Figure 10), some of which are repeated in the continuous monitoring phase. The first step involves the specification of the initial riser configuration via a file that contains the unique ID (RFID) of each of the joints in the riser assembly. Once specified, the system retrieves geometric data (length, weight, inertia, etc.), material properties (Young s modulus, S-N curves for fatigue calculation, etc.) and buoyancy data on the riser components from a master database and builds an analytic model for vibration analysis. At that point, the model can be viewed, and sensor locations displayed (Step 2). The remaining three steps perform analysis using the periodic sensor measurements and provide the rig operator with displays of high-level results related to the instantaneous state of fatigue damage in the riser assembly. Each time the riser configuration changes, such as when joints are repaired or interchanged, or when the assembly is moved to a shallower area and fewer joints are needed, the riser configuration file must be updated (Step 3). The riser components with the highest damage at any point in time can be viewed in Step 4 and the state of the health of the riser string is displayed in Step 5. Detailed information, such as RMS stress and acceleration values, and ocean current velocities can also be displayed for each riser component. 26

27 Figure 14: RLMS Software System Architecture Technical Approach and Results This section presents information on the methodology for estimating stress and fatigue damage from sensor measurements. However, due to intellectual property considerations, some of the details behind the method are not discussed. The RLMS will have accelerometers attached at various locations along the riser to obtain real-time acceleration data. The accelerometer data will be conditioned to remove potential spurious points and to isolate the vortex induced vibration response from other dynamic responses. Data conditioning tools such as anomaly detection that use Gaussian processes to determine outliers and noise will be used to further clean the data prior to its use in fatigue life estimation. The algorithm to obtain the excited modes, amplitudes and fatigue damage estimates from these data is being developed through a semi-analytical approach using the software package Shear7. This state-of-the-art VIV analysis code will predict the modes, mode shapes and fatigue damage in response to vortex-induced vibration caused by ocean currents. The Shear7 recommended values were used for the input parameters in the Shear7 model and based on previous tests and literature (e.g. strouhal number, reduced velocity bandwidth, power cut off ratio and primary zone amplitude limit). In addition, the empirical lift coefficients are taken from Shear7 lift coefficient curves. The measured acceleration data will be used in conjunction with a data-matching algorithm to tune the parameters in the Shear7 model in order to obtain the highest-fidelity fatigue damage rate predictions possible. The number of sensors and their locations along the length of the riser will be determined through numerical studies in order to achieve the best possible 27

28 match between measured and predicted dynamic responses. Publicly available model test VIV data will be used to benchmark the algorithm. The prediction of the real-time fatigue damage using accelerometer data will be performed using two approaches. The first approach being developed assumes that the ocean current velocities are measured from the ocean surface to the mudline; this results in the highest level of confidence in the predictions. In this case, only the dynamic analysis parameters such as the Strouhal number, reduced velocity bandwidth, primary zone amplitude limit and power cut off ratio are needed to estimate the vortex shedding frequency and will be calibrated to predict the fatigue damage. Even if the ocean current velocities are measured only up to a certain depth, curve fitting algorithms can be used to estimate the ocean current velocity along the entire riser length. In the second method, the ocean current velocities are not directly measured. This approach is being included under the presumption that sensor data may not be available during some (presumably short) periods of the drilling campaign due to measurement errors or sensor equipment failure. Along with some tuning of the Shear7 parameters, this algorithm will estimate the ocean current velocities and in turn the stresses and fatigue damage, albeit at a somewhat lower level of fidelity than in the first approach. Failure Modes and Effects Analysis As mentioned previously, a detailed risk assessment was performed to identify risk items related to all tasks associated with the development of the riser life monitoring system. A sub-team of experts in the areas of vibration and life assessment then rated the severity of each failure mode related to lifing. The results of the risk assessment are shown in Table 9. 28

29 Table 9 Results of Initial Risk Assessment for Vibration and Lifing Analysis Risk / Failure Mode Sev Prob Detect RPN Risk Mitigation Plan Vib & Lifing Unavailability of real time ocean current/velocity measurements Methodology will include ability to estimate stress &damage rates when current data are absent. Data screening not accurate Use anomoly detection and data cleansing algorithm Methodology will include a hybrid approach in which Ocean currents only measured to a certain ocean currents are known only for a portion of the riser depth string. Complex riser system components (e.g. Blow out preventer, Lower Marine Riser Package) are not part of the model or the model fidelity System will include integration capability with a global is too low Third-party software vendor(s) fails to deliver working software for the inverse problem Incorrect VIV model inputs (material properties, parameters, etc.) Inability to model surface waves and vessel drift riser working analysis with package industry leader with VIV in package the field of VIV analysis and prediction. Current plans call for testing and delivery of all software in Q Data-matching methodology for estimation of damage rates from sensor data includes tuning of VIV analysis parameters over time. System will include integration capability with a global riser analysis package with VIV package Incorrect riser model / configuration RFID methodology used to track riser configurations Imminent failure from a single event unlikely; system will Rig operator misses / overlooks fatigue-driven display alarm when severe conditions occur. Miss on event calculated by RISERLIFE high wellhead tension could be critical. Next Steps The next step for vibration and fatigue analysis are to develop a reliable fatigue damage prediction model based on sensor measurements. A number of numerical tests based on available field data will be conducted to build a robust vibration and fatigue model that uses measured acceleration data to make fatigue damage estimates. These tests are designed to provide data in order to achieve the following goals: 1. Determine the relationship between the number of motion sensors (accelerometer, angular rate) along the riser vs. model accuracy. The modal data (natural frequencies and modeshapes) was obtained from Shear7. Obtain the minimum number of sensors that can be used to obtain a desired level of accuracy between model responses (calculated via Shear7) and measured responses. 2. Test model accuracy using different ocean current velocity profiles from publicly available data 3. Assess the model prediction capabilities with ocean current velocities up to certain depths. This includes curve fitting/estimation for the remaining part of the velocity profile. 4. Calibrate the Shear7 parameters such as the Strouhal number, lift coefficients etc. to assess their effects on fatigue damage predictions. 29

30 5. Determine the influence of the top tension and mud weight on the mode shapes and in turn on fatigue damage. These tests will guide the calibration of the model for use in obtaining reliable real-time fatigue damage estimates and help in identifying any additional sensor needs, such as the placement of strain gauges at critical locations. Subtask Software Management Subsystem for RLMS Initial Design Criteria The subsea structural monitoring system should provide sensor measurement data for real-time estimation of actual loads (e.g. tension, bending moments) and motions (e.g., displacements, inclinations, angles) 2 in selected locations of the marine drilling riser. It is desired to have relevant data from existing rig system (e.g. mud weights, top tensions, environmental data) integrated with the subsea data. It is desired to have results of analysis of all relevant data should presented to the rig crew in near real-time in an intuitive view, such that the rig crew can optimize the rig and riser operation, compare the status with operating limits, and take necessary action to avoid exceeding the specified operating limits. It is desired to have raw data stored in a redundant database for post retrieval, processing and analysis. In addition, select data can be transmitted to an onshore database server or data center, to allow onshore support personnel to monitor the operation in near real-time with similar views for the on-board crew. Initial detailed specifications include: i. manual route-based data collection instruments ii. iii. iv. online intermittent condition monitoring data on essential assets various interfaces to process control and automation systems for importation/exportation of key parameters and statuses manual data entry of notes, and links to pertinent asset documentation such as manuals, drawings, and maintenance logs v. engineered interfaces to industry accepted Computerized Maintenance Management System systems Technical Approach & Results The initial prototype version of the Riser Lifecycle Monitoring System (RLMS) software will be built using a mature GE engineering software tool, 3DFAS (3D Fracture Analysis System). 3DFAS is a software engineering tool widely used across GE for fracture mechanics. Due to its ease-of-use and streamlined user interface design methodology, it was selected for development of the prototype RLMS Software, RiserLife, for near real time operational visibility and fatigue life assessment of deep water risers. 30

31 A review of the goals and objectives of 3DFAS and its software architecture is presented in this section, along with a discussion of the benefits of using 3DFAS. As background, 3DFAS evolved as an efficient and easy-to-use software framework for fracture mechanics based analysis of cracks in engineering structures. This tool facilitates the process of inserting cracks into either solid geometric models or finite element meshes. The model is then discretized and a stress and fracture analysis is performed to obtain stress intensity values along the crack fronts. This allows the analyst to determine whether or not a crack in a component will propagate under design loading. If so, a crack advancement analysis can be performed to determine the total part life which is the sum of the crack initiation life and the crack propagation life. Development of 3DFAS began in 2003 and continues today. The tool has been used in numerous NPI programs and for determination of the root cause of critical fracture-related field issues at GE Aviation, Power & Water, Oil & Gas, and Consumer & Industrial. During development, the tool has undergone about a dozen formal tollgate reviews under the auspices of GE s Software Tools Center of Excellence. It is built on a solid software foundation of C++ and Microsoft s foundation classes. Two versions of the tool are available: a 32-bit GUI version for the Windows operating system, and a 64-bit Linux version for use in GE s HAL cloud-computing environment. DOEs in which crack size parameters vary can be set up and run in batch-mode with either version. A diagram of the 3DFAS system architecture is shown in Figure 15. Figure 15: 3DFAS System Architecture The software architecture of 3DFAS has been used as the foundation for approximately 10 other visual engineering analysis codes, including oxidation lifing for coated metal airfoils, blade scrap rate prediction for Aviation services, and rotor lifing for steam turbines. As a result of ease and speed in which other tools can be built upon the 3DFAS software foundation, the decision was made to use 3DFAS for the foundation of the prototype of the 31

Riser Lifecycle Monitoring System (RLMS) for Integrity Management

Riser Lifecycle Monitoring System (RLMS) for Integrity Management Riser Lifecycle Monitoring System (RLMS) for Integrity Management 11121-5402-01 Judith Guzzo GE Global Research Ultra-Deepwater Floating Facilities and Risers & Systems Engineering TAC meeting June 5,

More information

Riser Lifecycle Monitoring System for Integrity Management

Riser Lifecycle Monitoring System for Integrity Management Riser Lifecycle Monitoring System for Integrity Management 11121-5402-01 Judith Guzzo GE Global Research RPSEA Ultra-Deepwater Technology Conference October 29-30, 2013 Lone Star College Conference Center

More information

IADC Conference, RIO 2005 Fatigue Monitoring of Deepwater Drilling Risers. Mateusz Podskarbi, Ricky Thethi, Hugh Howells; 2HOffshore Inc

IADC Conference, RIO 2005 Fatigue Monitoring of Deepwater Drilling Risers. Mateusz Podskarbi, Ricky Thethi, Hugh Howells; 2HOffshore Inc IADC Conference, RIO 2005 Fatigue Monitoring of Deepwater Drilling Risers Mateusz Podskarbi, Ricky Thethi, Hugh Howells; 2HOffshore Inc How Far the Eye Reaches? Slide No. 2 Drilling Riser Fatigue Fatigue

More information

Latest Developments in Subsea Wellhead and Riser Fatigue Monitoring

Latest Developments in Subsea Wellhead and Riser Fatigue Monitoring Latest Developments in Subsea Wellhead and Riser Fatigue Monitoring Wellhead and Riser Fatigue Monitoring Background to wellhead fatigue measurement Off line data collection Real time data collection Examples

More information

Mitigation and Control of Wellhead Fatigue

Mitigation and Control of Wellhead Fatigue Mitigation and Control of Wellhead Fatigue Workshop Geotechnical Input to Well Integrity Assessment BP Helios Plaza Building (Houston ) 29 April 2016 Kim Mittendorf Kim.Mittendorf@vulcanoffshore.com Overview

More information

Single / Dual Barrier HP Drilling Risers

Single / Dual Barrier HP Drilling Risers Single / Dual Barrier HP Drilling Risers Acteon HPHT Subsea Community Breakfast Meeting 23rd March 2011 Tim Eyles Director 2H Offshore Engineering tim.eyles@2hoffshore.com / +44 1483 774908 Agenda Introduction

More information

Learn more at

Learn more at Design of a Monitoring System for Determining Subsea Wellhead Fatigue Utilisation Richard Baker Senior Engineer, 2H Offshore Engineering OI2016, London, March 2016 Agenda Why monitor subsea wellhead fatigue?

More information

Implementing FPSO Digital Twins in the Field. David Hartell Premier Oil

Implementing FPSO Digital Twins in the Field. David Hartell Premier Oil Implementing FPSO Digital Twins in the Field David Hartell Premier Oil Digital Twins A Digital Twin consists of several key elements and features: 1. A virtual, dynamic simulation model of an asset; 2.

More information

Mitigation of Wellhead and Conductor Fatigue Using Structural Monitoring

Mitigation of Wellhead and Conductor Fatigue Using Structural Monitoring Mitigation of Wellhead and Conductor Fatigue Using Structural Monitoring Dr. Pei An, Pulse Structural Monitoring Edward Elletson, Pulse Structural Monitoring Phil Ward, 2H Offshore Ltd ABSTRACT Wellhead

More information

Closing the Collaboration Gap

Closing the Collaboration Gap Closing the Collaboration Gap Technology for Improved Offshore Piping and Structural Analysis Projects Bilal Shah MSc Structural Engineering (Hons) Software Development Manager, Piping Mark Upston B Mechanical

More information

Lloyd s BOP Register energy Risk servicesmodel Project Development. Scotty Roper Project Manager Moduspec USA, Inc.

Lloyd s BOP Register energy Risk servicesmodel Project Development. Scotty Roper Project Manager Moduspec USA, Inc. Lloyd s BOP Register energy Risk servicesmodel Project Development Scotty Roper Project Manager Moduspec USA, Inc. October 18, 2012 Agenda Project summary Product demonstration Conclusion Who we are Lloyd

More information

DNV GL Marine Renewables

DNV GL Marine Renewables ENERGY DNV GL Marine Renewables De-Risking Technologies, Insurance and Certification: The Certification Role Claudio Bittencourt Business Development Director Wave & Tidal Renewables Certification International

More information

Deepwater Precommissioning Services

Deepwater Precommissioning Services Deepwater Precommissioning Services Featuring Denizen remote subsea technologies Drilling Evaluation Completion Production Intervention Pipeline & specialty services Nitrogen services Pipeline services

More information

OCS leasing program draft PEIS comments Attachment A

OCS leasing program draft PEIS comments Attachment A Effective Oversight Requires Key Legislative, Regulatory, Enforcement and Transparency Upgrades Analysis by Lois N. Epstein, P.E. Engineer and Arctic Program Director The Wilderness Society Anchorage,

More information

VIRTUS CONNECTION SYSTEMS Advanced Diverless Connection Solutions for any Subsea Field Application

VIRTUS CONNECTION SYSTEMS Advanced Diverless Connection Solutions for any Subsea Field Application VIRTUS CONNECTION SYSTEMS Advanced Diverless Connection Solutions for any Subsea Field Application 2 Virtus Subsea Connectors Delivering Long-Lasting Reliability at Each Subsea Connection Subsea production

More information

Using new monitoring and control technology to advance safety and asset integrity in the oilfield

Using new monitoring and control technology to advance safety and asset integrity in the oilfield Lloyd s Register Energy Conference Safety-driven performance 2012 Using new monitoring and control technology to advance safety and asset integrity in the oilfield Chris Tolleson Systems and Controls Chief

More information

MARKSMAN DP-INS DYNAMIC POSITIONING INERTIAL REFERENCE SYSTEM

MARKSMAN DP-INS DYNAMIC POSITIONING INERTIAL REFERENCE SYSTEM cc MARKSMAN DP-INS DYNAMIC POSITIONING INERTIAL REFERENCE SYSTEM Sonardyne s Marksman DP-INS is an advanced navigation-based Position Measuring Equipment (PME) source for dynamically positioned (DP) rigs.

More information

Recommendations for Improvements to Wellbore Surveying and Ranging Regulations

Recommendations for Improvements to Wellbore Surveying and Ranging Regulations Recommendations for Improvements to Wellbore Surveying and Ranging Regulations Presented at the Public Technology Assessment Program (TAP) Forum February 17, 2017 Prepared for: US Department of Interior,

More information

Advancing Global Deepwater Capabilities

Advancing Global Deepwater Capabilities Advancing Global Deepwater Capabilities BP s Commitment The Deepwater Horizon incident was a tragic accident that took 11 lives and impacted thousands of people and the Gulf environment Going forward,

More information

Integrity Management of Offshore Assets

Integrity Management of Offshore Assets OIL & GAS Integrity Management of Offshore Assets Opening session Leif Collberg 05 May 2017 1 DNV GL 2015 05 May 2017 SAFER, SMARTER, GREENER How regulations can solve the challenge of being performance

More information

Applications. > > Oil & Gas. > > RoVs and auvs. > > Oceanography. > > Monitoring stations. > > Seismic. > > Networks and relay chains

Applications. > > Oil & Gas. > > RoVs and auvs. > > Oceanography. > > Monitoring stations. > > Seismic. > > Networks and relay chains Underwater acoustic Modems EvoLogics S2CR - series underwater acoustic modems provide full-duplex digital communication delivering an excellent performance, resistant to the challenges of the dynamic subsea

More information

Subsea Wellhead System Design for Fatigue Performance

Subsea Wellhead System Design for Fatigue Performance Subsea Wellhead System Design for Fatigue Performance F. Justin Rodriguez 11 March 2015 11 March 2015 Subsea Drilling Services Introduction to Fatigue Mechanics of the failure Dislocations accumulate near

More information

Life Cycle Management of Station Equipment & Apparatus Interest Group (LCMSEA) Getting Started with an Asset Management Program (Continued)

Life Cycle Management of Station Equipment & Apparatus Interest Group (LCMSEA) Getting Started with an Asset Management Program (Continued) Life Cycle Management of Station Equipment & Apparatus Interest Group (LCMSEA) Getting Started with an Asset Management Program (Continued) Projects sorted and classified as: 1. Overarching AM Program

More information

Learn more at

Learn more at Deepwater Riser System Challenges and Issues David Walters 2H Offshore Presentation Objectives Review riser system options Update on current industry status Highlight key issues Discuss current industry

More information

UNIT-III LIFE-CYCLE PHASES

UNIT-III LIFE-CYCLE PHASES INTRODUCTION: UNIT-III LIFE-CYCLE PHASES - If there is a well defined separation between research and development activities and production activities then the software is said to be in successful development

More information

Design of a Piezoelectric-based Structural Health Monitoring System for Damage Detection in Composite Materials

Design of a Piezoelectric-based Structural Health Monitoring System for Damage Detection in Composite Materials Design of a Piezoelectric-based Structural Health Monitoring System for Damage Detection in Composite Materials Seth S. Kessler S. Mark Spearing Technology Laboratory for Advanced Composites Department

More information

Seatooth Pipelogger. Ian Crowther Executive VP WFS Technologies

Seatooth Pipelogger. Ian Crowther Executive VP WFS Technologies Ian Crowther Executive VP WFS Technologies About WFS Technologies WFS Wireless For Subsea Founded 2003 Operations in UK & USA Wireless Solutions Drilling Subsea Vehicles Asset Integrity Management Field

More information

Structure Deflection Monitoring System

Structure Deflection Monitoring System Structure Deflection Monitoring System Generation II All rights reserved. This document may be distributed within receiving entity (from RTS/Seatronics) and utilized as tender documentation. However, due

More information

Advances in Subsea Integrity Monitoring Systems. Ross Macleod Business Development Director, Ashtead Technology

Advances in Subsea Integrity Monitoring Systems. Ross Macleod Business Development Director, Ashtead Technology Advances in Subsea Integrity Monitoring Systems Ross Macleod Business Development Director, Ashtead Technology Introduction to Ashtead Technology The market leading independent subsea sensor and ROV equipment

More information

ROV Deployable Dynamic Curvature Sensor to Monitor Fatigue in Subsea Pipelines

ROV Deployable Dynamic Curvature Sensor to Monitor Fatigue in Subsea Pipelines ROV Deployable Dynamic Curvature Sensor to Monitor Fatigue in Subsea Pipelines December 1 st 2016 Subsea Asia 2016 Agenda Introducing the Dynamic Curvature Sensor INTEGRIstick Lessons Learned from not

More information

SPE A Systematic Approach to Well Integrity Management Alex Annandale, Marathon Oil UK; Simon Copping, Expro

SPE A Systematic Approach to Well Integrity Management Alex Annandale, Marathon Oil UK; Simon Copping, Expro SPE 123201 A Systematic Approach to Well Integrity Management Alex Annandale, Marathon Oil UK; Simon Copping, Expro Copyright 2009, Society of Petroleum Engineers This paper was prepared for presentation

More information

Marine Well Containment Company Outer Continental Shelf Summer Seminar

Marine Well Containment Company Outer Continental Shelf Summer Seminar Marine Well Containment Company Outer Continental Shelf Summer Seminar June 4, 2015 INTRODUCTION 2 Why We re Here In order to receive a permit to drill in the U.S. Gulf of Mexico, regulations require operators

More information

Offshore Wind Risks - Issues and Mitigations

Offshore Wind Risks - Issues and Mitigations DNV Offshore Wind Soren Karkov DNV an independent foundation Our Purpose To safeguard life, property and the environment Our Vision Global impact for a safe and sustainable future 2 More than 145 Years

More information

The Marine Well Containment System. LSU Center for Energy Studies Energy Summit 2010 October 26, 2010

The Marine Well Containment System. LSU Center for Energy Studies Energy Summit 2010 October 26, 2010 The Marine Well Containment System LSU Center for Energy Studies Energy Summit 2010 October 26, 2010 Restoring Confidence in Deepwater Drilling Operations Our initiatives are aligned with Administration

More information

June 24, 2010 RPSEA Project 1502 Thomas E. Williams int.com

June 24, 2010 RPSEA Project 1502 Thomas E. Williams  int.com June 24, 2010 RPSEA Project 1502 Thomas E. Williams www.nautilus int.com RPSEA 1502 Coiled Tubing from a Small Vessel June 2010 Update Presentation Topics Background Project Objectives System Configuration

More information

Machinery Health Monitoring and Power Scavenging. Prepared for WMEA. Presented by Lewis Watt November 15 th, 2007

Machinery Health Monitoring and Power Scavenging. Prepared for WMEA. Presented by Lewis Watt November 15 th, 2007 Machinery Health Monitoring and Power Scavenging Prepared for WMEA Presented by Lewis Watt November 15 th, 2007 RLW, Inc. 2007 All Rights Reserved An Open Platform for Condition Monitoring Any Transducer

More information

M. Kevin McEvoy. Oceaneering International, Inc. Chief Executive Officer 2015 GLOBAL ENERGY AND POWER EXECUTIVE CONFERENCE JUNE 2, 2015 NEW YORK, NY

M. Kevin McEvoy. Oceaneering International, Inc. Chief Executive Officer 2015 GLOBAL ENERGY AND POWER EXECUTIVE CONFERENCE JUNE 2, 2015 NEW YORK, NY 2015 GLOBAL ENERGY AND POWER EXECUTIVE CONFERENCE JUNE 2, 2015 NEW YORK, NY M. Kevin McEvoy Chief Executive Officer Oceaneering International, Inc. Safe Harbor Statement Statements we make in this presentation

More information

Abstract. 1. Introduction

Abstract. 1. Introduction IBP1572_09 REMOTE EROSION AND CORROSION MONITORING OF SUBSEA PIPELINES USING ACOUSTIC TELEMETRY AND WET-MATE CONNECTOR TECHNOLOGY Howard Painter 1, Stewart Barlow 2, Daniel Clarke 3, Dale Green 4 Copyright

More information

ENGINEERING INNOVATION

ENGINEERING INNOVATION ENGINEERING INNOVATION ENGINEERING INNOVATION Viper Subsea provides control system distribution solutions for the global subsea oil and gas industry. Our product and service offering covers the full life

More information

Offshore Support Vessels Located in the US Gulf of Mexico in March 2018

Offshore Support Vessels Located in the US Gulf of Mexico in March 2018 Offshore Support Vessels Located in the US Gulf of Mexico in March 18 IMCA March 1, 18 Prepared by IMCA The International Marine Contractors Association (IMCA) is the international trade association representing

More information

Well Control Contingency Plan Guidance Note (version 2) 02 December 2015

Well Control Contingency Plan Guidance Note (version 2) 02 December 2015 Well Control Contingency Plan Guidance Note (version 2) 02 December 2015 Prepared by Maritime NZ Contents Introduction... 3 Purpose... 3 Definitions... 4 Contents of a Well Control Contingency Plan (WCCP)...

More information

Conductor Installation Services. Today s technology traditional values

Conductor Installation Services. Today s technology traditional values Conductor Installation Services Today s technology traditional values Adding value to the conductor installation process Conductor Installation Services Ltd (CIS) installs well conductors and pile foundations

More information

Friction Grip in Wellheads: An Innovative Approach to Load Support & Sealing

Friction Grip in Wellheads: An Innovative Approach to Load Support & Sealing Friction Grip in Wellheads: An Innovative Approach to Load Support & Sealing Brent Harrald Principal Engineer Plexus Ocean Systems Ltd. December 2009 Page 1 Table of Contents Introduction Plexus Ocean

More information

Taking a broader view

Taking a broader view Taking a broader view A brief introduction to DNV GL 1 SAFER, SMARTER, GREENER We are a global classification, certification, technical assurance and advisory company 2 In a challenging world we make businesses

More information

Cathodic Protection & Monitoring

Cathodic Protection & Monitoring Cathodic Protection & Monitoring THE COMPLETE SOLUTION MEASUREMENT COMMUNICATION INSIGHT Contents Cathodic Protection Services 2 Consultancy 3 Systems 5 Monitoring 8 Insight 10 1 Aquatec was founded by

More information

Solution of Pipeline Vibration Problems By New Field-Measurement Technique

Solution of Pipeline Vibration Problems By New Field-Measurement Technique Purdue University Purdue e-pubs International Compressor Engineering Conference School of Mechanical Engineering 1974 Solution of Pipeline Vibration Problems By New Field-Measurement Technique Michael

More information

@balance Deepwater. MPD services

@balance Deepwater. MPD services @balance Deepwater MPD services Drill faster and reach farther with @balance Deepwater MPD services Achieve drilling objectives with closed-loop systems MPD provides a closed-loop circulation system in

More information

Life Extension of Subsea Umbilical Systems Assessment Process Marian Copilet Technical Solutions Manager - APAC November 2016

Life Extension of Subsea Umbilical Systems Assessment Process Marian Copilet Technical Solutions Manager - APAC November 2016 Life Extension of Subsea Umbilical Systems Assessment Process Marian Copilet Technical Solutions Manager - APAC November 2016 2016 Oceaneering International, Inc. All rights reserved. About Oceaneering

More information

Intelligent and Flexible Monitor Circuits Detect & Record Load Profiles and Fault Events All Distribution Voltages All Conductor Types

Intelligent and Flexible Monitor Circuits Detect & Record Load Profiles and Fault Events All Distribution Voltages All Conductor Types IQ Insulator Self-powered Line Sensor & Insulator with Wireless Communications Monitor System Performance & Reliability Load Profiling and Fault Recording & Indication Intelligent and Flexible Monitor

More information

On the Development of the Blowout Preventer PRA Model

On the Development of the Blowout Preventer PRA Model On the Development of the Blowout Preventer PRA Model Jan Swider *ac, Charley Gallo bc, Gregg Walz c, and Jim Raney c a Cogoto, Inc., Simi Valley, USA b The Frontline Group, Houston, USA c Anadarko Petroleum

More information

905U Wireless. New Products... New Solutions. The wireless alternative to expensive cabling... Simple but Reliable. Easy to Use

905U Wireless. New Products... New Solutions. The wireless alternative to expensive cabling... Simple but Reliable. Easy to Use Wireless New Products... New Solutions The range of telemetry modules provide remote monitoring and control by radio or twisted-pair wire, over short or long distances. Transducer signals connected at

More information

Delivering Subsea Solutions Using a Systems Engineering Approach

Delivering Subsea Solutions Using a Systems Engineering Approach Delivering Subsea Solutions Using a Systems Engineering Approach William Kilpatrick, PhD, CEng MIMechE February 2018 Agenda 1. Frazer-Nash Consultancy Overview i. Systems Engineering 2. Using a Systems

More information

The Oil & Gas Industry Requirements for Marine Robots of the 21st century

The Oil & Gas Industry Requirements for Marine Robots of the 21st century The Oil & Gas Industry Requirements for Marine Robots of the 21st century www.eninorge.no Laura Gallimberti 20.06.2014 1 Outline Introduction: fast technology growth Overview underwater vehicles development

More information

Developments in Deepwater Handling Systems. Gregor McPherson, Caley Ocean Systems

Developments in Deepwater Handling Systems. Gregor McPherson, Caley Ocean Systems Developments in Deepwater Handling Systems Gregor McPherson, Caley Ocean Systems Caley Ocean Systems Glasgow based, over 45 years experience of building bespoke handling systems for the Offshore industry

More information

Dry trees for cost effective solution with the Wellhead Barge: WHB

Dry trees for cost effective solution with the Wellhead Barge: WHB Dry trees for cost effective solution with the Wellhead Barge: WHB Benjamin MAURIES SAIPEM PAU, FRANCE 5 7 APRIL 2016 Dry Tree Solution for Mild Environments Dry Tree solutions have been developed and

More information

New Multi-Technology In-Line Inspection Tool For The Quantitative Wall Thickness Measurement Of Gas Pipelines

New Multi-Technology In-Line Inspection Tool For The Quantitative Wall Thickness Measurement Of Gas Pipelines New Multi-Technology In-Line Inspection Tool For The Quantitative Wall Thickness Measurement Of Gas Pipelines A. Barbian 1, M. Beller 1, F. Niese 2, N. Thielager 1, H. Willems 1 1 NDT Systems & Services

More information

Investor Presentation

Investor Presentation Connecting What s Needed with What s Next Investor Presentation September 2017 Forward-Looking Statements Statements we make in this presentation that express a belief, expectation, or intention are forward

More information

OBSERVATORY SERVICING AND MAINTENANCE

OBSERVATORY SERVICING AND MAINTENANCE OBSERVATORY SERVICING AND MAINTENANCE How to deploy and maintain a network of observatories around Europe? We don t built what we cannot maintain! Jean-François DROGOU IFREMER Steve ETCHEMENDY M.B.A.R.I

More information

Industry Response - Post Macondo

Industry Response - Post Macondo Industry Response - Post Macondo Charlie Williams Chief Scientist Well Engineering Shell Energy Resource Company CSIS Energy and National Security Program - future of offshore oil & gas developments in

More information

SWiG Subsea Wireless Group - Presentation to API

SWiG Subsea Wireless Group - Presentation to API Commercial in Confidence SWiG Subsea Wireless Group - Presentation to API January 14 Commercial in Confidence Agenda About SWiG What is the technology? Where is it used? SWiG family of standards Where

More information

Instrumentation and Control

Instrumentation and Control Program Description Instrumentation and Control Program Overview Instrumentation and control (I&C) and information systems impact nuclear power plant reliability, efficiency, and operations and maintenance

More information

Xylem Analytics. Ocean & Coastal Monitoring Solutions

Xylem Analytics. Ocean & Coastal Monitoring Solutions Xylem Analytics Ocean & Coastal Monitoring Solutions Coastal Research Environmental Monitoring Ferrybox Aquaculture System Integration Recovery Marine Transport Offshore Installation Oceanography Oil &

More information

Methods for Managing Customer Needs

Methods for Managing Customer Needs Methods for Managing Customer Needs Goal of this lecture Introduce you to three tools HoQ FMEA Requirements flowdown Understand the uses/problems of each Assignment Need to perform FMEA, HoQ and requirements

More information

Multi-channel telemetry solutions

Multi-channel telemetry solutions Multi-channel telemetry solutions CAEMAX and imc covering the complete scope imc Partner Newsletter / September 2015 Fig. 1: Schematic of a Dx telemetry system with 4 synchronized transmitter modules Introduction

More information

Subsea Production Market and Industry Teaming. Presented by: Bruce Crager Executive Vice President: Expert Advisory Group Endeavor Management

Subsea Production Market and Industry Teaming. Presented by: Bruce Crager Executive Vice President: Expert Advisory Group Endeavor Management Subsea Production Market and Industry Teaming Presented by: Bruce Crager Executive Vice President: Expert Advisory Group Endeavor Management February 28, 2017 Worldwide Progression of Water Depth Capabilities

More information

SC200 Series. Signal Conditioner MNX10020, REV H 10/17/ Connection Technology Center, Inc Rae Boulevard Victor, NY (585)

SC200 Series. Signal Conditioner MNX10020, REV H 10/17/ Connection Technology Center, Inc Rae Boulevard Victor, NY (585) SC200 Series Signal Conditioner MNX10020, REV H 10/17/2012 1 CONTENTS SECTION 1: OVERVIEW... 4 Introduction... 4 Description... 4 Ordering Information... 4 Specifications... 5 Environmental... 5 Electrical...

More information

41ST ANNUAL MARINE / OFFSHORE INDUSTRY OUTLOOK CONFERENCE GEOSCIENCE UPDATE: MR. ALAN M. BREED EVP SALES & MARKETING

41ST ANNUAL MARINE / OFFSHORE INDUSTRY OUTLOOK CONFERENCE GEOSCIENCE UPDATE: MR. ALAN M. BREED EVP SALES & MARKETING 41ST ANNUAL MARINE / OFFSHORE INDUSTRY OUTLOOK CONFERENCE GEOSCIENCE UPDATE: MR. ALAN M. BREED EVP SALES & MARKETING AGENDA GEOSCIENCE UPDATE Market Outlook Financial Overview Regulatory Issues Technology

More information

Offshore Drilling Rigs

Offshore Drilling Rigs Offshore Drilling Rigs Drilling Offshore Drilling Rigs Many of the world s potential reserves of hydrocarbons lie beneath the sea, and the hydrocarbon industry has developed techniques suited to conditions

More information

Advancing Global Deepwater Capabilities

Advancing Global Deepwater Capabilities Advancing Global Deepwater Capabilities BP s commitments Determined to accelerate and further deploy the capabilities and practices that enhance safety in our company and the deepwater industry 200+ meetings

More information

Linear vs. PWM/ Digital Drives

Linear vs. PWM/ Digital Drives APPLICATION NOTE 125 Linear vs. PWM/ Digital Drives INTRODUCTION Selecting the correct drive technology can be a confusing process. Understanding the difference between linear (Class AB) type drives and

More information

Seeing through software

Seeing through software Seeing through software Gefei Liu and Cissy Zhao, Pegasus Vertex Inc., USA, explain how the use of advanced software can help engineers see underground by predicting subsurface conditions. Oil well drilling

More information

SEAM Pressure Prediction and Hazard Avoidance

SEAM Pressure Prediction and Hazard Avoidance Announcing SEAM Pressure Prediction and Hazard Avoidance 2014 2017 Pore Pressure Gradient (ppg) Image courtesy of The Leading Edge Image courtesy of Landmark Software and Services May 2014 One of the major

More information

DIGITAL IMPRESSION SCANNERS

DIGITAL IMPRESSION SCANNERS DIGITAL IMPRESSION SCANNERS Everything You Need to Know to Choose the Best Scanner for Your Practice R-Dent Dental Laboratory 7490 Bartlett Corporate Cove West, Bartlett, TN 38133 901-372-8020 www.rdentlab.com

More information

Drivers and Technologies for Next Generation Digital Connectivity in Offshore O&G Production Facilities

Drivers and Technologies for Next Generation Digital Connectivity in Offshore O&G Production Facilities Drivers and Technologies for Next Generation Digital Connectivity in Offshore O&G Production Facilities Wayne Nielsen, Managing Director, WFN Strategies Greg Otto, E&P DCT Field Digital Infrastructure

More information

Welcome to the Symposium, I am [name and title] from Keysight technologies.

Welcome to the Symposium, I am [name and title] from Keysight technologies. The evolution of tactical and public safety radio technologies presents new challenges in radio testing. For example; combination of new and legacy standards in a radio requires a wide range of test configurations,

More information

UNIT-4 POWER QUALITY MONITORING

UNIT-4 POWER QUALITY MONITORING UNIT-4 POWER QUALITY MONITORING Terms and Definitions Spectrum analyzer Swept heterodyne technique FFT (or) digital technique tracking generator harmonic analyzer An instrument used for the analysis and

More information

The wireless alternative to expensive cabling...

The wireless alternative to expensive cabling... The wireless alternative to expensive cabling... ELPRO 905U Wireless Solutions for Process Applications New Products... New Solutions The ELPRO 905U range of telemetry modules provide remote monitoring

More information

Using Critical Zone Inspection and Response Monitoring To Prove Riser Condition. M Cerkovnik -2H Offshore

Using Critical Zone Inspection and Response Monitoring To Prove Riser Condition. M Cerkovnik -2H Offshore Using Critical Zone Inspection and Response Monitoring To Prove Riser Condition M Cerkovnik -2H Offshore Agenda 1. Introduction 2. High level methodology 3. Verifying condition 4. Defining requirements

More information

Comprehensive Plug and Abandonment Systems

Comprehensive Plug and Abandonment Systems Comprehensive Plug and Abandonment Systems Abandon Your Well. Abandon Uncertainty. Complete, single-trip systems for P&A Schlumberger comprehensive plug and abandonment systems bring certainty and rig-time

More information

OTC seems to be able to afford to fix the problems associated with downtime due to an incomplete design.

OTC seems to be able to afford to fix the problems associated with downtime due to an incomplete design. OTC 15194 DEEPWATER BOP CONTROL SYSTEMS - A LOOK AT RELIABILITY ISSUES Earl Shanks, Transocean; Andrew Dykes, ABS Consulting; Marc Quilici, ABS Consulting; John Pruitt, ABS Consulting Copyright 2003, Offshore

More information

SEPTEMBER, 2018 PREDICTIVE MAINTENANCE SOLUTIONS

SEPTEMBER, 2018 PREDICTIVE MAINTENANCE SOLUTIONS SEPTEMBER, 2018 PES: Welcome back to PES Wind magazine. It s great to talk with you again. For the benefit of our new readerswould you like to begin by explaining a little about the background of SkySpecs

More information

Investor Relations Presentation April 30, 2013

Investor Relations Presentation April 30, 2013 Investor Relations Presentation April 30, 2013 FORWARD LOOKING STATEMENTS In addition to the historical data contained herein, this document may include forward-looking statements regarding the future

More information

Finite Element Analysis per ASME B31.3

Finite Element Analysis per ASME B31.3 Brief Discussion: Split-Body 12in Butterfly valve, Ph: 520-265-3657 Page 1 of 13 Finite Element Analysis per ASME B31.3 Prepared by: Michael Rodgers, P.Eng. Date: July 16, 2010 Page 2 of 13 Section Headings:

More information

Quartz Lock Loop (QLL) For Robust GNSS Operation in High Vibration Environments

Quartz Lock Loop (QLL) For Robust GNSS Operation in High Vibration Environments Quartz Lock Loop (QLL) For Robust GNSS Operation in High Vibration Environments A Topcon white paper written by Doug Langen Topcon Positioning Systems, Inc. 7400 National Drive Livermore, CA 94550 USA

More information

PRODUCTION OmniWell SUBSEA PERMANENT RESERVOIR MONITORING SYSTEM Acquire real-time data for more informed reservoir decisions and enhanced production

PRODUCTION OmniWell SUBSEA PERMANENT RESERVOIR MONITORING SYSTEM Acquire real-time data for more informed reservoir decisions and enhanced production PRODUCTION OmniWell SUBSEA PERMANENT RESERVOIR MONITORING SYSTEM Acquire real-time data for more informed reservoir decisions and enhanced production Get real-time data on demand for the life of your subsea

More information

Looking Ahead: Management in the GoM. June 2011

Looking Ahead: Management in the GoM. June 2011 Looking Ahead: Riser System Integrity Management in the GoM June 2011 Agenda Deepwater Gulf of Mexco riser lifecycle; Background Riser systems sectioning; Section criticality vs. integrity management maturity;

More information

COMPREHENSIVE SOLUTIONS

COMPREHENSIVE SOLUTIONS COMPREHENSIVE SOLUTIONS MCDERMOTT IS A PREMIER, FULLY INTEGRATED PROVIDER OF ENGINEERING, CONSTRUCTION AND TECHNOLOGY SOLUTIONS TO THE ENERGY INDUSTRY PROBLEM SOLVERS For more than a century, customers

More information

Technological and Logistical Challenges during Construction & Installation of Deepwater Mega Subsea Development in West Africa

Technological and Logistical Challenges during Construction & Installation of Deepwater Mega Subsea Development in West Africa Technological and Logistical Challenges during Construction & Installation of Deepwater Mega Subsea Development in West Africa 1 SAFER, SMARTER, GREENER Content Going Deeper Scale/Size of Deepwater Mega

More information

Blade Tip Timing Frequently asked Questions. Dr Pete Russhard

Blade Tip Timing Frequently asked Questions. Dr Pete Russhard Blade Tip Timing Frequently asked Questions Dr Pete Russhard Rolls-Royce plc 2012 The information in this document is the property of Rolls-Royce plc and may not be copied or communicated to a third party,

More information

Violent Intent Modeling System

Violent Intent Modeling System for the Violent Intent Modeling System April 25, 2008 Contact Point Dr. Jennifer O Connor Science Advisor, Human Factors Division Science and Technology Directorate Department of Homeland Security 202.254.6716

More information

AADE Houston Chapter. Group. 26 January 2011

AADE Houston Chapter. Group. 26 January 2011 AADE Houston Chapter Deepwater and Emerging Technologies Group 26 January 2011 BOEMRE Compliance Guidelines Department of Interior s Increased Safety Measures for Energy Development on the Outer Continental

More information

Improve asset protection and utilization

Improve asset protection and utilization QUALITROL 509 ITM Intelligent transformer monitor Improve asset protection and utilization Immediately know your transformer health with TransLife Optimize loading and equipment life Simplify root cause

More information

Presented on. Mehul Supawala Marine Energy Sources Product Champion, WesternGeco

Presented on. Mehul Supawala Marine Energy Sources Product Champion, WesternGeco Presented on Marine seismic acquisition and its potential impact on marine life has been a widely discussed topic and of interest to many. As scientific knowledge improves and operational criteria evolve,

More information

SYSTEM DEVELOPMENT FOR PROFILING DEEPER WATERS IN SUPPORT OF THE OIL AND GAS INDUSTRY

SYSTEM DEVELOPMENT FOR PROFILING DEEPER WATERS IN SUPPORT OF THE OIL AND GAS INDUSTRY SYSTEM DEVELOPMENT FOR PROFILING DEEPER WATERS IN SUPPORT OF THE OIL AND GAS INDUSTRY John Romeo Jan Van Smirren Michael J. Vogel RD Instruments Fugro/Geos Shell E & P Technology Company ABSTRACT- In recent

More information

Intervention/Decommissioning

Intervention/Decommissioning Intervention/Decommissioning By Nicholas Samford Lloyds Register Intervention/Decommissioning SME Working together for a safer world Planning Decommissioning Operations Planning Decommissioning and P&A

More information

High Resolution 3D Laser Imaging for Inspection, Maintenance, Repair, and Operations

High Resolution 3D Laser Imaging for Inspection, Maintenance, Repair, and Operations High Resolution 3D Laser Imaging for Inspection, Maintenance, Repair, and Operations 09121-3300-06 Carl Embry 3D at Depth Ultra-Deepwater Subsea Systems TAC Meeting January 22, 2013 Greater Fort Bend EDC

More information

The wireless alternative to expensive cabling...

The wireless alternative to expensive cabling... The wireless alternative to expensive cabling... ELPRO 105U ISO 9001 Certified New Products... New Solutions The ELPRO 105 range of telemetry modules provide remote monitoring and control by radio or twisted-pair

More information

Modern transformer relays include a comprehensive set of protective elements to protect transformers from faults and abnormal operating conditions

Modern transformer relays include a comprehensive set of protective elements to protect transformers from faults and abnormal operating conditions 1 Transmission transformers are important links in the bulk power system. They allow transfer of power from generation centers, up to the high-voltage grid, and to bulk electric substations for distribution

More information

Driving Cost Reductions in Offshore Wind THE LEANWIND PROJECT FINAL PUBLICATION

Driving Cost Reductions in Offshore Wind THE LEANWIND PROJECT FINAL PUBLICATION Driving Cost Reductions in Offshore Wind THE LEANWIND PROJECT FINAL PUBLICATION This project has received funding from the European Union s Co-funded by the Intelligent Energy Europe Seventh Programme

More information

API RP 53 Recommend Practices for Blowout Prevention Equipment Systems for Drilling Wells vs. Standard 53 4 th Edition 2011

API RP 53 Recommend Practices for Blowout Prevention Equipment Systems for Drilling Wells vs. Standard 53 4 th Edition 2011 API RP 53 Recommend Practices for Blowout Prevention Equipment Systems for Drilling Wells vs. Standard 53 4 th Edition 2011 Meeting with BOEMRE March 1, 2011 Presented by: Frank Gallander Chevron Chair

More information