NERC System Protection and Control Task Force. Presented to the Western Protective Relay Conference Spokane, Washington October 20, 2004

Similar documents
Summary of Relaying Reviews Reporting

Methods to Increase Line Relay Loadability

Switch-on-to-Fault Schemes in the Context of Line Relay Loadability

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell

Protection System Review Program

Unit Auxiliary Transformer Overcurrent Relay Loadability During a Transmission Depressed Voltage Condition

Standard Development Timeline

Transmission System Phase Backup Protection

Relay Loadability Exceptions

(Circuits Subject to Requirements R1 R5) Generator Owner with load-responsive phase protection systems as described in

Relay Loadability Exceptions

1

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

Final ballot January BOT adoption February 2015

PRC Disturbance Monitoring and Reporting Requirements

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

NERC Protection Coordination Webinar Series June 9, Phil Tatro Jon Gardell

Industry Webinar Draft Standard

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

Power Plant and Transmission System Protection Coordination of-field (40) and Out-of. of-step Protection (78)

Determination of Practical Transmission Relaying Loadability Settings Implementation Guidance for PRC System Protection and Control Subcommittee

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC

Wind Power Facility Technical Requirements CHANGE HISTORY

NERC Protection Coordination Webinar Series June 30, Dr. Murty V.V.S. Yalla

Power Plant and Transmission System Protection Coordination

Agenda Notes for 4 th Meeting of Sub Group in respect of Preparation of Reliability Standards for Protection System and Communication System

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1

FACILITY RATINGS METHOD TABLE OF CONTENTS

Unit Auxiliary Transformer (UAT) Relay Loadability Report

Power Plant and Transmission System Protection Coordination

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

Considerations for Power Plant and Transmission System Protection Coordination

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction

Setting and Verification of Generation Protection to Meet NERC Reliability Standards

AUTOMATIC CALCULATION OF RELAY SETTINGS FOR A BLOCKING PILOT SCHEME

System Protection and Control Subcommittee

Central Hudson Gas & Electric Corporation. Transmission Planning Guidelines

GridLiance Reliability Criteria

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

DUKE ENERGY CAROLINAS TRANSMISSION SYSTEM PLANNING GUIDELINES. Transmission Planning

Generation and Load Interconnection Standard

Generation and Load Interconnection Standard

Appendix S: PROTECTION ALTERNATIVES FOR VARIOUS GENERATOR CONFIGURATIONS

NPCC Regional Reliability Reference Directory # 12. Underfrequency Load Shedding Program Requirements

Recently, the SS38 Working Group on Inter-Area Dynamic Analysis completed two study reports on behalf of the UFLS Regional Standard Drafting Team.

MidAmerican Energy Company 100 kv and Above Facility Ratings Methodology

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting

Introduction. Disclaimer

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules. 45-day Formal Comment Period with Initial Ballot June July 2014

Table of Contents. Introduction... 1

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

Transmission Interconnection Requirements for Inverter-Based Generation

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules

System Protection and Control Subcommittee

System Operating Limit Definition and Exceedance Clarification

NERC / TVA STABILITY WORKSHOP

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. July 2016 Version 4

1200 MW Fault Induced Solar Photovoltaic Resource Interruption Disturbance Report

LONG-RANGE TRANSMISSION PLAN

E N G I N E E R I N G M A N U A L

NERC Protection Coordination Webinar Series July 15, Jon Gardell

Kansas City Power & Light Company. Transmission Facility Rating Methodology

Arizona Public Service Company and the Transmission Partnership for National Electric Power Company of Jordan

Voltage Control with Distributed Generators to Enhance Voltage Stability

Industry Webinar. Reactive Power Planning. NERC System Analysis and Modeling Subcommittee (SAMS) March 2017

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications

ELEMENTS OF FACTS CONTROLLERS

ESB National Grid Transmission Planning Criteria

Implementation Plan Project Modifications to PRC Reliability Standard PRC-025-2

August 14, 2003 Blackout. 3 Interconnections / 10 NERC Regions. NERC Control Areas. NERC Reliability Coordinators. Overview

Embedded Generation Connection Application Form

Application for A Sub-harmonic Protection Relay. ERLPhase Power Technologies

The Use of VSC-Based BtB as Grid Shock Absorber

BED INTERCONNECTION TECHNICAL REQUIREMENTS

NERC Protection Coordination Webinar Series June 23, Phil Tatro

Final ballot January BOT adoption February 2015

Central East Voltage and Stability Analysis for Marcy FACTS Project Phase I

Endorsed Assignments from ERS Framework

Jonathan (Xiangmin) Gao - GE Grid Solutions Douglas Rust - Dandsco LLC Presented by: Tom Ernst GE Grid Solutions

Inverter-Based Resource Disturbance Analysis

Grid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017

Tampa Electric Company Facility Rating Methodology Approved 11/20/2018

PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016

Southern Company Interconnection Requirements for Inverter-Based Generation

Transmission Facilities Rating Methodology for Florida

BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 7T-30A. NORTH COAST INTERCONNECTION: SKEENA BOB QUINN SUBSYSTEM Supersedes OO 7T-30A dated 07 July 2014

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. April 2009 Version 2

Study on the Improvement of the Special Protection Scheme (SPS) in the Korean power system

Embedded Generation Connection Application Form

Harmonizing the Changing Resource Mix Keeping the Grid Together

RELAY LOADABILITY CHALLENGES EXPERIENCED IN LONG LINES. Authors: Seunghwa Lee P.E., SynchroGrid, College Station, Texas 77845

MidAmerican Energy Company 100 kv and Above Facility Ratings Methodology

Transmission Lines and Feeders Protection Pilot wire differential relays (Device 87L) Distance protection

GENERAL REQUIREMENTS FOR TRANSMISSION INTERCONNECTION

TTC Study for: the PEGS-Ambrosia Lake 230 kv Line and the PEGS-Bluewater 115 kv Line

Definition of Bulk Electric System Phase 2

Power Plant and Transmission System Protection Coordination Fundamentals

Transcription:

NERC System Protection and Control Task Force Presented to the Western Protective Relay Conference Spokane, Washington October 20, 2004

Outline History Recommendations SPCTF Organization SPCTF Scope Comments from NERC Aug 14, 2003 Blackout Investigation Team Bob Stuart SPCTF Clarification of Ratings Bill Kennedy SPCTF Recommendations to NERC PC SPCTF Exception Criteria Jon Daume, Skip Williams Q&A - Panel 2

History WECC Blackouts 1996 Distance Relays were found to contribute January 1997 IEEE Computer Applications in Power Article by Carson Taylor and Dennis Erickson o Responses by Charles Henville and Charles Rogers in April 1997 Computer Applications in Power (letters to editor) August 14, 2003 Eastern Interconnection Blackouts U.S. Canada Power System Outage Task Force Reports on 11/19/03 and 4/4/04 NERC Investigation BOT Approved Recommendations on 2/10/04 July 13, 2004 NERC Technical Analysis Report ECAR Investigation Report on 2/16/04 3

History (Continued) All investigations into August 14, 2003 blackout found that Distance Relays tripping for non-fault conditions contributed to the blackout Much Criticism for Not Addressing Distance Relays after earlier blackouts NERC Planning Committee Formed a task force to address Relaying Issues relating to August 14, 2003 blackout SPCTF Scope was Approved by NERC on 3/25/04 SPCTF Staffed by NERC on 5/14/04 4

Recommendations NERC Recommendation 8a US Canada Power System Outage Task Force Recommendation 21a 5

SPCTF Organization Charles Rogers Consumers Energy Chairman (ECAR) Mark Carpenter TXU Electric Delivery Vice Chairman (ERCOT) John Mulhausen Florida Power and Light (FRCC) Al Darlington Tampa Electric (retired) (FRCC Alternate) Joe Burdis PJM Interconnection (MAAC) Bill Miller Excelon (MAIN) Deven Bahn WAPA (MAPP) Phil Tatro National Grid (NPCC) Phil Winston Georgia Power (SERC) Skip Williams AEP (ECAR Alternate) Fred Ipok Springfield, MO. SPP Dave Angell Idaho Power (WECC) Baj Agrawal APS (WECC Alternate) Jon Daume BPA (WECC Alternate) John Ciufo Hydro One (Canada - Eastern) Bill Kennedy Alberta Electric System Operator (Canada - Western) Jim Ingleson NYISO (ISO/RTO) Evan Sage PEPCO (IOU) Gary Kobet TVA (Federal) Keith Orsted American Transmission Company (TDU) Robert Stuart NEXANT, PGE (retired) (NERC Investigation Team) Tom Weidman Commonwealth Edison (retired) (NERC Investigation Team) Bob Cummings NERC Staff 6

SPCTF Scope Highlights Review and Report on Pros and Cons of Zone-3 Relays on Transmission Systems Review Zone-3 Relay Settings to Avoid Tripping on Load Review Requests for Exception and Report to PC Merits and Deficiencies of UVLS Review Region Evaluations of UVLS Feasibility and Benefits Review NERC Planning Standard III and Recommend Revisions as Appropriate General Review of Protection System Design to Improve Protection of System and Prevent/Mitigate Cascading Failures 7

SPCTF Activities To Date Clarified Definition of Rating Defined Zone 3 Further Defined Zone 3 Schedule and Assigned Major Roles to Regions Defined Temporary Exceptions and Technical Exceptions Developed draft Technical Exception Criteria Developed Technical Exception Reporting Form 8

NERC Investigation Team Bob Stuart NERC Investigation Team 9

NERC Investigation Team Zone 3 relays contributed to blackout Sammis Star 345 kv trip @ 16:05:57 escalated cascade East Lima Fostoria Central 345 kv trip accelerated cascade In total, 14 lines tripped by distance relay due to load encroachment 10

NERC Investigation Team Sammis Star tripped at 16:05:57 by Zone 3 Load Encroachment 120% emergency rating; 0.96 p.u. voltage (Sammis end); 27 degree line angle Zone 3 relay set for 200% of line to protect transformer 1500 MW of load dropped prior to line relaying would have contained disturbance to Cleveland 11

NERC Investigation Team Factors taken into consideration WECC Guidelines - 1997-30 degree power factor angle - 0.8 p.u. voltage - margin recommended based on power flow studies Establish capability to ride thru severe disturbances - Give operators 10 to 15 minutes to drop load or reconfigure system Discussed with investigation team 12

NERC Investigation Team Conductor short term emergency ratings - 15 minute ratings based on more aggressive conditions - Achievable over 50% of time - normal ratings at 75% of line rating 10 to 15 minutes to reach 100 degrees C Assumed 15 to 25 % relay margin - CT and PT error - Relay error 15 to 25% margin above short term emergency rating will still allow small margin for 150% of summer emergency ratings 13

NERC Investigation Team Calculated relay settings for various lengths of lines Determined that line lengths above 75 miles would be difficult to set zone 3 relays assuming 150% setting Make relays less sensitive to load encroachment - Increasing maximum torque angle to 90 degrees - Activating load encroachment feature on modern relays - Installing blinders Asked two large utilities (represented on Investigation Team) to review proposed policy very small percentage had some mitigation to do may not be representative Policy intended to drive stake in ground more specific guidelines would have to be generated later 14

SPCTF Recommendations Bill Kennedy - AESO 15

SPCTF Clarification on Ratings NERC Recommendation 8a footnote states emergency ampere rating NERC PC Minutes March 24 suggests long time summer emergency ampere rating SPCTF Clarification (June 18) Highest seasonal ampere circuit rating that most closely approximates a 4-hour rating considering the lowest ampere rated device in the line 16

SPCTF Recommendations TPSO Transmission Protection System Owner Current Process to Address Only Zone-3 Relays Zone-3 Relays Defined As Remote Backup Relays (IEEE C37.113 Clause 5.3.7.1) Inject Regions Into Zone-3 Process Build on Their Natural Relationships With the TPSO s TPSOs to Respond to Regions by Dates Established in NERC Recommendation 8a Regions to Assure That All TPSOs Have Responded and Respond to NERC 1 Month Later 17

SPCTF Recommendations (Continued) Establish Two Classes of Exception Temporary and Technical Temporary Exceptions to Request Delayed Schedule for Workforce or Construction Clearance Issues Must Include Proposed Schedule Technical Exceptions to Address Conditions Where Thermal Limits Are Not the Practical Limiting Condition SPCTF Developing Technical Exception Criteria SPCTF to Review All Exception Requests and Report to PC Denied Requests Must Be Mitigated in 1 Year 18

SPCTF Recommendations (Continued) All Other Load-responsive Relays to Be Reviewed and Addressed on a Schedule to Be Developed by SPCTF Exceptions to Be Reviewed by Regions Regions to Identify Critical Lines 115kv and Above for Inclusion in Review (Joint TF Recommendation 21a) All Recommendations were Approved by NERC PC on July 15, 2004 19

Implementation Timeline for NERC Recommendation 8a Activities 12/31/2004 TPSOs Submit to Regions: - Certification of conformance to loadability - Violation mitigation (before 12/31/05) plans - Applications for exceptions 12/31/2005 TPSOs Submit to Regions: - Certification of full conformance - Implementation dates for outstanding violations 9/30/2004 TPSOs report to Regions on Zone 3 reviews 2/10/2004-9/30/2004 TPSOs review Zone 3 relays for conformance 9/30/2004-12/31/2004 TPSOs mitigate violations 1/1/2005-12/31/2005 TPSOs mitigate violations 2/10/2004 NERC Rec. 8A Issued by Board Today 10/31/2004 Regions Report TPSO completion of 9/30 review to SPCTF 1/31/2005 Regions report TPSO responses of 12/31/04 to SPCTF 2/1/2006 Regions report TPSO responses of 12/31/05 to SPCTF 20

SPCTF Exception Criteria Temporary Exceptions Technical Exceptions Realistic Circuit Ratings Achieve Minimum Acceptable Protection Network Topology Transmission System Must be Adequately Protected, and Distance Relaying Must also allow for Maximum Practical Load Flow Distance Relaying Must Not Contribute to Cascading Outages 21

Ratings and Technical Exceptions NERC Recommendation 8a refers to circuit thermal ratings SPCTF Clarified to highest seasonal 4-hour rating of most limiting circuit element Thermal ratings may not represent practical circuit ratings Technical Exceptions attempt to address the other practical circuit capabilities 22

Temporary Exceptions Permit delayed implementation because of workforce issues, construction outage constraints, or availability of replacement equipment Not intended to provide for budget relief TPSO must do all possible to mitigate with Existing Equipment Must Include Proposed Schedule for Mitigation 23

Technical Exceptions Twelve Individual Technical Exception Criteria Establishes lower margins for shorter-term circuit ratings (1) Address other system limitations that present more realistic actual system rating criteria (5) Establish ratings based on minimally-adequate protection (2) Natural system limitations due to topology (4) 24

Technical Exception #1 Utilize the 15-Minute Rating of the Transmission Line The tripping relay should not operate at or below 115% of the 15-minute winter emergency rating Assuming: 0.85 per unit voltage line phase angle of 30 degrees 25

Maximum Power Transfer Diagram Sending X S = 0 X L X R = 0 Receiving E S = 1.0 PU V S P R = V S V R X sinδ L V R E R = 1.0 PU The maximum real power that a transmission line can transfer occurs when the voltage angle across the line reaches 90º. 26

Maximum Power Transfer Capability 345 kv (2 X 1272 ACSR) Line Loadability Apparent Power (MVA) & St. Clair (MW) 5000 4000 3000 2000 St. Clair Curve MW St. Clair MVA S 1.5xWE Ss (Vs=1 δ=90 ) 1000 0 0 50 100 150 200 250 300 350 400 Line Length (miles) 27

Derivation of the Exception Equation V P = P = V S 2 X L V R X sinδ L VS VS VR Q = cos X X ( o δ ) The real and reactive currents are equal at maximum power transfer Q = V L 2 X L 2 L 28 I total = 2 I real I total 2 V = 3 X L

Technical Exception # 2, 3 and 4 The protective relays only need to accommodate the power transfer capability of a transmission line #2 Line X only, 1.00 p.u. V Recertify when line is changed #3 Line and breaker interrupter rating, 1.05 p.u. V Recertify when breaker is underrated or changed #4 Line and actual source impedance, 1.05 p.u. V Recertify annually 29

Technical Exception #5 Special Considerations for Series- Compensated Lines Tripping relay should not operate at or below the greater of: 1. 1.15 times the highest emergency rating of the series capacitor 2. I total (calculated under Exception 2, 3, or 4 using full line inductive reactance) assuming 0.85 per unit voltage line phase angle of 30º 30

Technical Exceptions Part 2 Skip Williams AEP 31

Technical Exception #6 Weak Source Systems The tripping relay should not operate at or below 1.15 times I = 2 1. 05 I max Assuming: fault 0.85 per unit voltage at a load phase angle of 30 degrees where I max is the maximum end of line three-phase fault current magnitude. 32

Technical Exception 6 - Drawing OPEN FAULT TRANSMISSION SYSTEM R LOAD CENTER Weak Source Systems 33

Technical Exception #7 Long Line Relay Loadability Long line relay loadability can be adjusted as long as ALL of the following conditions are met: 1. Most sensitive tripping relay set 125% of total line impedance 2. MTA set as close to 90 degrees (sanctioned by manufacturer) 34

Technical Exception #7 (cont.) 3. Short-term emergency rating (I emergency ) of line is equal to or less than: 0.341 Vrelay cos( MTA Θline) I emergency = Zline cos( MTA 30 ) Where V is the nominal line-to-line voltage and Z line is the impedance of the line in ohms 4. I emergency used in all planning and operational modeling for STE Rating (15-min. or most closely approx. 15-min. rating) 35

Technical Exception #7 (cont.) 5. No current or subsequent planning contingency analyses identify any conditions where the recoverable flow is greater than I emergency 6. Transmission Operators take immediate remedial steps, including dropping load, if current reaches I emergency If any of these conditions are violated, then the condition must be fully mitigated to avoid the loadability issue 36

Technical Exception 7 - Drawing X Z RELAY 1.25 Z LINE Z LINE MTA 30 0 R Z RELAY 30 LINE Long Line Loadability 37

Technical Exception 8 Three (or more) Terminal Lines Similar to Exception 7, except considers apparent impedance to the most distant line terminal, instead of simply considering line impedance Includes lines with significant taps 38

Technical Exception #9 Generation Remote to Load The tripping relay should not operate for 1.15 times the maximum current, representing twice the aggregate generator MVA capability, assuming 0.85 per unit voltage line phase angle of 30 degrees 39

Technical Exception 9 - Drawings GENERATION CENTER LOAD BUS A R R OPEN OPEN LOAD BUS B LOAD BUS C LOAD CENTER R Generation Connected to System Multiple Lines 40

Technical Exception #10 Load Remote to Generation The tripping relay should not operate for 1.15 times the maximum current flow as calculated by the TPSO assuming 0.85 per unit voltage line phase angle of 30 degrees 41

Technical Exception 10 - Drawing GENERATION CENTER LOAD BUS A R R LOAD BUS B LOAD BUS C LOAD CENTER R Load Remote to Generation 42

Technical Exception #11 Remote Cohesive Load Center The tripping relay should not operate for 1.15 times the maximum current flow as calculated by the transmission owner assuming 0.85 per unit voltage a line phase angle of 30 degrees 43

Technical Exception 11 - Drawing TRANSMISSION SYSTEM R R LOAD CENTER R Remote Cohesive Load Center 44

Technical Exception #12 Cohesive Load Center Remote to Transmission System The Tripping relay should not operate for 1.15 times the maximum current flow as calculated by the TPSO assuming 0.85 per unit voltage line phase angle of 30 degrees 45

Technical Exception 12 - Drawing TRANSMISSION SYSTEM R R LOAD CENTER R Cohesive Load Center Remote to Transmissions System 46

Wrapup and Conclusions Dave Angell 47

Some Possible Mitigation Methods Must Adequately Protect System Disable Unnecessary Protective Elements Increase Distance Relay Maximum Torque Angle Utilize load-tolerant relay characteristics Utilize Transfer Trip for Remote Backup Transmission System modifications to Facilitate Protection Others? 48

SPCTF Next Distance Relay Activities All other load responsive relays (230 kv and above, and lower voltage level critical facilities) must also not limit practical loading capability. Includes Zone 2 relays, pilot-scheme relays, and overcurrent relays DCB Carrier Schemes can improperly operate on through load if lines are consuming significant real and reactive power Will have a different schedule for analysis, reporting, and mitigation Must adequately protect electrical system! 49

SPCTF Documents Approved SPCTF Documents may be found on the NERC web site at: http://www.nerc.com/~filez/spctf.html Official Reports on the August 14, 2003 Blackout may be found on the NERC web site at: http://www.nerc.com/~filez/blackout.html 50

SPCTF Contacts For detailed questions or suggestions, please contact Bob Cummings Bob.Cummings@nerc.net 609-452-8060 Charles Rogers cwrogers@cmsenergy.com 517-788-0027 Mark Carpenter mcarpen1@txued.com 817-215-6868 Any other SPCTF member We Need everyone s help for us to do the best possible job! 51

NERC SPCTF Q&A Panel Members All Available SPCTF Members 52