NEWTON COUNTY WATER AND SEWERAGE AUTHORITY RESIDENTIAL, COMMERCIAL, INSTITUTIONAL AND INDUSTRIAL SUBDIVISIONS CONSTRUCTION PLANS CHECK LIST

Similar documents
BRASELTON WATER AND WASTEWATER DEPARTMENT CONSTRUCTION PLAN REVIEW CHECKLIST May 2006

LOWNDES COUNTY ENGINEERING PLAN REVIEW CHECKLIST. Design Professional: Phone: Developer: Phone: 2 nd Submittal (No Fee)

UTILITY AND STREET CONSTRUCTION PLAN REQUIREMENTS SECTION 1

Sewer Line Extension Permit Design Checklist

CITY OF MUSKEGO DRAFTING STANDARDS

Plan Submittal and Review Checklist

Existing and proposed contours at 1-foot intervals. The fill and/or excavation quantities in cubic yards.

Grease Interceptor Design Checklist

List of Figures. List of Forms

Anne Arundel County Dept. of Inspections and Permits Water Sewer Plan Checklist

Authorized Agent: City of Manassas Check List Attached: Contact: Address: Phone Number: Fax Number: Developer s Name: Phone Number:

SECTION 3 IMPROVEMENT PLAN REQUIREMENTS

SUBDIVISION APPLICATION FOR DRT SUBMITTAL PUBLIC WORKS DEPARTMENT

SECTION 100 PRELIMINARY CONSIDERATIONS & INSTRUCTIONS

B.2 MAJOR SUBDIVISION PRELIMINARY PLAN CHECKLIST

SECTION III SUBMITTALS AND APPROVALS

CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA (360)

Engineering and Construction Services Division Construction Drawings for Sewers and Watermains. T No. Revision T No. Revision Remarks All T drawings

ACSA PLAN REVIEW CHECKLIST (Guideline Only) (4) Standard water and sewer general plan notes (attached).

APPENDIX 1: CONSTRUCTION PLAN CHECKLIST

CHECKLIST PRELIMINARY SUBDIVISION AND PRELIMINARY SITE PLAN

Oil-Water Separator Design Checklist

B17. Sewer Site Plans BULLETIN

City of Massillon Site Plan Checklist

WATER & SEWER CONSTRUCTION SITE PLAN DESIGN SUMMARY COMMERCIAL & RESIDENTIAL

1.1 GENERAL RECORD DRAWING REQUIREMENTS

CITY OF VISTA STANDARD DRAWINGS

SECTION 2.0 PREPARATION OF MASTER PLANS, CONSTRUCTION PLANS, AND RECORD DRAWINGS

CITY OF REEDLEY NEW DEVELOPMENT PLAN REVIEW CHECK LIST

CITY OF VISTA STANDARD DRAWINGS

MINIMUM DRAWING REQUIREMENTS FOR WATER AND SEWER LINE PROJECTS

3. DESIGN SPECIFICATIONS

September 21, Mannik Smith Group 1771 North Dixie Highway Monroe, Michigan RE: LA Fitness City File No.: CVLP

PLANNING AND DEVELOPMENT

Appendix C Construction Details

Porter County Plan Commission

CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division SANITARY SEWER IMPROVEMENT PLAN REVIEW CHECKLIST

Charlotte County Utilities DESCRIPTION

KC Water Rules and Regulations For Water Main Extensions and Relocations

PART 4 STANDARD DRAWINGS FOR CONSTRUCTION

Clarifications in italics added July 2018

CONCEPT REVIEW GUIDELINES

3. The PAC (Permit Application Center) will notify the design professional of plan review results.

10010 RECORD DRAWING INFORMATION

Subdivision Application Checklist

SECTION III STANDARD DRAWINGS ROYSE CITY GENERAL CONSTRUCTION NOTES & DETAILS

Zoning District: R-1, R-2, and R-4 Applicant: Exeter Rose Farm, LLC, 953 Islington Street #23D Portsmouth, NH 03801

50.24 Type, Size and Location Plans for Culverts, Bridges and Culvert Bridges

CITY OF LOMPOC DEVELOPMENT ASSISTANCE BROCHURE ENCROACHMENT PERMITS AND PUBLIC IMPROVEMENT PLANS

Section E NSPS MODEL STANDARDS FOR TOPOGRAPHIC SURVEYS Approved 3/12/02

Survey Requirements. Design Guidelines and Standards. June Office of the University Architect

DIVISION APPROVED MATERIAL LIST AND STANDARD DETAILS

PRECISE GRADING PLAN CHECKLIST

Washington County Road Engineering Plan Submittal/Review Checklist

CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division STORM DRAIN IMPROVEMENT PLAN REVIEW CHECKLIST

Construction Documents (CDs) Checklist

B-PERMIT PLAN CHECK MANUAL

Phone Number: Address:

CITY OF SALEM DEPARTMENT OF PUBLIC WORKS ADMINISTRATIVE RULES CHAPTER 109 DIVISION 002 DRAFTING AND DRAWING STANDARDS

STATE UNIVERSITY CONSTRUCTION FUND

SECTION 095 SPECIFICATIONS DETAIL DRAWINGS. Index of Detail Drawings

Town of Westlake Construction Plans Review Checklist

Site Plan Review Application. Interest in the Property (e.g. fee simple, land option, etc.)

MAJOR GRADING PLAN CHECKLIST

UPDATE LOG FOR STANDARD DRAWINGS Item(s) Changed 6/1/18 STANDARD DRAWINGS

SCHEDULE 10 ENGINEERING DRAWING SUBMISSION

Plan Preparation Checklist

Lincoln County Public Works Water and Sewer Submittal Application

Council Policy Engineering Drawing Submission Requirements

Babcock Ranch Water Utilities as operated by Town & Country Utilities and Babcock Ranch Irrigation

CITY OF LA MARQUE CHAPTER GRAPHIC REQUIREMENTS CONSTRUCTION PLAN AND MISCELLANEOUS REQUIREMENTS

Public Works City of Lebanon, Tennessee; Department of Public Works

CHAPTER 11. Plan Standards

SUPPLEMENTARY STANDARD DETAIL DRAWINGS

ACWWA DRAWING SUBMITTAL INFORMATION - UTILITY DRAWING REQUIREMENTS

TOWN of LAKESHORE SITE PLAN CHECKLIST

CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division STREET/ALLEY IMPROVEMENT PLAN REVIEW CHECKLIST

Minimum Drawing & Electronic Submittal Requirements For Record Drawings /As-Builts

DIVISION A GENERAL AND DRAFTING ENGINEERING STANDARDS

Project Name: County File No.: Checked by: For: Date:

Site Plan/Building Permit Review

CHAPTER 3 INFORMATION REQUIRED FOR PUBLIC IMPROVEMENT CONSTRUCTION PLANS TABLE OF CONTENTS

SITE PLAN, SUBDIVISION & EXTERIOR DESIGN REVIEW PROCESS

Anne Arundel County Dept. of Inspections and Permits Storm Drain Checklist

Application for Site Plan Review

Guidelines and Checklist For SAWS Sanitary Sewer. Developmental Engineering Division

Basic Plan Set Requirements

Community & Economic Development Department Planning Division Frederick Street PO Box 8805 Moreno Valley, CA SUBMITAL REQUIREMENTS

APPENDIX D: DRAWING SUBMISSION STANDARDS

This addendum forms a part of the Contract Documents dated: August 10, 2012.

SECTION 39 - MANHOLES TABLE OF CONTENTS

DOCUMENT MINIMUM CONSTRUCTION DRAWING REQUIREMENTS FOR PRELIMINARY REVIEW/APPROVAL 1.2. GALVESTON COUNTY CONSOLIDATED DRAINAGE DISTRICT (GCCDD)

DEVELOPMENT PLAN CHECKLIST

HUSSEY GAY BELL SAVANNAH, GEORGIA

Appendix E-4. City of Fort Collins. Requirements for Utility Plans

APPENDIX A DESIGN CHECKLIST

SANITARY SEWER SYSTEM ADMINISTRATIVE STANDARDS A.1 SANITARY SEWER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS

Bestall Collaborative Limited Planning Environment Construction Management Development

APPLICATION FOR SITE PREPARATION PERMIT

Engineering Plan Submittal Requirements. Revised: October 2, Page 1 of 13

Transcription:

NEWTON COUNTY WATER AND SEWERAGE AUTHORITY RESIDENTIAL, COMMERCIAL, INSTITUTIONAL AND INDUSTRIAL SUBDIVISIONS CONSTRUCTION PLANS CHECK LIST Project Name Checked By Date Designer Check List marks to be interpreted as follows: OK X Revision Required NA Not Applicable? Additional Information Required I. WATER LAYOUT 1. Site plan with water layout only (topographic overlay required). 2. Pipe locations and sizes (8" minimum for water mains). 3. Materials to be used. Ductile iron pipe required under all intersections, stream crossings, road crossings, over and under all cross drains and at all other locations specified by the Authority. 4. Location and size of gate valves at intersections, along water mains, at fire hydrants, and at connection to existing mains. 5. Thrust blocks at all bends and tees. 6. Location of all existing and proposed fire hydrants. 7.Existing water mains locations, sizes, and types of material surrounding the project. 8. Detail of connection to existing water main. 9. Nearest existing line valves on both sides of connection to existing water main. 10. Proposed meter sizes and locations. 11. Water mains on north and east side of road. 12.If proposed water line crosses private property, a 20 foot permanent easement must be provided. 13. Details: A. Fire hydrant at end of line in cul-de-sacs B. Air & Vacuum release valve assembly C. House service installation D. Line valve E. Typical fire hydrant installation 14. Location of air release valves. 1

Miscellaneous Subdivisions Page 2 15.A gate valve and a minimum of 36 feet of pipe shall be provided at the end of all lines for phased developments. The end of the line shall be provided with temporary plug and concrete thrust collar. 16.Detail dead end line with one full joint of D.I. Pipe, Fire Hydrant, M.J. Plug, Retainer Glands and concrete thrust blocking. 17. Flow test required for each phase. Place order with Newton County Water and Sewerage Authority. Current cost. II. SEWER LAYOUT 1.EPD Sanitary Sewer Extension Submittal Form filled out for proposed project. 2. Sewage acceptance letter issued by. 3. Landfill letter issued by Newton County. A. Land Disturbing Activity Permit B. SWCD Report of Technical Review 4. Site plan showing sewer layout (topography overlay required). 5.Sewer layout should have manhole numbers, line designations, flow arrows, street names, and topography. 6. Sewer layout showing proposed storm drain crossings. 7.Detail tie-in of proposed lines with existing lines providing existing and proposed pipe sizes, invert elevations. 8. Profile of proposed sewer lines with proposed grades. 9. Manhole numbers and locations on plan and profile. 10.Outside drop-manhole designated on profile where invert "in" elevation is more than 2.0 feet above the invert "out" elevation. 11. Percent grade and length on profile. 12. Size of mains on profile. 13. Lateral locations on plan. As-builts should have distances in feet from manhole to lateral as well as station numbers. 14.Materials to be used. Ductile Iron Pipe where required such as fills, shallow cover, less than 2 feet of clearance, over 14' of fill, etc. 2

Miscellaneous Subdivisions Page 3 15. Location in profile of streams and storm drains. 16.Permanent easements are to be 20 feet wide for sanitary sewer and 30 feet wide for easements containing both sanitary sewer and storm drains. 17. Easements for future sewer. 18. Details: A. Precast concrete manhole B. 6" service connection C. Sewer service location D. Manhole frame and cover E. Class A,B, C and Special PVC bedding F. Pipe adapter - Joining different types of pipe G. Cleanout Detail 19. No acute angles between "in" lines and "out" line in manhole. 20. Proper manhole spacing. material 21. Sewers within minimum and maximum slope requirements for expected flow, pipe and pipe size. 22. In manholes where the pipe size increases, the crown of the smaller pipe must be at the same elevation or higher than the crown elevation of the larger pipe. over 23. Minimum cover of 7 feet in roadway where laterals are located to obtain 6 feet of cover lateral at R/W limit, or D.I.P. laterals designated. III. ADDITIONAL REQUIREMENTS 1. Horizontal separation of at least 10 feet between water main and existing or proposed sewer (measured edge to edge). 2.Where water main crosses existing or proposed sewer, 18" vertical separation is required between the two mains (measured edge to edge) and include a note that a full joint of water main is required to be centered at sewer main crossing so that both joints are as far away from the sewer as possible. 3.Newton County utility location detail. Notes. 4. Newton County Water and Sewerage Authority Water System Construction General 5. Utilities Protection Center Detail. Miscellaneous Subdivisions 3

Page 4 43-15. 6. Water and sewer plans bear the stamp of a registered professional as required by OCG 7. All plans shall be submitted with plan sheets sized 22" x 34" or 24" by 36". 8. Existing water mains along existing roads shall be shown to be replaced with D.I.P. (if they are not already D.I.P.) beneath the proposed subdivision entrance and acceleration / deceleration lanes. NOTES: 1. Flow test valid for 6 months and only applies to a single phase/unit of this project. 2.Plan approval valid for 12 months without beginning construction. Plans subject to further review and approval if 12 months expire. 3. The Authority will not be responsible for any house built too low to be served nor for any service covered by construction. 4. As-builts are required to be submitted upon completion of construction. 5. New Subdivision & Line Extension Data Sheet shall be completed and submitted to the Authority upon project completion. (Forms attached.) 6.Existing county roads shall not be open cut unless permission is granted by the Georgia D.O.T. or the Newton County Road Department. Submittal of authorization letter from the Georgia D.O.T. or Newton County Road Department is required. 7.If work is performed on a Georgia D.O.T. or Newton County R/W, a letter from the governing agency is required to be submitted after construction is complete stating that grassing, clean-up, drainage, etc. is acceptable. 4

NEWTON COUNTY WATER AND SEWERAGE AUTHORITY INDIVIDUAL COMMERCIAL, INSTITUTIONAL, OR INDUSTRIAL SITE CONSTRUCTION PLANS CHECK LIST Project Name Checked By Check List marks to be interpreted as follows: Designer Date OK X Revision Required NA Not Applicable? Additional Information Required I. WATER LAYOUT 1. Site plan with water layout (topographic overlay required). 2. Proposed water service location and size. 3. Materials to be used. Ductile iron pipe required under all intersections, stream crossings, road crossings, over and under all cross drains and at all other locations specified by the Authority. 4. Location and size of gate valves at meter pit and at connection to existing mains. 5. Thrust blocks at all bends and tees. 6. Location of all existing and proposed fire hydrants. 7.Existing water mains locations, sizes, and types of material surrounding the project. 8. Detail of connection to existing water main. 9. Nearest existing line valves on both sides of connection to existing water main. 10. Proposed meter sizes and locations. 11. Proposed detector check location if required and backflow preventer location. 12.If proposed water line crosses private property, provision of a 20 foot easement is required. 13. Details: A. Compound Meter and Vault Installation B. Detector Check Assembly C. Backflow Preventer D. Line valve E. Typical fire hydrant installation 14. Flow test results. Place order with Newton County Water and Sewerage Authority. Current cost. Individual Site 5

Page 2 II. SEWER LAYOUT 1.EPD Sanitary Sewer Extension Submittal Form filled out for proposed project. 2. Sewage acceptance letter issued by. 3. Landfill letter issued by Newton County. A. Land Disturbing Activity Permit B. SWCD Report of Technical Review 4.Site plan showing proposed sewer service (topography overlay required). Show location, rim, e l e v a t i o n and invert elevation of existing manholes on or adjacent to site. 5.Lateral location on site plan. As-builts should have distances in feet from manhole to lateral. 6. Detail of service connection to existing sanitary sewer line providing existing and proposed pipe sizes, materials and invert elevations. 7.Permanent easements are to be 20 feet wide for sanitary sewer lines crossing site and 30 feet wide for easements containing both sanitary sewer lines and storm drains. 8. Finish floor elevations of buildings being served. 9. No acute angles between "in" lines and "out" line in manhole. 10. Outside drop-manhole designated on profile where invert "in" elevation is more than 2.0 feet above the invert "out" elevation. 11. Percent grade and length of service. 12. Details: A. Precast concrete manhole B. 6" service connection C. Sewer service location D. Manhole frame and cover E. Class A, B, C and Special PVC bedding F. Pipe Adapter - Joining different types of pipe G. Cleanout Detail 6

13.Lateral is to have minimum cover of 6 feet within public road right-of-way wherever possible., or D.I.P. laterals designated within right-of-way. 402.08. 14. Wyes cut into existing sewer lines shall be constructed in accordance with standard detail Individual Site Page 3 III. ADDITIONAL REQUIREMENTS 1. Horizontal separation of at least 10 feet between water main and existing or proposed sewer (measured edge to edge). 2.Where water main crosses existing or proposed sewer, 18" vertical separation is required between the two mains (measured edge to edge) and include a note that a full joint of water main is required to be centered at sewer main crossing so that both joints are as far away from the sewer as possible. 3.Water and sewer plans bear the stamp of a registered professional as required by OCG 43-15. 4. Newton County Water and Sewerage Authority Water System Construction General Notes. 5. Utilities Protection Center Detail. 6. Existing water mains along existing roads shall be shown to be replaced with D.I.P. (if they are not already D.I.P.) beneath the proposed subdivision entrance and acceleration/deceleration lanes. 7. All plans shall be submitted with plan sheets sized 22" x 34" or 24" by 36". NOTES: 1. Flow test valid for 6 months and only applies to a single phase/unit of this project. review 2. Plan approval valid for 12 months without beginning construction. Plans subject to further and approval if 12 months expire. 3. The Authority will not be responsible for any building built too low to be served nor for any service covered by construction. 4. As-builts are required to be submitted upon completion of construction. 5.Existing county roads shall not be open cut unless permission is granted by Newton County Road Department. Submittal of authorization letter from Newton County Roads Department required. 6.If work is performed on a Georgia D.O.T. or Newton County R/W, a letter from the governing agency is required to be submitted after construction is complete stating that grassing, clean-up, drainage, etc. is acceptable. 7