Chester County Voice Radio Project Monthly Status Webinar Meeting. 1 April :00 to 14:20

Similar documents
Voice Radio Project. Kick Off Meeting February 26, Westtown Road West Chester, PA 19382

SANITARY SEWER SYSTEM ADMINISTRATIVE STANDARDS A.1 SANITARY SEWER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS

CITY OF BROOKLYN PARK COMMUNICATIONS TECHNOLOGY SITE APPLICATION / MODIFICATION REQUEST FORM

BUTLER COUNTY RADIO RFP RESPONSES TO VENDOR QUESTIONS. Butler County 700 MHz, P25 Public Safety Radio Network Issued July 8, 2016

Residential Room Additions

NEVADA DEPARTMENT OF TRANSPORTATION Addendum 3 to RFP July 28, 2017

SECTION 2 GENERAL REQUIREMENTS

Sept 28, Mukhtar mook-tar Thakur

APPENDIX H PRICE WORKSHEETS, REVISED 12/26/15 1. BATTERIES, MODULAR FLOODED LEAD-ACID 2. BATTERIES, MODULAR VALVE REGULATED LEAD ACID

BRASELTON WATER AND WASTEWATER DEPARTMENT CONSTRUCTION PLAN REVIEW CHECKLIST May 2006

Ingham County Request for Proposals Public Safety Radio System Project Manager and Consulting Services Packet #120-18

Work Type Definition and Submittal Requirements Work Type: Subsurface Utility Engineering (SUE)

APPLICATION FOR SITE PREPARATION PERMIT

CLAY TOWNSHIP BOARD OF SUPERVISORS REGULAR MEETING MINUTES September 11, 2017

Lower Oxford Township Board of Supervisors Meeting Minutes July 9, 2018

CONVEYANCE PIPELINE AND PUMP STATION

Architectural Review Board Application For Modifications & Renovations

PRESENT: Directors Bill Paskle, Chair; Tony Ray; Ali Zolfaghari; Manuel Rodriguez; Tony Rouhotas; Brett VanWey; Stephen Rea.

Anne Arundel County Dept. of Inspections and Permits Storm Drain Checklist

DEPARTMENT OF THE AIR FORCE. SUBJECT: Excavation Dewatering at Eielson Air Force Base, Alaska

Section. DEVELOPMENT STANDARDS City of Ellensburg ILLUMINATION STANDARDS

The Corporation of the City of Nelson Office of the Finance and Purchasing Manager Telephone : (250) Fax : (250)

PASQUOTANK CAMDEN ELIZABETH CITY CENTRAL COMMUNICATIONS CENTER. Request for Proposals. VHF Simulcast Paging System

Maintenance of Traffic sequence of operations including any phasing and detour maps;

EMERGENCY COMMUNICATIONS

A. This section specifies procedural requirements for Shop Drawings, product data, samples, and other miscellaneous Work-related submittals.

ATTACHMENT - AESO FUNCTIONAL SPECIFICATION

CITY AND COUNTY OF DENVER POLICY DENVER FIRE DEPARTMENT. Emergency Responder Radio Enhancement Coverage System (RES)

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS

UNION COUNTY VOCATIONAL-TECHNICAL SCHOOLS West Hall Addition Project Raritan Road, Scotch Plains, NJ

CHESTER COUNTY AREA AIRPORT AUTHORITY MINUTES. May 1, 2012

CLAY TOWNSHIP BOARD OF SUPERVISORS REGULAR MEETING MINUTES August 8, 2011

SPECIFICATIONS FOR NEW UNDERGROUND RESIDENTIAL DISTRIBUTION SYSTEMS

REQUEST FOR COUNCIL DIRECTION ON PLACEMENT OF A RADIO TOWER ON DRAKES PEAK


A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

ADDENDUM 1. Forsyth County. Request for Qualifications and Proposals. Consulting Services for Public Safety Radio Communications

SUBMITTAL REQUIREMENTS RCV D REJECT PENDING

Signs, Canopies & Awnings City of Oshkosh Department of Community Development

Excavating, Backfilling, and Compaction for Utilities Piping (Plumbing).

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

Service Level Agreement

MEMORANDUM. Award of Alexis Tower Construction Project Phase 2 Emergency Radio Communications Project Alexis

Columbia Communications District Request for Information New Radio Communications System

Cover photo: Snow blanketed the State Radio Project s Mount Aldrich site in early November. The Grant County site sits at nearly 7,000 feet in

DEPARTMENT OF COMMUNITY DEVELOPMENT SITE PLAN INFORMATION

Statewide 800 MHz trunked radio system available for all emergency responders (local, State, Federal)

Suggested Traffic Signal Design Procedures Indefinite Delivery (ID) Contract Locations and Conventional Signal Contract Locations

NZQA unit standard version 3 Page 1 of 5. Install and maintain telecommunications radio frequency systems

MEMBERS ABSENT Buffalo Grove Fire Department, Rolling Meadows Fire Department.

SECTION ADMINISTRATIVE REQUIREMENTS

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

Russell Township ASSESSMENT TO CONNECT TO OFS FOR DISPATCH SERVICES PAGE 1 OF 7

Functional Specification Revision History

CITY OF RICHMOND SUBDIVISION PLAT AND PUBLIC INFRASTRUCTURE SUBMITTAL, REVIEW AND APPROVAL PROCEDURES

Delivering Reliability. Services. Strength You Can Count On. oldcastleprecast.com/services

FIT-OUT PERMIT REQUEST (GENERAL WORKS)

FDOT Upgrades for Interoperability

Overview of Mineral Exploration and Development Regulations in Ontario Municipality of Trent Lakes March 8, 2018

StormTrap Guide Specification. StormTrap SingleTrap on Pad Foundation Groundwater BELOW Invert Revised 11/21/18

B-PERMIT PLAN CHECK MANUAL

Mailing Address: Fax number: City: State: Zip: Property Owner: City: State: Zip: City: State: Zip:

SECTION SUBMITTAL PROCEDURES

September 21, Mannik Smith Group 1771 North Dixie Highway Monroe, Michigan RE: LA Fitness City File No.: CVLP

Cover photo: Smoke from a nearby wildfire is visible from the Lime Hill radio site in Baker County. A crew from Summit Solutions Group was on site

CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division STORM DRAIN IMPROVEMENT PLAN REVIEW CHECKLIST

NORTHWEST FIRE DISTRICT OUT OF DISTRICT FIRE CODE PERMIT FEE SCHEDULE JULY 1, 2014

NSP/007/019 - Guidance on Substation Design: EHV Substation Drawing Policy

StormTrap Guide Specification. StormTrap 2 SingleTrap on Aggregate Foundation Groundwater BELOW Invert Revised 11/30/17

Town of Holly Springs Sign Installation Packet

Cover photo: From the conference room between the Oregon State Police Northern Command Center and the Oregon Department of Transportation Northwest

DEVELOPMENT REVIEW COMMENTS LAND DISTURBANCE PERMIT (LDP) CLEARING CLEARING & GRUBBING GRADING. Date Reviewed by. Project Name

Radio System Replacement Project

SECTION SUBMITTAL PROCEDURES

TOWN of LAKESHORE SITE PLAN CHECKLIST

Washington County Road Engineering Plan Submittal/Review Checklist

Application for Site Plan Review

CITY OF BAYTOWN CENTRAL DISTRICT WASTEWATER TREATMENT PLANT GRIT, SECURITY, AND SCADA IMPROVEMENTS SCOPE OF SERVICES

February 12, Regular Session Bonifay, Florida

Ernie B. McNeely, Township Manager Michael J. McGrath, Superintendent of Police Lower Merion Township Radio System Replacement DATE: June 25, 2014

CHAPTER 28 ACTIVATING/DEACTIVATING A SIGNAL

Customer Connection Guide Updates Effective May 2017

The GMFI Process. Design Intent Document Preparation. Enroll in GMFI Program. Image Consultation. You are here. Design Intent Document.

WELCOME. C P S E n e r g y Q u a r t erly P o l e At t a c h m e n t Wo r k s hop. J a n u a ry 2 5,

SECTION STEEL LIGHTING STANDARDS. 1. Electrical conduit and fittings; Section

Wicomico County. RFP for new 700/800 hybrid P25 Phase II radio system

CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division SANITARY SEWER IMPROVEMENT PLAN REVIEW CHECKLIST

2020 Census Local Update of Census Addresses Operation (LUCA)

Information package for obtaining a building permit

CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division STREET/ALLEY IMPROVEMENT PLAN REVIEW CHECKLIST

CHECKLIST THE FOLLOWING INFORMATION AND DOCUMENTATION MUST BE SUBMITTED TO DEVELOPMENT SERVICES BEFORE YOUR APPLICATION CAN BE PROCESSED.

Conceptual, Preliminary and Final Site Plan Review in Holladay City

PORT OF ST. HELENS SCAPPOOSE INDUSTRIAL AIRPARK PARALLEL TAXIWAY B RELOCATON AIP PROJECT ADDENDUM NO. 1

PECO Energy EDACS Trunked Radio System

CHAPTER 14: TRAFFIC SIGNAL STANDARDS Introduction and Goals Administration Standards Standard Attachments 14.

UCCS University Hall Fire Sprinkler System Upgrade March 1, 2011 RTA SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL

ACSA PLAN REVIEW CHECKLIST (Guideline Only) (4) Standard water and sewer general plan notes (attached).

A. Action Submittals: Written and graphic information that requires Architect's responsive action.

PLANNING DIVISION COMMUNITY & NEIGHBORHOODS DEPARTMENT

OPERATIONAL ADVICE NOTICE (OAN) OAN 114/2018 MAN-TP PP16 HV & AGL PIT & DUCT INSTALLATION This OAN replaces OAN with immediate effect.

Transcription:

1 April 2015 14:00 to 14:20 Agenda The Agenda for the meeting was reviewed and encompassed: Construction Status Leasing Status Technical Overview Schedule Review Two Week Look-Ahead Additional items for discussion Site Highlights Construction Status The updated site construction status chart was reviewed by Prem. o Coatesville and Upper Uwchlan still have open items remaining o Caln, East Nantmeal, and King Ranch are in queue to begin work o Malvern, and Chadds Ford are in progress o Baron Hill, Bucktown, Downingtown, Elverson, Embreeville, Fairview, Forestville, Glen Run, Kemblesville, Little Britain, New Garden, Norco, Octorara, Phoenixville, Pocopson, South Coatesville, Valley Forge, Valley Hill, Westtown, and WPLY have been completed at this time Malvern o Trenching and underground wiring to get power from the new PECO pole is complete. Electrical Inspection was completed as well on 3/27 and PECO has the work order for a new meter expecting it by 4/3/15 Norco Site Construction underway. It s a multi week effort: Mobilization, Preconstruction Site meeting Excavation Shelter, generator, and propane foundation pads Site grounding and conduits installation Set shelter Install generator Install natural gas line Install RF antenna and lines PECO electrical service completed. Deliver and install LMR and MW equipment Site clean up Installation of the natural gas line took place yesterday. Construction is complete as of 3/31/15 and equipment delivery is scheduled for next week. Equipment for both Malvern and Norco is scheduled for delivery on Friday 4/3/15

Bucktown Site Construction underway, multi month effort: Mobilization, Preconstruction Site meeting Excavation and form piers New tower foundation Site grounding Tower delivered Site grading, backfill compaction Stack and install tower Install compound fencing Install RF antenna and lines. (antennas are installed) Deliver and install MW equipment Deliver and install LMR shelter equipment Site cleanup Construction is complete, fence installation wrapped up this morning. Alcatel MW installation is starting 4/1/15. Chadds Ford Site Construction is underway. Coordinating construction activities with Crown Castle: Construction of tower extension is underway by Crown Castle. Work started last week Installation of antenna mounting collar and side arms by TSU. TSU was able to coordinate with Crown Castle and perform this work while the extension was still on the ground Install the antennas and all ground work for new shelter Excavation Shelter, generator, and propane foundation pads Site grounding and conduits installation Set shelter and Install generator Install RF antenna and lines Deliver and install MW equipment Deliver and install LMR shelter equipment PECO power confirmed Site cleanup Shelter is expected to ship middle of April

King Ranch Site plans are being finalized and BP application submittal this week. Construction scheduled to start early May pending BP approval. The final NEPA/SHPO approval has now been received. Site Construction beginning multi month effort: Mobilization, Preconstruction Site meeting Excavation Shelter, generator, and propane foundation pads Site grounding and conduits installation Set shelter and Install generator Vertical antenna mount tower extension Install RF antenna and lines Deliver and install MW equipment Deliver and install LMR shelter equipment PECO power confirmed Site cleanup LMR Equipment Deliveries to Shelters The updated LMR equipment installation status chart was reviewed Delivery of equipment to Norco and Malvern possibly later this week Installation is underway at Phoenixville. Work should be completed by 4/3/15 A total of 15 sites are now connected into the P25 network: o Still pending open items are: King Ranch and Upper Uwchlan o Currently in queue are: Chadds Ford, East Nantmeal, Norco, and Malvern o Equipment has been delivered to: Bucktown, Caln, Coatesville, and Phoenixville o Installation is complete at: Baron Hill, Downingtown, Elverson, Embreeville, Forestville, Glen Run, Kemblesville, Little Britain, New Garden, Octorara, Pocopson, Valley Forge, Valley Hill, Westtown and WPLY. All of these sites have had their equipment fully connected into the Harris P25 radio network at this time

Alcatel Microwave Installation Status The Alcatel microwave installation status chart was reviewed by Harris Four of the new microwave paths are now fully tested and aligned Bucktown and Norco are currently scheduled for installation We are still waiting on the Coatesville site to connect the PSTC into the microwave network

Site Highlights Leasing Progress Caln o The Bill of Sale for Chester County to acquire the Nextel shelter is under review. We are hoping to have this on the April 14 th Commissioner s sunshine agenda o The Chester County team met with Caln township and a two phase approach to apply for building permits was discussed and agreed upon 1. Building permit for shelter interior work and moving the antenna lines has already been submitted by Harris 2. A separate drawing package and building permit application is being prepared for the generator installation. This permit needs to address the potential flood plain issue o Harris is scheduling a topographic survey at the site to support resolving the flood plain issue. This effort is all relative to the generator installation and will not hold up equipment installation or configuration Upper Uwchlan o The Lease Agreement has been signed by the Chester County Commissioners. The Lease will be on the April 14th Upper Uwchlan Township Board of Supervisors meeting for approval o The Upper Uwchlan Township Board of Supervisors are scheduled to make a decision at their meeting on April 14 th regarding Chester County s conditional use and land development applications o A Storm water Operations & Maintenance Agreement will also need to be approved and signed by Chester County and Upper Uwchlan Township o Harris is revising the Preliminary/Final Land Development Plans to address comments from the Upper Uwchlan Township engineering o Once the Preliminary/Final Land Development Plans are revised and approved, Harris intends to submit the revised plans along with the BP application submittal next week o There was some public opposition to the tower during the conditional use testimony East Nantmeal o Building retro fitting plans were finalized and submitted to Philips Brothers Electric for Chester County s equipment room modifications. These plans need to be included as part of the lease agreement with Philips Brothers Electrical Contractors o Building and electrical permit application is ready for submittal this week o Retro fitting material is on order and work is tentatively scheduled to start 4/20/15 Coatesville o The County received the new passing structural analysis from American Tower on 3/31/15 o ATC is now in discussions with PA American water to obtain the landlord consent o ATC will countersign the lease once American Water landlord consent is obtained

Site Approval Update The Tower License Agreement for East Nantmeal is on the Commissioner agenda for March 17th Sites that have already been turned over to Harris include: Baron Hill Bucktown Caln Chadds Ford Downingtown East Nantmeal Elverson Embreeville Technical Overview Fairview Forestville Glen Run Kemblesville Little Britain Malvern New Garden Norco Octorara Phoenixville Pocopson S. Coatesville Valley Forge Valley Hill Westtown WPLY Fifteen site installs and alignments are completed. Phoenixville and Bucktown sites are in queue for alignment and configuration Installation is underway at the South Coatesville alternate center for console equipment and backup dispatch radios. Work for the installation at Westtown will commence once South Coatesville is finished Remote VPN network access being coordinating with Chester County DES and DCIS to configure the firewall for remote access Establishing a connection between the CAD network and the Harris network to begin testing the PTT application with the Harris P25 system. Site alarms from the new sites are being brought into the existing TSM-8000 alarm monitoring system. Fleet Mapping This week is the second fleet mapping workshop Team is finalizing the system talk group list, unit numbering scheme, and radio personality templates Schedule As of Monday, we are at 78% overall completion of the project tasks Project completion is still scheduled for 4/21/2016

Next Two Weeks Chester County Voice Radio Project Ongoing activities for next several weeks: o LMR and MW equipment installation inside the shelters by Metropolitan o Site optimization by Harris-Metropolitan (15 complete with 2 in queue) o Testing sites and connections to NSCs and Control Points o Construction permit application filings o Site construction activities as sites moves thru the funnel o MW hop alignment and optimization for completed hops o Revise drawings and produce technical justifications for zoning/land development applications o Chester County and Harris continue to work on fleet mapping data Next meetings: o Face to Face will be on Wednesday 4/15/2015 at 14:00 o Webinar will be on Wednesday 5/06/2015 at 14:00 Q&A Discussions No additional questions or discussion took place The meeting concluded at 14:20.