CASE STUDY- FAULT IN POWER TRANSFORMER AT LOKTAK POWER STATION. - S K Mishra & S K Das NHPC Ltd O&M Division

Similar documents
RESIDUAL LIFE ASSESSMENT OF GENERATOR TRANSFORMERS IN OLD HYDRO POWER PLANTS

REPORT ON INVESTIGATION OF FAILURE OF 100 MVA, 220/66-33/11 KV POWER TRANSFORMER AT 220KV GEETA COLONY SUBSTATION OF DELHI TRANSCO LTD.

Benefits of SFRA - Case Studies

Chapter 7 Conclusion 7.1 General

Report on investigation of failure of 315 MVA Auto transformer at 400 kv Bawana Substation of Delhi Transco Ltd.(DTL)

Operational Management of Grid Transformers An Experience of POWERGRID

Innovative Test Techniques and Diagnostic Measurements to Improve the Performance and Reliability of Power System Transformers

Acoustic Emission in power transformers. Ajusco 15, Colonia Portales, Delegación Benito Juárez, C.P , México, D.F.

ABB Power Products Service

Variation in SFRA plot due to design and external parameter

N S Sodha, Former Executive Director, POWERGRID Corpn, Gurgaon

Power transformer failure management on the Eskom distribution network in Limpopo

Basic Principles and Operation of Transformer

Cholla T809 Condition Assessment Report Provided by students of Northern Arizona University with the support of Arizona Public Service

HOW TO SAFE GUARD THE TRANSFORMER..???

Transformer Factory Testing

Hands-On Transformer Testing and Maintenance

Advanced Diagnostic Testing Services. Provides detailed and reliable results

DEFERRING REPLACEMENT OF A 600 MVA, 345GRD Y/138GRD Y/ 13.8 kv SHELL TYPE WESTINGHOUSE AUTOTRANSFORMER

Substation Preventive Maintenance

Understanding the Value of Electrical Testing for Power Transformers. Charles Sweetser, OMICRON electronics Corp. USA

Monitoring Solutions For Power Transformers, Reactors, Bushings and Instrument Transformers

POWER TRANSFORMER SPECIFICATION, DESIGN, QUALITY CONTROL AND TESTING 18 MARCH 2009

Power Transformer Condition Assessment Based on Standard Diagnosis

GUJARAT TECHNOLOGICAL UNIVERSITY, AHMEDABAD, GUJARAT

Schedule of Accreditation issued by United Kingdom Accreditation Service 2 Pine Trees, Chertsey Lane, Staines-upon-Thames, TW18 3HR, UK

Understanding the Value of Electrical Testing for Power Transformers. Charles Sweetser - OMICRON

A Comparative Diagnosis Approach on Transformer s Insulating Oil Ming-Jong Lin

Power Transformers Basics

EPS AUSTRALIA SERVICES HV TESTING & COMMISSIONING CAPABILITY

TesTIng of Power. Transformers are the largest, most. feature. By brandon dupuis

Power Transformer Testing

CHAPTER 3 REVIEW OF POWER TRANSFORMER PROTECTION SCHEMES

FIELD ELECTRICAL TESTING SPX TRANSFORMER SOLUTIONS, INC.

Transformer Protection

IN ELECTRICAL ENGINEERING - I C M E T CRAIOVA

Application of Polarisation Depolarisation Current (PDC) technique on fault and trouble analysis of stator insulation

Discipline Electrical Testing Issue Date Certificate Number T-2837 Valid Until Last Amended on - Page 1 of 6 LOCATION 1

Effective maintenance test techniques for power transformers

Use of On and Offline Oil Analysis on the ESB, Distribution and Generation Networks

Matz Ohlen Director Transformer Test Systems. Megger Sweden

7. INSPECTION AND TEST PROCEDURES

Identification of Overheating in Transformer Solid Insulation by Polarization Depolarization Current Analysis

Transformers handling and transport

Martin Stoessl R&D Manager Siemens Transformers Austria - Weiz

PRE COMMISSIONING TESTS ON EQUIPMENT AT 33/11 KV SUB STATIONS. IR Values are to be read on the megger by meggering the Power transformer

Understanding and Extracting Valuable Information from Basic and Advanced Power Transformer Testing Techniques

Effective Maintenance Test Techniques and Diagnostic Measurements to Improve the Performance and Reliability of Power System Transformers

SERVICE OFFERINGS FOR POWER SYSTEM STUDY & CONDITION MONITORING FOR STATIC EQUIPMENT

Specialists in HV and MV test and diagnostics. Testing in Substations

Modern transformer relays include a comprehensive set of protective elements to protect transformers from faults and abnormal operating conditions

DATA SHEET FOR LIGHTING TRANSFORMER APPD. BY VDV PROJECT NO

Distribution Equipments - Technology and Applications. Training Module for DISTRIBUTION TRANSFORMER

About us. Vision. To lead our field in innovation, quality and customer service.

PARTIAL DISCHARGE MEASUREMENT

EI HIGH VOLTAGE INSULATION TESTING POLICY

EFFECETIVE TRANSFORMER CONDITION ASSESSMENT

HOLISTIC APPROACH TO ON-LINE TRANSFORMER MONITORING: KNOWLEDGE MANAGEMENT FIRST!

Welcome to the Session on. HT Distribution Network

A Novel Technique to Precise the Diagnosis of Power Transformer Internal Faults

B3-102 THE ROMANIAN EXPERIENCE REGARDING THE RISK OF MANAGEMENT IN THE OPERATION AND MAINTENANCE OF LARGE POWER TRANSFORMERS IN HV SUBSTATIONS

TIGHTENING TORQUE ON WOODEN CORE CLAMP (Nm) (STEEL FASTENER) 1 M M M M M

Form-IV. Form of Inspection/Test Report. (Under Regulation 43)

Commissioning Manual Distribution Transformers - Three-phase Oil Filled

IMPORTANCE & PROCESS OF RLA STUDIES IN ASSESSMENT OF NEED FOR R&M - A CASE STUDY. CPRI, Bengaluru

Testing and Diagnostic of Power Transformers & Distribution Transformers

KNOW MORE ABOUT THE TRANSFORMERS. Glossary Transformers

Fault Detection in Transformer Using Frequency (Sweep) Response Analysis

PDS100 Application Note: The use of High Frequency Current Transformer as sensor for Transformer diagnostics

TECHIMP Power Transformer Monitoring

ELE-CMOS-E-2001 Electrical Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS

Transformer condition assessment with an integrated test van

Training Fees 3,300$ per participant including Materials/Handouts, Tea/Coffee Refreshments & International Buffet Lunch.

Health indexes for power transformers: A case study

Case Studies of Electric Power Equipment Diagnostics Using Acoustic Emission

Condition Assessment of High Voltage Insulation in Power System Equipment. R.E. James and Q. Su. The Institution of Engineering and Technology

ECP HV INSULATION TESTING

TECHIMP Technologies & Services for Diagnostics and Monitoring of High Voltage Assets

SAMPLE. Determining the health of your power transformer begins with Transformer Clinic s SAMPLE testing programs.

Federal Power Transformers LLC based in Abu Dhabi, UAE


Shunt Reactors. Global Top Energy, Machinery & Plant Solution Provider

Transformer Shunt Fault Detection using Two Techniques

Efacec work every day to anticipate solutions for a sustainable world in the new energy era.

save energy, it is precious SYNERGY transformers Mfg. of all types of Distribution / Power & Furnace Transformers

شركة كهرباء محافظة القدس المساهمة المحدودة JERUSALEM DISTRICT ELECTRICITY CO. LTD.

DMRC ELECTRICAL STANDARDS & DESIGN WING (DESDW)

Mots clés Power Transformer, Condition Assessment, On-line Monitoring Internet. Par S. Tenbohlen *, T. Stirl, M. Rösner * * ALSTOM T&D, Germany

ECP HV INSULATION TESTING

TECHNICAL DATA TYPE CMD OIL-IMMERSED ON-LOAD TAP CHANGER

Transformer Winding Design. The Design and Performance of Circular Disc, Helical and Layer Windings for Power Transformer Applications

TRANSFORMER OPERATIONAL PRINCIPLES, SELECTION & TROUBLESHOOTING

Power Measurements and Basic Electrical Diagnostic Tests

Problems connected with Commissioning of Power Transformers

EE188: Transformer Design, Construction, Testing & Maintenance

TAP CHANGER SELECTING MANUAL TECHNICAL DATA

INTERPRETATION METHODOLOGY TO IDENTIFY FAULT LOCATION IN A POWER TRANSFORMER

Transformer Design: Economics & Reliability

EE223D: Distribution Power Transformer

Transcription:

CASE STUDY- FAULT IN POWER TRANSFORMER AT LOKTAK POWER STATION - S K Mishra & S K Das NHPC Ltd O&M Division 1

PRESENTATION COVERS Introduction DESCRIPTION OF EVENTS INITIAL RESPONSE DETAILED INSPECTION FINDINGS RESTORATION R OF TRANSFORMER ANALYSIS OF EVENT AND ROOT CAUSE FINDINGS CONCLUSION RECOMMENDATION 2

INTRODUCTION The faulted transformer (Identification no. B5255) under study is 13.33 MVA, single phase, 11 KV/132 KV/ 3, ONAF and was manufactured by GEC in 1977 and under operation since 1983. The winding of the said transformer was replaced in 2011 at factory works of OEM. The repaired transformer was transported to Power House by road & put into service in 2014. The Power evacuation system at Loktak Power Station consists of four 132 KV transmission line. Due to hilly terrain and the lines are laid through dense forest, frequent fault occurs on transmission lines. The transformers installed at Loktak Power Station are subject to frequent short circuit current vis-à-vis electro-mechanical stress. 3

DESCRIPTION OF EVENTS On 07/08/2016 all the three units ( 3 x 35 MW) of Loktak Power Station were running at full load prior to the event. At 9:00 hrs on 07/08/2016, Buchholz relay alarm of Y-phase transformer of Unit#3 appeared. During inspection, gas accumulation in the Buchholz relay was observed and the unit was stopped at 11:10 hrs for further investigation. Here it is pertinent to mention that, no other protection relay started or operated even after operation of transformer under fault condition for more than two hours which indicates low energy fault. 4

INITIAL RESPONSE Tan Delta and capacitance test: The test was conducted at 2 KV, 5KV & 10 KV at HV side and 1 KV, 3KV & 5KV at LV side at winding/oil temperature at 52 0 C. The test result at 10KV (HV side) and 5KV (LV side) is presented below: Sl. No. Insulation Tested Capacitance (pf) Tan Delta (%) The above test results showed no abnormality in transformer winding insulation. ma Watts 1 HV to LV +GND 4151 0.166 13.01 0.215 2 HV-GND 1718 0.181 5.395 0.097 3 HV-LV 2434 0.150 7.639 0.114 4 LV to HV +GND 7462 0.209 11.71 0.122 5 LV to GND 5030 0.238 7.891 0.094 6 LV to HV 2433 0.152 3.807 0.029 5

INITIAL RESPONSE Breakdown Voltage (BDV) test: The BDV of transformer oil was tested as 47 KV at 2.5 mm gap, which was also within permissible limit. Therefore, transformer oil insulation property also found to be acceptable. Insulation Resistance (IR) Test: IR test of transformer winding was conducted at 46 0 C by using 5KV applied voltage. Winding IR at 5KV/60Sec (GΩ) PI (IR at 10 min/ir at 1 min) HV-LV 20.3 1.4 HV-LV+E 62.0 1.28 LV-HV+E 36.9 1.8 The above test result showed readings within permissible limit. In addition to above turn ratio and magnetizing current tests were also conducted and the results were within normal limit. 6

INITIAL RESPONSE Result of DGA test: The DGA test of transformer oil (after fault) was conducted. The recent DGA test result of transformer oil sample along with that of previous result is as under: Characteristics PPM (measured on 08/08/2016) PPM (measured on 25/05/2016) Methane 70 4 Ethane 18 1 Ethylene 184 7 Acetylene 3 ND Hydrogen 29 2 Oxygen 17133 15645 Nitrogen 63041 55238 Carbon monoxide 345 241 Carbon dioxide 3541 2042 7

INITIAL RESPONSE The DGA test conducted on 08/08/2016 showed increased content of hydro-carbon gases i.e. Methane, Ethane, Ethylene and Acetylene as compared to that of previous result. This clearly indicated that there can be an arc inside the transformer causing overheating of oil and successive generation of hydro-carbon gases. The transformer was removed from service for further investigation. Unit#3 was restored using spare transformer. 8

DETAILED INSPECTION FINDINGS The faulty transformer was thoroughly inspected on 25/08/2016 at site. After dismantling of all the accessories and top cover from the transformer, it was found that the core along with winding had shifted from its original position. Metal dust was also found on the transformer tank guiding rail area. The core along with winding was removed from the transformer tank to check the extent of damage caused and it was found that the insulation sheet at the bottom of the tank got shifted from its original position. However, no deformation of core/winding or any hot spot was observed over the core/winding. The Inspection at tap changer section reveals partial melting of contact finger from its edge 9

DETAILED INSPECTION FINDINGS Fig.1 Metal Dust at core foundation rail Fig.2 Displacement of core insulation 10

DETAILED INSPECTION FINDINGS DETAILED INSPECTION FINDINGS Fig. 3 Healthy winding Fig. 4 Hot spot at Tap Changer contact 11

RESTORATION OF TRANSFORMER Thorough cleaning of transformer core and winding was done. It was decided to bypass the tap changer section based on following consideration: The tap changer is not used to control reactive power supply vis-à- vis bus voltage at our Generator Bus (PV bus). The reactive Power supplied by the generator is sufficient to control the bus voltage within permissible limit. Fig. 5 Tap Changer Bypassed 12

RESTORATION OF TRANSFORMER The transformer core-winding was put into transformer tank properly. The IR test was conducted to ensure proper insulation between Channel to core, Tank to Core and Channel to Tank. The transformer was properly boxed up by using new gaskets. All the accessories except conservator were fitted and the transformer was filled with Nitrogen with a pressure of 0.2 Kg/sqcm to ensure leakage free boxing up of transformer. The main tank of the transformer was kept under partial vacuum (at 400 mmhg) for 12 hrs to facilitate release of moisture from paper insulator. Oil filling was started thereafter by oil filtration plant after installation of Conservator and radiator. All electrical tests were conducted and the test results showed the value within permissible limit. The work was completed in 6 days & the transformer is kept as spare. 13

ANALYSIS OF EVENT & ROOT CAUSE FINDINGS Two possibilities for the failure is envisaged. a) Displacement of core-winding section may have occurred during transport of transformer after repair. b) Due to frequent line fault the transformer was subjected to electromechanical stress vis-à-vis vibration. This may have further contributed towards misalignment of tap changer contact finger and successive low energy PD/fault Premature O&M failures are occurring due to accelerated ageing and/or weakening of short circuit withstand capability of transformer due to repeated short circuits in the network. The number of through faults seen by the transformers being high has a cumulative effect on the mechanical weakening of the winding supports and insulation & increases the probability of premature failure of the transformer. 14

ANALYSIS OF EVENT & ROOT CAUSE FINDINGS A recent, extensive survey of about 1000 major transformer failures by CIGRE WG A2.37 [8] showed that: Windings are the most common failure location mechanical failures account for over 20% of all failures of substation transformers, External short-circuit is the second largest known failure cause (after ageing). 15

CONCLUSION The weakening of winding foundation, if any during transportation is required to be confirmed before putting the transformer into service. The Sweep Frequency Response Analysis Test (SFRA) should necessarily be conducted both before despatch and after receiving/installing of transformer at site. Any deviation in frequency response signatures before and after transport should be observed carefully as it indicates mechanical displacement and deformation of winding occurred during transport. The frequent faults in transmission line also aggravate the situation and further accelerate the deformation/displacement of transformer winding. 16

CONCLUSION The Following facts are presented here as envisaged from above analysis: a) Transformers subjected to frequent short circuit (through fault) condition, may develop faults due to mechanical stress. However, no routine electrical test could specifically pin point such fault as the fault do not involve earth and the same is evident from the above test results. c) The Power Station should do periodic DGA tests of the GSU transformer oil as per present practice. A database consisting of all test records of individual transformer along with fault/failure history should be maintained. c) Immediate shutdown of unit should be ensured if Buchholz alarm appears. Restart of unit can only be considered after completion of thorough investigation. d) Buchholz-relays may operate unnecessarily due to the vibrations that occur during short-circuit conditions. Therefore, the behaviour of such relays for any transformer should carefully be monitored and recorded. 17

RECOMMENDATIONS The Power Station should consider carrying out (preferably include in the specification) Sweep Frequency Response Analysis Test (SFRA) on transformer both before transportation from workshop and after receiving at site. By comparing the above two signatures, physical displacement of transformer winding, if any, caused during transportation can be assessed. Further, the transformer should be fitted with impact recorder before transportation to record the mechanical impact on the transformer during transportation. 18

THANK YOU 19