SECTION ADMINISTRATIVE REQUIREMENTS SECTION ADMINISTRATIVE REQUIREMENTS

Similar documents
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

SECTION PROJECT MANAGEMENT AND COORDINATION

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS

SECTION A. RFI: Request from Contractor seeking interpretation, information, or clarification of the Contract Documents.

SECTION ADMINISTRATIVE REQUIREMENTS

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

2016 CDM Smith All Rights Reserved July 2016 SECTION PROJECT MEETINGS

A. Action Submittals: Written and graphic information that requires Architect's responsive action.

JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia

SECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

East Central College

SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS

A. Action Submittals: Written and graphic information that requires Engineer's responsive action.

Section Meetings Section Material and Equipment. None Required

UNION COUNTY VOCATIONAL-TECHNICAL SCHOOLS West Hall Addition Project Raritan Road, Scotch Plains, NJ

UCCS University Hall Fire Sprinkler System Upgrade March 1, 2011 RTA SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL

SECTION CLOSEOUT SUBMITTALS SECTION CLOSEOUT SUBMITTALS

Answer: Qualification statement should be provided with the bid.

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

DIVISION 1 GENERAL REQUIREMENTS SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES

A. This section specifies procedural requirements for Shop Drawings, product data, samples, and other miscellaneous Work-related submittals.

SECTION SUBMITTAL PROCEDURES

SECTION CONTRACTOR SUBMITTALS. A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER.

DIVISION 1 - GENERAL REQUIREMENTS SECTION SUBMITTALS

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES

.2 Accompany all submissions with a transmittal letter, in duplicate, containing:.4 Specification Section number for each submittal

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

SECTION SCHEDULE OF VALUES PART 1 - GENERAL 1.1 THE REQUIREMENT A. This Section defines the process whereby the Schedule of Values (Lump Sum

Taylor County July 2011 SECTION SHOP DRAWINGS, WORKING DRAWINGS AND SAMPLES

SECTION PROJECT COORDINATION VIA BIM

SUBMITTAL PROCEDURES

STANDARD SPECIFICATIONS SECTION SUBMITTAL PROCEDURES

Bidders for the Oak Brook Park District Family Locker Room Renovation

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SECTION SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS

Jacksonville District Master

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

INDEX OF SPECIFICATIONS SECTION F SPECIAL CONDITIONS DIVISION 1 - GENERAL REQUIREMENTS:

SECTION 2 GENERAL REQUIREMENTS

DWG, Inc. Coastal Carolina University State Project No. Consulting Engineers HTC Arena Lighting H17-N112-JM

A. Section includes administrative and procedural requirements for project record documents, including the following:

Construction Phase Project Management and Documentation

What Are Submittals?

[Note to PSC: Include these sections in the Contract Documents, even though some are not included in the U of I Facilities Standards]

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 12/12/2018

UNIFIED FACILITIES GUIDE SPECIFICATIONS *************************************************************************** SECTION

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

Working Drawing Manual

SECTION OPERATION AND MAINTENANCE DATA

SUBCONTRACTORS PROCEDURES MANUAL EXHIBIT A.15 SAMPLE MANUAL ONLY FINAL MANUAL WILL BE CUSTOMIZED FOR GREAT WOLF LODGE

CHAPTER 11 PRELIMINARY SITE PLAN APPROVAL PROCESS

FTEV Repair Mezzanine Bldg Hurlburt Field, Florida SECTION DESIGN AFTER AWARD

Section Project Closeout

SECTION SUBMITTALS

National BIM Standard - United States Version 3

AIA Continuing Education

SANITARY SEWER SYSTEM ADMINISTRATIVE STANDARDS A.1 SANITARY SEWER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS

Chapter 1 General Design Information

Facility Services Subgroup Preface for Divisions 21` through 28

FAST TRACK WORKSHOP OBJECTIVES

01100 SUMMARY OF WORK

835 Gil Harbin Industrial Blvd Valdosta, GA 31601

***************************************************************************** DRAFT UFGS- 01 XX XX (FEB 2014)

ADDENDUM #2 September 12, 2018

Bid No. B14-02 Building 100 HVAC Improvements

Recommended Practice PS-24 Tracking the Procurement Process (TCM Framework Reference 7.7)

Vanderbilt University Standard Specification Revised 2/6/08

1. Land survey Work. 2. Civil and Structural engineering services.

State College Area School District

CITY OF RICHMOND SUBDIVISION PLAT AND PUBLIC INFRASTRUCTURE SUBMITTAL, REVIEW AND APPROVAL PROCEDURES

DIVISION 11 EQUIPMENT SECTION PHOTO DARKROOM FUME EXHAUST VENT-HOODS

Designer CM/Owner s Rep Prime Contractor SubContractor Supplier Manufacturer

PMA ONLINE TRAINING. Commercial Drawings. One Hour Continuing Education

PROCEDURE FOR PROCESSING WORKING DRAWINGS

Brad Luke. Director Peddle Thorp Auckland

Working Drawing Procedure

SPECIAL PROVISION Description of Project, Scope of Contract and Sequence of Work

2017 CDM Smith All Rights Reserved November 2016 SECTION PROJECT MANAGEMENT INFORMATION SYSTEM (PMIS)

DESIGN REVIEW PROCESS AND APPLICATION

The GMFI Process. Design Intent Document Preparation. Enroll in GMFI Program. Image Consultation. You are here. Design Intent Document.

SECTION BASIC MECHANICAL REQUIREMENTS GENERAL BASIC MECHANICAL REQUIREMENTS PART RELATED DOCUMENTS

Electronic Document Review (EDR)

UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS

City of Lompoc Building & Safety Services Section 100 Civic Center Plaza Lompoc, CA Phone: Fax:

Engineering Drawing System

Anticipated schedule, Page 2. Change the Contract Term from 635 Days to be 1,127 Days.

SECTION BASIC MATERIALS AND METHODS. A. The requirements of the General Conditions and Supplementary Conditions apply to all Work herein.

September 6, 2018 CITY OF BERKELEY SHATTUCK RECONFIGURATION AND PEDESTRIAN SAFETY PROJECT SPECIFICATION NO C ADDENDUM NO.

Fiscal 2007 Environmental Technology Verification Pilot Program Implementation Guidelines

NEVADA DEPARTMENT OF TRANSPORTATION Addendum 3 to RFP July 28, 2017

WATER MAIN ALONG ENTRANCE TO ENCINO PS / HWY 281 TO ENCINO TANK Solicitation Number: CO Job No.:

SECTION D BIM COORDINATION DRAWINGS - CONTRACTORS

Stanford University-Facilities Design Guideline SECTION Plans Review Submission Guidelines

Procedure for Obtaining Verification of a Stormwater Manufactured Treatment Device from New Jersey Corporation for Advanced Technology

B. The designated coverage areas shall include both indoor and outdoor coverage.

Transcription:

PART 1 GENERAL 1.01 SECTION INCLUDES A. Project Coordination. B. Preconstruction meeting. C. Progress meetings. D. Preinstallation conferences. E. Requests for information (RFI). F. Coordination drawings. SECTION 01 30 00 G. Submittals for review, information, and project closeout. H. Number of copies of submittals. I. Deferred submittals. J. Submittal procedures. K. Timing of submittals. L. Product submittals. 1.02 RELATED REQUIREMENTS A. Section 01 10 00 - Summary: Delegated design requirements. B. Section 01 32 00 - Construction Progress Documentation: Form, content and administration of schedules. C. Section 01 40 00 - Quality Requirements: Testing Laboratory Reports and Manufacturer's Field Services. D. Section 01 60 00 - Product Requirements: Contractor's list of Products. E. Section 01 70 00 - Execution: Additional coordination requirements. F. Section 01 78 00 - Closeout Submittals: Project record documents. G. Section 01 91 13 - General Commissioning Requirements: Additional procedures for submittals relating to commissioning. 1.03 PROJECT COORDINATION A. Coordinate scheduling, submittals, and the work of the various Sections of the Specifications to assure efficient and orderly sequence of installation of interdependent construction elements, with provisions for accommodating items installed later. B. Verify that utility requirement characteristics of operating equipment are compatible with building utilities. Coordinate work of various Sections having interdependent responsibilities for installing, connecting to, and placing in service, all such equipment. C. Coordinate space requirements and installation of mechanical and electrical work which are indicated diagrammatically on Drawings. Follow routing shown for piping, ductwork, and conduit as closely as practicable; place runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs. 1. Provide coordination drawings showing space requirements of various trades in accordance with coordination drawing Article below. Month Year Parkrose Middle School Project 01 30 00-1

D. In finished areas, except as otherwise indicated, conceal pipes, ducts, and wiring within the construction. Coordinate locations of fixtures and outlets with finish construction and components. E. Coordinate completion and cleanup of Work of separate Sections in preparation for Substantial Completion and for portions of Work designated for Owner occupancy. F. After Owner occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Owner activities. PART 2 PRODUCTS - NOT USED PART 3 EXECUTION 3.01 PRECONSTRUCTION MEETING A. Architect will schedule a meeting after Notice of Award. B. Attendance Required: 1. Owner. 2. Architect. 3. Contractor. 4. Contractor's Superintendent. 5. Major Subcontractors. 6. Major Suppliers when requested; others as appropriate. 7. Abatement Consultant. C. Agenda: 1. Introductions. 2. Distribution of Contract Documents. 3. Submission of list of Subcontractors, list of Products, schedule of values, and progress schedule. 4. Designation of personnel representing the parties to Contract, Owner and Architect. 5. Procedures and processing of field decisions, submittals, substitutions, applications for payments, BOLI requirements, proposal request, Change Orders, and Contract closeout procedures. 6. Project overview. 7. Schedule review. 8. Critical work sequencing. 9. Related work by Owner and coordination with Contractor. 10. Owner's requirements. 11. Construction facilities and controls. 12. Security and housekeeping procedures. 13. Procedures for testing. 14. Procedures for maintaining record documents. 15. Requirements for start-up of equipment and Commissioning. 16. Inspection and acceptance of equipment put into service during the construction period. 17. Status of permits. 18. Waste management plan. 19. Temporary utilities. 20. Use of premises and on-going facility operations. D. Architect will record minutes and distribute copies within two days after meeting to participants, with copies to Architect, Owner, participants, and those affected by decisions made. E. Persons designated by the Contractor to attend and participate shall have all required authority to commit the Contractor to solutions as agreed upon in the meeting. Month Year Parkrose Middle School Project 01 30 00-2

3.02 PROGRESS MEETINGS SECTION 01 30 00 A. Schedule and administer meetings throughout progress of the Work at maximum weekly intervals. B. Make arrangements for meetings, prepare agenda with copies for participants, preside at meetings. C. Attendance Required: Job superintendent, Owner, Architect, and major Subcontractors and suppliers, as appropriate to agenda topics for each meeting. D. Agenda: 1. Corrections to previous minutes. 2. Outstanding old business items. 3. New business items. a. Civil b. Architectural c. Structural d. Plumbing e. Mechanical f. Electrical 4. Submittals. 5. Requests for Information. 6. Change Order Proposals. 7. Schedule review. 8. Record Document review. 9. Procurement. E. Record minutes and distribute copies within two (2) days after meeting to participants, with one copy to Architect, Owner, participants, and those affected by decisions made. 1. Minutes shall number topics in a manner that reflects when each topic was first raised. 2. Each topic shall reflect who is responsible for acting on the topic and date by which resolution is required. 3. No topic shall be dropped from the minutes until the method of resolution is recorded. F. Persons designated by the Contractor to attend and participate shall have all required authority to commit the Contractor to solutions as agreed upon in the meeting. 3.03 PREINSTALLATION CONFERENCES A. When required in individual Specification Sections, convene a preinstallation conference at work site prior to commencing work of the Section. B. Attendance Required: Parties directly affecting, or affected by, Work of the Specific Section. C. Notify Architect and Owner minimum four (4) days in advance of meeting date. D. Review Contract Documents and submittals relating to the affected Work. E. Review conditions of installation, preparation and installation procedures, and coordination with related work. F. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions. G. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information. H. Do not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date. Month Year Parkrose Middle School Project 01 30 00-3

3.04 REQUESTS FOR INFORMATION (RFIs) SECTION 01 30 00 A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, prepare and submit an RFI in the form specified. 1. RFIs shall originate with Contractor. Architect will return RFIs submitted to Architect by other entities controlled by Contractor with no response. 2. Limit topics on each RFI to a single topic to expedite response. If more than a single topic is covered in an RFI the Contractor accepts full responsibility for any and all cost or schedule delays if RFI is not answered in a timely manner. 3. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors. 4. Coordinate work in field and ensure work involving RFIs being reviewed by the Architect does not proceed without direction from the Architect. Costs for corrective work shall be the responsibility of the Contractor. 5. If Contractor disagrees with Architect's response to Contractor's RFI, Contractor shall notify Architect within seven (7) days of receipt of response. Lack of such notification shall be understood to mean that Contractor agrees with response. B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following: 1. Date. 2. RFI number, numbered sequentially. 3. RFI subject. 4. Specification Section number and title and related paragraphs, as appropriate. 5. Drawing number and detail references, as appropriate. 6. Field dimensions and conditions, as appropriate. 7. Contractor's suggested resolution. If proposed solution impacts the Contract Time or the Contract Sum, state impact in the RFI. 8. The following statement: a. "This reply is not an authorization to proceed with work involving additional cost, time or both. If any reply requires a change to the Contract Documents, a Change Order or Construction Change Directive must be executed in accordance with the Contract Documents prior to implementation of the reply. Proceeding with the Work in accordance with this RFI response indicates Contractor's acknowledgement that there will be no change in the Contract Sum or Contract Time." 9. Contractor's signature. 10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings and other information necessary to fully describe items needing interpretation. C. Contractor and Architect shall utilize the Owner's web-based management system to submit and receive RFIs and their responses. D. Architect's Action: Architect will review each RFI, determine action required, and respond. Allow seven (7) working days for Architect's response for each RFI. RFIs received by Architect after 1:00 p.m. will be considered as received the following working day. 1. The following RFIs will be returned without action: a. Requests for approval of substitutions. b. Requests for adjustments in the Contract Time or the Contract Sum. c. Requests for interpretation of Architect's actions on submittals. d. Incomplete RFIs or inaccurately prepared RFIs. 2. Architect's action may include a request for additional information, in which case Architect's time for response will date from time of receipt of additional information. 3. Architect's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit a Proposal Request according to Section 01 26 00 - Contract Modification Procedures. Month Year Parkrose Middle School Project 01 30 00-4

a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Architect in writing within ten (10) days of receipt of the RFI response. b. A response to an RFI is not direction or approval of a change to either Contract Time or Contract Sum. c. Proceeding with the Work in accordance with an RFI response, without such written notification and an approved Change Order or Construction Change Directive, indicates Contractor's acknowledgement that there is no change to the Contract Time or the Contract Sum. E. On receipt of Architect's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Architect within three (3) days if Contractor disagrees with response. 3.05 COORDINATION DRAWINGS A. General: Prepare coordination drawings in accordance with requirements in individual Sections, where installation is not completely shown on Shop Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity. 1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable: a. Prepare sections, elevations, and details as needed to describe relationship of various systems and components. b. Coordinate the addition of trade-specific information to the coordination drawings by multiple contractors in a sequence that best provides for coordination of the information and resolution of conflicts between installed components before submitting for review. c. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, plumbing and electrical systems. d. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation. e. Show location and size of access doors required for access to concealed dampers, valves, and other controls. f. Indicate required installation sequences. g. Indicate dimensions shown on the Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Architect indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract. 2. Review: Architect will review coordination drawings to confirm that the Work is being coordinated, but not for the details of the coordination, which are the Contractor's responsibility. If the Architect determines that the coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, the Architect will so inform the Contractor, who shall make changes as directed and resubmit. 3.06 SUBMITTALS FOR REVIEW A. When the following are specified in individual sections, submit them for review: 1. Product data. 2. Shop drawings. 3. Samples for selection. 4. Samples for verification. B. Submit to Architect for review for the limited purpose of checking for conformance with information given and the design concept expressed in the contract documents. C. Samples will be reviewed only for aesthetic, color, or finish selection. Month Year Parkrose Middle School Project 01 30 00-5

D. After review, provide copies and distribute in accordance with SUBMITTAL PROCEDURES article below and for record documents purposes described in Section 01 78 00 - CLOSEOUT SUBMITTALS. 3.07 DEFERRED SUBMITTALS A. For delegated design elements defined in Section 01 10 00 - Summary, submit deferred submittals in accordance with the specified requirements and in accordance with Section 106.3.4.2 of the IBC. B. Architect or Engineer, as applicable, will review delegated design submittals, and, if the submittal is acceptable and receives a "No Exceptions Taken" or "Make Corrections Noted" action, will forward to the Contractor for submission to the building official with annotation indicating that the deferred submittal documents have been reviewed and that they have been found to be in general conformance with the design of the building. C. The Architect's and Engineer's approval is contingent upon approval of submittal by governing authorities. D. Contractor shall be responsible for submission to the governing agency and for coordinating with the governing agency for timely review and approval of the submittals. Architect will not be responsible for delays due to failure of the Contractor to submit with adequate time allowance for agency review of the submittals. E. The deferred submittal items shall not be installed until their design and submittal documents have been approved by the building official. F. Contractor is responsible for obtaining written approval from governing authority for all Deferred Submittals. G. Contractor is responsible for obtaining applicable permits for delegated design elements as required by governing authority. 3.08 SUBMITTALS FOR INFORMATION A. When the following are specified in individual sections, submit them for information: 1. Design data. 2. Certificates. 3. Test reports. 4. Inspection reports. 5. Manufacturer's instructions. 6. Manufacturer's field reports. 7. Other types indicated. B. Submit for Architect's knowledge as contract administrator for Owner. No action will be taken. 3.09 SUBMITTALS FOR PROJECT CLOSEOUT A. When the following are specified in individual sections, submit them at project closeout: 1. Project record documents. 2. Operation and maintenance data. 3. Warranties. 4. Bonds. 5. Other types as indicated. B. Submit for Owner's benefit during and after project completion. 3.10 NUMBER OF COPIES OF SUBMITTALS A. Submittals: Submit documents in an electronic, searchable form using.pdf file format when applicable (product data, shop drawings, certifications, etc.). Submittals will be provided on labeled CDs or DVDs in hard cases clearly identifying Project Name, Specification Sections and Month Year Parkrose Middle School Project 01 30 00-6

date. Provide one (1) file per document with the file name clearly identifying the project name, specification section, vendor, document (i.e. product data) and date. B. Samples: Submit the number specified in individual specification sections; one of which will be retained by Architect. 1. After review, produce duplicates. 2. Retained samples will not be returned to Contractor unless specifically so stated. 3.11 SUBMITTAL PROCEDURES A. Submit Schedule of all shop drawings, product data, samples and all other submittal requirements as specified in each individual Section of the Project Manual. Include submittal and installation dates of each product and assembly. Coordinate with construction schedule and allow ample time, but in no case fewer than fourteen (14) days, for Architect's review. Allow time for possible disapproval, correction, and resubmittal. B. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule. 1. Incomplete submittals are not acceptable, will be considered nonresponsive, and will be returned without review. C. Identify Project, Contractor, Subcontractor or supplier; pertinent drawing and detail number, and specification section number, as appropriate on each copy. D. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of Products required, field dimensions, adjacent construction Work, and coordination of information is in accordance with the requirements of the Work and Contract Documents. 1. Architect will not accept or process submittals which do not reflect Contractor's review and approval. E. Deliver submittals to Architect at address listed on title sheet of Project Manual or as approved by Architect. F. Schedule submittals to expedite the Project, and coordinate submission of related items. G. Do not fabricate products or begin work which requires submittals prior to return of submittal with Architect acceptance. H. Identify variations from Contract Documents and Product or system limitations that may be detrimental to successful performance of the completed Work. 1. Contractor's responsibility for deviations in submittals from requirements of Contract Documents is not relieved by Architect's review of submittals, unless Contractor notates specific deviations and the deviations are specifically approved by the Architect. I. Provide space for Contractor and Architect review stamps. J. When revised for resubmission, identify all changes made since previous submission. K. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report any inability to comply with requirements. L. Submittals not requested will not be recognized or processed. M. Contractor is responsible for timely and efficient submittals and the correctness of the documentation submitted. Costs associated with multiple reviews of submittal information beyond one (1) re-submittal (if any) shall be the responsibility of the Contractor. 3.12 TIMING OF SUBMITTALS A. General: 1. The listing of submittals hereinafter is set forth as a checklist for Contractor's convenience and is general in nature. Month Year Parkrose Middle School Project 01 30 00-7

2. Architect reserves the right to add to this list in case of omission of any submittals specified in other Sections but not listed hereinafter. 3. Documents shall be submitted in an electronic, searchable form using.pdf file format. Documents will be provided on labeled CDs or DVDs in hard cases clearly identifying Project Name, contents and date. Provide one file per document with the file name clearly identifying the project name, document name and date. B. Submittals - Required Within Seven (7) Days Postbid: 1. Contractor's Qualification Statement. 2. Letter from Insurance Company - insurance required effective upon Contract. 3. Letter from Surety - bonds required effective upon Contract. 4. Breakdown of bid (if requested). 5. Names of proposed suppliers for each of the principal portions of the Work. 6. Contractor's Construction Management Personnel: Project Manager - minimum 3 years experience; Field Superintendent - minimum 5 years experience. 7. Responsibility of Subcontractors. 8. A designation of the Work to be performed by the Contractor by his own forces. C. Submittals - Required Within Seven (7) Days After Notice of Intent to Award Contract (Prior to Execution of Contract): 1. Final List of Subcontractors and major material suppliers for principal portions of the Work. 2. Evidence of bondability (Performance Bond and Payment Bond). 3. Certificates of Insurance (on AIA Document G705 or equivalent). 4. Actual costs (%) of the Contractor's liability insurance. 5. Endorsements for additional insured. 6. Statements of State Worker's Compensation coverage. 7. Copy of Builder's Risk Policy. 8. Project Organizational Chart. 9. Key Staff Resumes with telephone and contact information. 10. Summary of Warranties included in Bid, including duration and start time of each. Itemize any deviations from Bid Document requirements. 11. Other documents required by Contract Documents. D. Submittals - Prior to Notice to Proceed: 1. Executed Agreement. 2. Certified copies of Contractor's Liability Insurance Policies (AIA Document G705). E. Submittals - Within Seven (7) Days Following Contract Execution and Prior to Commencing Work: 1. Deliver Bonds to Owner with copy to Architect. 2. Performance and Labor & Material Payment Bonds per Oregon Law with certified copy of Power of Attorney from Attorney-in-Fact executing bonds. 3. Certified Schedule of Prevailing Wage Rates (attach to executed contract). F. Submittals - Within Thirty (30) Days Following Notice to Proceed and Prior to First Payment Application: 1. Schedule of values - submit at least fourteen (14) days in advance of application. 2. Schedule of submittals. 3. Copies of acquired and unacquired building permit licenses etc. to complete the Work of the Contract. Submit copies of any remaining permits as they are acquired. 4. Approved Construction Schedule. G. Submittals - Prior to Each Month's Progress Payment: 1. Submit ten (10) days in advance of date established for progress payment. 2. Application and Certificate for Payment (AIA Document G702 and G703). 3. Notarized affidavit of payments to all subcontractors and major material suppliers (see application for payment). 4. Updated Construction Schedule. Month Year Parkrose Middle School Project 01 30 00-8

5. Public Works Contractor Wage Certification per Oregon Law. SECTION 01 30 00 H. Submittals - Prior to request for Substantial Completion: 1. Notification to Architect that Work of the Project is substantially complete. 2. Itemized listing of items of work to be completed or corrected. 3. Submit Certificate of Occupancy or Occupancy Permit issued by the Local Building Department for the entire Project. 4. Draft Operations and Maintenance Manuals. I. Submittals - Prior to request for Final Completion: 1. Certified copy of punchlist items completed. 2. Submit final Application for Payment. 3. Summary of Commissioning indicating all required items are completed. 4. Demonstration and Training training reports. 5. Final complete and correct Operations and Maintenance Manuals. 6. Record Drawings of Contract Documents with all changes indicated. 7. Final dated and signed Warranties. 3.13 CONSTRUCTION PROGRESS SCHEDULE A. Submit initial progress schedule as required in Section 01 32 00 - Construction Progress Documentation. B. Revise and resubmit as required. C. Review revised schedules with each Application for Payment, identifying changes since previous version, broken down by COR. 3.14 SCHEDULE OF VALUES A. Submit typed schedule on AIA Form G703. Contractor's standard form or media-driven printout will be considered on request. B. Format: Table of Contents of this Project Manual. Identify each line item with number and title of the major Specification Sections. C. Revise schedule to list change orders, for each application for payment. D. Comply with requirements in Section 01 20 00 - Price and Payment Procedures. 3.15 PRODUCT SUBMITTALS - DETAILED REQUIREMENTS A. Provide submittals in an electronic, searchable form using.pdf file format when applicable (product data, shop drawings, certifications, etc.). Submittals will be provided on labeled CDs or DVDs in hard cases clearly identifying Project Name, Specification Sections and date. Provide one file per document with the file name clearly identifying the project name, specification section, vendor, document (i.e. product data) and date. 1. Samples for Initial Selection: Submit one full set of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. Architect will return submittal with options selected. Architect will retain selected sample for confirmation of subsequent submittals. 2. Samples for Verification: Provide 3 copies of samples unless more are required for distribution to other subcontractors or fabricators for matching or preparation of finish samples. B. Present in a clear and thorough manner. Title each drawing with Project Name. C. Identify field-verified dimensions; show relation to adjacent or critical features of Work or products. D. Number submittals by submittal section number, followed by a number which sequentially numbers submittals in order submitted to Architect. For example, the initial submittal of Joint Month Year Parkrose Middle School Project 01 30 00-9

Sealers 07 90 05 would be designated 07 90 05-1. If the submittal must be resubmitted it shall be identified as 07 90 05-1-R1 and subsequent resubmittal shall be sequentially numbered in order as resubmitted. E. Product Data: 1. Submit only pages which are pertinent; mark each copy of standard printed data to identify pertinent products, referenced to Specification Section and Article number. 2. Modify manufacturer's standard schematic drawings and diagrams to supplement standard information and to provide information specifically applicable to the Work. Delete information not applicable. 3. Product data that has not been marked to indicate the applicable information will be returned without review. 4. Contractor shall assemble Product Data required for maintenance manuals and submit to Architect in accordance with Section 01 78 00 - Closeout Submittals. F. Samples: 1. Submit full range of manufacturer's standard finishes except when more restrictive requirements are specified, indicating colors, textures, and patterns, for Architect selection. 2. Submit samples to illustrate functional characteristics of products, including parts and attachments. 3. Approved samples which may be used in the Work are indicated in the individual Specification Sections. 4. Label each sample with identification required for transmittal letter. 5. Submit the number of samples specified in individual Specification Sections. One of which will be retained by the Architect. a. Submit additional samples when copies will be required for distribution to other subcontractors or fabricators for matching or preparation of finish samples. 6. Provide field samples of finishes at project site, at location acceptable to Architect, as required by individual Specifications Section. Install each sample complete and finished. Acceptable finishes in place may be retained in completed work if approved by Architect. G. Manufacturer's Instructions: 1. Provide at Minimum: Manufacturer's instructions for storage, preparation, assembly, installation, start-up, adjusting, balancing, and finishing in accordance with Section 01 40 00 - Quality Requirements. H. Manufacturer's Certificates: 1. When specified in individual Specification Sections, submit manufacturers' certificate to Architect/Engineer for review, in quantities specified herein. 2. Indicate material or product in conformance with or exceeding specified requirements. Submit supporting reference date, affidavits, and certifications as appropriate. 3. Certificates may be recent or previous test results on material or Product, but must be acceptable to Architect. END OF SECTION Month Year Parkrose Middle School Project 01 30 00-10