Southern Company Interconnection Requirements for Inverter-Based Generation

Similar documents
Transmission Interconnection Requirements for Inverter-Based Generation

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

Table of Contents. Introduction... 1

Wind Power Facility Technical Requirements CHANGE HISTORY

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

Embedded Generation Connection Application Form

Embedded Generation Connection Application Form

E N G I N E E R I N G M A N U A L

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

Appendix S: PROTECTION ALTERNATIVES FOR VARIOUS GENERATOR CONFIGURATIONS

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

Embedded Generation Connection Application Form

Connection Impact Assessment Application

GridLiance Reliability Criteria

Utility Interconnection and System Protection

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

INTERIM ARRANGEMENTS FOR GRID TIED DISTRIBUTED ENERGY RESOURCES. Technical Requirements for Grid-Tied DERs

Functional Specification Revision History

Remotes Case 2&3 Form REINDEER Cases 2&3 -Connection Impact Assessment (CIA) Application

Phase-phase/phase-neutral: 24/13.8 kv star, 13.8 kv delta, 12/6.9 kv star.

Generation and Load Interconnection Standard

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number: Address:

BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 7T-30A. NORTH COAST INTERCONNECTION: SKEENA BOB QUINN SUBSYSTEM Supersedes OO 7T-30A dated 07 July 2014

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF LARGE GENERATION FACILITIES. Document 9020

Grid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF GENERATION FACILITIES NOT SUBJECT TO FERC JURISDICTION

Generation and Load Interconnection Standard

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

ATTACHMENT - AESO FUNCTIONAL SPECIFICATION

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction

Impact Assessment Generator Form

1

Connection Impact Assessment Application Form

BED INTERCONNECTION TECHNICAL REQUIREMENTS

DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation

OPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC

Intermittent Renewable Resources (Wind and PV) Distribution Connection Code (DCC) At Medium Voltage (MV)

Generation Interconnection Requirements at Voltages 34.5 kv and Below

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting

The Connecticut Light and Power Company

Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES

IEEE sion/1547revision_index.html

Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES

GUIDE FOR GENERATOR INTERCONNECTION THE WIRES OWNER DISTRIBUTION SYSTEM

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

Facility Interconnection Requirements for Colorado Springs Utilities Version 03 TABLE OF CONTENTS

FACILITY RATINGS METHOD TABLE OF CONTENTS

69 kv to 500 kv INTERCONNECTION REQUIREMENTS FOR TRANSMISSION FACILITIES

OPERATING, METERING, AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 2,000 KILOWATTS

HUTCHINSON UTILITIES COMMISSION TRANSMISSION INTERCONNECTION GUIDELINES

I WP Asset # I ~:2 3. I Review Annual. ~c~~ Date: 'l/j(j/! ZL>IJ,...

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. July 2016 Version 4

Final ballot January BOT adoption February 2015

DUKE ENERGY CAROLINAS TRANSMISSION SYSTEM PLANNING GUIDELINES. Transmission Planning

Recently, the SS38 Working Group on Inter-Area Dynamic Analysis completed two study reports on behalf of the UFLS Regional Standard Drafting Team.

HOOSIER ENERGY REC, INC. Requirements for Connection of Generation Facilities. to the HE Transmission System

GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW

60 kv to 500 kv Technical Interconnection Requirements For Power Generators

NPCC Regional Reliability Reference Directory # 12. Underfrequency Load Shedding Program Requirements

Information and Technical Requirements For the Interconnection of Distributed Energy Resources (DER)

DRAFT. City of Lethbridge Electric ENGINEERING STANDARDS GUIDELINE FOR GENERATOR INTERCONNECTION THE CITY OF LETHBRIDGE ELECTRIC DISTRIBUTION SYSTEM

Power System Protection Where Are We Today?

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR SMALL GENERATION INTERCONNECTIONS

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell

Appendix C-1. Protection Requirements & Guidelines Non-Utility Generator Connection to Okanogan PUD

Generation Interconnection Guidelines for the Dairyland Power Cooperative Transmission System

Oklahoma Gas and Electric Co. Facility Connection Requirements MAINTAINED BY. Transmission Planning Engineering Department

RENEWABLE ENERGY SUB-CODE for Distribution Network connected Variable Renewable Energy Power Plants in Ghana

POWER QUALITY AND SAFETY

SYNCHRONISING AND VOLTAGE SELECTION

each time the Frequency is above 51Hz. Continuous operation is required

ReliabilityFirst Regional Criteria 1. Disturbance Monitoring and Reporting Criteria

WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/

System Protection and Control Subcommittee


Dairyland Power Cooperative June Transmission to Transmission (T-T) Interconnection Guidelines

Education & Training

NERC Protection Coordination Webinar Series July 15, Jon Gardell

Guide and Requirements for Service. at 69,000 to 287,000 Volts R 0.2

Bulk Electric System Definition Reference Document

Modelling Parameters. Affect on DER Impact Study Results

IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces

NERC Protection Coordination Webinar Series June 9, Phil Tatro Jon Gardell

TABLE OF CONTENT

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. April 2009 Version 2

TECHNICAL GUIDELINE FOR THE INTERCONNECTION OF DISTRIBUTED ENERGY RESOURCES TO EPCOR DISTRIBUTION AND TRANSMISSION INC. S DISTRIBUTION SYSTEM

FACILITY CONNECTION REQUIREMENTS

Transmission System Phase Backup Protection

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1

Technical Interconnection Requirements For Transmission Voltage Customers for Service at 60,000 to 287,000 Volts R XX

QUESTIONNAIRE for Wind Farm Power Stations only

Technical Requirements for Connecting Small Scale PV (sspv) Systems to Low Voltage Distribution Networks

UProtection Requirements. Ufor a Large scale Wind Park. Shyam Musunuri Siemens Energy

Arizona Public Service Company and the Transmission Partnership for National Electric Power Company of Jordan

Transcription:

Southern Company Interconnection Requirements for Inverter-Based Generation September 19, 2016 Page 1 of 16

All inverter-based generation connected to Southern Companies transmission system (Point of Interconnection (POI) > 40kV) shall comply with the following requirements. Generator interconnection studies will determine the required interconnection facilities and transmission system upgrades, evaluate whether the generation developer s initial generating facility design and equipment can comply with these requirements, and may prescribe additional requirements for specific sites/interconnections. The generation developer s final generating facility design and equipment will be further evaluated prior to Initial Synchronization and Commercial Operation. The generator owner/operator is expected to continue to comply with these requirements as a condition of interconnection with Southern Companies transmission system. The generator owner/operator must provide advance notice of any changes to generating facility equipment or any changes to equipment settings or programming, and the Transmission Provider will evaluate such changes to ensure that compliance with these requirements can be maintained. Generator Interconnection requirements include: I. Procedures for Requesting a New Generator Interconnection or Material Modification to an Existing Generator Interconnection 1. Generator Interconnection Request and Study Process 2. Generating Facility Technical Data Forms II. Technical Requirements 1. Transmission System Protection and Coordination i. Main GSU Winding Configuration ii. Anti-islanding Requirements iii. Protective Devices 2. Power Quality 3. Insulation and Insulation Coordination 4. Voltage, Reactive Power and Power Factor Control i. Reactive Power/Power Factor Design Criteria ii. Voltage Schedule Operating Requirements iii. Voltage Deviation 5. Generator Performance i. Frequency Response/Regulation ii. Voltage Ride Through iii. Frequency Ride Through iv. Active Power/Reactive Power Priority Control Settings v. Voltage Control Stability and Inrush Performance 6. Metering and Telecommunications III. Initial Synchronization and Operating Procedures 1. Initial Synchronization Requirements 2. Commercial Operation Requirements Page 2 of 16

I. Procedures for Requesting a New Generator Interconnection or Material Modification to an Existing Generator Interconnection Southern Company Services ( SCS ), as agent for Alabama Power Company, Georgia Power Company, Gulf Power Company, and Mississippi Power Company, collectively (Company), will coordinate any request for interconnection to the transmission system (POI > 40 kv) of any of these utilities. A request for interconnection to the distribution system (POI < 40 kv) of any of these utilities should be made directly with the utility according to their distribution interconnection procedures and requirements. 1. Generator Interconnection Request and Study Process A complete Generator Interconnection Request for transmission shall include the following: 1. A completed small generator ( 20 MW) or large generator (> 20 MW) interconnection application, and the additional generating facility technical data form if the request is for solar or wind generation. The application and additional solar or wind generating facility technical data forms can be found in the Generator Interconnection folder on the Home page of Southern Companies OASIS website (www.oasis.oati.com/soco). An electronic copy is acceptable including a scanned copy of the signature page. As mentioned in the application, also include: Single-line diagram of the generating facility signed and stamped by a licensed Professional Engineer. Site layout map, with enough detail to determine the property boundaries and proposed location of interconnecting substation. Dynamic modeling data (as listed in the application or additional data sheet for solar and wind generation), formatted for appropriate Siemens PSS/E Version(s) as specified in data sheet. 2. Appropriate application deposit which will be applied toward the interconnection study costs. For small generator interconnection requests, the application deposit is $1,000. For large generator interconnection requests, the application deposit is $10,000. Interconnection application and study deposits may be submitted via check or wire. A generator interconnection deposit form with instructions can be found in the Generator Interconnection folder on the Home page of Southern Companies OASIS website at: http://www.oasis.oati.com/soco/socodocs/gen-int_deposit-form.docx Page 3 of 16

A completed deposit form should be submitted with the application to help in tracking the deposit, and to provide information needed for any future deposit refunds. 3. Demonstration of site control. Site Control is documentation reasonably demonstrating the following: ownership of, a leasehold interest in, or a right to develop a site for the purpose of constructing the Generating Facility; an option to purchase or acquire a leasehold site for such purpose; or an exclusivity or other business relationship between Interconnection Customer and the entity having the right to sell, lease or grant Interconnection Customer the right to possess or occupy a site for such purpose. All of these items may be provided via email to the SCS Interconnections Project Manager (Jason Williams, JASRWILL@southernco.com), however note the following for emails with attachments: Incoming e-mail size is limited to 10 MB. Anything larger will be blocked by our email server. Zip file attachments are blocked by our email server. Rename the zip file with a.soco extension, and the email will pass through our email server. After the file is received, it will be renamed back to.zip in order to access the files within. A good practice is to include any ZIP file or non-microsoft file attachments in a separate email from the application and data sheet. That way, even if the email with the ZIP file is blocked, the application email will still be received. Once the interconnection application items are received, SCS will review the interconnection application and corresponding generator data, and notify the interconnection customer of any data deficiencies. After all data deficiencies have been resolved, the application will be considered a complete request, and the interconnection request may proceed to the scoping meeting and interconnection studies. It is important to note that the typical interconnection request requires approximately 12 months to work through the study process and reach an interconnection agreement before any utility construction can begin. 2. Generating Facility Technical Data Forms Inverter-based wind or solar generators require a separate generating facility technical data form in addition to the standard application. The appropriate data form can be found in the Generator Interconnection folder on the Home page of Southern Companies OASIS website at: http://www.oasis.oati.com/soco/socodocs/solar-generation-data.docx http://www.oasis.oati.com/soco/socodocs/wind-generation-data.docx Page 4 of 16

II. Technical Requirements 1. Transmission System Protection and Coordination i. Main Generator Step-Up (GSU) Winding Configuration One of the following criteria shall be used to determine the winding configuration of main step-up transformer connecting solar or wind generator to the system. 1. If the generator is proposed to connect to existing < 100 kv via a dedicated express line or feeder (no load on line or feeder), the high side (utility side) of the main step-up transformer s winding configuration shall be one of the following: a. Delta configuration (preferred) b. Y-grounded configuration (with delta on generator side) Example is shown in Figure 1. 2. If the generator is proposed to connect as a tapped generation on existing 230 kv or lower voltage radial line, the high side (utility side) of the main step-up transformer shall be connected in Delta configuration. Example is shown in Figure 2. 3. If the generator is proposed to connect as a tapped generation on existing >100 kv network line, the high side (utility side) of the main step-up transformer s winding configuration shall be one of the following: a. Delta configuration (preferred) b. Y-grounded configuration (with delta on generator side) Example is shown in Figure 3. 4. If the generator is proposing to connect to >100 kv network via a ring or straight bus in a substation, the main step-up transformer s winding configuration shall be one of the following: a. Y-grounded on high side (utility side) and Delta on low side. b. Y-grounded on high side (utility side) and low side with buried delta tertiary winding. Example is shown in Figure 4. Page 5 of 16

Figure 1. Example of Main GSU Criteria 1 Figure 2. Example of Main GSU Criteria 2 Page 6 of 16

Figure 3. Example of Main GSU Criteria 3 Figure 4. Example of Main GSU Criteria 4 Page 7 of 16

ii. Anti-islanding Requirements Interconnection configuration shall not allow the generator to island with other customer load. Company considerations include: a) Potential for adding load taps on the existing line. b) Load-to-generation ratio to assess risk of islanding. Recommended load-to-generation ratios, by generator type, are: i. Solar generator: If the minimum day time load to total generation (sum of existing and queued, if any) ratio is less than 2, anti-islanding protection is required. i. Minimum day time load should be determined based on historical load data between the hours of 9:00 am and 3:00 pm. ii. Exceptions can be made for generators with a dedicated feeder. ii. iii. Wind generator: if the minimum load to total generation (sum of existing and queued, if any) ratio is less than 2, anti-islanding protection is required. Variety of generation (conventional plus inverter-based) together forming an island: if the minimum load to total generation (sum of existing and queued, if any) ratio is less than 3, anti-islanding protection is required. c) Anti-Islanding protection should consider single contingency islanding scenarios. d) Generators connected to lines operated radially should be studied for the normal expected configuration only. For interconnections where anti-islanding protection is required, the individual inverter antiislanding protection will not be sufficient. Appropriate anti-islanding protection will be installed on the transmission system in order to disconnect the generator in a potential islanding scenario. This typically involves pilot relaying on the transmission system via fiber or power line carrier. iii. Protective Devices Various protective devices are required to permit the safe and proper operation of the interconnection. Determination of the device requirements will be made by the Company during the Interconnection studies. Determination of ownership of all protective equipment associated with the interconnection will be made during the Interconnection studies. The Generator s interconnection protective equipment and settings (if applicable) must be reviewed and accepted by the Company. Page 8 of 16

A. Relays Protective relays are required to promptly sense abnormal system conditions and initiate the isolation of the problem area. Protective relays can generally be categorized into two major groups: industrial grade and utility grade. Utility grade relays have a higher degree of reliability and accuracy, and are required in all cases. All relay settings for the inter-tie protection must be reviewed and approved by the appropriate Company Protection and Control department before implementation. B. Instrument Transformers Instrument transformers that are used to provide quantities representative of the high voltage power system to the relays are a critical part of the protection package. These current transformers (CT s) and voltage transformers (VT s) are available with different current and voltage ratings and accuracy class ratings. It is important that any current transformers involved in protective schemes are rated as relaying accuracy class devices. Revenue metering CT s are not suitable for protective relaying applications. C. Circuit Breakers The Interconnection study will determine the inter-tie circuit breaker rating which is sufficient. Upgrading or replacement of existing circuit breakers within or outside the area of the interconnection may be required due to the increased fault current levels. Circuit breakers owned by the Company are dedicated to utility protection and operation purposes and will not be used for the synchronization of the generator. E. Communication Channel In most cases, the tie-line between the interconnecting station and the generator site is very short. A communication channel between two sites may be necessary for high speed protection. The communication channel is required in cases where it is necessary to remotely send a signal to remove the generator from the transmission system due to a fault or other abnormal conditions which cannot be sensed by the protective devices at the generator location. Another possible need for a communications channel is for monitoring or control purposes. The communication channel could be based on power line carrier, fiber optic cable, radio, or other means. In some cases, redundant communication channels are also required. The Interconnection study will determine the communication channel requirements. Page 9 of 16

2. Power Quality All inverter-based generation shall comply with Southern Companies Power Quality Policy or limits specified by the Company, which can be found in the Generator Operating Requirements folder on the Home page of Southern Companies OASIS website (www.oasis.oati.com/soco): http://www.oasis.oati.com/soco/socodocs/soco_power_quality_policy.pdf 3. Insulation and Insulation Coordination The objective of insulation coordination is to coordinate equipment insulation levels and protective devices ratings. It is the responsibility of the interconnecting facility to ensure that the Southern Company substation equipment is protected against lightning and switching induced surges that originate in the interconnection facility through insulation design and protection that meets the latest IEEE C62 standards. Basic Lightning Impulse Insulation Level (BIL) for individual station equipment shall meet or exceed Southern Company s standard ratings listed in Table 1. Also, preferred surge arrester ratings for different system voltage levels have been provided. Nominal kv (Line-Line) Station BIL (kv) Table 1. Preferred Arrester Ratings Transformer Winding BIL (kv) Preferred Surge Arrester Ratings Duty Cycle (kv) 46 250 250 39 31.5 69 350 350 54 42 115 550 450 96 76 161 750 230 144 115 230 900 750 192 152 500 1800 Use Nameplate BSL MCOV (kv) 396 318 Page 10 of 16

4. Voltage, Reactive Power and Power Factor Control i. Reactive Power/Power Factor Design Criteria The Reactive Power Requirements ( for Generating Facilities Interconnecting to the Southern Companies Transmission System) document can be found in the Generator Operating Requirements folder on the Home page of Southern Companies OASIS website (www.oasis.oati.com/soco). http://www.oasis.oati.com/soco/socodocs/reactive-power-policy.pdf ii. Voltage Schedule Operating Requirements All Generators which are required to follow a voltage schedule while operating must comply with the Voltage Schedule Procedures posted in the Generator Operating Requirements folder on the Home page of Southern Companies OASIS website (www.oasis.oati.com/soco). https://www.oasis.oati.com/soco/socodocs/bpo-01_(voltage_schedules).pdf iii. Voltage Deviation In general, for inverter-based generation interconnecting to the transmission system at an operating voltage between 40 kv and 100 kv, a criterion of 2.5% maximum voltage deviation at the POI is used. 5. Generator Performance All inverter-based generation connected to Southern Companies transmission system (POI > 40kV) shall comply with the following requirements related to frequency response/regulation and frequency and voltage ride-through. i. Frequency Response / Regulation Frequency response and frequency regulation is necessary in order to maintain nominal frequency whenever system load and generation imbalances occur. Similar to conventional generators, inverter-based generators shall have the capability to provide primary frequency response during over-frequency events by having controls that reduce output power whenever the frequency at the point of interconnection exceeds 60.036 Hz. Primary frequency response shall be proportional to deviations from scheduled frequency. The ratio of per-unit frequency deviation (Δf) to per-unit Page 11 of 16

POI Voltage (pu) change in output power (ΔP) shall be similar to or more responsive than a droop characteristic of 5% used by conventional generators. The primary frequency response control functions shall be enabled at all times, and shall not be blocked or disabled without the express written permission of the Transmission Provider. ii. Voltage Ride Through All inverter-based generation shall remain connected to the system and operating at normal expected output during and following three-phase transmission system faults with clearing not exceeding 9 cycles. The voltage ride-through requirements shall be met at the point of interconnection, and are listed in Table 2 and depicted in Figure 5. It should be noted that the curves depicted in Figure 5 apply to all voltage excursions regardless of the type of initiating event. Table 2. Voltage Ride-Through Requirements High Voltage Ride-Through Low Voltage Ride-Through Voltage (p.u.) Time (sec) Voltage (p.u.) Time (sec) 1.2 Instantaneous Trip Allowed < 0.45 0.15 1.175 0.20 < 0.65 0.30 1.15 0.50 < 0.75 2.00 1.1 1.00 < 0.90 3.00 1.3 1.25 1.2 1.15 1.1 1.05 0.95 1 0.9 0.85 0.8 0.75 0.7 0.65 0.6 0.55 0.5 0.45 0.4 0.35 0.3 0.25 0.2 0.15 0.1 0.05 0 May Trip Zone No Trip Zone May Trip Zone 0 0.5 1 1.5 2 2.5 3 3.5 4 Time (sec) Figure 5. Voltage Ride-Through Requirements Page 12 of 16

Frequency (Hz) iii. Frequency Ride Through All inverter-based generation shall remain connected to the system and operating at normal expected output during frequency excursions as described in Table 3 and depicted in Figure 6. Table 3. Frequency Ride-Through Requirements High Frequency Ride-Through Low Frequency Ride-Through Frequency (Hz) Time (sec) Frequency (Hz) Time (sec) 61.8 Instantaneous Trip Allowed 57.8 Instantaneous Trip Allowed 60.5 10 (90.935-1.45713*f) 59.5 10 (1.7373*f-100.116) < 60.5 Continuous Operation > 59.5 Continuous Operation 63 62 May Trip Zone 61 60 No Trip Zone 59 58 May Trip Zone 57 0.1 1 10 100 1000 10000 Time (sec) Figure 6. Frequency Ride-Through Requirements iv. Active Power/Reactive Power Priority Control Settings ( P/Q-Priority) Inverters shall have the capability to provide voltage support to the grid by prioritizing Mvar output over MW output during voltage excursion events. The inverter must operate in the Q-Priority mode (i.e., this control function must be enabled at the inverters). Q-Priority is a feature for inverters to optimize its available MVA rating to produce more reactive power during abnormal low voltage conditions. For instance, with the Q-Priority feature enabled, the inverter control system activates reactive current injection logic when the voltage dips below a pre-determined set-point (V dip ). Once Page 13 of 16

the voltage has recovered (> V dip ), the inverter returns to steady-state operating mode. However, if the inverters purchased do not have such a feature, this requirement is not applicable. v. Voltage Control Stability and Inrush Performance The Generator Owner must design its facility to reliably operate for the Short-Circuit Ratio (SCR) range that is provided in the interconnection studies (i.e., SIS and FAC). The SCR is calculated by dividing the three-phase short circuit MVA capacity at the Point of Interconnection by the maximum rated MW output of the facility under a variety of normal and contingency operating conditions. The generating facility shall be designed to reliably manage both plant steady state voltage regulation and provide voltage support when subjected to transient voltage deviations (such as due to unanticipated transmission system faults electrically close to the facility). The facility must be designed for acceptable voltage deviation performance (refer to Southern Company PQ Policy) during transformer energization (both GSU and transformer(s) connected to the facility s inverters). Note per Southern Company Power Quality Policy, voltage deviations out of adherence to the DV/V limits as a result of inrush during transformer energization could result in operational restrictions. Southern Company could request additional transformer data (i.e., saturation characteristic including air-core reactance, and no load loss at rated voltage) in order to assess viable solutions that could include additional equipment (e.g., breaker equipped with pre-insertion resistors, etc.). 6. Metering and Telecommunications The company will install and verify metering equipment at the Point of Interconnection prior to any operation of the generating facility and shall own, operate, test and maintain such metering equipment. Power flows to and from the generating facility shall be measured at the Point of Interconnection. Company will provide metering quantities to the generating facility via Generatorprovided communication circuit (typically fiber from the generating facility to the interconnecting substation). Generator shall be responsible for contacting and coordinating with the appropriate electric service provider (which may or may not be the Company) to arrange for retail station service. The Point of Interconnection metering equipment does not include the generating facility s retail station service metering equipment unless approved as such by the Company. Page 14 of 16

III. Initial Synchronization and Operating Procedures 1. Initial Synchronization Requirements Generator shall coordinate with Southern Companies to complete all requirements necessary for the initial synchronization of the Generating Facility to Southern Companies Electric System. Generator interconnection implementation guidelines will be provided to the Generator upon execution of the Generator Interconnection Agreement. A complete list of specific project requirements and milestones to be completed prior to initial synchronization of the Generating Facility will be provided to the Generator at Notice to Proceed. In general, the Initial Synchronization requirements include: Generating facility physical design submittal and compatibility review. Generating facility modeling data submittal milestones. Interconnection protection relaying coordination and testing. Point of Interconnection metering installed. Retail service metering installed. Data telemetry installed and verified. Southern Companies EMS (and other operational tools) updated. Voice communications and GenComm setup and tested. Operating Protocols and Procedures document complete and reviewed. Affected System upgrades complete (if applicable). Prior to Initial Synchronization, Company will provide the Generator with Southern Companies Operating Protocols and Procedures document for interconnected generators. The Generator will comply with the operating and technical requirements of the Operating Protocols and Procedures document in order to ensure the safe and reliable operation of Southern Companies Electric System and compliance with any applicable reliability standards. Once all Initial Synchronization requirements have been complete and at least seven (7) days prior to the Initial Synchronization, Generator shall provide notice to the Company regarding its readiness to synchronize the generating facility to Southern Companies Electric System. Promptly following such notice, Company shall evaluate the synchronization of the generating facility to Southern Companies Electric System in order to ensure the safe and reliable operation of Southern Companies Electric System. Initial synchronization shall not occur without the prior written confirmation from Company that the generating facility may be synchronized to Southern Companies Electric System. Page 15 of 16

2. Commercial Operation Requirements Generator shall coordinate with Southern Companies to complete all requirements necessary for commercial operation of the Generating Facility. A complete list of specific project requirements and milestones to be completed prior to commercial operation of the Generating Facility will be provided to the Generator at Notice to Proceed. In general, the Commercial Operation requirements include: Electronic tagging and scheduling setup complete (as applicable). Generator imbalance arrangements complete (as applicable). Submittal of final generating facility dynamic modeling data (including final control settings) Validation of modeling data by comparison to test results. Verification of plant s ability to meet operational requirements (such as voltage, harmonics, etc.) at full load. Final plant commissioning report. Once all Commercial Operation requirements have been complete and at least seven (7) days prior to the scheduled Commercial Operation Date, Generator shall provide notice to Company regarding its readiness to achieve commercial operation. Promptly following such notice, Company shall evaluate such notice to ensure that the generating facility may safely and reliably commence operation while interconnected with Southern Companies Electric System. The Generator may not commence commercial operation prior to written confirmation from Company that the generating facility may commence operation while interconnected Southern Companies Electric System. Page 16 of 16