Abstract. 1 Introduction

Similar documents
FACTORY AND FIELD VERIFICATION TESTS OF CONTROLLED SWITCHING SYSTEM

Real Time Monitoring of SF6 Gas Pressure for Optimization Point on Wave Switching of SF6 Circuit Breaker

A3-308 HIGH SPEED GROUNDING SWITCH FOR EXTRA-HIGH VOLTAGE LINES

Although shunt capacitors

Tab 2 Voltage Stresses Switching Transients

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY

Calculation of Transient Overvoltages by using EMTP software in a 2-Phase 132KV GIS

DC current interruption tests with HV mechanical DC circuit breaker

Sources of transient electromagnetic disturbance in medium voltage switchgear

Electric Stresses on Surge Arrester Insulation under Standard and

PRACTICAL CONSIDERATIONS FOR CONTROLLED SWITCHING OF POWER TRANSFORMERS

CIRCUIT BREAKERS TRANSIENT REDUCTION BY USING A DEDICATED CONTROLLED SWITCHING SYSTEM

AORC Technical meeting 2014

Shunt Reactor Switching

Calculation of Transients at Different Distances in a Single Phase 220KV Gas insulated Substation

High voltage engineering

Experimental Investigations and Calculations in 6-35 kv Networks with Various Neutral Conditions

Fast Protection of Strong Power System With Fault Current Limiters and PLL - Aided Fault Detection

FGJTCFWP"KPUVKVWVG"QH"VGEJPQNQI[" FGRCTVOGPV"QH"GNGEVTKECN"GPIKPGGTKPI" VGG"246"JKIJ"XQNVCIG"GPIKPGGTKPI

CHAPTER 2. v-t CHARACTERISTICS FOR STANDARD IMPULSE VOLTAGES

In power system, transients have bad impact on its

ANALYSIS OF FAULTS INTERRUPTED BY GENERATOR

A TECHNICAL REVIEW ON CAPACITOR BANK SWITCHING WITH VACUUM CIRCUIT BREAKERS

GIS Disconnector Switching Operation VFTO Study

Switching Restrikes in HVAC Cable Lines and Hybrid HVAC Cable/OHL Lines

Power Quality and Reliablity Centre

ANALYSIS OF VOLTAGE TRANSIENTS IN A MEDIUM VOLTAGE SYSTEM

Fixed Series Compensation

Modelling of Sf6 Circuit Breaker Arc Quenching Phenomena In Pscad

EMC Philosophy applied to Design the Grounding Systems for Gas Insulation Switchgear (GIS) Indoor Substation

Method for Static and Dynamic Resistance Measurements of HV Circuit Breaker

MEDIUM & HIGH VOLTAGE

This is a preview - click here to buy the full publication

Weidong Zhang, May.9, 2016 Development of Pre-Insertion Resistor for an 800kV GIS Circuit Breaker. ABB Group May 11, 2016 Slide 1

Estimation of Re-striking Transient Over voltages in a 132KV Gas insulated Substation

Coherence and time-frequency analysis of impulse voltage and current measurements

CONTENTS. 1. Introduction Generating Stations 9 40

Insulation Co-ordination For HVDC Station

Transmission of Electrical Energy

PANIMALAR ENGINEERING COLLEGE Department of Electrical and Electronics Engineering

Analysis of MOV Surge Arrester Models by using Alternative Transient Program ATP/EMTP

HYBRID STATCOM SOLUTIONS IN RENEWABLE SYSTEMS

Do Capacitor Switching Transients Still Cause Problems?

SIMPLE SOLUTIONS FOR IMPROVING LIFE OF BREAKERS USED IN TRANSMISSION AND DISTRIBUTION SYSTEMS

Testing 320 kv HVDC XLPE Cable System

Chapter -3 ANALYSIS OF HVDC SYSTEM MODEL. Basically the HVDC transmission consists in the basic case of two

Conventional Paper-II-2011 Part-1A

EE 1402 HIGH VOLTAGE ENGINEERING

Grid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017

Technical Information General Purpose Relays

DC VACUUM CIRCUIT BREAKER

HVDC Transmission. Michael Muhr. Institute of High Voltage Engineering and System Performance Graz University of Technology Austria P A S S I O N

Relay Protection of EHV Shunt Reactors Based on the Traveling Wave Principle

Estimation of Re-striking Transient Overvoltages in a 3-Phase 132KV Gas insulated Substation

Electromagnetic Disturbances of the Secondary Circuits in Gas Insulated Substation due to Disconnector Switching

Lecture 36 Measurements of High Voltages (cont) (Refer Slide Time: 00:14)

VFTO STUDIES DUO TO THE SWITCHING OPERATION IN GIS 132KV SUBSTATION AND EFFECTIVE FACTORS IN REDUCING THESE OVER VOLTAGES

Modeling insulation in high-voltage substations

Insulation Test System

Lightning transient analysis in wind turbine blades

REDUCTION OF TRANSFORMER INRUSH CURRENT BY CONTROLLED SWITCHING METHOD. Trivandrum

2. Current interruption transients

ROEVER ENGINEERING COLLEGE ELAMBALUR, PERAMBALUR DEPARTMENT OF ELECTRICAL & ELECTRONICS ENGINEERING

FAULT IDENTIFICATION IN TRANSFORMER WINDING

DEPARTMENT OF EEE QUESTION BANK

DIFFERENCE BETWEEN SWITCHING OF MOTORS & GENERATORS WITH VACUUM TECHNOLOGY

Effects of Phase-Shifting Transformers, and Synchronous Condensers on Breaker Transient Recovery Voltages

Demagnetization of Power Transformers Following a DC Resistance Testing

Problems connected with Commissioning of Power Transformers

Investigation of Inter-turn Fault in Transformer Winding under Impulse Excitation

DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING QUESTION BANK SUBJECT CODE & NAME : EE 1402 HIGH VOLTAGE ENGINEERING UNIT I

RESULTS OF EXPERIMENTAL HIGH CURRENT IMPULSE 4/10 s OF METAL OXIDE VARISTORS ZINC IN THE HIGH VOLTAGE 220KV SURGE ARRESTER

DEVELOPMENTS IN EHV/UHV CIRCUIT BREAKER TESTING

Adi Mulawarman, P.E Xcel Energy Minneapolis, MN. Pratap G. Mysore, P.E Pratap Consulting Services, LLC Plymouth, MN

A Simple Simulation Model for Analyzing Very Fast Transient Overvoltage in Gas Insulated Switchgear

An Introduction to the CSCT as a New Device to Compensate Reactive Power in Electrical Networks

Analysis of lightning performance of 132KV transmission line by application of surge arresters

UNIT-4 POWER QUALITY MONITORING

Effect of High Frequency Cable Attenuation on Lightning-Induced Overvoltages at Transformers

POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS.

Comparison of switching surges and basic lightning impulse surges at transformer in MV cable grids

MODIFICATION OF THE ARRESTER ARRANGEMENT WHEN CONVERTING THE METHOD OF NEUTRAL TREATMENT

TECHNICAL REPORT. Insulation co-ordination

HVDC High Voltage Direct Current

Reducing the magnetizing inrush current by means of controlled energization and de-energization of large power transformers

High-Voltage Test Techniques

High Voltage DC Transmission 2

Insulation Test System

PMT/UMT(275) Power Gap Description and Use Application Note

Electric Power Systems Research

Impulse testing of coils and magnets: present experience and future plans

HV Module Systems for Testing, Training and Research

GIS Instrument Transformers: EMC Conformity Tests for a Reliable Operation in an Upgraded Substation

Analysis and modeling of thyristor controlled series capacitor for the reduction of voltage sag Manisha Chadar

Generation of Sub-nanosecond Pulses

Modelling of Restriking and Reignition Phenomena in Three-phase Capacitor and Shunt Reactor Switching

FUNCTIONS OF CIRCUIT BREAKERS

Pre location: Impulse-Current-Method (ICE)

Simulation of characteristics of impulse voltage generator for testing of equipment using MATLAB Simulink

Progress Report on Failures of High Voltage Bushings with Draw Leads By Jim McBride and Larry Coffeen, JMX Services / NEETRAC 7/26/2010

Transcription:

Energy Production and Management in the 21st Century, Vol. 1 345 Investigation of the electrical strength of a contact gap of the high voltage live tank circuit breaker 126 kv class using an intelligent controlled switching system D. Chernoskutov, D. Chechushkov & P. Tukanov Department of High Voltage Engineering, Ural Federal University named after the first President of Russia B.N. Yeltsin, Russia Abstract Uncontrolled switching of reactive elements of power networks may create electrical transients which cause equipment damage and system disturbances. The high frequency, high current transients, associated with uncontrolled energisation of capacitors can inductively couple voltage transients into control equipment and protective relays via the switchyard cabling. These transients may cause misoperation or failure of the control equipment. Controlling the point in the electrical cycle at which switching takes place is a possible method for minimising these negative effects. Controlled switching requires knowledge of electrical strength of contact gap. This paper is associated with investigating the electrical strength of a contact gap of a high voltage SF 6 circuit breaker 126 kv voltage class with sulfur hexafluoride gas SF 6 for development of the smartdesigned controlled switching system via investigation of the rate of decrease of dielectric strength. In this paper, a new approach to solve the problem of controlled switching is proposed. Keywords: SF 6 gas-insulated circuit breaker, electric arc, zero current, burning arc, shunt reactor, capacitor bank, rate of decrease of dielectric strength. 1 Introduction Modern high-voltage substation equipment Unified Energy Systems of Russia requires increased reliability of its elements. Special attention to improving the stability should be given to aspects of high-voltage switching, which are doi:10.2495/eq140341

346 Energy Production and Management in the 21st Century, Vol. 1 subjected to considerable stress in the various switching modes. The use of intelligent controlled systems is a more effective and functional means in comparison with pre-insertion resistors: allow control switching in the desired phase of the reference voltage and polarity, can eliminate the harmful effects caused by surges, inrush current, re-ignition and breakdowns. 2 Electrical endurance analysis The initial value of intension discharge at full lightning impulse among the insulating gas at a pressure of 0,1 p 0,6 MPa is given by: [1, equation 3-54] 0.88 0,180 E 89 p (1 ) 0. 5 ( p r ) where l contact distance, p pressure, Pa, r 0 the radius of curvature of the electrode with the maximum field strength, m; a and m coefficients depending on the nature of the change of the field in the gap. With the chosen design parameters of live tank SF 6 gas circuit breaker the guaranteed value of the pulse voltage at which there is no breakdown of the insulating gap is given by: U 467kV guar discharge.imp The selected value of the insulating gap is more than the rated standard value 450 kv by Russian National Standard 1516.3-96 [2] and provides the necessary dielectric strength of the gap by lightning impulse at the fully open position. The package ELCUT was used for numerical simulation of the electric field in the distance between the contacts. Obtained results of electric field simulation [3] are in good accordance with data, presented in [4]. 3 The principle of operation In this study an intelligent integrated controlled switching system (CSS) is considered as a means of contact closing near the peak of the reference voltage to plot the breakdown voltage curve in pure sulfur hexafluoride gas according to its electrophysical duration. The main principle of the controlled switching system is that the controller monitors the waveform of the reference voltage when the command to actuate the breaker, registers ideal point, and taking into account the opening time and other adaptive operating factors, forms on time delay so that the closing or opening of arcing contacts would occur in the required time, the required phase and polarity of the voltage reference. Control of switching moment of contacts with the process of electro pre-strike voltage relative to a reference system, which occurs when the reactive elements are an effective means for significantly reducing of inrush currents and surges that occur during switching of capacitor banks, shunt reactors, unloaded lines [4]. 0

Energy Production and Management in the 21st Century, Vol. 1 347 Figure 1: Electric field intension of the contact gap made in ELCUT package simulation moving contact case [3]. Figure 2: Electric field intension of the contact gap made in ELCUT package simulation stationary contact case [3].

348 Energy Production and Management in the 21st Century, Vol. 1 Figure 3: Electric field intension of the HGF 1014/63 ka SF 6 circuit breaker s contact gap [4]. Figure 5 shows the principle of operation of the controlled switching system. In the case of a synchronous switching on the circuit breaker (controller input synchronous closing ), or synchronous breaking (controller input synchronous opening ) system for each pole switch counts Δt command from the time of the next reference voltage crossing zero to the delivery of closing/opening command to operating drive of the corresponding pole considering its opening/making time (t opening /t closing ), so that the beginning of closing (or opening) of the arcing contacts pole had at the time of the transition sine wave voltage reference through a natural zero, then the timing is calculated as follows: Δt total = Δt command + t opening + t delay where Δt total total time of operation for synchronous performance of breaker s poles from the moment of the first corresponding phase sine wave voltage reference natural crossing zero after receipt the controller commands for synchronous operation to the start switching (opening or closing) the arcing contacts of this pole; Δt command delay of the control command (closing or opening) of the operating drive of circuit breaker s pole generated by the controller to perform switching (opening or closing) the arcing contacts of the circuit-breaker pole to the desired point of the associated phase of the reference voltage (Δt command value is calculated depending on the programmed settings); t opening /t closing programmed into the controller closing or opening time;

Energy Production and Management in the 21st Century, Vol. 1 349 t delay additional time delay in solenoid control command (closing/opening) to operating drive, that determines the phase of reference voltage at switching poles of CB (user selectable in milliseconds, between 0 and 20 ms during programming synchronization module). Research tests have been performed to determine the electrical strength of a contact gap of SF 6 gas live tank circuit breaker VGT 110 class 126 kv using a controlled switching system in high-voltage laboratory of JSC Uralelectrotyazhmash. This intelligent system provided a contact closing (prestrike) near the peak of the reference voltage during capacitive load switching (1000 pf). The pre-strike voltage was obtained by smooth voltage rise and changing of time delay for switching operation so that the time of pre-strike took place at the voltage maximum. The curve of contact travel curve was recorded by resistive travel sensor, electromagnetic interference during switching process have been corrected by processing filter programs by two methods. Recording of instantaneous values of analog and digital electrical signals was realized by recorder RES-03 with 15 khz sampling frequency. Figure 4: Distribution of electric field intensity of the HGF 1014 /63 ka SF 6 circuit breaker s contact gap [4].

350 Energy Production and Management in the 21st Century, Vol. 1 Figure 5: The algorithm of the subsystem clock synchronous operation of intelligent control switch system (independent single pole operation). The relation of pre-strike voltage according to duration at different reference voltages was determined. Angle characteristics of electrical breakdown at nominal pressure 0,5 MPa and a minimum 0,42 MPa operating pressures of pure sulfur hexafluoride, that define RDDS were defined by two methods of filtering electromagnetic interference. In Figures 6 9 trendlines are shown with coefficients that characterize the dielectric strength (RDDS) of a contact gap during pre-strike at nominal pressure 0,5 MPa and minimum 0,42 MPa accordingly. The main goal of the controlled switching system in the present study was to provide closing of arcing contacts (providing pre-strike as they touch) close to voltage peak for registration and subsequent plotting pre-strike voltage graph according to duration (that characterizes the rate of decrease of dielectric strength RDDS). 4 Experimental results The lines representing the RDDS were determined by linear interpolation. The kind of interpolation which best fits a given set of points might be dependent on the circuit-breaker design. It is quite evident that duration of the pre-strike in SF 6 is directly proportional to the pre-strike (breakdown) voltage, the experimental data results obtained by two filter methods in this research differ slightly. CIGRE S angle characteristics of RDDS are shown in p.u. without reference to rated voltage class of circuit breaker under test [5, І p.38]. However differences of obtained RDDS angle characteristics with CIGRE S characteristics of RDDS are in good accordance.

Energy Production and Management in the 21st Century, Vol. 1 351 Angle characteristics of RDDS obtained in this research are slightly steeper than RDDS presented in [5, І p.38]. Some differences may be explained by design features of test circuit breakers (mechanical scatter beginning of the contact movement, variation of contact speed, filling pressure, SF 6 quality, etc.) Two methods of filtering of electromagnetic interference have shown about the same results. 200 180 Upre-restrike, кv Pre-restrike voltage characteristic (method 1) Upre-restrike(tduration) 0,5 MPa y = 54.788x 160 140 120 100 80 60 40 20 tpre-restrike, ms 0 0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5 Figure 6: Pre-strike voltage (voltage breakdown) characteristic (RDDS) according to duration (method 1) at the filling pressure of 0.5 MPa. 200 180 160 Upre-restrike, кv Pre-restrike voltage characteristic (method 2) Upre-restrike(tduration) 0,5 MPa y = 53.763x 140 120 100 80 60 40 20 tpre-restrike, ms 0 0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5 Figure 7: Pre-strike voltage (voltage breakdown) characteristic (RDDS) according to duration (method 2) at the filling pressure of 0.5 MPa.

352 Energy Production and Management in the 21st Century, Vol. 1 240 220 200 180 160 140 120 100 80 60 40 20 0 Upre-restrike, кv Pre-restrike voltage characteristic (method 1) Upre-restrike(tduration) 0,42 MPa y = 40.883x tpre-restrike, ms 0 1 2 3 4 5 6 7 8 Figure 8: Pre-strike voltage (voltage breakdown) characteristic (RDDS) according to duration (method 1) at the filling pressure of 0.42 MPa. 240 220 200 Upre-restrike, кv Pre-restrike voltage characteristic (method 2) Upre-restrike(tduration) 0,42 MPa y = 41.483x 180 160 140 120 100 80 60 40 20 tpre-restrike, ms 0 0 1 2 3 4 5 6 7 8 Figure 9: Pre-restrike voltage characteristic RDDS according to duration (method 2) at the filling pressure of 0.42 MPa.

Energy Production and Management in the 21st Century, Vol. 1 353 Figure 10: Pre-restrike voltage (voltage breakdown) characteristics RDDS in p.u. according to duration CIGRE A3.07 WG data [5, І p.38]. Figure 11: The obtained curve of the dielectric strength according to contact travel, reference voltage and load voltage, obtained during capacitive load switching.

354 Energy Production and Management in the 21st Century, Vol. 1 Table 1: Pre-strike voltage values and durations at filling pressure of 0.42 Mpa. test Pre-strike voltage, kv Pre-restrike voltage (abs.), kv Duration, msec Approach 1 Approach 2 1 41.4 41.4 0.86 0.94 2 41.4 41.4 1.01 1.01 3-61.74 61.74 1.08 1.08 4 71.5 71.5 1.08 1.44 5-71.7 71.7 1.23 1.3 6-72.14 72.14 1.15 1.22 7 83.14 83.14 1.22 1.22 8 97.6 97.6 1.8 1.8 9-115.9 115.9 2.01 2.09 10 126.9 126.9 2.23 2.23 11 133.4 133.4 2.52 2.52 12-136.22 136.22 2.45 2.45 13-141.94 141.94 2.66 2.66 14 145.6 145.6 2.88 2.95 15-146.6 146.6 2.74 2.74 16 148.5 148.5 2.66 2.74 17 150.55 150.55 2.81 2.88 18 151.03 151.03 2.59 2.59 19-164 164 3.1 3.24 20 185.7 185.7 3.38 3.45 21 190.59 190.59 3.46 3.38 5 Conclusions With all the variety of controlled switching system s advantages this article is devoted only for investigation of the electrical strength of a contact gap of High Voltage SF 6 Circuit Breaker. The curve of dielectric strength according to the contact stroke and reference voltage was obtained. Electric field analysis, made by numerical simulation in ELCUT package, allowed us to optimize the configuration of stationary and moving contact assemblies, significantly reducing the amount of research tests. The data, obtained from this study, formed the basis, required for development of smart-designed controlled switching system and provide necessary time delays for successful circuit breaker s operation. Controlled switching system will eventually increase switching

Energy Production and Management in the 21st Century, Vol. 1 355 performance of the circuit breaker, degree of protection and reliability of substation equipment. With increasing of power consumption and innovative direction of the replacement and upgrading of substation s equipment such intellectual systems will find an active application in smart grids. References [1] V.V. Afanasyev, Text-book of High Voltage Apparatus M. Energoatomizdat, 1987. [2] Russian National Standard 1516.3-96. [3] Tukanov R., Glushkov D., Analysis of gas dynamic and electro processes in high voltage switching apparatus, Graduate thesis, Ekaterinburg 2010. [4] V.F. Hermosillo, Controlled switching C-B consideration, CIGRE Presentation Seminar/Workshop A3/07, 2003. [5] А3-07 Working Group, Сontrolled switching guide, parts I-III., K. Frohlich, A. Carvalho, H. Ito, 2004. [6] Tom Roseberg, Controlled switching of HVAC Circuit Breakersˮ, 6, 2007, Journal of Electrical Engineering. [7] H. Wilson, I. Hiroki, Factory and field testing of controlled switching systems and their service experienceˮ, CIGRE Transactions from 2004 Science Session.